upgrading the cost model for mobile termination in denmark · upgrading the cost model for mobile...
TRANSCRIPT
19176-225
Upgrading the cost model for mobile termination in DenmarkIan Streule, Matthew Starling, Alex Slinger
21 June 2011
2
19176-225
Contents
Background to the original LRAIC model
Introduction
Upgrades proposed to the cost model
Next steps
Glossary
3
19176-225
Introduction
Analysys Mason Limited (‘Analysys Mason’) has been commissioned to assist the National IT and Telecom Agency (‘NITA’) in upgrading the existing long-run average incremental cost (LRAIC) model for mobile networks in Denmark
The upgraded cost model will help inform future NITA decisions on the pricing of regulated mobile services: the upgraded cost model will feature additional functionality on top of
the original mobile LRAIC model addition of high-speed packet access (HSPA) technology possible addition of Long-Term Evolution (LTE) technology development of a new ‘generic operator’ derivation of costs of wholesale mobile voice/SMS termination,
consistent with the European Commission’s Recommendation for the ‘pure long-run incremental cost’ (pure LRIC), released in May 2009
4
19176-225
Ian Streule(Senior Manager)
Project Director (and Project Manager for the development of the original cost model)
Matthew Starling(Lead Consultant)
Project Manager, leading the development of the upgraded cost model
Alex Slinger(Associate Consultant)
Assisting in the development of the upgraded cost model
The Analysys Mason project team
Name and title Role in the project
Introduction • Project team
James Allen(Partner) Project Adviser
5
19176-225
Our process will allow significant input from industry parties Our experience of these projects, in both Denmark and other countries,
allow us to present an approach covering the:
management of various conceptual issues
interaction of industry parties/stakeholders
request and collection of relevant data
construction and upgrade of models that will be clear and robust
support for NITA in understanding the results and implications of
– charge controls based on LRAIC and other approaches
• including the specific case of the pure LRIC approach for wholesale mobile termination
Introduction • Approach
6
19176-225
The process involves four phases …
Phase 1:Model specification
Phase 2:Model preparation
Phase 3:Model consultation
and revision
Phase 4:Model finalisation
Industry workshop regarding the specification of the model Data request issued Reference paper on model specification for industry Consultation response and finalisation of specification
Interim bilateral meetings regarding the data request Data collection and review Construction of model upgrades and verification
Consultation on the draft model Consultation on the revised model/draft pricing decision
Finalisation of the upgraded cost model Publication of the final model and final pricing decision
Introduction • Approach
7
19176-225
… with industry involvement requested in each phase
Phase 1:Model specification
Phase 2:Model preparation
Phase 3:Model consultation
and revision
Phase 4:Model finalisation
Industry workshop regarding the specification of the model Consultation responses on the model specification
Data collection and data review meetings
Industry workshop on the draft model Industry workshop on the revised model and NITA’s draft
pricing decision Consultation responses following both workshops
Industry workshop on the final model and NITA’s final pricing decision
Introduction • Approach
8
19176-225
Jun2011
Industry meetings
4: Model finalisation
Consultation of revised materials
Review comments and revise model
Review comments and finalise materials
Consultation of draft model
Project completion
3: Model consultation and revision
2: Model preparation
Issue data request
Industry consultation
Industry workshop
Construction of upgrades
Data collection
Jul Aug
1: Model specification
MarJan2012
DecNovOctSep
Finalise specification
Apr May JunFeb
The project is due to last 12 monthsIntroduction • Timetable
KEYModel development
Operator consultation
Industry meetings/workshops
Holiday periods
9
19176-225
Phase 1: Draft specificationIntroduction • Timetable
Jun2011
Industry meetings
4: Model finalisation
Consultation of revised materials
Review comments and revise model
Review comments and finalise materials
Consultation of draft model
Project completion
3: Model consultation and revision
2: Model preparation
Issue data request
Industry consultation
Industry workshop
Construction of upgrades
Data collection
Jul Aug
1: Model specification
MarJan2012
DecNovOctSep
Finalise specification
Apr May JunFeb
Industry consultationDraft reference paper issued to industry prior to workshop
Workshop meetingToday
Data requestIssued to industry
KEYModel development
Operator consultation
Industry meetings/workshops
Holiday periods
10
19176-225
Phase 1: Final specification
KEYModel development
Operator consultation
Industry meetings/workshops
Holiday periods
Jun2011
Industry meetings
4: Model finalisation
Consultation of revised materials
Review comments and revise model
Review comments and finalise materials
Consultation of draft model
Project completion
3: Model consultation and revision
2: Model preparation
Issue data request
Industry consultation
Industry workshop
Construction of upgrades
Data collection
Jul Aug
1: Model specification
MarJan2012
DecNovOctSep
Finalise specification
Apr May JunFeb
Industry responsesResponses to the
reference paper due by 11 August 2011
Finalised approachCompleted by
the end of August 2011
Introduction • Timetable
11
19176-225
Phase 2: Model preparationIntroduction • Timetable
Jun2011
Industry meetings
4: Model finalisationConsultation of revised materials
Review comments and revise model
Review comments and finalise materials
Consultation of draft model
Project completion
3: Model consultation and revision
2: Model preparation
Issue data request
Industry consultation
Industry workshop
Construction of upgrades
Data collection
Jul Aug
1: Model specification
MarJan2012
DecNovOctSep
Finalise specification
Apr May JunFeb
Data requests11 weeks for parties to provide demand/network data
16 weeks for parties to provide cost data
Industry meetingsDiscussions of data received and any issues related
to data collection encountered during the process
KEYModel development
Operator consultation
Industry meetings/workshops
Holiday periods
12
19176-225
Phase 3: Model refinementIntroduction • Timetable
Jun2011
Industry meetings
4: Model finalisation
Consultation of revised materials
Review comments and revise model
