vickers et al-systems engineering approach to vecps
TRANSCRIPT
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
1/19
A SYSTEM ENGINEERING APPROACHTO VALUE ENGINEERING CHANGE
PROPOSALS (VECP)
James R. Vickers, Karen J. Gawron,and Connie L. Cobo,
Raytheon Missile Systems (RMS)
June 2008
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
2/19
June 2008 2
Background
{ Interest in Value Engineering (VE)
waned in late 1990sz Impacted by performance-based
acquisition
z Loss of knowledgeable staff
{ RMS began efforts to reenergize VE
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
3/19
June 2008 3
Background (contd)
{ RMS Formed teams
z Customer team meets annually
z Contracts team and technical team meet quarterly
{ Established fund for use with ValueEngineering Change Proposals (VECP)
{ Status of projects discussed at meetings{ Led to Systems Engineering VE approach
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
4/19
June 2008 4
VECPS - Proposal to Change Contract
and Share in the Savings
{ Simple Type
z Establish second source
z Change containers, packaging, etc.
{ More Complexz Change can affect other subsystems
z Change can require extensive testing
{ Therefore need a systemsengineering approach
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
5/19
June 2008 5
Systems Engineering Approach
{ Unique issues with weapon systems
z VECPs for one item saved money
z Often resulted in other increased costsin related components or subsystems
zSuboptimization
{ Look at system as a whole
{ Conduct functional analysis
{ Decomposition of the system
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
6/19June 2008 6
Weapon System Components
{ Operator
{ Fire control system
{ Launch platform
{ Missilez Mounted various ways - fixed location
or mounted for travel
z Land vehicle, ship, aircraft, shoulder ofwarfighter
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
7/19June 2008 7
US Air Force Weapon System
F-16 Aircraft
Launcher
Missile
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
8/19June 2008 8
Components of a Missile{ Warhead
{ Propulsion (rocket motor){ Airframe
{ Guidance and control (guidance section,
control section, wings, and fins).
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
9/19June 2008 9
Developmental Issues
{ Long lead-time required
{ Full-scale production may take upto ten years
{ Parts become obsolete and/orexcessively priced
{ Extensive testing requirementslimits the ability to change things
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
10/19June 2008 10
VE Changes at Component Level
{ One-piece mirror being phased out
by the manufacturer
{ Replaced with three-piece mirror
z Reduced the unit pricez Provided the same performance
z Was readily available
{ Adversely impacted guidancesystem
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
11/19June 2008 11
Unexpected Problem
{ One-piece mirror had compensation
factors for mass properties injectedinto firmware
{ Three-piece mirrors had differentmass propertiesz Guidance section was compensating for
the wrong measurements
z Caused shut down of production line tofix problem
z Resulted in increased costs
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
12/19June 2008 12
Taking a Different Approach to
Implementing VECPs
{ Replace an Inertial Measurement
Unit (IMU)z Original IMU priced at $32K, was
approximately 7 years old, reliable, andvery accurate.
z New IMU with equal performance usinga different technology was priced atapproximately $10K
z Could result in a $22K savings per unit
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
13/19June 2008 13
The Fast Approach
{ Three questionsz What is it?z What does it do?
z What must it do?
{ Functions documented andcategorized into basic, dependentand independent functions
{ A classical FAST diagram wascreated
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
14/19June 2008 14
Example of Original IMU FAST
DiagramIMU
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
15/19
June 2008 15
Example of New IMU FAST
DiagramIMU
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
16/19
June 2008 16
Example of Original Navigation
Processor FAST Diagram
IMU NavigationProcessor
Assembly
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
17/19
June 2008 17
Example of New Navigation
Processor FAST Diagram
IMU
NavigationProcessorAssembly
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
18/19
June 2008 18
Benefit to the Modified Approach
{ Inter-relationships of the lower level to
upper level components became obvious{ Various types of trade studies were
performed on each level of the system
that depicted a difference in the FASTdiagrams
{ Studies documented all system
components that would change inimplementing the new IMU
-
7/30/2019 Vickers Et Al-Systems Engineering Approach to VECPs
19/19
June 2008 19
Conclusion
{ Modified FAST approach proved a
viable solution to system sub-optimizations
z
Negative effects of the VECP can beneutralized
z May result in increased savings and
performance for the entire system.