western power future of the grid - midwestsummit.com.au
TRANSCRIPT
Western Power Future of the GridPresentation for Mid West Economic Summit
Doug Thomson
Transmission Grid Strategy Manager 18 February 2021
2
2,700+ strong workforce
271,000 streetlights
13 Community Batteries
1GW+ rooftop solar
(~30% homes)
~793 battery systems approved
2+ million people connected
Our grid
covers
254,920 km2
Figures correct as of January 2020
About Western Power
3
What we do
Power Generation Western Power Network
RetailerPower Generation Western Power Network
Retailer
4
Our traditional interconnected network
of poles and wires
A centralised network with consumers at the edge of the
network on island systems
An extreme model with no centralised network
A flexible model with a centralised grid embraces SPS, microgrids, VPPs
and other new technologies
Integrated Network
Fringe Disconnection
Modular Network
Fully Decentralised
Radial Network
Mesh Network
MicrogridStand-alone Power Systems (SPS)
A more flexible grid will support our customers adoption of changing generation and storage options. Grid evolution is reliant on community behaviour, technology advancement rates, regulation and policy.
Why we’re evolving our grid
5
Western Power’s Distribution Grid Vision identifies the key technologies that will underpin our delivery of services to customers into the future.
The autonomous grid will be serviced using SPS and microgrids to cover the low density areas of our network.
The remaining mesh grid will be serviced using overhead and underground network solutions enhanced through the control of advanced network operations and control, grid storage and customer DER.
Our distribution grid vision
Stand-alone power systems
7
• Solar, battery and backup generator (as required)
• Power a single connection
• Replaces end of life assets, avoiding network upgrade
• Significant improvement to reliability
• Round 1 – 7 in City of Greater Geraldton
• Round 2 – 29 in the Mid West with 4 in the Shire of Northampton
• Approx. 150 additional units proposed in the Mid West Region over the next 10 years
Battery energy storage system – Perenjori
Morawa
Perenjori
N2706750
N4590878
N1408817
Three Springs ZSS
PE1
BESS commissioned July 2018
• Objective: Improve town supply reliability
• Town supply: 33 kV feeder approx. 75km Three Springs 132/33 kV substation
• System design: Feeder supplying town is faulted (upstream BESS back towards Three Springs substation). BESS intentional island for supply continuity.
8
9
Perenjori BESS
• 25 hours outage avoided in 18 months• Planned and unplanned outages
avoided• Power quality improvements• 93 local mobile phones receiving text
message alerts
• Kalbarri peak (holiday) load of 3.7MVA
• Supplied by a 140km long rural feeder
exposed to environmental factors
• Feeder’s length, remoteness and
environmental conditions can lead to
extended outages
• Existing generation (wind turbines &
solar PV)
• Utilise renewable microgrid solution to
improve reliability
Kalbarri Microgrid
11
~~
North RegionEast Region
Central Region
South Region
• Large-scale renewable zones / energy hub(s)
• Increased dependency on the generation in this area
• Better utilisation of bulk 330kV network
• Rationalised transmission voltages
• Optimised network topology
• Decentralised generation
• Significant coal generation retirements
• Large-scale industrial zones
• Modularised, better utilised transmission network
• Renewable energy zone
• Volatile / high net worth (mining) customer demand
• Remote, radially connected region
FUTURE STATE OF THE TRANSMISSION GRID – REGIONAL CHARACTERISTICS
Flashpoints short term reliability issues
Hot Spots long standing reliability issues
Traditional
Asset management
New technologies
BESS
Microgrids
• Perenjori
• Kalbarri
Quick wins
• e.g. Fuse savers
Modular short term solutions
• HVIU
Automated analysis tool
What will drive the change
12