transport emissions evaluation model for...
TRANSCRIPT
Transport Emissions EvaluationModel for Projects
Sudhir Gota & Alvin MejiaClean Air AsiaLee Schipper Scholar (2013)
Asia LEDS Forum3rd October, 2013
Metro Manila
Sudhir Gota & Alvin MejiaClean Air AsiaLee Schipper Scholar (2013)
Asia LEDS Forum3rd October, 2013
Metro Manila
Why we developed TEEMP Models?Who is involved in TEEMP process?What are TEEMP models?How TEEMP was developed?What did we learn from TEEMP?…………………………………………..?
Outline
Why we developed TEEMP Models?Who is involved in TEEMP process?What are TEEMP models?How TEEMP was developed?What did we learn from TEEMP?…………………………………………..?
Reality or Myth?
Source : 16 MAY 2012, THE PIONEER, INDIA
Reality or Myth?
32% Reduction in total emission generation by constructing flyover
0.040
0.060
0.080
0.100
0.120U
S$ p
er v
ehic
le-k
m
Fuel
Value of Time Costs
Reality or Myth?
0.000
0.020
MC Medium Car Medium Truck Medium Bus
US$
per
veh
icle
-km
Source : World Bank Road Use Costs Study Results
Infrastructure projects provide fuel and time savings
Fuel savings are three time higher than travel time savings
Benefits in transport projects
Objective
Credit: Yang JIANG, Daizong LIU, Suping CHEN, Assessment Tools for China Low‐Carbon‐City Projects From the CSTC’s Perspective, 2011
Goals
• Relatively simple project sketch models that:- foster best practice design/operations- reflect complex induced travel/land use placeholders- focus on wide range of sustainable transport options- promote cobenefits- Easy and could be done even with low resources (decouple accuracy with
resources spent )
• Use defaults where data is poor/missing
• Capacity to boost analysis fidelity with local data
“a means to an end and not an end in itself”
• Relatively simple project sketch models that:- foster best practice design/operations- reflect complex induced travel/land use placeholders- focus on wide range of sustainable transport options- promote cobenefits- Easy and could be done even with low resources (decouple accuracy with
resources spent )
• Use defaults where data is poor/missing
• Capacity to boost analysis fidelity with local data
“a means to an end and not an end in itself”
● TEEMP – Transport Emissions Evaluation Model for Projects(can be pronounced as “temp” or temporary)
● Excel-based, free-of-charge, transparent spreadsheet models● Low cost applications, uses data required for economic analysis
of projects (not data intensive)● Results of TEEMP evaluation can help facilitate reasonable
direction for action and alternate options● Used by ADB, GEF, World Bank, GIZ, CTF, IADB, MOUD etc.
Introduction to TEEMP
● TEEMP – Transport Emissions Evaluation Model for Projects(can be pronounced as “temp” or temporary)
● Excel-based, free-of-charge, transparent spreadsheet models● Low cost applications, uses data required for economic analysis
of projects (not data intensive)● Results of TEEMP evaluation can help facilitate reasonable
direction for action and alternate options● Used by ADB, GEF, World Bank, GIZ, CTF, IADB, MOUD etc.
Technical Support –Clean Air Asia, ITDP
Technical Support -Clean AirAsia, ITDP and Cambridge
Systematics
First Generation TEEMPModels
Second GenerationTEEMP Models
Financial Support – ADBApplication - ADB
Financial Support – UNEP-GEF, Climate Works
Financial Support – ADB,IGES
and ITDPApplication – WB
2009
2010
Chronology of TEEMP development
ADB EvaluationReport
ADB EvaluationReport
GEF ApprovedGEF ApprovedClean Air Asia and ITDP
Clean Air Asia and ITDP
Third GenerationTEEMP Models
Financial Support – ADB,IGES
and ITDPApplication – WB
Financial Support – VeoliaEnvironment Institute
TEEMP City
2010, 2011
2012
TRAM
Clean Air Asia and ITDP Financial Support –UN-Habitat
2013
GEF ApprovedGEF Approved
Co-benefitsCo-benefits
Integrated CityApproach
Integrated CityApproach
Measuring using ASIF Framework
Avoid
Shift
Improve
Finance
Transport Plan & Project Emission Evaluation
TEEMPTEEMP
Source: Elizabeth Goller & John Rogers, Transport and Activity Measurement Toolkit, World Bank, 2011
TEEMPTEEMP
“tailor the tools developed to the needs of the various audiences and understand therelationship between costs of estimating GHG and criteria pollutant emissions andcertainty levels.”
