world bank document · 2016. 7. 11. · multi-donor trust fund for aceh and nias mis monitoring...
TRANSCRIPT
-
Document of
The World Bank
Report No: ICR00002182
IMPLEMENTATION COMPLETION AND RESULTS REPORT
(TF-56894)
ON A
MULTI-DONOR TRUST FUND (MDF) FOR ACEH AND NIAS GRANT
IN THE AMOUNT OF US$42 MILLION
TO THE
REPUBLIC OF INDONESIA
THROUGH THE
AGENCY FOR RECONSTRUCTION AND REHABILITATION FOR ACEH AND
NIAS
FOR THE
INFRASTRUCTURE RECONSTRUCTION ENABLING PROGRAM
June 20, 2012
Indonesia Sustainable Development Unit (EASIS)
Sustainable Development Department
East Asia and Pacific Region
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
-
CURRENCY EQUIVALENTS
(Exchange Rate Effective June 15, 2012)
Currency Unit = Indonesian Rupiah
IDR 1,000 = US$0.107
US$1 = IDR 9,385
FISCAL YEAR
January 1 – December 31
ABBREVIATIONS AND ACRONYMS
BRR Bureau for Rehabilitation and Reconstruction for Aceh and Nias
EIA Environment Impact Assessment
FM Financial Management
FMR Financial Management Report
GOI Government of Indonesia
IBRD International Bank for Reconstruction and Development
ICB International Competitive Bidding
IDA
IFR
International Development Association
Interim Financial Report
IPM Infrastructure Program Management
IREP Infrastructure Reconstruction Enabling Program
LARAP Land Acquisition and Resettlement Action Plan
MDF Multi-Donor Trust Fund for Aceh and North Sumatra later simplified to
Multi-Donor Trust Fund for Aceh and Nias
MIS Monitoring Information System
MOF
MoPW
Ministry of Finance
Ministry of Public Works
MOU Memorandum of Understanding
NCB National Competitive Bidding
NGO Non-Governmental Organization
O&M Operations and Maintenance
PIU
PDCS
Project Implementation Unit
Planning, Design and Construction Supervision
PMU Project Management Unit
TA Technical Assistance
Vice President: Pamela Cox
Country Director: Stefan G. Koeberle
Sector Manager: Franz R. Dress-Gross
Task Team Leader: Khairy Al-Jamal
ICR Team Leader: Khairy Al-Jamal
ICR Primary Author: Reda Hamedoun
-
Republic of Indonesia
Infrastructure Reconstruction Enabling Program
CONTENTS
Data Sheet
A. Basic Information ............................................................................................. i B. Key Dates ......................................................................................................... i C. Ratings Summary ............................................................................................. i
D. Sector and Theme Codes ................................................................................. ii E. Bank Staff ........................................................................................................ ii
F. Results Framework Analysis .......................................................................... iii G. Ratings of Project Performance in ISRs ..........................................................v
H. Restructuring (if any) ..................................................................................... vi I. Disbursement Profile ....................................................................................... vi
1. Project Context, Development Objectives and Design ..............................................1 2. Key Factors Affecting Implementation and Outcomes .............................................6 3. Assessment of Outcomes .........................................................................................15
4. Assessment of Risk to Development Outcome ........................................................18 5. Assessment of Bank and Borrower Performance ....................................................18
6. Lessons Learned.......................................................................................................21
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners..........23
Annex 1. Project Costs and Financing .........................................................................25 Annex 2. Outputs by Component.................................................................................26
Annex 3. Economic and Financial Analysis ................................................................29 Annex 4. Grant Preparation and Implementation Support/Supervision Processes ......30 Annex 5. Beneficiary Survey Results ..........................................................................33 Annex 6. Stakeholder Workshop Report and Results ..................................................34 Annex 7. Summary of Borrower's ICR and/or Comments on Draft ICR ....................35 Annex 8. Comments of Cofinanciers and Other Partners/Stakeholders ......................38 Annex 9. List of Supporting Documents .....................................................................41 MAP .............................................................................................................................42
-
A. Basic Information
Country: Indonesia Project Name:
ID-Aceh-Infrastructure
Reconstruction
Enabling Program
(IREP)
Project ID: P100218 L/C/TF Number(s): TF-056894
ICR Date: ICR Type: Core ICR
Lending Instrument: ERL Borrower: REPUBLIC OF
INDONESIA
Original Total
Commitment: US$42.00M Disbursed Amount: US$35.655M
Revised Amount : US$42.00M
Environmental Category: B
Implementing Agencies:
Bureau for Rehabilitation and Reconstruction for Aceh and Nias (BRR); and
Ministry of Public Works (MoPW)
Cofinanciers and Other External Partners:
Multi-Donor Trust Fund (MDTF)
B. Key Dates
Process Date Process Original Date Revised / Actual
Date(s)
Concept Review: 02/17/2006 Effectiveness: 09/13/2006
Appraisal: 03/27/2006 Restructuring(s):
01/07/2008
01/10/20091
04/15/2009
06/30/20102
Approval: 06/30/2006 Mid-term Review: 09/30/2008 12/19/2008
Closing: 10/31/2009 12/31/2011
1. Shifting costs between components and reviewing the scope of the IPM and PDCSs
through operational Bank clearance without formal amendment.
2. The date in the project portal was misquoted as June 28, 2010.
C. Ratings Summary
C.1 Performance Rating by ICR
Outcomes: Moderately Satisfactory
Risk to Development Outcome: Moderate
Bank Performance: Satisfactory
Borrower Performance: Satisfactory
-
ii
C.2 Detailed Ratings of Bank and Borrower Performance (by ICR)
Bank Ratings Borrower Ratings
Quality at Entry: Satisfactory Government: Satisfactory
Quality of Supervision: Satisfactory Implementing
Agency/Agencies: Satisfactory
Overall Bank
Performance: Satisfactory
Overall Borrower
Performance: Satisfactory
C.3 Quality at Entry and Implementation Performance Indicators
Implementation
Performance Indicators
QAG Assessments
(if any) Rating
Potential Problem Project
at any time (Yes/No): Yes
Quality at Entry
(QEA): None
Problem Project at any
time (Yes/No): No
Quality of
Supervision (QSA): None
DO rating before
Closing/Inactive status:
Moderately
Satisfactory
D. Sector and Theme Codes
Original Actual
Sector Code (as % of total Bank financing)
General water, sanitation and flood protection sector 25 9
Ports, waterway and shipping 25 18
Roads and highways 25 67
Water supply 25 6
Theme Code (as % of total Bank financing)
Other urban development 100 100
E. Bank Staff
Positions At ICR At Approval
Vice President: Pamela Cox Jeffrey Gutman (acting)
Country Director: Stefan G. Koeberle Andrew D. Steer
Sector Manager: Franz R. Drees-Gross Keshav Varma
Project Team Leader: Khairy Al-Jamal Aniruddha Dasgupta
ICR Team Leader: Khairy Al-Jamal
ICR Primary Author: Reda Hamedoun
-
iii
F. Results Framework Analysis
Project Development Objectives (from Project Appraisal Document)
Support the BRR's strategy for infrastructure reconstruction by providing high quality
technical assistance (TA) in order to ensure that infrastructure program management,
planning, design and construction management follow adequate standards, and to support
BRR in overall coordination of the infrastructure reconstruction program.
Revised Project Development Objectives (as approved by original approving authority)
The development objectives and key indicators were not revised.
(a) PDO Key Performance Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised Target
Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1 : Post Tsunami infrastructure reconstruction and development Monitoring
Framework for Aceh and Nias
Value
quantitative or
Qualitative)
N/A
Framework
developed and
applied
N/A Framework was
complete and applied
Date achieved 09/01/2006 12/31/2011 12/31/2011 12/17/2010
Comments
(incl. %
achievement)
Achieved
Indicator 2 : A strategic plan for infrastructure reconstruction in Aceh and Nias exists
Value
quantitative or
Qualitative)
N/A Plan to be prepared
and utilized N/A
Plan exists and has
been utilized
throughout the
project.
