Dam Safety/U.S. Levee Coalition Webinar
Yvonne Prettyman-BeckNational Program ManagerEmergency SupplementalPrograms Integration DivisionCivil Works Directorate, USACE
10, 30 January 2019
U.S. ARMY CORPS OF ENGINEERS IMPLEMENTATION/EXECUTION OF 2018 EMERGENCY SUPPLEMENTAL APPROPRIATIONS
As of 17 December 2018, 1900 EST
AGENDA
FY 2018 Emergency Supplemental Program Overview
Bipartisan Act of 2018 Civil Works Highlights
Chronology
Principles of Delivery (Execution Strategy)
Investigation & Construction Project List/Location
Conclusion
2
FY 18 EMERGENCY SUPPLEMENTAL: $17.4B Public Law 115-123, Bipartisan Act of 2018 (enacted 9 Feb 2018) Investigations $135M, 38 Study Activities
Initiate and/or Complete Current/Future Auth Studies, 100% Fed $75M for HIM Impacted States (5/2) + Up to $60M for Other Impacted States (33/3)
Construction $15.1B, 58 Projects (32 Ongoing; 26 Not-ongoing) $15B to Construct FRM Projects: Already Auth; Future Auth; Chief’s Report as of 9 Feb (not yet auth) w/ASA
determination; Studied using PL 115-123 Investigations funds w/ASA determination $10.4B for HIM Impacted States (5/2); $4.6B for Other Impacted States (33/3)
Projects in PR/VI 100% Fed; Suppl $$ applied to ‘On-going const’ projects cost-shared at 100% Fed; Other projects (NOT ongoing), normal cost-share applies except that the non-Federal cash contributions may be financed payable option over a 30 year finance period upon project completion
Up to $50M for FRM CAP Projects Not incl - 7 Projects (5 Ongoing; 2 Not-Ongoing)
Mississippi Rivers & Tributaries $770M, 10 Short-term / 2 Long-term Projects (Channels/Levees) $370M for Short-term Emergencies (10 Projects); $400M for Long-term FRM projects (2 Projects - Ongoing)
(Already Auth and/or Auth after enactment for emergencies)
Operations & Maintenance $608M, 90 Projects (Emergency Repairs) Dredge Fed Nav Channels and Repair Damages
Flood Control & Coastal Emergencies $810M, 81 Projects (Emergency Repairs) Includes Auth Shore Protection Projects to Full Project Profile at Full Federal Expense
Expenses $20MAs of 17 Dec 2018
3
PERFORMANCE CRITERIA Project and study allocations targeted to eligible states IAW PL 115-123
All eligible projects considered
A study/project allocation is considered a commitment to fund to completion with available supplemental funds
A risk management and future investment reserve will both mitigate delivery risk and support subsequent allocations for implementation of additional projects
Investment plans will be reviewed and updated over time
Performance criteria included: Project Benefit Cost Ratios Assessment of potential damage reduction provided by the project or study Advancement of non-structural and high life risk projects Confidence in efficient project delivery Study area impacted by disaster
4
Classification: Ongoing vs Not On-going Construction “Ongoing construction projects" include authorized Corps projects that have received Construction
account appropriations (i.e. an initial work allowance from a Statement of Managers, work plan, or supplemental appropriation) in any of the previous three fiscal years (FY 2015, 2016, or 2017)…includes all separable elements of the project and authorized projects with executed agreements for non-Federal sponsor construction w/potential reimbursement (i.e. Sections 211 or 206).
Financing: Cash Contribution For “not-ongoing” (new start) construction projects, Public Law 115-123 is explicit that the special
financing provisions apply to the non-federal cash contribution only. The FY18 Supplemental allows the Corps to use Supplemental funds to cover what would otherwise would be the required non-federal cash contribution, with the non-federal interest paying back that financed amount in accordance with the provisions of section 103(k) of Public Law 99-662 over a period of not more than 30 years from the date of completion of the project or separable element. It does not authorize the Corps of Engineers to finance the acquisition of real estate, with such acquisition remaining a non-federal responsibility.
