tt 162 final

Upload: thomas-lawson

Post on 02-Jun-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 TT 162 Final

    1/9

    TT-162 Environmental

    PROBABILISTIC DESIGN OF MINE-SITE PONDS USING A DYNAMIC WATERMANAGEMENT MODEL

    byDr. Ing. James R. Kunkel, Knight Pisold and Co., Senior Associate, 1580 LincolnStreet, Suite 1000, Denver, Colorado USA, Tel: +1 303 867 2286, Fax: +1 303 6298789,[email protected]

    andIng. Victor Lishnevsky, Knight Pisold and Co., Associate, 1580 Lincoln Street, Suite1000, Denver, Colorado USA, Tel: +1 303 867 2244, Fax: +1 303 629 8789,[email protected]

    SUMMARY

    Water management at a mine site is a critical component for the design of ponds for

    mine facility operation and mine facility closure. A comparison of pond sizes designed

    using both a probabilistic and deterministic dynamic water balance model is made.

    The two models both have the capability of using actual operational data and climate

    inputs to give storage requirements of the ponds. Both short-term (60 days) and long-

    term (many years) designs incorporating a user-selected storm event and a

    probabilistic or deterministic analysis may be utilized for calculating storage volumes

    for various mine facilities. Based on these, operational decisions based on actual

    values or probabilities over time can be made. Typically, the final design of the ponds

    is based on the average volume from the deterministic model plus the volume from the

    100-year return period storm. An example of such a design is presented in the paper.

    OBJECTIVES

    The overall objective of pond volume designs for mine facility operation and mine

    facility closure is to provide a specific set of operating rules and facility sizes for

    managing water over the life of the mine. The principal goals of the design are to:

    determine the range of normal operating volumes for the ponds so that the

    pond size and configuration can be approximately defined for the life of the

    mine in order to provide an efficient storage system,

    determine the maximum potential pond volume under conditions of extreme

    precipitation in order to provide the necessary pond freeboard on the dam at all

    times, and

    determine the water flow between a given pond and various other mine

    components, and to size required pipes and pumps between them.

    1

  • 8/10/2019 TT 162 Final

    2/9

    DATA GATHERING

    An important input component is climatological data which consist of monthly (or daily)

    precipitation, evaporation and runoff. The second input is the operation of the project

    and development of the facilities. How the mine site development and closure occurs

    over time is more important to the sizing of ponds for water storage than the

    climatological data. It also is important to note that if the development process

    changes, the pond design must be updated to assure that adequate storage is always

    available. Thus, inputs from both the mine owner related to mine development, long

    term climatological data from government agencies, and various water sources and

    sinks must be obtained and analyzed. This often is done in a separate climatology and

    water supply report.

    For the design example presented in this paper, the key climatological conditions at the

    site can be summarized as follows:

    the average annual precipitation is approximately 1,172 millimeters (mm),

    the average maximum temperature varies from 13 to 16 degrees Celsius and

    average minimum temperature varies from 1 to 12 degrees Celsius throughout

    the year,

    the average annual potential evaporation was estimated to be 1,685 mm,

    the average annual evaporation from a pond surface was estimated to be 1,180

    mm,

    the design 100-year/24-hour storm event produces 92 mm of precipitation,

    the mine life was 28 years, and

    the 45 years of detailed climatological data used in the design and analyses were

    defined in a separate climatological report.

    APPLICATIONThe pond sizing begins with a traditional operational water balance model (Kunkel,

    2001). The key component in the model is the pond storage which serves as a large

    reservoir for the process water supply. The model operates on a monthly basis by

    quantifying the monthly changes to the one or more storage ponds from inflows,

    outflows, evaporation, and absorption. The model uses the following governing

    equation:

    V = I Q E,

    2

  • 8/10/2019 TT 162 Final

    3/9

    where V = change in pond volume, I = inflows to the pond from direct precipitation on

    the pond, runoff and other water inflows, Q = outflows from the pond consisting of

    reclaim water to the process plant and excess water discharges to treatment or

    discharge, and E = evaporation.

    The procedure used in the operational water balance to perform pond design is the

    robust water balance previously described by Kunkel (2001) and Kunkel and

    Lishnevsky (2002). The traditional approach to an operational water balance is to use

    the systematic climatological time series data as average monthly values and once-

    through operation. This approach uses only a 12-season model with each season

    represented by a month. An alternative approach for operational water balance

    modeling is to use the complete monthly time series for as many years of data as are

    available, or to use a stochastically generated monthly time series. Modern stochastic

    climate data generating techniques are easily applied to obtain data in-fill and/or

    extension of the historical climatological data. Typical stochastic data generation

    models include WGEN (Richardson and Wright, 1984) and ClimGen (Stckle and

    others, 1998; 1999). Similar stochastic models also are available within the EPIC

    computer program (Sharpley and Williams, 1990) which is extensively used by Knight

    Pisold and Co.

    The robust operational water balance approach (Kunkel and Lishnevsky, 2002) uses

    the systematic climatological record or a synthetically generated monthly time series.

