workforce planning for new nuclear power programmes · 2011. 8. 17. · possibilities. grid...
TRANSCRIPT
![Page 1: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/1.jpg)
Regional Training Course on Management SystemsANL
22 August - 2 September 2011
Workforce Planning for new Nuclear Power Programmes
![Page 2: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/2.jpg)
BACKGROUND TO WORKFORCE PLANNING DOCUMENT
• IAEA developed new “Milestones” document, published in September 2007
• Identifies 3 distinct phases, each with its own milestone, to be completed in preparation for a first nuclear power plant
• Provides detailed guidance on timely preparations for a nuclear power programme
• Intended to help Member States to assess progress and prioritise actions necessary to order, license, construct and then safely operate a nuclear power plant
2
![Page 3: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/3.jpg)
Preparing for assuming commitments & obligationsIn
fras
truc
ture
dev
elop
men
t pro
gram
1st. N
PP P
roje
ct
Commissioning
Operation / decommissioning
Nuclear power option included within the
national energy strategy
∼ 10 – 15 years
PHASE 2
PHASE 3
PHASE 1
MILESTONE 1Ready to make a knowledgeable
commitment to a nuclear programme
MILESTONE 2Ready to invite bids
for the first NPP
MILESTONE 3Ready to commission and
operate the first NPP
Feasibility study Bidding process
Pre-project Project decision making Construction
Considerations before a decision to launch a nuclear power programme is taken
Preparatory work for the construction of a NPP after a policy decision has been taken
Activities to implement a first NPP
Maintenance and continuous infrastructure improvement
INFRASTRUCTURE DEVELOPMENT PROGRAMME3
![Page 4: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/4.jpg)
KEY INFRASTRUCTURE ISSUES
• National position• Nuclear safety• Management• Funding and financing• Legislative framework• Safeguards• Regulatory framework• Radiation protection• Electric grid• Human resource
development
• Stakeholder involvement• Site and supporting
facilities• Environmental protection• Emergency planning• Security and physical
protection • Nuclear fuel cycle• Radioactive waste• Industrial involvement• Procurement
Note: All 19 issues have a Human Resource component
4
![Page 5: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/5.jpg)
IAEA Nuclear Energy Series – NG-T-3.10
• Developed to provide guidance to Member States (MS) in the identification of, and to develop Workforce Plans for, the Human Resources needed to implement a New Nuclear Power Programme
• Includes actual Case Studies to illustrate how other Member States implemented their first Nuclear Energy Programme
5
![Page 6: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/6.jpg)
SCOPE OF THE DOCUMENT
• Focuses on ‘nuclear related’ competencies, while recognising significant non-nuclear resources also required, but assumed to be within Member State’s capability
• Addresses the Workforce requirements for each of the three phases focusing on 3 main organisational entities indentified as having specific responsibilities within the “Milestones” document:
― NEPIO (Nuclear Energy Programme Implementing Organization)
― Regulatory Body― Operating Organisation
6
![Page 7: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/7.jpg)
SCOPE OF THE DOCUMENT (cont’d)
• Focuses on ‘permanent’ resources (as above) and does not address construction, and other, resources, which are addressed in other IAEA documents.
• Assumes Turnkey project and therefore resource levels based on those needed to be an “Intelligent Customer”.
• As with the “Milestones” document, this document assumes MS has an existing national infrastructure for radiation, waste and transport safety
7
![Page 8: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/8.jpg)
WORKFORCE PLANNING:
“The systematic identification and analysis of what an organization/nation is going to need in terms of the size, type, and quality of workforce to achieve its objectives.”
Identifies the steps that should be taken to get the right number of the right people in the right place at the right time.
8
![Page 9: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/9.jpg)
INTELLIGENT CUSTOMER:
• An organisation (or individual) that has the competence to specify the scope and standard of a required product or service and subsequently assess whether the supplied product or service meets the specified requirements.
