  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    1/66

    USER REQUIREMENTS TEMPLATE

    for a

    Supervisory Control and Data Acquisition (SCADA)

    Process Control System

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    2/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 2 of 66

    URS, Rev.0 URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    NOTES for use of the User Requirements Template:

    Upon completion of the template, delete this page prior to updating the Table of Contents and printing.

    1. Many areas of this template have selections or tables that have been prepared for guidance andease of template completion. Text in italics is intended to be used as notes to the User and

    should be deleted prior to printing. Any options and/or examples that are not applicable to thespecific document being created should be deleted as well.

    2. To update the final Table of Contents, place the cursor inside the shaded area, press the Right

    mouse key, and select Update Field.

    3. Items that can be directly tested are identified with a !.

    4.

    Where possible, the User should identify the source (e.g. studies, standards, etc.) for theacceptable ranges of variables or other critical requirements that have been derived.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    3/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 3 of 66

    URS, Rev.0 URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    TABLE OF CONTENTS

    REVISION HISTORY ............................................................................................................................. 5

    1.0

    INTRODUCTION ........................................................................................................................ 61.1. PURPOSE...................................................................................................................................... 6

    1.2. ORIGIN AND CONTEXT................................................................................................................. 61.3. SCOPE.......................................................................................................................................... 7

    1.4. DOCUMENT ORGANIZATION........................................................................................................ 8

    2.0 OVERVIEW .................................................................................................................................. 9

    2.1. BACKGROUND.............................................................................................................................. 92.1.1. Project Overview ................................................................................................................ 9

    2.1.2. Facility Overview .............................................................................................................. 102.1.3. Automation Overview........................................................................................................ 12

    2.2. GENERAL SYSTEM FUNCTIONS.................................................................................................. 14

    2.3. SIMULATION SYSTEM................................................................................................................. 142.4. EXCLUSIONS AND FUTURE CONSIDERATIONS............................................................................ 14

    3.0 OPERATIONAL REQUIREMENTS ....................................................................................... 16

    3.1. FUNCTIONS................................................................................................................................ 163.1.1. Process Monitoring ........................................................................................................... 16

    3.1.2. Alarm Management ........................................................................................................... 173.1.3. Basic Control .................................................................................................................... 19

    3.1.4. Equipment Phase Control ................................................................................................. 233.1.5. Batch Management ........................................................................................................... 24

    3.1.6. Historical Data Collection and Retention ........................................................................ 253.1.7. Other Monitoring and Control Features .......................................................................... 26

    3.1.8. Modes of Operation .......................................................................................................... 263.1.9. Performance and Timing .................................................................................................. 28

    3.1.10. Response to Failures ......................................................................................................... 293.1.11. Security ............................................................................................................................. 30

    3.1.12. Safety ................................................................................................................................. 303.2. DATA......................................................................................................................................... 31

    3.2.1. Preliminary Data Definitions ........................................................................................... 313.2.2. Capacity Requirements ..................................................................................................... 32

    3.2.3. Access Speed ..................................................................................................................... 333.2.4. Archive Requirements ....................................................................................................... 34

    3.2.5. Data Security and Integrity ............................................................................................... 34

    3.3. USER INTERFACES...................................................................................................................... 363.3.1. General ............................................................................................................................. 363.3.2. Process Monitoring ........................................................................................................... 40

    3.3.3. Batch Management Interfaces .......................................................................................... 443.3.4. Alarm Management Interfaces .......................................................................................... 45

    3.3.5. PCS Status Interface ......................................................................................................... 483.3.6. Programming and Configuration Interfaces .................................................................... 49

    3.3.7. Recipe Management Interface .......................................................................................... 49

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    4/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 4 of 66

    URS, Rev.0 URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    3.3.8. Reports .............................................................................................................................. 493.4. REMOTE PCSACCESS................................................................................................................ 50

    3.5. INTERFACES WITH OTHER SYSTEMS........................................................................................... 50

    3.5.1. Intelligent Process Interfaces ........................................................................................... 503.5.2. Other Process Control Systems ........................................................................................ 503.5.3. Other Computerized Systems ............................................................................................ 50

    3.5.4. Shared Resources .............................................................................................................. 503.6. ENVIRONMENT........................................................................................................................... 51

    3.6.1. Layout ............................................................................................................................... 513.6.2. Physical Conditions .......................................................................................................... 51

    4.0 CONSTRAINTS .......................................................................................................................... 534.1. PROJECT CONSTRAINTS ............................................................................................................. 53

    4.1.1. Schedule ............................................................................................................................ 534.1.2. Procedural Constraints ..................................................................................................... 53

    4.2. COMPATIBILITY ......................................................................................................................... 544.2.1. Hardware Standards and Preferences .............................................................................. 54

    4.2.2. COTS Software Standards and Preferences ..................................................................... 554.2.3. PCS Configuration and Integration Standards ................................................................ 56

    4.2.4. PCS User Interface Standards .......................................................................................... 574.2.5. PCS Programming Standards ........................................................................................... 58

    4.3. MAINTENANCE........................................................................................................................... 59

    5.0 LIFE-CYCLE .............................................................................................................................. 59

    5.1. DEVELOPMENT........................................................................................................................... 595.2. TESTING..................................................................................................................................... 59

    5.3. DELIVERY.................................................................................................................................. 595.3.1. Documentation .................................................................................................................. 59

    5.4. SUPPORT .................................................................................................................................... 615.4.1. Start-up Support (list available options)........................................................................... 61

    5.4.2. Post Start-up Support (list post-startup support available) .............................................. 61

    6.0 GLOSSARY ................................................................................................................................ 62

    6.1. TERMINOLOGY........................................................................................................................... 626.2. ACRONYMS................................................................................................................................ 64

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    5/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 5 of 66

    URS, Rev.0 URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    REVISION HISTORY

    Rev. Date Approval REVISION SUMMARY

    A1 11/05/02 Initial document creation by Mark Tuepker

    A2 12/07/02 Modifications to more accurately reflect JETT format andcontent

    A3 6/1/03 Content Review by Chris Roerig, Paul Coury, Steve Smith,John Liebenthal

    A4 6/14/04 Content Review by Chris Roerig, Pat Cashman, Andre Powell,Sarah Powell, Michelle Ubele

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    6/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 6 of 66

    URS, Rev.0 URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    Project No.:

    Insert the unique project number associated with this particular URS.

    Document No.:Insert the Document Identification Number and Revision.

    PCS Identifier:

    Insert description of system, e.g. Process Control System for Sterile Manufacturing Area.

    1.0 INTRODUCTION

    1.1. Purpose

    This User Requirements Specification (URS) defines the purpose of the . It identifies the functions to be carried out, the data on which the system will

    operate, and the operating environment. It also defines any non-functional requirements,constraints such as time and costs, and what deliverables are to be supplied.

    1.2. Origin and Context

    has been contracted by to develop the URS for

    the , to be located in . The format and content of thisURS are based on the Good Automated Manufacturing Practices (GAMP) Guide

    available through the International Society for Pharmaceutical Engineering (ISPE).

    The project role and significance of this document is identified in:

    ! Once approved, this document will provide a foundation for the development of

    functional specifications, design specifications, and Performance Qualification testingprotocols. Modifications to, and/or deviations from, the specifications in an approved

    URS are subject to formal change control procedures.

