wastewater collection systems division 50 - … · aashto m45 sand for cement mortar aashto m306...

72
DESIGN AND CONSTRUCTION STANDARDS WASTEWATER COLLECTION SYSTEMS DIVISION 50 JOINT BASE ELMENDORF RICHARDSON JANUARY 2011 36010 ARCTIC VALLEY RD. JBER, ALASKA PO B OX 5469 JBER, AK 99505 (907) 4285355 FAX WWW. DOYONUTILITIES. COM

Upload: duongnhi

Post on 28-Jul-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGN AND CONSTRUCTION STANDARDS   

WASTEWATER COLLECTION SYSTEMS DIVISION 50 

  

JOINT BASE ELMENDORF RICHARDSON JANUARY 2011 

  

     

36010 ARCTIC VALLEY RD.  JBER, ALASKA  

  

  

PO  BOX  5469 JBER, AK  99505 

(907) 428‐5355 FAX      

WWW.DOYONUTILITIES.COM

Page 2: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATER‐JBERDIVISION50

TABLEOFCONTENTS

January2011 iJBER–Division50

Section 50.01     GENERAL ........................................................................................................................ 1 

Article 1.1     Scope of Work ............................................................................................................. 1 Article 1.2     Safety .......................................................................................................................... 1 Article 1.3     Applicable Standards .................................................................................................. 1 Article 1.4     Inspection, Notices, and Offical Communications ...................................................... 3 Article 1.5     Utility Locations and Excavation Permit Requirements .............................................. 3 Article 1.6     Hot Work Permits ....................................................................................................... 4 Article 1.7     Wastewater Shutdown Scheduling and Duration ....................................................... 4 Article 1.8     Submittals ................................................................................................................... 4 Article 1.9     Permanent Materials Furnished By Doyon Utilities                       And by Contractor ....................................................................................................... 5 Article 1.10   Other Division Requirements ..................................................................................... 5 

Section 50.02      GRAVITY SEWER LINES AND FORCE MAINS ................................................................. 8 

Article 2.1     General ........................................................................................................................ 8 Article 2.2     Material ....................................................................................................................... 8 Article 2.3     Construction .............................................................................................................. 11 Article 2.4     Inspection, Cleaning, Flushing, and Testing .............................................................. 18 

Section 50.03      SANITARY SEWER MANHOLES ................................................................................... 22 

Article 3.1     General ...................................................................................................................... 22 Article 3.2     Material ..................................................................................................................... 22 Article 3.3     Construction .............................................................................................................. 23 

Section 50.04       SANITARY SEWER DROP CONNECTIONS ................................................................... 26 

Article 4.1     General ...................................................................................................................... 26 Article 4.2     Material ..................................................................................................................... 26 Article 4.3     Construction .............................................................................................................. 26 

Section 50.05      SANITARY SEWER CLEANOUTS ................................................................................... 27 

Article 5.1     General ...................................................................................................................... 27 Article 5.2     Material ..................................................................................................................... 27 Article 5.3     Construction .............................................................................................................. 27 

Section 50.06      SANITARY SEWER LIFT STATIONS ............................................................................... 29 

Article 6.1     General ...................................................................................................................... 29 Article 6.2     Material ..................................................................................................................... 29 Article 6.3     Construction .............................................................................................................. 29 

Section 50.07       FORCE MAIN PERMANENT VENTS ............................................................................. 30 

Article 7.1     General ...................................................................................................................... 30 Article 7.2     Material ..................................................................................................................... 30 Article 7.3     Construction .............................................................................................................. 30 

 

Page 3: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATER‐JBERDIVISION50

TABLEOFCONTENTS

January2011 iiJBER–Division50

Section 50.08       POLYETHYLENE ENCASEMENT ................................................................................... 31 

Article 8.1     General ...................................................................................................................... 31 Article 8.2     Material ..................................................................................................................... 31 Article 8.3     Construction .............................................................................................................. 31 

Section 50.09        SANITARY SEWAGE BYPASS PUMPING .................................................................... 32 

Article 9.1     General ...................................................................................................................... 32 Article 9.2     Construction .............................................................................................................. 32 

Section 50.10        NEW CONNECTIONS TO EXISTING SANITARY SEWER MANHOLES .......................... 34 

Article 10.1    General .................................................................................................................... 34 Article 10.2    Material.................................................................................................................... 34 Article 10.3    Construction ............................................................................................................ 34 

Section 50.11       EXISTING MANHOLE REHABILITATION OR REMOVAL .............................................. 36 

Article 11.1    General .................................................................................................................... 36 Article 11.2    Material.................................................................................................................... 36 Article 11.3    Construction ............................................................................................................ 36 

Section 50.12    ADJUST EXISTING SANITARY SEWER MANHOLE                  FRAMES AND COVERS AND EXISTING MANHOLE                  CONES TO FINISH .......................................................................................................... 38 

Article 12.1    General .................................................................................................................... 38 Article 12.2    Material.................................................................................................................... 38 Article 12.3    Construction ............................................................................................................ 38 

Section 50.13       ADJUSTING EXISTING CLEANOUTS TO FINISH GRADE .............................................. 39 

Article 13.1    General .................................................................................................................... 39 Article 13.2    Material.................................................................................................................... 39 Article 13.3    Construction ............................................................................................................ 39 

Section 50.14    REMOVE AND DISPOSE OF EXISTING CESSPOOLS                   OR SEPTIC TANKS AND CONNECT TO NEW SEWER SERVICES .................................... 40 

Article 14.1    General .................................................................................................................... 40 Article 14.2    Material.................................................................................................................... 40 Article 14.3    Construction ............................................................................................................ 40 

Section 50.15       ABANDON PIPE IN PLACE .......................................................................................... 42 

Article 15.1    General .................................................................................................................... 42 Article 15.2    Material.................................................................................................................... 42 Article 15.3    Construction ............................................................................................................ 42 

 

 

Page 4: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATER‐JBERDIVISION50

TABLEOFCONTENTS

January2011 iiiJBER–Division50

Section 50.16      WASTEWATER COLLECTION SYSTEM STANDARD DETAILS ....................................... 43 

Detail  50‐1     Sanitary Manhole ‐ Type A ‐ Pipe 8” to 24”  ........................................................... 44 Detail  50‐2     Sanitary Manhole ‐ Type B ‐ Pipe Dia 30” to 36 ...................................................... 45 Detail  50‐3     Sanitary Manhole ‐ Type C ‐ Pipe Dia 40” to 48” .................................................... 46 Detail  50‐4     Type A and B Manhole Base Plan ........................................................................... 47 Detail  50‐5     Manhole Heights ..................................................................................................... 48 Detail  50‐6     Manhole Step .......................................................................................................... 49 Detail  50‐7     Sewer Service Connect for On‐Site Lift Station 1‐1/2” and 2” ............................... 50 Detail  50‐8     Manhole Cover ....................................................................................................... 51 Detail  50‐9     Manhole Frame ....................................................................................................... 52 Detail  50‐10   Watertight Manhole Ring ....................................................................................... 53 Detail  50‐11   Manhole Drop Connection ..................................................................................... 54 Detail  50‐12   Typical Beaver Slide Manhole ................................................................................. 55 Detail  50‐13   Sanitary Sewer Service (Complete) ........................................................................ 56 Detail  50‐14   Lateral Connection to Concrete Pipe ...................................................................... 57 Detail  50‐15   Service Riser/Top Entry .......................................................................................... 58 Detail  50‐16   Sanitary Sewer Service Connection (R.O.W. Only) ................................................. 59 Detail  50‐17   Sanitary Sewer Cleanout Cover .............................................................................. 60 Detail  50‐18   Sanitary Cleanout ................................................................................................... 61 Detail  50‐19   Special Manhole and Cleanout Detail (inside protective well radius) .................... 62 Detail  50‐20   Special Manhole and Cleanout Detail (inside protective well radius) .................... 63 Detail  50‐21   Special Manhole and Cleanout Detail (inside protective well radius) .................... 64 Detail  50‐22   Horse Shoe Sanitary Sewer Manhole Detail ........................................................... 65 Detail  50‐23   Contractor Field Installation Notes Sanitary Example ............................................ 66 Detail  50‐24   Manhole Cone Adjustment ..................................................................................... 67 Detail  50‐25   Manhole Ring Adjustment  ..................................................................................... 68  

      

Page 5: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 1JBER–Division50

SECTION50.01GENERAL

Article1.1ScopeofWork

The  Work  covered  by  these  Specifications  consists  of  providing  all  labor,  supervision, 

equipment,  supplies,  material,  transportation,  handling  and  storage,  and  performing  all 

operations necessary to complete new construction, modification, and/or repair of wastewater 

collection  facilities  operated  by  Doyon  Utilities  LLC  on  Joint  Base  Elmendorf  Richardson, 

hereafter referred to as JBER. 

All Division 50 shall be  in accordance with  the Plans, Special Provisions, Standard Details, and these Specifications. 

Article1.2Safety

The Contractor is solely responsible for all safety and safety compliance.  Safety includes, but is not limited to: worker and jobsite safety, safety of Doyon Utilities employees and agents, other JBER  personnel  and  property,  and  the  general  public,  safety  of  the  fish,  game,  and  the environment, and wastewater collection system and other utility safety. 

Wastewater  collection  system  safety  includes,  but  is  not  limited  to,  avoidance  of  cross‐connections between wastewater collection systems and potable water systems, and  integrity of wastewater  collection  systems  to  avoid  direct  health  hazards,  groundwater  pollution,  and surface water pollution. 

Article1.3ApplicableStandards

The  latest  revisions of  the  following  standards of  the American Association  for State Highway 

and  Transportation Officials  (AASHTO),  the American National  Standards  Institute  (ANSI),  the 

American  Society  of  Testing  and Materials  (ASTM),  the  American Water Works  Association 

(AWWA),  and  the  International  Code  Council  (ICC)  are  hereby  made  a  part  of  these 

Specifications.  

AASHTO M45  Sand for Cement Mortar 

AASHTO M306  Standard  Specification  for  Drainage,  Sewer,  Utility,  and  Related 

Castings 

ASTM A48  Specifications for Gray Iron Castings 

ASTM A185  Standard Specification  for Steel Welded Wire Reinforcement, Plain, for Concrete 

ASTM A615  Standard Specification for Deformed and Plain Carbon‐Steel Bars for Concrete Reinforcement 

Page 6: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 2JBER–Division50

 

ASTM A746  Standard Specification for Ductile Iron Gravity Sewer Pipe 

ASTM C150  Specification for Portland Cement 

ASTM C478 Specification for Precast Reinforced Concrete Manhole Sections 

ASTM C923 Standard Specification for Resilient Connectors Between Reinforced Concrete Manhole Structures, Pipes, and Laterals 

ASTM D2321 Standard Practice for Underground Installation of Thermoplastic Pipe for Sewers and Other Gravity‐Flow Applications 

ASTM D3035 Specification  for Polyethylene  (PE) Plastic Pipe  (SDR‐PR) Based on Controlled Outside Diameter 

ASTM D3261  Specification  for  Butt  Heat  Fusion  Polyethylene  (PE)  Plastic Fittings for Polyethylene (PE) Plastic Pipe and Tubing 

ASTM D3350  Specification  for  Polyethylene  Plastics  Pipe  and  Fittings Materials 

ASTM F1055  Standard  Specification  for  Electrofusion  Type  Polyethylene  Fittings  for Outside Diameter Controlled Polyethylene Pipe and Tubing 

ASTM F2620  Standard Practice  for Heat Fusion  Joining of Polyethylene Pipe and Fittings 

AWWA C104/ ANSI A21.4 

Cement‐Mortar  Lining  for  Ductile‐Iron  Pipe  and  Fittings  for Water 

AWWA C105/ ANSI A21.5 

Polyethylene Encasement for Ductile Iron Piping for Water and Other Liquids 

AWWA C110/ ANSI A21.10 

Ductile‐Iron  and  Gray‐Iron  Fittings,  3  in.  Through  48  in.,  for Water and Other Liquids 

AWWA C111/ ANSI A21.11 

Rubber‐Gasket  Joints  for  Ductile‐Iron  and  Gray‐Iron  Pressure Pipe and Fittings 

AWWA C151/ ANSI A21.51 

Ductile‐Iron  Pipe,  Centrifugally  Cast  in Metal Molds,  or  Sand‐Lined Molds, for Water or Other Liquids 

ICC IPC International  Plumbing  Code,  latest  edition  adopted  by  the Municipality of Anchorage, and current local amendments 

Page 7: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 3JBER–Division50

Article1.4Inspection,Notices,andOfficialCommunications

All work activities covered under this section,  including but not  limited to traffic maintenance, storm water pollution prevention, construction, hot  tapping, alignment and debris  inspection, flushing  and  cleaning,  pressure  testing,  continuity  testing,  wastewater  service  shutdowns, temporary  bypass  pumping,  on‐site  system  abandonment,  pipe  abandonment  in  place,  and punch  list  work,  are  subject  to  inspection  and  acceptance  by  Doyon  Utilities  LLC.    Work completed without inspection by Doyon Utilities’ Authorized Representative shall be subject to rejection. 