Date achieved 09/01/2006 12/31/2011 12/31/2011 12/31/2011
Comments
(incl. %
achievement)
Achieved
Indicator 3 : Donors and stakeholders are consulted on the plan and design of projects
that support implementation of the strategic reconstruction plan
Value
quantitative or
Qualitative)
N/A
Donors are
continually updated
on implementation of
the strategic
reconstruction plan.
N/A
Donors are fully
informed on program
and project activities,
now totaling
US$ 207 million of
infrastructure from
the strategic plan and
additional financing
of US$ 36.7 million
Date achieved 09/01/2006 12/31/2011 12/31/2011 12/17/2010
Comments Achieved
-
iv
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised Target
Values
Actual Value
Achieved at
Completion or
Target Years
(incl. %
achievement)
Indicator 4 : Proper safeguard measures are integrated into project preparation plan
Value
quantitative or
Qualitative)
Safeguard
framework is
established.
All IRFF supported
sub-projects will
adhere to the
safeguard framework.
N/A
IPM consultants
established a project
tracking system that
incorporated all
safeguard aspects of
projects. All
subprojects
supported by IRFF
adhered to the
framework.
Date achieved 09/01/2006 12/31/2011 12/31/2011 12/31/2011
Comments
(incl. %
achievement)
Achieved
Indicator 5 : Projects funded by BRR through IRFF are matched to articulate demands
of local governments.
Value
quantitative or
Qualitative)
None
Initial and updated
investments are
discussed and agreed
on with local
government and other
stakeholders. All
O&M MOUs to be
signed with local
government.
N/A
All IRFF investments
were included in the
annual investment
plans, and identified
as a priority by local
government. All
MOUs for O&M and
asset transfer were
signed for local
government project.
Date achieved 09/01/2006 12/31/2011 12/31/2011 12/17/2010
Comments
(incl. %
achievement)
Achieved
Indicator 6 : Works meet the specifications of the technical designs.
Value
quantitative or
Qualitative)
N/A
All works comply
with the design
specifications.
N/A
In general, quality of
works is good and in
compliance with the
design specifications.
Date achieved 09/01/2006 12/31/2011 12/31/2011 12/31/2011
Comments
(incl. %
achievement)
95% Achieved as two subprojects were not completed and required design
reviews.
Indicator 7 : Projects are of higher quality standards than those prepared and
implemented prior to the TA.
-
v
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised Target
Values
Actual Value
Achieved at
Completion or
Target Years
Value
quantitative or
Qualitative)
N/A
All sub-projects
under the TA will be
of higher standards
N/A
In general sub-
projects prepared
under the IREP were
of higher quality and
bids were subject to
minor variations and
designs were more
detailed.
Date achieved 09/01/2006 12/31/2011 12/31/2011 12/31/2011
Comments
(incl. %
achievement)
Achieved
(b) Intermediate Outcome Indicator(s)
Indicator Baseline Value
Original Target
Values (from
approval
documents)
Formally
Revised
Target Values
Actual Value
Achieved at
Completion or
Target Years
Indicator 1 : All Consultants are appointed and functioning.
Value
quantitative or
Qualitative)
No consultant is
selected
All consultants
including IPM,
PDCSs and FM are
selected.
N/A
All consultants
including IPM,
PDCSs and FM
were selected and
functional
Date achieved 09/01/2006 03/31/2007 03/31/2007 03/31/2007
Comments
(incl. %
achievement)
Achieved
G. Ratings of Project Performance in ISRs
No. Date ISR
Archived
Development
Objective
DO
Implementation
Performance
IP
Actual Disbursements
(US$ millions)
01 03/20/2007 Moderately
Satisfactory
Moderately
Satisfactory
0.00
02 01/04/2008 Moderately
Satisfactory
Moderately
Satisfactory
7.28
03 06/30/2009 Moderately
Satisfactory
Moderately
Satisfactory
17.80
04 06/30/2010 Moderately
Satisfactory
Moderately
Satisfactory
28.13
-
vi
05 03/29/2011 Moderately
Satisfactory
Moderately
Satisfactory
33.99
06 12/25/2011 Moderately
Satisfactory
Moderately
Satisfactory
34.89
H. Restructuring (if any)
Restructuring
Date
Board
Approved
PDO change
ISR Rating at
Restructuring
DO IP
Amount Disbursed
at Restructuring in
US$ Millions
Reason for
Restructuring &
Key Changes
Made
01/07/2008 MS MS 7.28 Review the scope of
the impacted area.
01/10/2009 MS MS 16.28 Review the scope of
IPM and the PDCSs
and shifting costs
between
components.
04/15/2009 MS MS 17.8 Restatement of GA,
MoPW became the
implementing
Agency after
closure of BRR and
extension of
Closing Date to
June 30, 2010.
06/30/2010 MS MS 28.13 Extension of the
closing date to
12/31/2011.
I. Disbursement Profile
-
vii
-
1
1. Project Context, Development Objectives and Design
1.1 Context at Appraisal
Country and sector context
The tsunami of December 26, 2004 killed or left missing more than 230,000 people in
Indonesia, and the total reconstruction and development program for Aceh and Nias was
estimated to cost up to US$9 billion through 2009. The estimate of the damage to the
housing sector alone was US$ 1.4 billion, with the demand for new housing ranging from
93,000 to 120,000 units. The government of Indonesia (GoI) created a dedicated
Rehabilitation and Reconstruction Agency– Badan Rehabilitasi dan Rekonstruksi (BRR)
- to lead the recovery efforts. The BRR’s priorities were to (i) strengthen coordination
between donors and government agencies; (ii) ensure pledges for infrastructure are
prioritized and matched with sector needs; (iii) improve the quality and pace of
infrastructure reconstruction supporting housing/settlements; (iv) develop institutional
resources for sustainable infrastructure operations and services after the BRR’s operating
period; (v) improve cost effectiveness through quality management and competitive
procurement; and (vi) and increase the efficiency and flexibility of the capital works
planning and budgeting process.
Rationale for Bank Assistance
As a leading international development agency in the area of post-disaster reconstruction,
with a longstanding engagement with relevant government agencies in Indonesia and
around the world, the Bank was well-position to support BRR in its reconstruction
efforts. In addition, the Bank’s involvement in Indonesia’s community-driven
development program also provided a platform to quickly replicate stakeholder
consultation and participation mechanisms and to scale up financing to specifically
address reconstruction needs. GoI had also asked the Bank to take a lead in coordinating
the donor community, requesting suggestions on how this could be handled in practice. In
March 2005, the Bank formally established the "Multi-donor Trust Fund for Aceh and
North Sumatra" (MDTFANS), later simplified to "Multi Donor Fund for Aceh and Nias
(MDF)". The Bank also provided at the same time a grant of US$25 million as a
contribution to the MDF. In all, 15 funding agencies contributed an initial US$550
million to the MDF. The Bank and the European commission channeled all their support
through the MDF, while the Nordic countries, the Netherlands and Belgium provided half
or more of their funding through the MDF.
Project Background and development
It was noted that most of the funds pledged to support rehabilitation and reconstruction in
Aceh were quickly programmed by the GoI, leaving mostly gaps to finance minimum
needs in certain critical areas. BRR’s strategy, therefore, was to focus on the remaining
-
2
available funds to ensure that they were allocated to cover these gaps. Of the donor
resources, the MDF was the largest source of programmable funds with US$230 million
still available to be programmed at the time IREP was approved. Among other priorities,
BRR’s medium-term strategy called for the main utilization of the remaining MDF
resources for the reconstruction and development (i.e., building back better) of
infrastructure in the areas most damaged by the tsunami and earthquake in Nias and
Aceh.
In order to guide the investment program during BRR’s assignment period, BRR
developed an Infrastructure Reconstruction Strategy. This strategy encompassed three
phases: (i) the execution of the ongoing MDF-supported Immediate Action Plan (IAP)
agreed upon in November 2005 to meet urgent infrastructure needs; (ii) the proposed
Infrastructure Reconstruction Enabling Program (IREP), which would provide technical
assistance for the mobilization of human resources and technical support to BRR,
provincial, and local governments; and (iii) investment in infrastructure works by BRR
and other donors, including through a proposed Aceh Infrastructure Reconstruction
Facility (IRFF). The implementation of IRFF would be financed through the MDF and
the GoI and the technical support would be managed under IREP.
