world bank document · 2016. 7. 11. · multi-donor trust fund for aceh and nias mis monitoring...

54
Document of The World Bank Report No: ICR00002182 IMPLEMENTATION COMPLETION AND RESULTS REPORT (TF-56894) ON A MULTI-DONOR TRUST FUND (MDF) FOR ACEH AND NIAS GRANT IN THE AMOUNT OF US$42 MILLION TO THE REPUBLIC OF INDONESIA THROUGH THE AGENCY FOR RECONSTRUCTION AND REHABILITATION FOR ACEH AND NIAS FOR THE INFRASTRUCTURE RECONSTRUCTION ENABLING PROGRAM June 20, 2012 Indonesia Sustainable Development Unit (EASIS) Sustainable Development Department East Asia and Pacific Region Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 28-Jan-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • Document of

    The World Bank

    Report No: ICR00002182

    IMPLEMENTATION COMPLETION AND RESULTS REPORT

    (TF-56894)

    ON A

    MULTI-DONOR TRUST FUND (MDF) FOR ACEH AND NIAS GRANT

    IN THE AMOUNT OF US$42 MILLION

    TO THE

    REPUBLIC OF INDONESIA

    THROUGH THE

    AGENCY FOR RECONSTRUCTION AND REHABILITATION FOR ACEH AND

    NIAS

    FOR THE

    INFRASTRUCTURE RECONSTRUCTION ENABLING PROGRAM

    June 20, 2012

    Indonesia Sustainable Development Unit (EASIS)

    Sustainable Development Department

    East Asia and Pacific Region

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

  • CURRENCY EQUIVALENTS

    (Exchange Rate Effective June 15, 2012)

    Currency Unit = Indonesian Rupiah

    IDR 1,000 = US$0.107

    US$1 = IDR 9,385

    FISCAL YEAR

    January 1 – December 31

    ABBREVIATIONS AND ACRONYMS

    BRR Bureau for Rehabilitation and Reconstruction for Aceh and Nias

    EIA Environment Impact Assessment

    FM Financial Management

    FMR Financial Management Report

    GOI Government of Indonesia

    IBRD International Bank for Reconstruction and Development

    ICB International Competitive Bidding

    IDA

    IFR

    International Development Association

    Interim Financial Report

    IPM Infrastructure Program Management

    IREP Infrastructure Reconstruction Enabling Program

    LARAP Land Acquisition and Resettlement Action Plan

    MDF Multi-Donor Trust Fund for Aceh and North Sumatra later simplified to

    Multi-Donor Trust Fund for Aceh and Nias

    MIS Monitoring Information System

    MOF

    MoPW

    Ministry of Finance

    Ministry of Public Works

    MOU Memorandum of Understanding

    NCB National Competitive Bidding

    NGO Non-Governmental Organization

    O&M Operations and Maintenance

    PIU

    PDCS

    Project Implementation Unit

    Planning, Design and Construction Supervision

    PMU Project Management Unit

    TA Technical Assistance

    Vice President: Pamela Cox

    Country Director: Stefan G. Koeberle

    Sector Manager: Franz R. Dress-Gross

    Task Team Leader: Khairy Al-Jamal

    ICR Team Leader: Khairy Al-Jamal

    ICR Primary Author: Reda Hamedoun

  • Republic of Indonesia

    Infrastructure Reconstruction Enabling Program

    CONTENTS

    Data Sheet

    A. Basic Information ............................................................................................. i B. Key Dates ......................................................................................................... i C. Ratings Summary ............................................................................................. i

    D. Sector and Theme Codes ................................................................................. ii E. Bank Staff ........................................................................................................ ii

    F. Results Framework Analysis .......................................................................... iii G. Ratings of Project Performance in ISRs ..........................................................v

    H. Restructuring (if any) ..................................................................................... vi I. Disbursement Profile ....................................................................................... vi

    1. Project Context, Development Objectives and Design ..............................................1 2. Key Factors Affecting Implementation and Outcomes .............................................6 3. Assessment of Outcomes .........................................................................................15

    4. Assessment of Risk to Development Outcome ........................................................18 5. Assessment of Bank and Borrower Performance ....................................................18

    6. Lessons Learned.......................................................................................................21

    7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners..........23

    Annex 1. Project Costs and Financing .........................................................................25 Annex 2. Outputs by Component.................................................................................26

    Annex 3. Economic and Financial Analysis ................................................................29 Annex 4. Grant Preparation and Implementation Support/Supervision Processes ......30 Annex 5. Beneficiary Survey Results ..........................................................................33 Annex 6. Stakeholder Workshop Report and Results ..................................................34 Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR ....................35 Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders ......................38 Annex 9. List of Supporting Documents .....................................................................41 MAP .............................................................................................................................42

  • A. Basic Information

    Country: Indonesia Project Name:

    ID-Aceh-Infrastructure

    Reconstruction

    Enabling Program

    (IREP)

    Project ID: P100218 L/C/TF Number(s): TF-056894

    ICR Date: ICR Type: Core ICR

    Lending Instrument: ERL Borrower: REPUBLIC OF

    INDONESIA

    Original Total

    Commitment: US$42.00M Disbursed Amount: US$35.655M

    Revised Amount : US$42.00M

    Environmental Category: B

    Implementing Agencies:

    Bureau for Rehabilitation and Reconstruction for Aceh and Nias (BRR); and

    Ministry of Public Works (MoPW)

    Cofinanciers and Other External Partners:

    Multi-Donor Trust Fund (MDTF)

    B. Key Dates

    Process Date Process Original Date Revised / Actual

    Date(s)

    Concept Review: 02/17/2006 Effectiveness: 09/13/2006

    Appraisal: 03/27/2006 Restructuring(s):

    01/07/2008

    01/10/20091

    04/15/2009

    06/30/20102

    Approval: 06/30/2006 Mid-term Review: 09/30/2008 12/19/2008

    Closing: 10/31/2009 12/31/2011

    1. Shifting costs between components and reviewing the scope of the IPM and PDCSs

    through operational Bank clearance without formal amendment.

    2. The date in the project portal was misquoted as June 28, 2010.

    C. Ratings Summary

    C.1 Performance Rating by ICR

    Outcomes: Moderately Satisfactory

    Risk to Development Outcome: Moderate

    Bank Performance: Satisfactory

    Borrower Performance: Satisfactory

  • ii

    C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)

    Bank Ratings Borrower Ratings

    Quality at Entry: Satisfactory Government: Satisfactory

    Quality of Supervision: Satisfactory Implementing

    Agency/Agencies: Satisfactory

    Overall Bank

    Performance: Satisfactory

    Overall Borrower

    Performance: Satisfactory

    C.3 Quality at Entry and Implementation Performance Indicators

    Implementation

    Performance Indicators

    QAG Assessments

    (if any) Rating

    Potential Problem Project

    at any time (Yes/No): Yes

    Quality at Entry

    (QEA): None

    Problem Project at any

    time (Yes/No): No

    Quality of

    Supervision (QSA): None

    DO rating before

    Closing/Inactive status:

    Moderately

    Satisfactory

    D. Sector and Theme Codes

    Original Actual

    Sector Code (as % of total Bank financing)

    General water, sanitation and flood protection sector 25 9

    Ports, waterway and shipping 25 18

    Roads and highways 25 67

    Water supply 25 6

    Theme Code (as % of total Bank financing)

    Other urban development 100 100

    E. Bank Staff

    Positions At ICR At Approval

    Vice President: Pamela Cox Jeffrey Gutman (acting)

    Country Director: Stefan G. Koeberle Andrew D. Steer

    Sector Manager: Franz R. Drees-Gross Keshav Varma

    Project Team Leader: Khairy Al-Jamal Aniruddha Dasgupta

    ICR Team Leader: Khairy Al-Jamal

    ICR Primary Author: Reda Hamedoun

  • iii

    F. Results Framework Analysis

    Project Development Objectives (from Project Appraisal Document)

    Support the BRR's strategy for infrastructure reconstruction by providing high quality

    technical assistance (TA) in order to ensure that infrastructure program management,

    planning, design and construction management follow adequate standards, and to support

    BRR in overall coordination of the infrastructure reconstruction program.

    Revised Project Development Objectives (as approved by original approving authority)

    The development objectives and key indicators were not revised.

