turnaround continuous improvement journey to tar program ... · •rca program development and...
TRANSCRIPT
PotashCorp.com
Turnaround Continuous
Improvement – Journey to
TAR Program
Enhancement
PCS Nitrogen – Geismar, LA
Josh Higginbotham – Maintenance
Manager
• Introduction - Geismar
• Organizational Awareness
• TAR Scope Definition - Inputs
• Reliability Inputs
• TAR Planning
• P&ID Review Inputs
• Logistics & Plot Plans
• Execution Management
• Manpower Quality Control
• Geismar Next Steps
Presentation Overview
Centralized Organization
Organizational Awareness
Maint. Manager
Reliability Supt.
(Mech)
Maint. Engineers
Inspectors
Vibration Analysts
I&E Supt.
I&E Engineer
I&E Super.
I&E Craft
DCS Techs
Maint. Super.
Maint Foremen
Maint Craft
Utilities Super.
Contract Monitors
Non-Nested Crafts
Planning Super.
MW Planners
PF Planners
I&E Planners
TAR Scope Definition - Inputs
EH&SEH&S Initiatives
HAZOP Recommendations
OperationsOperator Rounds
Process Issues
Breakdown Repair
Loss Production Tracking
Capital Projects5-yr Plan
Expansion
Opportunity
Sustaining
Minor
M & RReliability Bad Actor Upgrades
Condition Monitoring
Inspection Findings
RCM/RBI
PM Follow-ups
TAR Scope
Reliability
TAR Scope Definition - Inputs
These technicians are senior ex-craftsmen that have mastered their crafts and expanded their knowledge
into technical reliability areas.
Engineers are set up with team lead responsibilities over rotating and fixed equipment groups.
Responsible for ensuring all reliability programs are working and on track.
Reliability Super.
Maint/Reliab. Engineer -ODR/Misc.
Maint/Reliab. Engineer -Rotating
PdMSpecialist
PdMSpecialist
Reliability Technician
Maint/Reliab. Engineer -
Fixed
Inspector Lead
Vessel Inspector
Pipe Inspector
QA/QC Inspector
These Technicians will have mastered their respective crafts As part of the reliability team they
will lend technical insight to I&E areas.
I&E Engineer is responsible for ensuring that all reliability work processes are being kept up to-date.
I&E Superintendant has overall responsibility for I&E department and sponsors the I&E reliability
team.I&E Super.
I&E Engineer -
Instrument Specialist
Electrical Specialist
I&E Designer
Reliability Work Processes
• Monthly Reliability Review
• Opportunity List (i.e., Bad Actor Tracking)
• Reliability KPI’s (PM Compliance, Seal MTBF, A.I. Resolution, Program Implementation %)
• Rotating Equipment Team Update
• Fixed Equipment Team Update
• I&E Reliability Team Update
• Action Item Review/Generation
• RCA Program Development and Updates
• Reliability Fileshare Created to act as single repository for all reliability program documentation and equipment info
Fixed Equip. Work Processes
• Monthly Fixed Equipment Team
• Overdue Inspections Tracking
• RBI Program Implementation (more on this)
• Inspection Findings are reviewed
• QA/QC Program reviews for NDE, Flange Make-up, Foundation, Structural, Painting, …etc. non-conformances.
• Reliability Specialist keeps track of the RV program and keeps up with all associated documentation
Rotating Work Processes
• Monthly Rotating Equipment Team Meetings
• Condition Monitoring List Review
• PM Compliance Review
• Critical Spares are tracked for major compressor train equipment and parts pool items
• Mechanical Seal Program Update
• RCM Implementation (More on this)
ODR Work Processes
• Operator based vibration data collection
• Improved operator round sheets to include more equipment information
• Operations mechanical training
• Development of PI data historian integration (IOW’s)
• Formal Operator/Maintenance technician walk-throughs for cross function collaboration
I&E Reliability Work
Processes
• I&E Reliability Review Meetings
• Electrical Infrared Scanning Program
• Control Valve PdM Program
• Current Monitoring
• PM Overdue Tracking
• Asset Criticality Assessments
Reliability Centered Maintenance (RCM) and Risk Based Inspection (RBI)
Asset Criticality Ranking (Software FMEA by Equipment Type, I&E & Rotating)
RBI Risk
Reliability
TAR Scope Definition - Inputs
• TAR Planning Improvements Catalyzed by general poor outage execution.
• Critique meeting was held to identify improvement opportunities and lessons
learned.
• Missing/Incorrect materials
• Incomplete/Inaccurate job plans
• Poorly Organized Scope
• Lack of Qualified Manpower
• Undefined Critical Path
• Untimely Safety Permitting
• Late Submittal of Work Requests
• Met with Maintenance Staff and contractor corporate planning leadership to go
over next steps. Revamped the daily and TAR Planning processes as a result.
• Continual Focus on Incremental Improvement Drove Further Successes
TAR Planning – Time for a Change!
• Systemized W.O.’s (Hierarchy based
on Plant Processes and Craft)
• Pre-Work/Post Work Identification (with
books)
• Standard Job Plans (Planning
Program referencing Page of Nations)
• Critical Path Optimization (Multiple
Individual Job Plan Reviews
w/Contractor)
• Critical Chain/Mass Optimization
(Timeline Complete 80% of critical
path)
• Scheduling Tool with Organized
Attributes
• Manpower Leveling (120%)
TAR Planning Improvements
• Manpower Quality Control
• Material Coordination (Dedicated
Material Handlers, Lock it up)
• Tools and Consumables
Staging/Tracking
• Job Prioritizations (Risk)
• Three shift look ahead (Update books)
• Shutdown/Start-Up Schedules (by
System)
• Logistics Planning
• Plot Planning and Area Grouping
• Earlier Scope Identification and
Organization of Work Orders
PHOTO SHEET WONO: 40130
WONO TITLE: EFFLUENT PUMP & OCI
LOCATION:
• Proprietary excel driven software
utilizing Page of Nations for consistent
estimating. Provides consistent plan
packages that are compatible with
Primavera 6.