9
![Page 10: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/10.jpg)
WorkforcePlanningProcess
10
![Page 11: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/11.jpg)
DOCUMENT STRUCTURE
1. Introduction2. Nuclear Energy Strategy – an indication of how
the chosen strategy may affect workforce planning requirements
3. Analysis of Infrastructure activities – supported by matrix of 3 phases and 19 Infrastructure Issues to identify competence requirements and resources
4. Developing a Workforce Plan - some general considerations regarding when and how to recruit
11
![Page 12: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/12.jpg)
CURRENT DOCUMENT STRUCTURE
5. Staffing considerations – a phase by phase review of the resources needed by the 3 key groups leading into the operations phase
6. The role of Support Organisations – an indication of the role of Educational, Research & Development and other Support Organisations
7. Knowledge Management for New Nuclear Power8. Summary: How to get started9. Overview of Case Studies
12
![Page 13: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/13.jpg)
CASE STUDIES
• A range of actual case studies to give practical examples of how Member States implemented their Nuclear Energy programmes
• Case Studies may cover individual phases or whole programme
• Case Study Contributions: China, Republic of Korea, India, UAE, Armenia
13
![Page 14: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/14.jpg)
WORKFORCE PLANNING MATRIX
• The main activities to be undertaken to address each Infrastructure issue, together with an indication of the responsibilities of key organisations in completing these activities;
• An indication of the competencies required to complete these activities successfully
• Probable educational/professional requirements necessary to support achievement of these competencies, and
• Suggestions for the Workforce Planning needed to deliver these competencies within the project.
14
![Page 15: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/15.jpg)
Sample of Competencies Matrix
Activity Responsibilities of key organizations
NP specific competencies
Probable education sources/
professions
Inputs regarding Workforce Planning,
education and training
Comments
Study of grid capability/ capacity re nuclear power
NEPIO:Take a lead role in the study
Grid Operator:Provide information regarding the stability and reliability of the grid, and anticipated grid growth/changes and suitability for NPPs
Knowledge of grid characteristics that are important re an NPP Thorough understanding of electrical O/P characteristics of an NPP and their impact on existing grid/necessary upgrades
Nuclear power engineerElectrical Power Engineer with Nuclear Power training module
At least one nuclear power engineer with expert level competencyAt least one power engineer with expert level competency and Nuclear Power training
Core competence is Electrical Power Engineering, but training in specifics of NPP output characteristics would be necessary to address grid capability/upgrade requirements
Study of grid interconnection possibilities
Grid Operator:Provide information re grid characteristics and the issues related to their interconnection
In-depth knowledge of principles for, and lessons learned, regarding grid interconnections
Power engineer
One Power Engineer with expert level competencyOne or more with working level competence
Infrastructure Issue 10. Electrical Grid Phase 1
15
![Page 16: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/16.jpg)
Human Resource Development-Phase 1
• Knowledge and skills needed to support a nuclear programme identified by NEPIO
• Two fundamental aspects of Human Resource development to be considered:– What level of National involvement is
desired?– What level of National capability exists
or could be developed?• Workforce/Staffing Plans prepared • Workforce Plans needed for all
organisations and should be integrated upwards
16
![Page 17: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/17.jpg)
During Phase 1, NEPIO undertaking:•Feasibility studies and developing understanding of commitments associated with Nuclear Power.•Analysis of national capability•Development of 1st Workforce PlanNEPIO 25 – 50 personnel, depending on expert support.
Resource Requirements for Phase 1
17
![Page 18: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/18.jpg)
Core regulatory functions also established at this time for the development of regulations, for licensing, review and assessment, inspection, enforcement and public information
Resource Requirements for Phase 1 (cont’d)
18
![Page 19: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/19.jpg)
RECRUITMENT CHALLENGES IN PHASE 1
Lack of experience in phase 1 may be alleviated by:
• Contracting out whole work packages to experienced consultants, including requirements to utilise/train national staff in delivering the work package.
• Contracting with consultants to become ‘temporary’ staff working with nationals to deliver work packages, while developing national staff.
• Engaging senior consultants to ‘coach’ national staff in specific areas of competence.
