vol 10 commissioning final-01-12-13 10 commissioning...renewable energy guidelines nov. 2013 iii...

38
Renewable Energy Guidelines Volume 10 Pakistan Poverty Alleviation Fund, Islamabad Commissioning Guidelines PV MHP

Upload: others

Post on 11-Mar-2020

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

Renewable Energy Guidelines 

Volume 10 

Pakistan Poverty Alleviation Fund, Islamabad 

 

Commissioning Guidelines PV ‐ MHP 

 

Page 2: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

Copyright © Pakistan Poverty Alleviation Fund – 2013 

Reproduction is authorized provided the source is acknowledged and provided a reference copy is being sent to 

PPAF and the reproduction is not sold. 

For further information: Pakistan Poverty Alleviation Fund, www.ppaf.org.pk 

Note: The information contained within this document has been developed within a specific scope and might be 

up‐dated in the future. 

 

 

The Renewable Energy Guideline Series has been developed by the German‐Pakistan project “Development of 

Hydropower  and  Renewable  Energy  (HRE)  in  Khyber‐Pakhtunkhwa”,  funded  by  German  Development  Bank 

(KfW) on behalf of “Ministry for Economic Cooperation and Development” (BMZ). 

 

Pakistan Poverty Alleviation Fund (PPAF) 

Project team: 

Mr. Zaffar Pervez Sabri 

Senior Group Head, Public Goods and Services 

Mr. Kamal Afridi 

General Manager, Water, Energy & Climate Change 

Mr. Shaukat Ali 

Renewable Energy Specialist   

Contact  address:  

1‐Hill View Road, Banigalla, Islamabad 

PAKISTAN 

E‐mail: [email protected] 

Phone: (+92‐51) 261 3935‐50 

 

Name of Consultants: 

INTEGRATION 

Team:  

Dr. Ulrich Frings ‐ Team Leader 

Mr. Sher Khan – Deputy Team Leader 

www.integration.org  

Author: 

Ulrich Frings Mohammed Sadeq 

 

 

Date: June, 2013 

 

Page 3: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

     

  Renewable Energy Guidelines  Nov. 2013 i

Volume 10 Commissioning Guidelines 

Guidelines & Manuals 

Volume 1: Life Cycle Cost Analysis in MHP Planning 

Volume 2: Community Contribution Aspects in Rural Power Supply Systems 

Volume 3: General Design Criteria on MHPs 

Volume 4: Design Aspects of Community PV Systems 

Volume 5: Operation & Maintenance Aspects of MHPs 

Volume 6: Quality Assurance & Control of Civil Works 

Volume 7: Health, Safety & Environmental Aspects in Civil Works 

Volume 8: Transmission & Distribution in Rural Power Supply Systems Design ‐ Specification ‐ Installation 

Volume 9: Electro‐Mechanical Equipment for MHPs Design ‐ Specification ‐ Installation 

Volume 10: Commissioning Guidelines PV ‐ MHP 

Volume 11: Micro/Mini Hydropower Design Aspects 

Volume 12: Civil Works in Rural Power Supply Systems 

   

Page 4: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

 ii  Renewable Energy Guidelines  Nov. 2013

Volume 10 Commissioning Guidelines

Table of Contents 1  Commissioning of MHP Systems ................................................................................................ 1 

  Salient features ................................................................................................................... 1 1.1  Technical status................................................................................................................... 1 1.2  Performance check of installation .................................................................................... 11 1.3  Performance test .............................................................................................................. 15 1.4  Installation completion certification and remarks ............................................................ 15 1.5

2  Commissioning of PV plants ..................................................................................................... 19   Mechanical and visual inspection for PV‐ array area ........................................................ 20 2.1  Measurement of PV array ................................................................................................. 22 2.2  Mechanical and visual inspection for dc/ac Inverters ...................................................... 23 2.3  Measurement of dc/ac inverters ...................................................................................... 24 2.4  Mechanical and visual inspection for ac/dc ‐ dc/ac island inverter.................................. 25 2.5  Measurement of ac/dc/ac island inverter ........................................................................ 26 2.6  Mechanical and Visual inspection for distribution board ................................................. 27 2.7  Mechanical and visual inspection for battery/string/inverter fuse .................................. 28 2.8  Mechanical and visual inspection for battery/string/inverter fuse: ................................. 28 2.9  Mechanical and visual inspection for battery/string/inverter fuse .................................. 28 2.10  Mechanical and visual inspection for battery/string/inverter fuse: ................................. 28 2.11  Mechanical and visual inspection for battery/string/inverter fuse .................................. 29 2.12  Measurement of battery bank .......................................................................................... 29 2.13  Testing internal installation (Powerhouse) ....................................................................... 30 2.14  Training, awareness protocol ............................................................................................ 31 2.15  General installation testing & results ............................................................................... 32 2.16

    

Acronyms and abbreviations 

A    Ampere AC    Alternating Current AKRSP    Aga Khan Rural Support program ACSR    Aluminium Conductor Steel reinforced CDM    Clean Development Mechanism CO    Community Organizations  DC    Direct Current EC    European Commission ELC    Electronic Load Controller E&M    Electro‐mechanic FDC    Flow Duration Curve GI    Galvanized Iron 

GIS    Geographic Information System GIZ    German Technical Cooperation GOs    Government Organization GPS    Global Positioning System HDPE    High Density Polyethylene H&S    Health & Safety hrs    hours HV    High Voltage Hz    Hertz (frequency unit) INGOs    International Non Governmental Organization KfW    German Development Bank kW    Kilo Watt 

Page 5: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

     