    The following documents are related to the URS:

    # Reference Contains

    1 Project Scope and Charter

    2 Process design

    3 Applicable automation standards

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    7/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 7 of 66

    URS, Rev.0 URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    1.3. Scope

    This document begins to define the process control system requirements for:

    Hardware and software platforms

    Network communication

    Equipment control

    Automated process area sequencing

    Process equipment modeling for Batch management

    Human Machine Interface (HMI)

    Electronic data and record storage

    This document does not cover: Non-GMP Building Management System (BMS)

    GMP BMS

    Programmable Logic Controllers Hardware and Software

    Raw Material Information System

    Industrial Technologies (IT) systems hardware and software

    The key objective is to provide a process control system with the required functionality

    and flexibility while simultaneously meeting the requirements of ISPE GAMP 4, cGMP,

    FDAs 21 CFR Part 11, ISA S88.01, and policies and procedures. Thebenefit of meeting or exceeding these key objectives is a profitable manufacturing facilityoffering flexibility to meet market demand.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    8/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 8 of 66

    URS, Rev.0 URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    1.4. Document Organization

    In accordance with the GAMP Guide description of URS contents, the remainder of this

    document includes the following sections:

    # Section Sub-Section Contains

    2 Overview Background Facility Overview, Project Overview, and

    Automation Overview

    Key objectives and benefits General statement of automation constraints.

    Main functions and interfaces Description of the process control system role.

    Applicable GxP Requirements Specific identification of constraining regulatory

    requirements

    Other Applicable Regulations Specific identification of other constraining

    regulatory requirements

    3 Operational

    Requirements

    Functions Functions required, calculations, modes of

    operation, performance and timing requirements,action required in case of failure, safety, security

    Data Definition of data, capacity requirements, access

    speed requirements, archive requirements, data

    security and integrity

    Interfaces: User Interfaces User roles/functions and the interface provisions

    Interfaces: System Interfaces Interface with other automated or computerized

    systems

    Interfaces: Equipment Interfaces Interface to sensors and actuators

    Environment: Layout Space(s) provided for automation equipment

    Environment: Physical Conditions Physical conditions prevalent in space(s) provided

    for automation equipment

    4 Constraints Project Constraints Timescales and milestones, procedural constraintsCompatibility Existing systems, automation strategies, and

    automation policies

    Maintenance Availability, ease of maintenance, expansion

    capability, likely enhancements, expected lifetime,

    and long term support

    5 Life Cycle Development Methodologies, project management, and quality

    assurance

    Testing Testing strategies, special requirements, and

    simulations

    Delivery Information related to required supplier deliverables

    Support Support required after system acceptance

    6 Glossary Terminology List of document terms and their meanings

    Acronyms List of abbreviations and their meanings

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    9/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 9 of 66

    URS, Rev.0 URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    2.0 OVERVIEW

    2.1. Background

    2.1.1. Project Overview

    2.1.1.1. Project Summary

    The will be developed/modified as part of {Describe, in broad terms,the project of which the PCS development is a part. Include specific project identifiers,

    like project number(s), products, and key processing technologies.}

    2.1.1.2. Key Objectives

    The key objective is to provide a process control system with the required functionalityand flexibility while simultaneously meeting the requirements of ISPE GAMP 4, cGMP,FDAs 21 CFR Part 11, ISA S88.01, and policies and procedures. The

    benefit of meeting or exceeding these key objectives is a profitable manufacturing facilityoffering flexibility to meet market demand.

    2.1.1.3. Anticipated Benefits

    The following is a list of the major benefits anticipated from the project:

    Benefit Explanation

    Increased CapacityManufacturing Process Change

    Reduced Product Losses

    Increased Flexibility

    Improved Regulatory Compliance

    Reduced Maintenance

    Technology Upgrade

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    10/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 10 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    2.1.2. Facility Overview

    The is a manufacturing facility located in designed to

    produce . The following model identifies site equipmentpertinent to this project:

    {The diagram below is provided as a sample to indicate the appropriate level of detail for

    the facility overview. Replace with diagrams and/or information specific to yourfacility.}

    Receiving

    Warehouse

    Preweigh

    WFI

    Buffer Prep

    Shipping

    Material Handling

    High Purity Steam

    Chilled Water

    Instrument Air

    Waste Handling

    Utilities

    Reactor

    R100

    Centrifuge

    C100

    Wash Tank

    T100

    Receiving TankT101

    Manufacturing Cell A

    Reactor

    R200

    Centrifuge

    C200

    Wash Tank

    T200

    Receiving TankT201

    Manufacturing Cell B

    Bottle Prep A

    Bottling Line A

    Bottling Line B

    Cartoning

    Packaging Area A

    Existing New Modified

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    11/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 11 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    2.1.2.1. Existing Facilities and Equipment

    2.1.2.2. New Facilities and Equipment

    2.1.2.3. Modifications to Existing Facilities and Equipment

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    12/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 12 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    2.1.3. Automation Overview

    The following diagram identifies site automation systems pertinent to this project:

    {The diagram below is provided as a sample to indicate the appropriate level of detail forthe automation overview. Replace with diagrams and/or information specific to yourfacility.}

    MRP System

    Document Management

    System

    LIMS

    Process Historian

    Core Systems

    Warehouse Management

    System

    Preweigh MES

    Building Management

    System

    Material Handling

    Systems

    Buffer Prep

    Batching Stations

    Manufacturing Cell A

    Process Control System

    Manufacturing Cell B

    Process Control System

    Manufacturing

    Process Control

    High Purity Steam

    Skid Controller

    Chilled Water

    Skid Controller

    WFI

    Process Control System

    Utilities

    Process Control

    Process Automation Systems

    Regulated Systems

    Existing New Modified

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    13/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 13 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    2.1.3.1. Existing Systems

    2.1.3.2. New Systems

    2.1.3.3. Modifications to Existing Systems

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    14/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 14 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    2.2. General System Functions

    The PCS maintains a secure environment in accordance with cGMP, GAMP, and FDA

    21CFR Part 11 requirements using S88.01 standards. The PCS monitors and controls thecGMP portion of the to:

    Provide an interactive illustration of the process for operatorinformation and process control

    Provide equipment status and monitoring functionality

    Provide sequential process control via control modules, phases and/orprocedures

    Acquire process data for real-time and historical analysis

    Tailor procedural control of the process via parameter modification

    2.3. Simulation System

    The PCS vendor scope includes the hardware and packaged software necessary to

    configure and support an independent Simulation System. The Simulation System shallbe initially installed at the vendor site and utilized for the development and factory testing

    of the application software. When the applicationsoftware is ready for installation at the facility, it

    will be transferred from the Simulation System to the facility PCS hardware platform.Subsequently, the Simulation System hardware and packaged software will also be

    moved to the site, and utilized for PCS application maintenance andenhancement activities.

    2.4. Exclusions and Future Considerations

    The S88.01 standard and the utilized hardware/software platform provide extensive

    capabilities within a batch environment. has elected to limit the initialimplementation of select batch capabilities, favoring a high level of manual process

    interaction by operating personnel, supported by Standard Operation Procedure (SOP)driven paper system(s). This initial operating philosophy does not imply that future

    enhancement(s) will not take greater advantage of the capabilities provided by the PCS,but does significantly impact functions commonly associated with a S88.01 batch facility

    The PCS functionality is limited as follows:

    Implemented procedures pertain exclusively to CIP and SIP functions. Allother sequential functionality required is implemented at the unit phase level.

