u.s. epr leak-before-break (lbb) methodology

55
1 > NRC Audit Leak-Before-Break June 26, 2008 AREVA NP INC. U.S. EPR Leak-Before-Break (LBB) Methodology AREVA NP Inc. and the NRC June 26, 2008

Upload: others

Post on 15-Jun-2022

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: U.S. EPR Leak-Before-Break (LBB) Methodology

1> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

U.S. EPR Leak-Before-Break (LBB) Methodology

AREVA NP Inc. and the NRCJune 26, 2008

Page 2: U.S. EPR Leak-Before-Break (LBB) Methodology

2> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Introduction

Russ WellsLead Licensing Engineer, Chapter 3

Regulatory AffairsNew Plants Deployment

Page 3: U.S. EPR Leak-Before-Break (LBB) Methodology

3> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Agenda

> Meeting Objectives (R. Wells)> EPR LBB Approach and Methodology (A. Nana) > Summary (A. Nana)> Combined License Information (COL) Items

and ITAAC (R. Wells)> Surge Line Stratification (T. Bhagwagar)

Page 4: U.S. EPR Leak-Before-Break (LBB) Methodology

4> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Meeting Objectives

> Provide an overview of the LBB approach on three piping systems for U.S. EPR

> Provide clarifications and responses to initial comments/questions

Identify key internal references for audit review

> Respond to questions regarding NRC confirmatory LBB analysis

Page 5: U.S. EPR Leak-Before-Break (LBB) Methodology

5> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

U.S. EPR LBB Approach

Ashok NanaLead Engineer for LBB Analyses

Page 6: U.S. EPR Leak-Before-Break (LBB) Methodology

6> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Overview

> Three high-energy piping systems are identified for LBB

Main coolant loop (MCL) piping• Hot leg, cold leg and crossover leg

Pressurizer surge line (SL), andMain steam line (MSL) piping inside containment• From steam generators to first anchor point location at

Containment Building penetration

3 LBB Piping Systems

Page 7: U.S. EPR Leak-Before-Break (LBB) Methodology

7> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Isometric View Showing MCL and SL Piping

Page 8: U.S. EPR Leak-Before-Break (LBB) Methodology

8> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Plan View of MCL Piping

See FSAR Tier 2 Fig. 3.6.3-1

Page 9: U.S. EPR Leak-Before-Break (LBB) Methodology

9> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Elevation View of MCL Piping

See FSAR Tier 2 Fig. 3.6.3-2

Page 10: U.S. EPR Leak-Before-Break (LBB) Methodology

10> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Layout of SL Piping

See FSAR Tier 2 Fig. 3.6.3-3

Note: PZR Nozzle DM Weld will be revised to indicate it is a shop weld

Page 11: U.S. EPR Leak-Before-Break (LBB) Methodology

11> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Layout of MSL PipingInside Containment Portion to 30JMK10BQ110

Page 12: U.S. EPR Leak-Before-Break (LBB) Methodology

12> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

LBB Applicability

> Application of LBB limited to piping – “not-susceptible” to failure from various degradation mechanisms in service

Demonstrate – probability of fluid system rupture is “extremely low”Demonstrate/address following issues are not a concern:

• Pipe rupture due to water hammer• Creep damage• Degradation by erosion, erosion/corrosion, due to unfavorable flow

conditions and chemistry• Corrosion resistance of piping• Fatigue cracking or failure of piping system • Thermal aging and thermal stratification• Potential indirect sources of pipe rupture• Piping material not-susceptible to brittle cleavage type failure• Failure prevention and detection

LBB - applied to Class 1 & 2 or equivalent piping systems

Addressed in FSAR Tier 2 Section 3.6.3.3

Page 13: U.S. EPR Leak-Before-Break (LBB) Methodology

13> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Overall LBB Methodology

> Typical LBB analysis considers applied loadings in piping system – these are known, such as for operating plants

> The LBB analysis performed for U.S. EPR is consistent with methods and criteria of NUREG 1061, Vol. 3 and SRP 3.6.3

> In this approach the final LBB results are in the form of “Allowable Load Limit” (ALL) diagrams

If applied loading points lie within the ALL window, LBB is justified – with appropriate LBB safety margins already considered in window