  Renewable Energy Guidelines  Nov. 2013 iii

Volume 10 Commissioning Guidelines 

kWh    Kilo Watt Hour kV    Kilo Volt LED    Light‐Emitting Diode Lit    Liter LSOs    Local Support Organizations  LT    Low Tension LV    Low Voltage MCB    Moulded Circuit Breaker MCCB    Moulded Case Circuit Breaker MDPE    Medium Density Polyethylene MHP    Mini/micro Hydropower Plant MSDS    Material Safety Data Sheets NGOs    Non‐Governmental Organizations  O&M    Operation and Maintenance PF    Power Factor PCD    Pitch Circle Diameter PPAF    Pakistan Poverty Alleviation Fund POs     Partner Organizations (COs) PPIB    Private Power Infrastructure Board PURE    Productive Use of Renewable Energy  PPE    Personal Protective Equipment PV    Photovoltaics PVC    Polyvenylchloride SM     Social Mobilizer  SRSP    Sarhad Rural Support Program RCBO    Residual Current Breaker with Overload Protection SSLS    Solar Street/home Lighting System Rs.    Pakistani Rupees T&D     Transmission and Distribution  TOP    Terms of Partnership V    Volt WOs     Women Organizations 

XLPE    Cross‐linked polyethylene 

Page 6: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting
Page 7: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

     

  Renewable Energy Guidelines  Nov. 2013 1

Volume 10 Commissioning Guidelines 

1 Commissioning of MHP Systems 

Salient features 1.1

 Name of plant:    Name of Owner:   

 Location:       

 Manufacturer:    Supplier/Installer:   

 Ownership:  Private/community  No of households:   

 Gross head  ___m;   Design flow  m³/sRated output _______kW 

 

 System:  Single‐phase/Three‐phaseVoltage 

_____V; Maximum current 

_______A

 Start of construction of project:  day/month/year   

 Commissioning date:  day/month/year   

Technical status 1.2

1.2.1 Intake       

 Type of intake:      Permanent/Temporary 

 If permanent, any cracks observed:  Yes/No 

 Any leakage observed:      Yes/No 

 Trash rack at intake:      Installed/Not installed  If installed, Clearance:  mm,   

 Any structured cracks observed:    Yes/No 

 Type of Trash rack:      metal/local (special) 

 Flow controlling mechanism:  Sluice gate/wooden stop logs/bush‐boulder/Others (specify)

 Remarks on Intake ‐ Briefly discuss any major defects observed.     

1.2.2 Headrace       

 Length of headrace (section 1):  m Type of headrace (section 1): open earth/open 

 Rectangular/Trapezoidal/Triangular  Cemented, DPE conduit/others (specify) 

 Length of head race (section 2):  m Type of head race (section 2): open earth/open 

 Rectangular/Trapezoidal/Triangular  cemented/HDPE conduit/others (specify) 

 Length of headrace (section 3):  m Type of head race (section 2): open earth/open 

 Rectangular/Trapezoidal/Triangular  cemented/HDPE conduit/others (specify) 

Page 8: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

 2  Renewable Energy Guidelines  Nov. 2013

Volume 10 Commissioning Guidelines

 Any leakage observed:      Yes/No 

 Any cracks observed:      Yes/No 

 Remarks on Headrace – Briefly discuss any major defects observed     

1.2.3 Forebay             

 Type of Forebay:      Stone masonry in c/RCC/Others (specify) 

 Trash rack:      Installed/Not installed   

 If installed, Clearance:  mm           

 Any structured cracks observed:    Yes/No     

 Type of Trash rack:      metal/local (specify)    

 Spillover:      incorporated/not incorporated  

 Flushing arrangement:      Works weIl/defects observed   

 Air vent pipe:      installed/not installed   

 Remarks on Forebay ‐ Briefly discuss any minor/major defects observed:     

   

1.2.4 Gravel trap/settling basin 

         

 Type:      Stone masonry in c/RCC/Others (specify) 

 Flushing arrangement:      Works weIl/defects observed   

 Remarks on Gravel Trap ‐ Briefly discuss any minor/major defects observed     

   

1.2.5 Penstock pipes             

 Penstock Length (section 1/top):  m  Section 1: HDPE /GI/MS; Thickness  ______mm;OD

 Penstock Length (section 2/mid):  m  Section 2: HDPE /GI/MS; Thickness  ______mm;OD

 Penstock Length (section 3/bot):  m  Section 3: HDPE /GI/MS; Thickness  ______mm;OD

 Any leakage observed in Penstock:    Yes/No     

 Ground clearance maintained: 

    Yes/No (minimum 300 mm) 

 Expansion Joint:      Flange connected/Welded   

 Any leakages in expansion joint:    Yes/No     

Page 9: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

     

  Renewable Energy Guidelines  Nov. 2013 3

Volume 10 Commissioning Guidelines 

 No. of joints:      ____ Nos     

 Maximum expansion measured:    J1=______  J2=_____  J3=____  J4=______ 

 HDPE conduit buried:      Yes/No     

 No. of Penstock Sections:      ___________       

 Remarks on Penstock pipes ‐ Briefly discuss any major defects observed       

   

1.2.6 Anchor blocks/support pier           

 Any cracks observed in Anchor blocks:  Yes/No     

 Any cracks observed in support piers:  Yes/No     

 Remarks on Anchor blocks/support piers ‐ Briefly discuss any minor/major defects observed        

1.2.7 Powerhouse           

 Powerhouse size (internal):  L______m  B____ m           H  _______m 

         Construction:  Stone masonry in c/Dry stone/Others (specify) 

 Powerhouse roof:  Corrugated GI/Plain GI/Others (specify) 

 Powerhouse floor:  Compacted earth/Dry stone slabs/Cemented 

 Adequate working space for O/M:  Yes/No       

 Cleanliness:  Yes/No       

 Adequate lighting in PH:  Yes/No       

 Free of undue leakages:  Yes/No       

 Tailrace safely disposed off:  Yes/No       

 Earthing done properly:  Yes/No (Earth resistance < 10 ohm:) 