IREP was designed to work within the prevailing infrastructure framework and strategies
of GoI, and with numerous agencies and donors involved in the reconstruction effort in
Aceh and Nias. In conjunction with IREP, local and provincial governments were
expected to build project management capacity; prepare infrastructure development
plans, feasibility studies, detailed designs, comprehensive procurement planning; and
provide support during construction supervision.
1.2 Original Project Development Objectives (PDO) and Key Indicators (as
approved)
The development objective of the project was to support BRR's strategy for infrastructure
reconstruction by providing high quality technical assistance in order to ensure that
infrastructure program management, planning, design and construction management
follow adequate standards, and to support BRR in overall coordination of the
infrastructure reconstruction program.
The Key Performance Indicators for this development objective at appraisal were:
1. Development of a sustainable and strategic long-term infrastructure reconstruction plan for Aceh and Nias;
2. Donors and other stakeholders are consulted on the infrastructure reconstruction plan and design projects that support implementation of the strategy;
3. Technical designs created during project appraisal ensure appropriate quality measures have been included;
4. Consultant teams and local and provincial governments prepare projects that incorporate adequate procurement and financial management practices and safeguards
measures;
-
3
5. The scale of funding committed to implement projects submitted by local and provincial governments to BRR as part of their AIPs;
6. Projects are of higher quality standards than those prepared and implemented prior to the TA;
7. Increased participation of local and provincial government staff to incorporate appropriate safeguards measures and financial management and procurement
practices during project design and implementation.
In principle, the PDO and the performance indicators are consistent in the project
documents with very minor discrepancies between the PAD and the Legal Agreement.
1.3 Revised PDO (as approved by original approving authority) and Key Indicators,
and reasons/justification
The development objectives and key indicators were not revised.
1.4 Main Beneficiaries
In a narrow sense, the direct beneficiaries were the BRR, Ministry of Public Works
(MoPW), project management unit (PMU), project implementation unit (PIU), and local
consultants who saw their capacity in infrastructure management, design, monitoring and
construction supervision improve. However, the true beneficiaries in a broader sense
were the people of Aceh and Nias (around 1.6 million inhabitants), who benefitted from
the strengthened capacity of these entities to plan and implement infrastructure
reconstruction projects in the disaster affected area.
IREP was strategically integrated with the Infrastructure Reconstruction Financing
Facility (IRFF), another project executed with the Bank acting as Partner Agency on
behalf the MDF. To a large extent, IRFF focused on financing the infrastructure sub-
projects prepared with technical assistance from IREP. IREP worked with 12 local
governments: 7 local governments in the West Coast Logistical Area, 2 in Nias, the
remaining 3 local governments being Aceh Besar, Banda Aceh and Sabang. At the
provincial level, IRFF included strategic projects, prepared by the provincial government
with IREP support. Some of these projects were located outside the jurisdiction of the 12
local governments to cover the East Coast and central parts of Aceh but this was
consistent with amendment no. 1 to the Grant agreement.
1.5 Original Components (as approved)
The US$42 million program consisted of five consultancy TA components to be
implemented over a three-year period:
Component 1 - Infrastructure Program Management (US$19.5 million) to support the mobilization of a highly skilled Infrastructure Program Management (IPM) team
deployed within the existing BRR structure to coordinate the infrastructure program
and its activities at the macro level. These experts were mobilized to provide
assistance to BRR in eight specific areas: (i) overall strategic infrastructure planning
for Aceh and Nias, as per the BRR Infrastructure Reconstruction Strategy; (ii)
-
4
management of the infrastructure reconstruction program in Aceh and Nias; (iii)
review of local and provincial governments’ plans for infrastructure investment as a
basis for BRR funding; (iv) quality control, supervision, and monitoring o f BRR-
funded infrastructure projects; (v) procurement support; (vi) safeguard support for
BRR-funded infrastructure projects; (vii) anti-corruption support for BRR-funded
infrastructure projects; and (viii) management and coordination of other IREP
consultant teams. At all times, Consultants in Components 2, 3, 4, and 5 reported
directly to BRR, not the IPM Consultants. The first two tasks of this component
referred to the entire infrastructure reconstruction program throughout Aceh and Nias,
as these areas encompassed the work of both the government and other development
partners. The remaining six activities focused on BRR funded activities.
Component 2 - West Coast Infrastructure Planning, Design, and Construction Supervision (US$l0 million) to finance a technical team to undertake the planning,
project preparation, and implementation work for the West Coast Logistical Area.
This team provided assistance to the local governments in three main areas: (i)
strategic planning; and (ii) project design and implementation; and (iii) institutional
development support, including the development of a long term maintenance strategy,
and training. The assignment led to the mobilization of a project team with skills in
infrastructure planning and program management, institutional development,
implementation methods of essential services delivery, technical design and
procurement, construction planning and management, and construction supervision.
As planned, all works were conducted in close collaboration with local governments
and public works and in consultation with local communities.
Component 3 - Nias Infrastructure Planning, Design, and Construction Supervision (US$5 million) to support mobilization of a technical team to undertake the planning,
project preparation, and implementation work for the Nias logistical area. As planned,
the work focused on repairing the transport network. The consultant team provided
assistance to the local governments involved in three main areas: (i) strategic
planning; (ii) project design and implementation; and (iii) institutional development
support and training. All works were conducted in close collaboration with local
governments and public works and in consultation with local communities.
Component 4 - Strategic Infrastructure Project Planning, Design, and Construction Supervision (US$6 million) to finance a technical consulting team to undertake the
formulation, investment planning, design, and project implementation work for
strategic infrastructure projects at the provincial and or national level, or with local
governments not covered by components 2 and 3. This component was designed to
strengthen the ability of BRR and that of the relevant governments to carry out
project identification, appraisal, and implementation. The Provincial Government
participated in the selection and development of the “strategic projects” and
participated in management of the TA consultants. The infrastructure projects
financed under this TA were mainly related to ports, and key roads managed by
provincial, national or local government entities.
-
5
Component 5 - Financial Management of BRR-financed Projects (US$1.5 million) to
strengthen BRR’s capacity to put in place the financial management framework
required to ensure that it meets all its fiduciary responsibilities with respect to this TA
and other BRR investment projects. This assistance was provided by a team of
experts that, initially, was located within BRR and later worked side by side with the
PMU at the MoPW. Financial management of BRR-financed projects included PMU
and PIUs to establish and maintain financial accounting and statement arrangements
for project activities undertaken and expenditures incurred at all project locations,
including monitoring the operation of internal controls over implementation of the
contracts.
1.6 Revised Components
None.
1.7 Other Significant Changes:
Amendment No.1, “Review of the Project Area”, January 7, 2008: This amendment effected the change in the project service area and introduced the “West Coast
Logistical Area" which covers the West Coast Kabupatens of Aceh Jaya, Aceh Barat,
Nagan Rava, Aceh Barat Daya, Aceh Selatan, Aceh Singkil, Simeulue, Aceh Basear,
Banda Aceh and Sabang, and such additional Kabupatens as may be agreed by the
Association in writing. The original Legal Agreement referred only to Aceh Jaya,
Aceh Barat, Nagan Raya, Aceh Barat Daya, Aceh Selatan, Aceh Singkil and
Simeulue.
Amendment No. 2 “Grant Agreement Amendment and Restatement”, April 15, 2009: BRR closed on April 16, 2009, and the implementation of the project was entrusted to
the national Ministry of Public Works (MoPW). The institutional and legal transition
to MoPW was carried out smoothly. Thus, the implementing agency for IREP (and
IRFF) became the MoPW. The new PMU was tasked to handle the remaining
construction works in Aceh and Nias, and was staffed with many former BRR
officials for a seamless continuation of the project implementation. The IREP grant
agreement was amended to reflect the new arrangements and to extend the closing
date to June 30, 2010 in order to match the closing date of IRFF, at that time.
Amendment No. 3 “Extension of closing date”, June 30, 2010: the Regional Vice President approved a second closing date extension, which brought the cumulative
extension to 26 months.