• Attached to W.O.’s in CMMS
• Includes Summary, Schedule, Material
List, Marked Up P&ID’s, Photos
• TAR job books made for craft supervisor
walkthroughs, operations permitting,
management review, …etc.
• Actual jobs are planned by area
schedule planner and TAR planner.
• Allows accurate Productivity Tracking
Standard Job Plans
TAR Planning
REMOVE & REPLACE 14" CHECK
VALVE REMOVE 2 EA
14" VALVES
• Asset Hierarchies set up inside the scheduling tool (Match CMMS if possible)
• When work is scheduled for an asset it is already in the “process system”
• Company Codes should be unique for each Contractor’s work
• Allows for easy filtering by company
• Resources should be identified by Contractor and Craft
• i.e., Contractor1_PF, Contractor1_MW, …etc.
• Allows leveling by contractor and craft
• Schedule Ties between work orders
Scheduling Attribute Set-Up
TAR Planning
• Logistics Plan Considerations:
• Crane Placements
• Port-o-lets/Wash Stations
• Compressors
• Light Plants
• Parking
• Tool Trailers
• Break Tents
• Equipment Laydown
• Permit Areas
Logistics and Plot Plan Development
• Plot Plan Considerations:
• Individual Job Location
• Area Groupings
• Contractor Assignments
• Systemized grouping
• Expense vs. Capital Grouping
• Coordination with Logistics Plot Plan
Joint P&ID Reviews (Ops and Rel)
Early Scope ID and
Organization
P&ID Work Scope Generation List for 2018 TAR
Item # System P&ID Asset # Tag # Work Type Work Description
1 Helium 123456 A A-101 Mech.Remove Leak Clamp, Inspect
Flange and Replace Gasket
2 Helium 123456 B B-101 I&EPull and overhaul CV1234
(Resistance Curve Increase)
3 Helium 123456 C C-101 RotPull and Overhaul Helium
Compressor
4 Helium 123456 D D-101 MechReplace Air filter on Helium
Compressor
5 Helium 123456 E E-101 Insp.Perform internal inspection for
stress cracking per RBI
https://ardnas20.wordpress.com/2011/05/05/pid-what-is-it/
• Safety: Kickoff and Incentives
• Productivity Input to Schedule and
Cost Forecasting
• 𝐿𝑎𝑏𝑜𝑟 𝑃𝑟𝑜𝑑.=𝑀𝑛ℎ𝑟𝑠 𝐴𝑐𝑡𝑢𝑎𝑙
𝑀𝑛ℎ𝑟𝑠 𝐸𝑎𝑟𝑛𝑒𝑑
• 𝑆𝑐ℎ𝑑. 𝑃𝑟𝑜𝑑.=𝑀𝑛ℎ𝑟𝑠 𝐸𝑎𝑟𝑛𝑒𝑑
𝑆𝑐ℎ. 𝐸𝑎𝑟𝑛𝑒𝑑
• Construction Manager/s for timely
Issues Resolution
• Daily Management/Customer
Update Meetings
• Daily Critique Capture
Execution Management Improvements
0.00
1,000.00
2,000.00
3,000.00
4,000.00
5,000.00
6,000.00DIRECT LABOR MHRS
PlannedMHRS
Earned MHRS
ExpendedMHRS
CompanyEstimated
MH's
FCO
MH'sTotal MH's
MH's
Earned
MH's
SpentProd.
Contractor 11,172 287 1,459 1,459 1,342
1.09
Contractor 21,718 45 1,763 1,763 1,538
1.15
Contractor 32,917 17 2,934 2,934 3,135
0.94
Contractor 4463 16 479 479 536
0.89
Contractor 5981 - 981 981 1,018
0.96
Contractor 6874 6 880 880 643
1.37
Total8,125 371 8,496 8,496 8,212
1.03
• Large manpower requests tend to result in low craftsmen skill levels
• High local area demand for craftsmen
• Reviewed On-Boarding process and added a requirement for NCCER testing.
Now only craftsmen that have passed the NCCER for their respective craft are
allowed to join the TAR
• Other Staffing Considerations:
• Small-Medium Outages: Basic Jobs (majority of Critical Chain) handled by
Contractor augmented with additional NCCER qualified manpower.
• Medium-Large Outages/TAR’s: Area Groupings assigned to different Trusted
Contractors. Don’t want to give one contractor too much work.
• Critical Path Jobs or Specialty Work: Specialized contractors dictated by work
type (fresh air entry, catalyst, distillation tunneling, large projects, …etc.) May
be Incentivized.
Manpower Quality Control
• Contractor Contract Set-Up and score card development
• Consistent Estimation methods to allow accurate comparison of contractor
productivity
• Continue to work on negative outage critiques and reinforce positive critiques
• Ensure Field Change Orders and Found Work are added to the schedule daily
• Scheduling Tool Asset Hierarchy fully implemented
• Scheduling Specification sent out for Construction Bids
• Schedule attribute requirements spelled out
Geismar Next Steps