    (a) PDO Key Performance Indicator(s)

    Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised Target

    Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    Indicator 1 : Post Tsunami infrastructure reconstruction and development Monitoring

    Framework for Aceh and Nias

    Value

    quantitative or

    Qualitative)

    N/A

    Framework

    developed and

    applied

    N/A Framework was

    complete and applied

    Date achieved 09/01/2006 12/31/2011 12/31/2011 12/17/2010

    Comments

    (incl. %

    achievement)

    Achieved

    Indicator 2 : A strategic plan for infrastructure reconstruction in Aceh and Nias exists

    Value

    quantitative or

    Qualitative)

    N/A Plan to be prepared

    and utilized N/A

    Plan exists and has

    been utilized

    throughout the

    project.

    Date achieved 09/01/2006 12/31/2011 12/31/2011 12/31/2011

    Comments

    (incl. %

    achievement)

    Achieved

    Indicator 3 : Donors and stakeholders are consulted on the plan and design of projects

    that support implementation of the strategic reconstruction plan

    Value

    quantitative or

    Qualitative)

    N/A

    Donors are

    continually updated

    on implementation of

    the strategic

    reconstruction plan.

    N/A

    Donors are fully

    informed on program

    and project activities,

    now totaling

    US$ 207 million of

    infrastructure from

    the strategic plan and

    additional financing

    of US$ 36.7 million

    Date achieved 09/01/2006 12/31/2011 12/31/2011 12/17/2010

    Comments Achieved

  • iv

    Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised Target

    Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    (incl. %

    achievement)

    Indicator 4 : Proper safeguard measures are integrated into project preparation plan

    Value

    quantitative or

    Qualitative)

    Safeguard

    framework is

    established.

    All IRFF supported

    sub-projects will

    adhere to the

    safeguard framework.

    N/A

    IPM consultants

    established a project

    tracking system that

    incorporated all

    safeguard aspects of

    projects. All

    subprojects

    supported by IRFF

    adhered to the

    framework.

    Date achieved 09/01/2006 12/31/2011 12/31/2011 12/31/2011

    Comments

    (incl. %

    achievement)

    Achieved

    Indicator 5 : Projects funded by BRR through IRFF are matched to articulate demands

    of local governments.

    Value

    quantitative or

    Qualitative)

    None

    Initial and updated

    investments are

    discussed and agreed

    on with local

    government and other

    stakeholders. All

    O&M MOUs to be

    signed with local

    government.

    N/A

    All IRFF investments

    were included in the

    annual investment

    plans, and identified

    as a priority by local

    government. All

    MOUs for O&M and

    asset transfer were

    signed for local

    government project.

    Date achieved 09/01/2006 12/31/2011 12/31/2011 12/17/2010

    Comments

    (incl. %

    achievement)

    Achieved

    Indicator 6 : Works meet the specifications of the technical designs.

    Value

    quantitative or

    Qualitative)

    N/A

    All works comply

    with the design

    specifications.

    N/A

    In general, quality of

    works is good and in

    compliance with the

    design specifications.

    Date achieved 09/01/2006 12/31/2011 12/31/2011 12/31/2011

    Comments

    (incl. %

    achievement)

    95% Achieved as two subprojects were not completed and required design

    reviews.

    Indicator 7 : Projects are of higher quality standards than those prepared and

    implemented prior to the TA.

  • v

    Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised Target

    Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    Value

    quantitative or

    Qualitative)

    N/A

    All sub-projects

    under the TA will be

    of higher standards

    N/A

    In general sub-

    projects prepared

    under the IREP were

    of higher quality and

    bids were subject to

    minor variations and

    designs were more

    detailed.

    Date achieved 09/01/2006 12/31/2011 12/31/2011 12/31/2011

    Comments

    (incl. %

    achievement)

    Achieved

    (b) Intermediate Outcome Indicator(s)

    Indicator Baseline Value

    Original Target

    Values (from

    approval

    documents)

    Formally

    Revised

    Target Values

    Actual Value

    Achieved at

    Completion or

    Target Years

    Indicator 1 : All Consultants are appointed and functioning.

    Value

    quantitative or

    Qualitative)

    No consultant is

    selected

    All consultants

    including IPM,

    PDCSs and FM are

    selected.

    N/A

    All consultants

    including IPM,

    PDCSs and FM

    were selected and

    functional

    Date achieved 09/01/2006 03/31/2007 03/31/2007 03/31/2007

    Comments

    (incl. %

    achievement)

    Achieved

    G. Ratings of Project Performance in ISRs

    No. Date ISR

    Archived

    Development

    Objective

    DO

    Implementation

    Performance

    IP

    Actual Disbursements

    (US$ millions)

    01 03/20/2007 Moderately

    Satisfactory

    Moderately

    Satisfactory

    0.00

    02 01/04/2008 Moderately

    Satisfactory

    Moderately

    Satisfactory

    7.28

    03 06/30/2009 Moderately

    Satisfactory

    Moderately

    Satisfactory

    17.80

    04 06/30/2010 Moderately

    Satisfactory

    Moderately

    Satisfactory

    28.13

  • vi

    05 03/29/2011 Moderately

    Satisfactory

    Moderately

    Satisfactory

    33.99

    06 12/25/2011 Moderately

    Satisfactory

    Moderately

    Satisfactory

    34.89

    H. Restructuring (if any)

    Restructuring

    Date

    Board

    Approved

    PDO change

    ISR Rating at

    Restructuring

    DO IP

    Amount Disbursed

    at Restructuring in

    US$ Millions

    Reason for

    Restructuring &

    Key Changes

    Made

    01/07/2008 MS MS 7.28 Review the scope of

    the impacted area.

    01/10/2009 MS MS 16.28 Review the scope of

    IPM and the PDCSs

    and shifting costs

    between

    components.

    04/15/2009 MS MS 17.8 Restatement of GA,

    MoPW became the

    implementing

    Agency after

    closure of BRR and

    extension of

    Closing Date to

    June 30, 2010.

    06/30/2010 MS MS 28.13 Extension of the

    closing date to

    12/31/2011.

    I. Disbursement Profile

  • vii

  • 1

    1. Project Context, Development Objectives and Design

    1.1 Context at Appraisal

    Country and sector context

    The tsunami of December 26, 2004 killed or left missing more than 230,000 people in

    Indonesia, and the total reconstruction and development program for Aceh and Nias was

    estimated to cost up to US$9 billion through 2009. The estimate of the damage to the

    housing sector alone was US$ 1.4 billion, with the demand for new housing ranging from

    93,000 to 120,000 units. The government of Indonesia (GoI) created a dedicated

    Rehabilitation and Reconstruction Agency– Badan Rehabilitasi dan Rekonstruksi (BRR)

    - to lead the recovery efforts. The BRR’s priorities were to (i) strengthen coordination

    between donors and government agencies; (ii) ensure pledges for infrastructure are

    prioritized and matched with sector needs; (iii) improve the quality and pace of

    infrastructure reconstruction supporting housing/settlements; (iv) develop institutional

    resources for sustainable infrastructure operations and services after the BRR’s operating

    period; (v) improve cost effectiveness through quality management and competitive

    procurement; and (vi) and increase the efficiency and flexibility of the capital works

    planning and budgeting process.

    Rationale for Bank Assistance

    As a leading international development agency in the area of post-disaster reconstruction,

    with a longstanding engagement with relevant government agencies in Indonesia and

    around the world, the Bank was well-position to support BRR in its reconstruction

    efforts. In addition, the Bank’s involvement in Indonesia’s community-driven

    development program also provided a platform to quickly replicate stakeholder

    consultation and participation mechanisms and to scale up financing to specifically

    address reconstruction needs. GoI had also asked the Bank to take a lead in coordinating

    the donor community, requesting suggestions on how this could be handled in practice. In

    March 2005, the Bank formally established the "Multi-donor Trust Fund for Aceh and

    North Sumatra" (MDTFANS), later simplified to "Multi Donor Fund for Aceh and Nias

    (MDF)". The Bank also provided at the same time a grant of US$25 million as a

    contribution to the MDF. In all, 15 funding agencies contributed an initial US$550

    million to the MDF. The Bank and the European commission channeled all their support

    through the MDF, while the Nordic countries, the Netherlands and Belgium provided half

    or more of their funding through the MDF.

    Project Background and development

    It was noted that most of the funds pledged to support rehabilitation and reconstruction in

    Aceh were quickly programmed by the GoI, leaving mostly gaps to finance minimum

    needs in certain critical areas. BRR’s strategy, therefore, was to focus on the remaining

  • 2

    available funds to ensure that they were allocated to cover these gaps. Of the donor

    resources, the MDF was the largest source of programmable funds with US$230 million

    still available to be programmed at the time IREP was approved. Among other priorities,

    BRR’s medium-term strategy called for the main utilization of the remaining MDF

    resources for the reconstruction and development (i.e., building back better) of

    infrastructure in the areas most damaged by the tsunami and earthquake in Nias and

    Aceh.