Shifting costs between components, January 10, 2009: As detailed in Annex 1, the actual costs by component changed substantially from those estimated at appraisal.
The main change was to reduce the resources dedicated to Components 1 and 2, and
increase financing for Component 4. This was done to accommodate changing needs
and priorities, to take advantage of opportunities to increase project effectiveness and
efficiency, to make the best use of project resources and to balance the
-
6
implementation schedules of components 2, 3 and 4. The changes were requested by
the government, agreed by the Bank, and did not require amendments of the grant
agreement.
2. Key Factors Affecting Implementation and Outcomes
2.1 Project Preparation, Design and Quality at Entry
Institutional design: Four months after the devastating tsunami and earthquake, the GoI
established the BRR to manage the reconstruction program of Aceh with an estimated
budget of $6-9 billion. According to the end of first year assessment (December 2005),
the first reconstruction priority was the provision of housing (which was well underway
and progressing adequately). However, as the second reconstruction priority (rebuilding
and restoring essential infrastructure) made very little progress, BRR recognized the need
to apply better spatial planning to handle the reconstruction program. Accordingly, Aceh
and Nias were divided into five areas (North Coast, West Coast, Nias, East Coast and
Middle Aceh). BRR recognized the complexity of the scope and diversity of the skills
needed to implement the reconstruction program and the need to centralize the program
management under a limited number of relatively large consultancy services. The
thinking was to expedite the reconstruction process and to ensure adequate design and
construction quality, which led to the design of the project under its five components, as
described above. Based on its long experience and technical resources to respond to
emergency situations, the World Bank was requested to prepare IREP.
Lessons learned from similar operations: In order to optimize the design of IREP, BRR
incorporated lessons learned from its first year of operation. This included: (i) the need
for supplemental capacity in the BRR to implement and supervise infrastructure projects;
(ii) the imperative that local and provincial governments identify their priorities within a
framework of good practice; (iii) coordination across development partner and
government reconstruction programs; (iv) the allocation of sufficient resources for close
supervision of works to ensure quality construction; and (v) the importance of engaging
communities and other stakeholders throughout the project cycle.
BRR developed a Blueprint for projects before Component 1 was in place, due to the
time pressures of the reconstruction agenda and BRR’s own short life term. BRR
anticipated that this list would need to be revised at some stage and that the designs
would need to be updated. The scope of services of the PDCS consultants accounted for
such a need and all construction works under IRFF were subject to design review prior to
their tendering. Moreover, the priority list was adjusted to reflect the changing demands
from the local authorities and to account for socio-economic and political factors
(especially along the East Coast and Middle Aceh).
Design of the implementation arrangements: During the project's preparatory stage,
within the overall time constraints, the implementation arrangements were detailed and
set up satisfactorily (including necessary fiduciary requirements related to procurement,
-
7
disbursement and financial management). This was instrumental in the satisfactory
implementation of the project. By preparing the project in six months, the preparation
team also distinguished itself in terms of responsiveness, a crucial attribute in the
development of emergency operations. BRR had established the PMU, led by senior BRR
staff, to oversee project implementation and to interface with all consultants and donors
with the support from the IPM.
Assessment of risks: The financial management and procurement risks were rated as
substantial and high respectively, due to the limited capacity of BRR. However, the
project design addressed these risks adequately through: (i) the hiring of the FM
consultant as described in component 5 of the project; (ii) the hiring of a Procurement
Advisory (PA) team financed by DFID; (iii) the activation of internal FM controls; (iv)
application of BRR and MoPW internal audits; and (v) the hiring of the services of
external audits.
All in all, the project responded to GoI’s reconstruction priorities to produce a simple
design that avoided implementation difficulties. However, in hindsight, several areas
were identified where project preparation could have been improved:
Sub-project identification: The process of ex-ante definition of the portfolio seemed consistent at the time with the short timeframe available. However, this method made
it inevitable that some important projects would be missed, for some feasibility
studies to be insufficient at the outset (in water supply or ports) or for some projects
to be included for political reasons rather than reconstruction realities. Bank
supervision missions noted that there was pressure from BRR to approve incomplete
and preliminary designs.
Capacity Building: IREP design aimed at achieving both short-term reconstruction objectives and longer-term objectives of enabling and capacity building of local
governments. Though an emphasis on capacity building was rightly identified during
project preparation as crucial to ensure the sustainability and maintenance of the
assets produced by the program, the lack of resources devoted to it made its
achievement unrealistic. With a large reconstruction program to deliver in a tight time
frame and an under-sourced capacity building component, planning, procurement and
contract management could not always be conducted in a satisfactory manner.
Institutional design: IREP designed a one-door communication system, in which any communication between the consultants and the Bank, as well as coordination with
related central government level agencies would be carried out through the PMU. A
good concept in principle, this communication system turned out to be burdensome
for all parties involved. For an understaffed PMU, it meant an increased workload
while it had to manage a large infrastructure program. For the consultants, it resulted
in incomplete information sharing and time delays in receiving guidance and
instructions, as the flow of information with the gatekeeper (the PMU) became
increasingly imperfect. This situation was even clearer when the BRR was closed and
the MoPW became the implementing agency. For the Bank, it meant putting in place
-
8
a track for information gathering and monitoring that was independent from the PMU
in some instances, which led to an unnecessary increase in the workload for
consultants and the Bank task team.
Role of Infrastructure Program Management (IPM) Team: The IPM was designed to assume the responsibilities of a “super-consultant” and trusted advisor to the BRR,
which recognized during project preparation that it lacked the adequate capacities in
terms of strategic planning and program management. However, this role proved to
be too broadly designed and overly ambitious as it tasked the consultant to provide
assistance in eight different areas (strategic infrastructure planning, management of
infrastructure, review of local and provincial government plans, quality control,
procurement, safeguards, anti-corruption efforts, and management and coordination
of the four other IREP consultant teams).
2.2 Implementation
Scope, timing, and effectiveness of IPM consultancy. In mid-2008, it was decided that IPM should limit its focus to areas of core implementation, including program
management and quality assurance, and reduce its engagement in capacity building.
IPM had been delivering work outside of its original TORs in response to the client’s
requests, while at the same time having delays in the submission of key deliverables.
After consultation with the Bank, the BRR decided to refocus IPM resources to
optimize delivery of IRFF sub-projects and to save costs.
The IPM consultant was mobilized late, after BRR had started its planning. This
undermined the ability of IPM to influence strategic planning at the early stage and
did not help to properly position IPM to be in the driver’s seat in terms of leading the
reconstruction planning process. Moreover, the improper use of funds by the IPM
consultant as proven in 2010 led to a lack of trust between the consultant and BRR
and later MoPW. Accordingly, MoPW decided not to extend the contract of the IPM
consultant beyond its amended end date in March 2010.
Flexibility in allocating resources between contracts. In the course of implementation, the five consultancy contracts financed under IREP were amended to
reflect evolving priorities, adequately balance the allocation of resources among
consultants, and adapt to the closure of BRR. Due to the dynamics of the
reconstruction program, this proactive flexibility on the part of BRR and MoPW was
pivotal in facilitating the mobilization of adequately staffed international consultants
to ensure proper designs and good construction quality. This was particularly true for
the Planning, Design, and Construction Supervision (PDCS) activities. BRR regularly
reassessed whether the PDCS consultants had the right resources in place, and
contracts were amended to reflect these assessments.
Restructuring: As explained in more detail in Section 1.6, the project was restructured three times to clarify the geographic scope of the project, formalize the transition to a
-
9
new implementing agency, and extend the closing date twice. The restructurings were
fairly routine in nature, but helped ensure proper targeting, smooth implementation,
and alignment of IREP with IRFF (and in particular with the additional financing and
extension of IRFF).
2.3 Monitoring and Evaluation (M&E) Design, Implementation and Utilization
M&E Design: The project design included well-conceived, appropriate outcome
indicators that were clearly linked to the development objectives, verifiable either
quantitatively or qualitatively, and attributable to project interventions. There were some
minor discrepancies between one section of the PAD and another, but the substance was
the same, and the intent was clear. Due to the importance of the M&E in both guiding
project implementation and assessing outcomes, and the shortcomings in the capacity of
BRR, the design called for the IPM to provide support in carrying out the M&E functions.
