virginia railway express long bridge briefing

12
1 VIRGINIA RAILWAY EXPRESS 1 VIRGINIA RAILWAY EXPRESS LONG BRIDGE BRIEFING September 16, 2016 Oscar Gonzalez Project Manager Virginia Railway Express

Upload: others

Post on 22-Dec-2021

5 views

Category:

Documents


0 download

TRANSCRIPT

1

VIRGINIA RAILWAY EXPRESS 1

VIRGINIA RAILWAY EXPRESS LONG BRIDGE BRIEFING

September 16, 2016

Oscar Gonzalez Project Manager

Virginia Railway Express

2

VIRGINIA RAILWAY EXPRESS

Today’s Presentation Project Location Background Project Partners Project Schedule Purpose & Need Next Steps

LONG BRIDGE

3

VIRGINIA RAILWAY EXPRESS

58%

17%

13%

11% 1%

58%

VRE

BUS

METRORAIL AUTOMOBILE

OTHER

Peak Hour Trips from Virginia to DC

across the 14th Street Bridges

(6:30 to 7:30 AM)

Source: Transportation Planning Board 2013 Central Employment Core Cordon Count

21,934 TOTAL TRIPS

4

VIRGINIA RAILWAY EXPRESS

LONG BRIDGE LOCATION

L’Enfant

RO

Virginia L’Enfant

CSX Transportation Amtrak Passenger Station Interlockings Long Bridge Other Bridges

5

VIRGINIA RAILWAY EXPRESS

LONG BRIDGE

Strategic transportation asset for the Eastern Seaboard Links the North and the South

Next crossing 75 miles away in WV

Owned by CSX Transportation

Shared by passenger & freight

Typical Weekday Traffic 18 CSXT Freight trains

34 VRE Commuter trains 24 Amtrak trains

CSXT Freight

24% VRE

Commuter Passenger 45%

Amtrak Intercity Passenger

32%

6

VIRGINIA RAILWAY EXPRESS

LONG BRIDGE KEY DESIGN CHALLENGES

Constrained alignment Adjacent development

Adjacent highways Adjacent park/historic resources

Heightened security interest

Confined Rail Infrastructure Unknown Riverbed

Conditions

7

VIRGINIA RAILWAY EXPRESS

PROJECT PARTNERS Current efforts managed by a partnership of

DDOT, DRPT and VRE, in conjunction with CSXT and Amtrak

Led by FRA with FTA as cooperating agency Additional agencies with special areas of

interests and/or jurisdiction, for example: ‒ National Park Service ‒ National Capital Planning Commission ‒ Architect of the Capitol ‒ Commission on Fine Arts ‒ Department of Homeland Security

8

VIRGINIA RAILWAY EXPRESS

Phase 1: Feasibility Study (2012-2014) Led by DDOT

FRA ARRA Grant Phase 2: Development of Leading Alternatives (2015-2016)

Led by DDOT FRA ARRA Grant

Phase 3: EIS/Preliminary Engineering (2016-2018) Led by DDOT-VRE-DRPT Partnership

FRA TIGER Grant

PROJECT SCHEDULE YEAR:

QUARTER: 2 0 1 2 2 0 1 9

1st 2nd2 0 1 8

3rd 4th 1st 2nd 3rd 4th

Phase 3: EIS/Preliminary Engineering

2nd3rd 4th 1st

Phase 2: Development of Leading Alternatives

3rd 4th 4th 1st2nd 3rd 4th 1st 2nd 3rd

Phase 1: Feasibility Study

4th 1st 2nd 3rd1st 2nd2 0 1 3 2 0 1 4 2 0 1 5 2 0 1 6 2 0 1 7

9

VIRGINIA RAILWAY EXPRESS

LONG BRIDGE KEY PHASE 3 ACTIVITIES

Long List of Alternatives

(Phase 1 & 2)

Short List of Alternatives

Preferred Alternative

Purpose & Need

NEPA Studies

10

VIRGINIA RAILWAY EXPRESS

Purpose: to address reliability and long-term railroad capacity issues in the Long Bridge corridor Need: Increase railroad capacity Improve operational resiliency Enhance network connectivity Provide redundancy

LONG BRIDGE DRAFT PURPOSE & NEED

Carrier Trains per Weekday

Current 2040 Change

CSXT 18 42 +133%

Amtrak 24 44 +83%

VRE 34 92 +188%

MARC 0 8 N/A

NS 0 6 N/A

11

VIRGINIA RAILWAY EXPRESS

Procure Phase 3 contractor (DDOT) Conduct Phase 3 NEPA/PE Study

‒ Public and agency scoping meetings conducted on August 14, 20106

Prepare funding for Final Design and Construction ‒ DRPT and CSXT have pledged $30 million to

advance engineering beyond PE • Part of the FASTLANE Atlantic Gateway project

‒ Funding needed to complete Final Design and Construction

LONG BRIDGE NEXT STEPS

12

VIRGINIA RAILWAY EXPRESS 12