KARIM ELDASH www.projacs.com 1 Training Program Contract Management 16-18/01/2011 WORKBOOK Presented by Karim El-Dash PHD; CCE; PMP; RMP; AVS

Upload: others

Post on 01-Aug-2020

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    1 

Training Program

Contract Management

16-18/01/2011

WORKBOOK

Presented by

Karim El-Dash PHD; CCE; PMP; RMP; AVS

 

Page 2: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    2 

Table of Contents Karim M. EL‐DASH; ...................................................................................................................... 3 

REQUIREMENTS DOCUMENTATION ............................................................................................ 4 

ECONOMICS BASICS .................................................................................................................... 5 

CASH FLOW .............................................................................................................................. 5 

EQUIVALENT ANNUAL PAYMENT ............................................................................................ 7 

PROJECTS COMPARISON ......................................................................................................... 8 

PROJECT SCOPE MANAGEMENT ............................................................................................... 10 

PROJECT SCOPE STATEMENT ................................................................................................. 10 

WORK BREAKDOWN STRUCTURE (WBS) ................................................................................... 11 

WBS DICTIONARY .................................................................................................................. 12 

PROJECT TIME MANAGEMENT .................................................................................................. 13 

NETWORKS ............................................................................................................................ 13 

PERT ....................................................................................................................................... 14 

PROJECT COST MANAGEMENT .................................................................................................. 15 

RESOURCE ALLOCATION ........................................................................................................ 15 

CRASH COST ........................................................................................................................... 17 

PROJECT RISK MANAGEMENT ................................................................................................... 18 

PROBABILITY IMPACT MATRIX .............................................................................................. 18 

RISK REGISTER ....................................................................................................................... 19 

PUZZLE ....................................................................................................................................... 20 

 

Page 3: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    3 

KARIM M. EL‐DASH;  PhD; CCE; PMP; RMP; AVS

Professor of Construction Management 10-11-1961

PhD, Structural Engineering, North Carolina State University, USA (1995).

CCE, Certified Cost Engineer, Association for Advancement of Cost

Engineering International (AACEI), USA, (2009-2012).

PMP, Certified Project Management Professional, Project Management

Institute (PMI), USA (2000-2016).

PMI-RMP, Certified Risk Management Professional, Project Management

Institute (PMI), UAS (2010-2013).

AVS, Certified Associate Value Specialist, (2008)

Certified Consultant Engineer, Design of Reinforced Concrete Structures,

Egypt.

Delivered more than 30 technical and managerial academic courses in USA,

Egypt, and Kuwait.

Participated for more than 26 years in the management, structural design,

and building assessment and repair of many mega construction projects in

Egypt, Kuwait, and Saudi Arabia.

Lecturer and facilitator; prepared, delivered, and participated in more than

4000 training hours including more than 30 training subjects in the fields of

project management and construction. For example; facilitator for the

Cambridge University Project Management Diploma; facilitator for preparation

of Project Management Professional (PMP) certification and for certification

from International Project Management Association (IPMA).

Produced 28 research papers in the field of construction management, project

management, and structural engineering. Papers were published in

international recognized journals or presented in international conferences in

USA, GB, France, Canada, Spain, China, Norway, Greece, Nigeria, Jordan,

UAE, Qatar, and Egypt.

Page 4: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    4 

REQUIREMENTS DOCUMENTATION 

 

Project Title:______________________ Date Prepared: __________________

 

Stakeholder  Requirement Category Priority Acceptance Criteria 

         

         

         

         

 

Page 5: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    5 

ECONOMICS BASICS 

CASH FLOW 

A  project  consists  of  an  investment  of  KD100 million  in  capital  for  the  construction  of  the manufacturing operations. Each year after the completion of the construction, the project will sell product worth KD70 million. The costs of manufacturing this product are expected to by 60% of the value of the sales. 

The  taxes  are  expected  to  be  30%  of  taxable  income.  No  deductions,  such  as  those  for depreciation or capital allowance, are permitted  for the determination of the taxation charge. The working capital is 15% of the fixed capital. 

The working capital charge is incurred in the first year of operation and is recovered in the fifth year. Determine the free cash flow for the first five years of operation. 

Page 6: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    6 

PAYBACK PERIOD A new capital project has the following cash flow profile:

Year Cash flow

0 −10,000

1 −5,000

2–9 3,000

10–14 2,000

15 3,000

Determine the payback period.

