wave energy center -...

26
GRID WAVE ENERGY CENTER Technologies for connection of offshore renewable power plants to the electrical system Ana Díez 1oth may 2012

Upload: hoangthien

Post on 18-Feb-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

GRID

WAVE ENERGY CENTER

Technologies for connection of offshore

renewable power plants to the electrical system

Ana Díez

1oth may 2012

Page 2: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

GRID

1. Introduction

3. Equipment/Layout/Configurations

2. Project references

4. Grid integration: FACTS and HVDC transmission

Agenda

Page 3: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

1. Introduction

3. Equipment/Layout/Configurations

2. Project references

4. Grid integration: FACTS and HVDC transmission

Agenda

Page 4: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

Actividades Principales

Page 5: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

Barrow – Irish sea, UK

Contract Value: £9 M

Client & Operator: Barrow Offshore Wind Ltd. (Centrica & DONG Energy)

Completion Date: September 2006

Project Scope: 90 MW Offshore Wind Park with 30 Wind Turbine Generators (Vestas V90/3.0 MW)

Data: 20 m depth, 27 km HV sea cable

Alstom Grid Scope of Works:

− Electrical connection modelling and system studies

− Grid connection at Heysham − Module supply and fitout

• 132 kV & 33 kV GIS switchgear including protection

• Power transformer

• Relay and control panel suite room

• LVAC and DC plant room, refuge, mess and workshop modules

• Capacitor bank modules (2x 5 MVAr)

Page 6: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

Robin Rigg – Irish Sea UK

Alstom Grid Scope of Works:

2 Separate platforms – Connected in 4 groups at

33kV to Offshore 132/33kV S/S

− Onshore 132kV Substation

− Offshore 132/33kV Substation

Contract Value: £15.2 M

Client & Operator: E.ON UK Solway Offshore Ltd. and E.ON UK Offshore Resources Ltd.

Completion Date: Spring 2009

Project Scope: 180 MW Offshore Wind Park total 60 Wind Turbine (Vestas V90/3.0 MW)

30 m depth, 12 km from the coast

Page 7: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

Alpha Ventus - Germany

Contract Value: 7 M€

Client & Operator: DOTI GmbH (EON Climate&Renewables, Vattenfall Europe New Energy GmbH, EWE AG)

Completion Date: September 2008

Project Scope: 60 MW Offshore Wind Park with 12x5MW Wind Turbines

30m depth/45 km from coast

Alstoms Grid Scope of Works:

− 110/30kV substation on platform

− Turn-key delivery of topside including

• Protection and Control

• 110 kV & 30 kV GIS Switchgear

• 1 Hermetic Power transformer

• Cabling. Shunt reactors

• Auxiliary equipment /Diesel Generators

• Fire protection

• Commissioning

Page 8: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

Offshore substation. Loading.

Page 9: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

Offshore substation. Overview.

Page 10: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

Client & operator: Wetfeet Offshore Windenergy GmbH

Forecasted completion date: September 2012

Project scope: 400 MW offshore wind farm with 80 wind turbine generators (AREVA Multibrid M5000)

Distance: 125 km from the coast

Contract scope (ALSTOM Grid scope in liaison with partner):

− Turnkey delivery of a self-floating and self-installing offshore substation platform including

• 155/33 kV power transformer (4x 120 MVA) • 170 kV & 33 kV GIS switchgear • Substation protection & control, • PACiS solution • Cabling on platform • AC/DC equipment • Emergency diesel generators • Boat landing and helicopter landing deck • Self-contained platform with large working deck • Erection & commissioning of substation (onshore and

offshore) • Manufacturing and fit-out of the hull including

substructure • Permanent accommodation facilities for up to 37

people • Onshore erection and offshore installation

2009 - Global Tech 1 - Germany

Page 11: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

1. Introduction

3. Equipment/Layout/Configurations

2. Project references

4. Grid integration: FACTS and HVDC transmission

Agenda

Page 12: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

Offshore substation main equipment

High voltage

switchgear (GIS)

Power step-up

Transformer HV/MV

Medium voltage

switchgear (GIS)

Page 13: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

Power Transformers

Environmental, technical challenges:

− Weight and dimensions

− Corrosion protection:

• Cataphoretic painting

- Maintenance reduction

• Hermetic transformers: Expansion radiators instead of conservator and de-hydrating breather

• OLTC with vacuum chambers

• Integrated condition monitoring

Page 14: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

High voltage substation

Environmental criteria:

− Footprint − Transformer connection by cable

Technical criteria

− Well proven/highly reliabe − Voltage level: 145, 170 or 220 kV − Integrated Protection&Control

system

Cost criteria:

− Configuration: Compromise high availability vs. investment cost

Page 15: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

Offshore substation configuration

Page 16: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

1. Introduction

3. Equipment/Layout/Configurations

2. Project references

4. Grid integration: FACTS and HVDC transmission

Agenda

Page 17: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

Grid integration

- HVAC

- HVAC + FACTS

- HVDC

Selection criteria:

- Technical feasibility of HVAC (distance to the coast)

- Economics

- Grid Codes

Page 18: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

Grid code compliance: Shunt compensation by STATCOM STATCOM to Duneill Wind Farm site in Ireland

13 pcs– 850 kW wind turbines ->

P = 11.05 MW

3x 2MVar SVC MaxSine modules in container -> Q= 6 MVar

for Grid Code

compliance

Page 19: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

HVDC transmission

Page 20: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

HVDC Benefits

20

Station

Cost

DC

Converter

Stations

AC

Stations

DC

AC

Break Even

Distance

Transmission

Distance

• Higher efficiency

• Increased power system reliability and security

• Improved power system transient and dynamic stability

• Limited short circuit level contribution

• Distance break-even point (HVDC vs. HVAC) Underground >30-60 km Submarine >100 km (additional DC platform)

InverterRectifier

F F

Receiving

End

Idc

Vdc

Page 21: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

HVDC Connections - Offshore generation

DC cable

VSC VSC

Station 1

U AC

Network

Network

2

Offshore

generators

HVAC

platform

HVDC

platform

Onshore HVDC

station

Station 2

Page 22: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

First projects of its kind have:

- Steep learning curves with fast transfer to new projects

- Harsh operational conditions need

• Increased corrosion protection for all systems

• Learning from other industries (Oil & Gas,

automotive,…)

- Weather dependent restricted access need

• Minimized offshore installation & service time

• Integrated service concepts with wind farm operators

- Future wind farms need offshore substations with

Innovations in technical design such as

-Self-floating Self-installing platforms and

-Integrated designs

Summary

Page 23: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

ALSTOMs participation in OCEAN LIDER project

http://www.oceanlider.com

Page 24: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

www.alstom.com

Page 25: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

Typical Layout: Radial configuration (most common)

Page 26: WAVE ENERGY CENTER - oteo.inegi.up.ptoteo.inegi.up.pt/resources/154_18_ana_diez_-_oteo_conference... · WAVE ENERGY CENTER Technologies for connection of offshore renewable power

Ring configuration