    Manufacturing operations will be performed by manually initiating equipmentphases as required. Additionally, prior to initiating a phase, the operator may

    be required to manually perform any set-up required such as:verifying/placing all process unit valves in automatic mode, verifying/placingall control modules are in automatic mode, etc.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    15/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 15 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    It is s intent to continue development of various facilityprocedures, beyond those initially provided at PCS startup. It is the intent that

    phases developed for the project be suitable for use in these

    future procedure development activities. Where feasible, procedures andoperations are designed and implemented as a library of phase buildingblocks, even though a given phase may not be utilized in a procedure at the

    time of PCS startup. It is understood that the phase library at PCS startup,may not include all phases necessary to support continued proceduredevelopment, without the need for development of additional phases.

    In lieu of PCS implementation, SOP driven, manual paper system(s), are used to perform

    the following functions:

    Tracking process equipment fitness for use for a specific function (such as

    Clean, Sterile, Full, Empty, etc.), as well as equipment sterilityexpiration. When a PCS phase/procedure is initiated by an operator, it is theoperators responsibility, supported via manual paper systems, to ensure the

    subject process equipment is suitable for the PCS phase or procedureapplication. The PCS ensures that the subject process equipment is available

    and not currently in-use by another phase/procedure. The PCS equipmentmodel only maintains process unit statuses of In-Use or Available.

    Additional statuses or states pertaining to a units fitness for use are notrequired.

    Material tracking, including all batch/lot material and intermediate productgenealogy tracking.

    Batch/lot tracking, including batch/lot reporting. PCS-generated electronictickets and automated batch reports are not required. Additionally, PCS is

    not required to maintain or track unique batch identifiers. Lot Identifiers andProduct Codes are manually input to the PCS at appropriate process intervalsand utilized for historical data record retention as key fields.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    16/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 16 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    3.0 OPERATIONAL REQUIREMENTS

    3.1. Functions

    3.1.1. Process Monitoring

    3.1.1.1. Real-Time Data Collection and Dissemination

    The collects process data, as transmitted from process instrumentation,and makes the process data available for any or all of the following:

    Basic Data Processing (i.e., conversion to digital data in engineering units),

    Process Alarm Detection and Alarm Management,

    Processing to accomplish control strategies,

    Display to PCS users, and

    Historical data collection.

    Data from other sources (user inputs, recipes, tunable parameters, intelligent devices,

    etc.) are combined with process data into a single logical database that defines, in realtime, the known state of the process. Control strategy algorithms produce process control

    outputs that are also combined into the logical database to complete the process statedefinition.

    Design of PCS data collection features shall consider all of the following:

    Factor Description

    Requiredimmediacy

    Response time for value display and alarming, historical data

    collection frequency, and control processing requirements shoulddictate the minimum acceptable data collection and transfer rates.

    Required precisionInsignificant digits should not be presented to users, historicallycollected, or considered in data processing.

    Data consistency

    In some component systems, communication delays may introduce

    transient and/or scan-based differences in data values. Datacollection design must prevent inconsistent display, control

    response, and historical collection of alarm and other thresholdevents. The design must also avoid other data collection and

    communication mechanisms that could result in sustainedinaccuracies between display data, historical data, and control

    processing data.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    17/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 17 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    Factor Description

    Future expansion

    and/orenhancement

    Hardware, software, and communications design should provide

    capacity for future expansion and potential changes to controland/or display strategies.

    Fault tolerance

    The PCS must be designed to prevent any individual failure fromjeopardizing personnel safety and/or product quality. Where PCS

    features are instrumental in protecting personnel and/or productquality and/or major processing equipment, a Failure Modes and

    Effects Analysis (or comparable risk assessment) is required.

    3.1.1.2. Basic Data Processing

    All data monitored by the PCS shall be immediately converted to standard engineeringunits prior to use in any comparison or control logic. This conversion should also includenormalization of discrete data values (e.g., so that 1 always represents the alarm state

    for a discrete input alarm and the open state for a valve). Process control outputsshould undergo similar conversions immediately prior to transmittal.

    3.1.1.3. Process Alarm Detection

    Process alarm detection functionality compares data values against range and alarmlimits. Range errors and alarms should be propagated, as appropriate, to subsequent data

    processing logic. All non-discrete dynamic system inputs automatically monitored by thePCS should be subjected to both range checking and appropriate alarm checking.

    All non-discrete manual system inputs should also be subjected to range checking. Out-of-range manual data entries should be rejected (with an appropriate message explaining

    why the value was rejected) and/or treated as a process alarm (i.e., annunciated andsubjected to alarm management functions), as appropriate. All manual entries, including

    rejected entries, should be recorded in PCS event logs, if practicable.

    3.1.2. Alarm Management

    3.1.2.1. Alarm Configuration

    The PCS must provide for configuration of alarms to detect unexpected process

    excursions for operator notification and /or response. Two basic types of alarms must besupported by the PCS, process alarms and equipment alarms. Process alarms differ from

    equipment alarms in that their parameters such as, setpoint, time delay, deadband, etcmust be modifiable during progression of a batch process on a per step basis from the

    phase logic. Equipment alarm parameters are tuned to meet the specific equipmentrequirements and once set, are only modified if physical changes occur to the equipment.

    Both types are subjected to the alarm management requirements described in this section.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    18/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 18 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    The Locally Controlled Packaged Equipment section discusses the operator interfacewith vendor provided control system(s) on packaged equipment. Alarms originating

    within these vendor provided control system(s), but displayed on PCS screens, are also

    subject to the alarm management requirements as described within this section.The system shall provide for process alarm priorities, a minimum of five levels, whichare selectable during configuration. At least one of the priority levels will represent

    alarms that affect the quality of the batch (GMP alarm level). Other alarm priorities willbe assigned to equipment protection, personnel safety and operator information.

    The S88 concept of process units, grouped in plant cells and areas will allow for alarmenable/disable of those groupings (e.g. during maintenance, shutdown etc.). Additionally,

    it will also be possible to suppress temporarily (override), with proper authority, anindividual alarm caused by a defective device. Operator alarm override actions will be

    recorded by the system and will automatically be reset at the beginning of each controllerresident phase.

    The system shall support the following configuration parameters for each alarm

    Type of Alarm Absolute alarm, Offset from Setpoint, Percent Offset fromSetpoint.

    Alarm Setpoints for low-low, low, high and high-high severity levels

    Alarm Priority minimum of five levels definable during configuration

    Alarm Delay - time delay of alarm conditions to eliminate alarms associatedwith momentary measurement spikes (e.g., an alarm condition must exist for 5seconds before activating an alarm).

    Alarm Deadband the ability to configure an alarm to turn on at one valueand clear at another Ramp setpoints and configure alarms as setpoint +/-

    tolerance. This helps minimize nuisance alarms associated with normalcontrol loop setpoint changes.

    Pause Enable Configurable ability for alarm activation to cause runningbatch logic to pause. Note alarm point must be directly associated with aprocess unit.