    Figure 1 shows a typical monthly climatological time series of 33 years and a mine life

    of 6 years for a Per mine site, which indicates how the robust operational water

    balance operates. The first operational water balance model run is placed at the start

    of the mine life in the first year of the 33 years of precipitation data, while the second

    model run is placed in the second year of the data, and so on. Each model run is

    considered to be independent of the previous run. Therefore, each of the 33 runs

    produces 33 equally-likely, independent outcomes which can be analyzed to calculate

    the probability of occurrence of each of the runs. The reason for performing 33 equally

    likely and independent water balance runs is because it is unknown, a priori,when the

    mine project will come on line or what the climate conditions will be when the project

    comes on line.

    3

  • 8/10/2019 TT 162 Final

    4/9

    0

    50

    100

    150

    200

    250

    300

    350

    400

    450

    500

    Jan-

    64

    Jan-

    65

    Jan-

    66

    Jan-

    67

    Jan-

    68

    Jan-

    69

    Jan-

    70

    Jan-

    71

    Jan-

    72

    Jan-

    73

    Jan-

    74

    Jan-

    75

    Jan-

    76

    Jan-

    77

    Jan-

    78

    Jan-

    79

    Jan-

    80

    Jan-

    81

    Jan-

    82

    Jan-

    83

    Jan-

    84

    Jan-

    85

    Jan-

    86

    Jan-

    87

    Jan-

    88

    Jan-

    89

    Jan-

    90

    Jan-

    91

    Jan-

    92

    Jan-

    93

    Jan-

    94

    Jan-

    95

    Jan-

    96

    Jan-

    97

    Month/Year

    MonthlyPrecipitatio(

    m

    EXAMPLE: 6 YEAR MINE LIFE, 33 YEAR CLIMATE RECORD

    SECOND RUN

    FIRST RUN

    N-5 RUN

    0

    50

    100

    150

    200

    250

    300

    350

    400

    450

    500

    Jan-

    64

    Jan-

    65

    Jan-

    66

    Jan-

    67

    Jan-

    68

    Jan-

    69

    Jan-

    70

    Jan-

    71

    Jan-

    72

    Jan-

    73

    Jan-

    74

    Jan-

    75

    Jan-

    76

    Jan-

    77

    Jan-

    78

    Jan-

    79

    Jan-

    80

    Jan-

    81

    Jan-

    82

    Jan-

    83

    Jan-

    84

    Jan-

    85

    Jan-

    86

    Jan-

    87

    Jan-

    88

    Jan-

    89

    Jan-

    90

    Jan-

    91

    Jan-

    92

    Jan-

    93

    Jan-

    94

    Jan-

    95

    Jan-

    96

    Jan-

    97

    Month/Year

    MonthlyPrecipitatio(

    m

    EXAMPLE: 6 YEAR MINE LIFE, 33 YEAR CLIMATE RECORD

    SECOND RUN

    FIRST RUN

    N-5 RUN

    Figure 1. Operational Water Balance Procedure for 6-Year Mine Life and 33 Years of

    Climatological Data

    For the current case of a 28-year mine life and 45 years of climatological data, the

    model computes the volume in a given storage pond, together with certain other

    outputs (discharge rates, etc.) for each month during the mine life. The operational

    mine life was estimated by the mine owner to be 28 years (November 2011 through

    November 2038) or 336 months (28 years times 12 months per year). One run of the

    model has a duration of 336 months, and for 45-years of precipitation data, a total of 45

    independent model runs were computed. Each model run produced 336 months of

    output data (outcomes) covering the period of mine operations, and when all 45 of the

    runs were complete, each of the 12 months was represented by 45 values of output

    data (pond volumes, discharge rates, etc.). Monthly maximum, minimum and various

    other probabilistic values were then determined for the output data (outcomes) for each

    month of each of the 28 years of the mine life.

    DEVELOPMENT

    4

  • 8/10/2019 TT 162 Final

    5/9

    The pond design volume is calculated as the larger of the storm volume pond modeling

    or the probabilistic pond modeling defined as follows.

    Storm Volume Pond Modeling

    The average and maximum monthly sizes of pond volumes throughout the mine life

    from each run was determined by:

    Average Monthly Volume. This volume is calculated as the average of the 45 pond

    volumes predicted from each month the facility is in operation (336 months) by

    stepping the model through 45 years of data. The model is run for 28 years at a time

    (336 months), beginning in each of the 45 years of available data. The result is 45

    equally likely sets of outcomes of 28 years each. These 45 equally likely outcome

    sets are used to calculate probabilities of occurrence (see Probabilitstic Pond

    Modeling below), and

    Design Storm Event. This volume considers the runoff from the 100-year storm event

    occurring in 24 hours from the upstream catchment reporting to the pond plus 100

    percent of the precipitation falling within the limits of the pond.

    The sum of the average monthly and design storm event volumes was used to predict

    the maximum potential pond volume for every month the facility is in operation (336

    months). The largest monthly volume from this sum was selected as the design pond

    volume.