 Remarks on Powerhouse ‐ Briefly discuss any major defects observed        

 

Page 10: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

 4  Renewable Energy Guidelines  Nov. 2013

Volume 10 Commissioning Guidelines

1.2.8 Tailrace           

 Construction:  Stone masonry in c/Earth/Others (specify) 

 Section:  Rectangular/Trapezoidal/Triangular  Condition of tailrace:  good/bad   

 Any cracks observed in structure:  Yes/No       

 Remarks on Tailrace ‐ Briefly discuss any major defects observed       

     

 

1.2.9 Turbine and driving system           

 Type of Turbine:  Pelton/Cross flow / Francis / others (Specify) 

 Pressure gauge installed:  Yes /No        If yes, Size of gauge:    ______ kg/cm²    Pressure head during plant operation:    ______ kg/cm²    Pressure head during plant closure:    ______ kg/cm²    Type of valves installed:  Spear valve/Gate valve: 

 Runner mounting:  Vertical/Horizontal   

 Driving System:           

 Type of Belt:  V ‐Belt/Flat Belt OR Direct coupling/others (Specify)

 Size /No:  __________  Size      _________No 

 Alignment:  Well aligned/deviation observed 

 Remarks on Turbine and driving system ‐ Briefly discuss any m句or defects observed 

1.2.10 Generator               

 Specification:               

 Type:    Synchronous/Induction      Phase:    3 ‐phase/ 1‐phase  Voltage:  ______V  Capacity:  _______kW  PF      _______  RPM    _______min‐1  Full load current:  _______A  Frequency:  _______Hz          Insulation class:        Protection class:  _______IP 

 Manufacturer:               

 Earthing done properly:        Yes/No (Earth resistance < 10 ohm) 

 Remarks on Generator: ‐ Briefly discuss any major defects observed      

   

Page 11: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

     

  Renewable Energy Guidelines  Nov. 2013 5

Volume 10 Commissioning Guidelines 

 

1.2.11 Load controller and ballast         

 Load controller type:        ELC/ELC‐Extension/IGC/Others (Specify) 

 Capacity:  _______kW          Rating voltage:  _______Volt  Current:  ________A    Condition of load controller:      operates well/deviation observed    .                Ballast:                 

 Ballast heater type:     Immersed in tail race /Immersed in separate water tank 

         /Wall mounted space heaters/Others (specify) 

 Ballast heater specifications:  __________V; _______W;          Quantity ______nos. 

 Remarks on Load Controller: ‐ Briefly discuss any defects observed.      

   

1.2.12 Control panel and switchgear         

 Protection provided:          Yes  No   

     Over voltage/under voltage:    _____  ______   

     Over frequency/under Frequency:  _____  ______        Overload/Short circuited:    _____  ______   

 Are the installed fuses/breakers of adequate size:    Yes/No    

 Size of MCCB/MCB:  __________A  Rated breaking capacity of the breaker:  ______KA

 Type of Fuse installed:    Rating: ______ A   

 Emergency switch and feeder switch working properly:      Yes/No.   

 Lightning arrestors installed at the power house:      Yes/No.   

Earthing of lightning arrestors properly done (R<10 Ohm) 

    Yes/No  _____Ohm 

all metal parts in power house well connected to earth      Yes/No  ____ Ohm 

central neutral connector installed where all metal parts are directly connected to (with screws) 

    Yes/No   

 Measuring instruments incorporated in the Control panel to measure the following:   

   Main voltage and Ballast voltage  Yes (   )   No (   )    2.  Load currents        Yes (   )   No (   )    3.  Frequency        Yes (   )   No (   )    4.  Power (kW)      Yes (   )   No (   )    5.  Energy (KWh)  Yes (   )   No (   )    6.  Reactive Energy (kVAr)  Yes (   )   No (   )    6.  Indicator lamps       Yes (   )   No (   )   

 7.  Time totalizer (turbine operating hours)  Yes (   )   No (   )   

Page 12: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

 6  Renewable Energy Guidelines  Nov. 2013

Volume 10 Commissioning Guidelines

 Remarks on Control Panel and switchgears ‐ Briefly discuss any defects observed       

 

1.2.13 Cable, connections and supply   

Type of power cable used in the power house:  

Size of Cable 

Cable jointing and connections properly?  

Type of Service cable used for hooking up:  

Size of Cable: 

Tapping connection done properly?  

Consumer end voltage within limit? 

Receiving end voltage at peak load: 

At start of village: _____Volt  

At mid of village:______ Volt 

At end of village:______ Volt 

  

Copper/Aluminium 

________mm² 

  Yes/No 

Concentric/Twin /flat/Others 

_________mm² 

Yes/No 

Yes/No (total V drop < 8%) 

 

voltage trop in %: ________ 

voltage drop in %_________ 

voltage drop in %:_________ 

1.2.14 Transmission/distribution lines  

 Type of transmission/distribution 

 Length of the system: 

 Voltage transmission line: 

Voltage distribution line: 

Type of cable: 

Type of Pole: 

Overhead/underground 

_________m;  

________kV 

________kV 

ACSR/ABC/PVC Mild 

Steel/Wood/Concrete/Other 

Page 13: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

     

  Renewable Energy Guidelines  Nov. 2013 7

Volume 10 Commissioning Guidelines 

Lightning arrestor  installed at each end of  line and at every lightning prone areas of the system. 

∙ If neutral on top, is it grounded directly? 

∙ Are earthings provided to each lightning arrestor? 

∙ Are all joints along the earth path being brazed/soldered? 

∙ Should line patrolling be carried out before commissioning? 