    

Page 7: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    7 

EQUIVALENT ANNUAL PAYMENT 

An engineering  consultancy wishes  to purchase  an office  for KD300,000. The  current  interest rate for mortgages is 5% over a 25‐year term. What are the monthly repayments? 

   

Page 8: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    8 

PROJECTS COMPARISON 

Compare the NPV for the shown data of projects A, B, and C. Assume that all expenses are incurred at the end of the year. (i=10%)  

Project A Project B Project C Cash Flow Cash Flow Cash Flow

Year 1 (10,000) (4,000) (1,000) Year 2 (2,000) (4,000) 1,000 Year 3 5,000 3,000 2,000 Year 4 12,000 10,000 3,000

 

Page 9: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    9 

A company owns office buildings that it lets to tenants. A particular building that cost KD 40 million has 7,500 m2 of office space. The building is expected to last for 30 years. The maintenance costs are KD 2 million each year. If the company’s discount rate is 15%, determine the annual revenue that the company must make from rentals in this building in order to meet its investment criterion that the NPV must be greater than KD 1 million. Determine the minimum rental per square meter that the company must charge to meet this investment criterion. 

   

Page 10: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    10 

PROJECT SCOPE MANAGEMENT 

PROJECT SCOPE STATEMENT 

Project Title:______________________ Date Prepared: __________________

 Product Scope Description:

 Project Deliverables:

 Project Acceptance Criteria:

 Project Exclusions:

 Project Constraints:

Project Assumptions:

Page 11: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    11 

WORK BREAKDOWN STRUCTURE (WBS)    

Page 12: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    12 

WBS DICTIONARY 

Project Title:______________________ Date Prepared: __________________

 

Work Package Name:  WBS ID: 

Description of Work: 

 

Milestones: 

1. 

2. 

3. 

Due Dates: 

ID  Activity  Resource Labor Material  Total 

Cost Hours  Rate  Total  Units  Cost  Total 

                   

                   

                   

                   

Quality Requirements: 

 

Acceptance Criteria: 

 

Technical Information: 

 

Contract Information: 

 

Page 13: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    13 

PROJECT TIME MANAGEMENT 

NETWORKS 

For  the  shown  activities,  durations,  and  relationships,  it  is  required  to  construct  a network  showing  the  logic  of  the  activities,  early  and  late  starts  and  finishes  of  the activities as well as the total float of each one. 

 

ACTIVITY  PREDECESSOR  DURATION

A  ‐  4 

B  A  8

C  A  7 

D  A  8 

E  B,C  6 

F  D  9 

G  C,E  7 

H  C,F  9 

J  E,F  10 

K  H,J,G  4

 

 

   

Page 14: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    14 

PERT 

Given the following project activities and estimates of activity duration, determine the mean project duration and project duration variance. Assume all relationships are finish to start. 

 

ACTIVITY Duration 

OptimisticMost Likely 

Pessimistic

A  2 4 5

B  3 5 8

C  5 8 11

D  4 6 9

E  2 5 11

 

 

Page 15: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    15 

PROJECT COST MANAGEMENT 

RESOURCE ALLOCATION 

Draw a bar chart for the network diagram (early and late dates) shown below. Hence, assuming constant  rate of work  for  each  activity,  find  the daily  required  labor  for  each  activity,  then, allocate  the  required  labor  for  the  project  given  the  total  (man.day)  requirements  for  each activity (draw a histogram based on the early dates):  

Activity  Labor 

Start  0 

A  10 

B  24 

C  24 

D  36 

E  20 

F  8 

Finish  0 

 

 

 

   

660

B

166

110

C

100

550

A

111

165

D

211

211

E

201

000

START

000

141

F

261

202

FIISH

202

Page 16: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    16 

   

Page 17: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    17 

CRASH COST 

Given  the  following  information about a project and  the network diagram  (normal duration), compress the network from  its normal duration of 9 days to  its expedited duration. List those activities that are expedited and the costs associated with each compression. Plot the duration‐cost curve for this project. 

