walpole anaerobic digestion plant - south somerset
TRANSCRIPT
Overview
• Monsal technology• 30,000 tonne annual capacity• Potential further 15,000 tonnes• C 1mw electricity export per annum• C .3mw electricity parasitic loading• ABPR Compliant• PAS110 output• Heat use / gas injection
30,000 Biowaste plant–Short Mass Balance
Pre-Processing AD plant Biogas CHP
Waste 30,000 tpa
Power 1.3 MWe
Compost 13,000 tpa
Makeup Water
Biogas production500 m3/h
Waste Water
anaerobic digestion development
Food Waste Collection – Source Segregated
• Dry solids 23% - 28%• Few Contaminants
Waste Reception Processing
• Heavy duty shredder
•Twin shaft design/intelligent
•< 50mm initially
• Interim surge hopper (bunker)
• Localised odour containment/control
Waste dissolvers – pulping of biowaste
• Digester Feed Preparation
• Slurry Organics
• Reduce Particle Size
• Leave Plastics Intact
Waste dissolver – cleaning up and de-packaging
• Light fraction removal
• Large sump capacity
• Heavy fraction removal
• Compaction area
• Effective Separation
Buffer Tank / Hydrolysis Stage
• 6 Days retention
• Stage 1 of Digestion
• Pump mixed
• Dry solids 8% - 12%
• Connected to gas head space to contain odour
Pasteurisation Stage
• 3 Tank system
• 70C for >1hour
• Hot water from CHP
• Each batch logged for Animal Health
Digester
• Mesophilic Digester
• 2nd Stage (Methane)
• Energy Efficient Mixing
• Biogas for Heat and Power
advanced digestion technology
Dewatering / Product
• 25% dry solids
• Cake recycled to land
• ABPR Complete
• PAS 110
advanced digestion technology
advanced digestion technology
Odour Containment and Management
• Localised containment
• Common gas spaces
• 2-3 air changes/hour
• Positively displaced biofilter
Treatment of liquors (and recycling)
• Fully integrated system
• SBR biological treatment
• Provides buffering, treatmentand make up water
• Effluent can be discharged to sewer
Heat use - within the process for sterilisationother options
glasshousesleachate treatment works
Preferred option is Gas Injection
Heat use
Gas Injection
Gas injection –100 kw gas = 40kw electricity export100 kw gas = 90 kw gas export
Pressure swing absorber – scrubs CO2 and CO and other trace gassesBalanced with .5 mw engine for process CHP
Planning variation requiredPermit variation required
Time Lines
Ground raising has commenced
Civils - out to tendercommence April 2012
Plant - detailed design underwayfinal contract 13 January 2012on site commencement 2012
Operation - first waste reception mid April 2013final handover November 2013