wria 1 planning unit thursday, october 24, 2018, 5:30 - 8
TRANSCRIPT
WRIA 1 Planning Unit
Thursday, October 24, 2018, 5:30 - 8:30 PM
Garden Room, Civic Center Building, 322 N. Commercial, Bellingham
Topic Time # Subtopic Action Needed? Handout or Homework? Co-Lead
Introductions; Agenda Review and Approval
5:30 1. Call to Order/Introductions No No Shannon
5:35 2. Review and approve agenda Yes – Approval 10/24/2018 Agenda All
5:40 3. Housekeeping and misc. Review and approve 10/11
meeting summary Consider modification to Nov
14 meeting time (1:00-3:00)
Yes – Approval 10/11 draft summary All
Planning Unit Topics
5:45 4. Timeline through January 2019 Review projected timeline for
completing update
No No Gary
6:15 5. Monitoring and Adaptive Management Status update on Monitoring
and Adaptive Management
No - Information No Gary
6:45 6. NGWS Policy Proposal
Review and discuss NGWS proposal
Yes – approval, if possible
NGWS policy proposal John
6:55 7. Suite of Projects for Watershed Management Plan Update
Continue discussion from 10/4
Yes – Approval
Suite of Projects for Watershed Plan Update (continued from 10/11)
Gary
7:25 8. Early Grant Applications
Planning Unit members requested an opportunity for applicants to the Streamflow Restoration Grant to present their project information
Yes – Support for grant applications supporting WMP update projects
Information will be sent separately as it becomes available.
Applicants
Lead Agency Update
8:15 9. Lead Agency Update No- Informational
Lead Agency Update Gary
Next Steps 8:20 10. Review action items; call for agenda items for Nov. meetings
Yes- agree on agenda items
No All
Public Comments
8:25 11. Public Comment Period, conclude meeting
No No Public
Agenda Handouts/Links:
1. 10/24/18 Planning Unit Agenda
2. 10/11/18 Draft Planning Unit Meeting Summary
3. NGWS Caucus Policy Proposal (resending from 10/11)
4. Suite of Projects for Watershed Plan Update (resending from 10/11; includes references to RH2 Technical Memo #2 information)
October 24, 2018 WRIA 1 Planning Unit Meeting
HANDOUT #2
Draft Meeting Summaries 10/11/18 Planning Unit Meeting
Draft October 11, 2018 Planning Unit Meeting Summary Prepared by: Geneva Consulting
1
WRIA 1 Planning Unit Meeting 1
October 11, 2018 2
Meeting Summary 3
This summary captures key decisions and next steps from the October 11, 2018 meeting. Digital 4 recordings of the Planning Unit meetings can be found at the Planning Unit website at 5 www.wria1project.whatcomcounty.org. 6 7
Caucus Attendees: 8 Agriculture – Henry Bierlink 9 City of Bellingham –Inactive 10 Diking/Drainage – Fred Likkel 11 Environmental – Ander Russell 12 Federal Government – Not Represented 13 Fishers – Shannon Moore 14 Forestry – Dick Whitmore 15 Land Development – Dave Onkels 16 Non-Government Water Systems – John Mercer 17 Port of Bellingham – Kurt Baumgarten 18 Private Well Owners – Paul Isaacson 19 Public Utility District # 1 of Whatcom County – Rebecca Schlotterback 20 Small Cities – Mike Martin 21 State Government – Not Present 22 Water Districts – Dan Eisses 23 Whatcom County – Gary Stoyka 24
Others Present (based on sign-in sheets) 25 Alan Chapman Skip Richards Marian Beddill 26 Carole Perry Max Perry Karlee Deatherage 27 Dave Beatty Ellen Baker Kathy Sabel 28 Oliver Grah Tyler Schroeder Heather Good 29 Cliff Strong Chet Dow Rick Maricle 30 Molly Crocker 31 32 Shannon Moore called the meeting to order at 2:10 pm. 33
Planning Unit Motions That Passed1 34
Motion (Motion #1) by Alan Chapman with second by Skip Richards and amended by Ander 35
Russell to approve the minutes pending a correction to Motion #4 in the minutes based on 36