Review comments and finalise materials
Consultation of draft model
Project completion
3: Model consultation and revision
2: Model preparation
Issue data request
Industry consultation
Industry workshop
Construction of upgrades
Data collection
Jul Aug
1: Model specification
MarJan2012
DecNovOctSep
Finalise specification
Apr May JunFeb
Draft modelReleased in the middle
of December 2011
Revised modelRevised model (as well as NITA’s
draft pricing decision) released in early April 2012
Consultations4–5 week periods
for operators to respond
KEYModel development
Operator consultation Holiday periods
Industry meetings/workshops
13
19176-225
Phase 4: Model finalisationIntroduction • Timetable
KEYModel development
Operator consultation
Industry meetings/workshops
Holiday periods
Jun2011
Industry meetings
4: Model finalisationConsultation of revised materials
Review comments and revise model
Review comments and finalise materials
Consultation of draft model
Project completion
3: Model consultation and revision
2: Model preparation
Issue data request
Industry consultation
Industry workshop
Construction of upgrades
Data collection
Jul Aug
1: Model specification
MarJan2012
DecNovOctSep
Finalise specification
Apr May JunFeb
Final modelsFinal models (as well as
NITA’s final pricing decision) released in June 2012
14
19176-225
Background to the original LRAIC model
Introduction
Proposed upgraded cost model
Next steps
Glossary
Model specification
Reference design
15
19176-225
The original model was developed according to four key dimensions
Background to the original LRAIC model • Model specification
2. Technology
3. Service
1. Operator
4. Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs. data
Network vs. retailWACC*
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
Conceptual issues
*WACC = Weighted average cost of capital
16
19176-225
Conceptual issue Recommendation for original model
1. Structural implementation
Bottom-up, reconciled against top-down information
2. Type of operator Actual operators
3. Size of operator Actual size
Original concepts: operator
2.Technology
3.Service
1. Operator
4.Implementation
The original mobile LRAIC model captured the four actual mobile network operators (MNOs) in Denmark:
TDC, Telia, Telenor (Sonofon) and Hi3G
Only NITA had visibility of the model data from all MNOs:
MNOs only had visibility of their own model data
Background to the original LRAIC model • Model specification
Source: NITA
KEY To be reconsidered
17
19176-225
Original concepts: technologyConceptual issue Recommendation for original model4. Radio technology
standards2G and/or 3G, as needed to reflect actual operators
5. Technology generations Included within the model explicitly
6. Extension and quality of coverage
Reflect historical and expected future coverage
7. Transmission network
Actual transmission networks as far as possible
8. Network nodes Scorched-node calibration, optimised for efficiency and modern standards
9. Input costs Mixed approach based on actual/average costs
10. Spectrum situation Capability to capture hypothetical or actual allocations, plus licence fees
2.Technology
3.Service
1. Operator
4.Implementation
Background to the original LRAIC model • Model specification
Source: NITA
KEY To be reconsidered
18
19176-225
Original concepts: serviceConceptual issue Recommendation for original model
11. Service set Both voice services and non-voice services
12. Wholesale or retail Wholesale network costs only
The original mobile LRAIC model captured both voice and non-voice services:
including SMS, GPRS, EDGE, R99 data and video
However, HSPA was not considered explicitly, rather converted into R99-equivalent traffic
2.Technology
3.Service
1. Operator
4.Implementation
Background to the original LRAIC model • Model specification
Source: NITA
KEY To be reconsidered
19
19176-225Source: NITA
Original concepts: implementationConceptual issue Recommendation for original model
13. WACC Calculate using the capital asset pricing model (CAPM)
14. Depreciation method Economic depreciation
15. Increments One traffic increment; multiple subscriber increments
16. Years of results All relevant past and future years (1992–2041)
17. Mark-up mechanism Equi-proportionate mark-up (EPMU)
18. Network externality surcharge Not applied
2.Technology
3.Service
1. Operator
4.Implementation
Background to the original LRAIC model • Model specification
KEY To be reconsidered
20
19176-225
Background to the original LRAIC model
Introduction
Proposed upgraded cost model
Next steps
Glossary
Model specification
Reference design
21
19176-225
Structure of the reference design for the original mobile LRAIC model
Background to the original LRAIC model • Reference design
BTSTRXTRX
TRXTRX
BTSTRXTRXTRXTRX
TRXTRXTRXTRX
BTS
TRXTRXTRXTRX
TRXTRXTRXTRX
CKCK
CKCK
BTSNodeB
E1MUX
MUX
MUX
PCUSGSN
HLRINNMSCS POIPS
Internet
E1
SMSC Billing
STM1STM1
STM1STM1
E1E1
TRXTRXTRXTRX
TRXTRXTRXTRX
BTSBTS
BTSTRX
TRXTRXTRX
TRXTRXTRX
GGSN
MSCBSC
RNC
GMSC or
TSC
Overall design logic of network1. Coverage drivers
2. Network roll-out
3. Radio network
4. Backhaul network
5. MSC, TSC
6. Backbone network
7. HLR, SMSC, GSNs
8. Expenditure rules
9. Incremental costs
Source: Analysys Mason
22
19176-225
NITA’s Mast database was used to specify details of coverage …
All operators recognised c. 95% of Denmark as ‘rural’:
though key differences occurred in the number and size of urban geotypes
We averaged across operator data and used NITA’s Mast database to identify operator sites by geotype
Background to the original LRAIC model • Reference design • 1. Coverage drivers
Source: Analysys Mason, NITA
Dense urban
Urban
Suburban
Rural
Dense urban
Urban
Suburban
Rural
Geotype Area Size (sq. km)Dense urban 0.09% 40Urban 0.82% 350Suburban 3.34% 1 430Rural 95.75% 40 944
Map of geotypes in the original model
23
19176-225
MapInfo model of hexagonal outdoor coverage at each BTS
Calibrated cell radii, by geotype, for outdoor coverage
0
1
2
3
4
5
6
7
8
9
10
Denseurban
Urban Suburban Rural
Theo
retic
al ra
dius
(km
)
900MHz 1800MHz 2100MHz
Background to the original LRAIC model • Reference design • 1. Coverage drivers
Source: Analysys Mason, NITA
… and operator data was used to calibrate the cell radii
24
19176-225
Optimal versus scorched-node coverage was captured in the model In an optimal network, coverage would
be achieved with the theoretical cell radius
In reality, operators are constrained in the potential locations for their base transmitter stations (BTS), and must take a strategic decision about how well they fill the resulting gaps (by frequency)
