unfulfilled promise of italian renewable power generation ...€¦ · 2. 010-2015 800. 21.4. 17400....
TRANSCRIPT
unfulfilled promise of Italian renewable power generation investments: secondary market opportunity?
February, 2017
1
Italy has an old, strong tradition of renewables
100% = 110TWh/yr
Solar (PV)
Hydro
Bio/MSW
Wind 15
Producibility(Netplan est
based on 2015 hydro)
55,200MW
9100
Capacity installed
(incl 4GW pumping)
22500
23 18600
47
4200800
Geo
Domestic production about 280TWh in 2015 Renewables cover 39% of production Only 2000 hrs/yr average utilization (2015
hydro -22% vs 2014) Import 46 TWh in 2016, forced maintenance
of french nuclear may reduce it significantly in 2017, forcing more domestic production
120,000 MW active power gen capacity, 65,000 MW thermoelectric, 55,000 renewable (46%), no nuke
Peak load about 60,000 MW Even with no nuclear, relatively low carbon
footprint: 0.36 kg CO2/ kWh produced (about 1/3 less than UK)
19
6
2
€9B wind
Hydro3
€80B renewable power gen capex last 6 years in Italy
100% = 35.7TWh
Solar (PV)
5
Capital expenditure
GeoBio/MSW
0.1
6.8
5.6
Producibility added
23,800MW €80B
43001300
power added2010-2015
800
€63B21.4 17400
301.40.2
€10-20B low performing
assetts
Compliance issues (incomplete permitting)
Reduced incentives (- 8% on PV) Wrong resource assesments drived
excessive leverage (wind) Poor cost O&M management
3
Today, over 600,000 grid connected solar PV installations
Large ground mounted PV plants
3900
3400
11,300
588,000 Rooftop and <20kWmostly family owned rooftops
voters force gov’t to stay honest
20-200kW, 4900 plants, on sitegeneration, business owned
very dispersed
100% = 18,600 MW
about 12,000 investor owned large (>200kW) mostly ground mounted
plants, 1MW average size
active secondary market,5-30MW portfolios, €1.5 -10M EBITDA
4
PV positively contributing to grid management
2009 2010 2011 2012 2013 2014 2015
18.620
30
40
50
60
70 GW
2007 2008
import
thermoelectric
renewable
photovoltaic
Solar making baseload more manageablePeak demand shifting to summer
60 GW
Fonte: GSE Solare Fotovoltaico 2014Fonte: Terna, analisi sintetica dati 2015
5
Aggregators take advantage of disillusioned investors
aggregators
terra firma
Exiting
Patient equity investors Confident on positive outcome of
current litigations with regulator Very effective management of
operations
Passive operation management Nearing 10 years maturity High cost, time consuming asset
management Abusive, unpredictable regulator Concerned lenders
6
PVs are not financial investments: must be managed
Bank models may not represent the maximum achievable Actual resources may differ from predictions Technology evolves, creating new opportunities Costs must adapt to learning curves and competitive markets Rules change Power prices change Connected sites are more valuable than just PV Lenders may have different interests Panel deterioration may not resemble OEM guarantees Original equipment manufacturers evolve, merge or disappear Thefts and natural atmospheric events can be managed Insurance must be managed
The best possible is not the investor prospectus
7
Bank model is the wrong metric for PV (and for wind)
Improve performance
Reduce downtime
Maximize solar power generation
Leverage grid connections to add miniwind
8
PV production + 12% since turnaround
1288 kWh/kW/a
13671456
Actual performance
2013 2014 2015 2016
1285 kWh/kW/aBank model
1457€750,000 additional revenues for a 1MW plant over its bank model time
Netplan turnaround
9
Proper operations: enhancing revenues and cutting cost
11% revenue enancement
after turnaround
original budget
111€450k/yr =100
admin insurancegovernance
O&M
property tax
land rightsauxiliary energy
2
31
138
24
23
€110k/yr = 100
47% cost reduction
3
47
after turnaround
original budget
13
10
23
+12% volume
-1% price of electricity sold
15 power sold
85 incentive 20 years tenure
10
Low hanging fruits on PV: 9 months average pay back
Payback (months)
O&M contractOperating procedures
Grid fee exemptionAuxiliary power contract
Power sale agreementLand lease renegotiation
Stolen panel replacementFaulty panel replacement
New scada/ctrlUPS replacement
Inverter cooling
0 (no investment needed)0000
677
1015
17
EBITDA impact
€16k/yr per MW€ 10k/yr
€ 3000/yr€ 1000/yr€ 1400/yr€ 3000/yr€ 7600/yr€ 4500/yr€ 4600/yr€ 1000/yr€ 1000/yr
EBITDA improvements turn the project cash positive again7 initiatives still on going
other 9 upgrade initiatives with payback between 18 and 48 months not considered for turnaround
11
Own or lease land?