TEEMP Applications
Business as Usual
Highway
Introduction to TEEMP:BAU vs Interventions
ORIGIN DESTINATIONBRT
Metro
Highway
City
NMT
Introduction to TEEMP: Emission Savings
No ProjectScenario(BAU)
ProjectScenario(Intervention)
Emis
sion
s( C
O2,
PM
and
NO
x)
Emissionssavings fromproject Project
Scenario(Intervention)
Emis
sion
s( C
O2,
PM
and
NO
x)
Time
Emissionssavings fromproject
Construction emissions
Operating emissionsfrom motorized vehiclesin the identified scope
Introduction to TEEMP: Tools
Roads Projects – Expressways, Rural Roads and Urban Roads
Introduction to TEEMP: Tools
Bikeway Projects and Bike sharing Scheme
Introduction to TEEMP: Tools
Bus Rapid Transit Projects
Introduction to TEEMP: Tools
Times of India - 16 Apr 2010Walkability Improvement Projects
http://timesofindia.indiatimes.com/articleshowpics/2670814.cms
Introduction to TEEMP: Tools
Metro, LRT and Intercity Railway Projects
http://timesofindia.indiatimes.com/articleshowpics/5619485.cms
Introduction to TEEMP: Tools
http://timesofindia.indiatimes.com/articleshowpics/3148432.cms
http://timesofindia.indiatimes.com/articleshowpics/3844315.cms
TDM Strategies- Commuter Strategies, Pricing Strategies, Eco-Driving , PAYDInsurance
Introduction to TEEMP: Tools
TEEMP City and TRAM - MobilityPlans/ Low Carbon Transport Plans/Master Plans/ Comprehensive trafficand transportation study/Low costoptions for accurate data collection
TEEMP City and TRAM - MobilityPlans/ Low Carbon Transport Plans/Master Plans/ Comprehensive trafficand transportation study/Low costoptions for accurate data collection
Introduction to TEEMP: methodologyfeatures
1. With and without project cases2. Sketch and detailed analysis *3. Scorecard to see the impact of design – good vs bad*
(BRT/Bikeway)4. Emissions from construction and operations5. Dynamic baseline is considered6. Automatic definition of impact boundaries7. Quantification of CO2, PM ,NOx emissions, Fatality savings,
Fuel savings, travel time savings etc. *8. Tools are excel based spreadsheets with simple input/output
tables9. Default values are provided10. Can calculate total footprint and savings from BAU
1. With and without project cases2. Sketch and detailed analysis *3. Scorecard to see the impact of design – good vs bad*
(BRT/Bikeway)4. Emissions from construction and operations5. Dynamic baseline is considered6. Automatic definition of impact boundaries7. Quantification of CO2, PM ,NOx emissions, Fatality savings,
Fuel savings, travel time savings etc. *8. Tools are excel based spreadsheets with simple input/output
tables9. Default values are provided10. Can calculate total footprint and savings from BAU
Data Requirements
1. Basic Project related information2. Activity and Structure - Traffic data – baseline traffic volumes,
trip lengths, traffic composition, occupancy, induced traffic ,speed , fuel split of vehicles (with projections)
3. Intensity – Fuel efficiency of vehicles at 50kmph/ideal4. Construction materials - cement, steel, and bitumen5. Electricity consumed6. CO2 (kg/unit) - Gasoline, Diesel, LPG, electric etc.7. For PM and NOX – technology split of vehicles and PM and
NOx emission factors8. Proposed project design details
1. Basic Project related information2. Activity and Structure - Traffic data – baseline traffic volumes,
trip lengths, traffic composition, occupancy, induced traffic ,speed , fuel split of vehicles (with projections)
3. Intensity – Fuel efficiency of vehicles at 50kmph/ideal4. Construction materials - cement, steel, and bitumen5. Electricity consumed6. CO2 (kg/unit) - Gasoline, Diesel, LPG, electric etc.7. For PM and NOX – technology split of vehicles and PM and
NOx emission factors8. Proposed project design details
Data Availability
1. Number of lanes existing and proposed for roads/BRT system and lengthof road/MRT line - Available