The  Contractor  shall  schedule  hot  tapping,  alignment  and  debris  inspection,  flushing  and cleaning, pressure testing, continuity testing, wastewater service shutdowns, temporary bypass pumping  start‐up, on‐site  system abandonment, pipe abandonment  in place, punch  list work, and similar activities to occur on non‐holiday weekdays during normal working hours of 7 AM to 4 PM to facilitate inspection by Doyon Utilities’ Authorized Representative. 

Written notice of  traffic  lane closures and wastewater  shutdowns  shall be provided  to Doyon Utilities LLC by the Contractor at least fourteen (14) calendar days in advance. 

Written notice of traffic  lane closures shall be provided to the JBER Fire Department and JBER Police Department by the Contractor at least fourteen (14) calendar days in advance. 

Written  notice  of  traffic  maintenance  (excluding  lane  closure  work),  storm  water  pollution prevention  activities,  construction,  pressure  testing,  continuity  testing,  wastewater  service shutdowns,  temporary  bypass  pumping,  on‐site  system  abandonment,  pipe  abandonment  in place,  punch  list work,  and  similar  activities  requiring  inspection  shall  be  provided  to Doyon Utilities  LLC by  the Contractor  at  least  five  (5)  calendar days prior  to beginning  any of  these operations.  Failure to provide the required notice shall be grounds for issuance of a stop‐work order and/or complete rejection of the work. 

For wastewater service shutdowns and similar activities affecting wastewater system customers, first written notice of these activities, acceptable to Doyon Utilities’ Authorized Representative, shall be provided by  the Contractor  to all affected customers at  least seven  (7) calendar days prior to beginning any of these activities.  A second written notice of these activities, acceptable to Doyon Utilities’ Authorized Representative, shall be provided by the Contractor to all affected customers at least 24‐hours prior to beginning any of these activities. 

To be considered official and binding, all communication from and to Doyon Utilities LLC shall be in writing. 

Article1.5UtilityLocationsandExcavationPermitRequirements

The Contractor  shall place a  telephone,  fax, or on‐line  locate  request with Alaska Digline  Inc. (Anchorage telephone ‐ 278‐3121 or 811, statewide telephone ‐ 1‐800‐478‐3121, statewide fax – 1‐907‐278‐0696, on‐line – http://www.akonecall.com/).  Documentation of the Alaska Digline request  shall be provided  to Doyon Utilities’ Authorized Representative.   The Contractor  shall coordinate with utility company locator personnel to locate all existing utilities before digging. 

Page 8: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 4JBER–Division50

In addition  to obtaining utility  locations  through Alaska Digline  Inc.,  the Contractor obtain an excavation permit signed by all appropriate JBER departments, and provide a copy of the fully executed  excavation  permit  to  Doyon  Utilities’  Authorized  Representative.    A  minimum  of fourteen  (14) calendar days shall be allowed by  the Contractor  for complete processing of an excavation  permit.    The  Contractor  shall  comply with  all  requirements  of  the  fully  executed excavation permit. 

Article1.6HotWorkPermitRequirements

For any activity producing open  flames, or heat or  sparks  sufficient  to cause  combustion,  the Contractor obtain a hot work permit signed by the JBER Fire Department, and provide a copy of the fully executed hot work permit to Doyon Utilities’ Authorized Representative.  A minimum of fourteen (14) calendar days shall be allowed by the Contractor for complete processing of a hot work permit.  The Contractor shall comply with all requirements of the fully executed hot work permit. 

Article1.7WastewaterShutdownSchedulingandDuration

Scheduling and durations of wastewater  service  shutdowns  shall be  subject  to acceptance by Doyon Utilities’ Authorized Representative.   No wastewater  service  shutdown  shall  exceed  6 hours  in duration  in  any  24‐hour period.   Residential wastewater  service  shutdowns  shall be started and completed on non‐holiday weekdays between  the hours of 9 AM  to 3 PM.   Non‐residential wastewater  service  shutdowns  shall be  started and completed on days and during hours  determined  by  Doyon  Utilities’  Authorized  Representative  to  minimize  adverse consequences on JBER operations. 

Article1.8Submittals

The Contractor  shall provide paper  submittals or  electronic  submittals,  at  the option of Doyon Utilities’  Authorized  Representative,  for  review  and  acceptance  by  Doyon  Utilities.    Duplicate paper  submittals  shall  be  supplied  in  the  quantities  requested  by  Doyon  Utilities’  Authorized Representative.  Submittals shall clearly document compliance with Contract requirements to the satisfaction of Doyon Utilities’ Authorized Representative.   Any materials ordered  and/or work done in advance of written acceptance of submittals by Doyon Utilities’ Authorized Representative is subject to rejection. 

Submittals for Doyon Utilities review and acceptance are required for the following items. 

1. All permanent materials. 

2. Hot tap supervisor resume. 

3. Temporary bypass pumping plans. 

4. Work Site Traffic Supervisor certification and resume. 

5. Traffic Control Plans. 

Permanent material submittals shall be provided to Doyon Utilities’ Authorized Representative at  least thirty  (30) calendar days prior to ordering of materials.   Other submittals  listed above 

Page 9: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 5JBER–Division50

shall be provided to Doyon Utilities’ Authorized Representative at  least fourteen  (14) calendar days prior to the activity covered by the submittal. 

Doyon Utilities’ Authorized Representative  reserves  the  right  to  request additional  submittals for other Contractor procedures and personnel qualifications. 

Article1.9PermanentMaterialsFurnishedbyDoyonUtilitiesandbyContractor

Doyon Utilities may furnish some permanent materials on some projects.   When Doyon Utilities does  furnish permanent material, a  list of  these Doyon Utilities’‐provided permanent materials, and locations where these Doyon Utilities’‐provided materials shall be received by the Contractor, will be provided with the Request for Proposal and/or the Contract.  The Contractor shall perform a  complete  take‐off  of  all  permanent materials  required  for  the  project.    The  Contractor  shall furnish any and all permanent materials not supplied by Doyon Utilities, in order to complete the Project  in  accordance  with  the  Plans,  Standard  Details,  Special  Provisions,  and/or  these Specifications. 

The Contractor shall be responsible  for receiving  inspecting, and  inventorying Doyon Utilities’‐provided materials  at  locations  specified  in  the  Bidding Documents,  notifying Doyon Utilities Authorized  Representative  of  damage,  shortages,  etc,  loading  as  required,  delivery  to  the jobsite, and unloading at  the  jobsite.   Materials damaged during  transportation  to  the  jobsite and/or unloading at the jobsite shall be replaced at Contractor expense. 

Any surplus Doyon Utilities’‐provided materials not used on a project shall remain the property of Doyon Utilities, and shall be delivered by the Contractor to the Doyon Utilities storage yard and  carefully off‐loaded  and  stored on Contractor‐provided wooden pallets or other  suitable dunnage. 

Article1.10OtherDivisionRequirements

Except as specifically stated otherwise  in the various Sections of this Division 50, the following other Divisions and Sections of these Standard Specifications are incorporated by reference into all Sections of Division 50: 

A.  Earthwork and Related Activities 

The  Contractor  shall  provide  storm  water  pollution  prevention  plans  and  Best Management  Practices  in  accordance  with  Division  20  –Standard  Construction Specifications for Earthwork. 

The Contractor shall clear, grub, and strip to the limits shown on the Plans or as directed by Doyon Utilities’ Authorized Representative in accordance with Division 20. 

The Contractor  shall  remove existing Portland  cement  concrete  sidewalk, apron,  curb and  gutter,  and/or  concrete  similar  structures,  and  asphalt  pavement  in  accordance with Division 20. 

Page 10: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 6JBER–Division50

The  Contractor  shall  provide  all  excavation,  bedding,  classified  fill  and  backfill, backfilling, compaction, and  incidentals as necessary to  install sanitary sewer  lines and appurtenances in accordance with Division 20. 

The Contractor shall provide casing pipe as required in accordance with Division 20. 

The Contractor shall dispose of excess and unsuitable material as required in accordance with Division 20. 

The Contractor shall provide leveling course as required in accordance with Division 20. 

B.  Surface Restoration 

The  Contractor  shall  provide  3,500‐psi  design  strength  Portland  cement  concrete,  if required for surface restoration, in accordance with Division 30 ‐ Standard Construction Specifications for Portland Cement Concrete. 

The  Contractor  shall  provide  Class  E  asphalt  pavement,  if  required  for  surface restoration,  in  accordance with Division  40  ‐  Standard Construction  Specifications  for Asphalt Surfacing. 

The  Contractor  shall  provide  topsoil  and  hydroseeding,  if  required  for  surface restoration,  in  accordance with Division  75  ‐  Standard Construction  Specifications  for Landscaping Improvements. 

C.  Traffic Maintenance 

The Contractor is solely responsible to provide all traffic maintenance for vehicular, non‐motorized, and pedestrian  traffic.   All  traffic maintenance  shall be  in accordance with the Division 70 ‐ Standard Construction Specifications, Miscellaneous, and the Manual of Uniform Traffic Control Devices,  latest edition adopted by State of Alaska, and current local amendments.   For any operations  involving disruption of normal  traffic  flow,  the Contractor  shall  provide  Traffic  Control  Plans  for  review  and  acceptance  by  Doyon Utilities’  Authorized  Representative.    Traffic  Control  Plans  shall  be  provided  at  least fourteen  (14)  calendar days prior  to beginning  any operations  involving disruption of normal traffic  flow.   Acceptance of Traffic Control Plans by Doyon Utilities’ Authorized Representative is required prior to any operations involving disruption of normal traffic flow. 

D.  As‐Built Drawings 

The  Contractor  shall  maintain  as‐built  drawings  in  accordance  with  Division  65  ‐ Standard  Construction  Specifications  for  JBER  Construction  Surveys.    The  as‐built drawings  shall  be  up‐dated  weekly  by  the  Contractor  to  the  satisfaction  of  Doyon Utilities’ Authorized Representative.  As‐built drawings shall include; 

1. GPS coordinates and invert and rim elevations for all manholes and cleanouts. 

Page 11: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 7JBER–Division50

2. GPS coordinates and invert elevations for all buried stub‐out and service ends. 

3. GPS  coordinates  and  invert  elevations  for  all  service  line  alignment  changes, service line clean‐outs, and points at which service lines enter buildings. 

4. GPS coordinates and invert elevations for all force main pipe bends, force main points of curvature and tangency and at even 50‐foot and 100‐ foot stations  in horizontal curves.  

5. GPS  coordinates  and  invert  elevations  for  all  tees  and  crosses  for  future connection. 

6. GPS coordinates, elevations, and sizes for all pipe abandoned in place. 

7. Other  locations  called  out  in  these  Specifications  or  in  Section  65.02,  or requested by Doyon Utilities’ Authorized Representative. 

