ua015.012.do.00015.archival

103
1 THE FLETCHER SCHOOL OF LAW AND DIPLOMACY When “Power Failures” Undermine International Business Negotiations: A Negotiation Analysis of the Dabhol Power Project A MALD Thesis Presented to Jeswald Salacuse By PRIYA GHANDIKOTA April/2002

Upload: arijeet-das

Post on 23-Nov-2015

32 views

Category:

Documents


0 download

DESCRIPTION

enron case study

TRANSCRIPT

  • 1

    THE FLETCHER SCHOOL OF LAW AND DIPLOMACY

    When Power Failures Undermine International Business Negotiations: A

    Negotiation Analysis of the Dabhol Power Project

    A MALD Thesis

    Presented to

    Jeswald Salacuse

    By PRIYA GHANDIKOTA

    April/2002

  • 2

    Abstract: The purpose of this paper is to investigate the institutional factors that lead to the collapse of

    international business deals. To develop a working framework from which to discuss this problem, the Enron-promoted Dabhol Power project in Maharashtra, India will be discussed as a case study. Traditional business strategy fails to internalize the social, cultural, political and ideological dimensions of complex business transactions. A preliminary examination of the Dabhol case reveals that many of the problems that led to the inability and unwillingness of the parties involved to implement a business agreement can be explained by negotiation theory. Negotiation theory accounts for the personality of the players, asymmetrical power relations, the lack of cultural know-how, and other complex issues in the pre-negotiation, negotiation and post-negotiation phases that lend insight into why international business agreements may fail. This paper begins with a translation of the history of the Dabhol project, continues with the application of negotiation theory to analyze the problems that arose and concludes with a model that attempts to correlate factors explained by negotiation theory that collectively produce a successful international business negotiation strategy.

  • 3

    When Power Failures Undermine International Business Negotiations: A Negotiation Analysis of the Dabhol Power

    Project

    TABLE OF CONTENTS

    PART I. INTRODUCTION........................................................................................................................................................ 6

    PART II. THE HISTORY OF THE DABHOL POWER PROJECT ............................................................................ 9 A. INDIAS ENERGY SECTOR.............................................................................................................................................9

    An Energy Sector in Need of Investment........................................................................................................................... 9 The Move Towards Reform...............................................................................................................................................11

    B. THE SIGNED MOU WITH ENRON...............................................................................................................................12 C. EVENTS LEADING UP TO THE SIGNED PPA .........................................................................................................13

    Public Protest......................................................................................................................................................................13 The World Banks Initial Conclusions............................................................................................................................13 The Initial Findings of the CEA .......................................................................................................................................14 The World Bank Report .....................................................................................................................................................16

    C. NEGOTIATION OF THE PPA.........................................................................................................................................19 Sovereign Guarantees........................................................................................................................................................20

    D. CANCELLATION OF THE PPA ....................................................................................................................................20 The Results of the 1995 Maharashtra State Elections..................................................................................................20 The Report of the Cabinet Sub-Committee to Review the Dabhol Power Project...................................................21 Termination of the PPA .....................................................................................................................................................22 Arbitration............................................................................................................................................................................22 A Review Panel is Struck ...................................................................................................................................................24

    D. RE-NEGOTIATION OF THE PPA .................................................................................................................................24 E. NON-PAYMENTS AND ESCALATING HOSTILITIES ..........................................................................................25

    Invoking the Sovereign Guarantee...................................................................................................................................26 The Godbole Review Panel..........................................................................................................................................27 Pre-Termination Notice.....................................................................................................................................................30 Subsequent Rounds of Arbitration .............................................................................................................................31 Enrons Exit Strategy.........................................................................................................................................................32 Final Termination Notice.................................................................................................................................................33 The Singapore Meeting......................................................................................................................................................34 The Downfall of Enron.......................................................................................................................................................35

    PART III. APPLYING NEGOTIATION THEORY TO EXPLAIN THE FAILURE OF THE DABHOL DEAL................................................................................................................................

    A. UNDERSTANDING BATNA AND BATRNA..............................................................................................................38 The Indian Teams BATNA ...............................................................................................................................................38 Enrons BATNA...................................................................................................................................................................40 The Indian Teams BATrNA..............................................................................................................................................40 Enrons BATrNA .................................................................................................................................................................42

    B. TIME DEFICIENCIES .......................................................................................................................................................44 Speed.....................................................................................................................................................................................44 When the Time is `Ripe.....................................................................................................................................................48

    C. RESOURCING THE NEGOTIATIONS.........................................................................................................................48 Institutional Endowments..................................................................................................................................................49

  • 4

    Corruption............................................................................................................................................................................49 Technical Endowments......................................................................................................................................................51 Inflationary and Deflationary Expectations...................................................................................................................52

    D. ASYMMETERICAL POWER RELATIONS................................................................................................................54 Terms of the agreement......................................................................................................................................................54

    E. TRUST AS A STABILIZING FORCE IN NEGOTIATIONS ....................................................................................56 F. INCORPORATING STAKEHOLDERS.........................................................................................................................58

    Local Community................................................................................................................................................................59 The World Bank...................................................................................................................................................................62 The Bureaucracy.................................................................................................................................................................62 Indian Financial Institutions.............................................................................................................................................63 The Non-Resident Indian Community.............................................................................................................................64 When Stakeholder Interests Hold the Negotiation Process Hostage.........................................................................65

    G. MORAL BASED POSITIONING VS. INTEREST-BASED POSITIONING........................................................67 The GOMs Changing Interests .......................................................................................................................................67 Enrons Interests.................................................................................................................................................................68 Surmounting hostilities - Blaming the other Leads to Moral Positioning...........................................................70 When Inflexibility of the Agreement Contributes to Inflexible Positioning ..............................................................73 Personality of the Players.................................................................................................................................................75 The Hand of the White House...........................................................................................................................................79

    H. NEGOTIATING WITH CULTURAL BLINDERS......................................................................................................81 Theory...................................................................................................................................................................................82 Cultural Limitations in the Indian Teams Negotiating Strategy...............................................................................82 Cultural Limitations in Enrons Negotiating Strategy .................................................................................................84

    I. ORGANIZATIONAL CONSTRAINTS AND INSTITUTIONAL MEMORY AS DEBILITATING FACTORS......................................................................................................................................................................................................85

    Organizational Precedents................................................................................................................................................86 Institutional Memory As a Constraint in the Decision-making Process...................................................................86

    J. THE IMPORTANCE OF EFFECTIVE AND BROAD-BASED COMMUNICATION.........................................87 Theory...................................................................................................................................................................................87 The Breakdown of Effective Communication between the Negotiating Parties.......................................................87 The Breakdown of Effective Communication with Stakeholders................................................................................88

    K. SUMMARY..........................................................................................................................................................................90 PART IV - CONCLUSION ......................................................................................................................................................92

    A. VERNONS OBSOLESCING BARGAINING FRAMEWORK...................................................................................................92 B. AN INTEGRATIVE APPROACH TO ANALYZING BUSINESS TRANSACTIONS...................................................................93 C. CONCLUDING REMARKS......................................................................................................................................................96

  • 5

    TABLE OF FIGURES

    FIGURE 1 - REGIONAL POWER CAPACITY.............................................................................10 FIGURE 2 - BREAKDOWN OF RESPONSIBILITIES OF JV PARTNERS (1993) ....................20 FIGURE 3 - CAPITAL COST, ENERGY COST AND SIZE OF "FAST TRACK" PROJECTS IN

    INDIA ....................................................................................................................................22 FIGURE 4 - INDIA'S BATNAS .........................................................................................................38 FIGURE 5 - RAYMOND VERNON'S OBSOLESCING BARGAIN MODEL................................................93 FIGURE 6 - BALANCING CONSTRAINTS TO NEGOTIATE A SUCCESSFUL BUSINESS DEAL ...............96

  • 6

    When Power Failures Undermine International Business Negotiations: A Negotiation Analysis of the Dabhol Power

    Project

    PART I. INTRODUCTION

    "The end crowns all, and that old common arbitrator, time, will one day end- William Shakespeare, Troilus & C, Act IV, Sc.V

    The purpose of this paper is to investigate the institutional factors that lead to the collapse

    of international business deals. To develop a working framework from which to discuss this

    problem, the Dabhol Power project will be discussed as a case study. The Dabhol Power

    Company (DPC) was established as a joint venture between the Enron Corporation, General

    Electric and the Bechtel Corporation. A Power Purchasing Agreement (PPA) was signed

    between the DPC and the state Government of Maharashtra in India to generate a 2,015 MW

    base load power project at Dabhol in the Ratnagiri district, approximately 300 km south of

    Indias commercial and financial center of Mumbai. Divided into two phases, the project

    succeeded a re-negotiation of its terms, two changes in government, and twenty-four lawsuits.