• Organising national conferences/workshops where vendors and specialist support organisations can present their capabilities and services
19
![Page 20: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/20.jpg)
RECRUITMENT CHALLENGES IN PHASE 1
Opportunities to gain experience outside MS include:
• Establishing Bi- and Multi-lateral relationships with governments, regulatory agencies, vendors, utilities, educational institutions, etc.
• IAEA Training courses, Fellowships and Internships.
• Formal courses of overseas study (e.g. vocational, under- and post-graduate programmes).
• Building staff training and development assignments into potential contracts with vendors, service providers, etc.
• Developing ‘strategic alliances’ with vendors/equipment suppliers whereby national organisations obtain licenses to manufacture components in-country, which can include training and qualification in the country of origin.
20
![Page 21: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/21.jpg)
Human Resource Development-Phase 2
In preparation for inviting Bids to construct a first NPP:• Sufficient human resources are in place to be an “Intelligent Customer”
• A Systematic Approach to Training (SAT) of human resources needed for plant operation is initiated
• HR issues, including SAT requirements, are addressed in requirements for suppliers (turnkey assumed)
• Workforce/Staffing Plan(s) updated
21
![Page 22: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/22.jpg)
RECRUITMENT CONSIDERATIONS
• Attracting expatriate personnel who have worked in the nuclear sector abroad.
• Attracting experienced foreign personnel, either as employees (if permitted by national labour laws/regulations) or as consultants.
• Recruiting experienced personnel from appropriate national industries such as fossil fired power generation, process/production, oil and gas industries, who will already have many of the required competencies to work in the nuclear industry.
• Remember recruitment is a two-way process – allow for loss of staff to other industries/countries
22
![Page 23: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/23.jpg)
Resource Requirements for Phase 2
NEPIO resources peak during Phase 2, as responsibilities are handed over to Regulatory Body and Operating Organisation
23
![Page 24: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/24.jpg)
Resource Requirements for Phase 2 (cont’d)
Regulatory Body resources build during Phase 2 to enable it to develop necessary regulations, licensing arrangements and carry out its oversight responsibilities.
24
![Page 25: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/25.jpg)
Resource Requirements for Phase 2 (cont’d)
Operating Organisation commences staffing during Phase 2 due to allow time for training prior to commissioning
25
![Page 26: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/26.jpg)
Human Resource Development- Phase 3
• All human resources to commission and operate the first NPP are in place
• Education and training programmes for continuing flow of qualified people are in place
• Workforce/Staffing Plan(s) updated
26
![Page 27: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/27.jpg)
Resource Requirements for Phase 3
27
![Page 28: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/28.jpg)
Resource Requirements for Phase 3 (cont’d)
28
![Page 29: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/29.jpg)
Resource Requirements for Phase 3 (cont’d)
29
![Page 30: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/30.jpg)
ONGOING REQUIREMENTS
• Post-commissioning, SAT based training programmes should be in place in all organisations producing a ‘pipeline’for new staff
• Succession Management arrangements in place for all positions
• Workforce Planning should allow for follow-on NPPs if appropriate
• Long-term Workforce Planning arrangements should allow for full Lifecycle requirements including Plant Life Maintenance and eventual decommissioning
30
![Page 31: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/31.jpg)
Summary: How to effectively consider HR from the beginning?
• Use an integrated, systematic approach toward considering and implementing a NP programme (The “Milestones”Approach)
• Develop workforce/staffing plans that are based upon the roles and responsibilities for the activities in each of the 3 Phases, particularly focusing on the three key organisational entities
• Require SAT for all training programmes• Include SAT, and knowledge capture and transfer
requirements in supplier(s) contracts• Maintain this integrated workforce planning approach
through the entire lifecycle of the facilities/programmes
31
![Page 32: Workforce Planning for new Nuclear Power Programmes · 2011. 8. 17. · possibilities. Grid Operator: ¾ Provide information re grid characteristics and the issues related to their](https://reader033.vdocuments.mx/reader033/viewer/2022060901/609e8c0e6cab66000a4f76fb/html5/thumbnails/32.jpg)
Thank you – Any Questions?
…atoms for peace.32