    3.1.2.2. Alarm Acknowledgement

    Operators must be logged on to the PCS and have the proper authority as enforced byPCS security to acknowledge alarms. The PCS shall record in the operator action log all

    acknowledgement activities. The operators electronic signature, the action taken, dateand time must be recorded with each acknowledgement. The PCS shall support two

    means for operators to acknowledge alarms, on an individual basis, and on a group basis.The group shall be all current unacknowledged alarms displayed on the alarm list. Note

    that group acknowledgement shall result in an entry in the operator action log for eachindividual alarm.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    19/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 19 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    3.1.2.3. Alarm Output devices

    The system shall support the following output devices. System configuration shall allowfor changes in alarm states to activate any combination of the devices:

    Console screen (visual)

    Console screen (audible)

    Control room or plant floor flashing light and/or horn

    Alarm printer

    Annunciator panels

    3.1.3. Basic Control

    3.1.3.1. Concept

    Basic control consists of algorithms performed on monitored data values (includingprocess control inputs, user inputs, tunable parameters, and constants) to determine the

    state of process control outputs. Included in basic control are normal control modulealgorithms (valve control, pump control, feedback loop control, etc.) and interlocking.

    Basic control is intended to be completely independent of the intended use of the processequipment. This provides the flexibility to permit manual operations that may:

    Not have been anticipated during the process and/or control system design,

    Require some level of operator protection (alarms, interlocks, etc.),

    Require documented evidence of what was done, and/or

    Require some level of automation (input scaling, closed-loop control, etc.).

    3.1.3.2. Control Modules

    A control module is a regulating device, a state-oriented device, or a combination of

    regulating and state oriented devices that is operated as a single device. Examples ofcontrol modules include block valves, modulating valves, PID controllers, fixed-speed

    motors, and variable speed motors. Design of PCS control modules shall consider all ofthe following:

    Factor Description

    Commonality andconsistency

    All control modules should be instantiated from a limited number of

    control module classes. Uncommon control module attributes (e.g.,reverse-acting limit switch) should be transparent to PCS userswhere appropriate.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    20/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 20 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    Factor Description

    Class attributes

    Each control module class should have a specific and well-defined

    set of attributes. Typical attributes include:

    Setpoint (open, close, 50%, etc.),

    State (open, closed, etc.),

    Requested Mode (manual, automatic, etc.)

    Mode (manual, automatic, etc.), and

    Fault (failed to start, deviation from setpoint, etc.).

    Control request

    management

    Control modules should be designed to seamlessly accept, andrespond appropriately to, mode, state, and setpoint requests from:

    User interface(s) (including local control stations),

    Supervisory processes (e.g., phases), and

    Interlocks.Control module interfaces should, where possible, clearly identify

    the current state, the current mode, and the source of active control.Invalid user inputs should, where possible, produce a message

    identifying the reason the input will not be processed.

    Bumpless transferControl module mode changes should not cause an immediate

    corresponding change in control module state, setpoint, or output.

    Fault annunciation

    and response

    Every unexpected combination of I/O states (and/or values) shouldresult in a specific failure alarm (e.g., valve uuu-XV-iiii failed to

    open). Control module fault response should be designed tomitigate risk to personnel, product, and equipment.

    Harmony withsupervisory control

    Control modules may be subordinate to supervisory objectsincluding complex modules (e.g., header or dispensing system) and

    phases. Mode changes and faults in subordinate control modulesshall either:

    Propagate the mode or fault to the supervisory object, or

    Override the subordinate mode and/or fault monitoring andcomprehensively replace it with mode and/or fault

    monitoring by the supervisory object.

    Data utilization

    All relevant data (I/O, user requests, parameters, etc.) shall be

    appropriately considered by the control module algorithms. For

    example, if a block valve includes both an Open limit switch and aClosed limit switch, the state of both switches should be consideredin determining the actual state of the valve.

    Harmony withsimulation

    Where applicable and possible, installed simulation activation and

    I/O forcing shall be obvious from all impacted user interfaces andreports.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    21/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 21 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    3.1.3.3. Interlocks

    Interlocks modify control module states in response to process conditions in order toprotect personnel, process equipment, and/or product. Design of PCS interlocks shall

    consider all of the following:

    Factor Description

    Product

    independence

    Interlock functionality should notconsider current productprocessing requirements. In general, interlocks should only be

    applied for personnel protection, equipment protection, and/orprevention of product contamination.

    Harmony withsupervisory control

    Control modules may be subordinate to supervisory objectsincluding complex modules (e.g., header or dispensing system) and

    phases. Interlocks in subordinate control modules shall either:

    Propagate the interlock to the supervisory object, or

    Disable (fault) the supervisory object, or

    Override the subordinate interlock and replace it with acomplimentary interlock and/or fault monitoring by thesupervisory object.

    OverridesThe ability to manually override interlocks, if available, shall bereserved for engineering and maintenance users.

    Display

    Control module interfaces should, where possible, clearly identify

    whether or not a control module interlock is active. The specificcause of the interlock should be either displayed as part of the

    control module interface and/or readily accessible from the controlmodule interface.

    Record of interlockevents

    Historical data collection must include a record of interlock-relatedevents (activation, clearing, overrides, etc.). Reports that include a

    list of alarms and events should include interlock-related events.

    3.1.3.4. Complex Modules

    Complex modules include control modules with subordinate control modules and

    equipment modules with subordinate equipment modules and/or control modules.

    Common complex modules include: Header valve groups (where the complex module setpoint identifies a transfer

    source, a transfer destination, or a source-destination pair)

    Batch dispense stations (including a flow control valve, a totalizer, and one ormore block valves)

    Temperature control module (where media routing valves are controlled basedon a desired vessel jacket state or temperature setpoint)

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    22/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 22 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    NOTE: Complex Modules are differentiated from Equipment Phases which arecontrolled through the Batch Manager interface. A complex module is an independent

    object that can be utilized with and/or without the Batch Manager. PCS design need only

    include complex modules if routine non-automatic production is anticipated and manualequipment phase control is too cumbersome for this routine non-automatic production.

    Design of PCS complex modules shall consider all of the following:

    Factor Description

    Commonality andconsistency

    All complex modules should be instantiated from a limited number

    of complex module classes. Uncommon complex module attributes(e.g., extra routing valves) should be transparent to PCS users where

    appropriate.

    Class attributes

    Each complex module class should have a specific and well-defined

    set of attributes. Typical attributes include: Setpoint (Vxxxx-Vyyyy, charge, jacket control, etc.),

    State (Vxxxx-Vyyyy, charge, jacket control, etc.),

    Requested Mode (manual, automatic, etc.)

    Mode (manual, automatic, etc.), and

    Fault (failed to start, deviation from setpoint, etc.).

    Control request

    management

    Complex modules should be designed to seamlessly accept, and

    respond appropriately to, mode, state, and setpoint requests from:

    User interface(s) (including local control stations),

    Supervisory processes (e.g., phases), and

    Interlocks.Complex module interfaces should, where possible, clearly identify

    the current state, the current mode, and the source of active control.Invalid user inputs should, where possible, produce a message

    identifying the reason the input will not be processed.

    Bumpless transferComplex module mode changes should not cause an immediatecorresponding change in complex module state, setpoint, or output.