    Nevertheless, the DPC ultimately collapsed, with the future of its assets still uncertain.

    The Dabhol Power project was chosen as a case study because of its significance to the

    development of Indias foreign investment policy and the unprecedented size and scope of the

    project. Indeed, this project is the largest single foreign investment project in Indias history.

    Furthermore, it is a significant case study because the project was first regarded as a boon to an

    ailing energy sector faced with a myriad of demand-driven and supply driven problems. The

    company was created to serve a sector in India that is highly politicized, fraught with corruption

    and a sector that was expected to provide maximum linkages to other sectors of an economy that

    was poised for growth. The state electricity boards have suffered from consistent losses and

  • 7

    approximately a quarter of the power stations in India are over twenty-five years old and the

    inefficient maintenance of these stations has led to the breakdown of equipment and the shutting

    down of plants.1 Power shortages have had serious repercussions for Indias program of

    development since industry and transport account for seventy per cent of Indias power

    consumption.2 Finally, not only was the Dabhol deal expected to heal an ailing energy sector, but

    it was also touted as a symbol of economic reform, as it rode on the coattails of the aggressive

    liberalization reforms pursued by the Government of India (GOI) after 1991.

    From an international business perspective, the Dabhol Power project is an exemplary

    case of how and why international business transactions fail in large part due to a lack of

    strategic negotiation acumen. While the Enron-promoted project in Maharashtra is unique with

    respect to the size and scope of the project, it is not unique with respect to the institutional

    factors that led to its demise. Many of the problems that explain why the agreement was never

    fully implemented are problems that have surfaced in numerous other cases where international

    business deals have been negotiated, both in India and in other countries. For example, the

    problems inherent in the Dabhol deal have manifested themselves in other deals such as the

    Government of Indias failed negotiations with Bechtel Enterprises from 1963-1965 and the

    controversial energy agreement now the subject of dispute between US-based AES and the state

    government of Orissa in India.3

    Traditional business strategy, which is dominated by an applied microeconomic or

    macroeconomic approach that originates at the firm level or at the country level, provides only a

    1 Abhay Mehta, Power Play: A Study of the Enron Project (Abhay Mehta. Power Play: A study of the Enron Project (Hyderbad: Orient Longman Ltd, 1999), p.12. 2 Harvard Business School, Enron Development Corporation: The Dhabol Power Project in Maharashtra, India (A) , Case No. 9-797-086 (Cambridge, Massachusetts: Harvard Business School Publications, 1997), pg. 6 3 Ashok Kapoor provides an excellent analysis of the events leading to the failed mfp signed between the GOI and Bechtel Corporation. See Ashok Kapoor, International Business Negotiations: A study in India (New York: New York University Press, 1970).

  • 8

    limited explanation of the structures and events that lead to the failures of international business

    deals. Specifically, this discipline fails to internalize the social, cultural, political and ideological

    dimensions of complex business transactions. A preliminary examination of the Dabhol case

    reveals that many of the problems that led to the inability and unwillingness of the parties

    involved to implement a business agreement can be explained by negotiation theory. Negotiation

    theory accounts for the personality of the players, asymmetrical power relations, the lack of

    cultural know-how, and other complex issues in the pre-negotiation, negotiation and post-

    negotiation phases that lend insight into why international business agreements may fail.

    This paper begins with the history of the Dabhol project, continues with the application

    of negotiation theory to analyze the problems that arose and concludes with a model that

    attempts to correlate the factors that collectively produce a successful international business

    negotiation strategy. This model attempts to bridge the gap between negotiation analysis and

    traditional business strategy, where the latter is defined by a distributive bargaining framework,

    which features the competitive behavior and interests of the firm and the industry or country as

    key players.

  • 9

    PART II. THE HISTORY OF THE DABHOL POWER PROJECT `Enron came, they saw, and they conquered

    Maharashtra Chief Minister Manohar Joshi, Speech to the Maharashtra State Assembly A. INDIAS ENERGY SECTOR

    The Dabhol Power Company (DPC)4 is a fascinating case study primarily because the

    project was created to serve a sector in India that is highly politicized, fraught with corruption

    and a sector that was expected to provide maximum linkages to other sectors of an economy that

    was poised for growth.

    An Energy Sector in Need of Investment The DPC was first regarded as a boon to an ailing energy sector faced with a myriad of

    demand-driven and supply driven problems. At the time that an investigation was underway to

    study the viability of the project, per capita consumption of power in India was only 190KwH

    compared with 600 KwH for Malaysia, 3,000 KwH for Taiwan, and 10,000 KwH for the United

    States. Indias relative low consumption rate can be explained not by the fact that demand for

    power was low but by the fact that there was an insufficient supply of power generated. In 1991-

    1992, demand for power throughout the country exceeded supply by 22.5 billion KwHs and grew

    to 23.8 billion KwHs the year after.5 Power demand in India today outpaces supply by 11.1 per

    cent during peak periods.6 These shortages have had serious repercussions for Indias program of

    development since industry and transport account for 70% of Indias power consumption.7

    4 In popular press, the Dabhol debacle is also referred to as the Enron debacle; therefore, throughout this paper, references will sometimes interchangeably be made to the Dabhol Power Company and Enron. 5 Harvard Business School, Case (A) , 6.

    6 P.N.V Nair. Power Sector Needs Urgent Reforms, November 26, 2001 (accessed December 5, 2001); available from www.projectsmonitor.com. 7 Harvard Business School, Case (A) , 6.

  • 10

    Figure 1 - REGIONAL POWER CAPACITY

    Region Central Government Capacity

    Total Regional Capacity

    Northern States 9287 MW 23820 mw Western States 5512 MW 24301 MW Southern States 4640 MW 19459 MW Eastern States 2730 MW 12302 MW N. Eastern States 356 mw 1282 MW

    (Source: Harvard Business School, Enron Development Corporation: The Dabhol Power Project in Maharashtra, India (A), Exhibit 2)

    The problem of energy shortfalls in India can be explained not only by the phenomenon

    of demand outpacing supply but also by the inefficient management of existing power plants.

    Specifically, India suffers from one of the highest transmission losses in the world and has one of

    the worlds lowest utilization of installed capacity.8 According to one estimate, by 2007, the

    additional installed generating capacity required will be 85,000 MW accounting for a GDP

    growth rate of six per cent per year and 100,000 MW if the growth rate is eight per cent per year.

    At a relatively low fixed capital charge of US$1 million per MW, this additional capacity would

    require an investment of $85 to $100 billion US.9 Peaked demand is not met primarily because

    power stations in India run on coal and coal is often not delivered on time because of a failure to

    pay or due to the unavailability of transport. The State Electricity Boards (SEBs) themselves lack

    the ability to pay their principal supplier, the National Thermal Power Corporation (NTPC),

    which prevents the NTPC from paying Coal India (CIL) and other suppliers of fuel. In 1987-

    1988, the State Electricity Boards had operated consistently at a loss except for the State of

    Andhra Pradesh and Orissa in 1990-91, Maharashtra in 1986-87 and 1987 88 and Kerala in

    1985-6. The total outstanding debt of all the SEBs to various suppliers equaled Rs18, 500 crore

    8 Mehta,, p. 9. 9Kirit Parikh, The Enron Story and its Lessons, The Journal of International Trade & Economic Development 6, no. 2 (1997): 210.

  • 11

    at the end of October 1998.10 The problem of unprofitable SEBs is compounded by the fact that

    approximately a quarter of the power stations in India are over twenty-five years old and the

    inefficient maintenance of these stations has led to the breakdown of equipment and the shutting

    down of plants.11

    Official sources estimate that SEBs currently experience an average transmission and

    distribution (T &D) loss of 22 per cent. Unofficial reports estimate this figure to be 48 per cent.12

    The primary reason for these losses can be explained by politically driven subsidies offered to

    wealthy farmers and domestic consumers.13 Concessional power amounts to as much as 46 per

    cent in some states.14 According to The Economist, the SEBs have also become job creation

    centers for friends and relatives of politicians.15 As one author states, the Delhi Electricity

    Supply Undertaking is one of the most corrupt and bankrupt organizations in the country.16 In

    addition to politically driven subsidies, T & D losses can also be explained by transmission theft.

