wave energy center -...
TRANSCRIPT
GRID
WAVE ENERGY CENTER
Technologies for connection of offshore
renewable power plants to the electrical system
Ana Díez
1oth may 2012
GRID
1. Introduction
3. Equipment/Layout/Configurations
2. Project references
4. Grid integration: FACTS and HVDC transmission
Agenda
1. Introduction
3. Equipment/Layout/Configurations
2. Project references
4. Grid integration: FACTS and HVDC transmission
Agenda
Actividades Principales
Barrow – Irish sea, UK
Contract Value: £9 M
Client & Operator: Barrow Offshore Wind Ltd. (Centrica & DONG Energy)
Completion Date: September 2006
Project Scope: 90 MW Offshore Wind Park with 30 Wind Turbine Generators (Vestas V90/3.0 MW)
Data: 20 m depth, 27 km HV sea cable
Alstom Grid Scope of Works:
− Electrical connection modelling and system studies
− Grid connection at Heysham − Module supply and fitout
• 132 kV & 33 kV GIS switchgear including protection
• Power transformer
• Relay and control panel suite room
• LVAC and DC plant room, refuge, mess and workshop modules
• Capacitor bank modules (2x 5 MVAr)
Robin Rigg – Irish Sea UK
Alstom Grid Scope of Works:
2 Separate platforms – Connected in 4 groups at
33kV to Offshore 132/33kV S/S
− Onshore 132kV Substation
− Offshore 132/33kV Substation
Contract Value: £15.2 M
Client & Operator: E.ON UK Solway Offshore Ltd. and E.ON UK Offshore Resources Ltd.
Completion Date: Spring 2009
Project Scope: 180 MW Offshore Wind Park total 60 Wind Turbine (Vestas V90/3.0 MW)
30 m depth, 12 km from the coast
Alpha Ventus - Germany
Contract Value: 7 M€
Client & Operator: DOTI GmbH (EON Climate&Renewables, Vattenfall Europe New Energy GmbH, EWE AG)
Completion Date: September 2008
Project Scope: 60 MW Offshore Wind Park with 12x5MW Wind Turbines
30m depth/45 km from coast
Alstoms Grid Scope of Works:
− 110/30kV substation on platform
− Turn-key delivery of topside including
• Protection and Control
• 110 kV & 30 kV GIS Switchgear
• 1 Hermetic Power transformer
• Cabling. Shunt reactors
• Auxiliary equipment /Diesel Generators
• Fire protection
• Commissioning
Offshore substation. Loading.
Offshore substation. Overview.
Client & operator: Wetfeet Offshore Windenergy GmbH
Forecasted completion date: September 2012
Project scope: 400 MW offshore wind farm with 80 wind turbine generators (AREVA Multibrid M5000)
Distance: 125 km from the coast
Contract scope (ALSTOM Grid scope in liaison with partner):
− Turnkey delivery of a self-floating and self-installing offshore substation platform including
• 155/33 kV power transformer (4x 120 MVA) • 170 kV & 33 kV GIS switchgear • Substation protection & control, • PACiS solution • Cabling on platform • AC/DC equipment • Emergency diesel generators • Boat landing and helicopter landing deck • Self-contained platform with large working deck • Erection & commissioning of substation (onshore and
offshore) • Manufacturing and fit-out of the hull including
substructure • Permanent accommodation facilities for up to 37
people • Onshore erection and offshore installation
2009 - Global Tech 1 - Germany
1. Introduction
3. Equipment/Layout/Configurations
2. Project references
4. Grid integration: FACTS and HVDC transmission
Agenda
Offshore substation main equipment
High voltage
switchgear (GIS)
Power step-up
Transformer HV/MV
Medium voltage
switchgear (GIS)
Power Transformers
Environmental, technical challenges:
− Weight and dimensions
− Corrosion protection:
• Cataphoretic painting
- Maintenance reduction
• Hermetic transformers: Expansion radiators instead of conservator and de-hydrating breather
• OLTC with vacuum chambers
• Integrated condition monitoring
High voltage substation
Environmental criteria:
− Footprint − Transformer connection by cable
Technical criteria
− Well proven/highly reliabe − Voltage level: 145, 170 or 220 kV − Integrated Protection&Control
system
Cost criteria:
− Configuration: Compromise high availability vs. investment cost
Offshore substation configuration
1. Introduction
3. Equipment/Layout/Configurations
2. Project references
4. Grid integration: FACTS and HVDC transmission
Agenda
Grid integration
- HVAC
- HVAC + FACTS
- HVDC
Selection criteria:
- Technical feasibility of HVAC (distance to the coast)
- Economics
- Grid Codes
Grid code compliance: Shunt compensation by STATCOM STATCOM to Duneill Wind Farm site in Ireland
13 pcs– 850 kW wind turbines ->
P = 11.05 MW
3x 2MVar SVC MaxSine modules in container -> Q= 6 MVar
for Grid Code
compliance
HVDC transmission
HVDC Benefits
20
Station
Cost
DC
Converter
Stations
AC
Stations
DC
AC
Break Even
Distance
Transmission
Distance
• Higher efficiency
• Increased power system reliability and security
• Improved power system transient and dynamic stability
• Limited short circuit level contribution
• Distance break-even point (HVDC vs. HVAC) Underground >30-60 km Submarine >100 km (additional DC platform)
InverterRectifier
F F
Receiving
End
Idc
Vdc
HVDC Connections - Offshore generation
DC cable
VSC VSC
Station 1
U AC
Network
Network
2
Offshore
generators
HVAC
platform
HVDC
platform
Onshore HVDC
station
Station 2
First projects of its kind have:
- Steep learning curves with fast transfer to new projects
- Harsh operational conditions need
• Increased corrosion protection for all systems
• Learning from other industries (Oil & Gas,
automotive,…)
- Weather dependent restricted access need
• Minimized offshore installation & service time
• Integrated service concepts with wind farm operators
- Future wind farms need offshore substations with
Innovations in technical design such as
-Self-floating Self-installing platforms and
-Integrated designs
Summary
ALSTOMs participation in OCEAN LIDER project
http://www.oceanlider.com
www.alstom.com
Typical Layout: Radial configuration (most common)
Ring configuration