The ratio of effective-to-theoretical coverage per site (the ‘scorched-node coverage coefficient’) was used to calibrate cell radii by operator
Optimal locations of BTS
Sub-optimal locations of BTS
occurring in reality
BTS coverage assumptions
Background to the original LRAIC model • Reference design • 1. Coverage drivers
Source: Analysys Mason
25
19176-225
Both 900/1800MHz 2G networks and 2100MHz 3G networks were modelled The model input was defined by
geotype, frequency and time (history + forecast)
Historical coverage by operator was calculated from NITA’s Mast database and operator data, using MapInfo:
special sites (indoor, tunnel) were separately specified
The primary spectrum used for coverage was defined for each operator (900MHz for TDC and Sonofon; 1800MHz for Telia; 2100MHz for Hi3G)
Secondary spectrum coverage BTSs were deployed mainly on existing primary spectrum sites
3G coverage was deployed mainly on existing 2G sites
Both aspects varied by operator and geotype
Deployment is predominantly tri-sectored to maximise coverage:
some one-sector/two-sector deployments were assumed in rural areas with 900MHz
Background to the original LRAIC model • Reference design • 2. Network roll-out
26
19176-225
The BHE* to be conveyed were applied to the coverage network … Capacity of 2G coverage sectors was
calculated, taking into account: the amount of spectrum maximum reuse factor: 12 cell-blocking probability: 1–2% BTS capacity: four transceivers
(TRX) TRX capacity: 8×n, less CCH and
GPRS allocations
Capacity of the 3G coverage sectors was calculated, taking into account:
number of carriers (1–3) cell-blocking probability (1%) soft-handover margin (40%) NodeB capacity (15 kits) channel-kit (CK) capacity
(16 channel elements, or CE)
*Busy-hour Erlangs
Background to the original LRAIC model • Reference design • 3. Radio network
BTS, TRX, NodeB and CK capacities were further weighted by a utilisation factor, some of which varied by operator:
e.g. for BTS/TRX this varied depending on the (strategic) trade-off between more TRXs or more sites
27
19176-225
… with unsupported BHEs requiring additional sites The additional BTSs deployed were
always tri-sectored, and utilise primary and/or secondary spectrum in a certain (average) proportion by geotype
Other radio network elements were dimensioned more simply:
approximately 1% of traffic was carried on special sites (indoor and tunnel sites)
these were deployed with a fixed number of TRXs/CK per site, i.e. capacity elements not driven explicitly by traffic
Site types were deployed according to a percentage input
Own tower site Own monopole site
Third-party rooftop site*Third-party tower site*
*Blue shading denotes own equipment; light grey denotes third-party assets
Site types modelled
Background to the original LRAIC model • Reference design • 3. Radio network
28
19176-225
The model assumed separate 2G and 3G LMA* backhaul networks
3G backhaul network elements
BSC
8Mbit/s microwave (n E1 part-filled)
Access hub
n E1 leased lines per site on average
E1
E1 E1
2G fibre backbone links
1E1Special
sites
BTS
Rural sites
2G backhaul network elements
KEY 2G BTS 3G NodeB
8Mbit/s microwave (n E1 part-filled)
E11E1
Special sites
Access hub
NodeB
3G fibre backbone links
E1E1
Rural sites
RNC
Background to the original LRAIC model • Reference design • 4. Backhaul network
Source: Analysys Mason *LMA = Last-mile access
29
19176-225
The 2G MSC/TSC topology was driven by a simple reference table The 2G mobile switching centre (MSC) had a processing capacity, in busy-
hour call attempts (BHCA), subject to maximum utilisation
The number of MSCs calculated by this method was used to drive the topology of the switching network
Background to the original LRAIC model • Reference design • 5. MSC, TSC
Source: Analysys Mason
30
19176-225
The 3G MSC layer assumed separate servers and gateways
Mobile switching server (MSS) Media gateway (MGW)
3G BHCAsMSS processor maximum utilisation
MSS processor capacity Number of MSSs
Switching topologySwitching topology look-up table
Traffic per route
E1 ports
BHE on inter-switch, interconnect, VMS
MGW port maximum utilisation
MGW port capacity
Number of MGWs
Background to the original LRAIC model • Reference design • 5. MSC, TSC
Source: Analysys Mason
31
19176-225
The inter-MSC network was formed of one or more mesh layers
1
23
1
2
1
23
4 56
6 logical routes
10 logical routes
15 logical routes
0 logical routes
2 logical routes
3 logical routes
KEY Switching location Route
Background to the original LRAIC model • Reference design • 6. Backbone network
Source: Analysys Mason
Mature GSM networks are typically beyond three sites; however, evolving 3G networks have yet to reach the same extent
For 12 MSCs and 7 locations, a two-mesh transit layer was deployed
32
19176-225
Jutland fibre ring
Fyn fibre ring
Sealand fibre ring
The logical backbone links were deployed on a national fibre network A proportion of incoming, outgoing
and on-net voice traffic travelled between switching sites:
depending on caller locations and the locations of the points of interconnection (PoIs)
The average traffic per logical route was used to dimension the total E1 links between switching sites
National fibre backbone
Background to the original LRAIC model • Reference design • 6. Backbone network
Source: Analysys Mason
33
19176-225
Data servers were deployed using standardised rulesHLR Home location register (HLR) units
were driven by registered SIMs (both personal and non-personal):
the capacity per HLR unit, plus maximum utilisation, was used to calculate HLR units over time
2G and 3G subscribers were aggregated in the HLR
SGSN and GGSN Subscriber GPRS serving nodes
(SGSN) were dimensioned in terms of simultaneously connected (2G+3G) subscribers
Gateway GPRS serving nodes (GGSN) were dimensioned in terms of (2G+3G) active packet data control (PDP) contexts
SGSNs/GGSNs had defined capacities, subject to a utilisation factor
SMSC The peak SMS throughput was
calculated SMS centres (SMSC) had a peak
throughput capacity, subject to a utilisation factor
Background to the original LRAIC model • Reference design • 7. HLR, SMSC, GSNs
34
19176-225
The model purchased assets using both lead and replacement periods The model calculated active network
assets at mid-year
Capital expenditure (capex) on assets occurred 1–18 months in advance of activation:
depending on lead times and the size of network assets
Operating expenditure (opex) was incurred once the asset is active
A replacement lifetime (5–25 years) determined when an asset was replaced (at its current cost)
Time
Demand requirement (t)subject to max.