GPS coordinates shall be  to  the accuracy specified  in  the Request  for Proposal and/or Contract. 

Page 12: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 8JBER–Division50

SECTION50.02GRAVITYSEWERLINESANDFORCEMAINS

Article2.1General

The  Work  under  this  Section  includes  construction  of  gravity  sewer  mains,  gravity  sewer 

services, and force mains for wastewater collection systems. 

Refer to Section 50.01 for additional general requirements. 

Article2.2Material

A.  Line Sizes and Materials 

Gravity  sewer  mains  shall  be  minimum  8‐inch  nominal  diameter  and  shall  be constructed of ductile iron pipe. 

Gravity  sewer  services  shall  be  minimum  4‐inch  nominal  diameter  and  shall  be constructed of ductile iron pipe. 

Sanitary sewer force mains 3‐inch nominal diameter and  larger shall be constructed of ductile iron pipe or HDPE pipe. 

Sanitary sewer force mains 2‐inch nominal diameter and smaller shall be constructed of copper tubing. 

B.  Ductile Iron Pipe for Gravity Sewer Mains and Services 

Ductile iron pipe shall conform to the requirements of AWWA C151, Class 50, with cement mortar lining conforming to the requirements of AWWA C104/ANSI A24.1. 

C.  Ductile Iron Pipe for Sanitary Sewer Force Mains 

Ductile iron pipe shall conform to the requirements of AWWA C151, Class 52, with cement mortar lining conforming to the requirements of AWWA C104/ANSI A24.1. 

D.  Ductile Iron Pipe Fittings, Gaskets, Joint Restraints, and Bolting Materials 

Fittings  shall be  a minimum of 250 pounds pressure  rating, mechanical  joint,  cement lined, either cast  iron or ductile  iron.   All fittings shall conform to the requirements of AWWA C110/ANSI A21.10.   

Rubber gasket joints for ductile iron pipe and fittings shall conform to the requirements of AWWA C111/ANSI A21.11.  

Mechanical  joint  restraint  shall  be  provided  by  “EBAA  Iron MEGALUG®”  or  “Romac Industries RomaGrip” mechanical joint restraining glands, or Doyon Utilities’ Authorized Representative accepted equal.   Push‐on  joint restraint shall be provided by “U.S. Pipe 

Page 13: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 9JBER–Division50

Field LOK®” gaskets or Doyon Utilities’ Authorized Representative accepted equal. 

All mechanical  joint  T‐bolts  and  nuts  supplied  with  fittings  and  appurtenances  shall conform  to ASTM A242 weathering steel.   All T‐bolts and nuts shall be  factory‐coated with a blue  fluoropolymer  coating  for  corrosion  resistance.   T‐bolt  lengths  shall be of sufficient length that, when a bolt‐up is complete, each bolt extends completely through and at least 1/8‐inch beyond the nut, all around. 

E.  Transition Couplings for Connection of Existing to New Gravity Sewer Lines 

Transition  couplings  shall  be  “Romac  Style  501”  or  Doyon  Utilities’  Authorized 

Representative  accepted  equal, with  gaskets  as necessary  to match  existing  and new 

piping diameters. 

F.  Standard Ductile Iron Gravity Sewer Service Connections to Mains 

Standard ductile  iron gravity  sewer  service  connections  to mains  (including all gravity 

sewer service connections to mains other than deep service riser connections) shall be 

made  with  “Romac  Style  CB  Sewer  Saddles”  or  Doyon  Utilities’  Authorized 

Representative accepted equals. 

G.  Deep Service Riser Ductile Iron Gravity Sewer Service Connections to Mains 

Deep service riser connections to new gravity sewer mains shall be made with standard reducing tees, main size by 4‐inch or 6‐inch branch, 250‐PSI pressure rating, mechanical joint, cement lined, either cast iron or ductile iron.  Reducing tees shall conform to the requirements of AWWA C110/ANSI A21.10. 

Deep  service  riser  connections  to  existing  gravity  sewer  mains  shall  be  made  with 

tapping sleeve kits for ductile  iron main sizes from 8‐inch to 24‐inch nominal diameter 

and branch sizes of 4‐inch or 6‐inch nominal diameter.  Tapping sleeve kits shall include 

a two‐part full encirclement shell, an ANSI B16.5 Class 150 flanged outlet, test plug, and 

all  necessary  bolting  and  gasket materials  for  complete  installation.    The  shell,  lifter 

bars,  armors,  branch  outlet,  test  plug,  and  all  bolting  materials  shall  be  Type  304 

stainless  steel.    The  flange  shall  be  ductile  iron, ASTM  536‐80, Grade  65‐45‐12.    The 

wrap‐around shell gasket and flange gasket shall be virgin SBR.  Tapping sleeve kits shall 

be  “Romac  Industries Ductile+Plus  SST” or Doyon Utilities’ Authorized Representative 

approved equal. 

Deep  service  riser  pipe  flanges  for  existing  gravity  sewer mains  shall  be made with 

restrained  flange  coupling  adapters,  4‐inch  or  6‐inch  nominal  diameter,  ductile  iron 

ASTM A563, Grade 65‐45‐12,  fusion bonded epoxy coated and  lined, ANSI 16.5B Class 

150  flange  drilling,  “Romac  RFCA”  or  Doyon  Utilities’  Authorized  Representative 

accepted equal.   

 

Page 14: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 10JBER–Division50

Rubber flange gaskets shall conform to the requirements of AWWA C111/ANSI A21.11. 

Flange  bolts  shall  be  ASTM  A307B  heavy  hexagonal,  and  nuts  shall  be  ASTM  A563A 

heavy hexagonal.   All  flange bolt diameters  shall be 1/8‐inch  smaller  than  flange bolt 

hole  diameters.   All  flange  bolts  shall  be  of  sufficient  length  that, when  a  bolt‐up  is 

complete, each bolt extends completely through and at  least 1/8‐inch beyond the nut, 

all around.  If stud bolts are used for flange bolt‐up, the same length criteria shall apply 

to each end of each stud bolt. 

H.  Ductile Iron Force Main Connections to Manholes 

Connections of ductile iron force mains to manholes shall be made with “A‐LOK Z‐LOC” 

pipe‐to‐manhole waterstop connectors per Section 50.03 – Sanitary Sewer Manholes. 

I.  Continuity Straps and Test Leads for Ductile Iron Force Mains 

Continuity  straps  and  test  leads  shall  be  stranded Number  2 AWG  copper wire with HMWPE insulation suitable for direct burial. 

J.  High Density Polyethylene Pipe (HDPE) and Fittings 

High density polyethylene pipe (HDPE) and fittings shall be manufactured in accordance with ASTM D3035.  HDPE shall be manufactured from PE4710 polyethylene compounds that meet  or  exceed  ASTM D3350  Cell  Classification  445574.    HDPE  pipe  and  fitting material  compound  shall  contain  color  and  ultraviolet  (UV)  stabilizer  meeting  or exceeding  the  requirements  of  Code  C  per  ASTM  D3350.      Butt  fusion  fittings  shall comply with ASTM D3261.  Electro‐fusion couplings and fittings shall comply with ASTM F1055.  All fittings shall have pressure class ratings not less than the pressure class rating of the pipe to which they are joined.   HDPE pipe and fittings shall be SDR11 or heavier wall. 

K.  HDPE Force Main Connections to Manholes 

Connections of HDPE force mains to manholes shall be made with “A‐LOK Z‐LOC” pipe‐

to‐manhole waterstop connectors per Section 50.03 – Sanitary Sewer Manholes. 

L.  Trace Wire and Trace Wire Accessories for HDPE Pipe 

Trace wire  shall be  #12  solid  copper wire with HMWPE  insulation.    Trace wire  splice connectors shall be copper compression type, “Thomas & Betts C‐Tap, Color Key Red“ or Doyon Utilities’ Authorized Representative accepted equal.    Insulation  for splices shall be  125‐mil  by  3 ½‐inch  by  4 ½‐inch  “3M  Vinyl Mastic  Pad  2200”,  or Doyon Utilities’ Authorized Representative accepted equal. 

Page 15: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 11JBER–Division50

M.  Copper Tubing for Force Mains 

Copper tubing shall be Type K soft drawn ASTM B75 seamless tubing. 

N.  Copper Tubing Force Main Connections to Mains 

Connections  of  copper  tubing  force mains  to  gravity  sewer mains  shall  be made  in accordance with the Standard Details 

O.  Thaw Wire for Copper Tubing Force Mains 

Thaw  wire  shall  be  stranded  Number  2  AWG  copper  wire  with  HMWPE  insulation suitable for direct burial. 

P.  Detectable Underground Warning Tape 

Detectable underground warning  tape shall be 5‐mil by 6‐inch wide aluminum backed green tape with the words “Caution Buried Sewer Line Below”.  Detectable underground warning  tape  shall be  “Seton” or Doyon Utilities’ Authorized Representative accepted equal. 

Article2.3Construction

A.  General 

B.  Materials Delivery, Handling, and Temporary Storage 

Pipe and appurtenances  shall be handled  in  such a manner  to ensure delivery  to  the trench  in a sound, undamaged condition.   Particular care shall be taken not to damage the pipe, pipe coating, or  lining.   Before  installation, the pipe and appurtenances shall be  examined  for  defects  and/or  damage  by  the  Doyon  Utilities’  Authorized Representative. 

On‐site storage of pipe and other materials shall be to the satisfaction of Doyon Utilities’ Authorized Representative to avoid inconvenience and/or potential safety hazards. 

Rubber gaskets shall be protected from freezing temperatures or direct sunlight.  

C.  Removal and Off‐Site Disposal Sewage‐Saturated or Contaminated Soil 

The Contractor shall remove and dispose of all sewage‐saturated or contaminated soils 

encountered within the trench area.   Sewage‐saturated soils shall not be re‐used as fill 

material anywhere on JBER, but shall be disposed of at a disposal  location directed by 

Doyon Utilities’ Authorized Representative. 

 

 

Page 16: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 12JBER–Division50

D.  General Sewer Line Installation Requirements 

All ductile and cast  iron pipe and fittings shall be encased  in one  layer of polyethylene encasement in accordance with Section 50.08 ‐ Polyethylene Encasement. 

All pipe shall be bedded per Division 20. 

All  adjustments  to  line  and  grade  shall  be  done  by  removing  undisturbed  earth  as 

required or filling with suitable compacted bedding material under the pipe, but not by 

forcing the pipe down or blocking or wedging the pipe up. 

Water  shall  be  kept  out  of  the  trench  by  pumping,  if  necessary,  until  the  jointing  is completed.   

Pipe and appurtenances  shall be carefully  lowered  into  the  trench by means of  fabric slings, wire rope chokers, rope tag lines, and other suitable lifting and rigging gear.  Pipe placement,  including on‐site handling,  installing  in  the  trench, and backfilling,  shall be done  to  the  satisfaction  of  Doyon  Utilities’  Authorized  Representative  to  prevent damage  to  the  pipe  as  well  as  ductile  iron  pipe  cement  lining  and  polyethylene encasement.   

When  work  is  not  in  progress,  open  ends  of  the  pipe,  fittings,  and  valves  shall  be securely plugged so that no trench water, earth or other substances will enter the pipe or fittings.   

Where a new sanitary sewer  line  ties  into an existing  in‐service sanitary sewer, actual 

tie‐in  to  the  existing  system  shall  be  completed  after  all  upstream  underground 

construction, alignment checking, cleaning,  flushing, pressure  testing,  is complete and 

accepted by Doyon Utilities’ Authorized Representative.  All tie‐in methods and materials 

shall be subject  to acceptance by Doyon Utilities’ Authorized Representative.   Care shall 

be exercised during construction, flushing, and testing operations of a tie‐in section to 

assure that no foreign debris is diverted into an existing in‐service sanitary sewer. 

