transmission duong pardo & elmore 500kv bf protection

Upload: castrojp

Post on 03-Jun-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    1/27

    1

    500kV IPT

    Breaker Failure Protection65 th Annual TAMU Protective Relay Conference

    April 2 nd , 2012

    Vinh Duong, P. E., PMP ABBJorge L. Pardo, P. E. Progress Energy

    John Elmore Power Grid Eng.

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    2/27

    Road Map for the Paper

    Introduction Who We Are, What We DoExisting System ConfigurationBrief Overview of Breaker Failure Protection

    Need for ImprovementNew Application ConceptConclusions, Where We Go Next

    2

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    3/27

    Who We Are, What We Do3

    Progress Energy (March 2012)Utility company head quartered in Raleigh, NCListed in NYSE: PGNTwo operating entities: The Carolinas (PEC) and Florida (PEF)Serves 3.1 millions electric customers22,000 MW of regulated electric generating capacity

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    4/27

    PEF System Configuration

    4700 miles of transmission lines including 69kV,115kV, 230kV and 500kVOne nuclear generating site of 860 MW in westernFlorida Additional 13,000 MW from coal, combustion, andoil plants throughout the territory

    Five 500kV-230kV substation sites

    4

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    5/27

    500kV Transmission Syst. Protection5

    Transmission Lines: Three redundant high-speedpilot schemes Communication means including self-healing multiplexor over

    fiber optic network, power line carrier and micro-wave Autotransformers and Substation Buses: Dual

    redundant protection packages A dedicated breaker failure protection package

    (separate from other relay & control functions) Redundant battery systems with dedicated station

    DC load centers

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    6/27

    The Art of Line Protection

    To detect transmission line faults andinitiate isolation of that fault on the linesegment with minimal impact to the rest

    of the transmission system and to thecustomer.

    Do it by isolating the minimum faultedsection in the quickest time.

    6

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    7/27

    Typical 500kV Protection System7

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    8/27

    Breaker Failure Protection Scheme

    Expand the clearing area for faults due to breakermis-operation (stuck breaker)Time delayed operation initiated by all trippingrelays using breaker as clearing pointTime coordinated to allow primary zone clearing but faster than other backup functions in order toavoid system instability conditions

    8

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    9/27

    Typical BF Protection Logic9

    BF Scheme Needs:BFI input from protection relaysFault detector setting

    (*Transformer fault detector if necessary)

    BF timer setting

    OR AND

    TIMER62-1

    Breaker FailureScheme Output

    50FD87T*

    BFI

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    10/27

    Typical BF Timing10

    Not a problem if the total fault clearing time is 12+cycles

    The total fault clearing time shall not be longer thanthe system critical clearing time

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    11/27

    Line Relay Zones11

    instantaneousBlocked

    Blocked

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    12/27

    Typical Transmission Line12

    t1 time zerot2 relay operate time (1/2 to 3 cycles)

    t3 carrier start (immediate)t4 remote carrier received (channel time)t5 trip initiated from relayt6 breaker opens (2-4 cycle mechanical operate times)t7 breaker failure trip (20 cy from trip initiate)

    t8 - Zone 2 trip (30 cy) & t9 - Zone 3 trip (90cy)

    t1 t2 t3 t4 t5 t6 t7 t8 t9

    strike detect

    startreceive

    Trip

    Zone 3

    Zone 2

    BFoperate

    breaker

    opentimeline

    action

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    13/27

    The Need

    With addition of 2 nd nuclear site and expansion of500kV network, the recommended critical clearingtime would be:

    5.5 cycles for multi-phase fault8.0 cycles for single-phase fault

    Need faster reset times for BF schemes to avoidovertrip

    Use of IPT (Independent Pole Trip) breakers

    13

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    14/27

    Can the new scheme Meet the Need?

    14

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    15/27

    Considerations

    Relay operating time: 2 cyclesFailed breaker operating time: 2 cyclesRelay 50BF reset time: 1 cycle

    BF timer safety margin: 2 cyclesLocal and remote contributing breaker operating time: 2 cyclesDTT channel time: 0.5 cyclesTotal BF times = Critical clearing: 9.5 cycles

    15

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    16/27

    Latency16

    Just how fast must it be?

    < 6 ms

    Telecom Delivers the Message

    < 6 milliseconds

    Relay/Protection Executes the Action

    < 10 milliseconds

    Total Time to React< 1 Cycle ~ 16 milliseconds

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    17/27

    What system or relays are available?

    Line, auto, and bus differential protection relays to be sub-cycle type

    Directly tripping breaker(s) and issuing BFIEliminate auxiliary/tripping relays from the circuitReplace PLC, lease line, and micro-wave with dedicate fiberoptic cable or fiber optic based multiplexor

    17

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    18/27

    Breaker Failure Protection Relay18

    BF protection relay to be sub-cycle typeDirectly tripping breakers and DTT

    Re-sequence the BF logic to discount fault detector

    reset time Allow the BF timer to time out first

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    19/27

    BF Timing Improvement19

    Relay operating time: 1 cycles

    Failed breaker operating time: 2 cycles

    Relay 50BF reset time: 1 cycle

    BF timer safety margin: 2 cycles

    Local and remote contributing

    breaker operating time: 2 cycles

    DTT channel time: 0.5 cycles

    Total BF times = Critical clearing: 7.5 cycles

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    20/27

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    21/27

    Issues with IPT Breakers21

    Low SF6 Gas:Slow leakage to critically low => breaker opens and block closeFast leakage to critically low => breaker block operation andlock into its current position => all three poles inoperable

    Loss of Spring Charge:Sudden loss of spring charge => breaker block operation andlock into its current position => all three poles inoperable

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    22/27

    The Solution22

    Implement dual BF timer scheme with IPT breakerTypical time = 8.0 cycles for single-phase fault

    One IPT pole failsShort time = 5.5 cycles for multi-phase fault

    Two or three IPT pole failsBF relay armed to bypass the failed breaker and directly trips thelocal and remote contributing breakers

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    23/27

    Summary

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    24/27

    Multi-Phase Fault BF Time24

    Relay operating time: 1 cycles

    Failed breaker operating time: 2 cycles

    BF timer safety margin: 0 cyclesLocal and remote contributing

    breaker operating time: 2 cycles

    DTT channel time: 0.5 cycles

    Total BF times = Critical clearing: 5.5 cycles

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    25/27

    BF Time with Bypass Logic25

    Relay operating time: 1 cycles

    Failed breaker operating time: 2 cycles

    BF timer safety margin: 0 cyclesLocal and remote contributing

    breaker operating time: 2 cycles

    DTT channel time: 0.5 cycles

    Total BF times = Critical clearing: 3.5 cycles

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    26/27

    Where Do We Go Next26

    Consider its expanded use where criticalclearing time margins are becoming morecritical

    Continue to expand our fiber network toprovide communications assisted relayingand BF-DTTLook into peer to peer communication

    network among IEDs in the substation to cutdown IED contact operating time and wiring

  • 8/12/2019 Transmission Duong Pardo & Elmore 500kV BF Protection

    27/27

    Questions?

    27