    In New Delhi, transmission theft accounts for nearly fifty-four per cent of all T & D losses.17

    The Move Towards Reform

    During the Fifth Plan of the National Planning Commission, electricity was included in

    the minimum needs program.18 In the hopes of addressing the major structural deficiencies

    confronting the energy sector in India, the Electricity Supply Act (ESA) of 1948 was amended in

    1991. The revised Act adopted a cost-plus approach and assured a return of equity of 16 per

    10 Mehta, 12. 11 Ibid. 12Yamini Narayanan. Privatization of the Electric Utility Industry in India: A Case Study (Ph.D diss, University Of Oklahoma, 1998), p. 35. 13 Ibid., p. 21. 14Ibid., p. 35. 15Ibid., p. 36. 16 Mehta, 9. 17 Ibid., 8-9 18Narayanan, 19.

  • 12

    cent on investment in this sector.19 In May and June 1992, the Government of India established a

    team to visit the United States in pursuit of attracting foreign direct investment for Indias energy

    sector. The Houston-based energy company, Enron Corporation, responded favorably to the

    Government of Indias proposed reforms and expressed an interest in setting up a power station

    in India based on the import of liquefied natural gas (LNG).

    B. THE SIGNED MoU WITH ENRON

    Almost immediately after the Indian delegations promotional trip, representatives from

    Enron and General Electric arrived in India to survey sites for a potential project. Three days

    following their survey, on June 20, 1992, they signed a Memorandum of Understanding (MoU)

    with the Maharashtra State Electricity Board (MSEB) to build the Dabhol Power Project. The

    operating entity of the project would be the Dabhol Power Company (DPC), a joint venture

    between the Enron Corporation, General Electric and the Bechtel Corporation. The MoU,

    although not a legal document, stipulated that the company would establish a 2,015 MW base

    load power project at Dabhol in the Ratnagiri district, approximately 300 km south of Indias

    commercial and financial center of Mumbai. DPC would lease the project site from the

    Maharashtra Industrial Development Corporation.20. The project was initially established to

    generate 2,550 megawatts (MW) at a cost of $3.1 billion. Acting upon the recommendations of

    the Foreign Investment Promotion Board, the proposed project was later scaled down to 1,920

    MW, at a capital expenditure priced at $2.65 billion dollars and most importantly, the project

    was split into two phases. Phase I would run on imported distillate oil until LNG supply

    19 Mehta, 24. 20 Siva Y Sankar. Dabhol Power Co to export fruits, flowers; available from www.rediff.com/money/2000oct/06dabhol.htm).

  • 13

    contracts were secured and a LNG re-gassification plant and storage and harbor facilities were

    developed as part of Phase II.21

    C. EVENTS LEADING UP TO THE SIGNED PPA Public Protest

    The statement by Maharashtra Chief Minister Joshi that Enron came, they saw, and they

    conquered,22 while extreme and lined with political pretension, reflected the attitude of many

    opposed to the Enron deal. In light of this fact, it is remarkable that the Dabhol Power project

    steam-rolled ahead, at the pace that it did, in an environment where public and political

    opposition were fierce and where there was a low estimation of the benefits of the project and its

    viability amongst various local stakeholders. On July 7, 1994, Ramdas Nayak, a member of the

    BJP, a Hindu nationalist party, filed a High Court case against the Indian Government and the

    DPC on the grounds that the project was tainted by a lack of transparency and competitive

    bidding. Similarly, local residents and activists launched appeals to the Government of

    Maharashtra (GOM) to halt the project on the shared belief that environmental standards had

    been violated. Between 1992-1993, through the forum of public hearings and written

    correspondence, many local residents expressed the fear that the construction of a mega-power

    project in Dabhol would threaten their economic livelihood.

    The World Banks Initial Conclusions

    After the Memorandum of Agreement (MoU) was signed amidst public protest, the GOM

    requested the World Bank to review the project. On July 8, 1992, the World Bank concluded,

    this large project which is nearly 20 per cent of its (MSEBs) installed capacity is likely to have

    21Harvard Business School, Case (A) , p. 3 22 The GOMs translation of Chief Ministers Statement in the Maharashtra State Assembly; available from http://altindia.net/enron/Home_files/doc/gomSuit/Cmstate.html

  • 14

    an adverse financial impact.23 The World Bank cautioned the Maharashtra State Secretary for

    Energy and Environment that the MoU was one-sided in favor of Enron and encouraged the

    government to verify Enrons experience as an electricity generating company before

    proceeding with the project.24

    The Initial Findings of the CEA

    The amended Electricity Supply Act of 1948 specified that companies submitting

    proposals of projects exceeding a capital expenditure of twenty five crores were obligated to

    submit a scheme to the Central Electricity Authority (CEA) which included revenue details,

    financing agreements, costs, and supply and generation estimates. The CEA was therefore

    approached in early August 1992 by the Indian Secretary of Power to examine the technical and

    economic viability of the tariff, the cost considerations, and the welfare impact of the Dabhol

    project on Maharashtra. Similar to the World Banks analysis, the CEA concluded that the

    Dabhol project was not economically or technically viable. Specifically, the CEA estimated the

    cost of the plant to be Rs.1.81 crore per MW and Rs. 1.91 crore per MW, according to an

    estimation of December 1996 and December 1997 completed costs, and not Rs. 4.49 crore per

    MW as approximated by Enron.25 This significantly lower deduction in costs led the CEA to

    conclude that the DPC tariff structure needed to be significantly reduced to a more realistic

    estimate of total real costs. The CEA further argued that that the MoU did not produce pertinent

    details of the project including the total costs of the project, when the contract would begin, or

    when the electricity would be made available. There was a minimum level of cooperation

    exercised between Enron and the CEA as Enron insisted on providing lump sum estimates of

    23 Mehta, 28. 24 Human Rights Watch, The Enron Corporation: Corporate Complicity in Human Rights Violations, 1999 (accessed December 5, 2001); available from http://www.hrw.org/reports/19999/enron/enron2-1.htm. 25 Mehta, 52.

  • 15

    its costs. On November 10, 1993 in a letter addressed to respond to the CEAs request for a

    segmented breakdown of project costs, DPC officials replied, It is important to notethat

    capital costs are irrelevant to CEA26. DPC further claimed, (y)our request for more detailed

    project costs of equipment/system/works other than those provided in the capital cost summary

    cannot be supported and is not deemed necessary.27

    Concerns Raised by Enrons Legal Team

    As the CEA continued to express its reservations about the project and as the agency

    began to re-consider the total foreign exchange outgo upon request by the Indian High Powered

    Board, Enrons London-based legal team at Linklaters and Paines submitted a report to the

    Government of India outlining what it deemed to be legal and regulatory impediments to foreign

    investment in India. The report, entitled, Problems Concerning the Application of the Indian

    Electricity Acts, was submitted on September 4, 1992. One of the main concerns of the report

    was that the tariff regulations raised by the Government of India were found to be incompatible

    with the financial structure of a power station project in light of the assumed load factors, the

    admissibility of foreign exchange variations, the permitted return on equity, and the five year

    term of the tariff as stipulated in the pricing provisions of the PPA.28 The legal team raised the

    additional point that the indiscrete power afforded to the MSEB and the CEA to regulate DPC

    activities constituted a conflict of interest, as the CEA was the administrative agency selected to

    exercise juridical functions over any disputes arising between the DPC and the MSEB. In

    addition, Enron expressed concern about the remedies available for breach of a statutory duty.29

    Finally, the Enron legal team raised objection to the fact that under the Electricity Acts, the DPC

    26 Mehta, 61. 27 Ibid. 28 Ibid., 32. 29 Ibid.

  • 16

    would be obligated to furnish to the CEAaccounts, statistics, returns of other information

    relating to the generation, supply and use of electricity, adding to the DPCs existing

    obligations under the Companies Act.30

    The World Bank Report

    On March 12, 1993 the Finance Ministry formally approached the World Bank to finance

    the project. When submitting his report on April 30, 1993, World Bank India Country Director,

    Heinz Vergin, wrote to M.S. Ahluwalia, Secretary to the Department of Economic Affairs in the

    Indian Ministry of Finance, Our analysis based on the parameters provided to us indicated that

    the LNG-based project as presently formulated is not economically viable, and thus could not be

    financed by the Bank.31 The World Bank submitted its full report on April 30, 1993 to the

    Finance Ministry, which then forwarded the report to the Secretary of Power. In the report, the

    World Bank expressed concerns about the fact that a LNG plant was being promoted instead of a

    combined cycle production plant with coal, since LNG generation at a variable cost of about 150

    k/WH is much higher than coal-based production of 30 k/WH.32 Coal production would also

    allow the electricity boards to achieve significant cost advantages by relying on domestic

    equipment and domestic suppliers, thereby decreasing foreign exchange outgo.33

    The World Bank further argued that the willingness of industrial consumers to pay for

    electricity had been estimated at Rs. 2.2 kWH in the western region of Maharashtra, and 2.4

    kWH in Bombay, which were amounts substantially lower than the Rs. 4.6 kWH stipulated in the

    DPC proposal. According to the Bank, consumers had expressed a willingness to pay higher

    30 Ibid., 32-33. 31 Letter of April 30, 1993 signed by Heinz Vergin, India Country Director at the World Bank, addressed to Secretary of the Department of Economic Affairs, Indian Ministry of Finance; available from http://www.altindia.net/enron/Home_files/Wbnote.htm. 32 The World Bank, India: Dabhol Power Project, April 30, 1993; available from http://www.altindia.net/enron/Home_files/Wbnote.htm, line item 5. 33 Mehta, 40.