All  sewer  lines  shall  be  marked  with  detectable  underground  warning  tape.    The Contractor shall install detectable underground warning tape directly above and parallel to the axis of the sewer line with no breaks in continuity. The Contractor shall install the locator  tape  three  feet  (3’)  below  finish  grade  or  two  feet  (2’)  deep  in  the  street structural section. 

E.  Gravity Main and Service Installation Requirements 

All gravity mains and services shall be  installed with 5‐foot minimum earth cover from 

finished  grade.   All  gravity mains  and  services with  less  than 6‐feet of  cover  shall be 

insulated with  a minimum  of  4‐inches  of  rigid  board  insulation  in  conformance with 

Division 20. 

Minimum slopes for gravity sewer mains and service shall be as follows:  

Page 17: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 13JBER–Division50

Pipe Diameter               Slope 

   4"        2.08% (0.0208 feet per foot) 

   6"        1.00% (0.0100 feet per foot) 

   8"        0.40% (0.0040 feet per foot) 

 10"        0.28% (0.0028 feet per foot) 

 12"        0.22% (0.0022 feet per foot) 

 14"        0.17% (0.0017 feet per foot) 

 16"        0.14% (0.0014 feet per foot) 

 20"        0.10% (0.0010 feet per foot) 

 24"        0.08% (0.0008 feet per foot) 

Gravity main and service pipe  laying shall  in all cases proceed upgrade with the spigot 

ends of the pipe pointing in the direction of the flow.  Cutting of pipe shall be done in a 

neat and workmanlike manner without damage to the pipe.  The interior of the pipe and 

accessories shall be thoroughly cleaned of foreign matter prior to installation.  Each pipe 

shall be  laid true to  line and grade and  in such a manner as to form a close concentric 

joint with the adjoining pipe.  When completed, the alignment of the installed pipe shall 

appear straight to visual observation and shall be such that a full circle of  light can be 

seen between manholes, etc., when sighting along all points of the pipe circumference.  

Each section of pipe shall be handled carefully and placed accurately.  Each pipe shall be 

joined  in  accordance  with  the  pipe  manufacturer’s  recommended  standards.    Each 

section  of  pipe  shall  be  properly  supported  to  ensure  true  alignment  and  an  invert 

which is smooth and free from roughness or irregularity.  

When exposing an existing main or service stub‐out, the Contractor shall insure that the stub‐out has the proper slope and alignment and is free and clear of obstructions prior to connection of the new main or service extension.  If the existing main or service stub‐out  is  found  to  be  either misaligned  or  plugged,  the  Contractor  shall  notify  Doyon Utilities’  Authorized  Representative  immediately  or  shall  be  liable  for  correcting  the misalignment or unplugging the line at Contractor expense. 

Tie‐in methods and materials  for connection of new main or service piping  to existing main  or  service  stub‐outs  shall  be  to  the  satisfaction  of  Doyon  Utilities’  Authorized Representative. 

New  gravity  service  and/or  force main  connections  to  gravity  sewer mains  shall  be spaced at least 3‐feet apart. 

Holes in gravity sewer main side walls at service saddles, for connection of gravity sewer service  saddles,  shall  be  drilled  with  mechanical  hole  cutters  acceptable  to  Doyon Utilities’ Authorized Representative.   Gravity sewer main side wall drilled hole diameters shall be 1/8‐inch  larger that the service saddle hole diameters.   All gravity sewer main side wall drilled holes shall be completely  located  in the upper half of the main piping.  

Page 18: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 14JBER–Division50

Service  saddles  shall  be  installed  so  that  service  saddle  piping  connection  holes  are positioned concentric to gravity sewer main side wall drilled holes. 

Deep service risers shall be installed where sanitary sewer mains are in excess of 12‐feet deep  and  8‐feet  of  cover  can  be maintained  over  service  piping.   Deep  service  riser piping  shall  be  fully  restrained  from  the  riser‐main  connection  to  at  least  three  full horizontal piping joints upstream of the riser.  No more than two sanitary sewer service connections shall be installed on a single deep service riser. 

Supervisory  personnel,  for  hot  tapping  of  deep  sewer  riser  connections  to  existing mains, shall have a minimum of 5 years of experience in hot tapping of water mains. 

The  Contractor  shall  submit  procedures  and  supervisory  personnel  resume(s)  for  hot tapping,  for review and acceptance by Doyon Utilities’ Authorized Representative.   No hot  tapping  shall  commence  until Doyon Utilities’  Authorized  Representative written acceptance of Contractor procedures and supervisory personnel resume(s)  is provided.  Hot  tapping  procedures  that  have  been  accepted  by  Doyon  Utilities’  Authorized Representative shall be strictly followed in the field.  All hot tapping operations shall at all  times  be  prudently  conducted  to  ensure  sanitation  and  uninterrupted  service  of “live” sewer lines. 

Ends of sewer mains and services stubbed out for future shall be permanently marked with new vertical 4‐inch by 4‐inch pressure treated wood posts set directly over the end of pipes.    In non‐traffic areas,  the 4‐inch by 4‐inch pressure  treated wood posts  shall extend  at  least  one  foot  above  finished  grade,  shall  be  painted  green,  and  shall  be permanently  fitted  with  3‐inch  diameter  red  plastic  reflectors  on  all  four  sides.    In vehicular  and/or pedestrian  traffic  areas,  the 4‐inch by 4‐inch pressure  treated wood posts shall be cut off at a depth below grade as directed by Doyon Utilities’ Authorized Representative. 

F.  Force Main Installation Requirements 

All force mains shall be installed with 10‐foot minimum earth cover from finished grade. 

Ductile iron pipe thrust joint restraint components for force mains, including mechanical joint restraining  glands  and  field  lock  gaskets,  shall  be  installed  in  strict  accordance  with manufacturers’  recommended  procedures  and  to  the  satisfaction  of  Doyon  Utilities’ Authorized Representative.   Thrust restraint systems shall be  installed where the force main terminates or changes alignment, utilizing a tee, cross, bend, or similar fitting.  A minimum of 90‐feet of piping shall be completely restrained on both piping  legs all bends, on both piping  legs  at  tees  and  crosses with  two  piping  legs  and where  piping  turns  90o,  on branch  legs at  tees and crosses, and at all piping dead ends.   Piping stub‐outs shorter than 90‐feet shall be completely restrained including connections to other mains. 

Ductile iron force mains discharging into manholes shall be thrust blocked as necessary 

to  prevent  force main  piping  from  pulling  out  of manholes,  all  to  the  satisfaction  of 

Doyon  Utilities’  Authorized  Representative.    Thrust  blocking  shall  be  in  addition  to 

Page 19: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 15JBER–Division50

installation of mechanical joint restraining glands and field lock gaskets as specified above. 

Two parallel electrical  continuity  straps  shall be exothermically welded  to ductile  iron 

force main piping on both sides of every joint to provide redundant electrical continuity 

paths across the joint. 

At  intervals on ductile  iron  force mains not  to exceed 500‐feet  in  length,  sets of  two parallel electrical continuity test leads shall be installed.  Test lead sets shall be located so that the entire force main can be continuity tested.  Test leads shall extend from the pipe to 3‐feet minimum above finished grade and shall be permanently housed in valve boxes or in valve box top sections to provide accessibility for future use. 

Continuity straps and test  leads shall be exothermically welded to a clean, dry,  freshly ground bright metal pipe surface.  Weld quality shall be subject to acceptance by Doyon Utilities’ Authorized Representative.   All welds and bare pipe surfaces are to be coated with  coal  tar pitch or other  suitable  coating, all  to  the  satisfaction of Doyon Utilities’ Authorized Representative. 

All HDPE pipe and  fitting  joint butt  fusion  shall conform  to ASTM F2620 and  the pipe 

manufacturer's  recommendations  for  proper  equipment  and  procedures.    The  HDPE 

pipe  supplier  shall  supply  a  qualified  representative  acceptable  to  Doyon  Utilities’ 

Authorized Representative  to  instruct  the Contractor's personnel on butt  fusion, and  to 

witness the first twenty butt fusion joints. 

All HDPE coupling and  fitting electrofusion shall conform  to  the electrofusion coupling 

and  fitting manufacturer's  recommendations  for  proper  equipment  and  procedures.  

The  electrofusion  coupling  and  fitting  supplier  shall  supply  a  qualified  representative 

acceptable  to  Doyon  Utilities’  Authorized  Representative  to  instruct  the  Contractor's 

personnel  on  electrofusion,  and  to  witness  the  first  twenty  electrofusion  joints.

Page 20: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 16JBER–Division50

All HDPE pipe shall be spiral wrapped with #12 tracer wire.  Full spiral wrap lengths shall 

not exceed 2‐feet.  Splices in tracer wire shall be insulated with mastic pads, and mastic 

pads  shall  be  secured  with  vinyl  electrical  tape.    All  splice  details  shall  be  to  the 

satisfaction  of  Doyon  Utilities’ Authorized  Representative.   At  intervals  on  HDPE  force 

mains not to exceed 500‐feet in length, trace wire leads shall be brought to the surface.  

Trace wire lead sets shall be located so that the entire HDPE main can be located.  Trace 

wire leads shall extend from the pipe to 3‐feet minimum above finished grade and shall 

be  permanently  housed  in  valve  boxes  or  in  valve  box  top  sections  to  provide 

accessibility for future use. 

For copper tubing force mains, a thaw wires shall be  installed from the connections to the gravity main to  lift stations.   Thaw wires shall extend  from the to 3‐feet minimum above finished grade at  lift stations and shall be permanently housed  in valve boxes or in valve box top sections to provide accessibility for future use.  Thaw wire connections at force main piping connections to gravity mains shall be to the satisfaction of Doyon Utilities’ Authorized Representative. 

Force main high points shall be vented  in accordance with Section 50.07  ‐ Force Main Permanent Vents. 

G.  Sanitary Sewer Line Separation Requirements from Public Water Systems and  Water Lines 

All sanitary sewer  lines and appurtenances  including  lift stations, manholes, clean‐outs shall  be  constructed  to meet  all  separation  requirements  of  18  AAC  80.020,  or  the following requirements, whichever are more stringent: 

1. Lift stations, force mains, manholes, and clean‐outs shall be constructed at least 

200  feet  horizontal  from  Community  water  systems,  and  at  least  150  feet 

horizontal from Class C water systems. 

2. Community gravity sewer mains shall be constructed at least 200 feet horizontal 

from Community water systems, and at  least 100 feet horizontal from Class C 

water systems. 

3. Gravity  sewer  services  shall  be  constructed  at  least  100  feet  horizontal  from 

Community water systems, and at  least 75 feet horizontal from Class C water 

systems. 

4. Sanitary sewer lines shall be installed at least 10‐feet horizontal out‐to‐out from 

parallel water  lines  (mains,  fire hydrant assemblies,  fire  lines, water  services, 

permanent vent lines, etc). 

5. Sanitary  sewer  pipe  at  water  line  crossings  shall  be  installed  such  that  no sanitary sewer line pipe joints are located less than 9‐feet horizontal from the 

centerline  of  the  water  line  at  the  point  of  intersection  of  sewer/water 

horizontal alignments. 

Page 21: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 17JBER–Division50

6. Where  sanitary  sewer  lines  cross water  lines,  the vertical  separation between 

the  sanitary  sewer  and  water  lines  shall  be  18‐inches minimum  out‐to‐out 

between exterior pipe surfaces.   

7. At  crossings,  sanitary  sewer  lines within  10‐feet  of water  line  crossings,  and existing water  lines  exposed  at  sanitary  sewer  crossings,  shall  all be bedded 

from 6‐inches below to 6‐inches above the line with Class B bedding material in 

accordance with Division 20. 

H.  Alignment and Grade  

The Contractor also shall employ qualified persons for controlling alignment and grade, and shall use standard survey  instruments such as transits, engineer’s  levels, and  laser devices, all in good repair and calibration, for controlling line and grade.  The Contractor shall  record  line  and  grade  measurements  in  standard  survey  field  books  for  each installed pipe and appurtenance, and  shall promptly  furnish copies of notes  to Doyon Utilities’  Authorized  Representative.    Line  and  grade  personnel,  survey  instruments, procedures, and survey notes shall be to the satisfaction of Doyon Utilities’ Authorized Representative. 