2. Ridership/Traffic projections - Available3. Induced traffic – Not Available4. Mode shift projections - Limited5. Fuel Efficiency – Not Available6. Average Mode speed (projections) - Limited7. Average trip lengths (projections) - Limited8. Occupancy/Loading - Limited9. Construction materials – Not Available10.Annual improvement in fuel economy – Not Available11.Vehicle fuel and technology split (projections) – Not Available12.Emission factors – Not Available13.Electricity consumption by MRT - Available14.Project Design details - Available15.Landuse impact – Not Available
1. Number of lanes existing and proposed for roads/BRT system and lengthof road/MRT line - Available
2. Ridership/Traffic projections - Available3. Induced traffic – Not Available4. Mode shift projections - Limited5. Fuel Efficiency – Not Available6. Average Mode speed (projections) - Limited7. Average trip lengths (projections) - Limited8. Occupancy/Loading - Limited9. Construction materials – Not Available10.Annual improvement in fuel economy – Not Available11.Vehicle fuel and technology split (projections) – Not Available12.Emission factors – Not Available13.Electricity consumption by MRT - Available14.Project Design details - Available15.Landuse impact – Not Available
Source : CAA and ADB Evaluation Department
Insights from TEEMP Project Applications
Example - Impact of Speed
40
50
60
70
Incr
ease
in e
mis
sion
fact
or (%
g/Km
)as
sum
ing
50 k
mph
as 0
Savings – Emission, Fuel andTravel Time
Increase – AccidentFatalities
Savings –Travel TimeIncrease – Fuel,Accidents and
Emissions
-10
0
10
20
30
15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95
Incr
ease
in e
mis
sion
fact
or (%
g/Km
)as
sum
ing
50 k
mph
as 0
Savings –Travel TimeIncrease – Fuel,
Accidents and Emissions
Source : Sudhir Gota
Traffic Projections may not be realistic
0.400.600.801.001.201.401.601.80 Actual/Forecast Ratio
0.000.200.40
Man
ila L
RT 3
KL P
UTR
A
HK A
irpor
t
Pusa
n
Bang
kok
(gre
en)
Bang
kok
Blue
Shan
ghai
Line
1
Shan
ghai
Line
2
Shan
ghai
Line
3
Shan
ghai
Line
5
Beiji
ng Li
ne 1
3
Beiji
ng B
aton
g Li
ne
Beiji
ng Li
ne 5
Guan
gzho
u Li
ne 1
Nan
jing
Line
1
Shen
zhen
Firs
t Pha
se
Tian
jin B
inha
i Lin
e
Delh
i Pha
se-I
Source : Phil. Sayeg+ Sam Zimmerman + Sudhir Gota
Build Scenarios (compare demand in similar corridor) and use of ramp-up factors
-4000-2000
02000400060008000
100001200014000
CO2 saved (20 years) withconstruction
CO2 saved (10 years) withconstruction
Tons
/Yea
r/km
Impact of Project Life on Emissions
Analysis for 20 Years of Lifecycle
-4000-2000
02000400060008000
100001200014000
CO2 saved (20 years) withconstruction
CO2 saved (10 years) withconstruction
Tons
/Yea
r/km
Impact of Project Life on Emissions
Source : CAA and ADB Evaluation Department
Metro –Electricity Consumption
Neglecting landuse impact
Both traction andnon traction
Only tractionenergy
Savings from Modeshift (tons) 4569366 8681796
Construction Emissions (tons) 685707 685707
Emissions from Electricity Use (tons) 2389865 1162945Emissions from Electricity Use (tons) 2389865 1162945
Carbon footprint (million tons) 3.08 1.85
Total CO2 saved (20 years) (tons) 1493795 6833145
CO2 savings tons/km 34105 156008
CO2 savings tons/year/km 1705 7800
Be careful with electricity consumption data
Source : Chennai Metro Analysis ( Sudhir Gota)
Construction emissions
30%40%50%60%70%80%90%
100% CO2 Footprint(Tons/km/Year)Operation
CO2 Footprint(Tons/km/Year)Construction
0%10%20%30%
Surat Manor
Salem-Karur
VietNam
Belgaum Dharw
ad
Bangalore Metro
Manila LRT-1 N
orthExtension
Marikina GEF
Almaty–Kaskelen
Laos Rural AccessRoad
Railways-VietN
am
HighwaysMetro
RuralRoads
CDM methodology NM0266 neglects construction emissions from MRT
Source : CAA and ADB Evaluation Department
Construction Emissions
1 km of infrastructure Description tons of CO2
BRTS Considering only the quantity of steel,cement and asphalt.
