week 1 & 2 inspection & testing (basic) (powerp point file)
TRANSCRIPT
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
1/117
1
A problem with many installations,
particularly domestic, is that
Every man and his dog has had a
hand in it
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
2/117
2
periodic inspection and testing to ensure
continued safety is unlikely.
additions/alterations possibly undertaken
by unqualified persons.
The domestic electrical installation
likely to have been originally installed
by competent electrical contractor
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
3/117
3
To what standards should anelectrical installation conform?
The Institution of ElectricalEngineers Wiring Regulations
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
4/117
4
First Edition of the Regulations
Issued in 1882 and entitled
Rules and Regulations for thePrevention of Fire Risks
Arising from Electric Lighting
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
5/117
5
What about risk of electric shock
and death by electrocution?
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
6/117
6
Jointly owned by the Institution of
Electrical Engineers and B.S.I.
Latest edition
1st January 2002
Came into effect
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
7/117
7
Are these regulations statutory?
No, but they can be used as
evidence of compliance withstatutory regulations
limited value within the domesticinstallation in terms of enforcement
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
8/117
8
Very few enforceable regulations
apply to domestic installations
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
9/117
9
The commercial or industrial electrical
installation usually under the controlof competent persons.
Statutory measures in place toensure a safe working environment.
This includes the electricalinstallation and electrical equipment
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
10/117
10
Failure to comply with statutory regulations
within the workplace can lead to criminalprosecution
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
11/117
11
Other Interested Parties
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
12/117
12
Two organisations concerned with the
quality and safety of all aspects of electricalinstallation work in including domestic
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
13/117
13
The Electrical Contractors AssociationE.C.A.
National Inspection Council for Electrical
Installation Contracting
N.I.C.E.I.C.
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
14/117
14
Organisations only concerned with the
competence and quality of work for
those electrical contractors whoare members of their organisation
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
15/117
15
What happens if an electrical contractor
carries out work in an unsatisfactory
manner?
If the contractors are members of the ECAor NICEIC, then appropriate action can be
taken
If not, the trading standards office, or local
authority may be able to help
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
16/117
16
With many domestic installations there is
little or no maintenance undertaken toensure continued safety
In many cases, the integrity and safety ofthe installation is reduced by the D.I.Y.person!
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
17/117
17
The need for Inspection and Test
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
18/117
18
Installations should be inspected and tested
before being put into service -
(initial verification)
at regular intervals thereafter -
(periodic)
on completion of any alterations or
additions
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
19/117
19
The Initial Verification
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
20/117
20
For an initial verification
BS 7671:2001 states:
installed equipment to an appropriatestandard, i.e. BS, BS EN etc.
correctly selected and erected
not visibly damaged or defective as to
impair safety
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
21/117
21
The periodic installation inspection
BS 7671:2001 states
Periodic inspection and testing of an
electrical installation shall be carried out todetermine,so far as is reasonably
practicable, whether the installation is in a
satisfactory condition for continued service
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
22/117
22
Generally, the main reason for undertaking
an inspection and test is to ensure that theinstallation is safe to use
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
23/117
23
What are the likely reasons for an
installation failing to be safe?
Age
Wear and tear - may be considerable inrented accommodation
Botched work by incompetent persons, or
unscrupulous contractors
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
24/117
24
Periodic Inspection Report
Where is it required?
expiry of current certificate
change of ownership or use
as a result of damage - flood, fire, etc
mortgage/insurance purposes
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
25/117
25
Factors affecting the safety
some common factors will include:-
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
26/117
26
Damage to equipment or accessories
Poorly installed equipment/accessories
Loose connections giving rise to shock/fire
Overloaded circuits
Inadequate protection of circuits against
overcurrent
Circuit cables inadequate to safely carryload current
Inadequate earthing arrangements
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
27/117
27
The visual Inspection
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
28/117
28
For reasons of safety the supply
should preferably be switched offprior to conducting the inspection
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
29/117
29
Checking fixings of accessories
and cabling
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
30/117
30
Loose connections may result in
electric shock
fire
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
31/117
31
circuit connections may be dislodged bymovement of the socket outlet .
terminations should be checked beforesocket is secured
remember, loose
connections may
give rise to fireand shock
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
32/117
32
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
33/117
33
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
34/117
34
circuit connections may be dislodged bymovement of the joint-box .