The Contractor shall lay the gravity main and service pipe in the trench so that after the line  is  completed,  the  bottom  of  the  pipe  conforms  accurately  to  the  grades  and alignments shown on  the Plans.   Variance of  individual pipe sections  from established line and grade shall not be greater than those  listed  in the table below, providing that such variance does not result in a level or reverse sloping invert.  

Diameter Allowance (Inches)      Tolerance (Feet)  

  4            0.02 

  6            0.02 

  8            0.03 

10            0.03 

12            0.03 

14            0.04 

16            0.04 

20            0.05 

24            0.05 

The practice of placing backfill over a section of pipe  to provide a pad  for  transit and level  alignment  and  grade  observations  shall  be  subject  to  the  approval  of  Doyon Utilities’ Authorized Representative.    If such  intermittent backfilling  is allowed, backfill shall meet the requirements of Type II classified fill and shall be placed in loose 12‐inch lifts,  with  each  lift  shall  be  compacted  to  95%  minimum  density  before  placing additional backfill.  

Page 22: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 18JBER–Division50

At a sufficient distance, prior to encountering a known obstacle or tie‐in to an existing pipe, the Contractor shall expose and verify the exact  location of the obstacle or tie‐in point  so  that  proper  alignment  and/or  grade  may  be  determined  before  the  pipe sections are laid in the trench and backfilled. 

I.  As‐Builting 

The  Contractor  shall  obtain  accurate  GPS  coordinates  at  all  manhole  centerlines, manhole  covers,  clean‐out  45o  bends,  clean‐out  covers,  buried main  stub‐out  ends, service  lines  connections  to gravity main piping, buried  service  stub‐out ends,  service alignment changes, service clean‐outs, points where services enter buildings, force main bends, force main points of curvature and tangency, even 50‐foot and 100‐ foot stations in horizontal curves in force main piping, and other locations called out in Division 65 or requested by Doyon Utilities’ Authorized Representative,     All GPS coordinates shall be accurately recorded on as‐built drawings. 

Article2.4Inspection,Cleaning,Flushing,andTesting

The Contractor  shall  take precautions  to prevent  sewage  from entering a new  sanitary  sewer 

line until it has been inspected, cleaned, tested, and accepted for operation by Doyon Utilities’ 

Authorized Representative.   The Contractor may request  inspection, testing and acceptance of 

incremental segments of the work, such as a completed mainline sanitary sewer section with a 

completed manhole or cleanout at each end.  

A.  Alignment and Debris Inspection 

After gravity main and gravity service construction, including backfilling and compaction 

to  finished  grade,  is  complete,  gravity  mains  and  services  shall  be  inspected  for 

straightness  of  vertical  and  horizontal  alignment  and  for  debris.    After  force  main 

construction,  including backfilling and compaction to finished grade,  is complete, force 

mains shall be inspected for debris. 

For new gravity mains extending from new manhole to new manhole, horizontal and vertical alignment  inspection  shall  be made  by  lamping  and  direct  visual  inspection  of  each  new section  of  line.   A  full  circle  of  light must  be  seen  at  the  top,  bottom,  right  and  left springline of the pipe by Doyon Utilities’ Authorized Representative when a bright light is shined from the next new manhole to the new manhole occupied by Doyon Utilities’ Authorized Representative. 

Page 23: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 19JBER–Division50

For new gravity mains extending from a new manhole to a new clean‐out, new gravity mains extending from a new manhole to an existing manhole, new gravity service lines, new 3‐inch diameter and  larger  force mains, and other new  sewer  lines  that  can not be  inspected by direct  visual methods,  the  Contractor  shall  provide  for  closed  circuit  television  inspection acceptable to Doyon Utilities’ Authorized Representative. 

During direct visual inspections and/or television inspections of new gravity sanitary sewer mains and services, horizontal and vertical alignments shall be inspected for straightness to the satisfaction of Doyon Utilities’ Authorized Representative.  Visually detectable horizontal and/or vertical alignment changes shall be corrected at Contractor expense to the satisfaction of Doyon Utilities’ Authorized Representative. 

If significant amounts of debris are discovered in new gravity mains, gravity services, and/or force mains during direct visual  inspections and/or television inspections, these lines shall be flushed, cleaned, and re‐inspected at Contractor expense all to the satisfaction of Doyon Utilities’ Authorized Representative. 

B.  Cleaning and Flushing 

The Contractor shall clean and flush all sanitary sewer lines to the satisfaction of Doyon 

Utilities’ Authorized Representative to remove all detectable debris from  lines.   Debris 

shall not be allowed to flow into existing in‐service sanitary sewer systems. 

C.  Gravity Main and Service Air Testing 

The Contractor  shall  furnish all equipment and personnel  for air  testing.   Air  tests  for acceptance by Doyon Utilities’ Authorized Representative shall be made after mains and services  have  been  completely  constructed,  including  backfill  and  compaction  to finished grade.  

All main  and  service  pipe  openings  in  a main  section  to  be  tested  shall  be  suitably capped or plugged for testing.  Safety braces shall be required to hold caps and/or plugs in place to prevent the sudden release of plugs and/or caps.  For safety reasons, workers shall not be allowed in areas where caps or plugs have been placed while lines are under air pressure.   The Contractor's  testing equipment  shall be arranged  in  such a manner that a pressure relief device will prohibit the pressure in the pipeline from exceeding 10 PSI.  

Air  shall be  slowly  supplied  to  the plugged pipe  section until  the  internal air pressure reaches the test pressure of 4‐pounds per square inch over and above the largest back pressure of any ground water in contact with the pipe, as determined by Doyon Utilities’ Authorized Representative.   At  least two (2) minutes shall be allowed for temperature stabilization before proceeding with the actual test.  The test shall be maintained for ten (10) minutes, during which time the pressure drop shall not exceed the values shown in the table below for various pipe diameters. 

Page 24: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 20JBER–Division50

Main Diameter (Inches)   Allowable Pressure Drop in 10 Minutes 

    8              2.7 PSI  

  10              2.1 PSI  

  12              1.8 PSI  

  14              1.5 PSI  

  16              1.3 PSI  

  20              1.1 PSI 

  24              0.9 PSI 

Pressure gauges shall be incremented 0.1‐PSI increments for accurate testing.  

D.  Force Main Pressure Testing 

Force mains shall be hydrostatically tested at a constant pressure of one hundred fifty (150) psi minimum with no detectable pressure drop for a duration of 30 minutes.  If necessary because of topography, force main profile, and test pump location, the hydrostatic test pressure shall be increased as directed by Doyon Utilities’ Authorized Representative to assure that the entire force main is exposed to a test pressure of at least 150 psi.  After the required test pressure has been  reached, pumping will be  terminated.    If  the pressure  remains constant  for 30 minutes without  additional  pumping,  the  test  shall  be  considered  satisfactory  by  Doyon  Utilities' Authorized Representative. 

At  the end of a successful hydrostatic  test, pressure shall be  released at a  force main location remote from the test pump connection to prove the integrity of the hydrostatic test. 

E.  Leak Repair and Retesting 

For any gravity sewer main, gravity sewer service, or force main failing its pressure test, 

the line shall be repaired and testing shall be repeated, all at Contractor expense and to 

the  satisfaction  of  Doyon  Utilities’  Authorized  Representative,  until  satisfactory  test 

results  are  obtained.    All  leak  repair methods  shall  be  to  the  satisfaction  of  Doyon 

Utilities’ Authorized Representative.   Use of devices such as repair clamps shall not be 

permitted. 

F.  Ductile Iron Force Main Continuity Tests  

Continuity  tests  shall  not  be  performed  until  all  construction,  including  backfill  and 

compaction to finished grade, has been completed to the satisfaction of Doyon Utilities' 

Authorized Representative. 

A sufficient number of continuity tests shall be conducted so that all new ductile iron force main is continuity tested.  All continuity tests shall be through continuity test leads. 

Page 25: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 21JBER–Division50

During each continuity test, the Contractor shall maintain a circuit of six hundred (600) 

amperes DC current for a period of fifteen (15) minutes.  Return current shall be at least 

ninety  percent  (90%)  of  the  input  circuit.    All  equipment  necessary  to maintain  the 

circuit shall be supplied by the Contractor.  

G.  HDPE Force Main Trace Wire Continuity Tests 

The Contractor shall demonstrate continuity of all HDPE  force main  trace wires  to  the satisfaction of Doyon Utilities’ Authorized Representative. 

Page 26: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 22JBER–Division50

SECTION50.03SANITARYSEWERMANHOLES

Article3.1General

The Work under this Section includes construction of new sanitary sewer manholes. 

Refer to Section 50.01 for additional general requirements. 

Article3.2Material

A.  Bases, Barrel Sections, Reducing Slabs, Eccentric Cones, Top Slabs, and Grade Rings 

Portland  cement  concrete  manhole  bases,  barrel  sections,  reducing  slabs,  eccentric 

cones, top slabs, and grade rings shall conform to the requirements of ASTM C478 and 

the Standard Details.   Reinforcement steel shall conform to the requirements of ASTM 

A185 and ASTM A615, Grade 60 steel, and the Standard Details. 

B.  Pipe‐to‐Manhole Waterstop Connectors 

Pipe‐to‐manhole waterstop  connectors  shall  be  elastomer  sleeves  that  are  cast  into 

concrete manhole walls at penetrations, and shall fit snugly around the pipe perimeters 

to form water‐tight connections.  Pipe‐to‐manhole waterstop connectors shall conform 

to applicable provisions of ASTM C923.  Pipe‐to‐manhole waterstop connectors shall be 

“A‐LOK  Z‐LOK” or Doyon Utilities’ Authorized Representative  accepted  equal  for pipe 

outside diameters up to 18.25‐inches and “A‐LOK Premium” for pipe outside diameters 

larger than 18.25‐inches. 

C.  Manhole Steps 

Manhole steps shall conform to the Standard Details. 

D.  Standard Manhole Frames, Covers, and Dust Pans 

Standard manhole  frames,  covers,  and  dust  pans  shall  be  gray  iron with  a minimum 30,000‐pound  tensile  strength  in  accordance with  ASTM  A48,  shall  have  appropriate certifications  and  be  individually  marked  in  accordance  with  the  requirements  of AASHTO M306.  Standard manhole frames and covers shall be in conformance with the Standard Details  and  shall be  “East  Jordan  Iron Works  IFCO #740” or Doyon Utilities’ Authorized Representative accepted equal.  Dust pans shall be “East Jordan Iron Works #2640” or Doyon Utilities Authorized Representative accepted equal. 

Page 27: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 23JBER–Division50

E.  Watertight Manhole Frames and Covers 

Watertight manhole frames and covers shall be gray iron with a minimum 30,000‐pound tensile strength in accordance with ASTM A48, shall have appropriate certifications and be individually marked in accordance with the requirements of AASHTO M‐306.  Water tight manhole frames and covers shall be in conformance with the Standard Details and shall be “East  Jordan  Iron Works #2615” or Doyon Utilities Authorized Representative accepted equal. 

F.  Plastic Gasket Joint Sealer 

Gasket material for concrete‐to‐concrete bell‐and‐spigot joints in manhole sections shall be “Henry Ram‐Nek” or Doyon Utilities’ Authorized Representative accepted equal. 

G.  Manhole Exterior Surface Waterproofing 

Manhole exterior surface waterproofing shall be shop‐applied “Koch Materials TUFF‐N‐

DRI”  or  Doyon  Utilities’  Authorized  Representative  accepted  equal,  applied  in  strict 

accordance with waterproofing manufacturers’ recommendations. 

H.  Manhole External Joint Sealant 

External  joint  sealant  for  joints  in  manhole  sections  shall  be  “Marathon  Materials 

MacWrap” or Doyon Utilities’ Authorized Representative accepted equal. 