Rent for PV installations highly over priced (3-10x) vs alternative uses Rent is up to 25% of operating costs Initial agricultural land value would have been 5-7% of original capex PV land rent from €12 to €20,000/yr per MW, 25 years, inflation indexed Commercial value of nearby farm rent €1-3,000/yr, 3 years, ¼ of PV or
less Prevailing real estate value €30-50,000/MW Ownership paid in 2-3 years of plant operation
Power generating from connected sites can be upgraded once incentives are gone Current revenue 85% from incentives, yet 15% may represent
€70,000/yr per MW installed on fix tilt, €100,000/yr on tracker based plants
Restructured operating costs, excluding rent, 50-60% of current grid parity
Installed equipment life expectancy 1.5x incentive period Connected site could be upgraded for 10-30% more kWh output Generation prices expected to raise mid term due to planned German
nuclear shutdown and unexpected French nuclear turnaround
12
complete project development SPV merger, tax restructuring, and debt restructuring
revenues costs corporate structure
Split the problem into manageable initiatives
redefine op procedure new scada panel chk/ replacement stolen panel replacement
renegotiate O&M auxiliary power exemption grid fee renegotiate land lease
compliance
231 & adopt modelestablish OdVL81/08 safety complianceestablish DUVRI (safety)PoA reviewL421 remote grid safety
power sale agreementUPS optimization (3kVA)spare parts management
renegotiate insurance safety complianceformalize split of operating and governance responsibility
settle litigationsnegotiate debt restructuring Enel property transfer
UPS optimization 10kVAagricultural tarpInverter cabin cooling
New string box monitoring system
renegotiate property tax (IMU)
Inverter new service contract
remote prod monitoringNew alarm systemsUpgrade anti-theft, 5sites
Insulated dc boxAnti-theft measure 6sites
1H2015
2H2015
completed
ongoing
35 initiatives, €70k/MW total spent, multidisciplinary team: technical, legal, admin
Corporate fixingEBITDA driven
13
Must micromanage every initiative
• New O&M management (make rather than buy)• Renegotiated land rent contracts, purchase?• New SCADA, improved features• New UPS with remote monitoring• Inverter cooling systems• Infra-red modules inspection and replacement• Spare parts management for plant availability• Improved & enforced safety compliance• New panels anti-theft bolts on panels• New alarm and LED light systems• Advanced infra red cameras and DVR for betterremote night vision on all plants• Improved perimetral road and cable ducts• Sting re-wiring to improve performance• Agricultural tarp to avoid shadows by grass growth• Improved grounding• 421/595 Law upgrade
14
a Business not affected by evolving technology
b
c
d
e
f
No real incentive for cost reduction
Upsides opportunities left unattended
Chances considered as “problems”
Little management attention on operation excellence
Management focused into managing downsides such as regulatory changes
Italian PV investors lost grip & entrepreneurial spirit
6kW capacity, rather than MW grid access, it makes less efficient use of sites
Regulatory constrains
7
8
10