The design called for the development of a computerized Monitoring Information System
(MIS) which was expected to facilitate the monitoring of outcome indicators and routine
project implementation and financial management for both IREP and IRFF.
M&E Implementation: The IPM successfully produced regular M&E reports, which were
integral parts of the Semi Annual Reports that compiled data provided by the PDCS and
FM consultant (and confirmed by IPM quality assurance staff). In addition, the PMU
developed a Monthly Portfolio Review for a quick monitoring of the progress of all sub-
projects under IRFF and updated the performance indicator matrices for both IREP and
IRFF.
The efforts of IPM to develop a stand-alone computerized MIS were not fully successful
and the system was never used as the focal database for the program. Development of the
system took longer than expected, and ultimately the BRR developed its own MIS system
which made a separate system specifically for IREP redundant and unnecessary. While
the MIS was intended to monitor both physical progress and financial performance, the
shortcomings and delays in the MIS system did not significantly hinder monitoring of the
KPIs, many of which were qualitative in nature.
M&E Utilization: The data and information gathered from the field were compiled by the
IPM consultant and communicated to the PDCS consultants to review the designs of
some sub-projects. This is clear in some roads projects where the soil turned to be
unstable and the need to strengthen the road shoulders was eminent in order to mitigate
the impact of potential landslides. Moreover, in order to maximize the returns from
BRR’s MIS, it had been centrally connected to Bappenas’ MIS which enabled sharing the
project information at the central level.
2.4 Safeguard and Fiduciary Compliance
Procurement
-
10
All major procurement, such as the selection of the design review and construction
supervision consultants, FM consultant, and program management consultant was
performed in a timely fashion and was generally satisfactory over the course of the
project. BRR was assisted by the Procurement Advisor (PA), financed by DFID, to
prepare all of the early procurement packages. Only the delay in the appointment of
individual consultants for program management and supervision of the sub-projects
carried out under the relatively minor gaps of IRFF was moderately unsatisfactory.
IREP also provided support to BRR and the MoPW to set up adequate procurement
procedures for the procurement of the 56 contract packages (signed value of US$223.62
million) carried out under IRFF and followed by four contract packages (signed value of
US$31.51 million) under IRFF Additional Financing. In particular, IPM was tasked to:
Provide direct support to BRR and local government procurement activities during the first 1.5 to 2 years.
Identify and agree with BRR alternate and appropriate procurement procedures and regulations for each set of investments.
Assist the preparation of tender documents for international and national procurement on BRR, National or World Bank Guidelines.
Provide guidance on procurement, contract packaging and bid documentation to other agencies.
Recommend the contract packaging and detailed strategy of the works for BRR.
To this end, IPM provided comprehensive support throughout the procurement process
and proceeded to the establishment of a Central Procurement Unit (CPU) within BRR.
The Bid Documents were standardized for National Competitive Bidding (NCB),
applying to works costing up to US$5.0 million, International competitive Bidding for
large civil works (ICB large works) costing above US$10.0 million. The procurement
manual was prepared detailing the procurement implementation steps and decision- tree
for the procurement committees and CPU. The standard operating procedures were
designed. The packaging of works, identification of appropriate document procedures and
regulations for the identified sub-projects were developed. IREP, through IPM, also
provided advice to the CPU on the finalization of the procurement plans.
In addition to this, the IPM advised the procurement committees on bid evaluation,
advised the CPU on procurement decisions, investigated complaints, reviewed the bid
evaluation reports, addressed comments from the Bank, prepared winner notifications,
letters of acceptance and draft contracts, revised (after the Bank supervision mission of
September 2009) the General Conditions of Contract Clause 38 for both NCB and ICB
contracts to provide an allowance for physical contingencies or provisional sums for
unforeseen items, and prepared the procurement completion report of the 56 IRFF
contract packages.
As a result, the IRFF procurement phase was completed in 18 months with an average
time for procurement from advertising to contract signing of 150 days for NCB and 210
-
11
days for ICB. The Bank supervision mission of December 2008 noted that procurement
process was being carried out efficiently and in accordance with the scheduling process.
Financial Management
The FM aspects were in general in compliance with Bank procedures (and with
additional standards as the financial controls included a Supreme Audit evaluation report,
as well as an annual external audit evaluation report). The external audit reports also
concluded with unqualified compliance. However, the following issues were identified
during the early stages of project implementation:
Delayed payments during project implementation: The delays adversely affected the PDCS consultants’ work and their ability to retain staff and conduct field supervision.
The delays were mostly due to the bureaucratic complication of yearly reappointment
of PPK/Satkers who had responsibility and authority in the budget allocation
(DIPA’s) process. However the PPK/Satker reappointment delay was reduced by
PMU and MoF at the Bank prompting from three months to one month.
The Interim Financial Report (IFR) submissions were chronically late, despite the Bank missions’ systematic reminders that PMU (through IREP 5) should submit them
45 days after each quarter closes. The Bank also recommended that the PMU should
implement a financial penalty to any underperforming consultants who submitted
their reports late. These delays were also a reflection of the dysfunctional MIS, as the
FM consultant (IREP 5) could not rely on a comprehensive and up to date monitoring
database and information flows with the three other consultants (IPM and the three
PDCS) were not smooth. IREP 5 did not have access to some contract amendments,
or IPM did not receive updated physical progress information from PDCS in a timely
manner. Numerous occasions arose where the FM consultant received conflicting
information from the contractors and the PDCS consultant on the progres of works,
especially in Nias. These delays improved during the later stages of the project as the
FM consultant proactively compiled and consolidated IPM and PDCS reports.
The financial control systems were less than satisfactory as the oversight role of IREP 5 was limited. IREP 5 did not have adequate access to all documents and was
unable to verify all payments as per their TORs and project SOPs. A Bank
supervision mission in April 2009 noted that only 30% of payments were verified by
the FM consultant. Corrective measures, including that no payment request should be
processed without prior verification from the FM consultant, were raised by the Bank
and led to the gradual improvement of FM oversight as noted in the ISRs.
Environment
Although IREP’s scope encompassed only the procurement of services to support
infrastructure reconstruction, the PAD noted that it would have, in practice, the effect of
programming very significant resources for reconstruction in Aceh and Nias. Key
-
12
environmental impact areas to be considered included: resource extraction impacts
(primarily sourcing of sand, gravel and other quarry material) and construction impacts
(excavation, fuel spills, noise, dust, obstruction to drainage, pollution and sedimentation
of water courses).
The approach followed was to task the IPM team to support BRR efforts in meeting the
environmental safeguards requirements by providing advice to BRR on all safeguards-
related issues and in assisting it in drafting action plans, preparing an Environmental
strategy for approval by BRR, engaging additional and specialist consulting support to
prepare all required social and environmental studies (AMDAL, UKL/UPL, and LARAP)
and to ensure that contractors and suppliers operated in accordance with accepted
contractual safeguard requirements.
It was agreed from the start that the Indonesian AMDAL legislation and procedures
would satisfy the Bank’s requirements, particularly for the planning and design of the
packages. During the 2007 Bank supervision mission, the Bank and BRR agreed to
implement a modified system of quality assurance designed by the IPM safeguards team
that was set out in a draft Environmental Management and Monitoring Protocol. The
Protocol linked the design and planning phase to the implementation of the project and
applied to all project packages. In effect, this created the Construction Environmental
Action Plan (CEAP) as a unique feature applying to all IRFF sub-projects. However, 22
projects which were already approved or in the procurement stage at the time of the 2007
supervision mission were excluded from the new CEAP requirement.
Overall, environmental management during implementation was satisfactory, and the
Bank task teams showed serious interest and concern for good safeguard management.
This engagement was particularly visible in the following areas:
Regulatory requirements, including Bank review and clearance: Most regulatory requirements were met, and approval by GoI and review and clearance by the Bank
were issued. It must be noted, however, that some environmental assessment studies
were not up to Bank standards, which cleared some with the condition that a
supplementary CEAP be done for the construction stage. Also, the Bank’s
environmental specialists reviewed most AMDAL studies received, plus a sample of
the UKL/ UPL documents, and their quality was considered to be generally
acceptable.