  • 17

    tariffs only for guaranteed and/or additional supply during peak periods.34 The World Bank

    further critiqued the viability of the project on the grounds that the implementation of the

    project would place a significant long-term claim on Indias foreign exchange resources with

    the capacity payments (starting) at about US $175 million in 1996 and escalating at 5% per

    annum, reaching $US 400 million in 2015.35

    Responding to allegations that the MSEB overestimated growth of demand for energy,

    the MSEB maintained that there existed pending applications from certain industries for

    additional supply amounting to 4,100 MW, thereby increasing the peak load by 2100 MW by

    1997.36 Addressing this point, the World Bank argued that there was no substantive evidence

    determining that there were pending applications and even if the peak load was expected to

    increase, the LNG-based power plant was not the least cost option to meet surplus demand.37

    The World Bank concluded its report by advocating that investment needed to be targeted

    towards alternative energy projects (e.g. coal production).38 Enron management did not perceive

    the report to be entirely damning or immovable. In a letter addressed to the head of the MSEB,

    Joseph Sutton, Vice-chairman and head of the Enron Development Corporations Asia

    Operations, confidently wrote, I recently met with the World Bank and have been following the

    articles in the India papers. I feel that the World Bank opinion can be changed. We will engage a

    PR firm during the next trip and hopefully manage the media from here on.We need now to

    put the PPA behind us.39

    34 The World Bank, India: Dabhol Power Project, line item 13. 35 The World Bank, India: Dabhol Power Project, line item 7. 36 Mehta, 40-1. 37 Ibid., 41. 38 The World Bank, India: Dabhol Power Project, line item 11. 39 Mehta, 199.

  • 18

    Taking the lead on this confident note and in the first of many strategic miscalculations to

    follow, the Chief Minister of Maharashtra Sharad Pawar decided to overlook the

    recommendations of the World Bank and the CEA and in an August 1993 meeting with the High

    Powered Board, announced that the issues raised by the CEA were all issues that could be

    examined in a final review and were minor issues to be clarified.40 The project was

    subsequently approved by the various departments of the state government, the State Cabinet

    Ministry of Power and Finance, the Central Government and the Foreign Investment Promotion

    Board which was comprised of a high level committee of secretaries of the Central

    Government.41

    On November 26, 1993, the CEA in principle granted provisional clearance. This

    clearance, however, was not a final determination and was made with significant reservations. A

    study of the correspondence between the GOM and the CEA, and Enron executives and the

    GOM during this period suggest that the clearance was executed under pressure by Enron and

    the GOM so that Enron could finalize its financing for the project. In a letter to Chief Minister

    Pawar, Rebecca Mark wrote:

    The remaining concern seems to reside with Mr. Beg, Member Planning for Thermal Projects. He continues to hold up the project approval based upon the question of demand for power in Maharashtra .we have a project under the governments fast track program, approved by FIPB, but the CEA refuses to grant a clearance.It is critical that we get the Power Purchase Agreement approved and signed now and that we start Phase I financing immediately. Because of GOM delays in approval and the associated negative press of the last few weeks, the project is in danger. We are working on financing arrangements prior to project approval but the banks in India and externally are losing their enthusiasm based on lack of progress.We need to make immediate progress.42

    The CEA clearance was conditional on a readjustment of the price of electricity, the policy of

    importing liquefied natural gas and on DPCs ability to obtain other government permits from

    40 Ibid., 53. 41 Ibid., 142.

  • 19

    the Ministry of Environment and Forests and the Port Trust for construction of their harbor and

    port facilities.43

    C. NEGOTIATION OF THE PPA

    On December 8, 1993, a week after the CEAs preliminary clearance was issued, the

    Purchasing Power Agreement (PPA) of the first phase of the project was signed. DPC would

    build, own and operate a plant of approximately 2,000-2,400 MW capacity, which would be run

    on liquefied natural gas (LNG). The LNG plant would maintain an average plant load factor of

    ninety per cent.44 The Dabhol project would cost Rs. 4.36 crores/megawatt (MW) and the DPC

    would sell to the MSEB at a rate of Rs. 2.65/kWh in 1997 and the rate would increase after that

    date. The MSEB and GOM were responsible for building the transmission lines from the power

    station to its power grid. By the time DPC was ready for commercial production, the MSEB

    would still be obligated to make the capacity payments irrespective of whether the State followed

    through with its infrastructure commitments. The MSEB was required to purchase power from

    the DPC under a two-part tariff. The first part of the tariff was determined by established base

    load and peaking capacities. The second part of the tariff was determined by the actual output of

    power. The PPA further stipulated that after twenty years from the commencement of

    commercial production, the MSEB would have the option to extend the contract for five or ten

    years.45

    Loan commitments amounted to $643 million and equity contributions amounted to $279

    million for Phase I of the project. The major foreign lenders included the Bank of America, the

    42 Ibid., 204.

    43 Human Rights Watch, The Enron Corporation. 44 Average plant load factor is an indicator of operational efficiency as it measures the actual energy produced by the power plant as a percentage of the maximum capacity of the plant. Break down of Average Plant Load Factor (PLF): 92 per cent during the eight peak non-monsoon months and 86 per cent during the off-peak months.

  • 20

    Overseas Private Investment Corporation, the Export-Import Bank of the United States (EXIM

    Bank) and various Eurobank guarantors. The Indian creditors included the Industrial

    Development Bank of India (IDBI), the State Bank of India, the ICIC, the Industrial Finance

    Corporation of India and Canara Bank, with the IDBI assuming maximum exposure of risk.

    Figure 2 - BREAKDOWN OF RESPONSIBILITIES OF JV PARTNERS (1993)

    (Source: HBS Case A, Exhibit 1) Sovereign Guarantees

    On February 10, 1994 the State of Maharashtra issued a sovereign guarantee, assuming

    liability for all of MSEBs dues to the DPC under the PPA. On June 24, 1994, the State Support

    Agreement was signed between the GOM and the DPC. On September 16, 1994, the Union

    Ministry of Finance, on behalf of the Government of India, signed a counter guarantee.

    D. CANCELLATION OF THE PPA The Results of the 1995 Maharashtra State Elections

    In an interesting sequence of events, the February 1995 State elections in Maharashtra

    brought the project to an abrupt halt. The Hindu nationalist party, the Bharatiya Janata Party

    (BJP), won the Maharashtra elections to form a coalition government with the more conservative

    and fundamentalist religious party, the Shiv Sena (SS). The BJP-SS alliance officially took over

    the political reigns of power in April 1995. The new nationalist, swadeshi-oriented46

    government produced a different trajectory in the states vision of development and foreign

    45 Harvard Business School, Enron Development Corporation: The Dabhol Power Project in Maharashtra, India (B) Case No. 9-797-085 (Cambridge, Massachusetts, Harvard Business School, 1997), page 11.

    Company Enron Power Corporation

    Bechtel Enterprises Incorporated

    General Electric Company

    Equity $223 million $28 million $28 million Responsibilities Construction management,

    operations and maintenance, fuel management

    Construction and Contractor

    Construction

  • 21

    investment. Bal Thackeray, leader of the Shiv Sena party, often preached on the evils of foreign

    investment and rendered popular the slogan, Justice to All, Appeasement to None. With

    respect to the Dabhol project, the two most immediate mandates of this government were to

    replace the chairman of the MSEB and to establish a cabinet sub-committee to review the

    project. This committee was established on May 3, 1995 and was headed by Deputy Chief

    Minister, Gopinath Munde.