Use of Previously Funded Federal Funds: For on-going studies/projects with existing and FY19 Federal funds, pre-approved work for the use of
those funds will be used for that specific purpose and upfront. FY18 “Supplemental work” can begin immediately with work that is different than the non-supplemental work. Accountability must be maintained for the funding source, applicable cost-share and the executed work.
POLICY GUIDANCE ON IMPLEMENTATION5
IMPLEMENTATION PROGRESS (CHRONOLOGY)6
Aug Sep OctNov
Dec
Jan
Feb Mar MayApr Jun Jul Aug Sep Oct
2017 Hurricane Landfalls
Har
vey
(Cat
4) 2
5 Au
g, T
XIrm
a (C
at 4
) 10
Sep,
FL
Mar
ia (C
at 4
) 20
Sep,
PR
Nat
e (C
at 1
) 8 O
ct, M
S/LA
9 Fe
b -B
BA 2
018
Enac
ted
Mar
/Apr
–U
SAC
E dr
aft I
G to
Arm
y
11 M
ay -
Appr
oved
FC
CE
IG
5 Ju
l -O
MB
Cle
ared
Lis
ts /
Publ
ishe
d
9 Au
g -A
rmy
Appr
oved
Pol
icy
IG
10 A
ug, M
odel
FC
SAs
Tran
smitt
ed to
MSC
s
5-6
Sep
-USA
CE
Supp
lem
enta
l Wor
ksho
p
31 O
ct -
4Q E
GM
Cm
dPr
ogra
m B
riefs
21 S
ep -
OM
B U
pdat
e
16 J
ul -
DPM
–Pr
inci
ples
of D
eliv
ery
30 M
ay -
HQ
/Pro
gram
Dir
–D
eliv
ery
Prin
cipl
es
2 M
ay -
O&
M re
pairs
initi
al tr
anch
e pu
blis
hed
(31P
/2S)
23 A
pr -
Join
t Arm
y/U
SAC
E M
eetin
g
27 A
pr -
USA
CE
Rec
omm
ende
d Li
st to
Arm
y
7-10
May
–3Q
EG
M /F
Y18
Supp
lem
enta
l
6 Ju
n -C
, MR
&T
Appo
rtio
nmen
ts w
/cav
eats
13 &
21
Jun
-Arm
y/O
MB
Mee
ting
BBA 2018 Supplemental Implementation Execution
10 O
ct -
FCSA
s Ex
ecut
ion
Goa
l
Action Chronology
16 N
ov –
Initi
al P
rogr
am M
ilest
one
Bas
elin
e
Nov
22 M
ay -
FCC
E Ap
port
ionm
ent
31 A
ug -
Arm
y Ap
prov
ed P
PA M
odel
Tem
plat
es
7-20
Dec
–Fi
eld
Ref
ine
Prog
ram
Bas
elin
e
30 J
an -
Fina
l Pro
gram
Bas
elin
e Lo
ck
Dec
Short-term Repair Funding to Field (17 May-O&M; 23 May-FCCE;12 Jul-MR&T; 17 Jul-C) Long-term Construction Funding to Field late July
Jan
PRINCIPLES OF DELIVERY - EXECUTION STRATEGY7
Director’s Policy Memorandum (DPM), 16 July 2018 -Drive Aggressive and Quality Project Delivery to “Move Dirt”
Advance project delivery at every opportunity; use best available/most efficient project delivery methods and systems
Expeditionary mindset; focus first on project delivery, not process
Deliver quality and showcase outcomes (starts, completions, etc.)