1900
Bikeways Considering only the quantity of steel,cement and asphalt.
20
MRTS 2 lines for 80% elevated and 20%underground
15600MRTS 2 lines for 80% elevated and 20%underground
15600
Railways Considering only the quantity of steel andconcrete for single track
875
Roads Considering only the quantity of steel,cement and asphalt for a four lane road
2100
Source : CAA and ADB Evaluation Department
Lifecycle Emissions
30%
40%
50%
60%
70%
80%
90%
100%
Fuel Production
Operation and Maintainance
Manufacture
0%
10%
20%
30%
Sedans SUVs Bus Sedans SUVs Bus
GHG mt GGE PM10 (kg)
Per Vehicle Life
Manufacture
Road Construction andMaintainance
Limitation - TEEMP does not consider road construction impacts on air pollution
Source - Mikhail Chester
Mode shift data can be borrowed
Mode Shifts towards Bike Sharing Schemes Around the World
Mode shiftfrom (%)
Hangzhou Shanghai Beijing Paris Barcelona Lyon London DefaultValues
Pedestrian 16 26 23 20 26 37 21 22
Bus 51 40 48 65 51 50 34 46Bus 51 40 48 65 51 50 34 46
Taxi 4 4 3 5 4
Car 4 4 58 10 7 6
4
E Bike/Motorcycle 4 5 3 4
Private Bicycle 8 14 8 4 6 10
Others/No Trip 13 7 10 2 23 10
Source : Various studies
Impact of Bike sharing Scheme - CO2(Tons/Year)
Number of trips per bike per day1 2 4 6 8 12 16
Num
ber o
fBik
es
10 0.34 0.68 1.36 2.04 2.72 4.07 520 0.68 1.36 2.72 4.07 5.43 8.15 1130 1 2 4 6 8 12.22 1640 1 3 5 8 11 16.29 22
Num
ber o
fBik
es 40 1 3 5 8 11 16.29 2250 2 3 7 10 14 20.36 27
100 3 7 14 20 27 40.73 54500 17 34 68 102 136 203 271
1000 34 68 136 204 271 407 5435000 169 339 679 1018 1357 2036 2715
10,000 339 678 1357 2036 2715 4072 543020,000 678 1357 2715 4072 5430 8145 1086050,000 1697 3394 6787 10181 13575 20362 27150
Source : Sudhir Gota
Quiz
Scenario-IIn total Vehicle fleet 1 milliontrucks were not considered
Scenario-IIIn total Vehicle fleet 20
million two wheelers and 5million Cars were not
considered
Both scenarios are not ideal but which one would yield comparatively betterresults?
30
40
50
60
70
80
90
100
Impa
ct A
ssum
ing
MC
as 1
Multiplication Effect of Activity & Intensity (A*I)
0
10
20
30
PC Taxi HDT MDT LDT Mini T(G)
HDB LDB MC
Impa
ct A
ssum
ing
MC
as 1
Trucks and Buses have poor fuel efficiency and they travel more. So impactin fuel consumption is higher. Bus in terms of activity and intensity isequivalent to 90 two-wheelers. So focus more on getting best data for heavyvehicles. Source : Sudhir Gota
Use Dynamic Baselines
Emissions Are Not Static (+ more savings)
Travel activity trends (+)Mode share trends (+)Changing vehicle occupancy (+)Changing vehicle economy (-)Changing vehicle fuels (-)Changing vehicle emissionstandards (-)
2500
3000
3500
4000
CO2
save
d (t
ons/
km/y
ear)
Constant Mode Share
Motorization Scenario Emissions Are Not Static (+ more savings)
Travel activity trends (+)Mode share trends (+)Changing vehicle occupancy (+)Changing vehicle economy (-)Changing vehicle fuels (-)Changing vehicle emissionstandards (-)
0
500
1000
1500
2000
100% scenario 80% scenario 50% scenario
CO2
save
d (t
ons/
km/y
ear)
Source : Sudhir Gota
Contradiction ?