discussion of Agenda Item #5. 37
1 Note that motions (passed and not passed) are numbered in the order they were presented during the meeting.
Draft October 11, 2018 Planning Unit Meeting Summary Prepared by: Geneva Consulting
2
Vote: 38
13 in favor (Agriculture, Diking/Drainage, Environmental, Fishers, Forestry, Land 39
Development, Non-Government Water Systems, Port of Bellingham, Private Well 40
Owners, PUD #1, Small Cities, Water Districts, Whatcom County) 41
0 abstain 42
0 opposed 43
Motion passes 44
Motion (Motion #2) by Paul Isaacson to move agenda item #5 up as #3 and seconded by Alan 45 Chapman. The order of agenda items was switched so the NGWS Policy Proposal remains item 46 #4 and the Suite of Projects becomes agenda item #5. 47
Vote: 48
13 in favor (Agriculture, Diking/Drainage, Environmental, Fishers, Forestry, Land 49
Development, Non-Government Water Systems, Port of Bellingham, Private Well 50
Owners, PUD #1, Small Cities, Water Districts, Whatcom County) 51
0 abstain 52
0 opposed 53
Motion passes 54
Planning Unit Motions That Did Not Pass 55
None 56
Other Items Considered (or Announced) By Planning Unit 57
The Private Well Owner Caucus reviewed their proposal regarding the Process and 58
Procedural Agreement (PPA), Section 4.1 decision-making process. The Caucus would like 59
to see Section 4.1 applied to all components of the Plan update and not have it limited to 60
the final Plan update. Calling for a formal vote on each component using Section 4.1 would 61
have the outcome of knowing where each caucus and government stands on each issue and 62
identify the areas that are non-negotiable. The difference between using Section 4.0 and 63
4.1 is the formal consensus process involving the Initiating Governments. The vote in 64
Section 4.1 also requires that if someone votes no, it requires the caucus voting to state the 65
reason, explain why it affects their interests, and propose an alternative. Section 4.0 can 66
call for a vote for individual components with the outcomes being based on a majority of 67
members present. It was noted that with Section 4.0 when there is a motion and a vote, 68
the minutes currently report how each of the caucuses voted (yea, nay, or abstain). The 69
Planning Unit members agreed that there will not be requests for a “head nod” to move 70
plan elements forward; votes will be taken and recorded using Section 4.0 of the PPA. 71
The other topic associated with voting was clarification on tallying abstentions in Planning 72
Unit votes. Planning Unit uses a process for passing motions based on a majority of 73
Draft October 11, 2018 Planning Unit Meeting Summary Prepared by: Geneva Consulting
3
members present. Clarification was provided that if a motion is made it requires a 74
majority of members present to vote “yea” in order to pass since members abstaining are 75
counted as members present. 76
The Non-Government Water System (NGWS) Caucus introduced a revised policy proposal 77
related to topics of fees, water use allocation, and monitoring. The NGWS provided a 78
rationale for a proposal that supports maintaining the fee and water use metrics that are 79
identified in the legislation. The NGWS proposal supports the Planning Unit making the 80
intentional decision to not change the metrics rather than to not change them due to 81
indecision or the inability to reach consensus. There was brief discussion of the water use 82
and fee topics in the context of the NGWS proposal. In response to a call for members to 83
indicate their general support, some members said they support it, some generally support 84
but have questions and need to discuss with their caucus, and some appreciated the NGWS 85
taking a first step to provide the proposal but need to talk with their caucus before 86
discussing since they just received the proposal at the meeting. The NGWS proposal will be 87
added to the October 24 Planning Unit meeting. 88
Gary Stoyka reviewed the process that the Watershed Staff Team used to identify the suite 89
of projects being recommended to the Planning Unit for the Plan update per the Planning 90
Unit’s request. The projects in the suite of projects are primarily from the RH2 technical 91
memo #2 with the exception of one project that is new and a couple of modifications to 92
other projects. The new project is a Purchase of Development Right (PDR) program that has 93
site specific attributes because landowners apply to Whatcom County Planning and 94
Development Services to participate in the program. The PDR program is being 95
recommended by the Watershed Staff Team for inclusion in the suite of projects for the 96
Plan update as a WRIA-wide program. The Watershed Staff Team also recommended 97
consolidating all of the Managed Aquifer Recharge (MAR) projects that are listed in the RH2 98
appendices of Memo #2 into a single WRIA-wide MAR feasibility project. The final 99