Implement plans/schedules based on “full available funding”
Fully leverage partnering principles
Not all work must be performed by USACE
Leverage enterprise technical capabilities and capacity
Be innovative: use latest technologies, industry best practice
Leverage sponsor input and capabilities
Engage and communicate with Industry
Pacific Ocean Division (POD)
South Atlantic Division
(SAD)MississippiValley Division
(MVD)
Great Lakes & Ohio River
Division(LRD)
Alaska
Seattle
WallaWallaPortland
SanFrancisco
Los Angeles
Honolulu
Albuquerque
Omaha
Kansas City
Tulsa
Galveston
Little Rock
St.Louis
RockIsland
St. Paul
Vicks-burg
New Orleans
MobileJacksonville
Savannah
Charleston
Wilmington
Norfolk
PhiladelphiaNew York
NewEngland
Detroit Buffalo
BaltimorePittsburghChicago
Memphis
Nashville
Louisville
Hunting-ton
Sacramento
Atlanta
Dallas
Cincinnati
NorthwesternDivision (NWD)
South PacificDivision (SPD)
SouthwesternDivision (SWD)
Ft. Worth
North AtlanticDivision (NAD)
Middle East(Winchester, VA)
Civil Works Boundaries
Puerto Rico
8
INVESTIGATIONS - EXECUTION STRATEGY 3 May 2018 - DPM - Improving Efficiency and Effectiveness in USACE Civil Works
Project Delivery (Planning Phase and Planning Activities)
Directs delegation of policy/legal review and decision making authority to the MSC for all studies less than $3M Fed x 3 years
Clarifies roles/responsibilities for a more efficient/effective process of study delivery
Emphasizes study scoping is not a separate action, but continuous with multiple iterations
SMART planning principles apply to all supplemental studies Balance level of uncertainty and risk Ensure early/ongoing vertical team engagement Alternative Comparison and Selection…no single best plan Ensure all resources are identified and available
Agreements (FCSAs): 2 not required - comprehensive and watershed study activities 5 ongoing - 2 amendments executed; others no immediate need - using other available funds 31 new activities - ALL 31 FCSAs executed
9
As of 17 Dec 2018
WA$2,000,0001 - Study
OR$3,000,0001 - Study
OK$3,000,000
1 - Study GA$3,000,0001 - Study
TN$3,000,000
1 - Study
TX$15,902,0004 - Studies
1 - Watershed Study
CA$5,051,0002 - Studies
W
AlaskaHawaii
LA$15,000,0005 - Studies FL
$32,000,0006 - Studies1 - Comp Study
AL$6,000,0002 - Studies
PR$10,600,0005 - Studies
SC$6,000,0002 - Studies
NY$540,0001 - Study
LDRIP Investigations Initial Investments by StateStates Impacted by HIM (Group 1) ($83,302,000 / 27 Study Activities)States Impacted by 2 or more storms (Group 2) ($28,591,000 / 11 Study Activities)
USVI$800,0002 - Studies
VT$3,000,0001 - Study
Retains reserve for contingencies on initial study allocations & additional investments
KY$3,000,0001 - Study
10
As of 15 Dec 2018
INITIAL FUNDED STUDIES: HIM STATES & TERRITORIES (27 STUDY ACTIVITIES)
11
STUDY NAME (HIM States/Territories - GROUP 1) CLASSIFICATION STATE MSCOkaloosa County, FL New Study FL SADMonroe Co., FL CSRM New Study FL SADMiami Back Bay, FL CSRM New Study FL SADPinellas County, FL GRR New Study FL SADCollier County Beach Erosion Control, FL New Study FL SADDade County, FL GRR New Study FL SAD
South Atlantic Coastal Study New Comprehensive Study FL, PR, USVI SAD
Proctor, Fulton County, GA Flood Risk Management Study New Study GA SAD
Amite River & Tributaries Comprehensive Study East of MS River New Study LA MVD