Permitting for tracker and miniwindupgrade very complicated
Panel upgrade practically impossible
Punitive regulator, focusing on formal aspects, ignoring merits
1Any plant improvement needs lengthy approval, adding costs
Project finance
Imposed constrains
2
3
4
5
Projected life coincides with incentives, actual equipment life exceeds bank model
Residual value of connected site and equipment not considered
O&M contract clauses do not reflect competitive market conditions
Risks evaluated on a stand alone basis, while project portfolio has a reduced risk
9 No incentive of load optimization, DC/AC step-up, battery storage or trackers
15
The most evident result: unfinished projects
Administrative errors cadastral mistakes ignored prescriptions never ending construction phase
(switchgear title transfer to grid operator, as-built documentation…)
Unsettled minor claims Expired warranties Faulty equipment registration
Unattended prescriptions
Unfinished contractor’s work
Unprecise panel label
Cadastral issues
16
1
Shortage of components made availability, rather than performance, the key driver
2
Lenders focusing on wrong metrics (such as panel financial credibility) rather than quality of design
4
Incompetent technical advisors, certification focus on useless details, no focus on performance
5
Time pressured (non supervised) construction ended with uncompleted permitting and left over administrative issues
7
6
Low quality components and poor construction
Wrong cabling, missing string monitoring
Unreasonable incentives, unclear permitting
Time pressure did allow neither proper functional design nor resource measurements
No system optimization, no mature supplier performance qualification ($/W rather than $/Wh)
3 Grid demand considerations excluded from development of individual facilities, grid operator perceived developers as pain rather than opportunities: fix tilt preferred over trackers
10
9Time pressured detail design resulted in poor plant performances, such as shadows, overheated inverters and undersized cables
Shadows between panels rows
Unreasonable land right costs, missing the option to buy land with valuable grid connection infrastructure
8
Wrong start: PV attracted mostly speculators, not industry
17
Lots of efforts to complete project development
Pis
till
o
Pav
on
e
Gio
rdan
o N
.
Ch
iare
lla
Gio
rdan
o G
.
Gio
rdan
o M
2.
Lago
nig
ro
Mas
iell
o
Pic
ern
o
Ru
sso
Stac
ca
Pis
till
o
Pav
on
e
Gio
rdan
o N
.
Ch
iare
lla
Gio
rdan
o G
.
Gio
rdan
o M
2.
Lago
nig
ro
Mas
iell
o
Pic
ern
o
Ru
sso
Stac
ca
1. Analisi documentazione immobiliare 1.1 Atti preliminari per la costituzione dei diritti immobiliari (verifica intestazione, volture, ecc.)1.2 - Atti di provenienza (contratto di compravendita, di locazione, diritto di superficie, ecc.)1.2.1 - Eventuale Convenzione stipulata con il Comune (se richiesta)1.2.2 - Evidenza che l’area non sia interessata dalla presenza di sottoservizi 1.3 - Dati catastali (verifica aggiornamenti catastali, accatastamenti, categorie ecc.)
2. Analisi documentazione autorizzativa2.1 - Regolarità urbanistica2.1.1 Certificato di Destinazione Urbanistica (verifica presenza vincoli e destinazione urb.)
