university of sunderland cif 301 unit 4 cif 301 project planning unit 4

26
University of Sunderland CIF 301 Unit 4 CIF 301 CIF 301 Project Planning Project Planning Unit 4 Unit 4

Upload: gloria-hudson

Post on 14-Jan-2016

221 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

CIF 301CIF 301

Project Planning Project Planning

Unit 4Unit 4

Page 2: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

Project PlanningProject Planning

• Introduction

– Why plan?

Page 3: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

The consequences of poor The consequences of poor planningplanning

(in the order they happen)(in the order they happen)• premature project initiation

• wild enthusiasm

• disillusionment

• chaos

• search for the guilty

• punishment of the innocent

• promotion of the non-participants

• definition of the requirement

Page 4: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

Planning componentsPlanning components

• Objectives

• Programme

• Schedule

• Budget

• Forecast

Page 5: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

Planning componentsPlanning components

• Organisation

• Policy

• Procedures

• Standards

Page 6: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

Planning FrameworksPlanning Frameworks

• There are many planning and project frameworks– Two examples are:

• Step Wise

• Prince 2

Page 7: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

Step WiseStep Wise

• Step Wise has 10 defined steps ….

• Step 0 Select project– called step 0 because it is outside main project

planning process

• Step 1 Identify project scope and objectives

• Step 2 Identify project infrastructure

• Step 3 Analyse project characteristics

• Step 4 Identify project products and activities

Page 8: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

Step WiseStep Wise

• Step 5 Estimate effort for each activity

• Step 6 Identify activity risk

• Step 7 Allocate resources

• Step 8 Review / publicise plan

• Step 9 Execute plan

• Step 10 Lower levels of planning

• Within each step are various sub-sections

Page 9: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

Step WiseStep Wise

• Step 1 Identify project scope and objectives– Identify objectives and measures of

effectiveness in meeting them– Establish a project authority– Identify all stakeholders in the project and their

interests– Modify objectives in the light of stakeholder

analysis– Establish methods of communication with all

parties

Page 10: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

Step WiseStep Wise

• Step 2 Identify project infrastructure – Establish relationships between project and

strategic planning– Identify installation standards and procedures– Identify project team organisation

Page 11: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

Step WiseStep Wise

• Step 3 Analyse project characteristics– Distinguish the project as either objective or

product driven– Analyse other project characteristics– Identify high level project risk– Take into account user requirements concerning

implementation– Select general life-cycle approach– Review overall resource estimates

Page 12: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

Step WiseStep Wise

• Step 4 Identify project products and activities– Identify and describe project products (or

deliverables)– Document generic product flows– Recognise product instances– Produce ideal activity network– Modify ideal to take into account need for stages

and checkpoints

Page 13: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

Step WiseStep Wise

• Step 5 Estimate effort for each activity– Carry out bottom-up estimates– Revise plans to create controllable activities

Page 14: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

Step WiseStep Wise

• Step 6 Identify activity risk– Identify and quantify activity-based risks– Plan risk reduction and contingency measures

where appropriate– Adjust plans and estimates to take account of

risk

Page 15: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

Step WiseStep Wise

• Step 7 Allocate resources– Identify and allocate all resources– Revise plans and estimates to account for

resource constraints

Page 16: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

Step WiseStep Wise

• Step 8 Review/publicise plan– Review quality aspects of project plan– Document plans and obtain agreement

Page 17: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

Step WiseStep Wise

• Step 9 Execute plan

• Step 10 Lower levels of planning

– There are no sub-sections for steps 9 & 10

Page 18: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

PRINCE 2PRINCE 2

• PRINCE is an acronym for:– Projects IN Controlled Environments

• PRINCE was conceived and developed by the Central Computer and Telecommunication Agency (CCTA)

Page 19: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

PRINCE 2PRINCE 2

• PRINCE 2 defines three key elements

• Each element has several fundamental constituents

Page 20: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

PRINCE 2PRINCE 2

• Processes– Starting Up A Project (SU); – Initiating A Project (IP); – Directing A Project (DP); – Managing Stage Boundaries (SB); – Controlling A Stage (CS); – Managing Product Delivery (MP); – Closing A Project (CP); – Planning (PL) (also a Component and Technique)

Page 21: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

PRINCE 2PRINCE 2

• Components– Business Case– Organisation– Planning (also a Process and Technique)

– Controls– Management of Risk – Quality In A Project Environment– Configuration Management– Change Control

Page 22: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

PRINCE 2PRINCE 2

• Techniques– Product-Based Planning

– Change Controls

– Quality Reviews

Page 23: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

PRINCE 2PRINCE 2

• Example of actions within a process– Controlling A Stage process actions …

• Authorise work packages• Assess progress• Capture project issues• Examine project issues• Review stage status• Report highlights• Take corrective action• Escalate project issues• Receive completed work packages

Page 24: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

PRINCE 2PRINCE 2

• Actions within the Planning processPL 1 Design a Plan

PL 2 Define and analyse

PL 3 Identify activities and their dependencies

PL 4 Estimate effort for each activity

PL 5 Schedule

PL 6 Analyse risk

PL 7 Complete plan

Page 25: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

PRINCE 2PRINCE 2

• PRINCE2 can be a very powerful tool is used wisely

• PRINCE2 can become very prescriptive

• Overall PRINCE2 is a good framework to use

Page 26: University of Sunderland CIF 301 Unit 4 CIF 301 Project Planning Unit 4

University of Sunderland CIF 301 Unit 4

ConclusionConclusion

• Planning is important

• Planning Frameworks

• Project Frameworks