Bank supervision: In addition to the Bank’s regular supervision missions, Bank staff based in Banda Aceh carried out periodic field visits to review construction progress,
quality and safeguards aspects. As a matter of practice, the key findings were
provided immediately to the BRR, IPM and the three PDCS upon return from the
field, with detailed recommendations and target dates for completion of actions.
Environmental monitoring, reports and actions: The environmental monitoring site visits and subsequent reports by the PDCS consultants added significant value in
terms of quality improvement of implementation. A number of serious design flaws
-
13
were identified by these field visits. Actions for improvements, including specific
instructions to the contractors by the supervision engineers, were recommended by
the monitoring teams. They also provided coaching and mentoring to contractors and
supervision field staff on how to do better environmental management.
Interventions addressed at contractors: The CEAP model proved to very useful and positively impacted environmental performance under the construction contracts. For
instance, a template for a CEAP for a typical road project was prepared by the IPM
consultants, which helped to improve the quality of the plans, and ultimately the
quality of implementation. Two other contracts (Calang Port and Kota Sigli WS) used
a CEAP prepared with the help of the PDCS consultants and implementation quality
was found to be generally better.
Social Safeguards
Social safeguard policies triggered by IREP were, as outlined in the PAD, involuntary
resettlement and indigenous peoples. Although, the actual supervision and monitoring of
land acquisition/resettlement and compensation was within the scope of IRFF (IREP was
only tasked with providing consultancy services in this area), it should be noted that
timely compensation was provided for the ten sub-projects involving land acquisition.
Bank supervision missions regularly provided updates on the status of land acquisition
and documentation, and monitored the submission of IPRs. Where specific issues arose,
the Bank was pro-active and diligent. When the Tj. Meulaboh-Pante Cermin kabupaten
road subproject was about to acquire a piece of land with an old house on it, the Bank
requested IPM to confirm that a negotiation between the BRR and land owner would be
done properly, that compensation levels would be set at or above the market price and
that remaining land plots could be used for productive activities.
IPM was tasked to provide advice to BRR, help it prepare social studies, and assist in
ensuring that all social safeguards requirements were met. It was agreed for social
safeguards that the project would strictly follow Bank policies and procedures (the main
areas of difference between Bank and local policy included land acquisition,
compensation, resettlement, indigenous people, gender and social inclusion). To this end,
IPM developed social management plans for any subproject with a potential social impact
on surrounding communities, such as the Lohseumawe Drainage and Reservoir project
and Calang-Meulaboah Road. Both local and provincial governments were cooperative
and fairly compensated impacted people.
2.5 Post-completion Operation/Next Phase
The sustainability and maintenance of the assets was probably the most important issue
affecting the project. The PAD did identify the main sustainability risks arising from the
expiration of the BRR mandate in April 2009 (i.e., before the closure of IREP and IRFF):
(i) local and provincial governments might not own the projects financed by BRR, which
could result in inadequate maintenance in the post-BRR period, and (ii) local government
-
14
revenues derived from natural resources would likely decline as Aceh’s share of oil and
gas revenues would decrease after 2009.
Out of the 56 IRFF sub-projects, 13 sub-projects, comprising 34 % of the total asset cost
were handed over to the central authorities (5 ports to the Ministry of Transportation; and
8 national roads to the MoPW). Those packages are being managed following the
national standards and using national budget allocations.
9 provincial road sub-projects comprising 32% of the total asset cost were handed over to
the Aceh and North Sumatra provincial governments. As with other provincial assets,
these roads are being managed by the Provincial Dinas with adequate maintenance
budget allocations.
For the remaining projects (34% of the total assets), MoUs for assets handover were
signed between BRR and local governments (based on a standard template drafted by
IREP consultants), but the financial capacity of local governments did not always allow
them to devote sufficient funds for maintenance. In a context where decentralization
efforts have not been complete in the project area (infrastructure maintenance fund
allocation have been historically centralized in Jakarta), local governments do not always
dispose of sufficient funds to meet expenditures or prioritize new construction over
maintenance of existing assets. While the MOUs served to ensure smooth asset transfers
to the local authorities, the low capacity of these local authorities to manage these assets
remains a concern which is shared among the entire Aceh reconstruction program.
The Bank supervision teams were mindful of these risks, but efforts to remedy the risks
posed to sustainability of the assets produced limited results in terms of actual allocation
of maintenance funds. These efforts included:
The review by all PDCS and IPM of district level projects to assess if there were local government initiatives critical for successful and long-term operation of the
investment (these reviews were added to MOUs as addenda).
Local governments capacity assessments, which were implemented for 12 provincial/district governments, including: Aceh province, Banda Aceh, Sabang,
Aceh Besar, Aceh Jaya, Nagan Raya, Aceh Barat, Aceh Barat Daya, Aceh Selatan,
Aceh Singkil, Nias and Nias Selatan. Consequently, capacity building program plans
were produced. The assessments were conducted through a series of focus group
discussions that aimed at identifying strengths and weaknesses of local governments
in terms of reconstruction management and maintenance programming.
A request to the PMU in May 2010 to prepare a complete listing on each IRFF contract containing, among other data, an action list for ensuring final ownership and
sustainability.
The donors and MDF called upon GoI to ensure that the maintenance costs were
budgeted for and transferred to the local governments. It is worth noting that the local
governments have received some capacity building, through other projects like
-
15
Earthquake and Tsunami Emergency Support Project (ETESP) funded by ADB, Aceh
Emergency Response and Transitional Recovery project managed by the UNDP, Support
to Local Governments and Community Planning project, funded by GTZ and other
projects funded from USAID, EU, CIDA, JICA, the Netherlands and France. This needs
to be considered in the design of any future capacity building program to avoid
duplication.
3. Assessment of Outcomes
3.1 Relevance of Objectives, Design and Implementation
The project objectives remain highly relevant to the development priorities of Indonesia.
The development of large-scale infrastructure remains crucial to the country, and is a
pillar of the Bank’s engagement (Core Engagement 2) as outlined in the 2008-2012
Country Partnership Strategy (CPS). The document recognizes the need to strengthen the
accountability and capacity of institutions to deliver better infrastructure outcomes.
The project objectives are also highly relevant to the Bank’s strategy to play a major role
in disaster reconstruction, helping to reduce Indonesia’s vulnerability to natural disasters
as outlined in the CPS (Core Engagement 5). The document stressed that the Bank would
continue deepening the relationships established with Bappenas and the local
governments of Aceh and Nias in supporting selected elements of the Government’s
actions to strengthen natural disaster resiliency.
Implementation arrangements were consistent with the country policy to build capacity
within national institutions. After BRR closed in 2009, the implementing agency of IREP
became the MoPW. The new PMU was tasked to handle remaining construction work in
Aceh, and was staffed with many former BRR officials for continuity.
3.2 Achievement of Project Development Objectives
Provision of high quality technical assistance in order to ensure that infrastructure
program management, planning, design and construction management follow
adequate standards (Moderately Satisfactory):
The project strongly supported the BRR’s strategy for infrastructure reconstruction of
Aceh and North Sumatra by providing high quality technical assistance and capacity
building to BRR and MoPW. The project in effect enabled the implementation of the
IRFF by financing the technical assistance needed to perform the project implementation
management activities including procurement, financial management, quality control and
quality assurance, safeguards framework assurance and monitoring, implementation
monitoring and the design and construction supervision of all activities under the IRFF.
All major consultancy firms required to manage the implementation of IRFF were
appointed.
-
16
In general, and given the time constraints at the beginning, the project fulfilled its
primary objective in terms of the quality of the technical assistance provided. All 56 sub-
projects under IRFF, except for Siron Water Pipe Bridge and Siggli Water Intake, were
subject to detailed engineering design reviews and adequate construction supervision. In
some cases, designs were adjusted to take into consideration new findings in the field,
especially with respect to soil characteristics to mitigate for land-slides where road
shoulders are steep and/or the soil is unstable. The two failing sub-projects mentioned
above (Siron Water Pipe Bridge and Siggli Water Intake) couldn’t be finished before the
companion IRFF project closed. Thus, they have subsequently been reviewed and
redesigned and reconstruction is now underway from the MoPW’s own budget. As a
commitment guarantee, the involved PDCS liability was protected by renewing
performance liability insurance to anticipate any shortfall that may be identified due to
design fault or improper construction supervision.