    In order to guide the investment program during BRR’s assignment period, BRR

    developed an Infrastructure Reconstruction Strategy. This strategy encompassed three

    phases: (i) the execution of the ongoing MDF-supported Immediate Action Plan (IAP)

    agreed upon in November 2005 to meet urgent infrastructure needs; (ii) the proposed

    Infrastructure Reconstruction Enabling Program (IREP), which would provide technical

    assistance for the mobilization of human resources and technical support to BRR,

    provincial, and local governments; and (iii) investment in infrastructure works by BRR

    and other donors, including through a proposed Aceh Infrastructure Reconstruction

    Facility (IRFF). The implementation of IRFF would be financed through the MDF and

    the GoI and the technical support would be managed under IREP.

    IREP was designed to work within the prevailing infrastructure framework and strategies

    of GoI, and with numerous agencies and donors involved in the reconstruction effort in

    Aceh and Nias. In conjunction with IREP, local and provincial governments were

    expected to build project management capacity; prepare infrastructure development

    plans, feasibility studies, detailed designs, comprehensive procurement planning; and

    provide support during construction supervision.

    1.2 Original Project Development Objectives (PDO) and Key Indicators (as

    approved)

    The development objective of the project was to support BRR's strategy for infrastructure

    reconstruction by providing high quality technical assistance in order to ensure that

    infrastructure program management, planning, design and construction management

    follow adequate standards, and to support BRR in overall coordination of the

    infrastructure reconstruction program.

    The Key Performance Indicators for this development objective at appraisal were:

    1. Development of a sustainable and strategic long-term infrastructure reconstruction plan for Aceh and Nias;

    2. Donors and other stakeholders are consulted on the infrastructure reconstruction plan and design projects that support implementation of the strategy;

    3. Technical designs created during project appraisal ensure appropriate quality measures have been included;

    4. Consultant teams and local and provincial governments prepare projects that incorporate adequate procurement and financial management practices and safeguards

    measures;

  • 3

    5. The scale of funding committed to implement projects submitted by local and provincial governments to BRR as part of their AIPs;

    6. Projects are of higher quality standards than those prepared and implemented prior to the TA;

    7. Increased participation of local and provincial government staff to incorporate appropriate safeguards measures and financial management and procurement

    practices during project design and implementation.

    In principle, the PDO and the performance indicators are consistent in the project

    documents with very minor discrepancies between the PAD and the Legal Agreement.

    1.3 Revised PDO (as approved by original approving authority) and Key Indicators,

    and reasons/justification

    The development objectives and key indicators were not revised.

    1.4 Main Beneficiaries

    In a narrow sense, the direct beneficiaries were the BRR, Ministry of Public Works

    (MoPW), project management unit (PMU), project implementation unit (PIU), and local

    consultants who saw their capacity in infrastructure management, design, monitoring and

    construction supervision improve. However, the true beneficiaries in a broader sense

    were the people of Aceh and Nias (around 1.6 million inhabitants), who benefitted from

    the strengthened capacity of these entities to plan and implement infrastructure

    reconstruction projects in the disaster affected area.

    IREP was strategically integrated with the Infrastructure Reconstruction Financing

    Facility (IRFF), another project executed with the Bank acting as Partner Agency on

    behalf the MDF. To a large extent, IRFF focused on financing the infrastructure sub-

    projects prepared with technical assistance from IREP. IREP worked with 12 local

    governments: 7 local governments in the West Coast Logistical Area, 2 in Nias, the

    remaining 3 local governments being Aceh Besar, Banda Aceh and Sabang. At the

    provincial level, IRFF included strategic projects, prepared by the provincial government

    with IREP support. Some of these projects were located outside the jurisdiction of the 12

    local governments to cover the East Coast and central parts of Aceh but this was

    consistent with amendment no. 1 to the Grant agreement.

    1.5 Original Components (as approved)

    The US$42 million program consisted of five consultancy TA components to be

    implemented over a three-year period:

    Component 1 - Infrastructure Program Management (US$19.5 million) to support the mobilization of a highly skilled Infrastructure Program Management (IPM) team

    deployed within the existing BRR structure to coordinate the infrastructure program

    and its activities at the macro level. These experts were mobilized to provide

    assistance to BRR in eight specific areas: (i) overall strategic infrastructure planning

    for Aceh and Nias, as per the BRR Infrastructure Reconstruction Strategy; (ii)

  • 4

    management of the infrastructure reconstruction program in Aceh and Nias; (iii)

    review of local and provincial governments’ plans for infrastructure investment as a

    basis for BRR funding; (iv) quality control, supervision, and monitoring o f BRR-

    funded infrastructure projects; (v) procurement support; (vi) safeguard support for

    BRR-funded infrastructure projects; (vii) anti-corruption support for BRR-funded

    infrastructure projects; and (viii) management and coordination of other IREP

    consultant teams. At all times, Consultants in Components 2, 3, 4, and 5 reported

    directly to BRR, not the IPM Consultants. The first two tasks of this component

    referred to the entire infrastructure reconstruction program throughout Aceh and Nias,

    as these areas encompassed the work of both the government and other development

    partners. The remaining six activities focused on BRR funded activities.

    Component 2 - West Coast Infrastructure Planning, Design, and Construction Supervision (US$l0 million) to finance a technical team to undertake the planning,

    project preparation, and implementation work for the West Coast Logistical Area.

    This team provided assistance to the local governments in three main areas: (i)

    strategic planning; and (ii) project design and implementation; and (iii) institutional

    development support, including the development of a long term maintenance strategy,

    and training. The assignment led to the mobilization of a project team with skills in

    infrastructure planning and program management, institutional development,

    implementation methods of essential services delivery, technical design and

    procurement, construction planning and management, and construction supervision.

    As planned, all works were conducted in close collaboration with local governments

    and public works and in consultation with local communities.

    Component 3 - Nias Infrastructure Planning, Design, and Construction Supervision (US$5 million) to support mobilization of a technical team to undertake the planning,

    project preparation, and implementation work for the Nias logistical area. As planned,

    the work focused on repairing the transport network. The consultant team provided

    assistance to the local governments involved in three main areas: (i) strategic

    planning; (ii) project design and implementation; and (iii) institutional development

    support and training. All works were conducted in close collaboration with local

    governments and public works and in consultation with local communities.

    Component 4 - Strategic Infrastructure Project Planning, Design, and Construction Supervision (US$6 million) to finance a technical consulting team to undertake the

    formulation, investment planning, design, and project implementation work for

    strategic infrastructure projects at the provincial and or national level, or with local

    governments not covered by components 2 and 3. This component was designed to

    strengthen the ability of BRR and that of the relevant governments to carry out

    project identification, appraisal, and implementation. The Provincial Government

    participated in the selection and development of the “strategic projects” and

    participated in management of the TA consultants. The infrastructure projects

    financed under this TA were mainly related to ports, and key roads managed by

    provincial, national or local government entities.

  • 5

    Component 5 - Financial Management of BRR-financed Projects (US$1.5 million) to

    strengthen BRR’s capacity to put in place the financial management framework

    required to ensure that it meets all its fiduciary responsibilities with respect to this TA

    and other BRR investment projects. This assistance was provided by a team of

    experts that, initially, was located within BRR and later worked side by side with the

    PMU at the MoPW. Financial management of BRR-financed projects included PMU

    and PIUs to establish and maintain financial accounting and statement arrangements

    for project activities undertaken and expenditures incurred at all project locations,

    including monitoring the operation of internal controls over implementation of the

    contracts.

    1.6 Revised Components

    None.

    1.7 Other Significant Changes:

    Amendment No.1, “Review of the Project Area”, January 7, 2008: This amendment effected the change in the project service area and introduced the “West Coast

    Logistical Area" which covers the West Coast Kabupatens of Aceh Jaya, Aceh Barat,

    Nagan Rava, Aceh Barat Daya, Aceh Selatan, Aceh Singkil, Simeulue, Aceh Basear,

    Banda Aceh and Sabang, and such additional Kabupatens as may be agreed by the

    Association in writing. The original Legal Agreement referred only to Aceh Jaya,

    Aceh Barat, Nagan Raya, Aceh Barat Daya, Aceh Selatan, Aceh Singkil and

    Simeulue.