I.  Miscellaneous Concrete  

Miscellaneous concrete for on‐site construction of manhole channels, etc, shall be 3000‐

PSI minimum design strength, Class A‐3, per Division 30. 

J.  Mortar  

Cement  for  mortar  used  in  the  construction  of  manholes  shall  conform  with  the requirements  of  ASTM  C150,  Type  II.    Sand  shall  conform with  the  requirements  of AASHTO M45.  The mortar shall be composed of one (1) part cement and three (3) parts sand.   The addition of  lime  is not permitted.   The use of  five  (5) minute or  fast‐cure mortar is prohibited.  

Article3.3Construction

A.  General 

Manhole bases shall be installed such that primary sewer lines enter or leave radially at 

the  invert  elevations  shown on  the Plans.    The base  section  shall be  set plumb on  a 

prepared surface. 

Page 28: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 24JBER–Division50

Plastic gasket joint sealer shall be installed in strict accordance with the manufacturer's 

recommendations and to the satisfaction of Doyon Utilities’ Authorized Representative.  

Gaskets  shall be  trimmed on  the  inside of  the manhole  to prevent  the excess  gasket 

material from entering the sanitary sewer lines.  

Manholes shall have a minimum of 6‐inches minimum to 18‐inches maximum of precast 

concrete grade rings.  In non‐traffic areas, grade rings shall be set in and made secure by 

use of plastic gasket joint sealer.  In traffic areas, manhole grade rings and frames shall 

be placed on full beds of mortar to prevent settlement. 

Watertight manhole frames and covers shall be installed where called out on the Plans 

or where directed by Doyon Utilities’ Authorized Representative. 

Standard manhole frames and covers shall be installed with dust pans. 

The manhole frames and covers shall be set at the rim elevations shown on the Plans, 

and shall be  located relative to finished grade  in accordance with the Standard Details 

except  in  follows.    In  non‐traveled‐way  easement  installations, manhole  frames  and 

covers shall be set approximately 6‐inches above finished grade. 

Prior to backfilling, the Contractor shall apply exterior joint sealant at all manhole joints.  

Exterior  joint  sealant  shall  be  installed  in  strict  accordance  with  manufacturers’ 

recommendations and to the satisfaction of Doyon Utilities’ Authorized Representative. 

After application of exterior  joint sealant, the manhole exterior shall be wrapped with 

three  full  layers  of  8‐mil  polyethylene  sheeting  and  secured  with  duct  tape  to  the 

satisfaction of Doyon Utilities’ Authorized Representative.   

Care shall be taken during backfilling to protect manhole exterior surface waterproofing, 

exterior  joint  sealant,  and  polyethylene  sheeting  wrap  to  the  satisfaction  of  Doyon 

Utilities’ Authorized Representative. 

Any visually detectable  leakage paths  into completed manholes shall be sealed  to  the satisfaction of Doyon Utilities’ Authorized Representative. 

B.   Sanitary Sewer Manhole Invert Construction  

The invert channels shall be smooth and semicircular in shape conforming to the inside 

of the connecting sanitary sewer section.  Changes in directions of flow shall be made by 

forming a smooth radius sized to allow adequate access of a television camera and/or 

maintenance  equipment  into  the  served  sanitary  sewer  pipe.    Changes  in  size  and 

grades of the channels shall be made gradually and evenly. The invert channels shall be 

formed and poured  in place.   The  floors of manholes outside of  the channels shall be 

smooth and shall slope toward the channels at a grade of one inch per foot.  No surfaces 

shall  be  permitted  in  finished manhole  bases  that would  allow wastewater  solids  to 

accumulate in the event of wastewater backup. 

Page 29: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 25JBER–Division50

Beaver slide  inverts shall be  required where  inverts of  the connecting sanitary sewers are  above  the  crowns  of  the  receiving  sewers  and  invert  drops  in manholes  do  not exceed 24‐inches.  Beaver slides shall be constructed to provide smooth and continuous channels  directed  into  and  with  the  flow  of  the  receiving  sanitary  sewers  and  in accordance with the Standard Details.  

C.  As‐Builting 

The  Contractor  shall  obtain  accurate  GPS  coordinates  on  all  manhole  structure centerlines and covers, and record these coordinates on as‐built drawings. 

Page 30: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 26JBER–Division50

SECTION50.04SANITARYSEWERDROPCONNECTIONS

Article4.1General

The  Work  under  this  Section  includes  construction  of  sanitary  sewer  drop  connections  at 

manholes. 

Refer to Section 50.01 for additional general requirements. 

Article4.2Material

Pipe,  fittings,  joint  restraints, and other piping materials  for construction of drop connections shall meet the requirements of Section 50.02 – Gravity Sewer Lines and Force Mains. 

Article4.3Construction

All drop connections shall be constructed in accordance with the Standard Details. 

Horizontal and vertical piping at mechanical joint tees and 90‐degree bends shall be restrained with restraining mechanical joint glands. 

All  drop  connection  piping  shall  be  encased  in  one  layer  of  polyethylene  encasement  in accordance with Section 50.08 ‐ Polyethylene Encasement. 

Page 31: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 27JBER–Division50

SECTION50.05SANITARYSEWERCLEANOUTS

Article5.1General

The Work under  this Section  includes construction of gravity  sanitary  sewer main and  service 

cleanouts. 

Refer to Section 50.01 for additional general requirements. 

Article5.2Material

A.  Pipe, Fittings, Joint Restraints, and Other Piping Materials 

Pipe,  fittings,  joint  restraints, and other piping materials  for construction of cleanouts shall meet the requirements of Section 50.02 – Gravity Sewer Lines and Force Mains. 

B.  Main Cleanout Covers 

Main  cleanout  covers  shall  be  “East  Jordan  Iron  Works  #3668”  or  Doyon  Utilities Authorized Representative accepted equal. 

C.  Manholes for Special Cleanouts 

Manholes for special clean‐outs shall meet the requirements of Section 50.03 – Sanitary Sewer Manholes as modified by the Standard Details. 

Article5.3Construction

A.  General 

All  sanitary  sewer  cleanouts  shall  be  constructed  in  accordance  with  the  Standard Details. 

All buried cleanout piping shall be encased  in one  layer of polyethylene encasement  in accordance with Section 50.08 ‐ Polyethylene Encasement. 

B.  Gravity Main Cleanouts 

Main sewer and cleanout riser piping at cleanout 45‐degree mechanical joint bends shall be restrained with restraining mechanical joint glands. 

The first push‐on  joint downstream of a main cleanout 45‐degree bend, and any push‐on joints in cleanout riser piping shall be restrained with field lock gaskets. 

Page 32: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 28JBER–Division50

C.  Gravity Service Line Cleanouts 

Standard service line cleanout riser piping at cleanout mechanical joint wyes, 45‐degree bends, and access caps shall be restrained with restraining mechanical joint glands. 

Sanitary  service  cleanouts  shall  be  installed  within  five  feet  of  buildings  served, immediately upstream of all horizontal and/or vertical bends, and at 300‐feet maximum on centerline in straight sections of service piping. 

D.  Special Cleanouts 

Special cleanouts,  located  inside protective water well radiuses, shall be constructed  in accordance with the Standard Details. 

E.  As‐Builting 

The  Contractor  shall  obtain  accurate  GPS  coordinates  on  all  buried  cleanout  wyes and/or  45o  bends,  frames  and  covers,  access  caps,  and  special  cleanout  manhole centerlines and covers, and record these coordinates on as‐built drawings. 

Page 33: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 29JBER–Division50

SECTION50.06SANITARYSEWERLIFTSTATIONS

Article6.1General

The Work under this Section addresses construction of sanitary sewer lift stations. 

Refer to Section 50.01 for additional general requirements. 

Article6.2Material

Materials for sanitary sewer lift stations shall be as shown on the Plans and/or as specified in the 

Special Provisions. 

Article6.3Construction

Sanitary  sewer  lift  stations  shall be  constructed  in accordance with  the Plans and  the Special Provisions. 

Page 34: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 30JBER–Division50

SECTION50.07FORCEMAINPERMANENTVENTS

Article7.1General

The Work under this Section addresses construction of force main permanent vents. 

Refer to Section 50.01 for additional general requirements. 

Article7.2Material

Materials for force main permanent vents shall be as shown on the Plans and/or as specified in 

the Special Provisions. 

Article7.3Construction

Force main permanent vents shall be constructed in accordance with the Plans and the Special Provisions. 

Page 35: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 31JBER–Division50

SECTION50.08POLYETHYLENEENCASEMENT

Article8.1General

The Work under this Section includes providing polyethylene encasement on all ductile iron pipe 

and fittings.  

Refer to Section 50.01 for additional general requirements. 

Article8.2Material

The polyethylene encasement material  for pipe  shall  conform  to  the most  current  edition of 

AWWA C105/ANSI A21.5.  

Article8.3Construction

Polyethylene encasement shall be installed on all ductile iron gravity sewer mains and services, 

force mains, drop connections, and cleanouts.  

The polyethylene encasement shall be installed in strict conformance to the methods described 

in  the most  current  editions  of AWWA  C105/ANSI A21.5  and  the Ductile  Iron  Pipe  Research 

Association's  "A  Guide  for  the  Installation  of  Ductile  Iron  Pipe."    The  Contractor  shall  use 

Method A of ANSI/AWWA C105/A21.5 to install polyethylene encasement.  

Bedding and backfill material around pipelines with polyethylene encasement  shall be placed 

using protective measures  such as  shields, guards,  coating  systems, and/or other methods as 

needed  to protect  the polyethylene encasement  from becoming  torn, punctured or otherwise 

damaged during  the Work.   Damage  to  the  integrity of  the polyethylene encasement shall be 

either repaired or the pipeline removed and the polyethylene encasement replaced as directed 

by  Doyon  Utilities’  Authorized  Representative.    Repair  and/or  replacement  of  damaged 

polyethylene encasement shall be at Contractor expense. 

Page 36: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 32JBER–Division50

SECTION50.09SANITARYSEWAGEBYPASSPUMPING

Article9.1General

The Work under  this Section  includes all planning, coordination, and operations pertaining  to 

the bypass pumping of sewage flows around those portions of the sanitary sewer facilities to be 

rehabilitated.  This work shall also include the installation, stocking, cleaning, and maintenance 

of  portable  toilets  for  exclusive  use  by  building  occupants  affected  by  shutdown  of  sanitary 

sewer facilities to be rehabilitated. 

Refer to Section 50.01 for additional general requirements. 

Article9.2Construction

The  sewage  flows  shall be bypassed around  sections of  sanitary  sewer  system designated  for 

rehabilitation. 

Under no circumstances shall the Contractor allow the discharge of sanitary sewage anywhere 

other  than an existing operational  sanitary wastewater collection  system or a holding  tank or 

tank  truck  acceptable  to  Doyon  Utilities’  Authorized  Representative.    No  excavation will  be 

permitted to facilitate this Work, except as indicated on the Plans. 

Sanitary sewer service to any building shall not be interrupted more than six consecutive hours, 

or more than once in a twenty‐four hour period. 

The number and  location of portable toilets shall be as directed by Doyon Utilities’ Authorized 

Representative.    These  portable  toilets  shall  be  for  the  exclusive  use  of  affected  building 

occupants.   Portable toilets shall have toilet paper and hand sanitizer dispensers, shall be well 

venting,  and  shall  be  cleaned,  maintained,  and  stocked  just  prior  to  installation  and  daily 

thereafter, all to the satisfaction of Doyon Utilities’ Authorized Representative. 

At least fourteen calendar days prior to construction, the Contractor shall submit a written plan, 

for acceptance by Doyon Utilities’ Authorized Representative, addressing the following issues: 

1. An estimate of the minimum and maximum sewage flow rates expected to be bypassed, 

including  an  allowance  for  larger‐than‐normal  sewage  flows  due  to  heavy  rainfall  or 

other causes. 