Support BRR in overall coordination of the infrastructure reconstruction program
(Moderately Satisfactory):
The project also supported BRR and MoPW in the overall coordination of the
infrastructure reconstruction program through the IPM consultant. The IPM consultant
provided solid support to BRR with regards to managing the work programs,
performance and outputs of the three PDCS consultants and the FM consultant in charge
of the implementation of four other components of IREP. It strengthened the coordination
arrangements with the PDCS consultants, notably in terms of quality assurance and
control, construction supervision, monthly certificates preparation and program revisions
such as the gaps and actions on Bank Aide-memoires. IPM regularly monitored their
performance and discussed findings with the PMU, prompting the issuance of jointly
formulated action plans. IPM performance was also solid in terms of environmental and
social safeguard compliance of all stakeholders, as IPM consultants had established a
project tracking system that incorporates all safeguard aspects of projects.
As discussed earlier, there were some shortcomings in the IPM consultants’ overall
effectiveness, as the workload and number of deliverables under the original TORs were
not matched by IPM capabilities and staffing. In particular, the performance of IPM was
found lacking in terms of completing the MIS, and at an early implementation stage,
quarterly and mid-term reporting, PIPs and quality assurance were lagging behind. The
very high turnover of IPM leadership and expatriate staff also affected its coordination
capacities and strained its working relationship with BRR, PMU and the four other
consultants. In May 2008, the Bank recommended to BRR to reduce the scope of works
of IPM in areas such as capacity building and planning, which further reduced the
capacities of IPM. Ultimately, the IPM contract was cut by almost a third, and the
completion date was moved from June 2010 to March 2010.
3.3 Efficiency
-
17
The performance of BRR is worth noting as being efficient, especially against the
backdrop of the very real constraints following the tsunami and earthquakes of 2004. In a
short time, the BRR was able to lead the implementation of a US$6+ billion investment
program including the 56 sub-project under IRFF.
However, the midterm review noted that all in all, the project provided low value for
money. While IPM was supposed to serve the overall infrastructure construction process
(all GOI, BRR and other donor projects), the consultant worked almost exclusively on
IRFF sub-projects. PDCS consultants also almost exclusively worked on IRFF sub-
projects. As a consequence, the ratio of cost of the overall TA provided by IREP (US$42
million) to the capital investment (US$200 -300 million) was relatively high.
On the other hand, the ratio of the cost of the design and construction (i.e., only PDCS)
on IRFF capital investment was around 11%, putting it within the Indonesian good
practice range (8-12%).
3.4 Justification of Overall Outcome Rating
Rating: Moderately Satisfactory
The project achieved its primary development objective of supporting the BRR's strategy
for infrastructure reconstruction by providing technical assistance in order to ensure that
infrastructure program management, planning, design and construction management
follow adequate standards. IREP also managed to support the BRR/MoPW in the overall
coordination of this large infrastructure program, and enabled the 56 IRFF sub-projects to
come to fruition in a timely and adequate manner, for the benefit of the people of Aceh
and Nias. However, as discussed earlier, monitoring (through the failed MIS
implementation), and capacity building of the local authorities could have been improved.
In summary, IREP achieved its development objectives, albeit with moderate
shortcomings. It remains highly relevant to the country infrastructure and disaster
mitigation priorities. During the implementation, quality assurance, financial
management and post-completion operation and maintenance problems were identified
and mitigated for the most part. As such, an overall rating of moderately satisfactory is
justified.
3.5 Overarching Themes, Other Outcomes and Impacts
(a) Poverty Impacts, Gender Aspects, and Social Development
IREP enabled the construction of 56 sub-projects including Ports, Roads, General Water
Sanitation/Flood Protection and Water Supply. Although no socio-economic impact study
was conducted, it seems that the project has positively impacted the livelihoods of Aceh
and Nias through (i) the improvement of sea and land connectivity and mobility; (ii) the
improvement of livelihoods for the local community and the stimulation of local
economic growth (increasing the number of cargo boats and docks loading and unloading
-
18
consumer items, processed products and crops. In particular, cloves and crude palm oil
have increased by more than 20%); (iii) the development of new economic growth
contributors such as restaurants, shops, hotels and public services facilities (which all
increased the districts’ disposable income); (iv) the improvement of Banda Aceh’s solid
waste management through the construction of a sanitary landfill with recycling and
composting capacity; and (v) the improved provision of clean water supply.
(b) Institutional Change/Strengthening
The project provided an intense on-the-job training to the PMUs, PIU and other staff of
Bappenas, MoF, MoPW and the provincial and local governments staff in program
design and implementation, engineering designs, construction supervision and financial
management. The implementation arrangement initiated by BRR was adopted by MoPW
after the closure of BRR. Moreover, MoPW maintained the PMU structure after IREP
closed.
(c) Other Unintended Outcomes and Impacts
NA
3.6 Summary of Findings of Beneficiary Survey and/or Stakeholder Workshops
NA
4. Assessment of Risk to Development Outcome
Rating: Moderate
The IREP program has enabled proper design and construction of good quality
infrastructure and has mitigated the risk of short life and/or failure of the assets. As
mentioned earlier (see Section 2.5), the majority of large IRFF sub-projects are managed
at the national and provincial levels, where capacity to maintain them is adequate.
However, sub-projects which were transferred to the local authorities might very well be
affected by poor asset management and maintenance. This significant risk is currently
being addressed by central, provincial and local governments.
5. Assessment of Bank and Borrower Performance
5.1 Bank Performance
(a) Bank Performance in Ensuring Quality at Entry
Rating: Satisfactory
The Bank Task Team ensured that IREP’s overall development objectives were closely
aligned with both GoI and Bank strategies on infrastructure management and disaster
mitigation. This alignment, combined with sound implementation arrangements,
-
19
facilitated timely completion without compromising environmental concerns or social
safeguards. The program attracted the attention of the highest management level in the
Bank including the close involvement of its regional Vice President for East Asia Pacific.
The design ensured timely delivery of the majority of the project development objectives.
The IREP was designed for carry out a disaster response program covering 12 districts in
Aceh Province and Nias Island. The program was successful in supporting the 56 priority
sub-projects previously identified throughout the design, procurement, supervision and
implementation stages.
Considering the time constraints during the IREP preparation stage, the IPM’s role
(especially in terms of balancing the effectiveness and the wide geographic scope) was
too ambitious. Some of the IPM functions, such as the project supervision of QA, were
found to be overlapping with the PDCS role. As a result, BRR streamlined the IPM ToRs,
limited such functions to the PDCS and requested the IPM to be more focused on
implementation management activities until its contract ended.
(b) Quality of Supervision
Rating: Satisfactory
Bank supervision is rated satisfactory. Task Team Leaders initially followed the project
from Washington DC but were in continuous contact with infrastructure team members
who were based in Banda Aceh. This turned out to be critical for such a large size post-
disaster reconstruction program. Moreover, in late 2010, the TTL was re-located to
Jakarta which further enhanced the quality of supervision. This supervision set up and the
permanent presence of Bank staff in the reconstruction areas ensured continuous Bank
oversight throughout project implementation. The Bank’s supervision strategy resulted
in relatively high supervision costs which were financed from the MDF and which
considered the success of the project a top priority.
While implementation difficulties did occur, the pro-activeness of Bank supervision
could be noted in a number of aspects, such as:
Working with the PMU systematically to address weaknesses in reporting and in
financial management.
Increased attention to technical design, implementation quality and achievement of
quality outcomes.
Designing post-BRR institutional arrangements with MoPW, MoF and Bappenas.
Moreover, the Bank’s policies and procedures were applied consistently. Supervision
missions were conducted in a professional and constructive manner, and mission teams
consistently included the experts needed to discuss relevant supervision topics and issues.