modification is to the outdoor conservation program, which in the RH2 memo is focused on 100
agricultural outdoor use. The Watershed Staff Team recommendation for the suite of 101
projects is a domestic outdoor water conservation program. The summary table identifies 102
the aggregated sub-basin that the project would be located in and the offset amount 103
provided. 104
A motion was made by the Small Cities Caucus representative to support the suite of 105
projects and later tabled because some Planning Unit members did not feel like they had 106
enough information on the projects to support or reject the motion. One suggestion was 107
that those initiating the projects provide a one page summary of their projects. It was also 108
suggested that the Planning Unit look at existing projects that support mitigation that are 109
already moving forward such as the Middle Fork Passage Project. With regard to the Middle 110
Fork Project, several Planning Unit members noted that it is not a project that will provide 111
offset. The suite of projects will be added for continued discussion on the October 24 112
Draft October 11, 2018 Planning Unit Meeting Summary Prepared by: Geneva Consulting
4
Planning Unit meeting. It was suggested that Planning Unit members needing more 113
information about the projects contact Gary in advance of the October 24 meeting. 114
Planning Unit members discussed the Streamflow Restoration Grant that opened for 115
applications on October 1. Applications are due October 31. The Ag Caucus expressed 116
interest in presenting their application to the Planning Unit for endorsement. It was noted 117
that other entities may also be considering an application. Planning Unit members would 118
like sponsors of applications to present an overview of their project application at the 119
October 24 Planning Unit meeting. Some Planning Unit members requested that a draft of 120
the application be provided to the Planning Unit in advance. 121
Planning Unit members briefly discussed meeting duration and that it may be necessary to 122
plan for three hour meetings. 123
Actions and Follow Up 124
The Planning Unit members agreed that there will not be requests for a “head nod” to move 125
plan elements forward; votes will be taken and recorded using Section 4.0 of the PPA. 126
Clarification was provided that if a motion is made it requires a majority of members 127
present to vote “yea” in order to pass since members abstaining are counted as members 128
present. 129
The NGWS proposal will be added to the October 24 Planning Unit meeting. 130
The suite of projects will be added for continued discussion on the October 24 Planning Unit 131
meeting. 132
Planning Unit members would like sponsors of applications to present an overview of their 133
project application at the October 24 Planning Unit meeting. 134
Public Comment 135
Kathy Sabel comments on the October 2 RH2 Task 2 Memo, reference in Watershed Staff 136
Team meeting summary to adaptive management flow chart, and whether the Planning 137
Unit needs to request funding for next year’s County budget. 138
Rick Maricle commented on fees associated with wells and that any fee should apply to all 139
wells regardless of use (e.g., domestic, commercial, municipal, etc.) 140
Meeting adjourned 4:15 pm. 141
October 24, 2018 WRIA 1 Planning Unit Meeting
HANDOUT #3
Non-Government Water Systems (NGWS) Policy Proposal
Page 1 of 2
NGWSC proposal regarding policy issues quantity, fees, and monitoring revised 10/9/2018 1 2 The following policy proposal has been updated based on the generous feedback from caucus and 3
community members since the submittal of previous versions. Please note, no voting is required to 4
implement the proposed course of action contained within. The purpose of this proposal is to gain clarity 5
on where we are at on policy issues in a concise manner and support the momentum of the planning 6
unit’s efforts toward completion of 6091 related objectives by the impending deadlines. 7
8
Whereas: 9 10 The planning unit has recently received a request to consider a number of policy decisions; and 11 12
Of these policy decisions, some that have been presented are divisive and pose a very real and 13
disproportionate risk related to our cumulative goal of successfully meeting imposed deadlines; and 14 15 ESSB 6091 the “Water Availability” Act, later codified as RCW 90.94 “Streamflow Restoration”, Identifies 2 16
“policies” that may be modified in WRIA 1: (1) Fees, & (2) water use quantities; and 17 18
Groundwater and streamflow monitoring are critical components of adaptive management and plan 19
implementation; and 20 21 With respect to WRIA 1, 90.94 is categorically silent regarding the policy of metering, specifically on any 22
requirements to individually meter any new permit exempt well; and 23 24
Metering is not contemplated in the Law, and further contemplation of individual well metering at this 25