2. A pictorial plan  layout and written description of  the bypass pumping system showing 

and/or  describing  primary  bypass  pumps,  locations,  capacities,  spare  pumps,  suction 

and  discharge  line  types,  diameters,  lengths,  and  routings,  and  other  relevant 

information. 

3. Head‐discharge curves for proposed primary bypass pumps and spare pumps.   Primary 

bypass pumps shall have capacities equal to the expected maximum sewage flow rates.  

Spare bypass pumps shall have capacities equal to primary bypass pumps and equal to 

the expected maximum sewage flow rates. 

Page 37: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 33JBER–Division50

4. A description of pumping system control such that the sewage level both upstream and 

downstream of the bypass will not reach elevations that will cause backup and damage 

to the properties being served,  including a discussion of the elevation of the upstream 

sewage level needed to actuate the pumping cycle. 

5. A  discussion  of  noise  and  odors  generated  by  bypass  pumping  and  other  possible 

nuisance conditions, and how these conditions will be mitigated. 

6. An operations and maintenance manpower plan for bypass pumping. 

7. A schedule of the planned dates and hours of operation of bypass pumping. 

8. A  pictorial  plan  layout  of  portable  toilets  for  exclusive  use  by  personnel  affected  by 

shutdown of sanitary sewer facilities. 

9. Any  other  relevant  information  needed  to  assess  the  Contractor’s  plan  for  providing 

bypass pumping and portable toilets. 

The Contractor  shall  install, operate,  and maintain  the bypass pumping  system  in  substantial 

conformance  with  the  bypass  pumping  plan  accepted  by  Doyon  Utilities’  Authorized 

Representative.    The  Contractor  shall  only  deviate  from  the  accepted  plan  as  necessary  to 

accommodate emergencies and potentially detrimental conditions not anticipated or addressed 

in the accepted plan. 

Spare bypass pumps shall be on site and operational for the entire duration of sewage bypass 

pumping. 

The  Contractor  shall  be  liable  for  all  damages which  result  from  sewage  flows  not  properly 

bypassed during the progress of bypass pumping.   The Contractor  is reminded that after‐hours 

pumping may require a permit to exceed the allowable noise levels.  Should such permit not be 

available  for certain  locations,  such  lack of availability  shall not  cause  for  claim  for additional 

compensation or time extension.  

Page 38: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 34JBER–Division50

SECTION 50.10 NEW CONNECTIONS TO EXISTING SANITARYSEWERMANHOLES Article10.1General

The Work under this Section includes new sewer line connections to existing manholes.  

Refer to Section 50.01 for additional general requirements. 

Article10.2Material

A.  Pipe‐to‐Manhole Waterstop Connectors 

Pipe‐to‐manhole waterstop  connectors  shall be elastomer  sleeves  that are  installed  in 

core drilled manhole penetrations, have expansion devices to seal tightly in cored holes, 

and  fit  snugly  around  the  pipe  perimeters,  all  as  required  to  form  water‐tight 

connections.    Pipe‐to‐manhole  connectors  shall  conform  to  applicable  provisions  of 

ASTM C923.   Pipe‐to‐manhole  connectors  shall be  “A‐LOK G3 Boot  System” or Doyon 

Utilities’ Authorized Representative accepted equal for pipe outside diameters from 3.5‐

inches  to  13.5‐inches.    Pipe‐to‐manhole  connectors  for  pipe  outside  diameters  larger 

than  13.5‐inches  shall  be  as  shown  on  the  Plans  and/or  as  specified  in  the  Special 

Provisions. 

B.  Other Materials 

Other materials  for new connections  to existing manholes  shall be  in accordance with 

Section 50.03 – Sanitary Sewer Manholes 

Article10.3Construction

Connections  to existing sanitary sewer manholes will be allowed only after all portions of  the 

Contractor's sewer work upstream of connection points has been  inspected, and satisfactorily 

flushed, cleaned, and tested. 

Demolition and  construction debris  shall be prevented  from escaping  from existing manholes where  new  connections  are  being  made  to  the  satisfaction  of  Doyon  Utilities’  Authorized Representative. 

If new connections to existing manholes are in conflict with existing manhole ladder rungs, the Contractor shall remove the existing  ladder rungs and  install new  ladder rungs as necessary to clear of piping penetrations.   New  ladder  rungs  shall be  in accordance with Standard Details.  The  Contractor  shall  rotate  existing  cone  sections  and  unaltered  existing  barrel  sections  as necessary to align with new ladder rungs.  As part of rotating existing cone and barrel sections, all  existing  manhole  joint  gasketing  shall  be  removed,  existing  manhole  exteriors  shall  be pressure washed, and new plastic gasket joint sealer and external joint sealant shall be provided in accordance with Section 50.03 – Sanitary Sewer Manholes, all  to  the  satisfaction of Doyon 

Page 39: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 35JBER–Division50

Utilities’ Authorized Representative. 

New  sewer piping  shall be connected  to existing manholes  so  that  inverts enter at elevations 

shown on the Plans. 

Connections  to  new  sewer  piping  to  existing manholes  shall  be made  by  core  drilling  new 

penetrations  into manholes  and  installing  pipe‐to‐manhole waterstop  connectors  to  produce 

water  tight  seals.    Core  drilled  hole  diameters  and  details,  and  pipe‐to‐manhole  waterstop 

connector  installation,  shall be  in  strict  accordance with waterstop  connector manufacturer’s 

instructions. 

Existing manhole  channels  shall be broken out as necessary  to  form  smooth new  channels  in 

accordance with requirements of Section 50.03 – Sanitary Sewer Manholes. 

Beaver slide inverts shall be installed where inverts of the connecting sanitary sewers are above the crown of receiving sewers and the new  invert drops  in manholes do not exceed 24‐inches.  Beaver  slides  shall be  constructed  to provide  smooth and  continuous  channels  in accordance with the Standard Details.  

Any visually detectable leakage paths into existing manholes with new piping connections shall be sealed to the satisfaction of Doyon Utilities’ Authorized Representative. 

Completed connections to existing manholes shall be water tight and have smooth flow surfaces 

and curves, all to the satisfaction of Doyon Utilities’ Authorized Representative. 

Page 40: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 36JBER–Division50

SECTION50.11EXISTINGMANHOLEREHABILITATIONORREMOVALArticle11.1General

The Work under this Section includes the following activities: 

1. Removal of existing manhole  covers  and  frames  and  replacement with new  standard manhole covers and frames. 

2. Removal of existing manhole covers and frames and replacement with new water‐tight manhole covers and frames. 

3. Removal and replacement of grade rings.  

4. Removal and replacement of manhole ladder rungs.  

5. Removal and replacement of cone sections.  

6. Removal and replacement of barrel sections.  

7. Removal and replacement of base sections.  

8. Removal and replacement of entire manholes. 

9. Removal of entire manholes without replacement. 

Refer to Section 50.01 for additional general requirements. 

Article11.2Material

Replacement piping materials for existing manhole rehabilitation shall be in accordance with 

Section 50.02 – Gravity Sewer Lines and Force Mains. 

Replacement manhole materials for existing manhole rehabilitation shall be in accordance with 

Section 50.03 – Sanitary Sewer Manholes. 

Article11.3Construction

The  manhole  components  to  be  removed  and  replaced  for  specific  manholes  shall  be  as identified in the Plans.  The Contractor shall protect and reuse those manhole components that are not scheduled for replacement in rehabilitated manholes. 

Where the work requires disassembly and reuse of components that are assembled with grout 

and/or plastic gasket joint sealer, the Contractor shall completely remove these materials from 

the components, and replace the existing grout and/or plastic gasket joint sealer with new grout 

and/or plastic gasket joint sealer during reassembly of the rehabilitated manhole.  

Where the work requires the removal and replacement of all existing ladder rungs in a manhole, 

these  rungs  shall  be  cut  off  and  ground  smooth  against  the  interior wall  of manhole.   New 

ladder rungs shall be in accordance with Standard Details. 

Page 41: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 37JBER–Division50

Where  the  work  requires  the  removal  and  replacement  of  manhole  cone  sections,  barrel 

sections,  and/or  base  sections,  exterior  joints  shall  be wrapped with manhole  external  joint 

sealant,  and  the  entire manhole  exterior  shall  be wrapped with  three  layers  of  8‐mil  plastic 

sheeting, all in accordance with Section 50.03 – Sanitary Sewer Manholes. 

New channeling shall be installed as required in new manhole bases in accordance with Section 50.03 – Sanitary Sewer Manholes. 

Any  visually  detectable  leakage  paths  into  rehabilitated  manholes  shall  be  sealed  to  the satisfaction of Doyon Utilities’ Authorized Representative. 

Piping modifications  for manhole  rehabilitation  or  removal without  replacement  shall  be  as 

shown on the Plans or as directed by Doyon Utilities’ Authorized Representative. 

New and existing ductile iron piping impacted by manhole rehabilitation shall be encased in new 

polyethylene encasement in accordance with Section 50.06 ‐ Polyethylene Encasement. 

The  Contractor  shall  dispose  of  manhole  components  not  scheduled  for  reuse  in  manhole 

rehabilitations, and all other unsuitable or waste materials created in the execution of the work, 

at a location specified by Doyon Utilities’ Authorized Representative. 

Page 42: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 38JBER–Division50

SECTION50.12ADJUSTEXISTINGSANITARYSEWERMANHOLEFRAMESANDCOVERSANDEXISTINGMANHOLECONESTOFINISHGRADE Article12.1General

The Work under this Section includes adjustment of existing manhole frames and covers and/or 

existing manhole cones to finish grade. 

Refer to Section 50.01 for additional general requirements. 

Article12.2Material

Manhole materials for adjustment of existing manhole frames and covers and/or manhole cones 

to  finish grade,  including replacement of damaged and/or missing manhole components, shall 

be in accordance with Section 50.03 – Sanitary Sewer Manholes. 

Article12.3Construction

A.  General 

All existing manhole frame and cover and/or existing manhole cone adjustment shall be 

completed in accordance with Section 50.03 – Sanitary Sewer Manholes. 

The final frame elevations of adjusted manholes shall be as shown on the Plans and/or 

in accordance with the Standard Details. 

B.  Manhole Frame and Cover Adjustments 

For manhole  frame  and  cover  adjustments,  the  Contractor  shall  remove  and  salvage 

existing  frames  and  covers,  remove  existing  grade  rings  or  add  new  grade  rings  as 

required, and reinstall frames and covers to the correct elevations. 

C.  Manhole Cone Adjustments 

For manhole cone adjustments, the Contractor shall remove and salvage existing cones, 

grade  rings,  frames,  and  covers,  remove existing barrel  sections  if  required,  add new 

barrel  sections  if  required,  reinstall cones,  reinstall  some or all existing grade  rings as 

required, add new grade rings as required, and reinstall frames and covers to the correct 

elevations. 

Page 43: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 39JBER–Division50

50.13ADJUSTEXISTINGCLEANOUTSTOFINISHGRADE

Article13.1General

The Work under this Section  includes adjustment of existing gravity main and standard gravity 

service line cleanouts to finish grade. 

Refer to Section 50.01 for additional general requirements. 

Article13.2Material

Materials for adjustment of existing gravity main and standard gravity service  line cleanouts to 

finished grade,  including replacement of damaged and/or missing cleanouts components, shall 

be in accordance with Section 50.02 ‐ Gravity Sewer Lines and Force Mains, and Section 50.05 ‐ 

Sanitary Sewer Cleanouts. 

Article13.3Construction

All  existing main  cleanout  adjustment  shall be  completed  in  accordance with  Section 50.05  ‐ 

Sanitary Sewer Cleanouts. 

For main  cleanout adjustments,  the Contractor  shall  remove and  salvage existing  frames and covers, cut off and remove existing riser piping if required, add new riser piping if required using new mechanical  joint  long  sleeve  fittings  and  new mechanical  joint  restraining  glands,  and reinstall  frames  and  covers  to  the  correct  elevations.    If  new  riser  piping  is  added  during cleanout adjustment,  the new  riser piping  joint shall be  restrained  in accordance with Section 50.02  ‐ Gravity  Sewer  Lines  and  Force Mains,  and  new  riser  piping  shall  be  encased  in  new polyethylene encasement in accordance with Section 50.08 ‐ Polyethylene Encasement. 