TransMilenio Phase II to IV
Monitoring 2006 Monitoring 2008 Monitoring 2009 Monitoring 2010
Actual Expected Actual Expected Actual Expected Actual ExpectedPassengers transported byproject (million)
94 147 118 356 134 478 149 478
Share of passengers whichwould have used passengercars (%)
Share of passengers whichwould have used passengercars (%)
4.3 5.5 2.4 5.5 2.1 5.5 2.6 5.5
Share of passengers whichwould have used taxis (%)
5.5 5.6 5.5 5.6 4.8 5.6 5 5.6
Share of passengers whichwould have used buses (%)
89.1 88 91.4 88 92.5 88 91.6 88
Share of passengers whichwould have used NMT or notmade the trip (%)
1.1 0.8 0.7 0.8 0.6 0.8 0.7 0.8
Emission reductions -40% -70% -74% -74%BRT Bogotá, Colombia: TransMilenio Phase II To IV (monitoring report 2010)
Contradiction ??
11.5%VEHICLES
(ASIA)
10.1%CO2
ROADTRANSPORT
(ASIA)
9.8%FUEL
(ASIA)
11.5%VEHICLES
(ASIA)
10.1%CO2
ROADTRANSPORT
(ASIA)
8%GDP
Emission Reduction = baseline emissions – project scenario emissions – leakageemissions
In leakage –1. Changes of the load factor2. “Emissions due to reduced congestion on affected roads, provoking higher
average vehicle speed, plus a rebound effect”3. Construction emissions4. “Emissions due to scrapping vehicles which would otherwise have continued
to operate.”
CDM – Baseline and Leakages
In leakage –1. Changes of the load factor2. “Emissions due to reduced congestion on affected roads, provoking higher
average vehicle speed, plus a rebound effect”3. Construction emissions4. “Emissions due to scrapping vehicles which would otherwise have continued
to operate.”
How will people travel without project?
73579081
10000
15000
20000
25000
LanekmVKM (Million)
Singapore
0
5000
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
VKM (Million)
In Cebu BRT - If BRT is not implemented, roads need to be widened to accommodatetraffic – more than 320 Million USD of investment is required to build 10 more lanes
In Cebu BRT - If BRT is not implemented, roads need to be widened to accommodatetraffic – more than 320 Million USD of investment is required to build 10 more lanes
NEVER CONSIDERED IN ECONOMIC ANALYSISSource : Sudhir Gota
Fuel and Vehicle Technology split
Borrow from the city or country dataBorrow from the city or country data
Impact of Design
85 or above 70-84 55-69
ITDP BRT Standard 2013
1. Service Planning2. Infrastructure3. Station Design and Station-Bus Interface4. Quality of Service and Passenger information Systems5. Integration and AccessBRT is evaluated and calculated score is used as a bonus weight for
ridership increaseExample - Integration and access is 14 points
85 or above 70-84 55-69
Sensitivity of ASIF variables
10 10
-9 -9-14
2
0
5 912 12
-19-11
-2 -1
10
23
BRT Metro
-19-29
10%
Incr
ease
in R
ider
ship
10%
Incr
ease
in T
riple
ngth
of a
ll m
odes
10%
incr
ease
in F
uel
Effic
ienc
y of
all
mod
es
10%
incr
ease
inO
ccup
ancy
of a
ll m
odes
10%
Incr
ease
in S
peed
of
all m
odes
10%
Incr
ease
in B
RTDe
sign
fact
or/M
etro
Ram
p U
p Fa
ctor
for…
10%
incr
ease
in q
uant
ityof
cons
truc
tion
mat
eria
ls
10%
incr
ease
in c
ar m
ode
shift
from
PT
10%
cha
nge
in c
arbo
nem
issio
n fa
ctor
for f
uel
Sensitivity of ASIF variables in a BRT and Metro Project ( % Change in Tons/km/year)Source : Sudhir Gota
Example on Methodologies-Guangzhou BRT
Method CO2/Year
Percent Error(according to
adhoc)Time toestimate
DataIntensity Cost ($)
Guangzhou, China opened its first, 22.5-kilometer Bus Rapid Transit corridor in 2010 in an effortto cut congestion on one of the city’s busiest roads, Zhongshan Avenue, and to improve theefficiency of the city’s bus system. The system now has 805,000 daily boardings.