point in our planning process is both pre-mature and counter-productive; and 26 27 The policies we adopt may, per RCW 90.94.020 (6) (c) include updates to fees based on the planning unit's 28
determination of the costs for offsetting consumptive water use; and 29 30 It is our understanding that the principal intent of fees collected from new permit exempt well owners is 31
to proportionately fund the administrative costs of the offset and net ecological benefit projects; and 32
33
Grant funding has been made available, to fund capital and ongoing maintenance costs for consumptive 34
use offset and net ecological benefit projects; and 35
36
The current maximum annual average withdrawal of three thousand gallons per day per connection is 37
sufficient for the use of new permit exempt well owners based on reports received by the Planning Unit; 38
and 39
40
The likely annual average number of new wells based on the RH2 tech memo is something like 125 per 41
year, which will be consumptively using approx. 35 acre-feet per year (0.0483 CFS) across the entire 42
WRIA; and 43 44 There does not seem to be much adverse feedback from the current codified metrics of 3000 gpd and 45
$500 fee; and 46 47
Changes to the current codified metrics of 3000 gpd and $500 fee are likely to adversely affect the 48
Planning Unit’s ability to complete the collaborative process it began when 6091 was passed. 49 50 51
Page 2 of 2
Therefore: 52
53
We offer this base case policy proposal: 54
55
Maintain the existing codified metrics of: 56
90.94.020 (5) (f) (i) An applicant shall pay a fee of five hundred dollars to the permitting 57
authority; 58
90.94.020 (5) (f) (ii) An applicant may obtain approval for a withdrawal exempt from 59
permitting under RCW 90.44.050 for domestic use only, with a maximum annual average 60
withdrawal of three thousand gallons per day per connection. 61
62
Rationale: 63 64 In support of the proposal we offer the following: 65 66 Quantity: The RH2 technical investigation has shown that the amount of water that will be consumptively 67
used over the next twenty years is far less than the one percent of the total that all the existing domestic 68
permit-exempt wells are using. Leaving the quantity at 3000 gpd and offsetting for the consumptive use of 69
the same serves to build in an exponential excess of offset input given that 3000 gpd is roughly ten times 70
the calculated actual average day demand of rural service connections. Limiting new permit-exempt wells 71
to less than that, and subsequently reducing offsets to match, will do nothing to improve streamflow. 72
Streamflow improvements require massive capital and effort to make noticeable improvements. The 73
focus should be in that direction. The Hirst decision only highlights our greater streamflow challenges. 74 75 Fees: The August staff team policy memo outlined many of the issues surrounding fees. If in fact the 76
intent of the legislature is to fully fund 6091 “Water Availability” projects through the grant program 77
made available by the same, then the $500 fee for administrative and permit processing costs seems 78
reasonable. 79 80 Monitoring: Monitoring is a necessary component of adaptive management. With limited resources, we 81
should endeavor to be mindful of which monitoring exercises have the greatest cost benefit ratio. We 82
have received a technical memo stating that if a new well was put to full beneficial use under current law, 83
the resulting use will fall short of the 3000 gpd limit that we are currently contemplating. Exceedances of 84
the 3000 gpd limit would be very difficult if not impossible to attain and most likely be caused by activities 85
that are already governed and enforced by law. 86
87
Therefore, if we maintain the 3000 gpd limit, individual well metering is no longer needed or the best use 88
of resources or focus. Knowing that we have assigned an exponentially high value to permit exempt well 89
use, we can shift our much-needed focus and efforts to stream gauging, groundwater monitoring, and 90
offset/NEB project performance monitoring. 91
92
Decision Making 93
Please note that an intentional decision to not change codified metrics is the preferred alternative to not 94
changing the same due to indecision or the inability to come to a decision by consensus. Review of the 95
facts at hand do not support changing codified metrics. The scope and authority afforded to the planning 96
unit by the 6091 “water availability” legislation is very limited and any attempts to reach beyond our 97
scope and authority are counterproductive and endanger our ability to meet 6091 deadlines. 98
99
October 24, 2018 WRIA 1 Planning Unit Meeting
HANDOUT #4
Suite of Projects for Watershed Plan Update (continued discussion from 10/11/18)
CN CW CS LN NF MF SF S LW
185 139 41 194 23 1 5 38 23
Project
No.