utilisationLook-aheadperiod
Ord
erin
gP
urch
asin
gD
eplo
ymen
tTe
stin
gA
ctiv
atio
n
Dep
loym
ent
Purchase requirement subject to
look-ahead
Lead time expenditure profile
Background to the original LRAIC model • Reference design • 8. Expenditure rules
Source: Analysys Mason
35
19176-225
Network elements were removed when no longer required Due to migration off the networks,
traffic-driven assets sometimes became unnecessary, although coverage rules still applied
The rate at which assets were removed from the network was an input to the model
Removal saved: asset replacement costs opex
Investment costs were still fully recovered; but removal was considered to be at zero cost with zero scrap value Time
Dep
loym
ent
Actual requirement according to
demand
t=1 t=2 t=100
Retirement options
Background to the original LRAIC model • Reference design • 8. Expenditure rules
Source: Analysys Mason
36
19176-225
The LRAIC approach used a four-part mark-up
Dedicated 2G assets
Incremental
Applicable to 2G-only services
Dedicated 2G assets –
common
Dedicated 3G assets
Incremental
Applicable to 3G-only services
Dedicated 3G assets –
common
Shared assets
Incremental
Applicable to 2G+3G services
Shared assets – common
Retail incremental and common costs
Business overhead common costs
Mark-up sequenceIncremental and common cost components
Shared
Overheads
3G2G
Background to the original LRAIC model • Reference design • 9. Incremental costs
Source: Analysys Mason
37
19176-225
Background to the original LRAIC model
Introduction
Proposed upgraded cost model
Next steps
Glossary
Model specification
Reference design
38
19176-225
Several conceptual issues are being revisited in this upgrade …
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs. data
Network vs. retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
Conceptual issues
To be revisited in more detailKEY To effectively remain as in original
Proposed upgraded cost model • Model specification
39
19176-225
Conceptual issue
New recommendations for upgraded cost model
A. Supplementary interconnect services
Separately calculate the cost of establishment of interconnect
B. Pure LRIC increment
Implement a pure LRIC calculation of voice/SMS termination consistent with the EC Recommendation
… and a small number of new ones are being introduced
KEY To be reconsidered
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs. data
Network vs. retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
Proposed upgraded cost model • Model specification
40
19176-225
A particularly important upgrade is the inclusion of a ‘generic operator’ A generic operator will be added
into the cost model:
industry parties, other than NITA, will only see their own inputs (if applicable) and the generic outputs
This structure will increase transparency, whilst preserving confidentiality and ensuring the model still reflects Danish mobile operations
Proposed upgraded cost model • Model specification
As visible to NITA
As visible to operators (e.g. TDC)
Generic bottom-up calculation
engine
Common inputs
Generic operator inputs
TDC-specific inputs
Telia-specific inputs
Telenor-specific inputs
Hi3G-specific inputs
Generic operator outputs
TDC outputs
Telia outputs
Hi3G outputs
Telenor outputs
TDC-specific inputs
Common inputs
Generic operator inputs
Generic operator inputs
TDC outputsGeneric bottom-up calculation
engine
41
19176-225
The structure of the model will remain the same
1. Structure:
The overall structure of the original mobile LRAIC model will be retained:
the model will continue to be a bottom-up calculation with top-down validation
Industry data will be used for hybridisation:
calibration to ensure the number of modelled assets (sites/equipment) reflects those actually deployed
reconciliation to ensure that modelled expenditures reflect expenditures actually incurred
KEY To effectively remain as in original
Proposed upgraded cost model • Model specification • Operator
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
Technology
42
19176-225
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
The model will still consider both 2G and 3G technologies
5. Technology generations:
The upgraded cost model shall continue to capture the effects of technology generations between 2G and 3G (and LTE if modelled)
We expect the 2G network to be shut down in the longer term, consistent with the principles of the original model:
this assumes that 3G is the long-term replacement for 2G and it would be inefficient for both technologies to coexist
KEY To effectively remain as in original
Proposed upgraded cost model • Model specification • Technology
43
19176-225
The generic operator will assume an efficient network
8. Network nodes:
The generic operator will adopt the modified scorched-node principle, as was used in the original model
The model will reflect the number of nodes in real operators’ networks, but the function of the node may be ‘scorched’ if not efficiently deployed
Examples of scorching would include: moving remote base station
controllers (BSCs) to the main switching sites, and replacing with a transmission hub or radio site
interchanging radio sites between macro, micro and pico sites
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
KEY New recommendations
Proposed upgraded cost model • Model specification • Technology
44
19176-225
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
MNOs cost data and benchmarks will be used to derive cost inputs
9. Input costs: The cost base for the generic operator
will be based on the actual costs incurred by operators, validated against international benchmarks
Where operators have materially different cost inputs, an average could be taken, but other processing will be used where appropriate:
confidential data will not be used directly in any model released to industry
In the absence of operators’ input cost information, a suitable benchmark, adjusted for efficient purchasing scale, will be utilised
KEY To effectively remain as in original
Proposed upgraded cost model • Model specification • Technology
45
19176-225
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
The generic operator will have access to average spectrum holdings
10. Spectrum situation: The model will remain capable of
capturing the network/cost differences arising from different spectrum allocations and fee structures
For the generic operator, we propose to assume spectrum of:
2×8.8MHz of 900MHz spectrum 2×18.8MHz of 1800MHz spectrum 2×15MHz of 2100MHz spectrum 2×20MHz of 2600MHz spectrum
The model will include 3G licence fees (but not 2G), and spectrum usage fees based on the current NITA charges
New recommendations KEY To effectively remain as in original
Proposed upgraded cost model • Model specification • Technology
46
19176-225
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
The key service change in the upgrade is the inclusion of HSPA
11. Service set:
The generic operator will provide all the commonly available (current and planned) Danish non-voice services alongside voice services:
this will include mobile data services such as HSPA
Economies of scope will be shared across all services:
forecast sensitivities will be explored to ensure that uncertain growth forecasts do no over-influence the economic cost of voice/SMS
New recommendations KEY To effectively remain as in original
Proposed upgraded cost model • Model specification • Technology
47
19176-225
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
Only wholesale network costs will be considered
12. Wholesale or retail:
Following NITA’s market definition, only wholesale network costs will be calculated
Business overheads common to both retail and network operations will be:
included in the LRAIC costing approach (through a mark-up on all services)
excluded from the pure LRIC approach
New recommendations KEY To effectively remain as in original
Proposed upgraded cost model • Model specification • Services
48
19176-225
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
The WACC will be updated with the most recent data available
13. WACC:
The original LRAIC model used a nominal, pre-tax WACC derived using the CAPM:
sector-specific parameters include beta and the optimal gearing ratio
It will be investigated whether the value of WACC requires revision:
to ensure that the most up-to-date parameters are implemented, this will only be undertaken in the final costing stage
KEY To effectively remain as in original
Proposed upgraded cost model • Model specification • Implementation
49
19176-225
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
The model will continue to use economic depreciation
14. Depreciation method:
It is appropriate to continue using economic depreciation to recover network expenditures in line with modern equivalent asset (MEA) price trends, network output over the long run, and the discount rate
Economic depreciation
Year1 2 3 4 5
Plus change in utilisationover the asset lifetime
Change in asset priceover the asset lifetime
KEY To effectively remain as in original
Proposed upgraded cost model • Model specification • Implementation
50
19176-225
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
The years modelled and the mark-up mechanism remain the same
16. Years of results:
The model will still consider the years 1992 to 2041 (as in the original model):
we will ensure consistency between expenditure, network activity and cost-recovery timeframes
17. Mark-up mechanism:
The model will continue to use EPMU for calculating network common costs and shared business overheads:
however, the pure LRIC calculation will not require mark-ups
KEY To effectively remain as in original
Proposed upgraded cost model • Model specification • Implementation
51
19176-225
A new ‘generic operator’ will be developed …
2. Type of operator: This is one of the most significant
changes to the upgraded cost model: the most recent termination pricing
decision used the highest cost operator from the original model
NITA has also decided to consider a generic operator:
this operator will be based on an efficient mobile network deployment
this allows the calculation to be fully shared with industry stakeholders, thereby increasing transparency
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
KEY New recommendations
Proposed upgraded cost model • Reconsidered principles • Operator
52
19176-225
… but actual operator data will still be required for hybridisation
This approach has been recently used successfully in the Netherlands and Sweden
The model can be shared, as model inputs and other parameters will use market averages and benchmarks
However, it is still necessary to collect real operator inputs to allow comparison:
this data is not included in any public release of the model
these inputs will allow the model to still be hybridised (both calibration and reconciliation)
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
KEY New recommendations
Proposed upgraded cost model • Reconsidered principles • Operator
53
19176-225
Both transparency and accuracy will be ensured in the upgrade
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
KEY New recommendations
Industry bottom-up data
Bottom-up model
Bottom-up calculations
Industry top-down data
Top-down verifications
Top-down calculations
Hybridised model
Final results
Upgraded model calculationA generic operator calculation ensures transparency and
shareability
Calibration/reconciliation ensures that real-world accuracy is preserved
Proposed upgraded cost model • Reconsidered principles • Operator
54
19176-225
Given the historical development of Danish operators …
3.1. Steady state size of the operator:
Prior to 2010, the number of active MNOs in Denmark has been made of two periods:
two active operators between 1992 and 1998
four (almost) constantly since 1998
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
Historical number of operators in Denmark
Source: NITA
012345
Num
mbe
r of a
ctive
M
NOs
KEY New recommendations
Proposed upgraded cost model • Reconsidered principles • Operator
55
19176-225
… the generic operator will be assumed to have 25% market share
In NITA’s 2011 mobile termination pricing decision, the market share of each of the Danish MNOs was assumed to be 25% from 2010 onwards:
this principle will be retained for the generic operator in 2010
We note that recent market developments indicate a degree of network sharing between Danish MNOs in the future
The evolution of the MNOs’ future market share will depend on the nature of the integration involved (radio-network only, or integration of the retail brands as well)
For the moment, a steady-state market share of 25% will be assumed for the generic operator
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
KEY New recommendations
Proposed upgraded cost model • Reconsidered principles • Operator
56
19176-225
How the generic operator reaches this market share is also important
3.2. Assumed evolution to the steady-state size: The past evolution of an operator will
influence the economic costs calculated, thus affecting the unit cost of traffic
Therefore, it is a key costing issue for wholesale mobile termination (though it affects LRAIC+ more than pure LRIC)
Higher output (higher utilisation) over the network lifetime generally gives rise (through economies of scale) to a lower unit of traffic
We have suggested four options that could be modelled for the generic operator (see next slide)
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
KEY New recommendations
Proposed upgraded cost model • Reconsidered principles • Operator
57
19176-225
The four profile options depend on increasing amounts of historical data
0%
25%
50%
75%
100%
0%
25%
50%
75%
100%
0%
25%
50%
75%
100%
0%
25%
50%
75%
100%
1. Hypothetical new entrant 2. Reach immediate scale
3. Hypothetical existing entrant 4. Historical-based profile
Area coverage Market share of subscribers
Area coverage Market share of subscribers
Proposed upgraded cost model • Reconsidered principles • Operator
Source: Analysys MasonNote: Values are for illustration purposes only
58
19176-225
We currently consider option 1 and option 4 to be less suitable …
Proposed upgraded cost model • Reconsidered principles • Operator
0%
25%
50%
75%
100%
Area coverage Market share of subscribers
0%
25%
50%
75%
100%
Area coverage Market share of subscribers
1. Hypothetical new entrant
4. Historical-based profileOption 4:
Relies heavily on long-past historical information from periods when the mobile market was configured differently from the current four-player situation
Option 1:
Does not reflect likely future market developments
Source: Analysys MasonNote: Values are for illustration purposes only
59
19176-225
… therefore, we recommend options 2 or 3, but invite industry feedback
0%
25%
50%
75%
100%
Area coverage Market share of subscribers
3. Hypothetical existing entrant
Option 2:
Equivalent to an operator undertaking a full renewal of its network deployment disregarding all previous expenditures
Option 3:
A period to achieve coverage roll-out would be specified along with a period to achieve steady-state size
This means that real technology transitions can be reflected
0%
25%
50%
75%
100%
Area coverage Market share of subscribers
2. Reach immediate scale
Proposed upgraded cost model • Reconsidered principles • Operator
Source: Analysys MasonNote: Values are for illustration purposes only
60
19176-225
There are range of choices to a hypothetical profile for both 2G …
Using 900MHz, with 1800MHz available
from 1997:
As was the case for the two early 2G Danish entrants
Using 1800MHz, with 900MHz available
from 2001:
As was the case for the two later 2G entrants
Using both 900MHz and 1800MHz:
First year where both 2G frequency bands were
allocated to all 2G operators
Using both 900MHz and 1800MHz:
First year where 2G and 3G frequencies were
available to all 2G operators
Using both 900MHz and 1800MHz:
Assuming instantaneous scale
Using both 900MHz and 1800MHz:
First year in which all current MNOs had access to
900MHz, 1800MHz and 2100MHz spectrum
1992 1997 2001 2005 2010 2011
Proposed upgraded cost model • Reconsidered principles • Operator
61
19176-225
… and 3G network developments
Using 2100MHz spectrum:
First year in which 3G networks were
commercially active in Denmark
Using 2100MHz spectrum:
First year in which 2100MHz frequencies
were available
Using 2100MHz spectrum:
First year in which the four current 3G networks were commercially active
Using 2100MHz spectrum:
First year in which the four current 3G network operators
had 2100MHz
Using 2100MHz spectrum:
Assuming instantaneous
scale?
