update of nesc subcommittee #5 activities
DESCRIPTION
Overhead Delivery Issues. Update of NESC Subcommittee #5 Activities. 2004 APPA E&O Joseph Rempe, P.E. Principal Engineer T&D, Tacoma Power APPA Representative on SC5. What the NESC IS and What it is NOT. It IS a Performance Code – Set the minimum standard for operating performance. - PowerPoint PPT PresentationTRANSCRIPT
Update of NESC Subcommittee #5 Activities
2004 APPA E&OJoseph Rempe, P.E.
Principal Engineer T&D, Tacoma Power
APPA Representative on SC5
Overhead Delivery Issues
What the NESC IS and What it is NOT
• It IS a Performance Code – Set the minimum standard for operating performance.
• It is NOT a design standard (ie. NEC) – It is not intended to be the design processes by which lines are designed.
• A difficult act to maintain – the Nature of Engineers.
Highlighted Proposed Changes for the 2005 NESC being considered by
SC5
• Rule 250B – New Ice & Wind Loading Map
• Rule 250C - 60 foot exclusion removed and Extreme Wind considered on all Distribution Structures.
• New Rule 250D – Construction & Maintenance Loads
Changes Cont.
• Rule 261 - FRC (Fiber Reinforced Composite) acknowledged and accepted similar to Steel and Pre-Stressed Concrete.
• Rule 277 – Insulator Strength
• Section 25, 26, & 27 rewrite to reflect Reliability Based Design methodology of applying loads and structure strength.
Rule 250B – Ice & Wind Loading
• To include ASCE 7 Ice and Wind map.
• Developed after the “Perfect Storm” crushed the NE and Eastern Canada
• Cold Regions Research and Engineering Lab (CRREL) of the Army Corps of Engineers (Kathy Jones) & Bonneville Power Administration
Rule 250B – Ice & Wind Loading Continued
• Conductor Clearances is being addressed by Sub-Committee #4.
Rule 250C – 60 foot exclusion • All wind data taken at 10m (33 ft.) [Can
the current statement be defended in court?]
• Larger Distribution Conductors and more Telecommunications attachments
• Distribution Line Failures – typical rural line crossing over a hill: Bernoulli Effect
• Most areas will not see the controlling load change from current practices for Grade C Construction.
Rule 250C – Continued
• Coastal areas are major exceptions. The rule change will limit wind pressure for Grade B design to withstand Class 2 hurricane strength winds. (Winds above this do major structure and vegetation damage that are not reasonable to design for)
• Grade C max 15psi, Grade B max 22psi
New Rule 250D – Construction and Maintenance Loads
• Intent of new rule is to ensure a safe structure for workers to climb and/or work on from initial construction through replacement.
• Rule 263A reference for Grade N construction
Rule 261 - Fiberglass Reinforced Composite (FRC) Poles
• The sub-committee has received a change proposal that supports the inclusion of FRC Poles in the same manner as Steel and Pre-Stressed Concrete Poles.
• New ASCE Engineering Practice #104 for design using FRC Poles.
Rule 277 – Insulator Strength• A presentation by ANSI C29 Committee to
SC5 highlighted failure tests performed on Ceramic and NCI insulators. (Endurance factors need to be seriously considered when loading of Insulators.)
• Sufficient concern was expressed by members of SC5 that a CP was created to address findings of ANSI C29 Committee.
• Rule 253 would include new Rule 253B and new Table 253-3 for Support Hardware and Insulators.
Section 25, 26, & 27 Rewrite
• ANSI is developing a manual for designing structures following the Reliability Based Design (RBD) methodology for applying loads and selecting support structures and hardware.
• To reflect the work of the RBD Task Force.
Please Join Me on SC5!
We have a chair open for you!
•History
•Stories
•Your input on the process
•A chance to visit Piscataway, NJ
Contact Mike Hyland.