RH2
AssessmentProject Name Est. Offset RH2 Rationale for Assessment Potential Negative Side Effects Staff Team Member Comments
Capital Est.
Cost
O & M Est.
Annual Costs
Project Description- location within RH2
Memo. 2 High Bertrand WID Ground Water Augmentation of
Tributaries
170.7 171 Bertrand WID had recent success for two wells and
received temporary permit to continue. Could expand to
original vision of more wells if funding is provided. Year-
round closure of Bertrand Creek could pose a problem.
Timing of flow augmentation should coincide with
fishery needs.
Potential negative impacts on
salmonids.
Moving people off surface water
diversion preferred over gw
augmentation. Needs to be further
fleshed out; there are homing issues,
temporal issues (only provides water
August to November), and water
quality concerns to address.
$917,000 $0 Appendix B
24 High Birch Bay Water & Sewer District Deep Wells 880.0 440 440 Preliminary results from deep well drilling look
encouraging. New source of water could be used to
meet future growth and also to replace local sources. If
water from the District, imported from this well field, is
able to replace water used under an existing water right,
that water right can be placed into the Trust Water
Rights Program and could be used to offset consumptive
impacts in the Lower Nooksack Aggregated Sub-Basin.
Water quality differences in
municipal systems.
440 per basin split so can do the
assesment. May have water quality
issues. At this time the project is only
scoped to provide water to water
systems.
$27,695,000 $0 Appendix B
1 High Dairy Waste Processing/Treatment 13.4 13.4 Fully funded project will provide offset water and, as a
pilot project, may foster similar projects elsewhere in
WRIA 1. An NPDES permit is needed. There is a
mechanical system to operate and maintain. Water can
reduce irrigation need or benefit instream flows as
offset water.
Could degrade water quality,
especially if discharged water has
lower water quality (especially
temperature) than receiving water;
NPDES permit should address
quality, including temperature.
$903,305 $0 (farmer
supplies)
Appendix B
27 Med-High Coastal North-Convert Surface Use to Groundwater Use 7.3 7.3 Similar projects have been approved in WRIA 1. They
can be effective in reducing impacts on instream flows
but Foster decision limits flexibility under current
conditions. Stream gaging recommended to assess and
document benefits and the need for any changes or
adjustments. Offset will be approx. 10% of the full water
right quantities. Very low costs both initially and long
term.
Additional GW impacts due to
more direct withdrawal from the
acquifer.
Good project and spatial distribution
project. Same with project #26. RH2
assumed a 10% benefit- need to know
how solid the offset amounts are.
$837,000 $0 Appendix B
26 Med-High Lower Nooksack-Convert Surface Use to Groundwater
Use
158 158 Similar projects have been approved in WRIA 1. They
can be effective in reducing impacts on instream flows
and creating higher flows during the irrigation season
but Foster decision limits flexibility under current
conditions. NO negative impact on instream flows is
allowed. Offset will be approx. 10% of the full water
right quantities. Very low costs both initially and long
term.
Additional GW impacts Same comments as project #27 $2,566,000 $0 Appendix B
23 Med-High Middle Fork Porter Creek Alluvial Fan Project 11.2 11.2 This project increases groundwater storage according
the project sponsor. It needs to be determined whether
the increased storage results in actual increased
groundwater flow to the river. If this project reliably
provides an increase in instream flows it deserves a high
rating. If the flow component is uncertain,
unquantifiable, or less than anticipated, the project
seems likely to provide environmental benefits.