Using 900/1800/2100MHz
spectrum:
Assuming a hypothetical new entrant
2002 2003 2007 2010 201120051992 1997
Proposed upgraded cost model • Reconsidered principles • Operator
62
19176-225
The generic operator will be assumed to use both 2G and 3G
4. Radio technology standards: The model design will continue to
consider both 2G and 3G networks, and include HSPA technology explicitly
We note that LTE assets could share some costs of termination traffic (i.e. site sharing and core transmission network): however, the impact on the
LRAIC+ or pure LRIC is likely to be only small and downward
in the medium term, LTE is unlikely to convey large volumes of wholesale mobile termination
We therefore propose that LTE is not modelled
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
KEY New recommendations
Model specification • Reconsidered principles • Technology
63
19176-225
The coverage profile of the generic operator depends on other factors
6. Extension and quality of coverage:
The four geotypes as defined in the original model will be retained in the upgraded cost model
However, the final 2G/3G coverage profiles for the generic operator depends on:
the market share evolution profile adopted
the assumed spectrum holdings
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
KEY New recommendations
Model specification • Reconsidered principles • Technology
64
19176-225
The generic operator’s LMA will be based on those of actual operators
7. Transmission network: We propose a mixture of microwave
and leased-line LMA backhaul for the generic operator, based on the actual 2G/3G networks
HSPA will require modelling of additional backhaul options (e.g. Ethernet backhaul), due to higher traffic throughput:
HSPA transmission upgrades shall be modelled as an upgrade of the 3G LMA network
Greater levels of efficient integration at the backbone transmission layer may be modelled if reasonable for Danish deployments
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
KEY New recommendations
Model specification • Reconsidered principles • Technology
65
19176-225
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
KEY New recommendations
Costs for the establishment of interconnect will be separated out
A. Supplementary interconnect services:
NITA wants the upgraded cost model to be capable of separately specifying the costs of interconnection establishment: originally these were captured in the
overall cost base, so we will ensure double-counting is avoided
Set-up and maintenance-related costs shall be considered separately
The model will use data from both stakeholders and the Co-location model from NITA’s fixed network cost model
Section 5 of the data request outlines questions related to these services
Model specification • Reconsidered principles • Service
66
19176-225
The EC recommends a ‘smaller’ increment for wholesale termination
15. Increments:
The EC Recommendation of May 2009 outlines a derivation of the pure LRIC of wholesale mobile termination:
the current model uses LRAIC+
This ‘smaller increment’ approach of pure LRIC is only relevant to wholesale mobile termination services
This approach will be implemented as an add-on to the existing model:
the LRAIC calculations will also be retained
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
KEY New recommendations
Model specification • Reconsidered principles • Implementation
67
19176-225
NITA is now looking to quantify this pure LRIC of termination in Denmark
Cost-volume of pure LRIC
Pure LRIC increment
pure LRIC
Volume
Cos
t
Incremental cost of termination
Network share of business overheads
Large parts of mobile coverage network, plus traffic related costs
for other services
Network common costs (some coverage, spectrum)
SIM
Volume
Cos
t
LRAICCommon costs
Cost-volume of LRAIC+
LRAIC+ increment
Incremental cost of all traffic(radio sites, base station
controllers, mobile switching centres etc.)
Network share of business overheads
Network common costs (some coverage, spectrum)
SIM
Model specification • Reconsidered principles • Implementation
Source: Analysys Mason
68
19176-225
Pure LRIC is derived as the difference of two modelling states
KEY Input OutputCalculation
Run model with all traffic
Run model with all traffic except
termination increment
volume
Expenditures with termination
Output profile with termination
Expenditures without
termination
Output profile without
termination
Difference in expenditures
Difference in output
Capex and opex trends
Economic cost of difference in expenditures
Total economic cost of the difference
Unit ‘pure LRIC’Termination traffic volume
Model specification • Reconsidered principles • Implementation
Source: Analysys Mason
69
19176-225
The upgraded model will also calculate the cost of MT-SMS
B. Treatment of the costs of voice/SMS: The upgraded cost model will contain
a new costing approach capable of calculating the pure LRIC of mobile termination for mobile-terminated (MT) wholesale voice and wholesale SMS
We propose to assume a single increment definition for terminated traffic in this calculation, i.e. it is either:
MT-voice only both MT-voice and MT-SMS
The avoided costs will be allocated between these services using routeing factors
Technology
Service
Operator
Implementation
TypeSize
Network designRadio technology
SpectrumVoice vs data
Network vs retailWACC
DepreciationSize of incrementYear(s) of resultMark-up method
Structure
KEY New recommendations
Model specification • Reconsidered principles • Implementation
70
19176-225
We have rejected the use of a separate increment for MT-SMS
Out of the three approaches to derive the pure LRIC of voice and SMS, we believe it appropriate to disregard both:
separate independent increments, as it can lead to double-counting of avoided costs
and separate dependent increments, as it is complex and may lead to different results depending on the order of traffic removal
Incremental cost ofvoice and/or SMS termination
Network share of business overheads
Majority of coverage network, plus other traffic-related costs
Network common costs (some coverage, spectrum)
SIM
Incremental cost ofvoice termination
Network share of business overheads
Majority of coverage network, plus other traffic related costs
Network common costs (some coverage, spectrum)
SIM
Incremental cost ofSMS termination
Single increment to be used*
Separate increment rejected*
*Costs associated with the shaded boxes are included in the approach
Possible double-counting of avoided costs
Model specification • Reconsidered principles • Implementation
71
19176-225
Background to the original LRAIC model
Introduction
Proposed upgraded cost model
Next steps
Glossary
Model specification
Reference design
72
19176-225
Small revisions are required to the original reference design The reference design has been
revised in several places
Industry comment is welcome
1. Demand inputs:
The original mobile LRAIC model considered 3G packet data as one category
The upgraded cost model will distinguish between R99 and HSPA data megabytes on the 3G networks:
LTE data-only subscriptions would also need to be considered separately for a holistic forecast
1. Demand inputs
2. Network design parameters
3. Network design algorithms
