wp mp-update-col riverconvey-april_25_2013
TRANSCRIPT
Dave Chamberlain, P.E.
October 2003, Colorado River Quantification Settlement Agreement (QSA) executed • 45- to 75-year water conservation and
transfer agreement w/ IID • 110-year canal lining agreement (All
American and Coachella Canals) • 280,200 AFY of Colorado River Supplies • Currently wheeled through MWD System • MWD Exchange Agreement for up to 45 yrs
Previous studies identified two preferred alignments • Jointly studied w/ Mexico • Not pursued after 2003 Master Plan
April 2012 Board direction • Amend Master Plan to include a “Supply
from the East” Alternative 2
Reexamine preferred alignments from previous evaluations • New facility owned and operated by Water Authority Size project for QSA
deliveries only Evaluation approach
• Facility requirements • Energy management • Operational impacts • Compare risks • Project cost refinement • Implementation schedule
Portal
3
Land Use • New development along proposed alignments • Change in land ownership or access rights • Changes to permit process
Implementation of New Facilities • San Vicente Dam Raise, Pump Station, and Pipeline not considered
previously. More treatment plants may now be served
Sunrise Powerlink • Provides closer proximity to power and opportunity to reduce costs
Updated Construction Costs • Use current indices to estimate cost of construction
4
Characteristic Tunnel Corridor Pipeline Corridor Canal, Miles 12 0 Pipeline, Miles 30 81 Tunnel, Miles 41 11 Total Length, Miles 83 92 Pump Stations (800 ft. lift) 2 5 Power Generating Facilities 0 3
Annual Conveyance
(acre-feet/year)
Design Flow Rate
(cfs)
Pipeline Diameter (inches)
Fully Lined Tunnel Diameter
(inches) 280,200 490 961 120
1. Pipelines are sized to avoid on-peak energy pricing.
5
6
7
Normal operations allow QSA supply to be delivered to SVR or directly to untreated aqueduct pipelines
QSA deliveries are monthly as one twelfth (1/12) of total annual supply • Approximately 24,000 acre feet/month in
2021 • Analyze wet weather untreated demand
Address potential impact on winter month operations • Consider portion of the QSA supply in winter
months delivered through the MWD system • Identify required operational changes • Drawdown San Vicente and place water in
storage
Salinity Management
8
Tunnel Alignment
Pipeline Alignment
MWD Wheeling
Total Capital Cost $1.98 billion $2.30 billion
Annual operating cost $71 million $132 million
Unit cost – capital recovery2
$450/AF
$530/AF
Unit cost – annual operating2 $250/AF $470/AF1
TOTAL Unit Cost (2013 Dollars)2 $700/AF $1,000/AF $453/AF
1 – Includes credit for hydroelectric power generation 2 – Amounts are rounded
9
Did not assess feasibility or cost of permitting or environmental mitigation • Cost assumptions and schedule impacts
included in estimates
Time to complete remaining phases • 3 to 4 years for preliminary design, agency
coordination, and environmental compliance • 2 to 3 years for detailed design • 5 to 10 years for construction
Estimate of 10 to 17 years from current project status to bring project online
Final conclusions and recommendation to be included in Master Plan issued later this year • Benefits include avoiding Pipeline 6/expanded
capacity from MWD • Improved conveyance reliability?
10