    The Report of the Cabinet Sub-Committee to Review the Dabhol Power Project

    The Report of the Maharashtra Cabinet Sub-Committee to Review the Dabhol Power

    Project recommended the termination of the project based on the conclusion that the cost of the

    project was inflated at least by twenty-five per cent47 and that there was a lack of competitive

    bidding and transparency that resulted in a one-sided agreement which favored Enron and its

    partners. The committees report specifically cited regulations that had been relaxed to expedite

    the project. The Cabinet Sub-Committee, also known as the Munde Committee, further argued

    that a proper environmental impact assessment of the project was not executed. Finally, the

    Committee determined that the Dabhol project was more expensive than other fast-track

    projects (see Figure 3 below).

    46 Swadeshi translates to home rule and was one of the nationalist slogans employed during Indias Independence movement. 47 This estimate is based on a study of the US based Advanced Light Water Rector Program (ALWR) which cites other projects such as the Jerapadu and Godavari gas-based projects in the range of 3.52-3.60 crore per MW.

  • 22

    Figure 3 - CAPITAL COST, ENERGY COST AND SIZE OF "FAST TRACK" PROJECTS IN INDIA48

    Project Size (MW) Capital Cost (Rs.Crore per MW)

    Cost of Energy (Rs. Per KW)

    NTPC-Gandhar 648 3.53 -------- GVK-Jegurupadu 216 3.52 2.21 Spectrum-Godavari 208 3.60 1.87 Torrent-Gandhar 654 4.27 2.17 Enron-Dabhol 695 4.49 2.40 Congentrix-Mangalore* 1,000 5.08 2.59 AES-Ib Valley* 420 4.82 2.39 Ashok Leyland-Vizag* 1,000 5.81 ---- CMS-Neyveli 250 4.50 3.10 NTPC-Kayamkulam* ----- 3.20 2.61 NTPC-Faridabad ----- 3.00 2.12

    (Source: HBS Case Study-B; referencing the Ministry of Power, Dabhol Power Company) *Coal Powered Projects

    Termination of the PPA

    The report of the Munde Committee symbolized the first of many events that effectively

    rendered the agreement void. Based on the Committees findings, on July 8, 1995, the new Chief

    Minster, Manohar Joshi, announced to the Maharashtra State Assembly that the Government of

    Maharashtra had decided to cancel the second phase of the project and halt directives associated

    with the first phase of the project. Chief Minister Joshi in his admonishment of the project made

    what is now an often-cited declaration (from) the speed with which this process was completed,

    one can say that `Enron came, they saw, and they conquered.49 Joshi continued to state that the

    decision to cancel the agreement was, not against the United States; but against the Dabhol

    project. The deal is against the interest of Maharashtra. Accepting this deal would indicate an

    absolute lack of self respect and would amount to betraying the trust of the people50

    Arbitration The PPA included an arbitration clause that committed the MSEB and DPC to dispute

    resolution should the two parties not be able to resolve the conflict through non-legal means.

    48 These projects were under negotiation at the time that the case study was written (December 1996). 49 The GOMs translation of Chief Ministers Statement in the Maharashtra State Assembly

  • 23

    Arbitration would be conducted in London and would be presided over by a panel of

    independent experts in accordance with the United Nations Commission on International Trade

    Law (UNCITRAL) rules of arbitration and the 1958 New York Convention. The DPC chose to

    invoke this clause by initiating arbitration in London against the MSEB and the GOM to claim

    damages well over $300 million (Rs. 1,000 crore).51 Throughout the arbitration proceedings,

    however, Enron repeatedly and publicly expressed its willingness to renegotiate the terms of the

    agreement.52

    In response to the DPC initiating arbitration, on August 3, 1995, the Government of

    Maharashtra filed suit against the DPC in the Bombay High Court seeking cancellation of the

    PPA on grounds of fraud, corruption and a lack of competitive bidding. The Government of

    Maharashtra argued in court that the PPA was null and void on the basis that it violated several

    statutory provisions, including sections 18, 29, 30, and 43A of the Electricity Supply Act, and

    that the PPA suffered from the vice of misrepresentation by Enron and was conceived in

    fraud.53 On August 19, 1994, the Bombay High Court ruled that an open invitation for

    competitive tenders should have occurred to ensure the transparency of the deal.54

    Enrons commitment to the project was demonstrated by its efforts to resuscitate

    negotiations by engaging in significant diplomatic maneuvering after the cancellation of the

    project. Joseph Sutton, Scott Bayman from General Electric, Ashok Mehta , Vice-President of

    DPC, and Sanjay Bhatnagar from the Enron Development Corporation made a trip to New Delhi

    during the second week of April 1995 to meet with the Union Minister for Power, N.K.P Salve,

    50 Harvard Business School, Case B 4. 51 Jeswald W. Salacuse, Renegotiating International Project Agreements, Fordham International Law Journal 24, no. 4. (April 2001): 1352. 52 Chris Ayres. Enron to pull out of Indian project, The Times (London), November 6, 2001 (accessed December, 2001); available from Lexis -Nexis Academic Universe. 53 Mehta, 147. 54 Ibid., 141.

  • 24

    Finance Minister, Manmohan Singh, and the General Secretary of the BJP, Pramod Mahajan.55.

    The DPC team received the assurances it needed from the Center to forge ahead. Specifically,

    Salve was forthright in his declaration that the Center was committed to continuing the project

    and that the State of Maharashtra should honor the pact because a renouncement of its

    contractual obligations would have adverse ramifications for the entire nation.56 On November 7,

    1995, Rebecca Mark met with Bal Thackeray, founder and leader of the Shiv Sena party in

    Maharashtra. Thackeray was an important political figure with whom to reconcile differences, as

    he remains an influential nationalist, with little sympathy for foreign investors and he has

    immense political connections throughout Maharashtra. Despite having missed a scheduled

    meeting with Manohar Joshi, Mark was later able to secure a commitment from the Chief

    Minster that the GOM would explore the possibility of recommencing negotiations.

    A Review Panel is Struck

    On November 8, 1995, the GOM commissioned a Review Panel, comprising of

    government officials, academics and industry experts.57 Based on its negotiations with the Enron

    team and principal critics of the project, the panel submitted a proposal to the GOM on how to

    restructure the Dabhol deal with recommendations to restructure the electricity tariff, capital

    costs, terms of payment and delineation of environmental responsibilities.58

    D. RE-NEGOTIATION OF THE PPA

    The renegotiated agreement transformed the Dabhol deal into the single largest foreign

    direct investment project in Indias history. The recommendations put forward by the Review

    55 Mehta, 143-144. 56 Ibid., 144. 57 Salacuse, Renegotiating International Project Agreements, 1353. 58 Ibid., 1353.

  • 25

    Panel lay the foundation for the amendments made to the PPA. Specifically, the total capital cost

    of the plant was reduced by $330 million to US$2.51 billion.59 The plant was reconfigured to be

    a multi-fuel generating plant, which would run on naphtha during Phase I. This adjustment had

    the benefit of reducing Indias dependence on imported fuel and lowering the capital costs of the

    project. Additional capacity was negotiated from 695 MW in Phase I to 740 MW and in Phase II,

    from 2,015 MW to 2,184 MW. The committee also fixed a price of 5.9375 cents/kWhr for Phase

    I and 5.906 cents/kWhr for both phases.60 The load factor remained set at eight-six per cent.61

    Responding to criticism about the environmental impact of the project on local horticulture and

    fishing, the renegotiating committee arrived at an agreement whereby there would be regular

    monitoring of marine life and whereby the DPC would plant one hundred and fifty hectares of

    mango and cashew trees in the area.62 One of the most important features of the newly structured

    deal was the allocation of thirty per cent equity in the project to the MSEB, and a reallocation of

    Enrons equity holding from eighty to fifty per cent.

    On May 27, 1996, the Union Cabinet issued an extended counter guarantee. In August

    1996, each party withdrew their respective suits in their courts to sign the renegotiated PPA. By

    May 1999, final construction of the project had completed and the project received financing for

    its second phase. By March 1999, Phase I was well underway while Phase II was expected to

    commence in 2001.

    E. NON-PAYMENTS AND ESCALATING HOSTILITIES

    In October 1999, a new government came into power in the State of Maharashtra. This

    government, led by the Democratic Front (DF), was fragile and politically dwarfed by its many

    59 Parikh, 216. 60 This amount translates to Rs. 1.90k/Whr for Phase I and Rs.1.89/kWhr for both phases. See Parikh, 217. 61 Ibid., 217.