    Fault annunciation

    and response

    Every unexpected combination of control module states (and/orvalues) should result in a specific failure alarm (e.g., valve uuu-

    XV-iiii failed to open). Complex module fault response should bedesigned to mitigate risk to personnel, product quality, and process

    equipment.

    Harmony with

    supervisory phases

    Mode changes and faults in complex modules that are subordinate toa phase shall either:

    Propagate the mode or fault to the phase, or

    Override the subordinate mode and/or fault monitoring andcomprehensively replace it with mode and/or faultmonitoring at the phase level.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    23/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 23 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    Factor Description

    Harmony with

    simulation

    Where applicable and possible, installed simulation activation and

    I/O forcing shall be obvious from all impacted user interfaces andreports.

    3.1.4. Equipment Phase Control

    3.1.4.1. Concept

    Equipment phases provide all of the recipe-driven processing functionality of the PCS.

    Each equipment phase provides a strategic combination of regulatory and sequentialcontrol intended to exploit a specific processing capability of the equipment. The

    following principles should guide the identification of equipment phases:

    Equipment phases should be based on process equipment capability andshould in no way be product-specific,

    Equipment phases should operate autonomously, except as necessary tocoordinate material transfers or other multi-unit activities,

    Equipment phases should not share control modules with other equipmentphases except where necessitated by process equipment design, and

    Shared equipment phases and shared control modules should notunnecessarily restrict or otherwise interfere with parallel activities.

    3.1.4.2.

    Normal OperationOnce initiated, an equipment phase typically initiates appropriate monitoring (e.g., faultdetection) and proceeds through an orderly sequence of steps. The quantity and identity

    of steps should be sufficient to clearly distinguish the equipment phase progress and tosupport orderly restart logic.

    If general, successful equipment phase operation should not be contingent upon:

    The execution of previous equipment phases, or

    The execution of parallel equipment phases (except as needed for producttransfers), or

    The execution of subsequent equipment phases, or

    The anticipated state or status of uncontrolled equipment.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    24/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 24 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    3.1.4.3. Exception Handling

    Equipment phase exception handling should respond, as appropriate, to controlledequipment alarms, interlocks, and faults, unexpected process deviations, invalid

    parameter values, communication faults, and user intervention commands. Exceptionhandling should be sufficiently exception-specific in order to provide the least intrusive

    response that still provides adequate personnel, equipment, and product protection. Forexample, a product temperature deviation should not necessarily disable automatic

    temperature control.

    Equipment phase exception handling should be sufficiently robust that:

    Direct and immediate actions are taken to ameliorate any condition thatjeopardizes personnel, equipment, or product,

    Exception handling actions are appropriate to both the type of exception andthe progress of the equipment phase sequence at the time of the exception,

    Equipment phase execution is not interrupted by minor anomalies that areunlikely to jeopardize personnel, equipment, or product (though operatornotification of all anomalies is generally required),

    The response of concurrently executing equipment phases is appropriatelyimpacted to preserve the integrity of a Unit Operation,

    The equipment phase, and associated Unit Operation, can be restarted by anoperator with a minimum of extraordinary manual restart preparations (e.g.,by simply commanding the Unit Operation to restart), and

    Restarting an equipment phase, and associated Unit Operation, shouldautomatically resume manufacturing operations without unnecessarily

    repeating steps or extending execution times (e.g., by unnecessarily resettingtotalizers, counters and timers).

    3.1.5. Batch Management

    The automation solution includes both the PCS and a batch managementsystem. The PCS shall be implemented within the framework of the Instrument Society

    of America (ISA) standards S88.01, Standard for Batch Models and Terminology, anddraft standard dS95.01, Standard for Enterprise Control System Integration Models and

    Terminology. The use of these standards supports application of industry standard

    software packages and provides for flexibility and modularity required by the businessand automation objectives. The S88.01 control activity model defines the followingactivities

    Production Planning and Scheduling

    Information Management

    Recipe Management

    Process Management.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    25/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 25 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    Unit Supervision and

    Process Control

    The focus of this PCS is the Process Control activities defined by the S88 Standard. Thissection defines the interface requirements for the PCS to the Unit Supervision, Process

    Management and Recipe Management activities implemented by the Batch ManagementSystem as well as the required operator interfaces to these control activities. The Batch

    Manager Interface (BMI) is required to:

    Provide an operator interface for manual control of batch state transitions

    Report status for equipment procedural logic elements used as a part of recipeexecution

    Provide download and upload capability for recipe parameters

    Provide for PCS ad hoc event reporting to the Batch Manager.

    3.1.6. Historical Data Collection and Retention

    3.1.6.1. Historical Data Values

    Key process and production data values shall be collected and retained in a historicaldatabase. Since these data are important electronic records, the PCS should employ

    appropriate provisions for secure data collection and retention (e.g., automatic dailybackup, disaster recover provisions, long-term data archiving and restoration procedures,

    etc). Existing site database facilities, capabilities, and procedures should be exploited, ifpossible. Historical data shall be accessible for display in historical trends and, as

    applicable, reports.

    3.1.6.2. Alarms and Events

    Process alarm and event data shall be accumulated in a historical database. Each record

    shall include a date/time stamp, Batch/Lot identifier and the source process unit as theprimary keys for data retrieval. Since these data are important electronic records, the

    PCS should employ appropriate provisions for secure data collection and retention (e.g.,automatic daily backup, disaster recover provisions, long-term data archiving and

    restoration procedures, etc). Existing site database facilities, capabilities, and proceduresshould be exploited, if possible. Historical alarm and event data shall be accessible for

    inclusion in onscreen displays and, as applicable, reports.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    26/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 26 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    3.1.7. Other Monitoring and Control Features

    3.1.7.1. Locally Controlled Packaged Equipment

    Select process equipment is packaged in a stand-alone configuration that includessufficient local control capability to perform the intended functionality. These packaged

    systems are designed to include the necessary interface capability to permitcommunication with the PCS. It is the responsibility of the System Integrator to

    coordinate with the packaged equipment vendor(s) to determine the appropriate PCScontrol strategy, general interface requirements, etc. Where practicable, PCS interface to

    packaged equipment should follow S88 paradigms (e.g., by treating the packagedequipment operation as an equipment phase).

    3.1.7.2. Resource Management

    Modes, states, statuses, and other attributes of all process resources (including processunits, bulk material supplies, logical modules such as totalizers, etc.) should be clearly

    defined and appropriately managed. User interfaces to these process resources shouldprovide for attribute monitoring and, with appropriate security, manual adjustment.

    Managed resource attributes (e.g., bulk material supply Ready status and process unitClean status) should be considered in Basic Control interlocks and Equipment Phase

    exception handling, as appropriate.

    3.1.7.3. Engineering Parameters

    In general, hard-coded values related to both Basic Control and Equipment Phase Control

    should be scrupulously avoided. Instead, tunable variables and/or constants should be

    identified, initialized, and used throughout the control logic. Examples of tunablevariables and/or constants, referred to generally as Engineering Parameters, include:

    Scaling constants and alarm limits,

    Deadbands and delays,

    Controller tuning constants,

    Dispensing pre-action limits and tolerances, and

    Conversion constants (e.g., material specific gravity).