2.1.2 Accesso all'area interessata (Verifica servitù di passaggio, ecc.)2.1.3. Verifica rispetto distanze minime da confini e strade indicate sul PRG
2.2 - Autorizzazioni alla realizzazione dell’impianto (Verifica DIA con tutti gli allegati)2.2.1 Verifica Relazione Tecnica Generale2.2.2 Verifica Relazione Tecnica di Asseverazione2.2.3 Verifica Relazione Tecnica su inserimento nel PUTT2.2.4 Verifica Atti di Assenzo e Nulla Osta necesari per vincoli o limitazioni presenti2.2.5 Verifica eventuale voltura del procedimento autorizzativo
2.3 - Difformità progetto autorizzato/realizzato2.3.1 Verifica posizionamento cabine rispetto al progetto presentato2.3.2 Verifica layout impianto rispetto al progetto presentato2.3.3 Verifica presenza problematica "DIA a grappolo"
2.4 - Connessione alla rete2.4.1 Verifica istanza DIL alla Provincia2.4.2 Verifica Nulla Osta/pareri2.4.3 Verifica voltue necessarie2.4.4 Verifica servitù di elettrodotto2.4.5 Verifica Verbale di Allaccio o Allegato Q2.4.6 Verifica progetto esecutivo elettrodotto vidimato da Enel2.4.7 Verifica Nulla Osta MSE all'Esercizio (stato sopralluoghi MSE, richieste ecc.)2.4.8 Verifica atto di cessione o della documentazione richiesta da Enel
3. Analisi pratica GSE3.1 - Conto Energia
3.1.1 Schema di incentivazione richiesto (numero conto energia)3.1.2 Accettazione tariffa incentivante GSE (verifica documentazione inviata e congruità)3.1.3 Eventuale maggiorazione richiesta (verifica documentazione inviata e congruità)
3.2 – Stato pratica3.2.1 Verifica Soggetto Responsabile e necessità voltura3.2.2 Verifica congruità comunicazione fine lavori (GSE ENEL Comune)3.2.2 Verifica congruenza scheda tecnica GSE con autorizzazione e varianti 3.2.3 Verifica riconoscimento incentivo e Convenzione
4. Analisi pratica Genio Civile4.1 - Fondazioni e strutture di sostegno
4.1.1 Verifica Istanza di deposito Genio Civile5. Analisi pratica Agenzia delle Dogane
5.1 - Denuncia di Officina Elettrica5.2 Verifica aggiornamento Registri delle Letture settimanali
6. Analisi Documentazione Impianto6.1 Progetto as built, (layout, unifilare ecc)6.2 Dichiarazioni di conformità6.3 Elenco matricole moduli fv6.4 Certificati di taratura contatori6.5 Documentazione sicurezza secondo D.Lgs. 81/086.6 Documentazione impianto di terra (as built, verifiche DPR 462/01)
ESI I ESI IIESI I ESI II2015 2016
• Plant documents to be collected and recovered from MiSe, GSE, Terna, Municipalities, Enel, GenioCivile, …• Documents must be checked for consistency, administrative and legal validity • After the authorization process is complete, property title of power lines and switchgears must be transferred to grid operators• Civil work over public roads must be completed, original status restored
18
Abusive regulator demands require firm response
Regulator is administering €6B/yr of 25 years termrenewable energy incentives to 600,000+ generators
Retroactive Spalmaincentivi decree (-8%) confirmed byhighest Court, investors appeals rejected
GSE (regulator) is searching for even minor administrativeirregularities to revoke incentives
Irregularities include immaterial errors on permitting bylocal authorities, such as typos, wording,…
GSE is asking owners documents that belong tocontractors, suppliers or authorities, and are not accessible
GSE should focus on fundamentals included in theincentive regulation
GSE removing incentives without awaiting for the results ofcourt cases, producing bankruptcy of leveraged SPVs
Netplan estimates €60-70B project financing underchallenge for wind and PV projects
Due to legal battles, uncertainties heavily influencedsecondary market: exit from investments is at loss, even iflong term prospects are excellent
19
Renegotiate all contracts
Turnaround is possible, it requires structured approach
1 Segment issues
Rank initiatives, set priorities
Get alternate suppliers first, get intelligence on counterparts, competitors
Challenge every line of P&L and B/S
All means all, challenge every clause in contracts
Know the business from the root, from blue collar upHave the right people to replace any supplier, if needed
Netplan assisted the teenager on the right to fly: it toke well structured approach: scientific calculations, systematic assembly, very rigorous quality control and 18 staff to let 187 balloons to lift him with proper safety and media coverage...