47
Method CO2/Year
Percent Error(according to
adhoc)Time toestimate
DataIntensity Cost ($)
TEEMP Sketch - KM based 44,000 118% Minutes Very Low 0
TEEMP Sketch - Pax based 244,000 61% Minutes Low 0
TEEMP Detailed Model 130,000 26% 5 Days max Medium <2000
Detailed Ad Hoc 96,000 ? Month High ~15000
CDM* ? 74% Months/Years Very High >500,000
Source – based on ITDP Guangzhou BRT analysis and CDM Monitoring reports for TransMilenio Phase II To IV.
● ADB transport loans & grants approved 2000–2009● Analysis of project emissions over a 20-year life● Gross carbon emissions from construction & operations of
ADB-funded transport projects estimated at 792 million tons:• Average 39.6 million tons/year• About equal to transport sector emissions of Thailand or Philippines
● CO2 impact would have been cut by ¼ if half of funding thatwent to motorway projects had instead funded roadrehabilitation, BRT, NMT projects
TEEMP Used to Estimate ADB TransportProgram Impacts
● ADB transport loans & grants approved 2000–2009● Analysis of project emissions over a 20-year life● Gross carbon emissions from construction & operations of
ADB-funded transport projects estimated at 792 million tons:• Average 39.6 million tons/year• About equal to transport sector emissions of Thailand or Philippines
● CO2 impact would have been cut by ¼ if half of funding thatwent to motorway projects had instead funded roadrehabilitation, BRT, NMT projects
48
Source: ADB. 2010. Reducing Carbon Emissionsfrom Transport Projects
Indicators ( based on TEEMPapplications)
DescriptionCO2 Savings Indicator
(ton per unit) unit
Expressway -700 ton/km/yearBikeway 250 ton/km/year
Rural Road (capacity) 0 ton/km/yearRural Road (Rehabilitation) 10 ton/km/yearRural Road (Rehabilitation) 10 ton/km/year
Metro/Monorail 6200 ton/km/yearBRTS 5000 ton/km/year
Railway 2900 ton/km/yearUrban Road 2 lane to 4 lane -400 ton/km/yearUrban Road 4 lane to 6 lane -200 ton/km/year
Parking 25 Tons/terminal/yearPedestrian Walkway Improvement 0.0200 ton/S investment
Bike sharing 0.17 tons/bike/yearAugmentation of Bus fleet 25 ton/bus/year
Indicators ( based on ADB applications)
CO2 Footprint(Tons/km)
CO2 Footprint(Tons/million$)
Expressway 88,000 58,667Bikeway 24 960Rural Road (capacity) 10,000 20,000Rural Road (Rehabilitation) 600 5,000Metro 24,000 686Metro 24,000 686BRTS 44,000 14,667Railway 42,000 31,111
It is important to consider all three indicators - footprint, investment and savings
Indicators ( based on ADB applications)
BAU With ProjectCO2
g/passengerkm
CO2 g/ton km
CO2g/passenger
km
CO2 g/ton km
Expressway 59 81 47 61Bikeway - - - -
Rural Road (capacity) 84 73 74 61Rural Road (capacity) 84 73 74 61Rural Road (Rehabilitation) 149 199 55 68
Metro 137 38BRTS 137 28
Railway 20 23
Note - with transport interventions, emissions per passengers/ton decrease…
CO2/km +
+-
LOSERS:LOSERS:-- MoreMore congestioncongestion-- MoreMore drivingdriving
ExpresswaysExpressways
Urban Roads/InterchangesUrban Roads/Interchanges
Transport project outcomes:More or Less Carbon?
Total Veh-km
+-
-
BRTBRT
WINNERS:WINNERS:-- LessLess congestioncongestion-- LessLess drivingdriving
TDM StrategiesTDM Strategies
MetroMetro
Bikeways,Bikeways, BikeshareBikeshare,, WalkabilityWalkability Rural low speed RoadsRural low speed RoadsRehabilitation of RoadsRehabilitation of Roads
Urban Roads/InterchangesUrban Roads/Interchanges
BusBusRailwaysRailways
Source : Sudhir Gota
Need for TEEMP City
● Move from isolated large-scale projects to integrated transportsystems to integrated urban development
● From carbon emissions to sustainable development driven bymultiple co-benefits
● Many plans being created without adequate knowledge onemissions(CDP/CTTS/CMP)
● Need to link – Investment with projects and Cobenefits● Need for models which work with less data● future transport NAMA’s (unilateral NAMA’s & supported NAMA’s)
Integrating Projects: Taking it to scale
53
Need for TEEMP City
● Move from isolated large-scale projects to integrated transportsystems to integrated urban development
● From carbon emissions to sustainable development driven bymultiple co-benefits
● Many plans being created without adequate knowledge onemissions(CDP/CTTS/CMP)
● Need to link – Investment with projects and Cobenefits● Need for models which work with less data● future transport NAMA’s (unilateral NAMA’s & supported NAMA’s)
TEEMP City - Evaluating Impact of City Investments
• An assessment tool to provide guidance on CO2 and air pollution emissionsincluding fuel consumption and other co-benefits to policy makers whilepreparing mobility plans/low carbon transport plans.