  • 26

    alliances and coalitions. Inheriting an incredible deficit of 9,848 crores from Chief Minister

    Joshis government, the newly elected Democratic Front government in Maharashtra, led by

    Vilasrao Deshmukh, discovered that it could no longer sustain payments to the DPC. In February

    2001, Chief Minister Deshmukh remarked (l)et us face it. We cannot afford the power given to

    us by the DPC. The MSEB is in no position to pay the monthly power bills Dabhol sends to us.

    We have asked the Centre to buy all the power generated by Enron, from both phases of the

    project and distribute it through the NTPC (the National Thermal Power Corporation) grid. If we

    want power for the state, we will buy it from NTPC.63 Deshmukh also declared, we have given

    all the necessary powers to the MSEB Chairman to take any action, including disconnection of

    power supply lines, against defaulters. We need full police force for this. We are prepared to do

    this.64 Even the Indian Finance minister admitted that the cost of power supplied by the DPC

    was too high and the government would have to see if the state can use all the power generated

    and that if the excess power can be wheeled out to needy states.65

    Invoking the Sovereign Guarantee

    During the first week of February 2001, under pressure from its lenders, the DPC

    responded to the MSEBs refusal to pay its dues by invoking the GOIs counter-guarantee.66 The

    GOI argued that it would not pay the estimated amount of Rs. 1.02 crore (15 million pounds) on

    the grounds that Enron engaged in certain technical violations.67 Specifically, the GOI

    62 Ibid., 220. 63 Raghunatha, TN. Empowered to overpower problems, The Pioneer, Feb. 18, 2001 (accessed December 5, 2001); available from www.dailypioneer.com. 64 Siva Y. Sankar. Maharashtra move may help solve Enron tangle, February 7, 2001 (accessed December 5, 2001); available from www.rediff.com/money/2001/feb/07enron.htm. 65 Binoy Sharma. Centre to send sole representative, April 25, 2001 (accessed December 5, 2001), available from www.dailypioneer.com. 66 Sujata Anandan, Enron willing to amend Power Purchase Agreement, The Hindustan Times, February 9, 2001 (accessed December 5, 2001); available from www.hindustantimes.com. 67 Khozem Merchant, Enron Dispute heading for Court, April 9, 2001 (accessed December 5, 2001; available from http://globalarchive.ft.com.

  • 27

    concurred with the MSEBs allegation that the DPC had fallen short in its guaranteed supply of

    power and therefore was subject to the RS. 401 crore non-performance penalty as stipulated by

    the PPA.68 On September 11, 2001, the DPC invoked a letter of credit (LoC) from the Canara

    Bank accusing MSEB for non-payment of dues. The MSEB countered this action by restraining

    the DPC from encashing the LoC by obtaining an injunction from the Mumbai High Court,

    which was later upheld by the Supreme Court on September 21.69 That same week, the DPC

    invoked its second federal counter-guarantee.70

    The Godbole Review Panel

    To respond to tensions mounting between the DPC and the MSEB, a review panel was

    established by the GOM. The panel was headed by Dr. Madhav Godbole, former finance

    secretary, and was comprised of energy experts.71 In April 2001, the Godbole Panel submitted its

    review report of the Dabhol project. In this report, the panel recommended de-linking the LNG

    terminal from the project, restructuring the loan repayment clause in the PPA, and removing the

    dollar-rupee denomination of payments. Probably one of the most significant statements made by

    the Godbole Review Panel Report was its resignation of the fact that though development of

    DPC has been fraught with infirmities, its existence cannot be wished away and it now stands as

    a near completed project on Indian soil.72 The Panel, therefore, arrived at the conclusion that a

    restructuring of the Dabhol project was needed.

    68 Centres firm no to DPC, The Pioneer, August 18, 2001 (accessed December 5, 2001); available from www.dailypioneer.com. 69 SC decides to continue interim order, The Statesman (India), November 3, 2001 (accessed December 5, 2001); available from Lexis -Nexis Academic Universe. 70 Khozem Merchant, India to hold inquiry into Enron Affair. 71 Energy experts on the committee included N. N. Lele and R N Pachouri, long associated with Tata Electricity and Kirit Parikh, of the Indira Gandhi Institute of Development Research. 72 Godbole Panel Stresses on negotiation with DPC, The Pioneer, April 13 2001 (accessed December 5, 2001); available from www.dailypioneer.com

  • 28

    The Godbole Re-Negotiating Committee

    Chief Minister Deshmukh ultimately resigned himself the fact we can not bring down

    the cost of power (sold by the DPC) unless the PPA is re-opened. The issues like the rupee-dollar

    parity which has contributed to the hike in the power rates will have to be considered while

    undertaking re-negotiations.73 At the end of April 2001, his government, acting on the

    recommendation of the Mumbai High Court to arrive at an amicable settlement, commissioned

    the Godbole panel to form a committee to renegotiate terms of the PPA with Enron. Pressured

    from the leftist groups in Deshmukhs coalition government, the committee was commissioned

    to ultimately bring down the cost of power by restructuring the tariff rate, to explore the options

    of attracting third party purchasers of the energy, and to ultimately soften what had become to be

    perceived as a hardliner stance developed by Enron.

    Recognizing that other state electricity boards could share in absorbing excess capacity

    generated by the Dabhol plant during off-peak periods, the Godbole committee immediately

    began to organize simultaneous meetings with the SEBs. Representatives of the state electricity

    boards from Madhya Pradesh, Karnataka, Delhi and Punjab met the Madhav Godbole Committee

    on July 26, 2001 to negotiate buying power from the DPC but their expectation of price and

    supply was too low to ease the financial pressure of the Maharashtra government. With the

    exception of the SEBs of Madhya Pradesh and Punjab, which were willing to pick up

    approximately 200 MW as base load power, the other states were seeking a power arrangement

    that would meet seasonal shortfalls of power.74

    The efforts of the Godbole committee to arrive at a renegotiated settlement was severely

    hampered by the various legal acrobating that was simultaneously taking place in London and in

    73 Maharashtra softens stand ahead of London meet, The Pioneer, April 26, 2001.

  • 29

    Mumbai by the GOM, DPC and Indian creditors. Furthermore, three of the committee members

    resigned from the committee in an act of protest directed towards the leadership of Dr. Madhav

    Godbole and the political interference exercised by the Center. One of the members of the

    committee who resigned, R.K. Pachauri, argued that Dr. Godboles suggestion of a judicial

    enquiry into the DPCs activities, would have the unintended consequences of driving the Enron

    team farther away from the negotiating table. In one interview, he stated (h)ow long do such

    judicial enquiries in India normally take and how many have achieved anything tangible? Can

    the government of Maharashtra renegotiate a deal with Enron if a judicial enquiry is in progress,

    and would the public accept any such deal till the enquiry is over? And till it is over, the

    Government of Maharashtra would continue to run up huge bills even as the State is unable to

    absorb the power generated by Dabhol.75

    On May 3, 2001, the efforts of the Godbole committee became further impeded when the

    Enron team backed out of a meeting scheduled for May 5 with officials of the state government,

    the MSEB and members of the Godbole committee to re-chart the renegotiation process.76 Even

    when the energy company initially agreed to meet, it cautioned, the published terms of

    reference of the Godbole report do not represent an acceptable basis for further

    discussionsThis meeting should in no manner be construed as an open offer from DPC to

    renegotiate the terms of the contract.77 The Dabhol team made clear that any specific proposals

    brought forward for renegotiation should be premised on the principle of lifting the entire base

    74 Julie Earle. Enron wants out of Indian Power Project in The Financial Times (London), July 27, 2001 (accessed December 5, 2001); available from Lexis -Nexis Academic Universe. 75 R K Pachauri rejects Godboles suggestion to institute `Judicial Enquiry, available from http://www.teriin.org/news/may012.htm 76 Agenda for fresh talks with Enron chalked out, Business Line, May 5, 2001 (accessed March 31, 2002); available http://www.blonnet.com/businessline/2001/05/06/stories/14065607. 77 DPC agrees to meet govt panel as a `courtesy: Godbole terms of reference not acceptable, rediff.com, May 4, 2001 (accessed December 5, 2001); available from http://www.rediff.com/money/2001/may/04enron.htm

  • 30

    load power produced at the plant.78 They further reasoned that no exercise of re-negotiation

    would be fruitful for them without a basic assurance of payment for the second phase of the

    project, which was due to go online on June 7, 2001. Since the MSEB could not provide for

    these assurances, the Enron team decided to issue its pre-termination notice.79

    Before the pre-termination notice was actually issued, several attempts were made by the