Upper Barataria Basin FRM Study New Study LA MVDSouth Central Coast, LA New Study LA MVDLake Pontchartrain & Vicinity, LA: GRR for Levee Lifts New Study LA MVDWest Bank & Vicinity, LA: GRR for Levee Lifts New Study LA MVDRio Guayanilla, PR New Study PR SADSan Juan Metro Area CSRM Study New Study PR SADRio Grande de Manati, PR (Ciales) New Study PR SADPuerto Rico CSRM Study New Study PR SADRio Culebrinas, PR New Study PR SADCharleston Peninsula, SC New Study SC SADFolly Beach, SC New Study SC SADCoastal Texas Protection and Restoration Study, TX Continuing Study TX SWDBuffalo Bayou and Tribs Study New Study TX SWDHouston Regional Watershed Assessment, TX New Watershed Study TX SWDBrazos River, Fort Bend County Erosion Mgmt Study New Study TX SWDGuadalupe and San Antonio River Basins, TX Continuing Study TX SWDTurpentine Run, St. Thomas, USVI New Study USVI SADSavan Gut Phase II, St. Thomas, USVI New Study USVI SAD
INITIAL FUNDED STUDIES: NON-HIM STATES/TERRITORIES (11 STUDY ACTIVITIES)
12
STUDY NAME: Non-HIM STATES/TERRITORIES CLASSIFICATION STATE MSC
Selma, AL Flood Risk Management Study New Study AL SAD
Valley Creek, AL Flood Risk Management Study New Study AL SAD
Los Angeles County Flood Control System, CA New Study CA SPD
Westminster East Garden Grove, CA Continuing Study CA LRD
Metro Louisville, KY Flood Protection System New Study KY LRD
Nassau County Back Bays, NY Continuing Study NY NAD
Tulsa West Tulsa Levees, Oklahoma New Study OK SWD
Portland Metro Levee System New Study OR NWD
Memphis Wolf River Backwater Levee System, TN New Study TN MVD
Upper Connecticut River, VT New Study VT NAD
Mill Creek, Walla Walla County, WA Continuing Study WA NWD
CONSTRUCTION - EXECUTION STRATEGIES
Emphasis on project delivery & schedules; 16 July 2018, DPM - established expedited durations for project/study completions
Moving Beyond Status Quo - balanced use of in-house engineering and private sector resources in pre-construction phase while leveraging traditional and non-traditional acquisition tools in the construction phase
Set goal of 35-40% for private sector Architectural Engineering resourcing
Communications/Outreach Initiatives ongoing Corps-wide: HQs Reverse Industry Day, plus several Regional/District Industry Engagements; Small Business Conference
Consideration of Design-Build, Design-Bid-Build methods for product delivery
Critical Activity - Working very closely with Sponsors
Agreements (PPAs): 32 Ongoing Construction - 4 executed; 9 w/MSC for NFS negotiations; 8 not required
26 Not ongoing - 1 executed; 13 w/MSC for NFS negotiations
13
As of 8 Jan 2019
NM$6,500,000
1 - ON
GA$13,000,000
1 - ON
TN$15,900,000
1 – NO
TX$4,879,913,000
7 - ON3 - NO
CA$2,466,933,1855 - ON2 - NO
Alaska Hawaii
LA$1,373,000,0001 - ON 3 - NO (1 RZ)
FL$802,418,0007 - ON 8 - NO
KY$198,000,0002 - ON (Non-Struct)
PR$2,505,345,0003 - ON3 - NO
SC$31,458,0001 - ON2 - NO
WV$690,936,0002 - ON1 - NO (RZ)
LDRIP Construction Initial Allocations by StateStates Impacted by HIM - Group 1 ($9,607,134,000 / 39 projects)States Impacted by 2 or more storms (Group 2) ($4,305,946,526 / 19 projects)
Retains reserve for contingencies on initial project allocations & additional investments.
HI$345,076,0001 - NO
ON - Ongoing Const (32)NO - Not Ongoing (26)RZ - Resumption
MO$11,300,000
1 - ON
KS/MO$453,821,3411 - ON1 - NO
14
As of 15 Dec 2018
LDRIP CONSTRUCTION PROJECTS
Ala Wai Canal
Folsom Dam
Herbert Hoover Dike
Santa Ana RiverMainstem161
216
Isabella Dam
514
13Yuba R. Basin
74
1566 American River
258
Tule R., L. Success
177
S. SanFranciscoShoreline
158 Dade Co.
17 Flagler Co.
14Manatee Co.25
20Palm Beach Co. (2)
St. Lucie Co.