    Amendment No. 2 “Grant Agreement Amendment and Restatement”, April 15, 2009: BRR closed on April 16, 2009, and the implementation of the project was entrusted to

    the national Ministry of Public Works (MoPW). The institutional and legal transition

    to MoPW was carried out smoothly. Thus, the implementing agency for IREP (and

    IRFF) became the MoPW. The new PMU was tasked to handle the remaining

    construction works in Aceh and Nias, and was staffed with many former BRR

    officials for a seamless continuation of the project implementation. The IREP grant

    agreement was amended to reflect the new arrangements and to extend the closing

    date to June 30, 2010 in order to match the closing date of IRFF, at that time.

    Amendment No. 3 “Extension of closing date”, June 30, 2010: the Regional Vice President approved a second closing date extension, which brought the cumulative

    extension to 26 months.

    Shifting costs between components, January 10, 2009: As detailed in Annex 1, the actual costs by component changed substantially from those estimated at appraisal.

    The main change was to reduce the resources dedicated to Components 1 and 2, and

    increase financing for Component 4. This was done to accommodate changing needs

    and priorities, to take advantage of opportunities to increase project effectiveness and

    efficiency, to make the best use of project resources and to balance the

  • 6

    implementation schedules of components 2, 3 and 4. The changes were requested by

    the government, agreed by the Bank, and did not require amendments of the grant

    agreement.

    2. Key Factors Affecting Implementation and Outcomes

    2.1 Project Preparation, Design and Quality at Entry

    Institutional design: Four months after the devastating tsunami and earthquake, the GoI

    established the BRR to manage the reconstruction program of Aceh with an estimated

    budget of $6-9 billion. According to the end of first year assessment (December 2005),

    the first reconstruction priority was the provision of housing (which was well underway

    and progressing adequately). However, as the second reconstruction priority (rebuilding

    and restoring essential infrastructure) made very little progress, BRR recognized the need

    to apply better spatial planning to handle the reconstruction program. Accordingly, Aceh

    and Nias were divided into five areas (North Coast, West Coast, Nias, East Coast and

    Middle Aceh). BRR recognized the complexity of the scope and diversity of the skills

    needed to implement the reconstruction program and the need to centralize the program

    management under a limited number of relatively large consultancy services. The

    thinking was to expedite the reconstruction process and to ensure adequate design and

    construction quality, which led to the design of the project under its five components, as

    described above. Based on its long experience and technical resources to respond to

    emergency situations, the World Bank was requested to prepare IREP.

    Lessons learned from similar operations: In order to optimize the design of IREP, BRR

    incorporated lessons learned from its first year of operation. This included: (i) the need

    for supplemental capacity in the BRR to implement and supervise infrastructure projects;

    (ii) the imperative that local and provincial governments identify their priorities within a

    framework of good practice; (iii) coordination across development partner and

    government reconstruction programs; (iv) the allocation of sufficient resources for close

    supervision of works to ensure quality construction; and (v) the importance of engaging

    communities and other stakeholders throughout the project cycle.

    BRR developed a Blueprint for projects before Component 1 was in place, due to the

    time pressures of the reconstruction agenda and BRR’s own short life term. BRR

    anticipated that this list would need to be revised at some stage and that the designs

    would need to be updated. The scope of services of the PDCS consultants accounted for

    such a need and all construction works under IRFF were subject to design review prior to

    their tendering. Moreover, the priority list was adjusted to reflect the changing demands

    from the local authorities and to account for socio-economic and political factors

    (especially along the East Coast and Middle Aceh).

    Design of the implementation arrangements: During the project's preparatory stage,

    within the overall time constraints, the implementation arrangements were detailed and

    set up satisfactorily (including necessary fiduciary requirements related to procurement,

  • 7

    disbursement and financial management). This was instrumental in the satisfactory

    implementation of the project. By preparing the project in six months, the preparation

    team also distinguished itself in terms of responsiveness, a crucial attribute in the

    development of emergency operations. BRR had established the PMU, led by senior BRR

    staff, to oversee project implementation and to interface with all consultants and donors

    with the support from the IPM.

    Assessment of risks: The financial management and procurement risks were rated as

    substantial and high respectively, due to the limited capacity of BRR. However, the

    project design addressed these risks adequately through: (i) the hiring of the FM

    consultant as described in component 5 of the project; (ii) the hiring of a Procurement

    Advisory (PA) team financed by DFID; (iii) the activation of internal FM controls; (iv)

    application of BRR and MoPW internal audits; and (v) the hiring of the services of

    external audits.

    All in all, the project responded to GoI’s reconstruction priorities to produce a simple

    design that avoided implementation difficulties. However, in hindsight, several areas

    were identified where project preparation could have been improved:

    Sub-project identification: The process of ex-ante definition of the portfolio seemed consistent at the time with the short timeframe available. However, this method made

    it inevitable that some important projects would be missed, for some feasibility

    studies to be insufficient at the outset (in water supply or ports) or for some projects

    to be included for political reasons rather than reconstruction realities. Bank

    supervision missions noted that there was pressure from BRR to approve incomplete

    and preliminary designs.

    Capacity Building: IREP design aimed at achieving both short-term reconstruction objectives and longer-term objectives of enabling and capacity building of local

    governments. Though an emphasis on capacity building was rightly identified during

    project preparation as crucial to ensure the sustainability and maintenance of the

    assets produced by the program, the lack of resources devoted to it made its

    achievement unrealistic. With a large reconstruction program to deliver in a tight time

    frame and an under-sourced capacity building component, planning, procurement and

    contract management could not always be conducted in a satisfactory manner.

    Institutional design: IREP designed a one-door communication system, in which any communication between the consultants and the Bank, as well as coordination with

    related central government level agencies would be carried out through the PMU. A

    good concept in principle, this communication system turned out to be burdensome

    for all parties involved. For an understaffed PMU, it meant an increased workload

    while it had to manage a large infrastructure program. For the consultants, it resulted

    in incomplete information sharing and time delays in receiving guidance and

    instructions, as the flow of information with the gatekeeper (the PMU) became

    increasingly imperfect. This situation was even clearer when the BRR was closed and

    the MoPW became the implementing agency. For the Bank, it meant putting in place

  • 8

    a track for information gathering and monitoring that was independent from the PMU

    in some instances, which led to an unnecessary increase in the workload for

    consultants and the Bank task team.

    Role of Infrastructure Program Management (IPM) Team: The IPM was designed to assume the responsibilities of a “super-consultant” and trusted advisor to the BRR,

    which recognized during project preparation that it lacked the adequate capacities in

    terms of strategic planning and program management. However, this role proved to

    be too broadly designed and overly ambitious as it tasked the consultant to provide

    assistance in eight different areas (strategic infrastructure planning, management of

    infrastructure, review of local and provincial government plans, quality control,

    procurement, safeguards, anti-corruption efforts, and management and coordination

    of the four other IREP consultant teams).

    2.2 Implementation

    Scope, timing, and effectiveness of IPM consultancy. In mid-2008, it was decided that IPM should limit its focus to areas of core implementation, including program

    management and quality assurance, and reduce its engagement in capacity building.

    IPM had been delivering work outside of its original TORs in response to the client’s

    requests, while at the same time having delays in the submission of key deliverables.

    After consultation with the Bank, the BRR decided to refocus IPM resources to

    optimize delivery of IRFF sub-projects and to save costs.

    The IPM consultant was mobilized late, after BRR had started its planning. This

    undermined the ability of IPM to influence strategic planning at the early stage and

    did not help to properly position IPM to be in the driver’s seat in terms of leading the

    reconstruction planning process. Moreover, the improper use of funds by the IPM

    consultant as proven in 2010 led to a lack of trust between the consultant and BRR

    and later MoPW. Accordingly, MoPW decided not to extend the contract of the IPM

    consultant beyond its amended end date in March 2010.

    Flexibility in allocating resources between contracts. In the course of implementation, the five consultancy contracts financed under IREP were amended to

    reflect evolving priorities, adequately balance the allocation of resources among

    consultants, and adapt to the closure of BRR. Due to the dynamics of the

    reconstruction program, this proactive flexibility on the part of BRR and MoPW was

    pivotal in facilitating the mobilization of adequately staffed international consultants

    to ensure proper designs and good construction quality. This was particularly true for

    the Planning, Design, and Construction Supervision (PDCS) activities. BRR regularly

    reassessed whether the PDCS consultants had the right resources in place, and

    contracts were amended to reflect these assessments.

    Restructuring: As explained in more detail in Section 1.6, the project was restructured three times to clarify the geographic scope of the project, formalize the transition to a

  • 9

    new implementing agency, and extend the closing date twice. The restructurings were

    fairly routine in nature, but helped ensure proper targeting, smooth implementation,

    and alignment of IREP with IRFF (and in particular with the additional financing and

    extension of IRFF).