    Center to engage officials from the DPC, the MSEB and the GOM in a dialogue to resolve their

    differences. On May 11, 2001, officials of Enron India and the Godbole committee met to

    discuss the future of the Dabhol project with no headway, as the MSEB continued to reiterate its

    stance that the DPC should adjust its dues owed by the MSEB for not achieving peak supply

    levels.80

    Pre-Termination Notice On April 26, in a decision of six to one, the Board of Directors of DPC had authorized

    Neil McGregor, Managing Director, to issue a notice of intent to terminate the PPA at a future

    date to be determined by the DPC management. The MSEB was not allowed to vote on the issue

    because of its status as an interested party.81 On May 19, the DPC issued its pre-termination

    notice. The pre-termination notice attributed the decision to terminate the project to the failure of

    the MSEB to pay its dues amounting to two months of electricity payments, and to the MSEBs

    unwillingness to increase the size of the letter of credit and provide escrow cover as provided for

    in the PPA. According to clause 17.8 of the termination procedure outlined in the PPA,

    following the giving of a preliminary termination notice, the parties shall consult for a period of six months (or such longer period as they may agree) as to what step shall be taken with a view to mitigating the consequences of the relevant event

    78 Dabhol issues termination notice still open to `solutions minus Godbole report, Business Line, May 20, 2001 (accessed March 31, 2002); available from http://www.blonnet.com/businessline/2001/05/20/stories/14205601.htm 79 Dabhol issues termination notice. 80 Talks begin on Dabhol Issue, Business Line, May 12, 2001, (accessed March 31, 2001); available from http://www.blonnet.com/businessline/2001/05/12/stories/14125602.htm 81 DPC board authorises MD to issue PPA termination notice, Business Line, April 27, 2001, (accessed March 31, 2001); available from http://www.blonnet.com/businessline/2001/04/27/stories/142756dh.htm

  • 31

    having regard to all the circumstances..82

    The DPCs pre-termination notice, therefore, would expire on Nov.19, 2001, after which the

    DPC board would have to approach its lenders for approval to issue a final termination notice.

    As the MSEB continued to rescind on its contractual payments and its unpaid bills escalated to

    approximately $185 million, DPC officials decided to shut down the first phase of the project

    (740 MW) in May 2001.

    At the end of July, Enron CEO, Kenneth Lay, formally announced Enrons intention to

    sell its equity stake, signifying a formal departure from the project. Lay reported We have made

    it pretty clear to the government leadership we are now at a point where we would like to be

    taken out and we think most of our partners do.83 Wade Cline further explained we are not in

    the business of litigation but of selling energy worldwide. November 19 is our exit path and no

    way are we going to take a merchant risk in the power purchase agreement. I surely have a

    distressed asset but not a distressed PPA.84

    Subsequent Rounds of Arbitration

    The DPC resorted to arbitration against the State Government, again on the basis of a

    breach of contract. The company had accused the Government of not honoring its guarantees and

    supplemental support guarantees by refusing to pay the amount due for MSEBs December and

    January bills. The GOM responded to the arbitration proceedings again by filing its own suit in

    the Bombay High Court alleging that the DPC had misrepresented terms of the agreement by

    inflating the operating characteristics and scope of the project.85 The GOM further supported the

    82 Ibid. 83 Earle, Enron wants out of Indian Power Project. 84 Enrons exit countdown begins from November 19, The Pioneer, August 13, 2001 (accessed December 5, 2001); available from www.dailypioneer.com 85 MSEB forced to rescind PPA?, The Pioneer, August 6, 2001 (accessed December 5, 2001); available from www.dailypioneer.com.

  • 32

    MSEBs argument that the DPC was required to adjust payments due by the MSEB according to

    a Rs.401 crore penalty for performance default, as stipulated in the PPA. Furthermore, on

    September 19, 2001, Indian authorities announced that they were to launch a judicial

    investigation into the origins and legality of the $2.8 billion company. Fearful that this initiative

    was an attempt to stall arbitration proceedings in London, by declaring DPC activities illegal, the

    commercial court in London passed an ex parte order in October 2001 against the State

    government restraining it from taking any legal action against international arbitration initiated

    by DPC.86

    Enrons Exit Strategy

    Wade Cline, of the DPC, articulated the desire that apart from deflating the sale price of

    its assets from $3 billion to $1 billion, at the end of the day, they wanted to complete the project

    before leaving Dabhol. Though we are looking at exit routes, DPC is ready to get the original

    contractors and ensure completion of the project as the original designs and drawings of the plant

    are not with the company, but with them.87

    Once it was clear that the GOI would not purchase Enrons equity stake in the company,

    on January 30 2002, the IDBI invited Expressions of Interest (EOI) for acquisition of eight-

    five percent stake in DPC from domestic and international companies with a minimum net worth

    of $200 million or its equivalent in Indian currency or from a consortium with a net worth of

    $400 million having requisite experience in managing and operating power and LNG plants.88

    Three bidders, Tata Power Company, BSES Ltd. and the Gas Authority of India submitted their

    EOIs. For practical reasons, Enron preferred selling its assets to a local Indian buyer. Wade Cline

    86 India: Arbitrators meet in Singapore on Dabhol, Business Line, November 23, 2001 (accessed December 5, 2001); available from Lexis -Nexis Academic Universe. 87 Enrons exit countdown begins from November 19.

  • 33

    argued that if a local buyer bought the project, the rupee-dollar parity, that became an issue of

    contention in negotiations between the GOM and the DPC, would disappear if an Indian

    company bought the project. Cline further maintained that the project then also could be run on

    a 30 per cent plant load factorbelieve me no foreign guys are going to do that.89

    Final Termination Notice

    On November 6, 2001 Enron officially announced that it would serve its final termination

    notice to close the power project after November 19, when a six-month deadline for resolving the

    payment dispute would end.90 Enron served a notice to transfer the 2,184MW asset to MSEB and

    was willing to demand compensation based on independent valuation.91 Domestic lenders,

    including the State Bank of India, ICIC Ltd., the Industrial Development Bank of India and IFCI

    Ltd., filed a lawsuit in the Mumbai High Court. The creditors demanded the immediate re-

    commencement of the plant to protect their investments.92 On November 9, 2001, the Mumbai

    High Court ruled in favor of the Indian creditors and issued and issued a stay order against the

    DPCs final notice of termination. This action prevented the DPC from issuing its final

    termination notice until a hearing was called, which would not take place until December 3,

    2001. The Court further ruled that the fourteen-day period beginning November 19, during

    which the DPC could file the final termination notice as per the PPA, would not expire.93

    88 Expression of Interest Invited for DPC Sale, IndiaInfo.com, January 30, 2002 (accessed March 31, 2002); available from http://finance.indiainfo.com/news/2002/01/30/30enron.html 89 Enrons exit countdown begins from November 19. 90 Enron India Units lenders issue court challenge to prevent project pullout, AFX EUROPE, November 8, 2001 (accessed December 5, 2001); available from http://globalarchive.ft.com 91 Sanjeev Srivastava, Enron set to leave India, BBC News.com, November 6, 2001 (accessed December 5, 2001); available from http://news.bbc.co/uk/hi/english/business/newsid_1641000/164100.stm 92 Enron delays closure notice for Indian plant after legal action, Agence France Presse, November 19, 2001 (accessed December 5, 2001); available from Lexis -Nexis Academic Universe. 93 Indian Court Bars Enron From Serving Financial Termination Notice, Asia Pulse, Nov. 12, 2001 (source: http://globalarchive.ft.com)

  • 34

    The Singapore Meeting

    Following the action of the Indian financial institutions of filing a suit against the DPC,

    the DPC decided to `boycott` the November 10-12 meeting held in Singapore where the DPCs

    institutional lenders, including Citibank, ABN Amro and Bank of America and the IBDI and the

    State Bank of India, met in a final attempt to discuss the financial restructuring of the DPC. After

    the DPC received personal assurances from the Center and the financial institutions that they

    intended to present new proposals at this meeting with respect to a negotiated settlement to the

    dispute, the DPC agreed to attend the meeting.94 At the meeting, the lenders were concerned

    about facilitating the sale of the Dabhol assets with prospective buyers, including Tata Power

    and BSES. The financial institutions also devised a proposal that was ultimately rejected by the

    MSEB. The proposal called for the MSEB to off-take power from Phase I and relinquish to the

    potential new buyer its exclusive distribution area where there are key industrial centers. The

    MSEB rejected this proposal with the argument that if it forfeited these prized areas, then it

    would not be able to absorb the power from DPCs first phase of 740 MW. The MSEB further

    protested the fact that FIs did not call us to the Singapore meet and had no right to make such an

    offer without consulting and taking MSEB into confidence.95 An official at the MSEB went on

    to declare that (f)inally, if things get sorted out and DPC is taken over by another company, it is

    MSEB which is going to be the largest consumer of the plant, and strangely despite having a 15

    per cent stake in the company, it is not even involved in DPCs sale process.96

    94 Singapore meet spills over; no proposals given, says DPC, in rediff.com, November 9, 2001 (accessed December 5, 2001); available from http://www.rediff.com/money/2001/nov/09enron1.htm 95 `FIs completely ignored us in DPCs proposed sale says MSEB, The Press Trust of India, November 23, 2001, available from Lexis -Nexis Academic Universe. 96 Ibid.