37 St. Johns Co. (2)
13Tybee Isl.
345
117Cedar Rapids
454Kansas City
147
80
Miss, R. Channel Improvement
Dallas Floodway
118Martin
Johnson Co.
34325576015
GrandIsle
W. Shore L.Pontchartrain
E. BatonRouge
Comite R.
11 Bois Brule
1552500
25083 60
60
Rio Puerto Nuevo
Rio Grande de Loiza
Rio de la Plata
Rio Grande de AreciboRio Guanajobo at MayaguezRio Nigua at Salinas
22Colleton Co. Edisto Is
16
99Mill Creek
574 Bluestone Lake
20McDowell Co.
96Lower Mud R.
3957Sabine Pass toGalveston Bay
22353
Miss, R. Channel Improvement
Dallas Floodway Extension
75Brays Bayou
295Clear Creek
65Hunting Bayou
45White Oak Bayou
73Lower Colorado R.
92Lewisville Lake
60 Construction Projects (minus CAP)* Projects Cleared July 2018* 34 Ongoing CN (PPA Amendments)* 26 Not Ongoing CN (PPA Negotiations)* Surveys/Design Underway* Sponsors ROW and Relocations
1Buf Bayou & Tribs
Pawleys IsFolly Beach
92
6 Alamogordo
2 Brevard Co.
2 Broward Co.2Sarasota Co.
2 Duval Co.
2Lee Co.
Nassau Co.22
2
15
INITIAL FUNDED CONSTRUCTION PROJECTS(HIM STATES/TERRITORIES - 39 PROJECTS)
16
PROJECT NAME - GROUP 1 STATUS STATE MSCDade County, FL Ongoing Construction FL SAD
Nassau County, FL Ongoing Construction FL SAD
Duval County, FL Ongoing Construction FL SADSt John's County, FL Ongoing Construction FL SADBrevard County, FL Ongoing Construction FL SADPalm Beach County, FL Not Ongoing FL SADPalm Beach County (Mid-Town Beach Segment), FL Not Ongoing FL SADBroward County, FL Ongoing Construction FL SADLee County, FL Not Ongoing FL SADSarasota County (Venice), FL Not Ongoing FL SADFlagler County, FL CSRM Not Ongoing FL SADHerbert Hoover Dike, FL Ongoing Construction FL SADManatee County, FL Not Ongoing FL SADSt Lucie County (South Segment), FL CSRM Not Ongoing FL SADSt. John’s County (Villano Segment), FL CSRM Not Ongoing FL SADTybee Island, GA Ongoing Construction GA SADComite River, LA Ongoing Construction LA MVD
East Baton Rouge Flood Control, LANot Ongoing (Resumption) LA MVD
Grande Isle, LA Not Ongoing LA MVD
West Shore, Lake Pontchartrain, LA Not Ongoing LA MVD
PROJECT NAME - GROUP 1 STATUS STATE MSCRio de La Plata, PR Ongoing Construction PR SAD
Rio Grande de Arecibo, PR Ongoing Construction PR SADRio Grande de Loiza, PR Not Ongoing PR SADRio Guanajibo at Mayaguez, PR Not Ongoing PR SADRio Nigua at Salinas, PR Not Ongoing PR SADRio Puerto Nuevo, PR Ongoing Construction PR SADColleton County (Edisto Island), SC Not Ongoing SC SADFolly Beach, SC Ongoing Construction SC SADPawleys Island, SC Not Ongoing SC SADBrays Bayou, TX Ongoing Construction TX SWDBuffalo Bayou and Tributaries, TX Ongoing Construction TX SWDClear Creek, TX Not Ongoing TX SWDDallas Floodway, TX Not Ongoing TX SWDDallas Floodway Extension, TX Ongoing Construction TX SWDHunting Bayou, TX Ongoing Construction TX SWDLewisville Dam, TX Ongoing Construction TX SWDLower Colorado River Ph 1 (Wharton), TX Ongoing Construction TX SWDSabine Pass to Galveston Bay, TX Not Ongoing TX SWDWhite Oak Bayou, TX Ongoing Construction TX SWD