∙ Is measured ground resistance < 10 ohm? 

∙ Are Fuses/switches (DB) provided at branch points of the distribution lines for load more than 10 kW. Are DB boxes weatherproof and rain protected? 

∙ Shall pole stays be used at all poles at angle and at line 

ends? 

∙ Preservative or anti corrosion paint (Black Japan paint) applied on pole foundation? 

 

∙ Safety clearances adequate? 

General clearances: Ground to Wire: Off road:

  Across road:

  Along sides of motor road:

 Insulator type acceptable? 

 

Yes/No 

Yes/No 

Yes/No 

Yes/No 

Yes/No 

 

Yes/No 

 

Yes/No 

Yes/No 

 

Yes/No 

________m 

________m 

_________m 

Yes/No 

Remarks on electrical lines: Briefly discuss any defects observed in construction, finishing, cable jointing and terminations, service cable tapping, bedding, clearance and safety of transmission and distribution system.      

Page 14: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

 8  Renewable Energy Guidelines  Nov. 2013

Volume 10 Commissioning Guidelines

Transformers:                Type:_________      No:__________   Capacity:      _________ kVA   _________ kVA   _______ kVA  Nominal losses:     no load________    ________ load          no load________    _________load          no load_________    _________load  installed at:      masonry/concrete stands/between poles/inhouse/other          installation height above ground:_______ m  transformers well protected against any form of unauthorized access:      Yes/No  Cable with connected:                  Yes/No  lightning arrestors installed    Yes/No   Resistivity:_______ Ohm      feeder switches and fuses installed and well working:           Yes/No  earthing installed and workable:    Yes/No     __________Ohm 

Remarks on Transformers: 

1.2.15 Subscriber connection 

             

Power Limiters installed: 

    Yes/No           

Power limit               

Number                 

Limit switch type                 

Remarks                 

House Connections:                 

connection:  wires/single/cables/PV cables/other  diameter:_____mm² 

Meter:  No/Mechanic/Electronic  _____nominal current A 

safety devices installed 

Yes/No  Type: Ordinary fuses/breaker/earth fault current switch 

    Nominal A:_________    fault current:__________ mA 

 

Page 15: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

     

  Renewable Energy Guidelines  Nov. 2013 9

Volume 10 Commissioning Guidelines 

1.2.16 Manuals and other related documents 

All the specified manuals are supplied (Acceptable)       口   

Few of the specified manuals are supplied 

(Not acceptable ‐ Non Critical)    口   

Non of the specified manuals are supplied (Not acceptable‐ Critical)     口   

Confirm supply of following manuals: 

           

(a) Operation, Maintenance and trouble shooting manual.  Yes/No

(b) Check list for fault detection and communication with manufacturer, checklist for   normal operation (bearings, instruments, belts, coupling rubbers, noise vibrations).  Yes/No

(c) Technical manual of as ‐ built plant. 

Yes/No

(d) Sample (master copy) of operation sheet for the operator (e.g. data, instrument   readings, observations, reading interval, signature etc).      Yes/No

(e) Sample (master copy) of maintenance sheet for the operator (lubrication intervals,   check intervals, signature etc). Wiring diagram of power station with description of all   

fuses (type and size).            Yes/No

(f) Address, phone number of suppliers and sub‐suppliers for spare parts, ordering and   guarantee claims.              Yes/No

(g) Wiring diagram of power station with description of all fuses and switches (type and size)   (h) operation diary  Yes/No

              Yes/No

Remarks:       

             

1.2.17 Spares parts and tools         

List the spare parts and tools supplied to the plant:         

Spare parts  Tools 

Description  Remarks/Condition  Description  Remarks/Condition

     

     

Comment on supplied v/s quoted list of spare parts and tools:   

Recommend any additional spare or tool that is required for the site and equipment condition:    

Page 16: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

 10  Renewable Energy Guidelines  Nov. 2013

Volume 10 Commissioning Guidelines

1.2.18 Other remarks and observations     

 a. All power and control cable within the powerhouse are armored cable        (or PVC cables in HDPE conduit) and are either buried or in trench:  Yes (   )  No (   )  b. Power and control cable terminations without control boxes are     

   marked/numbered and connected through terminal connectors.  Yes (   )  No (   ) 

 c. Equipment outer surface is painted with matching color where needed.  Yes (   )  No (   ) 

 d. Equipment metal parts are earthed with all different parts connected     

   in parallel to one star‐point (central neutral point).  Yes (   )  No (   )  e.  Connecting underground cables along straight‐through sections are     

   done using jointing kits.  Yes (   )  No (   ) 

 Remarks:     

   

Page 17: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

     

  Renewable Energy Guidelines  Nov. 2013 11

Volume 10 Commissioning Guidelines 

Performance check of installation 1.3

1.3.1 Situation 1 ‐ Static condition  

(Nozzles,  valves  all  closed;  fore  bay  drain  closed;  Approximately  required  amount  of  water diverted  toward  headrace  and  penstock  pipe  slowly  filled  and  water  expelled  via  spillover channel.) 