  • 35

    The Downfall of Enron One of the most interesting developments that emerged in this case, is the downfall of the

    energy giant Enron. Enrons declaration of bankruptcy on December 2, 2001 signified the largest

    filing of bankruptcy in US history. The question of finding a local buyer through the Singapore

    negotiations assumed less importance with respect to time and investment as Enron became

    embroiled in a series of US federal investigations on the transparency of its accounting practices

    and dealings. It was revealed that Enron had been omitting from its balance sheet financial losses

    incurred in relationships with private partnerships run by some of its own corporate officers. As

    Enron shares plummeted from $82 in January 2001 to $11.82 on November 5, 200197, Kenneth

    Lay announced to Enron shareholders that Enron would regain billions from, among its many

    assets, sale of its broadband telecommunications and its assets in Dabhol.98

    One analyst states the Dabhol investment played an insignificant or no role in the

    collapse of Enron. Several analysts concur with this argument maintaining that the company

    went down under the collective weight of its extraordinary corporate ambitions and the

    cumulative effect of sharp practices. 99 On the other hand, some Wall Street analysts had been

    complaining that Enrons complex web of businesses had contributed to lack of clarity in its

    financial reporting. An analyst at Salomon Smith Barney argued that the lack of strategic focus

    in acquisitions and operations contributed to Enrons undisclosed financial losses. Raymond

    Niles specifically argues that among other unrelated projects, power plants in India are

    unrelated, or only tangentially related, to their core merchant energy business.100 The Enron

    97 Ayres, Enron to pull out of Indian project 98 Stacie Babula, Enron falls amid concern debt threatens Dynergy bid, Bloomberg News, November 20, 2001 (accessed December 5, 2001); available from Lexis -Nexis Academic Universe. 99 The Enron Collapse and India, The Free Press Journal, January 23, 2002 (accessed March 12, 2002); available from www.samachar.com) 100 Simon London and Sheila McNulty. Enron flickers: Once a paragon of the new economy, the US energy group is under scrutiny for its opaque accounting and free-wheeling management, The Financial Times (London) October 29, 2001 (accessed December 5, 2001); available from Lexis -Nexis Academic Universe.

  • 36

    collapse, however, did play a significant role in the fate of the Dabhol project. Specifically,

    under pressure to sell its assets quickly to raise much-needed cash, Enrons bargaining position

    was significantly depressed vis--vis DPCs potential local Indian buyers and the GOM. Amidst

    allegations that Enron was over-leveraged and under pressure to cut costs in various business

    segments, Enron highlighted the Dabhol project as one of its most notably poor investments and

    noted that it would accelerate the process of trying to dispose of these failed assets to raise cash

    to pay its $12 billion debt. As Ronald Barone of UBS Warburg states Tata would be a faster

    exit and resolve it once and for all. It is better to take a small loss and move along. Dabhol

    periodically becomes a problem and an issue, and it depresses the stock.101 As a result of this

    decline in Enrons bargaining position, subsequent negotiations of the sale of the Dabhol assets

    involved a sale price that was substantially discounted.

    101 TATA in talks to buy Enron power plant, The Financial Times (London), October 15, 2001 (accessed December 5, 2001); available from Lexis -Nexis Academic Universe.

  • 37

    PART III. APPLYING NEGOTIATION THEORY TO EXPLAIN THE FAILURE OF THE DABHOL DEAL

    In fact, the entire negotiation with Enron is an illustration of how not to negotiate, how not to take a weak position in negotiations and how not to leave the initiative to the other side Report of the Munde Committee (August 1995)

    When discussing the importance of the pre-negotiation phase, Harold Saunders outlines

    four steps necessary to produce a commitment to a negotiated settlement: that it no longer serves

    either partys interest to pursue the present situation (i.e. conflict situation); that the alternatives

    to a negotiated settlement (BATNA) are not better than a foreseeable settlement; that each side

    makes its own estimates of whether the other side would accept a negotiated solution and is

    willing to reach a compromise; and finally, that an equal power balance exists to permit a fair

    settlement.102 This framework of analysis captures several of the reasons why the Dabhol deal

    failed, for even though a settlement was ultimately reached in the form of a negotiated PPA and a

    renegotiated PPA, the agreement was undermined in various stages because it served the

    interests of the ruling government to contest the PPA, because `compromise became an ugly

    word when the Dabhol project became politicized and when mistrust escalated on each side and

    furthermore when compromises were made, the right kind of compromises were not made and

    finally, because the PPA reflected an asymmetrical power balance as it was negotiated with a

    supply-side bias.

    Elements of Saunders framework and other frameworks that draw from negotiation

    theory and the field of conflict resolution will be explored in this section, as they lend insight

    into the failures of the Dabhol project in India, and ultimately why international business

    transactions can fail.

    102Harold H. Saunders, We Need a Larger Theory of Negotiation: The importance of Pre-negotiating Phases in Negotiation Theory and Practice, eds. William J. Breslin and Jeffrey Z. Rubin (Cambridge, Massachusetts: The Program on Negotiation at Harvard Law School, 1999), 65-68.

  • 38

    A. UNDERSTANDING BATNA and BATrNA

    In Getting to Yes: Negotiating Agreement Without Giving In, Roger Fisher and William

    Ury, argue that the best way to estimate a negotiated agreement is to measure it against what

    would be considered to be the parties best alternative to a negotiated agreement (BATNA).103 In

    the Dabhol case, the concepts of BATNA and what I refer to as BATrNA (Best Alternative to a

    Renegotiated Agreement) help explain how and why both parties were willing to enter into

    negotiations to construct the power project in Dabhol and ultimately why the parties agreed to

    renegotiate the PPA in an environment of escalating hostilities.

    The Indian Teams BATNA The table below is a summary of Indias alternatives to a negotiated PPA with Enron and its

    partners.

    Figure 4 - India's BATNAs

    Ranking Alternatives Best Alternative

    Contract a domestic private investor to build, own and operate the energy plant

    2nd Best Alternative

    Domestic company becomes majority partner in power project

    3rd Best Alternative

    Tap into alternative forms of energy sourced domestically (e.g. coal production)

    4th Best Alternative

    Have another foreign investor build, own and operate the energy plant

    The Best Alternative and 2nd Best Alternative in this case were untenable in the Indian

    context as Supriya Roychowdhury states, the ...private corporate sector in India has in general

    failed to demonstrate the characteristics of a vigorous entrepreneurial class, has grown based on

    state support and speculative behavior in a range of activities relating to underutilization of

    capacities making quick profits in a protected market, using its monolithic structure to preempt

    103 Roger Fisher and William Ury. Getting to Yes: Negotiating Agreement Without Giving In, 2nd ed, ed. Bruce Patton (New York: Penguin Books, 1991), 97.

  • 39

    competition and to perpetuate a market of shortages.104 A study done by Yamini Narayanan

    reveals that on a cost basis alone, there were incentives to pursue Enron as the lead supplier

    instead one of Indias leading national suppliers of energy, the National Thermal Power

    Corporation (NTPC)105, as Enron had the capacity and resources to supply power at a cost 8.45

    million dollars less than that of the NTPC.106 The reconstruction and revitalization of SEBs have

    been ear-tagged as investment risks by the World Bank, which made it difficult for the state

    governments to borrow for electricity generation and therefore placed a premium on the need for

    foreign investment.107 The GOM and the MSEB quickly disqualified the third best alternative

    noted above, as demonstrated by their disregard of recommendations to explore domestic sources

    of energy production such as coal production. Consequently, the merits and downfalls of this

    third best alternative did not influence or inform their decision to enter into negotiations with

    Enron. Finally, Enron, when compared to other foreign energy companies, was poised to be the

    lead contractor, as it possessed a portfolio o