    2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization

    M&E Design: The project design included well-conceived, appropriate outcome

    indicators that were clearly linked to the development objectives, verifiable either

    quantitatively or qualitatively, and attributable to project interventions. There were some

    minor discrepancies between one section of the PAD and another, but the substance was

    the same, and the intent was clear. Due to the importance of the M&E in both guiding

    project implementation and assessing outcomes, and the shortcomings in the capacity of

    BRR, the design called for the IPM to provide support in carrying out the M&E functions.

    The design called for the development of a computerized Monitoring Information System

    (MIS) which was expected to facilitate the monitoring of outcome indicators and routine

    project implementation and financial management for both IREP and IRFF.

    M&E Implementation: The IPM successfully produced regular M&E reports, which were

    integral parts of the Semi Annual Reports that compiled data provided by the PDCS and

    FM consultant (and confirmed by IPM quality assurance staff). In addition, the PMU

    developed a Monthly Portfolio Review for a quick monitoring of the progress of all sub-

    projects under IRFF and updated the performance indicator matrices for both IREP and

    IRFF.

    The efforts of IPM to develop a stand-alone computerized MIS were not fully successful

    and the system was never used as the focal database for the program. Development of the

    system took longer than expected, and ultimately the BRR developed its own MIS system

    which made a separate system specifically for IREP redundant and unnecessary. While

    the MIS was intended to monitor both physical progress and financial performance, the

    shortcomings and delays in the MIS system did not significantly hinder monitoring of the

    KPIs, many of which were qualitative in nature.

    M&E Utilization: The data and information gathered from the field were compiled by the

    IPM consultant and communicated to the PDCS consultants to review the designs of

    some sub-projects. This is clear in some roads projects where the soil turned to be

    unstable and the need to strengthen the road shoulders was eminent in order to mitigate

    the impact of potential landslides. Moreover, in order to maximize the returns from

    BRR’s MIS, it had been centrally connected to Bappenas’ MIS which enabled sharing the

    project information at the central level.

    2.4 Safeguard and Fiduciary Compliance

    Procurement

  • 10

    All major procurement, such as the selection of the design review and construction

    supervision consultants, FM consultant, and program management consultant was

    performed in a timely fashion and was generally satisfactory over the course of the

    project. BRR was assisted by the Procurement Advisor (PA), financed by DFID, to

    prepare all of the early procurement packages. Only the delay in the appointment of

    individual consultants for program management and supervision of the sub-projects

    carried out under the relatively minor gaps of IRFF was moderately unsatisfactory.

    IREP also provided support to BRR and the MoPW to set up adequate procurement

    procedures for the procurement of the 56 contract packages (signed value of US$223.62

    million) carried out under IRFF and followed by four contract packages (signed value of

    US$31.51 million) under IRFF Additional Financing. In particular, IPM was tasked to:

    Provide direct support to BRR and local government procurement activities during the first 1.5 to 2 years.

    Identify and agree with BRR alternate and appropriate procurement procedures and regulations for each set of investments.

    Assist the preparation of tender documents for international and national procurement on BRR, National or World Bank Guidelines.

    Provide guidance on procurement, contract packaging and bid documentation to other agencies.

    Recommend the contract packaging and detailed strategy of the works for BRR.

    To this end, IPM provided comprehensive support throughout the procurement process

    and proceeded to the establishment of a Central Procurement Unit (CPU) within BRR.

    The Bid Documents were standardized for National Competitive Bidding (NCB),

    applying to works costing up to US$5.0 million, International competitive Bidding for

    large civil works (ICB large works) costing above US$10.0 million. The procurement

    manual was prepared detailing the procurement implementation steps and decision- tree

    for the procurement committees and CPU. The standard operating procedures were

    designed. The packaging of works, identification of appropriate document procedures and

    regulations for the identified sub-projects were developed. IREP, through IPM, also

    provided advice to the CPU on the finalization of the procurement plans.

    In addition to this, the IPM advised the procurement committees on bid evaluation,

    advised the CPU on procurement decisions, investigated complaints, reviewed the bid

    evaluation reports, addressed comments from the Bank, prepared winner notifications,

    letters of acceptance and draft contracts, revised (after the Bank supervision mission of

    September 2009) the General Conditions of Contract Clause 38 for both NCB and ICB

    contracts to provide an allowance for physical contingencies or provisional sums for

    unforeseen items, and prepared the procurement completion report of the 56 IRFF

    contract packages.

    As a result, the IRFF procurement phase was completed in 18 months with an average

    time for procurement from advertising to contract signing of 150 days for NCB and 210

  • 11

    days for ICB. The Bank supervision mission of December 2008 noted that procurement

    process was being carried out efficiently and in accordance with the scheduling process.

    Financial Management

    The FM aspects were in general in compliance with Bank procedures (and with

    additional standards as the financial controls included a Supreme Audit evaluation report,

    as well as an annual external audit evaluation report). The external audit reports also

    concluded with unqualified compliance. However, the following issues were identified

    during the early stages of project implementation:

    Delayed payments during project implementation: The delays adversely affected the PDCS consultants’ work and their ability to retain staff and conduct field supervision.

    The delays were mostly due to the bureaucratic complication of yearly reappointment

    of PPK/Satkers who had responsibility and authority in the budget allocation

    (DIPA’s) process. However the PPK/Satker reappointment delay was reduced by

    PMU and MoF at the Bank prompting from three months to one month.

    The Interim Financial Report (IFR) submissions were chronically late, despite the Bank missions’ systematic reminders that PMU (through IREP 5) should submit them

    45 days after each quarter closes. The Bank also recommended that the PMU should

    implement a financial penalty to any underperforming consultants who submitted

    their reports late. These delays were also a reflection of the dysfunctional MIS, as the

    FM consultant (IREP 5) could not rely on a comprehensive and up to date monitoring

    database and information flows with the three other consultants (IPM and the three

    PDCS) were not smooth. IREP 5 did not have access to some contract amendments,

    or IPM did not receive updated physical progress information from PDCS in a timely

    manner. Numerous occasions arose where the FM consultant received conflicting

    information from the contractors and the PDCS consultant on the progres of works,

    especially in Nias. These delays improved during the later stages of the project as the

    FM consultant proactively compiled and consolidated IPM and PDCS reports.

    The financial control systems were less than satisfactory as the oversight role of IREP 5 was limited. IREP 5 did not have adequate access to all documents and was

    unable to verify all payments as per their TORs and project SOPs. A Bank

    supervision mission in April 2009 noted that only 30% of payments were verified by

    the FM consultant. Corrective measures, including that no payment request should be

    processed without prior verification from the FM consultant, were raised by the Bank

    and led to the gradual improvement of FM oversight as noted in the ISRs.

    Environment

    Although IREP’s scope encompassed only the procurement of services to support

    infrastructure reconstruction, the PAD noted that it would have, in practice, the effect of

    programming very significant resources for reconstruction in Aceh and Nias. Key

  • 12

    environmental impact areas to be considered included: resource extraction impacts

    (primarily sourcing of sand, gravel and other quarry material) and construction impacts

    (excavation, fuel spills, noise, dust, obstruction to drainage, pollution and sedimentation

    of water courses).

    The approach followed was to task the IPM team to support BRR efforts in meeting the

    environmental safeguards requirements by providing advice to BRR on all safeguards-

    related issues and in assisting it in drafting action plans, preparing an Environmental

    strategy for approval by BRR, engaging additional and specialist consulting support to

    prepare all required social and environmental studies (AMDAL, UKL/UPL, and LARAP)

    and to ensure that contractors and suppliers operated in accordance with accepted

    contractual safeguard requirements.

    It was agreed from the start that the Indonesian AMDAL legislation and procedures

    would satisfy the Bank’s requirements, particularly for the planning and design of the

    packages. During the 2007 Bank supervision mission, the Bank and BRR agreed to

    implement a modified system of quality assurance designed by the IPM safeguards team

    that was set out in a draft Environmental Management and Monitoring Protocol. The

    Protocol linked the design and planning phase to the implementation of the project and

    applied to all project packages. In effect, this created the Construction Environmental

    Action Plan (CEAP) as a unique feature applying to all IRFF sub-projects. However, 22

    projects which were already approved or in the procurement stage at the time of the 2007

    supervision mission were excluded from the new CEAP requirement.

    Overall, environmental management during implementation was satisfactory, and the

    Bank task teams showed serious interest and concern for good safeguard management.