• Bottom-up excel spreadsheet (with defaults) tool to:
1. Evaluate the impact of mobility plans/ low carbon transport plans on CO2emissions
2. Quantify the cobenefits of implementing such transport plan ( fuelconsumption, air pollution, safety benefits and travel time savings)
3. Assess the adequacy, comprehensiveness and governance related issueswith respect to the mobility plan proposal /implementation and possibleimpact of such a measure.
4. Provide guidance on investment packages i.e. shift in investment patternimpact, increasing/decreasing the investment impact/ changing theproposal schedule etc.
54
• An assessment tool to provide guidance on CO2 and air pollution emissionsincluding fuel consumption and other co-benefits to policy makers whilepreparing mobility plans/low carbon transport plans.
• Bottom-up excel spreadsheet (with defaults) tool to:
1. Evaluate the impact of mobility plans/ low carbon transport plans on CO2emissions
2. Quantify the cobenefits of implementing such transport plan ( fuelconsumption, air pollution, safety benefits and travel time savings)
3. Assess the adequacy, comprehensiveness and governance related issueswith respect to the mobility plan proposal /implementation and possibleimpact of such a measure.
4. Provide guidance on investment packages i.e. shift in investment patternimpact, increasing/decreasing the investment impact/ changing theproposal schedule etc.
City level Estimates - Plans andProposals ( Bangalore CTTS)
Description Intensity Year ofImplementation
Augmentation ofbus fleet 2500 Bus 2007-2012
BRTS 156 Km 2007-2012
Metro/monorail 130 Km 2007-2012
Pedestrian walkwayimprovement
Remarks
Partly (due to JNNURM)
Not yet
Only 7.5 km under operation
Reasons - due to lack of investment, lack of political willingness, lack of institutional capacity, poorscheduling of projects, not comprehensive and lack of support from stakeholders
Pedestrian walkwayimprovement 56200000 $ investment 2007-2012
Urban road 2 laneto 4 lane 443 Km 2007-2012
New roads 4 lane Km 2007-2012Urban road 4 lane
to 6 lane 272 Km 2007-2012
Parking 17 parking terminal 2007-2012
Truck terminals 27000000 $ investment 2007-2012Railway 46 Km 2007-2012
Minimal investment
Partly done
Partly done
Partly done
Only few
partlyNot yet
Source : Sudhir Gota
City level Estimates
Savings (over twenty years)High Low
VKT (million) 40868 19208CO2 (million tons) 36 17
PM (tons) 1451 682NOx (tons) 4938 2321Fatalities 5198 2443Fatalities 5198 2443Injuries 77967 36644
Hours (million) 9836 4623Petrol-million liter 5524 2596Diesel-million liter 9795 4604
TEEMP City model application to Jaipur Comprehensive Mobility Plan.
A scorecard is used to evaluate the mobility plan - a set of 27 parameters are evaluated. Thisscorecard i.e. Low scenario accounts for delay in implementation due to lack of commitment/ support /quality etc.
