+ WOODSIDE TURBINE CONTROLS SYSTEM UPGRADE PROJECT TURBO-MACHINERY SYSTEMS Featured Project For turbo-Machinery SySteMS + PROJECT OVERVIEW The Woodside Control Systems Upgrade (TCSU) project involved upgrading and replacing the control, safety and protection systems and instrumentation on twenty-one gas turbines at the Karratha Gas Plant. This $135M project was successfully completed in 2011 after an intensive five-year program. + OUR SERVICES The scope of our work included project management, implementation planning, design, hazardous areas engineering, vendor coordination, testing, installation supervision and commissioning. The project involved twenty-one gas turbines (fifteen for gas compression, and six for power generation) and included the replacement of Turbine Speed Control Systems, Fire & Gas Systems, Condition Monitoring Systems, AVR and Protection (for power generators), replacement of Instrumentation and Sampling Systems and additional new instrumentation to raise the Safety Integrity Level (SIL) of the control systems. DAD – System Information Modelling software was utilised for the design of Control and Safety Systems to ensure accuracy and to avoid time- consuming errors during the twenty-one critical shut-down periods. Please visit our website at www.iesystems.com.au for further information or contact our Business Development Managers: Western Australia and International: Barry Pretorius on +61 (0)8 9442 4280 or email [email protected] Australia (excluding WA): Rob Gillespie on +61 (0)408 309 788 or email [email protected] Level 2, 445 Hay Street, Perth, Western Australia 6000 Tel: +61 (0)8 9442 4242

Upload: others

Post on 02-Oct-2021

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WOODSIDE TURBINE CONTROLS SYSTEM UPGRADE PROJECT

+WOODSIDETURBINECONTROLSSYSTEMUPGRADEPROJECT TURBO-MACHINERYSYSTEMS

Featured Project For turbo-Machinery SySteMS

+PROJECTOVERVIEWThe Woodside Control Systems Upgrade (TCSU) project involved

upgrading and replacing the control, safety and protection systems

and instrumentation on twenty-one gas turbines at the Karratha Gas

Plant. This $135M project was successfully completed in 2011 after an

intensive five-year program.

+OURSERVICESThe scope of our work included project management, implementation

planning, design, hazardous areas engineering, vendor coordination,

testing, installation supervision and commissioning.

The project involved twenty-one gas turbines (fifteen for gas compression,

and six for power generation) and included the replacement of Turbine

Speed Control Systems, Fire & Gas Systems, Condition Monitoring

Systems, AVR and Protection (for power generators), replacement

of Instrumentation and Sampling Systems and additional new

instrumentation to raise the Safety Integrity Level (SIL) of the control

systems.

DAD – System Information Modelling software was utilised for the design

of Control and Safety Systems to ensure accuracy and to avoid time-

consuming errors during the twenty-one critical shut-down periods.

Please visit our website at www.iesystems.com.au

for further information or contact ourBusiness Development Managers:

Western Australia and International:Barry Pretorius on +61 (0)8 9442 4280or email [email protected]

Australia (excluding WA):Rob Gillespie on +61 (0)408 309 788or email [email protected]

Level 2, 445 Hay Street,Perth, Western Australia 6000Tel: +61 (0)8 9442 4242

Page 2: WOODSIDE TURBINE CONTROLS SYSTEM UPGRADE PROJECT

Featured Project For turbo-Machinery SySteMS

+THERESULTSThe Woodside maintenance shut-down schedule for the gas turbines was

strictly controlled so the challenge for our team was to perform the system

replacement activities in these regulated short shutdown periods. Our

team successfully achieved all the system replacement activities without

causing any delay to Woodside’s production planning.

Our technical knowledge, management expertise, design and

commissioning accuracy, commitment to safety and effective

co-ordination of activities exceeded Woodside’s requirements and

expectations for the project.

As stated by Woodside’s Project Manger at Transfield Worley:

“The project delivered outstanding performance on key deliverables:

Safety targets – zero incidents or injuries �

Quality – zero construction punch list items �

Schedule – P50 targets achieved on all shutdowns �

Compliance - SAP & maintenance systems integrated on time �

A fantastic outcome and superb team performance.”

+CONTACTUSFor further information about Turbo-Machinery Services please contact

our Business Development Managers:

Western Australia and International: Barry Pretorius on

+61 (0) 8 9442 4280 or via email at [email protected]

Australia (excluding WA): Rob Gillespie on +61(0)408 309 788

or via email at [email protected]