    3.1.8. Modes of Operation

    3.1.8.1. Startup

    System documentation shall include detailed procedures for starting the PCS (in total)

    and for starting individual PCS components, as appropriate. On startup, the PCS shallmaintain controlled process equipment in its pre-defined safe (typically de-energized)

    state until specific user commands are applied to begin process control.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    27/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 27 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    To the extent possible, PCS event log(s) shall record events indicating the startup of PCScomponents. The ability to restart the PCS components after an abnormal shutdown

    (e.g., power interruptions) shall, in general, be available to any user with a valid PCS user

    account.

    3.1.8.2. Shutdown

    System documentation shall include a detailed procedure for performing a controlled andcomplete shutdown of the PCS. PCS shutdown shall cause controlled process equipment

    to revert to a pre-defined safe (typically de-energized) state.

    The ability to shutdown the PCS shall be restricted to Supervisors, System

    Administrators, Engineering, and Maintenance personnel. PCS event log(s) and/or alarmlog(s) shall indicate the normal shutdown of any PCS component. Where possible, PCS

    event log(s) and/or alarm log(s) shall indicate abnormal PCS component shutdowns (e.g.,

    power interruptions).

    3.1.8.3. Normal Operation

    On PCS restart according to the PCS startup procedure(s), normal operation shall beenabled. System documentation shall include detailed procedures for normal PCS

    operation (e.g., display elements and navigation, starting batches, using control modules,etc.). The ability to perform normal PCS operations shall be based on privileges

    associated with the users account.

    3.1.8.4. Simulation

    The PCS shall include process simulation capability including:

    The ability to temporarily force any discrete or analog input to any validvalue, and

    The ability to set individual control modules feedback simulation to auto-respond to control module states (e.g., Open feedback energizes and closedfeedback de-energizes whenever the valve stat is OPEN).

    The ability to enable simulation shall be restricted to Supervisors, System AdministratorsEngineering, and Maintenance personnel. PCS event log(s) and/or alarm log(s) shall

    indicate transitions to/from simulation mode.

    3.1.8.5. Disaster RecoverySystem documentation shall include detailed procedures for a complete re-install of

    software on each PCS component. These procedures shall include sufficient detail tocompletely re-build the PCS from purchased hardware and archived software.Independent electronic copies of all software required to re-build the PCS shall be

    supplied with the PCS.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    28/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 28 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    3.1.9. Performance and Timing

    3.1.9.1. PCS Performance

    PCS performance should be adequate to provide a safe, effective, and responsive system.The following guidelines are intended to indicate performance expectations:

    Activity/Event Performance Expectation

    Process Monitoringand Basic Control

    Response

    PCS control responses (e.g., PID controller output change in

    response to a deviation from setpoint) should be commensurate withthe potential significance of the process change. For example:

    Slow-moving regulatory response (e.g., vessel temperaturecontrol) should occur within five (5) seconds.

    Fast-moving regulatory response (e.g., line pressure control)should occur within one (1) second.

    Process InputDisplay

    PCS display of process condition changes should be commensurate

    with the potential significance of the process change. For example:

    All changes in process conditions (i.e., instrument readingsand discrete feedback states) should be reflected in PCS

    displays within five (5) seconds.

    For process conditions that can exhibit rapid and significantchanges (e.g., pressure and flow readings, vessel rupture

    disks), changes should be reflected in PCS displays withintwo (2) seconds.

    User Control

    Command

    Evidence of PCS response to user commands (e.g., changing control

    module states, starting a batch) should be presented to the userwithin one (1) second (e.g., by changing a commanded stateindication). Process control response to user commands should be

    commensurate with the potential significance of the requestedchange. For example:

    A valid user command to start a batch should activate thefirst equipment phase within ten (10) seconds.

    A valid user command to change the state of a control

    module should change the appropriate control output withintwo (2) seconds.

    Display NavigationEvidence of PCS response to a user command to change displaysshould be presented to the user within one (1) second. The target

    display should be completely painted, with up-to-date data values,within five (5) seconds.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    29/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 29 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    Activity/Event Performance Expectation

    WorkstationSynchronization

    When a process attribute is changed from one workstation, the

    attribute change must be reflected on other workstation displays.Such attribute changes should be reflected on all workstations

    within three (3) seconds.

    PCS StartupIn general, it should be possible to bring the PCS from a de-

    energized state to a full working state within fifteen (15) minutes.

    PCS ShutdownIn general, it should be possible to bring the PCS from a fullworking state to a fully de-energized state in a controlled manner

    within fifteen (15) minutes.

    3.1.9.2. Date and TimeThe PCS shall be designed to minimize and, as necessary, compensate for differences indate and time values among PCS components. The following is a description of the

    recommended date/time compensation procedure for a networked PCS:

    A single timekeeper node shall be designated for the PCS. The date/time value for the

    timekeeper node will be periodically reconciled to a known accurate date/time source.Timekeeper node date/time value should not normally deviate from the known accurate

    date/time source value by more than ten (10) seconds between periodic reconciliations. Ifmanual intervention is required to reconcile the timekeeper node date/time value,

    reconciliations should not be required more frequently than once per week.

    PCS nodes that base any activity, log, or display on the local date/time value shouldautomatically (i.e., without user intervention) reconcile their date/time value with thetimekeeper node date/time value periodically (typically once per day). Node date/time

    values should not normally deviate from the timekeeper node date/time value by morethan ten (10) seconds between periodic reconciliations. All date/time reconciliations

    (including the timekeeper node reconciliation) shall be recorded in the PCS event log(s)in a way that allows determination of the pre-reconciliation date/time value offset.

    3.1.10. Response to Failures

    PCS components should include self-diagnostic capabilities for detecting:

    Hardware failures and anomalies, Software (application and services) failures and anomalies,

    Operating System failures and anomalies, and

    Communication failures and anomalies.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    30/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 30 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    All such PCS failures and anomalies should be treated as process alarms (i.e.,annunciated and subjected to alarm management functions). PCS fault conditions that

    potentially impact data quality should be propagated and accommodated, as appropriate,

    in data processing, collection, and display.

    3.1.11. Security

    All PCS components and networks shall be designed to protect against deliberate and/oraccidental activities that could potentially compromise personnel, product, equipment,

    and electronic records. Physical controls should include protection of all PCScomponents (through locking individual enclosures and/or through isolation in protected

    areas such as locked rooms) from reasonable attempts to disrupt or modify thecomponent. Logical controls should include user authentication for any process control

    or PCS modification activity. Refer to the User Interfaces section for additionaldescriptions related to logical PCS controls.

    3.1.12. Safety

    The PCS must be designed to both mitigate process hazards and to prevent introductionof any new hazards related to the PCS components. The following process hazards

    should be considered in PCS design:

    Process Hazard Description

    The following PCS component hazards should be considered in PCS design:

    PCS Hazard Description

    Repetitive StressInjury

    Components that require routine use (e.g., user interface hardware)

    should be ergonomically designed. All PCS components shouldallow for easy access to facilitate cleaning, preventive maintenance,

    and replacement.

    Electrical

    PCS equipment should comply with site electrical and construction

    standards including appropriate grounding and fusing.

    ExplosivePCS equipment should comply with regulations and standardsrelated to the explosive hazard classification of the installation area.