Page 14: U.S. EPR Leak-Before-Break (LBB) Methodology

14> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Typical ALL Diagram Considering Various Axial Loads

Page 15: U.S. EPR Leak-Before-Break (LBB) Methodology

15> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Overall LBB Methodology

> Like typical LBB analysis, it involves:Phase I: performing leak rate analysis – to obtain leakage crack sizes (ℓ) with recommended margin of 10 on leak detection capabilityPhase II: performing detailed flaw stability analysis –• Considering safety margin of two on leakage crack size or

(2ℓ)

> Like typical LBB analysis, for consideration of selection of location for LBB, it involves:

Pipe or nozzle geometryBase and weld metal materialsOperating pressures and temperatures

Page 16: U.S. EPR Leak-Before-Break (LBB) Methodology

16> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Overall LBB Methodology

> In typical LBB analysis - actual loads are known: Only those locations that have least favorable combination of stress and material properties needs to be demonstrated for LBB

> In the ALL diagram approach: A significant number of initially assumed normal operating loadings are considered in the leak rate analysis Corresponding maximum allowable moment loads are then determined through flaw stability analysis

Page 17: U.S. EPR Leak-Before-Break (LBB) Methodology

17> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Identification of LBB Location

> Considering geometry, materials and operating conditions.

If any of the three parameters change it is identified as an LBB locationExample - Following this process of selection, five locations are determined for the MCL piping:

• 1) RV outlet nozzle region at hot leg• 2) SG inlet nozzle at hot leg• 3) SG outlet nozzle• 4) Crossover leg, RCP outlet nozzle, cold leg, RV inlet• 5) RCP inlet nozzle region

Page 18: U.S. EPR Leak-Before-Break (LBB) Methodology

18> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Phase I - Leak Rate Analysis

> Perform leak rate analysesFor MCL & SL piping – In-house code KRAKFLO used

• Benchmarked for subcooled & saturated liquid conditionsFor MSL piping – SQUIRT code used

• Benchmarked for saturated steam conditionsVarious assumed normal operating loads are considered.

• Moment loadings ranging from a small fraction of the yield strength to gradual increments of loadings above yield strength of the material

• Axial load due to pressure• Low external pipe axial load conservatively assumed

Leakage flaw sizes are then determined considering a factor of 10 times the leak detection capability flaw sizeFatigue flaws postulated at all locations. Lower bounding limit curve or minimum moment curve is generated

Page 19: U.S. EPR Leak-Before-Break (LBB) Methodology

19> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Leak Rate Analyses

> For the MCL Piping:Loadings ranged from pressure only case to small increments in loadings of 2.5E6 in-lbs up to 20E6 in-lbs.From 20E6 in-lbs to 50E6 in-lbs; increment increased to 5E6 in-lbsFrom 50E6 in-lbs to 140E6 in-lbs; increment increased to 10E6 in-lbs

> A family of curves of:Leak rate versus crack lengths are thereby established for each loading condition

• Leak rates ranging from 1 to 10 gpm are shown for a typical location

> For MCL, with leak detection capability of 0.5 gpmTherefore, desired leakage crack sizes are for 5 gpm

Page 20: U.S. EPR Leak-Before-Break (LBB) Methodology

20> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Leak Rate Versus Crack Length – SG Inlet Nozzle

Page 21: U.S. EPR Leak-Before-Break (LBB) Methodology

21> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Minimum Moment Vs Crack Length Curve

For 5 gpm Leak Rate

Page 22: U.S. EPR Leak-Before-Break (LBB) Methodology

22> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Minimum Moment Curve

> The leak rate analyses help establish the Minimum Moment Curve

Minimum moment corresponds to deadweight, steady state pressure and thermal expansion moment for normal operation.

Lower Bound Limit Curve

Page 23: U.S. EPR Leak-Before-Break (LBB) Methodology

23> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Materials & Material Properties

> The MCL and SL are fabricated from F304LN stainless steel (SS) and 308/308L SS welds

Safe ends F316LNDissimilar metal welds (DMW) – Alloy 52/52MAll welds fabricated using GTAW processAttached RV nozzles – SA-508 Grade 3 Class 1Attached SG & PZR nozzles – SA-508 Grade 3 Class 2

> RCP casings – SA 351 CF3> MSL piping – SA 106 Grade C carbon steel matl.