    This engagement was particularly visible in the following areas:

    Regulatory requirements, including Bank review and clearance: Most regulatory requirements were met, and approval by GoI and review and clearance by the Bank

    were issued. It must be noted, however, that some environmental assessment studies

    were not up to Bank standards, which cleared some with the condition that a

    supplementary CEAP be done for the construction stage. Also, the Bank’s

    environmental specialists reviewed most AMDAL studies received, plus a sample of

    the UKL/ UPL documents, and their quality was considered to be generally

    acceptable.

    Bank supervision: In addition to the Bank’s regular supervision missions, Bank staff based in Banda Aceh carried out periodic field visits to review construction progress,

    quality and safeguards aspects. As a matter of practice, the key findings were

    provided immediately to the BRR, IPM and the three PDCS upon return from the

    field, with detailed recommendations and target dates for completion of actions.

    Environmental monitoring, reports and actions: The environmental monitoring site visits and subsequent reports by the PDCS consultants added significant value in

    terms of quality improvement of implementation. A number of serious design flaws

  • 13

    were identified by these field visits. Actions for improvements, including specific

    instructions to the contractors by the supervision engineers, were recommended by

    the monitoring teams. They also provided coaching and mentoring to contractors and

    supervision field staff on how to do better environmental management.

    Interventions addressed at contractors: The CEAP model proved to very useful and positively impacted environmental performance under the construction contracts. For

    instance, a template for a CEAP for a typical road project was prepared by the IPM

    consultants, which helped to improve the quality of the plans, and ultimately the

    quality of implementation. Two other contracts (Calang Port and Kota Sigli WS) used

    a CEAP prepared with the help of the PDCS consultants and implementation quality

    was found to be generally better.

    Social Safeguards

    Social safeguard policies triggered by IREP were, as outlined in the PAD, involuntary

    resettlement and indigenous peoples. Although, the actual supervision and monitoring of

    land acquisition/resettlement and compensation was within the scope of IRFF (IREP was

    only tasked with providing consultancy services in this area), it should be noted that

    timely compensation was provided for the ten sub-projects involving land acquisition.

    Bank supervision missions regularly provided updates on the status of land acquisition

    and documentation, and monitored the submission of IPRs. Where specific issues arose,

    the Bank was pro-active and diligent. When the Tj. Meulaboh-Pante Cermin kabupaten

    road subproject was about to acquire a piece of land with an old house on it, the Bank

    requested IPM to confirm that a negotiation between the BRR and land owner would be

    done properly, that compensation levels would be set at or above the market price and

    that remaining land plots could be used for productive activities.

    IPM was tasked to provide advice to BRR, help it prepare social studies, and assist in

    ensuring that all social safeguards requirements were met. It was agreed for social

    safeguards that the project would strictly follow Bank policies and procedures (the main

    areas of difference between Bank and local policy included land acquisition,

    compensation, resettlement, indigenous people, gender and social inclusion). To this end,

    IPM developed social management plans for any subproject with a potential social impact

    on surrounding communities, such as the Lohseumawe Drainage and Reservoir project

    and Calang-Meulaboah Road. Both local and provincial governments were cooperative

    and fairly compensated impacted people.

    2.5 Post-completion Operation/Next Phase

    The sustainability and maintenance of the assets was probably the most important issue

    affecting the project. The PAD did identify the main sustainability risks arising from the

    expiration of the BRR mandate in April 2009 (i.e., before the closure of IREP and IRFF):

    (i) local and provincial governments might not own the projects financed by BRR, which

    could result in inadequate maintenance in the post-BRR period, and (ii) local government

  • 14

    revenues derived from natural resources would likely decline as Aceh’s share of oil and

    gas revenues would decrease after 2009.

    Out of the 56 IRFF sub-projects, 13 sub-projects, comprising 34 % of the total asset cost

    were handed over to the central authorities (5 ports to the Ministry of Transportation; and

    8 national roads to the MoPW). Those packages are being managed following the

    national standards and using national budget allocations.

    9 provincial road sub-projects comprising 32% of the total asset cost were handed over to

    the Aceh and North Sumatra provincial governments. As with other provincial assets,

    these roads are being managed by the Provincial Dinas with adequate maintenance

    budget allocations.

    For the remaining projects (34% of the total assets), MoUs for assets handover were

    signed between BRR and local governments (based on a standard template drafted by

    IREP consultants), but the financial capacity of local governments did not always allow

    them to devote sufficient funds for maintenance. In a context where decentralization

    efforts have not been complete in the project area (infrastructure maintenance fund

    allocation have been historically centralized in Jakarta), local governments do not always

    dispose of sufficient funds to meet expenditures or prioritize new construction over

    maintenance of existing assets. While the MOUs served to ensure smooth asset transfers

    to the local authorities, the low capacity of these local authorities to manage these assets

    remains a concern which is shared among the entire Aceh reconstruction program.

    The Bank supervision teams were mindful of these risks, but efforts to remedy the risks

    posed to sustainability of the assets produced limited results in terms of actual allocation

    of maintenance funds. These efforts included:

    The review by all PDCS and IPM of district level projects to assess if there were local government initiatives critical for successful and long-term operation of the

    investment (these reviews were added to MOUs as addenda).

    Local governments capacity assessments, which were implemented for 12 provincial/district governments, including: Aceh province, Banda Aceh, Sabang,

    Aceh Besar, Aceh Jaya, Nagan Raya, Aceh Barat, Aceh Barat Daya, Aceh Selatan,

    Aceh Singkil, Nias and Nias Selatan. Consequently, capacity building program plans

    were produced. The assessments were conducted through a series of focus group

    discussions that aimed at identifying strengths and weaknesses of local governments

    in terms of reconstruction management and maintenance programming.

    A request to the PMU in May 2010 to prepare a complete listing on each IRFF contract containing, among other data, an action list for ensuring final ownership and

    sustainability.

    The donors and MDF called upon GoI to ensure that the maintenance costs were

    budgeted for and transferred to the local governments. It is worth noting that the local

    governments have received some capacity building, through other projects like

  • 15

    Earthquake and Tsunami Emergency Support Project (ETESP) funded by ADB, Aceh

    Emergency Response and Transitional Recovery project managed by the UNDP, Support

    to Local Governments and Community Planning project, funded by GTZ and other

    projects funded from USAID, EU, CIDA, JICA, the Netherlands and France. This needs

    to be considered in the design of any future capacity building program to avoid

    duplication.

    3. Assessment of Outcomes

    3.1 Relevance of Objectives, Design and Implementation

    The project objectives remain highly relevant to the development priorities of Indonesia.

    The development of large-scale infrastructure remains crucial to the country, and is a

    pillar of the Bank’s engagement (Core Engagement 2) as outlined in the 2008-2012

    Country Partnership Strategy (CPS). The document recognizes the need to strengthen the

    accountability and capacity of institutions to deliver better infrastructure outcomes.

    The project objectives are also highly relevant to the Bank’s strategy to play a major role

    in disaster reconstruction, helping to reduce Indonesia’s vulnerability to natural disasters

    as outlined in the CPS (Core Engagement 5). The document stressed that the Bank would

    continue deepening the relationships established with Bappenas and the local

    governments of Aceh and Nias in supporting selected elements of the Government’s

    actions to strengthen natural disaster resiliency.

    Implementation arrangements were consistent with the country policy to build capacity

    within national institutions. After BRR closed in 2009, the implementing agency of IREP

    became the MoPW. The new PMU was tasked to handle remaining construction work in

    Aceh, and was staffed with many former BRR officials for continuity.

    3.2 Achievement of Project Development Objectives

    Provision of high quality technical assistance in order to ensure that infrastructure

    program management, planning, design and construction management follow

    adequate standards (Moderately Satisfactory):

    The project strongly supported the BRR’s strategy for infrastructure reconstruction of

    Aceh and North Sumatra by providing high quality technical assistance and capacity

    building to BRR and MoPW. The project in effect enabled the implementation of the

    IRFF by financing the technical assistance needed to perform the project implementation

    management activities including procurement, financial management, quality control and

    quality assurance, safeguards framework assurance and monitoring, implementation

    monitoring and the design and construction supervision of all activities under the IRFF.

    All major consultancy firms required to manage the implementation of IRFF were

    appointed.