    TrippingPCS equipment should not block normal entry and egress pathwaysor other personnel traffic areas.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    31/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 31 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    3.2. Data

    3.2.1. Preliminary Data Definitions

    {Include or attach any project-specific data relevant to PCS specification and/or design.The following should be considered minimum essential preliminary data:

    Process Flow Diagram

    Process Description

    Scope of Automation

    The following additional preliminary data should be included if available:

    P&IDs

    I/O List

    Instrument List

    Identification of Critical Parameters

    Proposed PCS System Architecture and/or Hardware List(s)

    Alarm Lists (Priorities, Types, Areas, Specific Alarms

    Process Units List

    Control Module Classes List

    Control Modules List

    Interlock List

    Complex Module Classes List

    Complex Modules List

    Equipment Phase Class Lists (including parameter and faults)

    Equipment Phase List

    Recipe Lists (Procedures, Unit Operations, and Operations)

    Historical Data Collection List

    Locally Controlled Equipment List and/or Description(s)

    Managed Resources List

    Engineering Parameters List

    User Interfaces List

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    32/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 32 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    User Interface Displays List

    Statistical Process Control Description

    Reports List and/or Description(s) External PCS Interfaces List and/or Description(s)

    Refer to Attachment A for sample Preliminary Data Formats. Note that much of the

    additional preliminary data listed above represents preliminary functional and/ordesign specifications. If practicable, development and publication of these items should

    be reserved for the Functional Specification and/or Design Specification documentation.}

    3.2.2. Capacity Requirements

    Hardware and software selection should allow for some expansion without additional

    hardware or software purchase. Hardware and software selection should allow for

    significant future PCS expansion and/or extension with the purchase of additionalhardware and/or software. The following capacity constraints are recommended:

    Feature Capacity

    Process Inputs andOutputs

    At least 10% installed spare capacity should be provided for each

    I/O type (discrete inputs, discrete outputs, analog inputs, analogoutputs, etc.). At least 25% total spare space should be available

    for installation of additional I/O (i.e., additional wiring, terminals,and I/O modules) without the need for additional conduits or

    cabinets. Theoretical ability to expand the scope of the PCS by atleast 50% (e.g., through addition of cabinets, processors, etc.)

    should be provided.

    Processing PowerNo more than 50% of the processing capacity of PCS componentsshould be required to provide normal processing and display

    functionality with satisfactory performance.

    Memory

    No more than 50% of the installed physical memory in PCS

    components should be required to provide normal processing anddisplay functionality.

    Local Electronic

    Storage

    No more than 50% of the installed hard disk capacity in PCS

    components should be consumed by installed software.

    Historical andArchive Storage

    Historical data storage capacity should allow for online retrieval ofat least 30 days of any historical data. Archive data storage shouldbe adequate to fulfill current electronic record retention

    requirements with at least 25% spare capacity.

    User InterfacesThe PCS should have the ability to expand user interfaces(workstations and/or displays) by at least 25% without deviating

    from the fundamental PCS architecture.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    33/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 33 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    Feature Capacity

    3.2.3. Access Speed

    3.2.3.1. Real-time Data

    Access to real-time data, via workstation displays, is a primary function of the PCS.

    Refer to the Functions - Performance and Timing subsection for a description ofperformance expectations including input display and workstation synchronization

    features.

    3.2.3.2.

    Online Historical DataPCS historical data includes all of the following:

    Time-sequenced instrument readings and other process-related analog values,

    Alarm and event logs, and

    Batch event and data records.

    Online user interfaces to PCS historical data includes all of the following:

    Time-sequenced trending of analog values,

    Query-driven display of alarm, event, and batch records, and

    Pre-configured reports.

    Access to online (i.e., not yet archived) historical data should be optimized for efficientretrieval. However, no specific access speed specification is applicable due to the diverse

    nature of potential queries. Instead, the following interface guidelines are recommended:

    For data retrieval that could take more than ten (10) seconds, an on-screen inprogress indication should be provided.

    For data retrieval that could take more than twenty (20) seconds, an ability tocancel the query should be provided.

    For data retrieval that could take more than thirty (30) seconds, a roughprogress indicator (e.g., percent complete bar graph) should be provided.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    34/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 34 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    3.2.3.3. Archived Historical Data

    Access to archived historical data should also be optimized for efficient retrieval. Sincearchiving and retrieval mechanisms vary, no specific access speed specification is

    applicable. In general, access to archived data in a specific format (report, chart, orrestoration to online status) should not require more than one (1) calendar day.

    3.2.4. Archive Requirements

    PCS historical data retention capabilities must conform to site and/or product dataretention requirements. In general, all PCS historical data (including time-sequenced

    analog values, alarm, event, and batch logs) should be accessible for at least ten (10)years. Any robust archiving technology is acceptable, however, existing site archiving

    facilities, technologies, and procedures should be exploited if possible. Archive systemdesign should consider the potential for having to migrate the historical data so that

    access can be preserved beyond the point of PCS de-commissioning.

    PCS system manuals must include detailed procedures for committing historical data to

    archive and for retrieving historical data from archive. Retrieved historical data mustinclude any and all data that was, or may have been, considered for verifying

    manufacturing and/or product quality. Retrieved data context, format, and/or access mustbe identical to, or at least comparable to, original data context, formats, and/or access.

    The PCS must provide the ability to retrieve archived data without interrupting ongoingprocess operations.

    3.2.5. Data Security and Integrity

    PCS data security and integrity features must be consistent with controls required by 21

    CFR Part 11 to protect electronic records. The following table identifies anticipated PCSdesign features intended to satisfy these requirements:

    Part 11 Control PCS Compliance Feature(s)

    System Validation

    PCS development lifecycle and documentation must be adequate to

    support system validation. This should include a specificationstraceability matrix and/or similar quality control mechanisms.

    Copying Records

    PCS manuals should include detailed procedures for generating

    accurate and complete copies of records in both human readableand electronic form.

    Protection throughRetention Period

    Refer to the Data - Archive Requirements subsection of thisdocument.

    Limiting System

    Access

    Refer to the Functions - Security and User Interfaces - General:

    Security subsections of this document.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    35/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 35 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    Part 11 Control PCS Compliance Feature(s)

    Audit Trails

    All PCS historical records shall use secure, computer-generated,

    time-stamped audit trails to independently record the date and timeof operator entries and actions that create, modify, or delete

    electronic records. Record changes shall not obscure previouslyrecorded information.

    Operational SystemChecks

    PCS specification documentation shall clearly identify permittedsequencing of steps and events that must be enforced, if any. The

    PCS must be designed to enforce this sequencing, as appropriate.

    Authority ChecksRefer to the Functions - Security and User Interfaces - General:Security subsections of this document.

    Device Checks

    PCS specification documentation shall clearly identify restrictions

    to valid sources of data input or operational instruction, if any. ThePCS must be designed to enforce these restrictions, as appropriate.

    Training

    Project documentation must identify minimum qualifications(experience and training) for PCS developers. Each PCS

    developers qualifications must be vetted against theserequirements. Developer resumes, or similar certificates of

    qualification, must be included in project and/or PCSdocumentation.

    System

    DocumentationControls

    System operation and maintenance documentation must beincluded with the PCS. Distribution of, access to, and use of this

    documentation must be adequately controlled and subject torevision and change control procedures that maintain an audit trail

    that documents time-sequenced development and modification ofsystems documentation.

