turbine cw pipe status updated2

Upload: vivekpathak101

Post on 05-Apr-2018

230 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    1/21

    PRESENTATION

    ON

    Steam Turbine (685 MW)-GMR Energy.

    by

    VIVEK PATHAK

    Date : 9th April 12

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    2/21

    GMR ENERGY steam Turbine(2X685MW)

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    3/21

    CONTENTS

    1 INTRODUCTION(685 MW STEAM TURBINE2 TURBINE DESIGN FEATURES.

    3 TURBINE CHARECTERSTICS.

    4 TURBINE WEIGHT- WISE BREAK UP

    5 TURBINE CATENARY

    6 BEARING

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    4/21

    Technical Specification

    The Steam turbine is 685 MW,3000 rpm , a tandem compounded 4 flow ,four casings.Itconsists of High pressure Turbine, intermediate pressure Turbine and Two low pressure

    turbines with 850.9mm last stage buckets.

    The Unit uses off-shell design two(2) main stop and four(4) control valves, connecting tothe upper and lower half casing.

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    5/21

    Turbine Design features

    Turbine Design Features

    :Main steam inlet Pressure: 255 kg/sq.cm Reheat temperature :597*c Reheat pressure:48.14 kg/sq.cm

    Rated steam turbine speed:3000 rpm No. of Cylinders:4 cylinder

    Compounding Type: Tandem compounded

    HP turbine:10stages single flow

    IP turbine:2x9 double flow

    LP A Turbine: 2x6 double flow

    LP B turbine :2x6double flow

    Turning Gear Speed: 3 to7 rpm.

    Main steam inlet Temperature565*c

    Main steam inlet Pressure 255 kg/sq.cm

    Reheat temperature597*c

    Reheat pressure 48.14 kg/sq.cm

    Rated steam turbine speed 3000 RPM

    No. of Cylinders 4 CYLINDER

    Compounding Type TANDEM COMPOUNDED

    HP turbine 10 STAGES SINGLE FLOW

    IP turbine 6X2 DOUBLE FLOW

    LP A Turbine 6X2 DOUBLE FLOW

    TURNING GEAR SPEED 3 TO 7 RPM

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    6/21

    HP Turbine Characteristics:

    HPT uses double casing construction with first stage in the nozzle box. HPT Diaphragms are centre line supported in the hp inner casing.

    HP inner casing centre line with HP outer casing.

    HP casing is centre line supported on the front standard.

    Bearing #1 and Bearing#2 are Tilting pad.

    IP Turbine Characteristics: Double Flow

    2 nos of exhaust which feed a single cross over pipe to LPT

    Bearing #3 and Bearing #4 are tilting pad

    LP Turbine characteristics: Double flow.

    Eleptical bearing.

    Nozzle spray cooling at the diffuser both end.

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    7/21

    HP casing

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    8/21

    Material of construction

    :

    HP outer casings :ZG1Cr1Mo1 HP inner casing :ZG1Cr1Mo1

    IP outer casing :ZG1Cr1Mo1

    IP inner casing: ZG1Cr1Mo1

    LP casing: Q235-B

    SHAFT: HP rotor:30Cr1Mo1V

    IP rotor:30Cr1Mo1V LP Rotor:30Cr2Ni4MoV

    TURBINE CASING

    HP outer casings ZG1Cr1Mo1

    HP inner casing ZG1Cr1Mo1

    IP outer casing ZG1Cr1Mo1

    IP inner casing ZG1Cr1Mo1

    LP casing Q235-B

    SHAFT

    HP rotor 30Cr1Mo1V

    IP rotor 30Cr1Mo1V

    LP Rotor 30Cr2Ni4MoV

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    9/21

    Turbine blades

    Dovetail : Fastening of bucket to rotorVane : conversion of thermal energy to torque energy.Cover :control of leakage of steam passing through the end of the vaneto reduce the bucket vibrationTenon : Fastening of the cover at the vane tip to the bucket.

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    10/21

    Material of construction

    BLADES(First Stage)

    HP moving blades:2Cr11Mo1NbV HP stationary blades:ZG2Cr12NiMoW1V

    IP moving blades:2Cr11Mo1NbV

    IP stationery blades:2Cr11Mo1VNbN

    LP moving blades:1-4 Stages-1Cr13,

    5-6 stage-2Cr12NiMo1W1V LP stationary blades:ZG1cr13

    OTHER STAGES: HP moving blades:2Cr12NiMo1W1V

    HP stationary blades:ZG2Cr12NiMo1W1V IP moving blades:2Cr11Mo1VNbN

    IP stationery blades:2Cr12NiMo1W1V

    LP moving blades:1-4 Stages-1Cr13, 5-6 stage-2Cr12NiMo1W1V

    LP stationary blades:2Cr12NiMo1W1V

    BLADES(First Stage)