  • 16

    In general, and given the time constraints at the beginning, the project fulfilled its

    primary objective in terms of the quality of the technical assistance provided. All 56 sub-

    projects under IRFF, except for Siron Water Pipe Bridge and Siggli Water Intake, were

    subject to detailed engineering design reviews and adequate construction supervision. In

    some cases, designs were adjusted to take into consideration new findings in the field,

    especially with respect to soil characteristics to mitigate for land-slides where road

    shoulders are steep and/or the soil is unstable. The two failing sub-projects mentioned

    above (Siron Water Pipe Bridge and Siggli Water Intake) couldn’t be finished before the

    companion IRFF project closed. Thus, they have subsequently been reviewed and

    redesigned and reconstruction is now underway from the MoPW’s own budget. As a

    commitment guarantee, the involved PDCS liability was protected by renewing

    performance liability insurance to anticipate any shortfall that may be identified due to

    design fault or improper construction supervision.

    Support BRR in overall coordination of the infrastructure reconstruction program

    (Moderately Satisfactory):

    The project also supported BRR and MoPW in the overall coordination of the

    infrastructure reconstruction program through the IPM consultant. The IPM consultant

    provided solid support to BRR with regards to managing the work programs,

    performance and outputs of the three PDCS consultants and the FM consultant in charge

    of the implementation of four other components of IREP. It strengthened the coordination

    arrangements with the PDCS consultants, notably in terms of quality assurance and

    control, construction supervision, monthly certificates preparation and program revisions

    such as the gaps and actions on Bank Aide-memoires. IPM regularly monitored their

    performance and discussed findings with the PMU, prompting the issuance of jointly

    formulated action plans. IPM performance was also solid in terms of environmental and

    social safeguard compliance of all stakeholders, as IPM consultants had established a

    project tracking system that incorporates all safeguard aspects of projects.

    As discussed earlier, there were some shortcomings in the IPM consultants’ overall

    effectiveness, as the workload and number of deliverables under the original TORs were

    not matched by IPM capabilities and staffing. In particular, the performance of IPM was

    found lacking in terms of completing the MIS, and at an early implementation stage,

    quarterly and mid-term reporting, PIPs and quality assurance were lagging behind. The

    very high turnover of IPM leadership and expatriate staff also affected its coordination

    capacities and strained its working relationship with BRR, PMU and the four other

    consultants. In May 2008, the Bank recommended to BRR to reduce the scope of works

    of IPM in areas such as capacity building and planning, which further reduced the

    capacities of IPM. Ultimately, the IPM contract was cut by almost a third, and the

    completion date was moved from June 2010 to March 2010.

    3.3 Efficiency

  • 17

    The performance of BRR is worth noting as being efficient, especially against the

    backdrop of the very real constraints following the tsunami and earthquakes of 2004. In a

    short time, the BRR was able to lead the implementation of a US$6+ billion investment

    program including the 56 sub-project under IRFF.

    However, the midterm review noted that all in all, the project provided low value for

    money. While IPM was supposed to serve the overall infrastructure construction process

    (all GOI, BRR and other donor projects), the consultant worked almost exclusively on

    IRFF sub-projects. PDCS consultants also almost exclusively worked on IRFF sub-

    projects. As a consequence, the ratio of cost of the overall TA provided by IREP (US$42

    million) to the capital investment (US$200 -300 million) was relatively high.

    On the other hand, the ratio of the cost of the design and construction (i.e., only PDCS)

    on IRFF capital investment was around 11%, putting it within the Indonesian good

    practice range (8-12%).

    3.4 Justification of Overall Outcome Rating

    Rating: Moderately Satisfactory

    The project achieved its primary development objective of supporting the BRR's strategy

    for infrastructure reconstruction by providing technical assistance in order to ensure that

    infrastructure program management, planning, design and construction management

    follow adequate standards. IREP also managed to support the BRR/MoPW in the overall

    coordination of this large infrastructure program, and enabled the 56 IRFF sub-projects to

    come to fruition in a timely and adequate manner, for the benefit of the people of Aceh

    and Nias. However, as discussed earlier, monitoring (through the failed MIS

    implementation), and capacity building of the local authorities could have been improved.

    In summary, IREP achieved its development objectives, albeit with moderate

    shortcomings. It remains highly relevant to the country infrastructure and disaster

    mitigation priorities. During the implementation, quality assurance, financial

    management and post-completion operation and maintenance problems were identified

    and mitigated for the most part. As such, an overall rating of moderately satisfactory is

    justified.

    3.5 Overarching Themes, Other Outcomes and Impacts

    (a) Poverty Impacts, Gender Aspects, and Social Development

    IREP enabled the construction of 56 sub-projects including Ports, Roads, General Water

    Sanitation/Flood Protection and Water Supply. Although no socio-economic impact study

    was conducted, it seems that the project has positively impacted the livelihoods of Aceh

    and Nias through (i) the improvement of sea and land connectivity and mobility; (ii) the

    improvement of livelihoods for the local community and the stimulation of local

    economic growth (increasing the number of cargo boats and docks loading and unloading

  • 18

    consumer items, processed products and crops. In particular, cloves and crude palm oil

    have increased by more than 20%); (iii) the development of new economic growth

    contributors such as restaurants, shops, hotels and public services facilities (which all

    increased the districts’ disposable income); (iv) the improvement of Banda Aceh’s solid

    waste management through the construction of a sanitary landfill with recycling and

    composting capacity; and (v) the improved provision of clean water supply.

    (b) Institutional Change/Strengthening

    The project provided an intense on-the-job training to the PMUs, PIU and other staff of

    Bappenas, MoF, MoPW and the provincial and local governments staff in program

    design and implementation, engineering designs, construction supervision and financial

    management. The implementation arrangement initiated by BRR was adopted by MoPW

    after the closure of BRR. Moreover, MoPW maintained the PMU structure after IREP

    closed.

    (c) Other Unintended Outcomes and Impacts

    NA

    3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops

    NA

    4. Assessment of Risk to Development Outcome

    Rating: Moderate

    The IREP program has enabled proper design and construction of good quality

    infrastructure and has mitigated the risk of short life and/or failure of the assets. As

    mentioned earlier (see Section 2.5), the majority of large IRFF sub-projects are managed

    at the national and provincial levels, where capacity to maintain them is adequate.

    However, sub-projects which were transferred to the local authorities might very well be

    affected by poor asset management and maintenance. This significant risk is currently

    being addressed by central, provincial and local governments.

    5. Assessment of Bank and Borrower Performance

    5.1 Bank Performance

    (a) Bank Performance in Ensuring Quality at Entry

    Rating: Satisfactory

    The Bank Task Team ensured that IREP’s overall development objectives were closely

    aligned with both GoI and Bank strategies on infrastructure management and disaster

    mitigation. This alignment, combined with sound implementation arrangements,

  • 19

    facilitated timely completion without compromising environmental concerns or social

    safeguards. The program attracted the attention of the highest management level in the

    Bank including the close involvement of its regional Vice President for East Asia Pacific.

    The design ensured timely delivery of the majority of the project development objectives.

    The IREP was designed for carry out a disaster response program covering 12 districts in

    Aceh Province and Nias Island. The program was successful in supporting the 56 priority

    sub-projects previously identified throughout the design, procurement, supervision and

    implementation stages.

    Considering the time constraints during the IREP preparation stage, the IPM’s role

    (especially in terms of balancing the effectiveness and the wide geographic scope) was

    too ambitious. Some of the IPM functions, such as the project supervision of QA, were

    found to be overlapping with the PDCS role. As a result, BRR streamlined the IPM ToRs,

    limited such functions to the PDCS and requested the IPM to be more focused on

    implementation management activities until its contract ended.

    (b) Quality of Supervision

    Rating: Satisfactory

    Bank supervision is rated satisfactory. Task Team Leaders initially followed the project

    from Washington DC but were in continuous contact with infrastructure team members

    who were based in Banda Aceh. This turned out to be critical for such a large size post-

    disaster reconstruction program. Moreover, in late 2010, the TTL was re-located to

    Jakarta which further enhanced the quality of supervision. This supervision set up and the

    permanent presence of Bank staff in the reconstruction areas ensured continuous Bank

    oversight throughout project implementation. The Bank’s supervision strategy resulted

    in relatively high supervision costs which were financed from the MDF and which

    considered the success of the project a top priority.

    While implementation difficulties did occur, the pro-activeness of Bank supervision

    could be noted in a number of aspects, such as:

    Working with the PMU systematically to address weaknesses in reporting and in

    financial management.

    Increased attention to technical design, implementation quality and achievement of

    quality outcomes.

    Designing post-BRR institutional arrangements with MoPW, MoF and Bappenas.

    Moreover, the Bank’s policies and procedures were applied consistently. Supervision

    missions were conducted in a professional and constructive manner, and mission teams

    consistently included the experts needed to discuss relevant supervision topics and issues.