Page 24: U.S. EPR Leak-Before-Break (LBB) Methodology

24> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Materials & Material Properties

> Material Testing Program:

> Material properties of comparable materialsObtained from industry literature

> For MSL – used experimental data

Page 25: U.S. EPR Leak-Before-Break (LBB) Methodology

25> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

J-R Curve for 2.75T CT Specimens

Page 26: U.S. EPR Leak-Before-Break (LBB) Methodology

26> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

J-R Curve for 1.5T CT Specimens

Page 27: U.S. EPR Leak-Before-Break (LBB) Methodology

27> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

J-R Curve for Alloy 52 Fusion Line

Page 28: U.S. EPR Leak-Before-Break (LBB) Methodology

28> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

J-R Curve for RCP, Nozzles & Alloy 52

Page 29: U.S. EPR Leak-Before-Break (LBB) Methodology

29> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

J-R Curve for SA 106 Grade C - MSL

Page 30: U.S. EPR Leak-Before-Break (LBB) Methodology

30> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Phase II – Flaw Stability Analysis

> Perform flaw stability analyses – Applied J> Circ. T-W crack in straight pipe solution

For MCL & MSL piping – Used EPRI/GE method for axial tension & bending solutionFor SL piping – Used EPRI/GE method for bending solution

• Effect of axial load also considered through determining Meq

> Detailed J-Tearing analysis is performedSince a margin of two is recommended between leakage crack size, ℓ, and critical crack size, 2ℓ

• Leakage crack sizes from Phase I are doubled for flaw stability analysis i.e. flaw size, a = ℓ

For normal operating + SSE loadings – since absolute sum load combination is considered, a factor of 1.0 on loadings is applicable

Page 31: U.S. EPR Leak-Before-Break (LBB) Methodology

31> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Illustration of Instability Point in J/T Analysis

Page 32: U.S. EPR Leak-Before-Break (LBB) Methodology

32> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Phase II – Flaw Stability Analysis

> At each applied minimum moment load, maximum allowable moment load considering a factor of two on leakage crack size is determined.

> Joining these loci of points creates the Upper Bounding Limit Curve called the ALL diagram for a given LBB location

Page 33: U.S. EPR Leak-Before-Break (LBB) Methodology

33> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Phase II – Flaw Stability Analysis

> From Phase I - leak rate analysis Lower Bound or Minimum Moment Curve is determined

> From Phase II –J-T analysis method Upper Bound or Maximum Moment Curve is established

> Combining the results from the above analyses results in an ALL diagram

Page 34: U.S. EPR Leak-Before-Break (LBB) Methodology

34> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

ALL Diagram for SG Inlet Nozzle – Various Axial Loads

0

20000

40000

60000

80000

100000

120000

140000

0 20000 40000 60000 80000 100000 120000 140000

Minimum Moment, in-kips

Max

imum

Mom

ent,

in-k

ips

2000 kips2500 kips3000 kipsMin. Moment

Page 35: U.S. EPR Leak-Before-Break (LBB) Methodology

35> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

ALL Diagram – Showing Allowable LBB Zone

Page 36: U.S. EPR Leak-Before-Break (LBB) Methodology

36> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

LBB Demonstrated

> For each major segment of piping system Locations identified for LBB

• Geometry, materials, and operating conditionUnique ALL diagramActual loads when available – compared against the associated ALL diagramIf all the loads fall in the ALL LBB zone – LBB is demonstrated

Page 37: U.S. EPR Leak-Before-Break (LBB) Methodology

37> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Preliminary Loads - SG Inlet Nozzle

Page 38: U.S. EPR Leak-Before-Break (LBB) Methodology

38> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Preliminary Loads – MSL (SF=2)

Page 39: U.S. EPR Leak-Before-Break (LBB) Methodology

39> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Preliminary Loads – MSL (SF=1.7)

Page 40: U.S. EPR Leak-Before-Break (LBB) Methodology

40> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Preliminary Loads – SL (SF=2.0)

Page 41: U.S. EPR Leak-Before-Break (LBB) Methodology

41> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Summary

> LBB analysis conforms to GDC 4 and applicable regulatory guidance

> LBB can be successfully demonstrated for the entire piping system

> Benefit of this approach – LBB analysis would not need to be re-performed due to future structural loads re-analysis.