TEEMP City Excel Tool Screenshot
57
TEEMP City Results
58
CO2, PM, NOx
Time travel savings and other co-benefits – fatalities, injuries
The Bank has worked closely with the GEF Secretariat, STAP and ADB to develop andadopt a methodology that overcomes this impasse both in terms of ex ante (proposalstage) estimates and ex post (results stage) assessments. The Bank is especiallycommitted to following through on the application of this consistent methodology in itscurrent cohort of projects of over 30 medium size cities in developing countries. –World Bank (Building an Effective Knowledge Base - The smart road to sustainabletransport)
TEEMP Further Support
Tools currently available to support GHG evaluation include sketch tools, advancedtravel demand forecasting and simulation models, and emission factor models. Due todata limitations, it will often be necessary to use sketch level tools such as TEEMP,or ad-hoc methods developed by the project sponsor using available data. Theaccuracy of these methods can be improved over time as additional local datais collected. – IADB (Mitigation Strategies and Accounting Methods for GreenhouseGas Emissions from Transportation)
TEEMP Limitations
1. Needs “live” applications and a mechanism to improve the defaults andthe sketch analysis ( ex Bike/Walk scorecard) – need to train model withgood data
2. TEEMP is still perceived as a “complicated tool”
3. Benefits such as “Value of travel time”, “fuel savings” and “Accidentsavings” and “economic analysis” are still not included in some models
4. Needs good data for reliable estimates
5. TEEMP does not include “freight”
6. TEEMP can be easily “manipulated” to provide “desired” results
7. Needs to quantify – employment, health benefits etc.
8. Defaults improvement is a continuous process
1. Needs “live” applications and a mechanism to improve the defaults andthe sketch analysis ( ex Bike/Walk scorecard) – need to train model withgood data
2. TEEMP is still perceived as a “complicated tool”
3. Benefits such as “Value of travel time”, “fuel savings” and “Accidentsavings” and “economic analysis” are still not included in some models
4. Needs good data for reliable estimates
5. TEEMP does not include “freight”
6. TEEMP can be easily “manipulated” to provide “desired” results
7. Needs to quantify – employment, health benefits etc.
8. Defaults improvement is a continuous process
[email protected] 3505 Robinsons Equitable Tower
ADB Avenue, Pasig CityMetro Manila 1605
Philippines
Clean Air Asia Center
[email protected] Reignwood Building,
No. 8 YongAnDongLiJianguomenwai Avenue Beijing
China
Clean Air Asia China [email protected] Floor, Building No. 4
Thyagraj Nagar Market, Lodhi ColonyNew Delhi 110003
India
Clean Air Asia India Office
For more information: www.cleanairasia.orgFor more information: www.cleanairasia.orgFor more information: www.cleanairasia.org
China . India . Indonesia . Nepal . Pakistan . Philippines . Sri Lanka . Vietnam
[email protected] Reignwood Building,
No. 8 YongAnDongLiJianguomenwai Avenue Beijing
China
[email protected] Floor, Building No. 4
Thyagraj Nagar Market, Lodhi ColonyNew Delhi 110003
India
Clean Air Asia Country Networks
61
Clean Air AsiaCenter Members
•Shell•Asia Clean FuelsAssociation•Corning
240 Clean Air AsiaPartnership Members
• Cities• Environment ministries and government
agencies• Development agencies and foundations• Non-government organizations• Academic and research institutions• Private sector companies and associations
Donors in 2012 to 2013Asian Development Bank Cities Development Initiative for Asia ClimateWorks Foundation DHL/IKEA/UPS Energy Foundation Fredskorpset Norway Fu Tak Iam Foundation German International Cooperation (GIZ) Institute for Global Environmental Strategies(IGES) Institute for Transport Policy Studies Institute for Transportation and DevelopmentPolicy International Union for Conservation of Nature L'Agence Française deDéveloppement (AFD) MAHA Pilipinas Shell Rockefeller Brothers Fund ShaktiFoundation Shell Foundation United Nations Environment Program Partnership for CleanFuels and Vehicles (UNEP PCFV) USAID CEnergy Veolia World Bank
Thanks Lee
BRTS
Bikeways
Walkability
Roads
Select type of project e.g. expressway, ruralroads including village roads, and urban roads
Input roughness, local traffic details andvehicle split w.r.t. fuel and emission standard,average fuel efficiency at 50kmph, occupancyand loading and other ASIF parameters
The model conducts capacity analysis andderives annual speed based on V/C ratio and
saturation limits
Using the speed, the model calibrates the fuelefficiency and emission factors
Input roughness, local traffic details andvehicle split w.r.t. fuel and emission standard,average fuel efficiency at 50kmph, occupancyand loading and other ASIF parameters
Input induced traffic elasticity with lane miles,V/C saturation limits, PCU values and Capacity
Input or modify default speed-flow values
Using the speed, the model calibrates the fuelefficiency and emission factors
Input Amount of materials consumed/km oruse defaults to calculate construction emissions
The model calculates both capacity expansionimpact and/or roughness improvement impact
Output – CO2, PM and NOx