4. Unit costs
5. Network costing
6. Top-down data and reconciliation
7. WACC
8. Economic depreciation
9. Routeing factors
10. Service costing and mark-ups
11. Model documentation
KEY Different to original reference design
Upgraded cost model • Reference design • 1. Demand inputs
73
19176-225
Network parameters will be added to capture HSPA …
KEY Different to original reference design
Upgraded cost model • Reference design • 2. Design parameters
2. Network design parameters
A large number of the existing network design aspects will still be used:
some parameters require enhancements due to the implementation of HSPA (and, were it to be modelled, LTE)
Network loading parameters
Changes
Call attempts and ringing time
No change anticipated
Busy-hour profile The packet data busy-hour profile will be re-examined given recent growth in data volumes. If possible, GPRS, EDGE, R99, HSPA (and LTE) volumes will be analysed separately
Treatment of SMS and GPRS
No change anticipated
74
19176-225
… though many factors are subject to the outcome of the data request
KEY Different to original reference design
Upgraded cost model • Reference design • 2. Design parameters
Network loading parameters
Changes
Treatment of high-speed packet data
• R99 packet data remains unchanged• High-speed data will be modelled separately according to
the load on 3G cells• A range of throughput options for these data services are
proposed, but these may change based on the responsesto the data request
Location updates and handovers
• No changes to the 2G layer, or R99 voice/data• No uplift needed for HSDPA traffic
Cell load • No changes for voice traffic• An average throughput of 40% of peak will be assumed,
unless the data provided implies otherwise
75
19176-225
We propose that 800MHz spectrum be modelled for use in 3G/LTE
KEY Different to original reference design
Upgraded cost model • Reference design • 2. Design parameters
Coverage parameters
Changes
Geotypes • The four geotypes used will be retainedCell radii • (Were they to be needed, LTE cell radii would be
estimated using the same process as for 2G/3G in the original mobile LRAIC model)
Spectrum differences • 800MHz will be assumed to be available from 2013 onwards for use in 3G networks (and LTE were it to be modelled) as per the currently expected auction date
Special areas • No change anticipatedTraffic by geotype • No change anticipated
76
19176-225
Equipment capacity parameters
Changes
Radio element capacities
• HSDPA (respectively HSUPA): it is assumed that each 2×5MHz carrier conveys up to 21.1Mbit/s (respectively 11.5Mbit/s) in the data busy-hour
• LTE: were it to be modelled, each 2×5MHz carrier would be assumed to convey 86.4Mbit/s)
Backhaul links • Higher-capacity backhaul links required compared to the original model (which used E1s). HSPA backhaul would be an upgrade of the 3G LMA backhaul
• The modelled fibre network will also be enabled to convey a proportion of this traffic
Both radio element capacities and backhaul elements will be updated
KEY Different to original reference design
Upgraded cost model • Reference design • 2. Design parameters
77
19176-225
Equipment capacity parameters
Changes
BSC and RNC switches
• Were it to be modelled, the LTE network could require a radio network controller (RNC) equivalent, depending on operator feedback and the final network design
Remote BSC vs. co-located BSC
• No changes anticipated, subject to operator information submitted
BSC-MSC links • No changes anticipated, subject to operator information submitted
MSC-MSC links • Separate 2G MSC–2G MSC and 3G MSS–3G MSS links are modelled. Operator asset upgrades (e.g. further integration) will be accounted for in the model
Network software • No changes anticipated
If LTE is not modelled, most switch and link designs remain the same
KEY Different to original reference design
Upgraded cost model • Reference design • 2. Design parameters
78
19176-225
Equipment capacity parameters • 2G MSC and 3G MSS/MGW switches
(including VLR functionality)Changes• 2G/3G layer to remain unchanged
• An LTE core architecture would be needed to carry the data traffic as shown. Switches deployed according to the minimum number of locations and the busy-hour load on the processor (Mbit/s). Ports on these switches will be calculated according to their different functions
If LTE were to be modelled, a new core architecture would be needed
Proposed LTE architecture
Control plane
Control platforms
IP multimedia subsystem
Management entity
Service platforms
Voice Interconnect
Data Interconnect
eNode B eNode B
Packet-domain services only
Access gateway
KEY Different to original reference design
Upgraded cost model • Reference design • 2. Design parameters
79
19176-225
Few changes are needed to capacity inputs, but GSNs may be refined
KEY Different to original reference design
Upgraded cost model • Reference design • 2. Design parameters
Equipment capacity parameters
Changes
Data servers The original model considered separate 2G and 3G units. Unless indicated otherwise, it is expected that the GSN will now be dual-technology rather than separate-technology units
The fibre network No changes anticipatedSMS centre (SMSC) No changes anticipated. MT-SMS does not use the SMSC,
therefore the pure LRIC of MT-SMS will not include its contribution
HLR and other network elements
No changes anticipated, subject to operator information submitted
Capacity utilisation factors
No changes anticipated, subject to operator information submitted
80
19176-225
The modelled generic backbone design will be retainedNetwork topology
The original generic network design will be used as the starting point for upgrade
Geographically, a physical network topology was assumed that consisted of:
a 1000km fibre backbone
PoIs, core switching sites, remote hubs (BSC/RNC) in a specific number of locations
backhaul link topology consistent with the real operator’s network design
Jutland fibre ring
Fyn fibre ring
Sealand fibre ring
National fibre backbone
Source: Analysys Mason
Upgraded cost model • Reference design • 2. Design parameters
81
19176-225
4. Unit costs:
No changes currently required, but future developments may mean that unit asset cost trends require adjusting to reflect network sharing
5. Network costing:
Subject to operator information, new assets will be assigned lifetimes and planning periods based on equivalent existing assets:
if equivalents do not exist, then international benchmarks and/or stakeholder data will be used to inform the inputs
3. Network design algorithms:
The modelled HSPA deployment based on both stakeholder information and our network design experience from other jurisdictions
For pure LRIC, the network design algorithm may need to be refined in order to model the mobile network when termination traffic is not included:
Section 4 of the data request allows operators to provide feedback that may help guide any appropriate modifications
The HSPA implementation will be based on stakeholder feedback
KEY Different to original reference design
Upgraded cost model • Reference design • 3,4,5. Network factors
82
19176-225
Hybridising the generic operator model will still be an important step
KEY Different to original reference design