Static head indicated by pressure gauge in powerhouse, Hg = ______m (1 bar = 1 kg/cm² = 10m) 

1. Flow‐controlling mechanism at intake 

a. Flow c an completely be blocked if desired, and amount of water flowing toward 

headrace can be controlled           (acceptable)  口 

b. Flow cannot be stopped and controlled     (not acceptable ‐ non critical)  口 

2. Free board in Headrace Canal 

a. Free board of at least 30 cm or half the height of water at design flow is maintained 

throughout             (Well and Acceptable)  口  

b. Free board of at least 10 cm is maintained throughout     (acceptable)   口 

c. Free board less than 10 cm       (not acceptable non critical)  口 

3. Headrace performance: 

a. Minor leakage or no leakage through headrace     (Acceptable)  

  口 

b. Minor leakages but in many parts of the headrace (Not acceptable‐ non critical) 

  口 

c. Major leakages and cracks in the structure     (Not acceptable‐critical)

  口 

4. HDPE pipe Burial 

a. All HDPE sections along headrace are buried or covered    (acceptable)  口 

b. Any portion not buried or not covered     (not acceptable ‐ critical)  口 

5. Spillway 

a. All of design flow can safely be expelled from the spillover channel (acceptable)  口 

b. All design flow can not be expelled safely from spillway channel  

              (not acceptable ‐ critical)  口 

6. Penstock 

a. No water leakage from penstock joints/welded section     (Acceptable)   口 

b. Water leakage from penstock joints/welded section (not acceptable ‐ critical)   口 

7. Support piers and Anchor blocks 

a. Metal penstocks are adequately supported to form straight lengths (acceptable)

  口 

b. Penstock line sagging         (not acceptable ‐ critical)   口 

c. Cracks in the structure         (not acceptable ‐ critical)   口 

Page 18: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

 12  Renewable Energy Guidelines  Nov. 2013

Volume 10 Commissioning Guidelines

8. Earth resistance Test 

a. Neutral earthing at powerhouse < 10 ohm       (acceptable)   口 

b. > 10 ohm           (not acceptable ‐ non critical)   口 

c. > 50 ohm           (not acceptable ‐ critical)   口 

  Value: ______Ohm 

d. Any other remarks for performance check during static condition 

 

 

1.3.2 Situation 2 ‐ Dynamic condition         

(All valves are slowly opened to maximum open condition so as to operate the set at full flow condition. Forebay should still be filled with water up to the spillover channel crest level. Bring more water if required) 

Note dynamic head indicated by the pressure gauge in powerhouse, Hn =___________m 

Water discharge at tailrace, Q =_______m³/s 

(approximate measure by means of weir at tailrace) 

                       

  Gen. 

volt

   

Gen. Freq.  _____Hz 

 Feeder line current  __________A 

Ballast volt/current _____(full ballast; (no village load) 

  ____V   

         

2  Gen. 

volt

_____  V Gen. Freq. ___ 

HzFeeder line 

Ballast volt/current______(village load = 50% of rated plant capacity) 

       

 Volt. Change_____ V 

Freq.change__ Hz ______current A

                       

2a  Switch OFF village load 

Time to return to steady state condition: 

sec 

                 

2b  Switch ON village load 

Time to return to steady state condition: 

sec 

                 

3  Gen. voltage: ________________V 

Gen. Freq. ____Hz Feeder line  Ballast volt/current_______(set ‐ zero)  

  Volt. change ______V 

Freq. Change__Hz current _____A Pf of village load  ____________  

3a Switch OFF village load 

Time to return to steady state condition:  _______ sec 

3b Switch ON village load 

  Time to return to steady state condition:  _______ sec 

3c For Micro Hydros: Power factor of village load should be maintained at no worse than 0.8. For this, if some tube lamps are used, total wattage due to tube lamps should not be more than about one ‐ third of total wattage due to incandescent lamps (or resistive loads). 

4 Calculate approx. total power produced, P = Generated voltage x Feeder line current x Power factor  

  Give the Value power produced,  kW         

Page 19: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

     

  Renewable Energy Guidelines  Nov. 2013 13

Volume 10 Commissioning Guidelines 

P:______ 

  Guaranteed power produced             (acceptable)   口 

  Guaranteed power not produced       (not acceptable ‐ critical)  口 

               

 5 For Micro Hydros: Calculate approximate power factor = Cos [tan‐1 {P2 x 1.73} / {P 1 + P2}), Where, P1 = total resistive wattage; P2 = total tube lamp wattage; power factor of tube lamp 0.5 

 6  Calculate water to wire efficiency = P x 102/(Hg x Q) = 

 7  Calculate MHP efficiency = P x 102/(Hn x Q)=    

8   The following tests are mandatory during commissioning: 

Checking operation of mechanical and electrical protection systems; Compared to 

nominal values trip setting of the protection devices should be as follows (both 

synchronous and induction generator where applicable) 

  1. Over voltage at 10%  2. Under Voltage at 20% 

  3. Over frequency at 15%  4. Under frequency at 10% 

Insulation test of cables, generator, transformer and braking system 

No‐load test with AVR Excitation test 

Loading test (Load acceptance, load rejection, output test, stability of 

controller/governor) 

Efficiency test water to wire using calibrated test ballast and instruments 

1.3.3 Other tests and observations on dynamic situation:   

 1. Check for unusual noises and vibrations, bearing temperature and other anomalies: (with total ballast 

 and without excitation):     

   A=Acceptable:  NA=Not acceptable     

 Rated  Vibration  Noise  Bearing Temp  Body Temp 

 Speed           

20% 

Un‐noticeable (A)  Uniform high pitch sound  Cool to touch (A)  Warm to touch (A) 

Minimum (A)  (A)  Hot to touch (A)  Hot to touch (A) 

Noticeable (NA)  Non uniform high or low  Too hotωtouch (NA)  Too hot to touch 

    pitch sound (NA)    (NA) 

50% 

Un‐noticeable (A)  Uniform high pitch sound  Cool to touch (A)  Warm to touch (A) 

Minimum (A)  (A)  Hot to touch (A)  Hot to touch (A) 

Noticeable (NA)  Non uniform high or low  Too hot to touch (NA)  Too hot to touch 

    pitch sound (NA)    (NA) 

100% 

Un‐noticeable (A)  Uniform high pitch sound  Cool to touch (A)  Warm to touch (A) 