> ALL diagram concept – very convenient for structural analysts to verify that LBB requirements continues to be met for the given piping system

Page 42: U.S. EPR Leak-Before-Break (LBB) Methodology

42> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

COL & ITAAC

Russ Wells

Page 43: U.S. EPR Leak-Before-Break (LBB) Methodology

43> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Regulatory Implementation of LBB Approach

> As noted in previous slides, the U.S. EPR LBB approach is intended to be a “bounding approach” for purposes of the design certification application (FSAR Tier 2 Section 3.6.3)

> Verification of this bounding approach is accomplished through COL information items and ITAAC

Page 44: U.S. EPR Leak-Before-Break (LBB) Methodology

44> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

LBB COL Information Items

> COL Information Item 3.6-3 (FSAR Tier 2 Section 3.6.3)

A COL applicant that references the U.S. EPR design certification will confirm that the design LBB analysis remains bounding for each piping system and provide a summary of the results of the actual as-built plant specific LBB analysis, including material properties of piping and welds, stress analyses, leakage detection capability, and degradation mechanisms.

Page 45: U.S. EPR Leak-Before-Break (LBB) Methodology

45> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

ITAAC

> FSAR Tier 1 Table 2.2.1-5—RCS Inspections, Tests, Analyses, and Acceptance Criteria

An analysis exists that assesses the LBB capability of the piping and equipment listed in Table 2.2.1-1

An analysis will be performed.

The piping and interconnected component nozzles listed in Table 2.2.1-1 have been evaluated for LBB

Acceptance Criteria

Inspection, Test or Analysis

Design Commitment

Page 46: U.S. EPR Leak-Before-Break (LBB) Methodology

46> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Stratification in Surge Line

Tehemton BhagwagarSupervisory Engineer RCS and Class 1 Piping

Analysis

Page 47: U.S. EPR Leak-Before-Break (LBB) Methodology

47> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Surge Line Stratification

> Low potential for thermal stratification in U.S. EPR surge line due to:

Improved geometry• Continuous 5 degree slope from the PZR to the HL to prevent

water stagnation• Vertical take-off from the HL with a 6.7D length to minimize

turbulent penetrationImproved system operation • Continuous spray bypass flow at normal operation to suppress

turbulent penetration• The PZR-to-HL temperature difference is minimized during

plant heat-up by initiating in-surges via the CVCS system

Page 48: U.S. EPR Leak-Before-Break (LBB) Methodology

48> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Surge Line Stratification in Operating Plants

SL Stratification Results for a Westinghouse PWR

Source: “An Investigation of Thermal Stress Ranges Under Stratification Loadings,” T.H. Liu and E.L. Cranford, Westinghouse Electric Corporation, published in Journal of Pressure Vessel Technology, Transactions of the ASME, Vol. 113, May 1991, page 330

Page 49: U.S. EPR Leak-Before-Break (LBB) Methodology

49> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Surge Line Geometry for a Westinghouse PWR

Source: “An Investigation of Thermal Stress Ranges Under Stratification Loadings,” T.H. Liu and E.L. Cranford, Westinghouse Electric Corporation, published in Journal of Pressure Vessel Technology, Transactions of the ASME, Vol. 113, May 1991, page 326

Page 50: U.S. EPR Leak-Before-Break (LBB) Methodology

50> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

SL Stratification Results for a B&W PWR

Page 51: U.S. EPR Leak-Before-Break (LBB) Methodology

51> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Surge Line Geometry for a B&W PWR

Page 52: U.S. EPR Leak-Before-Break (LBB) Methodology

52> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

SL Stratification Results for a French PWR

Page 53: U.S. EPR Leak-Before-Break (LBB) Methodology

53> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Surge Line Geometry for a French PWR

Page 54: U.S. EPR Leak-Before-Break (LBB) Methodology

54> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Surge Line Geometry for U.S. EPR

Page 55: U.S. EPR Leak-Before-Break (LBB) Methodology

55> NRC Audit Leak-Before-Break June 26, 2008AREVA NP INC.

Questions?