Upgraded cost model • Reference design • 6,7,8. Cost factors
6. Top-down data and reconciliation:
As mentioned earlier, model hybridisation will still be undertaken (i.e. calibration and reconciliation exercises):
real world data will help increase model robustness
The generic operator cannot be expected to exactly match real operators’ asset or cost data:
but, for example, there should not be significantly fewer/more sites deployed for a comparable level of coverage
7. WACC:
No changes to value at present:
NITA is expected to update the WACC value at a later stage
8. Economic depreciation:
No changes; economic depreciation will be used as before
83
19176-225
The documentation will be updated to include all model developments9. Routeing factors:
No changes anticipated, subject to operator information submitted:
though changes may arise from the adaptation of the network design (e.g. the explicit addition of HSDPA)
10. Service costing and mark-ups:
As mentioned earlier, pure LRIC does not require mark-ups, but mark-ups will be retained for the LRAIC+ calculation
KEY Different to original reference design
11. Model documentation
Documentation will be updated to reflect the upgraded model, including enhancements made
The aim is to position users to understand both the main features of the model and its technicalities
The documentation will explain, where possible, the reasons for choices adopted in the model
Upgraded cost model • Reference design • 9,10,11. Other factors
84
19176-225
Background to the original LRAIC model
Introduction
Proposed upgraded cost model
Next steps
Glossary
85
19176-225
The data-collection process will begin following this workshop
replies by 12 September 2011 on demand and network data– coverage data– subscriptions and volumes– network loading data– asset information and lifetimes– network dimensioning rules– upcoming deployments
replies by 17 October 2011 on remaining data– pure LRIC specific relationships– interconnection data– bottom-up equipment unit costs– top-down expenditure data
Data requests were issued to industry stakeholders prior to the industry workshop
Data submissions will be split into two parts:
Next steps
86
19176-225
Next steps and upcoming milestones following this industry meeting Electronic versions of these slides will be uploaded onto NITA’s website
Industry stakeholders are invited to provide feedback, by 11 August 2011 to NITA, on the draft reference paper
We will be available to clarify any aspects of the data collection in the coming weeks:
in the week commencing 29 August 2011, we have provisionally scheduled time in Copenhagen to discuss the data request with stakeholders
Next steps
87
19176-225
Main contacts
For NITA
Morten Møller Johnsen or
Frederik Rygaard
+45 3545 0000
For Analysys Mason
Matthew Starling
+44 845 600 5244
Next steps
88
19176-225
Relevant documents [1 of 3]
Reference paper for the original mobile LRAIC model:
http://www.itst.dk/tele-og-internetregulering/smp-regulering/engrospriser/filarkiv-engrospriser/lraic/lraic-processer/lraic-mobil/horing-over-lraic-mobil-principdokument/LRAIC%20principdokument_final.pdf
Original mobile LRAIC model documentation:
http://en.itst.dk/telecom-internet-regulation/smp-regulation/lraic/filarkiv-lraic/lraic-pa-mobil/udsendelse-d-19-6-08/Final%20v4%20NITA%20model%20documentation_090608.pdf
Documentation related to the upgraded mobile cost mobile project will be made available on NITA’s website:
http://www.itst.dk/tele-og-internetregulering/smp-regulering/engrospriser/lraic-1/lraic-processer/lraic-mobil/opbygning-af-lraic-mobil-2011-2012/
Next steps
89
19176-225
Relevant documents [2 of 3]
Act on ‘Competitive Conditions and Consumer Interests in the Telecommunications Market’:
http://en.itst.dk/law-material/filarkiv/acts/Act%20on%20Competitive%20Conditions%20and%20Consumer%20Interest%20in%20the%20Telecommunications%20Market.pdf
NITA’s decision on wholesale mobile SMS termination regulation:
http://www.itst.dk/tele-og-internetregulering/smp-regulering/markedsundersogelser/2-runde-af-markedsundersogelser/horing-over-markedsanalyser/marked-7-sms-terminering
EC Recommendation on wholesale termination costing:
http://eur-lex.europa.eu/LexUriServ/LexUriServ.do?uri=OJ:L:2009:124:0067:0074:EN:PDF
Next steps
90
19176-225
Relevant documents [3 of 3]
Denmark’s most recent Executive Order, February 2011:
https://www.borger.dk/Lovgivning/Hoeringsportalen/Sider/Fakta.aspx?hpid=2146002408
Redacted shell of the original mobile LRAIC model:
http://www.itst.dk/tele-og-internetregulering/smp-regulering/engrospriser/filarkiv-engrospriser/lraic/lraic-processer/lraic-mobil/horing-over-udkast-til-eftersporgsels-og-netmodel/Modeludkast.zip
NITA’s pricing decision on wholesale mobile termination, 2011:
http://www.itst.dk/tele-og-internetregulering/smp-regulering/engrospriser/filarkiv-engrospriser/lraic/lraic-priser/2010/prisafgorelse-for-mobilterminering
Next steps
91
19176-225
Background to the original LRAIC model
Introduction
Proposed upgraded cost model
Next steps
Glossary
92
19176-225
Glossary
2G: Second generation of mobile telephony
3G: Third generation of mobile telephony BHCA: Busy hours call attempts BSC: Base station controller BTS: Base transmitter station or base
station CAPM: Capital asset pricing model CCH: Control channel CE: Channel element CK: Channel kit E1: 2Mbit/s unit of capacity EC: European Commission EDGE: Enhanced data for global evolution eNodeB: LTE equivalent of a NodeB EPMU: Equi-proportionate mark-up
GGSN: Gateway GPRS serving node GMSC: Gateway mobile switching centre GPRS: General packet radio system GSM: Global system for mobile
communications GSN: GPRS serving node HLR: Home location register HSDPA: High speed downlink packet
access HSPA: High speed packet access HSUPA: High speed uplink packet access IP: Internet Protocol IN: Intelligent network LMA: Last-mile access LRAIC: Long-run average incremental cost LRIC: Long-run incremental cost
93
19176-225
Glossary
LTE: Long-term evolution Mbit/s: Megabits per second MEA: Modern equivalent asset MGW: Media gateway MHz: Megahertz MNO: Mobile network operator MSC: Mobile switching centre MSS: MSC server MT: Mobile terminated NITA: National IT and Telecom Agency NMS: Network management system NodeB: Denotes the 3G equivalent of a
BTS PCU: Packet control unit PDP: Packet data protocol
PoI: Point of interconnect PS: Packet switch R99: Release-99 RNC: Radio network controller SGSN: Subscriber GPRS serving node SIM: Subscriber identity module SMS: Short message service SMSC: SMS centre STM: Synchronous transport module TDC: Tele-Denmark Communications TRX: Transceiver unit TSC: Transit switching centre VLR: Visitor location register WACC: Weighted average cost of capital
94
19176-225
Copyright © 2011. Analysys Mason Limited has produced the information contained herein for the National IT and Telecom Agency
(NITA). The ownership, use and disclosure of this information are subject to the Commercial Terms contained in the contract between
Analysys Mason and NITA
Analysys Mason Limited
St Giles Court, 24 Castle Street
Cambridge CB3 0AJ, UK
Tel: +44 (0)845 600 5244
Fax: +44 (0)1223 460866
www.analysysmason.com
Registered in England No. 5177472