Minimum (A)  (A)  Hot to touch (A)  Hot to touch (A) 

Noticeable (NA)  Non uniform high or low  Too hot to touch (NA)  Too hot to touch 

    pitch sound (NA)    (NA) 

 2. Power cables temperature (near termination/contact point) 

   

 a.  Cool     Acceptable      口 

 b. Warm   Not Acceptable – Critical  口 

 3. Meter readings as compared to readings of a hand held test meter readings   

Page 20: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

 14  Renewable Energy Guidelines  Nov. 2013

Volume 10 Commissioning Guidelines

 a.Within 5%                 ( acceptable)  口 

 b. More than 5%           (not acceptable ‐ non critical)  口 

 

4. Earth fault test trip and simulation test (in case of under ground lines) 

a. Successful               (acceptable)  口 

b. Unsuccessful           (not acceptable ‐ non critical)  口 

5.  110% sustained over current simulation test result 

a. De excites               (acceptable)  口 

b. Under‐voltage operation below 20%     (not acceptable ‐ critical)  口 

c. Feeder breaker trips             (acceptable)  口 

d. Generator over heats         (not acceptable ‐ critical)  口 

e. Nothing happens (acceptable provided feeder load switching off does not cause more than 10% 

over voltage or excitation breakers trip) 

6.  120% sustained over current simulation test result 

a. De excites               ( acceptable)  口 

b. Under‐voltage operation below 20%     (not acceptable 一 critical)  口 

c. Breaker trips               (acceptable)  口 

d. Generator over heats         (not acceptable ‐ critical)  口 

e. Nothing happens (not acceptable – critical) this may cause over voltage even for ballast heaters 

when feeder load gets switched off) 

T. Sustained over 10 % voltage simulation test 

a. Excitation breakers trip             (acceptable)  口 

b. Nothing happens          (not acceptable – critical)  口 

8.  For both synchronous and induction generator, 

a. Steady state voltage deviation: within ‐ 5% to +5%     (acceptable)  口 

b. Beyond ‐ 5% to + 5%         (not acceptable ‐ critical)  口. 

9.  For synchronous generator (ELC), 

a. Steady state frequency deviation: within ‐5% to +5%     (acceptable)  口 

b. Beyond ‐5% to +5%         (not acceptable ‐ critical)  口 

10.  In case of induction generator (IGC), 

a. Steady state frequency deviation: within ‐5% to + 10%     (acceptable)  口 

b. Beyond ‐5% to + 10%         (not acceptable ‐ critical)  口 

11. Transient voltage and frequency deviations due to sudden load changes 

a. Within 15% and 20% respectively           (acceptable)  口 

b. Beyond that             (not acceptable)    口 

12. Any other remaining remarks or observation on dynamic test performed 一 

  (Requirements as per the prevailing standards for MHP installation should be met) 

Page 21: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

     

  Renewable Energy Guidelines  Nov. 2013 15

Volume 10 Commissioning Guidelines 

Performance test 1.4

 The performance test includes a 36 hour continuous operation for Micro hydropower and 72 hours continuous operation for Mini hydropower plants.  

Operation recorded (hourly basis) in operation diary:          Yes/No 

Plant operation was well without any defect/interruption in operation    Yes/No 

if No please specify:      

 

Check for unusual noises   

   A=Acceptable:  NA=Not acceptable     

   Vibration  Noise  Bearing Temp  Body Temp 

 

Un‐noticeable (A)  Uniform high pitch sound  Cool to touch (A)  Warm to touch (A) 

Minimum (A)  (A)  Hot to touch (A)  Hot to touch (A) 

Noticeable (NA)  Non uniform high or low  Too hot touch (NA)  Too hot to touch 

    pitch sound (NA)    (NA) 

 2. Power cables temperature (near termination/contact point) 

   

 a.  Cool     Acceptable      口 

 b. Warm   Not Acceptable – Critical  口 

 3. Meter readings as compared to readings of a hand held test meter readings   

 a. Within 5%                 ( acceptable)  口 

 b. More than 5%           (not acceptable ‐ non critical)  口 

Installation completion certification and remarks 1.5

 1. Installation fully accepted with 1 year warranty   

 Signature of Inspector  Signature of Owner Signature of Installer/Supplier 

 Name:  Name:  Name: 

 Date:  Date:  Date: 

 2. Installation conditionally accepted provided all defects are of non‐critical type and that they 

 would be corrected within defects correction period of 1 year. ("Non critical") 

 Signature of Inspector  Signature of Owner Signature of Installer/Supplier 

 Name:  Name:  Name: 

Page 22: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

 16  Renewable Energy Guidelines  Nov. 2013

Volume 10 Commissioning Guidelines

 Date:  Date:  Date: 

 3. Installation not accepted as one or more of the defects are of critical type_ 

   ("NOT accepted ‐ critical") 

 Signature of Inspector  Signature of Owner  Signature of Installer 

 Name:  Name:  Name: 

 Date:  Date:  Date: 

     Witness 1:      Witness 2:      Witness 3:  

Note: Please also attach the photographs of various civil and electromechanical components along with the testing commissioning format    

Flow Measurement Methods: 

 

1 ‐ Salt Dilution Method 

 

Water flow measurement by salt dilution method of _____________________ River 

Date/Time: 

Weather: 

Salt used: _______ gram  Water temp:____ °C 

 

Baseline Conductivity:___________________ mS (i.e. conductivity in the river before pouring salt 

solution) 

Salt constant k = _______ 

 

Time (sec) 

05  10  15  20  25  30  35  40  45  50  55  60  Sum 

Water conductivity in µS 

Minutes 

1                           

2                           

3                           

4                           

5                           

6                           

7                           

8                           

9                           

Page 23: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

     

  Renewable Energy Guidelines  Nov. 2013 17

Volume 10 Commissioning Guidelines 

10                           

TOTAL:   

 Area (A) under the curve = 

 

Note that the "Area" here is the area under the graph of conductivity in μS in the vertical axis and time 

in second in the horizontal axis excluding the baseline conductivity (i.e., conductivity measure before 

pouring the salt solution upstream). Hence, the units of "Area" under the graph are μS*Sec. 

