tube nipping

19
NIPPING OF F-201 TUBE # 21 PREPARED BY: HAFIZ ABID HUSSAIN / SOHAIL RAZA

Upload: adnan-sheikh

Post on 28-Nov-2014

197 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Tube Nipping

NIPPING OF F-201 TUBE # 21

PREPARED BY: HAFIZ ABID HUSSAIN / SOHAIL RAZA

Page 2: Tube Nipping

Introduction / Background

• F-201 Catalyst tubes are in service since 1982 and completed a service life of > 227,760 hrs against design of 100,000 hrs.

• Higher life achieved due to lower Tube Metal Temperatures (TMT value around 895 0C against design value of 925 0C).

Page 3: Tube Nipping

Process

Convection

SectionK -201

Vent Stack

Radiant

Section

Reformed

Gas

Natural Gas + Steam

Page 4: Tube Nipping

RADIANT SECTIONF-201 Radiant Section

Refractory Lining

Fire Box

Radiant Tubes

Burners

Page 5: Tube Nipping

Hairpin

Inlet Header

Catalyst Tube

Outlet Pigtail

Hot Collector

Mechanical Description

Page 6: Tube Nipping

1. Tube # 160 April 27, 2003

2. Tube # 228 July 25, 2003

3. Tube # 164 January 22, 2006

4. Tube # 21 June 26 , 2008

Tube Leakage History

Page 7: Tube Nipping

• On June 26, 2008 at 1930 area operator reported high noise

level in A/B chamber of primary reformer F-201 and backfiring

of Burner # 1.4B.

• Burner was immediately isolated.

• On checking through peep door, a black vertical spot was

sighted at the bottom of a tube.

• Burner # 1.5B was also extinguished due to improper burning.

• Coordination / Shift Engineer visited the site and declared

Tube # 21 in Hot collector # 41 as the leaking tube.

• Insulation from pigtails of tubes from 19 to 23 was removed,

TMTs taken and hourly monitoring started.

Tube Leakage Detection

Page 8: Tube Nipping

• Noise level in A/B chamber was 111 dB as compared

to 99dB in C/D chamber.

• TMT of tube # 21 was 8900C.

• Insulation removed from pig tails of tubes # 19 to 23

to check pigtail temperature.

• Pig tail temperature of tube # 21 was initially 7680C,

while at adjacent tubes temperature was 7800C.

• This temperature reduced to 7550C until nipping of

the tube.

Observations / Actions taken

Page 9: Tube Nipping

• B # 1.4B found glowing from inner side.

• Hot spot at external burner plate was increased to

4450C with LS application.

• Burner # 1.4A at opposite end of Tube # 21 was

removed to take observations of the leaking tube.

• A log sheet developed for monitoring of tube

leakage.

Actions taken….

Page 10: Tube Nipping

• Before Tube nipping activity Shop Test was carried out as per standard nipping practices.

• The purpose of shop test is to simulate the actual nipping conditions.

• This is required to:– Check work ability of the equipment to be used on

the job.– Train all the team member for the actual job.

Tube Nipping

Page 11: Tube Nipping

• Plant Emergency Actions were discussed in detail within the group and with other units.

• Safety squad alerted. (Situation was discussed with Deputy Warden)

• Fire truck arranged for rescue purpose.

• Safety talk conducted before job execution.

• Doctor on duty was informed about the job and Ambulance was arranged with dispenser.

• All possible scenarios were discussed with maintenance team and area operators.

• Plant-II coordination Engineer and other units were informed about the activity.

• Lime water arranged at F-201 bottom and top for avoiding dehydration of personnel working in hot environment.

• Ice cooled jackets with complete fire protection suits arranged by the maintenance Engineer for the nipping team.

Safety Precautions Adopted

Page 12: Tube Nipping

– On June 27 tube nipping activity was carried out

from 1930 to 1945 hrs.

– It was nipped first from the bottom pigtail at

13000 PSI and then from top hair pin at 4500 PSI

pressures.

Tube Nipping Activity

Page 13: Tube Nipping

• Noise level in A/B chamber was reduced from 111 to 100 dB.

• Tube color changed to glowing red from top to the leaking

point. Tube bottom portion remained dark.

• Burner plate hot spot reduced from 445 to 900C.

• Temperature at HC # 40/41 were reduced from 788/789 to

782/7750C respectively.

• Flue gas temperature decreased from 1002 to 9800C.

• CH4/CO2 slippages increased from 0.65/0.1100 to 0.78/0.1150 %.

• Syn. gas flow had to increase from Zero to 3200 NMC/hr to

control Syn. machine 1st stage discharge pressure.

Observations After Nipping

Page 14: Tube Nipping

Hairpin

Inlet Header

Catalyst Tube

Outlet Pigtail

Hot Collector

Mechanical Description

Nipping point for outlet pigtail

Nipping point for inlet hairpin

Page 15: Tube Nipping
Page 16: Tube Nipping

BURNER# 1.4B GLOWING BEFORE NIPPING

Page 17: Tube Nipping

BURNER # 1.4B BECAME NORMAL AFTER TUBE NIPPING

Page 18: Tube Nipping

BEFORE NIPPING PIG TAIL OF TUBE # 21 IS GLOWING

Page 19: Tube Nipping

AFTER NIPPING PIGTAIL BECAME DARK