None Seasonal creek and dries up during the
critical instream flow season
$706,383 $0 Appendix B
Consumptive Use Calculations AFY (RH2 Tech Memo #1, August 21, 2018) [Note, these
values have not been subject to uncertainty analysis, a margin of safety, and may
change for other reasons)
Except where noted, the suite of projects identified below are from the RH2 Task 2 Memorandum, Appendix A Matrix for Evaluation of Early Action and Preliminary Projects. The suite of projects represent the
Watershed Staff Team's recommendation for the Watershed Plan update pending completion of the NEB evaluation.
Other factors that have been identified by some Staff Team members:
a. The distribution of offsets does/may not align with the distribution of projected impacts
b. Three aggregated subbasins do not have specific projects identified. WRIA 1 wide projects and programs are proposed that could/would address those aggregated subbasins.
c. The timing of offsets will/may be an issue in places.
Watershed Staff Team Suite of Projects Pending Net Ecological Benefit (NEB) Evaluation
The information in these three columns was added 10/17/18 to assist
Planning Unit members with their review. The information is taken from
the October 2, RH2 Technical Memo #2. Projects that list "appendix B"
have a one page description of the project in the appendix. Projects in
"Appendix C" are in a matrix
Link to October 2, RH2 Technical Memo #2 Referenced Below
Compiled by Geneva Consulting
October 4, 2018 1 of 3
CN CW CS LN NF MF SF S LW
185 139 41 194 23 1 5 38 23
Project
No.
RH2
AssessmentProject Name Est. Offset RH2 Rationale for Assessment Potential Negative Side Effects Staff Team Member Comments
Capital Est.
Cost
O & M Est.
Annual Costs
Project Description- location within RH2
Memo.
Consumptive Use Calculations AFY (RH2 Tech Memo #1, August 21, 2018) [Note, these
values have not been subject to uncertainty analysis, a margin of safety, and may
change for other reasons)
The information in these three columns was added 10/17/18 to assist
Planning Unit members with their review. The information is taken from
the October 2, RH2 Technical Memo #2. Projects that list "appendix B"
have a one page description of the project in the appendix. Projects in
"Appendix C" are in a matrix
Link to October 2, RH2 Technical Memo #2 Referenced Below
19NG Med-High Wetland Restoration, Enhancement, and/or Creation on
Ecology-Approved NEP Parcels
2-5 2-5 Potential for water supply benefits and fishery
enhancements exists. Large amount of uncertainty
regarding effectiveness. The project will eliminate
agricultural activities on 30 acres and decommission
drainage ditches and retain excess moisture during the
winter which could be released to stream in the late
season. Provides shade to promote cooler water
temperatures. Additional study likely required.
Reduced ag land. $354,500 $32,500 Appendix B
28 Low-Med-High Storage Projects including Gravel Pits 365 365 This type of project has potential to be an effective
means of augmenting late season stream flows with
cooler water. However, the degree of effectiveness will
depend on local conditions including such
considerations as land ownership, elevations (is
pumping required?), the impact of the level of the water
table (will an increase flood basements or septic drain
fields?), the nature of the aquifer (does the water drain
to the stream too quickly or too slowly?), the volume of
water that can realistically be stored, etc. Design needs
to ensure that the project does not impair floodplain
function. Project currently contains a large amount of
uncertainty and therefore should be assumed to be low
with the potential to increase in rating
Increase GW levels and flooding,
potential for capture and stranding
of fish, potential for negative
impacts to floodplain habitat
connectivity, availability, and
formation.
PUD is looking at six potential locations-
end of oct should have two prioritized.
3 of the 6 would directly contribute to
tributaries
$1,946,000 $66,000 Appendix C
44 Med-High PUD #1: Vista Road Project 194 (this
value can be
greater than
194 afy)
194 Requires domestic well new construction to purchase
water from the PUD for offset (O&M costs). This would
introduce new water into the watershed, providing
100% offset. The importation of foreign water to the
drainage may impair homing of anadromous fish.
Concerns about interbasin
transfers negatively affecting
salmon homing
PUD will work with DFW and Tribes to
address oncerns associated w/ water
transfer
$1,000,000 $82,000 Appendix C
45 Med-High PUD #1: Lake Terrell 324 (this
value can be
greater than
324 afy)
185 139 Pipeline already existing, just needs to provide a tap and
potentially an energy dispersion structure. The
importation of foreign water to the drainage may impair
homing of anadromous fish.