The timing of formal supervision missions (on average twice a year and supplemented by
frequent routine supervision missions by the TTLs and the task team members who were
based in Banda Aceh) was appropriate and comments received from PMU and
BRR/MoPW staff indicated a respectful working relationship and a flexible approach by
-
20
Bank staff. Aide Memoires, Management Letters, ISRs and other project
communications and documents were completed in a timely manner with clear references
to needed actions covering all aspects of project components, safeguards and fiduciary
issues.
(c) Justification of Rating for Overall Bank Performance
Rating: Satisfactory
The Bank's overall performance rating is based on satisfactory ratings for both quality at
entry and supervision.
5.2 Borrower Performance
(a) Government Performance
Rating: Satisfactory
Performance of GoI was satisfactory, especially in terms of the strong and sustained
commitment to the project development objective. The agencies (MoF, MoPW and
Bappenas) turned out to be extremely cooperative and very effective in taking decisive
action in a timely manner, in particular with regard to the Bank recommendations on
implementation activities, including channeling the budget allocation (DIPA) and
preparing sufficient yearly budget allocations.
(b) Implementing Agency or Agencies Performance
Rating: Satisfactory
Performance of the implementing agencies was satisfactory. BRR and the MoPW
protected the integrity of the project and sustained its development objective. As an
independent agency, BRR performed effectively and was able to channel and manage a
reconstruction effort valued more than US$6 billion in only 4 years. This fast pace was
supported by the strong authority which BRR was granted which enabled it to avoid most
of the bureaucracy faced by line ministries.
The slowdown of the implementation was clearly noticed following the closure of BRR
and the handover of the implementation to the MoPW where the PMU functioned more
as a Program Management Unit and effective implementation was mostly managed by a
number of PIUs which sometimes were difficult to coordinate. This setup required the
Task Team to devote extra efforts to ensure compliance with Bank fiduciary and
safeguards procedures and guidelines.
(c) Justification of Rating for Overall Borrower Performance
Rating: Satisfactory
-
21
Both GoI and the Implementing Agencies (BRR and MoPW) managed to implement the
IREP with satisfactory performance.
6. Lessons Learned
Lessons were learned for both future operations in both Indonesia and future similar
reconstruction TAs in other countries, particularly in the following areas: Contract
Management and Flexibility; Social and Environmental safeguards management;
Implementation Arrangements; Maintenance and Capacity building; Stakeholder
Participation and Commitment; and Implementation Support Arrangements.
a) Future operations in Indonesia
Contract Management and Flexibility: BRR did not allow any sub-project to make any
change that would have led to an increase of the signed contract price. Thus, and to
account for any design changes, the only way was to reduce the scope of the works. This
has led to some incomplete works. While this policy gave BRR a tighter control on the
budget, it also adversely affected some sub-projects. Incomplete works were grouped
under the “Gaps” packages and were tendered separately, which turned out to be more
costly. Also, loading the consultancy contracts with reimbursable payments resulted in
some fund misuse and false reporting on reimbursable expenses (as was the case in the
IPM contract). To mitigate this, it would be best to design such contracts with very few or
no reimbursable payments in the future. Alternatively, more rigorous FM monitoring
would be required.
Social and Environmental Safeguards management: the projects handled the design and
implementation of 56 sub-projects of diverse types and in different locations and
environment, leading to many safeguards issues. These were addressed through: (i) the
allocation of provisional budgets to implement environmental management plans as part
of the civil works contracts; (ii) staffing of all PDCS consultants with the relevant
safeguards specialists; (iii) IPM QA and QC functions included the safeguards aspects
(iv) close involvement and commitment of the implementing agency, provincial and local
governments to implement LARAPs satisfactorily; and (v) close Task Team monitoring
and follow up with Indonesian counterparts.
b) Future similar reconstruction TAs in client countries
Implementation arrangements: The establishment of BRR as the entity responsible for
the implementation of the reconstruction program of Aceh undoubtedly boosted the
construction pace. BRR was empowered to operate outside the daily bureaucratic
constraints, a setting that made the mobilization of financial and human resources easier.
Moreover, BRR was created with a limited lifetime to enable the line ministries, like the
MoPW in this case, to pursue their roles seamlessly after the closure of the BRR. Also,
BRR established its own Procurement Central Unit (PCU) to manage all procurement
activities.
-
22
On the other hand, the daily implementation was fragmented between a large number of
changing PIU/Satkers and thus many procurement committees. The PMU had no control
over the implementation and was mandated with the program planning. This made it
sometimes difficult for effective communication. Also, a large and comprehensive
reconstruction program such as the one supported by IREP was bound to be fraught with
continuous changes in engineering designs, issues with the flows of information and
unforeseen events.
More care will be needed in future operations in the design of roles and institutional
coordination between the Bank, the PMU and the various contracted consultants.
Implementation models for consultant management could be based on the review of best
practices in terms of progress of delivery, financial viability, quality of delivery,
environmental soundness and asset end-user satisfaction. Having IPM assisting the
program management was not sufficient, especially where their ToRs overlapped with the
mandate of the PDCSs like in the case of the quality assurance and quality control.
Maintenance and Capacity building: In order to ensure the sustainability, as a medium-
term development objective, of built assets, mechanisms to allocate sufficient funds or
establish a maintenance fund should be effectively designed, especially in environments
where decentralization efforts are lagging. Also, it seems that a regionalized large
infrastructure program such as this one are best suited in an environment where the
capacity of the local government is sound and devolution of authority is real.
In the end, and understandably, the emphasis in this project was always on the
completion of the large building programs under institutional, budgetary and time
pressures rather than on the sustainability of these assets after handover. The project did
not put enough emphasis in effective training in infrastructure management, operation
and maintenance of local government staff, as was underscored by the reduction of
funding devoted to these activities. Local governments, on the other hand, did not
allocate funds to these training activities. Capacity building in infrastructure management
can only be effective when based on a sound analysis of the incentives and capacity of
the local government, to which assets are to be handed over. It is recommended that in
the future, local governments will allow for funding of capacity building programs in
their medium term development plans to acquire the proper skills in infrastructure
management.
Also, in some remote areas such as Nias, the working environment for outside contractors
was challenging and made it less attractive for workers to stay. This led to the termination
of some contracts and when local contracts were subcontracted, the quality of works was
not always satisfactory. To mitigate this, it is thus recommended that capacity building in
similar regional reconstruction projects include local contractors in the future.
Stakeholder Participation and Commitment: The project is a successful example of
stakeholder participation and commitment, which led for instance to the satisfactory
design of the sub-projects priority list and the support of the various authorities to
-
23
facilitate and safeguard project implementation. Stakeholders included the central,
provincial and local governments; local communities, NGOs, Donors, MDF and the Bank.
Implementation Support Arrangements: Both the MDF and the Bank acknowledged the
necessity to be closer to the project area, and the MDF supported the opening of a field
office in Banda Aceh. This proximity to the center of activity greatly facilitated
implementation on a day to day basis and provided continuous support to the client.
7. Comments on Issues Raised by Borrower/Implementing Agencies/Partners
(a) Borrower/implementing agencies
In general, the government of Indonesia was satisfied with the project’s outcomes. The
original implementing agency (BRR) was closed in 2009. The borrower completion
report and comments on the ICR were prepared by the Ministry of Public Works
(MoPW), and were mostly related to contract management.
BPK’s audit in 2010: The BPK (Government Auditor) criticized the PMU for awarding contracts which exceeded Engineer Estimates and for the allocation of
environmental budget for some sub-projects under IRFF. The PMU requested a
formal clarification from the Bank supporting their views. The Bank invited the BPK
and clarified that this can happen under normal circumstances and this is why the
Bank issued the no objection letters to the award of contracts. Nonetheless, BPK
requested the PMU to re-bid these contracts but the Bank considered that this was not
a sufficient basis for rebidding. Moreover, the Bank addressed a general letter to BPK
explaining that the Bank, as a matter of general practice, only issued a no objection
letter and that it was the implementing agency’s responsibility to approve and sign the
contracts as a legal entity. The Bank had also made it clear that making provisional
sums to implement environmental action plans was not against sound procurement
principles and that it was up to the implement