 Q=Mk/A 

 

Note: 

Use separate sheet if other method has been used for flow 

measurement. 

Give minimum estimated flow using MIP method. 

 

 

 

Page 24: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

 18  Renewable Energy Guidelinesl  Nov. 2013 

Volume 10 Commissioning Guidelines 

Power Output Test Form                                           

Name of MHP:                    Owner:                    Date     

Location                          District:                         

No  Village Load Power     Ballast Load Power 

  

UAN IA  pf  PA  UBN  IB  pf  PB  UCN  IC  pf  PC Total Power 

Freq. UAb  UBb  UCb  PA  PB  PC Total Ballast Power 

weir height 

Discharge 

Pressure gauge 

Valve position 

Remarks 

   (V)  (A)     (kW)  (V)  (A)     (kW)  (V)  (A)     (kW) (kW)  (Hz)  (V)  (V)  (V)  (kW) (kW)  (kW)  (kW)  (m) (m³/s) (kg/cm²) (%)    

1                                                                               

2                                                                               

3                                                                               

4                                                                               

5                                                                               

6                                                                               

Design Head (m):         Design Flow (m³/s):        Design Power (kW):        Minimum Power requirement (kW):     

Actual Head (m):        Actuval Flow (m³/s):        Actual Power (kW):        Stream Flow at Intake (m³/s):      

                                                      

I/We hereby certify that I/we have measured and ferified power outpur from the MHP.                        

 I/we hereby certify that the measured power output for the design flow of this installation is _______ kW                  

                                                                                

Data Recorded by                             Name                          Signature and Date       

Owners's Representative:                                                

                                                                                

Installer's Representative as witness                                            

                                                                                

Inspector:                                                      

                                                                                

Page 25: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

       

  Renewable Energy Guidelines  Nov. 2013  19

Volume 10 Commissioning Guidelines 

2 Commissioning of PV plants 

  Date:         Region:         

Village / Area:         

Installation Company:        

Technician name:       , Tel:        (From Installation Company: ___________________________________) 

PPAF responsible:       , Tel:           (Name/ Function:  __________________________ / ________________) 

PO responsible:       , Tel:           (Name/ Function:  __________________________ / ________________) 

Community responsible:       , Tel:           (Name/ Function:  __________________________ / ________________) 

 

Page 26: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

 20  Renewable Energy Guidelinesl  Nov. 2013 

Volume 10 Commissioning Guidelines

Mechanical and visual inspection for PV‐ array area 2.1

PV String array      Loose        Tight       

Fence        Loose        Tight 

Cable connections    Loose        Tight      Rust 

Shading on the PV array  Yes        No 

Vegetation under PV array  Yes        No 

 

PV Module Serial No. 

       

       

       

       

       

       

       

 

   

Page 27: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

       

  Renewable Energy Guidelines  Nov. 2013  21

Volume 10 Commissioning Guidelines 

dc/ac inverters:  Type /Serial Nos. 

ac/dc/ac island inverters:  Type / Serial Nos. 

___________________________________  ___________________________________ 

___________________________________  ___________________________________ 

___________________________________  ___________________________________ 

___________________________________  ___________________________________ 

___________________________________  ___________________________________ 

___________________________________  ___________________________________ 

___________________________________  ___________________________________ 

 

Page 28: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

 22  Renewable Energy Guidelinesl  Nov. 2013 

Volume 10 Commissioning Guidelines

Measurement of PV array  2.2

(please take the measure at sunshine) 

No 

Electrical Equipment 

To be Measured 

Voltage (V)  Current (A)  Connected to 

Remark Ref 

(STC) 

Measured  Var 

Ref 

(STC) 

Measured  Var  dc/ac inverter no. MPP‐Tracker no. // to string no. 

1  PV String 1 / DC             ___________________________   

               ___________________________   

               ___________________________   

               ___________________________   

               ___________________________   

               ___________________________   

               ___________________________   

               ___________________________   

               ___________________________   

               ___________________________   

               ___________________________   

Remark:                        

                         

                         

                   

Recommendation:                     

                         

                         

                   

   

Page 29: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

       

  Renewable Energy Guidelines  Nov. 2013  23

Volume 10 Commissioning Guidelines 

Mechanical and visual inspection for dc/ac Inverters  2.3

 Type or No.                    

Functional        Yes        No 

Mounting        Loose        Tight 

Cable connection      Loose        Tight     

Noise          Normal       High 

Page 30: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

 24  Renewable Energy Guidelinesl  Nov. 2013 

Volume 10 Commissioning Guidelines

Measurement of dc/ac inverters  2.4

Type or No.                    

No 

Electrical Equipment 

To be Measured 

Voltage (V)  Current (A)  Connected to 

Remark 

Ref 

(STC) 

Measured Var Ref

(STC) 

Measured Var  Distribution box no.  Fuse no. 

 _______________/ AC  220‐240      ……. (Max)     

  

 _______________/ AC  220‐240      ……. (Max)     

  

 _______________/ AC  220‐240      ……. (Max)     

  

 _______________/ AC  220‐240      ……. (Max)     

  

 _______________/ AC  220‐240      ……. (Max)     

  

 _______________/ AC  220‐240      ……. (Max)     

  

 _______________/ AC  220‐240      ……. (Max)     

  

 

Remark:                        

                           

Recommendation:                     

                         

                           

 

Page 31: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

       

  Renewable Energy Guidelines  Nov. 2013  25

Volume 10 Commissioning Guidelines 

Mechanical and visual inspection for ac/dc ‐ dc/ac island inverter  2.5

 Type or No.                    