Concerns about interbasin
transfers negatively affecting
salmon homing
PUD will work with DFW and Tribes to
address oncerns associated w/ water
transfer
$500,000 $82,000 Appendix C
43 Med-High PUD #1: Pipeline from Mainstem to Tributaries
(Previously "Pipe from Plant 2 to Tributaries"
1,452 1,452 Project is feasible from an engineering standpoint and
the PUD has sufficient water rights to provide this water.
Costs are a big issue. The issue of discharge in a manner
than does not impair homing of anadromous fish is
critical to success. Potential impacts of reduced flows in
the Lower Nooksack should also be considered. New
permit exempt wells could offset some of the O&M
costs.
Increasing diversions would reduce
flows in the Lower Nooksack below
the PUD's Plant 2 plus concerns
about interbasin transfers
negatively affecting salmon
homing.
$39,800,000 $549,000 Appendix C
19 Med-Low Skookum Creek Restoration 1,449 1,449 Medium-Low rating selected due to positive
environmental benefits but the uncertainty of the
quantity of offset water provided.
None $4,000,000 $0 Appendix C
21 Med-Low Stewart Mountain/SF Nooksack Conservation Sale 7,245-14,490 x x x Medium-Low rating selected due to positive
environmental benefits but the uncertainty of the
quantity of offset water provided. The potential for
benefits to instream flow due to changes in forest
management exists although the benefits, if they occur,
may be slow to accrue.
None $4,000,000 $0 Appendix C
22 Not Assessed North Fork Maple Reach Restoration Phase 1 Unknown Not assessed Not assessed Staff Team added for North Fork
habitat
not available Appendix D
46 Not Assessed Glacier WD Groundwater Study and Augmentation Unknown need
23
Not assessed Not assessed Staff Team added for North Fork offset;
project needs to provide at least 23 afy
not available
Modification of
Project #47
WRIA 1-Wide Conservation Program Unknown x x x x x x x x x Not assessed Not assessed Staff Team added for outdoor domestic
water conservation
not available Staff Team recommendation is for
domestic water conservation; project
description in RH2 matrices is for
agricultural conservation.
Compiled by Geneva Consulting
October 4, 2018 2 of 3
CN CW CS LN NF MF SF S LW
185 139 41 194 23 1 5 38 23
Project
No.
RH2
AssessmentProject Name Est. Offset RH2 Rationale for Assessment Potential Negative Side Effects Staff Team Member Comments
Capital Est.
Cost
O & M Est.
Annual Costs
Project Description- location within RH2
Memo.
Consumptive Use Calculations AFY (RH2 Tech Memo #1, August 21, 2018) [Note, these
values have not been subject to uncertainty analysis, a margin of safety, and may
change for other reasons)
The information in these three columns was added 10/17/18 to assist
Planning Unit members with their review. The information is taken from
the October 2, RH2 Technical Memo #2. Projects that list "appendix B"
have a one page description of the project in the appendix. Projects in
"Appendix C" are in a matrix
Link to October 2, RH2 Technical Memo #2 Referenced Below
Modification of
MAR Projects
MAR Feasibility Study Unknown x x x x x x x x x Not assessed Not assessed Staff Team added a MAR Feasibility
Study that would evaluate feasibility
including locations and costs for MAR
not available Appendix D - consolidation of MAR
projects into single WRIA-wide feasibility
study
Not Assessed Purchase of Development Rights Program Unknown x x x x x x x x x Not assessed Not assessed Staff Team added the PDR program,
which has geographically specific
program applications. The specific
parcels for which applications have
been submitted is as of 10/4/2018 and
provided by Whatcom County
Planning. In addition to the site
specific parcels, the PDR program
could be a WRIA 1 wide tool that
supports other actions, projects, and
programs. NOTE: This is a new project
that was not included in the RH2
project matrices.
not available This program was not included in the
RH2 project matrices.
Compiled by Geneva Consulting
October 4, 2018 3 of 3