    HP moving blades 2Cr11Mo1NbV

    HP stationary blades ZG2Cr12NiMoW1V

    IP moving blades 2Cr11Mo1NbV

    IP stationery blades 2Cr11Mo1VNbN

    LP moving blades blades:1-4 Stages-1Cr13,5-6 stage-2Cr12NiMo1W1V

    LP stationary blades ZG1cr13

    OTHER STAGES

    HP moving blades 2Cr12NiMo1W1V

    HP stationary blades ZG2Cr12NiMo1W1V

    IP moving blades 2Cr11Mo1VNbN

    IP stationery blades 2Cr12NiMo1W1V

    LP moving blades 1-4 Stages-1Cr13, 5-6 stage-2Cr12NiMo1W1V

    LP stationary blades 2Cr12NiMo1W1V

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    11/21

    Turbine weight wise breakup

    HP TURBINE:

    HP Rotor:18 MT HP diaphragm:8MT

    HP inner Casing:35.2 MT

    HP outer casing:72.9 MT

    HP Standard:18.1 MT

    Total HP Turbine:152.2MT

    IP TURBINE IP ROTOR:36.3 MT

    IP diaphragm:32.1 MT IP inner casing:55.3 MT

    IP outer casing:104.5 MT

    IP Standard: 22.7 MT

    Total IP Turbine:250.9

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    12/21

    Turbine weight wise breakup

    LP TURBINE:

    LPA ROTOR :56.6 MT

    LPB ROTOR:56.8 MT

    LP Diaphragm(A& B each):111.584 MT

    Hood Extension:73 MT

    LP hood (TE&GE):136.6 MT

    CROSS OVER PIPE:63.4 MT

    GENERATOR:414.673MT Generator Rotor:74.628 MT

    Generator Stator:283.836 End shields:22.845MT

    Domes:17.706MT

    High Voltage Bushing:1.634

    Excitor collector Housing:4.086

    Cooler (empty):9.98

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    13/21

    TURBINE BEARING ARRANGEMENT

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    14/21

    Types of bearing Used in Steam turbine:Elliptical bearing-Radial type of simple journal Bearing.

    Tilting type bearing-self aligned ,radial type journal bearing.

    Thrust bearing: pad type of journal bearing for axial thrust of rotor

    TURBINE BEARINGS

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    15/21

    THRUST BEARING:Double collarPosition at middle standard.

    Used for axial position and Thrust load of rotor.

    Size of thrust bearing:2258 sq. cm

    Bearing pad made of copper back to increase bearing heat transfer.

    ELLIPTICAL BEARING:

    TURBINE BEARING

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    16/21

    TILTING PAD BEARING:

    Improved dynamic performance of the rotor-bearing system.

    Bearing adaptability to shaft movements as a result of to the ability

    of the shoe to tilt.

    Uniformly distributed oil flow from equidistant radial feed holes.

    Increased stability due to greater damping.

    Lower spare parts costs since only the pads need to be changed.

    Used Where there are larger temp. changes and therefore greatermis-Alignment potential.

    TURBINE BEARING

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    17/21

    NOZZLE BOX & DIAPHRAGM

    Steam flow concerns:(A) Steam path contour(B) Nozzle area(C) Nozzle angle(D) Flow coefficientFull and partial arc admission system

    Nozzle & Diaphragm

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    18/21

    Lower bending Stress and deflection due to the high stagepressure drop.

    In the smaller diaphragms ,nozzle partitions are inserted intothe punched band for easier welding and to maintain properuniform throat condition between partitions.

    Larger diaphragms nozzle partitions are welded directly tofabricated or forged outer rings and inner web plates.

    Nozzle & Diaphragm

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    19/21

    STEAM PATH CONTOUR

    Steam Balance holes are provided.

    Removable Radial strips segment

    Smaller rotor packing diameter andmore packing Teeth

    Steam balance holes control thrust

    STEAM PATH CONTOUR

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    20/21

    TURBINE VALVESMax. travel of Main stop valve stemis 330mm

    Max. travel of control valve is stem

    is 216mm.Max. travel of combined reheatvalve stem is 673mm

    TURBINE VALVES

  • 7/31/2019 Turbine Cw Pipe Status Updated2

    21/21

    TURBINE EXTRACTION STEAM PRESSURE & TEMPERATURE

    S.NO EXTRACTIONPOINT

    PRESSURE

    TEMP. STEAM(T/HR)

    HEATER

    1 HP-7 STAGE 77.36 391.91 166.201 HP HEATER-8

    2 CRH PIPE 48.56 330.62 231.956 HP HEATER-7

    3 IP-15 STAGE 17.03 450.06 94.522 HP HEATER-6

    4 IP-19 STAGE 7.78 335.42 44.987 DEARATOR

    5 LP A/B-20STAGE

    4.76 287.81 62.325 LP HEATER-4

    6 LP A/B-21STAGE

    2.45 216.11 97.255 LP HEATER-3

    7 LP A/B-24STAGE

    .65 92.55 49.083 LP HEATER-2

    8 LP A/B 24

    STAGE

    .29 67.58 41.055 LP HEATER-1

    TURBINE EXTRACTION