was raised by the gulf cooperation council - epcc · pdf filewas raised by the gulf...
TRANSCRIPT
The concept of electrical interconnection
was raised by the Gulf Cooperation Council
(GCC) in early 80s to ensure security and
stability of their local electrical networks.
Technical and economical studies for
feasibility were conducted during mid 80s
to justify the requirements and benefits.
Brief History
• Initiation – Early 80’s
• Committee formed – 1986
• First Detailed Study – 1990 • Authority established by Royal Decree - 2001
• • Second Study – 2003
• GCC Joint Ministerial committee meeting in Kuwait allowed ‘Go Ahead’ - 2004
Pre-Construction
• Tendering & Adjudication - 2005
• Contracts Awarded for : - Construction (2005) - Org. Develop (2005) - Legal (2006)
• Preliminary ROW Survey (Land) - 2004
• Sea Survey Contract 2004
• Recruitment Process
Construction • Regulation • Systems
Operations
• System Maintenance
• Training
• Market Operations
Operations
Summary of Activities
Established in July 2001 by Royal Decree No. M/21
Owned by the six GCC Countries the authorized share capital is ($US 1,407,000,000) divided into (1,407,000) shares of ($US 1,000)
each share.
The Authority is managed by a (twelve member) Board of Directors; each member country is represented by two members. The Chairmanship is rotated among the member states every three years.
The primary objective of the Authority is to: link up the power grids of the six GCC countries operate and maintain the interconnection become a leading player in the regional electricity market
About GCC Interconnection Authority
GCCIA has redefined its vision, mission and values according to the newly approved Business strategy plan: Mission: Interconnecting Our World Vision: To serve the GCC countries and beyond, by leading the development of an efficient power market, and providing knowledge excellence in power systems integration Values: Safety, Reliability & Sustainability, Collaboration, Innovation, Efficiency, and Co-prosperity & Customer focus
GCCIA Mission, Vision and Values
2014 GCC total installed capacity is about 110 GW with peak demand of 100 GW
Kuwait
Saudi Arabia
Bahrain
Qatar
UAE
Oman
Kuwait
Saudi Arabia
Bahrain Qatar
UAE
Oman
Contribution by country to GCC peak demand
Phase I
Phase II Phase III
BAHRAIN
U.A.E.
EMIRATES NATIONAL GRID
AL FOUHAH 220kV 220kV
AL FADHILI 400kV
JASRA 400kV GHUNAN
400 kV 600MW
SALWA 400kV
SALWA 400kV
QATAR
1200 MW
90km 90km
DOHA SOUTH SUPER 400kV DOHA SOUTH SUPER 400kV
290km 290km
150km 150km
SILAA 400kV 400kV
1400 MW OMAN
OMAN NORTHERN
GRID
MHADAH 220 kV
400MW
52km
112km
100km 100km
KUWAIT AL ZOUR
400kV AL ZOUR
400kV
310km 1200 MW SAUDI ARABIA
SEC - ERB HVDC BACK - TO - BACK
1200MW
Country (Arabic Alphabetical Order)
Percentage%
United Arab Emirates 15.40 Kingdom of Bahrain 9.00
Kingdom of Saudi Arabia 31.60 Sultanate of Oman 5.60
State of Qatar 11.70 State of Kuwait 26.70
TOTAL 100.00
Total
The value of the awarded contracts to the six contractors are as follows:
$251,705,956 $217,451,173 $310,300,246 $343,122,125 $34,546,981
Actual Value
$17,901,497
ABB Areva-Cogelex NCC & MEEDCO
Prysmian-Nexans Areva-Cogelex
Contractor
SNC-Lavalin
Substations HVDC OHL Cable
Control
Lots
Supervision
$1,175,027,978
11
Contracts Value for Phase I
Project Timeframe
The Project timeframe for the Phase I Interconnection Project is as follows:
Event Date
Project Commissioning Year 2009
Tendering Period Bid Evaluation
Pre-Award Meetings
April 2005 May-August 2005 September 2005
Contract Award Ceremonies Project Construction Commencement
November 2005 December 2005
Total
The value of the awarded three(3) contracts are as follows:
$ 69,104,000
$ 43,718,000 $ 5,611,105
Actual Value
NCC Transmission Line Group
NCC Substation Group
Areva-Cogelex
Contractor
OHL Substation
Control
Contract No
$118,433,105
13
Contracts Value for Phase III
Project Timeframe
The Project timeframe for the Phase III Project is as follows:
Contract Award Completion Date
Salwa (KSA) to Silla (UAE) Transmission Line
August 2008 March 2011
Date
Contract Award Completion Date
July 2009 May 2011
Contract Award November 2009
Silla (UAE) 400 KV Substations Date
Control, Protection and Telecommunication Date
Completion Date May 2011
GCC Ministerial Committee
GCCIA Board of Directors
GCCIA - CEO
General Agreement
PETA
E & W Ministerial Committee Level
General Assembly & Board Level
GCC Utilities Level
Articles / Bylaws
Planning Committee
Operating Committee
Advisory & Regulatory Committee
Transmission & Metering Codes
Member States
Utilities ۱٥
Overall Framework
First Energization : 17 Feb 2009
Synchronized Operations
26th July 2009
Kuwait – Qatar Synchronized 20th July 2009
UAE Synchronized 24th July 2011
Oman and UAE interconnected
end of 2011
Since the 1st day of the operational phase for GCC Interconnection, the security and reliably of the overall interconnected network is highly enhanced
Over 1200 incidents were recoded on the overall interconnected network that range from single generator tripping up to 3000 MW with no impact on system security
GCC Interconnection helped to avoid partial or total blackout during some of the critical incidents for some of the MS grids
• Harmonization of Policies and Procures has been achieved through Operation Committee and Panning Committee
• Both committees meet on quarterly basis where all GCC TSOs representatives meet and discuss the common interest
Policies and Procures Harmonization
Installation of PMU and Power Performance System
• GCCIA installed PMUs network that covers all the GCCIA substations with master station at ICC for accurate analysis of system incidents
• this system avails a real time centralized
collection of PMUs information which enables GCCIA to implement a Wide Area Monitoring (WAM) system to have real time visualization of the status of operation of the power system
Fiber Optic Opportunity
GCCIA engaged in utilizing the OPGW fibre optic cable which is part of the transmission line and land & submarine cable
The cable consists of 96 fibres; in which 24 fibres will be reserved for electrical power uses and the remaining 72 fibres can be used for future applications
Currently negotiating with major telecommunication providers for the leasing and usage of the remaining fibres.
Considering the role of the GCC Interconnection grid for GCC energy sector, GCCIA approached world class entities in order to support GCCIA in the efforts to promote the energy trading between GCC countries
several workshops were conducted to highlight the energy exchange opportunities between GCC countries
Energy Trading
Although the energy trading has commenced between two of GCC counties during summer 2010, the utilization of the interconnection for energy trading is low
Major Challenges that limit the energy trading includes subsidies and Regulatory issues
Energy Trading
Establishing The Interconnection 2005-2011
Initiating a GCC Power Market 2010-2015
Beyond the GCC Power Market 2015-2020
Future Prospects
EJLIST
UCTE
East
Arab Maghreb GCC
24
Future Prospects
Thank you