update of nesc subcommittee #5 activities

22
Update of NESC Subcommittee #5 Activities 2004 APPA E&O Joseph Rempe, P.E. Principal Engineer T&D, Tacoma Power APPA Representative on SC5 Overhead Delivery Issues

Upload: evangeline-pugh

Post on 01-Jan-2016

44 views

Category:

Documents


1 download

DESCRIPTION

Overhead Delivery Issues. Update of NESC Subcommittee #5 Activities. 2004 APPA E&O Joseph Rempe, P.E. Principal Engineer T&D, Tacoma Power APPA Representative on SC5. What the NESC IS and What it is NOT. It IS a Performance Code – Set the minimum standard for operating performance. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Update of NESC Subcommittee #5 Activities

Update of NESC Subcommittee #5 Activities

2004 APPA E&OJoseph Rempe, P.E.

Principal Engineer T&D, Tacoma Power

APPA Representative on SC5

Overhead Delivery Issues

Page 2: Update of NESC Subcommittee #5 Activities
Page 3: Update of NESC Subcommittee #5 Activities
Page 4: Update of NESC Subcommittee #5 Activities
Page 5: Update of NESC Subcommittee #5 Activities

What the NESC IS and What it is NOT

• It IS a Performance Code – Set the minimum standard for operating performance.

• It is NOT a design standard (ie. NEC) – It is not intended to be the design processes by which lines are designed.

• A difficult act to maintain – the Nature of Engineers.

Page 6: Update of NESC Subcommittee #5 Activities

Highlighted Proposed Changes for the 2005 NESC being considered by

SC5

• Rule 250B – New Ice & Wind Loading Map

• Rule 250C - 60 foot exclusion removed and Extreme Wind considered on all Distribution Structures.

• New Rule 250D – Construction & Maintenance Loads

Page 7: Update of NESC Subcommittee #5 Activities

Changes Cont.

• Rule 261 - FRC (Fiber Reinforced Composite) acknowledged and accepted similar to Steel and Pre-Stressed Concrete.

• Rule 277 – Insulator Strength

• Section 25, 26, & 27 rewrite to reflect Reliability Based Design methodology of applying loads and structure strength.

Page 8: Update of NESC Subcommittee #5 Activities

Rule 250B – Ice & Wind Loading

• To include ASCE 7 Ice and Wind map.

• Developed after the “Perfect Storm” crushed the NE and Eastern Canada

• Cold Regions Research and Engineering Lab (CRREL) of the Army Corps of Engineers (Kathy Jones) & Bonneville Power Administration

Page 9: Update of NESC Subcommittee #5 Activities

Rule 250B – Ice & Wind Loading Continued

• Conductor Clearances is being addressed by Sub-Committee #4.

Page 10: Update of NESC Subcommittee #5 Activities
Page 11: Update of NESC Subcommittee #5 Activities
Page 12: Update of NESC Subcommittee #5 Activities
Page 13: Update of NESC Subcommittee #5 Activities
Page 14: Update of NESC Subcommittee #5 Activities

Rule 250C – 60 foot exclusion • All wind data taken at 10m (33 ft.) [Can

the current statement be defended in court?]

• Larger Distribution Conductors and more Telecommunications attachments

• Distribution Line Failures – typical rural line crossing over a hill: Bernoulli Effect

• Most areas will not see the controlling load change from current practices for Grade C Construction.

Page 15: Update of NESC Subcommittee #5 Activities

Rule 250C – Continued

• Coastal areas are major exceptions. The rule change will limit wind pressure for Grade B design to withstand Class 2 hurricane strength winds. (Winds above this do major structure and vegetation damage that are not reasonable to design for)

• Grade C max 15psi, Grade B max 22psi

Page 16: Update of NESC Subcommittee #5 Activities
Page 17: Update of NESC Subcommittee #5 Activities
Page 18: Update of NESC Subcommittee #5 Activities

New Rule 250D – Construction and Maintenance Loads

• Intent of new rule is to ensure a safe structure for workers to climb and/or work on from initial construction through replacement.

• Rule 263A reference for Grade N construction

Page 19: Update of NESC Subcommittee #5 Activities

Rule 261 - Fiberglass Reinforced Composite (FRC) Poles

• The sub-committee has received a change proposal that supports the inclusion of FRC Poles in the same manner as Steel and Pre-Stressed Concrete Poles.

• New ASCE Engineering Practice #104 for design using FRC Poles.

Page 20: Update of NESC Subcommittee #5 Activities

Rule 277 – Insulator Strength• A presentation by ANSI C29 Committee to

SC5 highlighted failure tests performed on Ceramic and NCI insulators. (Endurance factors need to be seriously considered when loading of Insulators.)

• Sufficient concern was expressed by members of SC5 that a CP was created to address findings of ANSI C29 Committee.

• Rule 253 would include new Rule 253B and new Table 253-3 for Support Hardware and Insulators.

Page 21: Update of NESC Subcommittee #5 Activities

Section 25, 26, & 27 Rewrite

• ANSI is developing a manual for designing structures following the Reliability Based Design (RBD) methodology for applying loads and selecting support structures and hardware.

• To reflect the work of the RBD Task Force.

Page 22: Update of NESC Subcommittee #5 Activities

Please Join Me on SC5!

We have a chair open for you!

•History

•Stories

•Your input on the process

•A chance to visit Piscataway, NJ

Contact Mike Hyland.