    Probabilistic Pond Modeling

    From the 45 equally likely average, maximum, and minimum pond volumes determined

    for each of the 336 months the facility will be in operation, a frequency analysis was

    performed to determine the 1 percent (represents a 100-year return period), 10 percent

    (10-year return period) and 50 percent (2-year return period) chance of exceedance

    pond volumes for each of the 336 months. The largest monthly volume was selected as

    the required probability analysis pond volume. The percent chance of exceedance was

    calculated using an Extremal Type I Distribution (Kite, 1977).

    Pond Volume Design

    Selection of the design pond volume is based on the monthly volume from either (1)

    storm volume pond modeling, or (2) the probabilistic pond modeling, whichever is

    5

  • 8/10/2019 TT 162 Final

    6/9

    larger. In some cases, freeboard was added to the pond design volume to determine

    the final size of the pond.

    For the current case of a 28-year mine life and 45 years of climatological data, the

    average monthly results of the design pond volume with the 100-year, 24-hour storm

    event are shown on Figure 2.

    Figure 2. Operational Pond Volume with Storm Event (Storm Volume Modeling)

    The probabilistic pond modeling results are presented on Figure 3.

    6

  • 8/10/2019 TT 162 Final

    7/9

    Figure 3. Probabilistic Pond Volume Modeling

    Analyses of the results shown in Figures 2 and 3 indicate that the average pond

    volume from the storm volume modeling (Figure 2) is approximately the same as the

    50 percent probability volume (Figure 3), as would be expected. In this case if the

    decision to design the pond to store approximately 4,500,000 m 3was taken, the mine

    owner may feel comfortable that sufficient storage was available to reduce the

    likelihood of overtopping on average (the 1 in 2 year probability). Normally, the mine

    owner would never know that there is a risk of having to store larger volumes unless

    the probability analyses were performed as shown on Figure 3.

    If less risk is desired, a design pond volume of approximately 6,000,000 m3(the 1 in 10

    year probability) may be appropriate, or even a design pond volume of 8,000,000 m 3

    (the 1 in 100 year probability). Typically, the traditional operational water balance

    would provide a pond volume with the 100-year, 24-hour storm event as shown on

    Figure 2; whereas, the probabilistic design pond volume with less risk would be as

    shown on Figure 3.

    CONCLUSIONS

    Our conclusions related to operational water balance modeling for pond storage at

    mine sites include the following:

    The type of operational water balance utilized for design of pond storage

    volumes at mine sites can result in startlingly different results which may

    7

  • 8/10/2019 TT 162 Final

    8/9

    impose excessive risk of either overtopping or a water shortage during

    operation.

    The robust water balance method should be utilized for operational volumes

    and flows of all mine facilities for both surface- and ground-water management.

    The probabilistic results should be presented so that mine owners and

    managers can assess their risk related to design storage volumes or design

    flow rates for various facilities.

    Water management components other than ponds, such as heap leach pads,

    tailing storage facilities, processing facilities, hydroelectric facilities, water

    treatment plants, land application facilities, and other mine-related facilities can

    be analyzed using a similar technique.

    This modeling approach can be made available as a web-based model which

    can be shared within a given mine project.

    REFERENCES

    Kite, G.W., 1977, Frequency and Risk Analysis in Hydrology, Fort Collins: WaterResources. Publications, 224 pp., http://www.wrpllc.com/links.html

    Kunkel, J.R. and V. Lishnevsky, 2002, A Robust Water-Balance Method for Sizing

    Heap Leach Solution Ponds, Proceedings of the SME Annual Meeting,Phoenix, Arizona, February 25-27, 2002, (only available on compact disk),Preprint 02-049, 5p.

    Kunkel, J.R. 2001,A Robust Water-Balance Method for Sizing Heap Leach SolutionPonds and Reservoirs, Proceedings of the XXV Convention of Peruvian MiningEngineers, Arequipa, Peru, September 10-14, 2001 (only available on compactdisk), 11p.

    Richardson, C.W. and D.A. Wright, 1984, WGEN: A Model for Generating DailyWeather Variables, U.S. Department of Agriculture, Agricultural ResearchService, ARS-8, August, http://soilphysics.okstate.edu/software/cmls/WGEN.pdf

    Sharpley, A.N., and J.R. Williams, 1990, EPIC-Erosion/Productivity Impact Calculator:1. Model Documentation, US Department of Agriculture Technical Bulletin No.1768, 235 p., http://www.epa.gov/nrmrl/pubs/600r05149/600r05149epic.pdf

    Stckle, C.O., P. Steduto, and R.G. Allen, 1998, Estimating Daily and Daytime MeanVPD from Daily Maximum VPD. 5th Congress of the European Society ofAgronomy, Nitra, The Slovak Republic.

    Stckle, C.O., G.S. Campbell, and R. Nelson, 1999, ClimGen Manual. BiologicalSystems Engineering Department, Washington State University, Pullman, WA,

    28 p., http://bsyse.wsu.edu/climgen/

    8

  • 8/10/2019 TT 162 Final

    9/9

    9