    Open System

    Controls

    Systems with any component(s) that are not installed in an

    environment in which system access is controlled by personsresponsible for the content of electronic records that are on the

    system are considered Open Systems. Open systems mustinclude controls to ensure the authenticity and integrity of

    electronic records from the point of their creation to the point oftheir receipt. Such procedures and controls shall include additional

    measures such as document encryption and use of appropriatedigital signature standards.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    36/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 36 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    3.3. User Interfaces

    3.3.1. General

    3.3.1.1. User Interface Design

    User Interfaces are designed to facilitate both general process awareness and specific

    PCS tasks. The following table outlines the specific tasks accommodated by PCS userinterface features:

    Task Description

    Process Monitoring:

    Overview

    Features designed to provide a rapid and accurate assessment of the

    status of the entire process within the scope of PCS control.Overview displays typically display key module states and/or

    measurements for a process cell, or a portion of a process cell, in agraphical format.

    Process Monitoring:

    Unit

    Features designed to provide structured access to the primarystate(s) and values for all modules and/or measurements. Unit

    displays typically present modules related to a single process unitand/or ancillary equipment in a graphical format.

    Process Monitoring:

    Detail

    Features designed to provide structured access to all important

    attributes (including identification, modes, states, setpoints, values,etc.) of an individual module and/or instrument. Detailed process

    monitoring is commonly provided through onscreen popups thatmimic traditional analog instrument faceplates.

    Process Monitoring:

    Analytical

    Features designed to display historical and/or statistical informationto users. These typically include a historical trend display and, for

    discrete manufacturing, one or more Statistical Process Controldisplays.

    Process Control:Detailed

    Features that allow users to manipulate process control elements

    (e.g., by changing control module modes, states, etc.). Processcontrol is commonly provided as part of the process monitoring

    detail interface features.

    Process Control:Batch Management

    Features that provide for monitoring and control of recipe

    execution. Batch management features typically include screensfor batch initiation, resource arbitration, batch monitoring, user

    prompts/responses, individual phase control, alarms, and reports.

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    37/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 37 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    Task Description

    SupervisoryFunctions

    Features, protected from operator access, designed to provide

    extraordinary process and batch management controls. Protectedsupervisory capabilities may include overriding interlocks,

    modifying batch execution, temporarily modifying engineeringparameters, workstation shutdown, etc.

    Alarm ManagementFeatures designed to notify user of monitored alarms, allowacknowledgement of those alarms, provide a record of alarm-

    related events, and display summaries and histories of alarms.

    PCS AnalysisFeatures designed to display the status of the Process ControlSystem components.

    ReportsFeatures designed to select and display/print written summaries of

    historical production data.

    Programming and

    Configuration

    Features provided to allow for future modification of application

    configuration and/or source code. These typically include access tothe primary operating system interface(s) and employ strict user

    access controls to help enforce adherence to change controlprocedures.

    Recipe ManagementFeatures provided to allow for creation, modification, and deletionof process recipes.

    3.3.1.2. User Interface Hardware

    User Interface hardware may include computer terminals, panel-mounted interface

    equipment (push-buttons, signal/status lights, hand switches, etc.), tower lights, horns,message displays, and printers. User interface hardware locations are intended to provide

    users ready access to the PCS in close proximity to the process operation or processequipment of interest. Hardware and/or enclosures must be suitable to the installation

    environment (refer to the Environment - Physical Conditions subsection for details).

    User Interface hardware fault-tolerance features must be appropriate to the hardware

    function. Where possible, hardware failure alerts should be integrated with the user

    interface in a way that allows for appropriate response and maintenance.

    3.3.1.3. Security

    All PCS user interfaces must be designed to control user access. Access controls must beconsistent with 21 CFR Part 11 requirements for protection of computer systems that

    employ electronic records and electronic signatures. These include (but are not limitedto) the following:

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    38/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 38 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    User accounts shall be unique to one individual and shall not be reused by, orreassigned to, anyone else.

    User accounts not based on biometrics shall employ at least two distinct

    identification components such as a User ID and password. At least one ofthese components should be secret or otherwise guaranteed to be unique.

    Workstation logins should expire (e.g., by automatic logout) if no user activityoccurs within a pre-determined, definable time period.

    Use of transaction safeguards to prevent unauthorized use of a user account,and to detect and report in an immediate and urgent manger any unauthorizedaccess attempt to the system security unit, and, as appropriate, toorganizational management.

    Access level assigned to an individual will dictate which workstations, interfaces, anddisplays a user has access to, and which operations the user can perform. Where feasible,

    user access administration should leverage existing site computer security policies andprocedures (including security administration servers and existing user accounts).

    Users may be allowed to view and navigate operating displays without login. However, alogin is required to perform any activity that changes any process attribute (e.g., module

    modes and states, setpoints, and parameter values) or in any way modifies the ProcessControl System (e.g., configuration changes, node startup/shutdown, and code changes).

    Activity-based, as opposed to workstation login based, security features are preferred.Records of operator actions should include the operators identity, as confirmed by user

    account login information. All PCS access attempts and results must be recorded andaccessible for review and/or reporting.

    3.3.1.4. Workstation Roles and Access

    Startup characteristics of each workstation should be appropriate to the role of theworkstation and/or the workstation login account authority. For example, process

    operator workstations should start by showing a startup menu and/or overview displayappropriate to the specific role of the workstation. The following may be controlled

    according to the workstation role:

    Access to specific displays,

    Menu system(s) appearance,

    Alarms annunciated locally, and

    Alarm list filtering.

    Workstation features should allow for changing the specific role of the workstationwithout restarting.

    With proper authority, all PCS operating displays should be accessible from any PCSworkstation. Security features should be capable of limiting workstation functionality

    according to the following user characteristics:

  • 8/11/2019 USER REQUIREMENTS TEMPLATE for a Supervisory Control and Data Acquisition (SCADA) Process Control System

    39/66

    JETTUSER REQUIREMENTS

    SPECIFICATION

    Process Control System

    Page 39 of 66

    URS, Rev.0

    December 7, 2002

    JOINT EQUIPMENT TRANSITION TEAM

    User Attribute

    Level/class of Authority (operator, maintenance, supervisor, etc)

    Area of Process Responsibility (utilities, process unit A, cleaning, etc.)

    Recipe or Recipe Class Responsibility

    Training Certification (process and/or recipe training course completion)

    3.3.1.5. Workstation Display Navigation

    Display navigation design should provide easy access to all user interface features. Thefollowing navigation characteristics should be provided:

    Navigation Attribute

    Display navigation should be limited, as appropriate, based on theworkstation role and/or user login.

    Navigation from any display to any other display should not require morethan four (4) keystrokes or pointing device clicks (excluding login).

    A hierarchical menu system (e.g., in site map format and/or dropdown

    list) should be provided. Process displays should provide singlekeystroke/click navigation to this menu system.

    Off-screen connectors to/from a process display should include singlekeystroke/click navigation to the appropriate source/destination display.

    Process displays should provide single keystroke/click navigation to detail

    displays related to objects shown on the display (e.g., overview to unit andunit to faceplate).

    Process displays should provide single keystroke/click navigation to the

    previously viewed display(s) (e.g., a Back button).

    Process displays should provide sin