  

Activity  ND  CD  NC  CC/day 

A  4  3  100  25 

B  4  3  250  150 

C  2  1  150  150 

D  4  1  450  150 

E  1  0.5  200  400 

F  5  2 200 50 

    

Page 18: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    18 

PROJECT RISK MANAGEMENT  

PROBABILITY IMPACT MATRIX 

 Project Title: Date Prepared:  

Ver

y H

igh

Hig

h

Me

diu

m

Lo

w

Ver

y L

ow

Very Low Low Medium High Very High

 

Page 19: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    19 

RISK REGISTER 

Project Title: Date Prepared:   

Risk ID 

Risk Statement  Probability Impact  Score  Response 

Scope  Quality  Schedule Cost

                 

                 

                 

                 

                 

                 

                 

                 

                 

                 

 

   

Page 20: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    20 

PUZZLE 

SCHEDULE RESOURCE REQUIREMENTS

BREAK EVEN ANALYSIS

ACTIVITY SEQUENCE

ACTIVITY COST EARNED VALUE CRASHING ACTIVITIES EXPECTATIONS

RATE OF RETURN PAYMENT RECEIVED DELIVERABLES ACCEPTANCE

BUDGET SCOPE DEFINITION SCOPE STATEMENT CHARTER

VERIFICATION REQUIREMENTS RESOURCE RATES ACTIVITY DURATION

 

Page 21: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    21 

PUZZLE 

SCHEDULE RESOURCE REQUIREMENTS

BREAK EVEN ANALYSIS

ACTIVITY SEQUENCE

ACTIVITY COST EARNED VALUE CRASHING ACTIVITIES EXPECTATIONS

RATE OF RETURN PAYMENT RECEIVED DELIVERABLES ACCEPTANCE

BUDGET SCOPE DEFINITION SCOPE STATEMENT CHARTER

VERIFICATION REQUIREMENTS RESOURCE RATES ACTIVITY DURATION

 

 

 

   

Page 22: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

 

 

KARIM EL‐DASH      www.projacs.com                                    22 

 

1 2 3 4

5 6 7 8

9 10 11 12

13 14 15 16

17 18 19 20

 

Page 23: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

Appendix F

Discrete Compound Interest Tables

Symbols

The following symbols are used in the following tables:

A Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts,$F Future value, a single lump sum value occurring at the end of the last of n time periods, $i Interest rate per period, decimaln Total number of compounding periods, decimal P Present value, a single lump sum occurring at time zero, the first of n time periods, $G Uniform or arithmetic gradient amount, a constant increase in funds flow at the end of each peri-od, $

General Notification of Compound Interest Factors

Compound interest factors were developed to facilitate economic analysis before the advent of the pro-grammable calculator and personal computer. Today, many engineering economic evaluations are per-formed using spreadsheet at great ease. However, the ability to use compound interest factors willdemonstrate the true skill of performing basic economic analysis. The compound interest factor followsa general format:

(X/Y, i, n)

In this notation, X and Y denote two sums of money, and X/Y denotes the ratio of X to Y. The letters iand n denote the interest rate and the number of interest periods, respectively. When the value of Y isgiven, the unknown variable X is calculated from the following;

X (X/Y, i, n) = X * Compound Interest Factor

For example, given the present value P, find the future value F

F = P (F/P, i, n) or simplified as F = P (F/P)

Compound interest factor is applied to a known variable with monetary value of $1 to calculate theunknown variable.

F.1

Appendix F Discrete Compound Interest Tables

Page 24: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

Table F.2—5% Interest Rate

F.3

Appendix F Discrete Compound Interest Tables

Page 25: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

Table F.3—6% Interest Rate

F.4

Appendix F Discrete Compound Interest Tables

Page 26: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

Table F.4—8% Interest Rate

F.5

Appendix F Discrete Compound Interest Tables

Page 27: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

Table F.5—10% Interest Rate

F.6

Appendix F Discrete Compound Interest Tables

Page 28: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

Table F.6—12% Interest Rate

F.7

Appendix F Discrete Compound Interest Tables

Page 29: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

Table F.7—15% Interest Rate

F.8

Appendix F Discrete Compound Interest Tables

Page 30: WORKBOOK - bu.edu.eg · Cash Flow Cash Flow Cash Flow ... Periodic payment (i.e. Annual amount). A uniform series of end-of-period payments or receipts, $ F Future value, ... P Present

Table F.8—20% Interest Rate

F.9

Appendix F Discrete Compound Interest Tables