The final main cleanout frame elevations of adjusted main cleanouts shall be as shown on the 

Plans and/or in accordance with the Standard Details. 

For  standard  service  cleanout  adjustments,  the  Contractor  shall  remove  and  salvage  existing 

mechanical joint caps, cut off and remove existing riser piping if required, add new riser piping if 

required using new mechanical  joint  long  sleeve  fittings and new mechanical  joint  restraining 

glands, and reinstall existing mechanical joint caps with new mechanical joint restraining glands 

to the correct elevations.  If new riser piping is added during cleanout adjustment, the new riser 

piping  shall  be  encased  in new polyethylene  encasement  in  accordance with  Section  50.08  ‐ 

Polyethylene Encasement. 

Page 44: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 40JBER–Division50

SECTION50.14REMOVEANDDISPOSEOFEXISTINGCESSPOOLSORSEPTICTANKSANDCONNECTTONEWSEWERSERVICES Article14.1General

The Work under this Section includes removal and disposing of existing cesspools or septic tanks 

and connection of existing building sewer piping to operating sanitary sewer systems.  This work 

also  includes  the  installation,  stocking,  cleaning,  and  maintenance  of  portable  toilets  for 

exclusive use by building occupants affected by removal of existing cesspools or septic tanks. 

Refer to Section 50.01 for additional general requirements. 

Article14.2Material

A.  Fill Material 

Fill material shall be Type II classified fill in accordance with Division 20. 

B.  New Sewer Service Piping Materials 

Piping material  shall  be  in  accordance with  Section  50.02  ‐  Gravity  Sewer  Lines  and 

Force Mains. 

C.  Transition Couplings  for Connection of Existing Building Sewers  to New Sewer Service 

Piping 

Transition  couplings  shall  be  “Romac  Style  501”  or  Doyon  Utilities’  Authorized 

Representative  accepted  equal, with  gaskets  as  necessary  to match  existing  building 

sewer and new sewer service diameters. 

Article14.3Construction

Portable toilets shall be provided for exclusive use of affected building occupants during sanitary 

sewer  service  interruption.    At  least  one  portable  toilet  shall  be  provided  for  each  affected 

building,  but  additional  portable  toilets  shall  be  provided  if  directed  by  Doyon  Utilities’ 

Authorized  Representative.    Portable  toilets  shall  have  toilet  paper  and  hand  sanitizer 

dispensers,  shall be well  venting, and  shall be  cleaned, maintained, and  stocked  just prior  to 

installation  and  daily  thereafter,  all  to  the  satisfaction  of  Doyon  Utilities’  Authorized 

Representative. 

Construction work shall be scheduled and coordinated so that sanitary sewer service shall not 

be  interrupted  for more  than 6 hours,  and  so  that  all  construction work occurs on  a normal 

week day between the hours of 9 AM and 3 PM. 

The following general procedures shall apply:  

Page 45: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 41JBER–Division50

1 The receiving sewer system shall be made complete and operable to the satisfaction of Doyon  Utilities’  Authorized  Representative  in  advance  of  septic  system  or  cesspool removal. 

2 The existing building  sewer  shall be  located at  least 48 hours  in advance and existing piping material and diameter shall be determined by the Contractor, all in coordination with Doyon Utilities’ Authorized Representative.  A transition coupling shall be provided in advance of the proper size and configuration to transition from the existing building sewer piping to new sewer service piping. 

3 The  portable  toilet(s)  shall  be  supplied  at  a  convenient  location  (or  locations)  for building occupants to the satisfaction of Doyon Utilities’ Authorized Representative. 

4 If  possible,  new  sewer  service  piping  shall  be  constructed  and  connected  to  existing building  sewer  piping  in  advance  of  cesspool  or  septic  tank  removal.    If  new  sewer service  piping  cannot  be  connected  to  existing  building  sewer  piping  in  advance  of cesspool or septic tank removal, then new sewer service piping shall be constructed as close as possible to existing building sewer piping to the satisfaction of Doyon Utilities’ Authorized Representative. 

5 The  liquid and  sludge  from  the existing  cesspool or  septic  tank  shall be pumped  into septic  pumper  trucks,  transported,  and  disposed  of  at  an  approved  sewage  dump station  designated  by  Doyon  Utilities’  Authorized  Representative.    Care  shall  be exercised to avoid spillage occurs during transport and disposal.  

6 The existing building  sewer  shall be excavated and neatly  cut off.   Provisions  shall be made to catch and dispose of accidental sewage discharges prior to connection of the new sewer service, all to the satisfaction of Doyon Utilities’ Authorized Representative. 

7 The  septic  tank,  cesspool  including  logs  or  cribbing,  any  remaining  sludge,  and  any saturated gravel  remaining  in  the area,  shall be  removed  to  the  satisfaction of Doyon Utilities’ Authorized Representative, and disposed of at a disposal area designated by Doyon Utilities’ Authorized Representative. 

8 If necessary, the excavation created by removal of the cesspool or septic tank shall be backfilled and compacted to 95%  in 12‐inch  loose  lifts to the  level needed to complete installation of any remaining new sewer service piping and tie‐in to the existing building sewer.  

9 Installation of any remaining new sewer service piping and tie‐in to the existing building sewer  shall  be  completed  to  the  satisfaction  of  Doyon  Utilities’  Authorized Representative.   

10 The Contractor  shall obtain accurate GPS coordinates at new  sewer  service alignment changes,  clean‐outs,  and  the  point  where  the  new  service  connects  to  the  existing building sewer.  All GPS coordinates shall be accurately recorded on as‐built drawings. 

11 The excavation shall  then be  fully backfilled and compacted  in  lifts  to 95%  to  finished grade. 

12 The portable  toilet(s)  shall be promptly  removed when  the work  is  completed  to  the satisfaction of Doyon Utilities’ Authorized Representative. 

Page 46: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 42JBER–Division50

SECTION50.15ABANDONMENTOFPIPEINPLACE

Article15.1General

The Work under this Section includes abandonment of existing pipe in place. 

Abandonment  of  existing  pipe  in  place  shall  only  be  allowed  if  specifically  called  out  on  the Plans,  authorized  in  the  Special  Provisions,  or  directed  by  Doyon  Utilities’  Authorized Representative.   Otherwise, existing pipe that  is taken out of service  in the course of a Doyon Utilities  project must  be  removed  and  disposed  of  offsite  at  a  location  directed  by  Doyon Utilities’ Authorized Representative. 

Refer to Section 50.01 for additional general requirements. 

Article15.2Material

A.  Pumpable Grout Mix 

The Contractor shall provide a pumpable grout mix composed of water, sand, cement, 

and admixtures.  

B.  Pipe Caps and Restraints 

Pipe caps and  restraints shall meet  the  requirements of Section 50.02 – Gravity Sewer 

Lines and Force Mains. 

Article15.3Construction

Wherever existing pipe  is to be abandoned  in place, the Contractor shall empty the  line of all sewage, cap  or  plug  ends  of  the  line,  retrain  or  thrust  block  pipe  ends  as  necessary  to  prevent  pipe  joint separation, and fill the pipe full of pumpable grout, all to the satisfaction of Doyon Utilities’ Authorized Representative. 

The Contractor shall demonstrate to Doyon Utilities’ Authorized Representative that the entire pipe to be abandoned has been filled with pumpable grout prior to backfilling of pipe ends. 

In the event that exposed pipe to be abandoned  is damaged such that  it  is not fit for abandonment  in 

place as determined by Doyon Utilities’ Authorized Representative, then the Contractor shall excavate 

to undamaged pipe acceptable to Doyon Utilities’ Authorized Representative, neatly cut off and remove 

the  damaged  pipe,  and  begin  abandon‐in‐place  operations  there.    Damaged  pipe  that  cannot  be 

abandoned in place shall be disposed of off site at Contractor expense.  

The Contractor shall obtain accurate GPS coordinates, elevation, and pipe size at the ends of abandoned 

pipe, and shall clearly record these coordinates on as‐built drawing.

Page 47: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 43JBER–Division50

 

SECTION50.16WASTEWATERCOLLECTIONSYSTEMSTANDARDDETAILS

 The following attached 2009 Municipality of Anchorage Standard Details are  incorporated  into these JBER Standard Specifications: 

 Detail    Description 50‐1     Sanitary Manhole ‐ Type A ‐ Pipe 8” to 24”  50‐2     Sanitary Manhole ‐ Type B ‐ Pipe Dia 30” to 36”  50‐3     Sanitary Manhole ‐ Type C ‐ Pipe Dia 40” to 48”  50‐4     Type A and B Manhole Base Plan  50‐5     Manhole Heights  50‐6     Manhole Step  50‐7     Sewer Service Connect for On‐Site Lift Station 1‐1/2” and 2”  50‐8     Manhole Cover  50‐9     Manhole Frame  50‐10     Watertight Manhole Ring  50‐11     Manhole Drop Connection  50‐12     Typical Beaver Slide Manhole  50‐13     Sanitary Sewer Service (Complete)  50‐15     Service Riser/Top Entry  50‐16     Sanitary Sewer Service Connection (R.O.W. Only)  50‐17     Sanitary Sewer Cleanout Cover  50‐18     Sanitary Cleanout  50‐19    Special Manhole and Cleanout Detail (inside protective well radius) 50‐20    Special Manhole and Cleanout Detail (inside protective well radius) 50‐21    Special Manhole and Cleanout Detail (inside protective well radius) 50‐22      Horse Shoe Sanitary Sewer Manhole Detail  50‐23     Contractor Field Installation Notes Sanitary Example  50‐24     Manhole Cone Adjustment  50‐25     Manhole Ring Adjustment  

 In  the  event  of  a  conflict  between  JBER  Standard  Specifications  and  the  attached  2009 Municipality of Anchorage Standard Details, JBER Standard Specifications shall govern.  All section number references on the attached 2009 Municipality of Anchorage Standard Details shall be disregarded.  The words  “ENGINEER”,  “AWWU  ENGINEERING”,  and  similar wording  on  the  attached  2009 Municipality  of  Anchorage  Standard  Details  shall  refer  to  Doyon  Utilities’  Authorized Representative.  All  references  to  payment  or  pay  limits  on  the  attached  2009  Municipality  of  Anchorage Standard Details shall be disregarded.  

Page 48: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 44JBER–Division50

 

Page 49: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 45JBER–Division50

 

Page 50: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 46JBER–Division50

 

Page 51: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 47JBER–Division50

 

Page 52: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 48JBER–Division50

 

Page 53: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 49JBER–Division50

Page 54: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 50JBER–Division50

 

Page 55: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 51JBER–Division50

Page 56: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 52JBER–Division50

Page 57: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 53JBER–Division50

 

Page 58: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 54JBER–Division50

Page 59: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 55JBER–Division50

 

Page 60: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 56JBER–Division50

Page 61: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 57JBER–Division50

 

Page 62: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 58JBER–Division50

Page 63: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 59JBER–Division50

Page 64: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 60JBER–Division50

 

Page 65: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 61JBER–Division50

Page 66: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 62JBER–Division50

 

Page 67: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 63JBER–Division50

Page 68: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 64JBER–Division50

 

Page 69: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 65JBER–Division50

 

Page 70: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 66JBER–Division50

Page 71: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 67JBER–Division50

 

Page 72: WASTEWATER COLLECTION SYSTEMS DIVISION 50 - … · AASHTO M45 Sand for Cement Mortar AASHTO M306 Standard Specification for Drainage, Sewer, Utility, and Related Castings

DESIGNANDCONSTRUCTIONSTANDARDSWASTEWATERCOLLECTIONSYSTEMS‐JBERDIVISION50

January2011 68JBER–Division50