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
35/117
35
Thats assuming they bothered to usea joint box in the first place.
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
36/117
36
Blimey hes even left
the screwdriver bit
in the terminal block
potential fire/shock risk due to mechanical
damage or loose connections
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
37/117
37
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
38/117
38
Overheating due to loose connections
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
39/117
39
Correct connection of single-way switch
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
40/117
40
Correct connection of single-way switch
surface box secure
earth wire sleeved
terminations secure
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
41/117
41
Basic one-way lighting circuit
switch
Lamp
P
N
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
42/117
42
switch
lamp
P
N
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
43/117
43
Switch connectionsfor two-way lighting
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
44/117
44
P
N
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
45/117
45
P
N
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
46/117
46
P
N
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
47/117
47
P
N
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
48/117
48
P
N
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
49/117
49
When converting one-way
to two-way lighting the earth
wire used as live conductor
Very dangerous practice
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
50/117
50
When installing socket outlets
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
51/117
51
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
52/117
52
Fuses and Circuit Breakers
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
53/117
53
The purpose of a fuse or circuit breaker
device is automatically to interrupt circuit
current in the event of fault or overloadconditions
E i t fl lt f
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
54/117
54
Excessive current may flow as a result of:
overload (excessive connected load)
short circuit between live and neutral
earth fault (live or neutral to earth)
Overload
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
55/117
55
Overload
(excessive connected load)
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
56/117
56
Under normal circumstances the fuse or
circuit breaker should operate before the
circuit cables reach a dangerously hightemperature
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
57/117
57
If the fuse or circuit breaker is to high for
the circuit, the cables may reach a dangerouslyhigh temperature resulting in fire
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
58/117
58
Short circuit
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
59/117
59
Phase and neutral conductors touching
Phase to neutral short resulting fromloose connections at a socket outletLarge fault current flows - fuse or circuit
breaker should operate
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
60/117
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
61/117
61
Combined main switch and r c d
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
62/117
62
Least sensitive of the two devices and protectscircuits feeding fixed equipment.
Combined main switch and r.c.d.
Earth fault
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
63/117
63
a fault condition that exists between liveconductors and earth
Excess current should cause fuse orcircuit breaker to operate
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
64/117
64
rewirable fuse -
most widely abused
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
65/117
65
Incorrect size of element
Most likely reason fordevice failing to operate
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
66/117
66
fuse element too large
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
67/117
67
a fuse failing to operate under
fault conditions may wellresult in fire
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
68/117
68
The Rewirable fuse is an antiquated
device. even with the correct
rating of fuse element it may not safelyinterrupt high levels of fault current
Cartridge fuses to BS 1361
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
69/117
69
Cartridge fuses to BS 1361
scattering of hot metal particles
contained within cartridge thusreducing fire risk duringoperation
operates much closer to itscurrent rating when compared tothe rewirable fuse
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
70/117
70
has the ability to interrupt high levels of faultcurrent
less likelihood of premature failure due to
oxidisation when compared to the rewirable
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
71/117
71
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
72/117
72
Selection of fuses used in consumer units
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
73/117
73
Circuit-breakers to BS EN 60898
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
74/117
74
Circuit breakers to BS EN 60898
most widely used type of
overcurrent protective device,particularly for domestic applications
Thermal-magnetic operation
thermal - overload
magnetic - short circuit conditions
Older miniature circuit breakers toBS 3871
Circuit-breakers to BS EN 60898
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
75/117
75
rating (A) application
6 lighting circuits
20 13A socket radial
32 13A socket rings
32 13A socket radial
45 cooker/shower circuits
3 bell transformers
16 immersion heaters
The Residual Current Device (r.c.d.)
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
76/117
76
The Residual Current Device (r.c.d.)
Provides protection against earth faults interms of:
electric shock, and
fire of an electric origin
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
77/117
77
Why bother with an r.c.d. when a fuse or circuit
breaker can provide protection against earth fault
conditions?
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
78/117
78
an r.c.d can operate in the region of milli-amps
in fact a r.c.d. rated at 30mA can provide
protection against electrocution
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
79/117
79
fuses and circuit breakers require relatively
high currents in order to operate
for example, for a 30A rewirable fuse requiresapproximately 200A to operate within a safe
time period
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
80/117
80
Types of r.c.d.