2
3
4
5
6
7
8
9 In house legal/contractual/commercial expertise as well as engineering
20
Italian wind assets with a slightly different scenario
Large operators with strong industrial tradition already consolidated the market:ERG, EdF, Enel, E.On, Alerion, IVPC, Friel, Falck, …
Plants with incentives developed early 2000s, already nearing end of incentives New plants competing with public renewable energy tenders, last price €66/MWh Best sites (2500 hrs/yr) already taken, marginal sites are either too small, or too
far from HV connections Very strong tradition of high quality asset management and of competitive,
independent, OEM-approved operation and maintenance service providers Active mini-wind industry, yet individual 30-60kW WTG sites, excessively
dispersed…
yet: Plenty of poorly managed small size sites Local small owners with generational change, no desire to stay in business (it
applies also to some of the small hydro concessions) Raising complexity of bidding process
21
Wind case: widely long term underperformance
1643hrs/yr
1726
Site 1
1878hrs/yr
2183
Site 2
1534hrs/yr
1650
Site 3
Actual2010-2015
P75 (bank model)
P50
1624hrs/yr
1659
Site 4
19862388 17991869
22
Power curve WTG 15
Actual 2015
0.841
24%
9%67%
Grid constrains
Availability74 MWh/yr(€11k/yr)
Recoverable, 560 MWh/yr (€80k/yr)
2413hrs/yr
1984 hrs/yr
0500
1000150020002500
0 10 20 30 40
Pow
er [k
W]
v [m/s]
Power Curve PMC WTG 15
Real data 2015
4.827 GWh/yr
3.968 GWh/yr
0,0
500,0
1000,0
1500,0
2000,0
2500,0
1 3 5 7 9 11 13 15 17 19 21
Pow
er (k
W)
Wind speed (m/s)
Guaranteed Electrical Power Curve and Actual Production
Production WTG 34 Power Curve
grid restrictionrecoverable
Proper individual WTG monitoring Well planned maintenance Readily available spare parts Inefficient third party O&M contracts
Performance improvement on individual WTG equipment
23
Vision, competence and passion for details are critical
Continuous production supervision is crucial toreach challenge budget
Effective operating procedures work better thantech advisors’ check lists
Competent, rather than qualified operators andlocal presence key
Health & Safety rules must be monitored again Monitoring systems (0,2% plant value)
fundamental for careful operations Revamping to be always considered Local community engagement protects assets Stay local, stay small to capture upsides of
renewable energy
24
Netplan PV enhancement team
PhD Engineering, Insead & Caltech;Formerly CEO, Enel Green Power, 9REN/ Gamesa Solar (Spain), Solopower(California), Chairman Element Power Solar (Oregon), exec at GE, Bain, KTI; BoD Iren, formerly BoD Pirelli, Ryanair, Ducati, Camco
PhD engineering, MBA Bologna Business School; Formerly Operations manager GSF, senior project manager 9REN, engineering office Aeroporti di Puglia
PhD Engineering, Gov’t Commissioner for cultural institutions, formerly CEO ERG Petroli, ERG Power & Gas, Chairman TotalERG, manager Bain&co, developer AE, engineer ISMES
PhD Law, CMBA BBS/9RENFormerly OdV Element Power, CEO 9REN asset, head of legal affairs 9REN, corporate governance at Enel, junior lawyer EnelGreenPower
Giacomo DachillePaolo Pietrogrande Pier Francesco Pinelli
Angela Pirro Caterina Semola Nicoletta PanebiancoPhD Business Administration Managing Director, Netplan Italia, former CPA for privately owned solar projects
PhD Business Administration, CPA, External payroll, FMC, and tax specialist for 9REN Group, Element Power Italy, Suncity 25
Clean tech, energy and utilities references
Partners
Netplan
26