unbalanced bids part 04-03 – unbalanced bids march 1, 2001

13
Unbalanced Bids Part 04-03 – Unbalanced Bids March 1, 2001

Upload: caitlyn-moudy

Post on 14-Dec-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Unbalanced Bids Part 04-03 – Unbalanced Bids March 1, 2001

Unbalanced Bids

Part 04-03 – Unbalanced BidsMarch 1, 2001

Page 2: Unbalanced Bids Part 04-03 – Unbalanced Bids March 1, 2001

Purpose To acquaint students with the

concept of unbalanced bids and why Contractors submit them, and why Owners allow this practice.

Page 3: Unbalanced Bids Part 04-03 – Unbalanced Bids March 1, 2001

Learning Objectives Students should be able to

compute the advantage, in terms of Net Present Value, of a simple unbalance bid example.

Page 4: Unbalanced Bids Part 04-03 – Unbalanced Bids March 1, 2001

Basic Idea The basic idea is to “over charge”

for work in the front-end of the contract.

While “under charging” a equal amount at the tail-end of the contract.

And investing the “surplus” for as long as you can “get away with it.”

Page 5: Unbalanced Bids Part 04-03 – Unbalanced Bids March 1, 2001

Lets Assume the Following “Engineers Estimate.”

1 2 3 4 5 6 7 8 9 10 11 12

Work 2 10 20 30 30 30 30 20 10 1 1 1

$$'s 2 10 20 30 30 30 30 20 10 1 1 1

Work Units and Corresponding estimated $$ Amounts per contract period.

Page 6: Unbalanced Bids Part 04-03 – Unbalanced Bids March 1, 2001

Let’s Say The Project was Actually Bid and Executed like this.

1 2 3 4 5 6 7 8 9 10 11 12

Work 2 10 20 30 30 30 30 20 10 1 1 1

$$'s 2 10 20 30 30 30 30 20 10 1 1 1

1 2 3 4 5 6 7 8 9 10 11 12

Work 2 10 20 30 1 1 1 30 30 30 20 10

$$'s 20 20 30 40 1 1 1 20 20 20 10 2

Engineers Estimate on Top; Contractors plan on Bottom. The $$ sums are the same.

Page 7: Unbalanced Bids Part 04-03 – Unbalanced Bids March 1, 2001

Look at the NPV at 10%

1 2 3 4 5 6 7 8 9 10 11 12

Work 2 10 20 30 30 30 30 20 10 1 1 1

$$'s 2 10 20 30 30 30 30 20 10 1 1 1

PV@10%122 132 135 126 106 83 59 31 12 3 2 1

1 2 3 4 5 6 7 8 9 10 11 12

Work 2 10 20 30 1 1 1 30 30 30 20 10

$$'s 20 20 30 40 1 1 1 20 20 20 10 2

PV@10%128 118 108 86 51 54 59 64 48 31 12 2

Page 8: Unbalanced Bids Part 04-03 – Unbalanced Bids March 1, 2001

Class DiscussionWhat will the Owner Say?

Is the the NPV the same? At 0%?, at 10%?

What happens if the Owner Decides to “fire” the Contractor?

Can you name any “notorious” local examples?

Do you think that you can repeat this on an Exam?

Page 9: Unbalanced Bids Part 04-03 – Unbalanced Bids March 1, 2001

Another Example: The Engineer’s Estimate calls for

1,000,000 CY of dirt to be moved at $1.00/CY and 10,000 CY of rock to be moved at $5.00/CY for a total of $1,050,000.

1,000,000 $1.00 $1,000,000

10,000 $5.00 $50,000 $1,050,000 <- Total

Page 10: Unbalanced Bids Part 04-03 – Unbalanced Bids March 1, 2001

You Bid You assume that the Estimate is in

Error and you bid $10 for the rock and $.95 for the dirt.

1,000,000 $0.95 $950,000

10,000 $10.00 $100,000 $1,050,000 <- Total

Page 11: Unbalanced Bids Part 04-03 – Unbalanced Bids March 1, 2001

You just made an extra $45,250

The estimate was in error by 5,000 CY of Rock and You made money.

995,000 $0.95 $945,250

15,000 $10.00 $150,000 $1,095,250 <- Total

Page 12: Unbalanced Bids Part 04-03 – Unbalanced Bids March 1, 2001

Class DiscussionWhat will the Owner Say or Do?

Q: How can the owner guard against this? A: 10% renegotiation rule. A: Better estimates? What if a consultant

made the estimate? A: Change unit price categories.

Q: Should the owner even care? A: If the errors are accidental (random), it

will all balance out.

Page 13: Unbalanced Bids Part 04-03 – Unbalanced Bids March 1, 2001

Class Assessment Please take a minute to write 1

sentence on the “muddiest” topic.