Socket outlet incorporating r.c.d. protection
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
81/117
81
Socket outlet incorporating r.c.d. protection
High level of personal
protection against shock,
particularly when using
portable electricalequipment outdoors
Domestic consumer unit with two r.c.d.s
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
82/117
82
Extensively used in conjunction with an earthelectrode earthing system
Providing personal protection
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
83/117
83
Second r.c.d. has greater sensitivity and isused to protect socket outlet circuits
g p p
Combined r.c.d. circuit breaker (RCBO)
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
84/117
84
single device providesprotection against both
overload, short circuit andearth fault currents
Combined r.c.d. circuit breaker (RCBO)
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
85/117
85
An r.c.d. is a device which can provide protection
against:
fire resulting from earth faults
earth faults where circuit resistance is too highfor protection by conventional devices, i.e.circuit breakers or fuses
where greater protection against electric shock,for example socket outlet circuits likely tosupply portable equipment outdoors
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
86/117
86
fuses and circuit breakers are totally unable to
provide this level of shock protection
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
87/117
87
What rating of r c d are generally available and
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
88/117
88
What rating of r.c.d. are generally available and
where would they be used?
as a guide
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
89/117
89
30mA for personal protectionsocket outlet circuits
100mA or above for protection
against fire
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
90/117
90
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
91/117
91
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
92/117
92
P
N
E
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
93/117
93
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
94/117
94
Correct polarity
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
95/117
95
Edison-screw
p y
Correct polarity of Edison-type screw
fittings essential if shock is to be avoided
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
96/117
96
Centre contact must always be connected
to the phase conductor of the supply
P
N
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
97/117
97
neutral
phase
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
98/117
98
Phase
Neutral
Phase and neutral connections reversed
Reversed polarity
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
99/117
99
A person removing an Edison-screw lamp
could receive a serious electric shock if
they touched the lamp thread before ithad completely been removed from the
fitting
Reversed polarity
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
100/117
100
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
101/117
101
The socket tester
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
102/117
102
useful but limited in its application
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
103/117
103
All lights green indicates correct polarity
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
104/117
104
red - red -green indicates P-E reversed
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
105/117
105
The socket tester will INDICATE
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
106/117
106
The socket tester will INDICATE
THE PRESENCE OF SUPPLY
IDNETIFY THE CORRECT POLARITY OF THEPHASE CONDUCTOR
THAT SOME FORM OF EARTH CONNECTION ISPRESENT AT THE SOCKET OUTLET
The socket tester will NOT INDICATE
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
107/117
107
The socket tester will NOT INDICATE
A HIGH RESISTANCE EARTH PATH
A REVERSED NEUTRAL
EARTH CONNECTION
AND ABOVE ALL
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
108/117
108
NEVER USE A SOCKET TESTER TO PROVETHAT A CIRCUIT IS ISOLATED, (dead).
AND ABOVE ALL
Earthing
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
109/117
109
In order to prevent electric shock the exposedmetalwork of electrical appliances, metal
conduit etc should be earthed.
In the majority of cases the earthing facility is
provided by the local electricity supplier.
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
110/117
110
Inadequate earthing arrangements may lead
to electric shock or death through electrocution
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
111/117
111
Earthing arrangements
Typical domestic intake
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
112/117
112main incoming earth
earth
terminal
consumer unitmeter
service cutout
Earth connection is obtained from supplierssheath (main incoming cable)
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
113/117
113
sheath (main incoming cable)
This method of earthing is still widely usedand is reliable
Modern earthing arrangement where the earth
is connected to the incoming neutral at the
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
114/117
114
is connected to the incoming neutral at theservice head
Rapidly becoming the most widely used
supply arrangement
Widely used in agricultural/rural areas.
Earthing relies on earth electrode (rod/spike)
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
115/117
115
Gradually being phased out wherever possible
Earthing relies on earth electrode (rod/spike)
Earth rod and typical enclosure
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
116/117
116
Earth rod and typical enclosure
Problems with earth electrodes
-
7/30/2019 WEEK 1 & 2 Inspection & Testing (Basic) (powerp point file)
117/117
generally does not provide a very good
earth return path
liable to corrosion and mechanical
damage