As of 5 September 2018
INITIAL FUNDED CONSTRUCTION PROJECTS(NON-HIM STATES - 19 PROJECTS)
17
PROJECT NAME - GROUP 2 STATUS STATE MSCAmerican River - Common Features, CA Not Ongoing CA SPDAmerican River Watershed (Folsom Dam Raise), CA Ongoing Construction CA SPDIsabella Lake, CA Ongoing Construction CA SPDSanta Ana River Mainstem, CA Ongoing Construction CA SPDSouth San Francisco Shoreline, CA Not Ongoing CA SPDTule River/Lake Success Enlargement (Success Dam), CA Ongoing Construction CA SPD
Yuba River Basin, CA Ongoing Construction CA SPDAla Wai Canal, Oahu, HI Not Ongoing HI PODCedar River, Cedar Rapids (FRM), IA Not Ongoing IA MVDKansas Citys, KS & MO Ongoing Construction KS & MO NWDArmourdale, KS & MO Not Ongoing KS & MO NWDJohnson County, Section 202, KY Ongoing Construction KY LRDTown of Martin. Section 202, KY Ongoing Construction KY LRDBois Brule, MO Ongoing Construction MO MVDAlamogordo, NM Ongoing Construction NM SPDMill (Seven Mile) Creek, TN Not Ongoing TN LRDBluestone Lake, WV Ongoing Construction WV LRDLower Mud River, Milton, WV Not Ongoing (Resumption) WV LRDMcDowell County, Section 202, WV Ongoing Construction WV LRD
As of 5 September 2018
MR&T - EXECUTION STRATEGIES
Mississippi River Channel Improvement Fully funds the construction of Armor One, replacement of the Mat
Sinking Unit Includes Prototype Testing, Award of Barge Contract, Robotics
Construction Contract, Continued Engineering Efforts, Modifications, Spare Equipment and Parts, Contract Support, Warranty and Start Up
Mississippi River Levees Applying same strategies as construction program Includes Floodwall Construction, Levee Enlargements with Seepage
Remediation
18
W
AlaskaHawaii
LDRIP MR&T Initial Investments by StateStates Impacted by HIMStates Impacted by 2 or more storms
Retains reserve for contingencies on initial study allocations & additional investments
19
MO$3,400,0001 – Levee Items
AR$7,400,0001 – Levee Items
LA$101,800,00017 - Levee Items
MS$34,800,00011 - Levee Items
MR&T States
As of 15 Dec 2018
SPDRegional Resource
IntegratorMs. Kelley Campbell
SADHurricane EmergencyRestoration Division
Ms. Lisa Grande
HQUSACE National Program
National Senior Program ManagerMs. Yvonne Prettyman-Beck
SWDHarvey
Support TeamMr. Tim Macallister
MVDSUPP Team - PM, PgM, Pgm Analyst
Ms. Renee TurnerMr. Charles Stokes LRD
Mr. Phil Johnson
NADMr. Paul Sabalis
NWDMr. Dana Knudtson
PODMr. Steve Yamamoto
EMERGENCY SUPPLEMENTAL PROGRAM -PLANNED OVERSIGHT / MANAGEMENT
20
WAY AHEAD - CONCLUSION
Successful Program Execution is a top USACE priority Must Continue Proficient Execution of “Regular” Appropriations Program
Maintain Transparent Communications with Project Partners & Industry
Critical Component for Facilitating Both Quality Projects and Accelerated Delivery
Timeliness/Flexibility in Resolution
of Rising Issues is Key
21
https://www.usace.army.mil/FY18 Emergency Supplemental
HQUSACE POC: [email protected]
Additional Information located at:
Questions
22