    The timing of formal supervision missions (on average twice a year and supplemented by

    frequent routine supervision missions by the TTLs and the task team members who were

    based in Banda Aceh) was appropriate and comments received from PMU and

    BRR/MoPW staff indicated a respectful working relationship and a flexible approach by

  • 20

    Bank staff. Aide Memoires, Management Letters, ISRs and other project

    communications and documents were completed in a timely manner with clear references

    to needed actions covering all aspects of project components, safeguards and fiduciary

    issues.

    (c) Justification of Rating for Overall Bank Performance

    Rating: Satisfactory

    The Bank's overall performance rating is based on satisfactory ratings for both quality at

    entry and supervision.

    5.2 Borrower Performance

    (a) Government Performance

    Rating: Satisfactory

    Performance of GoI was satisfactory, especially in terms of the strong and sustained

    commitment to the project development objective. The agencies (MoF, MoPW and

    Bappenas) turned out to be extremely cooperative and very effective in taking decisive

    action in a timely manner, in particular with regard to the Bank recommendations on

    implementation activities, including channeling the budget allocation (DIPA) and

    preparing sufficient yearly budget allocations.

    (b) Implementing Agency or Agencies Performance

    Rating: Satisfactory

    Performance of the implementing agencies was satisfactory. BRR and the MoPW

    protected the integrity of the project and sustained its development objective. As an

    independent agency, BRR performed effectively and was able to channel and manage a

    reconstruction effort valued more than US$6 billion in only 4 years. This fast pace was

    supported by the strong authority which BRR was granted which enabled it to avoid most

    of the bureaucracy faced by line ministries.

    The slowdown of the implementation was clearly noticed following the closure of BRR

    and the handover of the implementation to the MoPW where the PMU functioned more

    as a Program Management Unit and effective implementation was mostly managed by a

    number of PIUs which sometimes were difficult to coordinate. This setup required the

    Task Team to devote extra efforts to ensure compliance with Bank fiduciary and

    safeguards procedures and guidelines.

    (c) Justification of Rating for Overall Borrower Performance

    Rating: Satisfactory

  • 21

    Both GoI and the Implementing Agencies (BRR and MoPW) managed to implement the

    IREP with satisfactory performance.

    6. Lessons Learned

    Lessons were learned for both future operations in both Indonesia and future similar

    reconstruction TAs in other countries, particularly in the following areas: Contract

    Management and Flexibility; Social and Environmental safeguards management;

    Implementation Arrangements; Maintenance and Capacity building; Stakeholder

    Participation and Commitment; and Implementation Support Arrangements.

    a) Future operations in Indonesia

    Contract Management and Flexibility: BRR did not allow any sub-project to make any

    change that would have led to an increase of the signed contract price. Thus, and to

    account for any design changes, the only way was to reduce the scope of the works. This

    has led to some incomplete works. While this policy gave BRR a tighter control on the

    budget, it also adversely affected some sub-projects. Incomplete works were grouped

    under the “Gaps” packages and were tendered separately, which turned out to be more

    costly. Also, loading the consultancy contracts with reimbursable payments resulted in

    some fund misuse and false reporting on reimbursable expenses (as was the case in the

    IPM contract). To mitigate this, it would be best to design such contracts with very few or

    no reimbursable payments in the future. Alternatively, more rigorous FM monitoring

    would be required.

    Social and Environmental Safeguards management: the projects handled the design and

    implementation of 56 sub-projects of diverse types and in different locations and

    environment, leading to many safeguards issues. These were addressed through: (i) the

    allocation of provisional budgets to implement environmental management plans as part

    of the civil works contracts; (ii) staffing of all PDCS consultants with the relevant

    safeguards specialists; (iii) IPM QA and QC functions included the safeguards aspects

    (iv) close involvement and commitment of the implementing agency, provincial and local

    governments to implement LARAPs satisfactorily; and (v) close Task Team monitoring

    and follow up with Indonesian counterparts.

    b) Future similar reconstruction TAs in client countries

    Implementation arrangements: The establishment of BRR as the entity responsible for

    the implementation of the reconstruction program of Aceh undoubtedly boosted the

    construction pace. BRR was empowered to operate outside the daily bureaucratic

    constraints, a setting that made the mobilization of financial and human resources easier.

    Moreover, BRR was created with a limited lifetime to enable the line ministries, like the

    MoPW in this case, to pursue their roles seamlessly after the closure of the BRR. Also,

    BRR established its own Procurement Central Unit (PCU) to manage all procurement

    activities.

  • 22

    On the other hand, the daily implementation was fragmented between a large number of

    changing PIU/Satkers and thus many procurement committees. The PMU had no control

    over the implementation and was mandated with the program planning. This made it

    sometimes difficult for effective communication. Also, a large and comprehensive

    reconstruction program such as the one supported by IREP was bound to be fraught with

    continuous changes in engineering designs, issues with the flows of information and

    unforeseen events.

    More care will be needed in future operations in the design of roles and institutional

    coordination between the Bank, the PMU and the various contracted consultants.

    Implementation models for consultant management could be based on the review of best

    practices in terms of progress of delivery, financial viability, quality of delivery,

    environmental soundness and asset end-user satisfaction. Having IPM assisting the

    program management was not sufficient, especially where their ToRs overlapped with the

    mandate of the PDCSs like in the case of the quality assurance and quality control.

    Maintenance and Capacity building: In order to ensure the sustainability, as a medium-

    term development objective, of built assets, mechanisms to allocate sufficient funds or

    establish a maintenance fund should be effectively designed, especially in environments

    where decentralization efforts are lagging. Also, it seems that a regionalized large

    infrastructure program such as this one are best suited in an environment where the

    capacity of the local government is sound and devolution of authority is real.

    In the end, and understandably, the emphasis in this project was always on the

    completion of the large building programs under institutional, budgetary and time

    pressures rather than on the sustainability of these assets after handover. The project did

    not put enough emphasis in effective training in infrastructure management, operation

    and maintenance of local government staff, as was underscored by the reduction of

    funding devoted to these activities. Local governments, on the other hand, did not

    allocate funds to these training activities. Capacity building in infrastructure management

    can only be effective when based on a sound analysis of the incentives and capacity of

    the local government, to which assets are to be handed over. It is recommended that in

    the future, local governments will allow for funding of capacity building programs in

    their medium term development plans to acquire the proper skills in infrastructure

    management.

    Also, in some remote areas such as Nias, the working environment for outside contractors

    was challenging and made it less attractive for workers to stay. This led to the termination

    of some contracts and when local contracts were subcontracted, the quality of works was

    not always satisfactory. To mitigate this, it is thus recommended that capacity building in

    similar regional reconstruction projects include local contractors in the future.

    Stakeholder Participation and Commitment: The project is a successful example of

    stakeholder participation and commitment, which led for instance to the satisfactory

    design of the sub-projects priority list and the support of the various authorities to

  • 23

    facilitate and safeguard project implementation. Stakeholders included the central,

    provincial and local governments; local communities, NGOs, Donors, MDF and the Bank.

    Implementation Support Arrangements: Both the MDF and the Bank acknowledged the

    necessity to be closer to the project area, and the MDF supported the opening of a field

    office in Banda Aceh. This proximity to the center of activity greatly facilitated

    implementation on a day to day basis and provided continuous support to the client.

    7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners

    (a) Borrower/implementing agencies

    In general, the government of Indonesia was satisfied with the project’s outcomes. The

    original implementing agency (BRR) was closed in 2009. The borrower completion

    report and comments on the ICR were prepared by the Ministry of Public Works

    (MoPW), and were mostly related to contract management.

    BPK’s audit in 2010: The BPK (Government Auditor) criticized the PMU for awarding contracts which exceeded Engineer Estimates and for the allocation of

    environmental budget for some sub-projects under IRFF. The PMU requested a

    formal clarification from the Bank supporting their views. The Bank invited the BPK

    and clarified that this can happen under normal circumstances and this is why the

    Bank issued the no objection letters to the award of contracts. Nonetheless, BPK

    requested the PMU to re-bid these contracts but the Bank considered that this was not

    a sufficient basis for rebidding. Moreover, the Bank addressed a general letter to BPK

    explaining that the Bank, as a matter of general practice, only issued a no objection

    letter and that it was the implementing agency’s responsibility to approve and sign the

    contracts as a legal entity. The Bank had also made it clear that making provisional

    sums to implement environmental action plans was not against sound procurement

    principles and that it was up to the implement