 

Functional        Yes        No 

Mounting        Loose        Tight 

Cable connection      Loose        Tight     

Noise          Normal       High 

 

   

Page 32: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

 26  Renewable Energy Guidelinesl  Nov. 2013 

Volume 10 Commissioning Guidelines

Measurement of ac/dc/ac island inverter  2.6 

Type or No.                    

No  Electrical Equipment 

To be Measured 

Voltage (V)  Current (A)  Connected to 

Remark 

Ref 

(STC) 

Measured Var Ref

(STC) 

Measured Var Distribution box no. Fuse no. 

 _______________/ AC 

202‐253 

   ……. (Max) 

    

 

 _______________/ AC 

202‐253 

   ……. (Max) 

    

 

 _______________/ AC 

202‐253 

   ……. (Max) 

    

 

 _______________/ AC 

202‐253 

   ……. (Max) 

    

 

 _______________/ AC 

202‐253 

   ……. (Max) 

    

 

 _______________/ AC 

202‐253 

   ……. (Max) 

    

 

 _______________/ AC 

202‐253 

   ……. (Max) 

    

 

 _______________/ AC 

202‐253 

   ……. (Max) 

    

 

Remark:                        

                     

  ______________________________________________________________________________ 

Recommendation:                     

                         

                     

 

   

Page 33: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

       

  Renewable Energy Guidelines  Nov. 2013  27

Volume 10 Commissioning Guidelines 

Mechanical and Visual inspection for distribution board 2.7

Type          No.             

 

Functional        Yes        No 

Mounting         Loose        Tight 

Cable connection      Loose        Tight 

Connected to: 

Inverters Nos.  Strings Nos.  Battery Banks Nos.  Other ‐ describe 

       

       

       

       

       

       

       

 

Remark:                        

                         

   

Recommendation:                     

                         

   

   

Page 34: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

 28  Renewable Energy Guidelinesl  Nov. 2013 

Volume 10 Commissioning Guidelines

Mechanical and visual inspection for battery/string/inverter fuse 2.8

Type        Battery bank/String/Inverter No.       

Functional        Yes        No 

Mounting         Loose        Tight 

Cable connection      Loose        Tight 

Mechanical and visual inspection for battery/string/inverter fuse: 2.9

Type        Battery bank/String/Inverter No.       

Functional        Yes        No 

Mounting         Loose        Tight 

Cable connection      Loose        Tight 

Mechanical and visual inspection for battery/string/inverter fuse  2.10

Type        Battery bank/String/Inverter No.       

Functional        Yes        No 

Mounting         Loose        Tight 

Cable connection      Loose        Tight 

Mechanical and visual inspection for battery/string/inverter fuse:  2.11

Type        Battery bank/String/Inverter No.       

Functional        Yes        No 

Mounting         Loose        Tight 

Cable connection      Loose        Tight 

 

 

   

Page 35: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

       

  Renewable Energy Guidelines  Nov. 2013  29

Volume 10 Commissioning Guidelines 

Mechanical and visual inspection for battery/string/inverter fuse 2.12

Type        Battery bank/String/Inverter No.       

Functional        Yes        No 

Mounting         Loose        Tight 

Cable connection      Loose        Tight 

 

Mechanical and visual inspection for battery bank  

Type or No.                    

Cable connection      Loose        Tight 

 

Battery Commissioning Report    missing       OK 

Measurement of battery bank  2.13

Type or No.                    

 

No  Electrical Equipment 

To be Measured 

Voltage (V)  Current (A)  Connected to  Remark Ref 

(STC) 

Measured Var Ref

(STC) 

Measured Var Fuse no: ac/dc/ac inverter no: 

  Battery bank  48               

  Battery bank  48               

  Battery bank  48               

  Battery bank  48               

  Battery bank  48               

Remark:                        

     

Recommendation:                     

     

Page 36: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

 30  Renewable Energy Guidelinesl  Nov. 2013 

Volume 10 Commissioning Guidelines

Testing internal installation (Powerhouse) 2.14

Are all Socket outlets functional?       Yes      No  If No, How many socket outlets are not functional?                  Are all Switches functional?        Yes      No  If No, How many switches are not functional?                  Are all Bulbs functional?         Yes      No  If No, How many Bulbs are not functional?         Air Conditining Installed?      functional?   Yes      No  Heating Installed?        functional?   Yes      No  Doors & Windows sufficiently tight and closing? Yes        No  Other openings ( please describe )?                  

                       

Remark:                       

                         

                     

Recommendation:                     

                         

                         

                         

                 

   

Page 37: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

       

  Renewable Energy Guidelines  Nov. 2013  31

Volume 10 Commissioning Guidelines 

Training, awareness protocol 2.15

 Participants list 

  Name  Position 

1     

2     

3     

4     

5     

6     

 

No   Title of lecture   Time  Delay  

1  Source of PV‐Solar system  180 min   

2  Conversion of solar energy 

3  DC to AC conversion 

4  Battery protection  60 min   

 Remark:                        

                         

                         

                         

                         

                         

                         

           

 

   

Page 38: Vol 10 Commissioning final-01-12-13 10 Commissioning...Renewable Energy Guidelines Nov. 2013 iii Volume 10 Commissioning Guidelines kWh Kilo Watt Hour kV Kilo Volt LED Light‐Emitting

 

 32  Renewable Energy Guidelinesl  Nov. 2013 

Volume 10 Commissioning Guidelines

General installation testing & results 2.16

Remark:                       

                         

                         

           

 

Recommendation: