transformer sizing presentation.pdf

Upload: rjcm

Post on 01-Jun-2018

267 views

Category:

Documents


7 download

TRANSCRIPT

  • 8/9/2019 Transformer Sizing Presentation.pdf

    1/54

    2013 ElectriCitiesElectric Utility

    Webinar Series

    Sizing of

    Transformers

    Calculationof Loads

  • 8/9/2019 Transformer Sizing Presentation.pdf

    2/54

    Demand and Demand Factor

    Demand The value of electrical power required for a

    particular load. Expressed in kW.

    Usually averaged over a 15-minute or 30-minute period for billing

    purposes.

    Peak Demand The maximum Demand of the whole

    system at any one time.

  • 8/9/2019 Transformer Sizing Presentation.pdf

    3/54

    Demand and Demand Factor

    Demand Factor The Peak Demand of the whole

    system compared to the connected Demand of thesystem.

    Expressed as a percentage or a ratio less than 1.

  • 8/9/2019 Transformer Sizing Presentation.pdf

    4/54

    Demand and Demand Factor

    Example - Average Home

    Typical Electrical Loads:

    Water Heater 4,500 watts (4.5 kW)

    Range / Oven 8,000 watts (8.0 kW)

    Central Air Conditioner 6,000 watts (6.0 kW)

    Clothes Dryer 5,000 watts (5.0 kW)

    Dishwasher 2,000 watts (2.0 kW) Lighting, Fans, Appliances, Other 7,500 watts (7.5 kW)

    Connected Demand = 33 kW

    Peak Demand = 18 kW

    Demand Factor = 18 kW / 33 kW = 0.545

  • 8/9/2019 Transformer Sizing Presentation.pdf

    5/54

    Residential Transformer Loading

    Diversity Method

    Information Required

    Average Square Footage of the Homes

    Number of Homes with Gas and Electric Heat

    Information from Tables Peak kW Demand for the size of the home.

    Add all of the Peak Demands for the number of homes connected to thetransformer.

    Apply the appropriate Diversity Factor to the connected Peak Demand

    for the number of homes. Use the calculated Demand to determine the size of the transformer

    based on the Maximum kVA Loading.

  • 8/9/2019 Transformer Sizing Presentation.pdf

    6/54

    Residential Transformer Loading

  • 8/9/2019 Transformer Sizing Presentation.pdf

    7/54

    Residential Transformer Loading

    Example Diversity Method

    5 Homes - All Electric; between 1,500 and 1,800 square feet.

    Step 1 Determine the Connected Peak kW for each home.

    Electric

    Summer

    Electric

    Winter

    Gas

    Summer

    Gas

    Winter

    kW for 1,200 s.f. 13 15 8 8

    kW for 1,500 s.f. 15 18 10 10

    kW for 1,800 s.f. 16 20 11 11

    kW for 2,400 s.f. 18 21 12 11

    kW for 3,000 s.f. 21 26 14 11

  • 8/9/2019 Transformer Sizing Presentation.pdf

    8/54

    Residential Transformer Loading

    Example Diversity Method

    Peak kW per Home = 20 kW winter; 16 kW summer

    Step 2 Add the Peak Demands for all of the homes.

    20 kW x 5 homes = 100 kW Winter Peak Demand

    16 kW x 5 homes = 80 kW Summer Peak Demand

    Step 3 Apply the Diversity Factor to the Connected Peak Demand.

    Number of Customers 1 2 3 4 5 6 7 8 9 10

    Diversity Factor 100% 90% 75% 65% 63% 62% 61% 61% 61% 61%

    Number of Customers 11 12 13 14 15 16 17 18 19 20

    Diversity Factor 60% 59% 58% 58% 57% 57% 56% 54% 54% 54%

  • 8/9/2019 Transformer Sizing Presentation.pdf

    9/54

    Residential Transformer Loading

    Example Diversity Method

    Diversity Factor for 5 homes = 63%

    Step 4 Calculate the Peak Load on the Transformer.

    100 kW x 63% = 63 kW; 80 kW x 63% = 51 kW

    Step 5 Determine the Transformer Size based on the Maximum kVA

    Loading Table.

    Transformer

    Size

    Summer

    140%

    Winter

    160%

    Transformer

    Size

    Summer

    140%

    Winter

    160%

    10 14 16 50 70 80

    15 21 24 75 105 120

    25 35 40 100 140 160

    37.5 53 60 167 234 267

  • 8/9/2019 Transformer Sizing Presentation.pdf

    10/54

    Residential Transformer Loading

    Example Diversity Method

    Step 4 Calculate the Peak Load on the Transformer.

    Winter Demand = 100 kW x 63% = 63 kW

    Summer Demand = 80 kW x 63% = 51 kW

    Step 5 Determine the Transformer Size based on the Maximum kVALoading Table.

    For a 37.5 kVA Transformer:

    Winter 160% Loading = 60 kW

    Summer 140% Loading = 53 kW For a 50 kVA Transformer:

    Winter 160% Loading = 80 kW

    Summer 140% Loading = 70 kW

  • 8/9/2019 Transformer Sizing Presentation.pdf

    11/54

    Demand and Coincidence Factor

    Coincidence Factor A ratio of the average running kW

    load to the connected kW load on a utility transformer

    based on the number of customers connected to the

    transformer.

    Expressed as a percentage or a ratio less than 1.

    Usually will decrease as the number of connected customers

    increases.

    Applied by the use of tables.

  • 8/9/2019 Transformer Sizing Presentation.pdf

    12/54

    Residential Transformer Loading

    Coincidence Factor Method

    Information Required Highest Summer kWh and Winter kWh Usage (from billing records).

    Number of Homes Connected to the Transformer.

    Information from Tables

    Determine the kW Demand for the home based on kWh usage.

    Add all of the Peak Demands for the customers connected to thetransformer.

    Apply the appropriate Coincidence Factor to the connected PeakDemand.

    Use the calculated Demand to determine the size of the transformerbased on the Maximum kVA Loading.

  • 8/9/2019 Transformer Sizing Presentation.pdf

    13/54

    Residential Transformer Loading

  • 8/9/2019 Transformer Sizing Presentation.pdf

    14/54

    Residential Transformer Loading

    Example Coincidence Factor Method

    3 Homes

    Step 1 Determine the Summer and Winter Peak kWh Usage for each

    home (listed in table below)

    Summer kWh Winter kWh

    Customer # 1 2,224 853

    Customer # 2 2,734 1,274

    Customer # 3 1,849 1,283

  • 8/9/2019 Transformer Sizing Presentation.pdf

    15/54

    Residential Transformer Loading

    Example Coincidence Factor Method

    Step 2 Determine the kW Demand for each home.

    Step 3 Add the kW Demands.

    Summer Winter

    kWh kW Demand kWh kW Demand

    Customer #1 2,224 11.57 853 7.47

    Customer #2 2,734 13.16 1,274 9.97

    Customer #3 1,849 10.29 1,283 10.27

    Totals 35.0 27.7

  • 8/9/2019 Transformer Sizing Presentation.pdf

    16/54

    Residential Transformer Loading

    Example Coincidence Factor Method

    Step 3 Add the kW Demands. Summer Demand = 35.0 kW

    Winter Demand = 27.7 kW

    Step 4 Determine the Coincidence Factor for the number of customers

    from the table.

    Number of

    Customers

    Coincidence

    Factor

    1 1.00

    2 0.85

    3 0.74

    4 0.66

    5 0.61

  • 8/9/2019 Transformer Sizing Presentation.pdf

    17/54

    Summer Winter

    Coincidence

    Factor

    Total kW

    Demand

    Transformer

    kW Demand

    Coincidence

    Factor

    Total kW

    Demand

    Transformer

    kW Demand

    0.74 35.0 kW 25.9 kW 0.74 27.7 kW 20.5 kW

    Residential Transformer Loading

    Example Coincidence Factor Method

    Step 4 Determine the Coincidence Factor for the number of customersfrom the table.

    Coincidence Factor = 0.74

    Step 5 Multiply the total kW Demand by the Coincidence Factor for

    Summer and Winter loads. Summer Transformer Demand = 35.0 kW x 0.74 = 25.9 kW

    Winter Transformer Demand = 27.7 kW x 0.74 = 20.5 kW

  • 8/9/2019 Transformer Sizing Presentation.pdf

    18/54

    Residential Transformer Loading

    Example Coincidence Factor Method

    Step 6 The answer yields the peak 15-minute demand on thetransformer.

    Summer Transformer Demand = 35.0 kW x 0.74 = 25.9 kW

    Winter Transformer Demand = 27.7 kW x 0.74 = 20.5 kW

    Apply the two kW demands in step 5 to the Maximum kVA Loading table for

    transformers.

    Transformer

    Size

    Summer

    140%

    Winter

    160%

    Transformer

    Size

    Summer

    140%

    Winter

    160%

    10 14 16 50 70 80

    15 21 24 75 105 120

    25 35 40 100 140 160

    37.5 53 60 167 234 267

  • 8/9/2019 Transformer Sizing Presentation.pdf

    19/54

    Residential Transformer Loading

    Example Coincidence Factor Method

    Determine the Transformer Size based on the Maximum kVA LoadingTable.

    Summer Transformer Demand = 25.9 kW

    Winter Transformer Demand = 20.5 kW

    For a 15 kVA Transformer:

    Summer 140% Loading = 21 kW

    Winter 160% Loading = 24 kW

    For a 25 kVA Transformer:

    Summer 140% Loading = 35 kW

    Winter 160% Loading = 40 kW

  • 8/9/2019 Transformer Sizing Presentation.pdf

    20/54

    Residential Transformer Loading

    Example Adding a New Customer

    Step 1 - Determine the Additional Load on the Transformer based onthe Diversity Method Tables.

    New 2,200 square foot Home, Total Electric.

    Summer Peak = 18 kW

    Winter Peak = 21 kW

    Step 2 - Add kW for the New Customer to the Total Connected Load of

    the Existing Customers

  • 8/9/2019 Transformer Sizing Presentation.pdf

    21/54

    Residential Transformer Loading

    Example Adding a New Customer

    Step 2 - Add kW for the New Customer to the Total Connected Load ofthe Existing Customers

    Summer Winter

    kWh kW Demand kWh kW Demand

    Customer #1 2,224 11.57 853 7.47

    Customer #2 2,734 13.16 1,274 9.97

    Customer #3 1,849 10.29 1,283 10.27

    New Customer - - - 18 - - - 21

    Totals 53.0 48.7

  • 8/9/2019 Transformer Sizing Presentation.pdf

    22/54

    Residential Transformer Loading

    Example Adding a New Customer

    Step 3 Add the kW Demands. Summer Demand = 53.0 kW

    Winter Demand = 48.7 kW

    Step 4 Determine the Coincidence Factor for the number of customers

    from the table.

    Number of

    Customers

    Coincidence

    Factor

    1 1.00

    2 0.85

    3 0.74

    4 0.66

    5 0.61

  • 8/9/2019 Transformer Sizing Presentation.pdf

    23/54

    Summer Winter

    Coincidence

    Factor

    Total kW

    Demand

    Transformer

    kW Demand

    Coincidence

    Factor

    Total kW

    Demand

    Transformer

    kW Demand

    0.66 53.0 kW 35.0 kW 0.66 48.7 kW 32.1 kW

    Residential Transformer Loading

    Example Adding a New Customer

    Step 4 Determine the Coincidence Factor for the number of customersfrom the table.

    Coincidence Factor = 0.66

    Step 5 Multiply the total kW Demand by the Coincidence Factor for

    Summer and Winter loads. Summer Transformer Demand = 53.0 kW x 0.66 = 35.0 kW

    Winter Transformer Demand = 48.7 kW x 0.66 = 32.1 kW

  • 8/9/2019 Transformer Sizing Presentation.pdf

    24/54

    Residential Transformer Loading

    Example Adding a New Customer

    Step 6 The answer yields the peak 15-minute demand on thetransformer.

    Summer Transformer Demand = 53.0 kW x 0.66 = 35.0 kW

    Winter Transformer Demand = 48.7 kW x 0.66 = 32.0 kW

    Apply the two kW demands in step 5 to the Maximum kVA Loading table for

    transformers.

    Transformer

    Size

    Summer

    140%

    Winter

    160%

    Transformer

    Size

    Summer

    140%

    Winter

    160%

    10 14 16 50 70 80

    15 21 24 75 105 120

    25 35 40 100 140 160

    37.5 53 60 167 234 267

  • 8/9/2019 Transformer Sizing Presentation.pdf

    25/54

    Residential Transformer Loading

    Square Footage Table Method

    Very Useful in Sizing and Laying out Transformers in NewSubdivisions

    Information Required

    Average Square Footage of Homes in the Section of the Subdivision

    Number of Homes that are Total Electric and that have Gas Heat.

    Number of Homes proposed to connect to each transformer location.

  • 8/9/2019 Transformer Sizing Presentation.pdf

    26/54

    Residential Transformer Loading

    Square Footage Table Method

    Information from Tables The Number of Total Electric Customers.

    The Number of Gas Heat Customers

    The Number of Homes that will be connected at the Transformer

    Location. Use the Table to Determine the Transformer Size for the particular

    Location

  • 8/9/2019 Transformer Sizing Presentation.pdf

    27/54

    Residential Transformer Loading

    Example Square Footage Table Method

    3 Homes - Gas Heat; between 1,500 and 1,800 square feet.

    4 Homes - Total Electric; between 1,500 and 1,800 square feet.

  • 8/9/2019 Transformer Sizing Presentation.pdf

    28/54

    Residential Transformer Loading

    Example Square Footage Table Method

    3 Homes; Gas Heat; go down from 3 Gas Customers

    4 Homes; Total Electric; go right from 4 Electric Customers

    Table recommends 50 kVA transformer.

  • 8/9/2019 Transformer Sizing Presentation.pdf

    29/54

    Residential Transformer Loading

    Diversity Method - Useful when sizing transformers fornew customer load.

    Can be used with a variety of sizes of homes located within thesame subdivision.

    Useful when there is a mix of Total Electric and Gas Heathomes.

    Square Footage Table Method - Useful when sizingtransformers for new customer load. Can only be used when the sizes of homes to be served from

    the service transformer are relatively the same size.

    Useful when there is a mix of Total Electric and Gas Heathomes.

  • 8/9/2019 Transformer Sizing Presentation.pdf

    30/54

    Residential Transformer Loading

    Coincidence Factor Method - Useful when sizing

    transformers for existing loads or adding new load to

    existing loads. Can be used with only available customer billing information.

    Easily accommodates the addition of new residential loads to

    existing service transformer locations.

  • 8/9/2019 Transformer Sizing Presentation.pdf

    31/54

    Commercial Transformer Loading

    Watts per Square Foot Method

    Information Required

    Type of Business or Institution.

    Total square footage of the facility.

    Information from Tables

    By using the Average Watts per Square Foot tables the average kW

    Demand of the facility can be estimated.

  • 8/9/2019 Transformer Sizing Presentation.pdf

    32/54

    Commercial Transformer Loading

  • 8/9/2019 Transformer Sizing Presentation.pdf

    33/54

    Commercial Transformer Loading

    % of Connected Load Method

    Information Required Type of Business or Institution.

    Total connected electrical load of the facility.

    Information from Tables By using the % of Connected Load tables the average kW Demand of

    the facility can be estimated.

  • 8/9/2019 Transformer Sizing Presentation.pdf

    34/54

    Commercial Transformer Loading

  • 8/9/2019 Transformer Sizing Presentation.pdf

    35/54

    Commercial Transformer Loading

  • 8/9/2019 Transformer Sizing Presentation.pdf

    36/54

    Commercial Transformer Loading

  • 8/9/2019 Transformer Sizing Presentation.pdf

    37/54

    Commercial Transformer Loading

    Example Watts per Square Foot Method

    Grocery Store

    Winter = 10.1 watts per square foot

    For structures with electric heat.

    Summer = 10.4 watts per square foot Size of the Facility = 40,000 square feet

    Average Demand:

    Winter = 40,000 x 10.1 = 404,000 watts = 404 kW

    Summer = 40,000 x 10.4 = 416,000 watts = 416 kW

  • 8/9/2019 Transformer Sizing Presentation.pdf

    38/54

    Commercial Transformer Loading

    Example % of Connected Load Method

    Grocery Store

    Total Connected Load = 920 kW

    Of the total 920 kW, 250 kW is Winter Heating.

    Average Demand: Winter = 920 kW x 45% = 414 kW

    Summer = (920 kW 250 kW) = 670 kW x 61% = 409 kW

  • 8/9/2019 Transformer Sizing Presentation.pdf

    39/54

    Commercial Transformer Loading

    Comparison of Two Methods

    Grocery Store

    Watts per Square Foot Method

    Winter = 404 kW

    Summer = 416 kW % of Connected Load Method

    Winter = 414 kW

    Summer = 409 kW

    The calculated Peak kW Demand for the Grocery Store should bearound 400 kW.

    These calculations would then be used to determine the

    Transformer Size.

  • 8/9/2019 Transformer Sizing Presentation.pdf

    40/54

    Commercial Transformer Loading

    Application of Maximum kVA Loading on Three PhaseTransformers for Commercial Applications

    Transformer

    Size

    Summer

    120%

    Winter

    140%

    Transformer

    Size

    Summer

    120%

    Winter

    140%

    150 180 190 750 900 1,050

    225 270 315 1,000 1,200 1,400

    300 360 420 1,500 1,800 2,100

    500 600 700 2,500 3,000 3,500

    % of Connected Load Method

    Winter = 414 kW

    Summer = 409 kW

    Watts per Square Foot Method

    Winter = 404 kW

    Summer = 416 kW

  • 8/9/2019 Transformer Sizing Presentation.pdf

    41/54

    Commercial Transformer Loading

    Determine the Transformer Size based on the Maximum kVALoading Table.

    Maximum Average Transformer Demand Summer = 416 kW

    Winter = 414 kW

    For a 225 kVA Transformer:

    Summer 120% Loading = 270 kW Winter 140% Loading = 315 kW

    For a 300 kVA Transformer:

    Summer 120% Loading = 360 kW

    Winter 140% Loading = 420 kW

    For a 500 kVA Transformer:

    Summer 120% Loading = 600 kW

    Winter 140% Loading = 700 kW

  • 8/9/2019 Transformer Sizing Presentation.pdf

    42/54

    Commercial Transformer Loading

    Another Method Engineering Loading Data

    Use the supplied electrical loading data supplied by the buildingelectrical plans supplied by the buildings engineer.

    Information will include total connected and diversified load

    information. This information and calculations used in the engineers

    determination are based on National Electric Code load tables, not

    on Utility practices and history.

    Be Cautious Check the calculations for yourself to satisfy yourself

    that you are installing the correct size transformer so serve the load.

  • 8/9/2019 Transformer Sizing Presentation.pdf

    43/54

    Commercial Transformer Loading

    Another Method Engineering Loading Data

    TOTAL CONNECTED ELECTRICAL LOAD

    DESCRIPTIONAMPS AT 277/480, 3 PHASE, 4 WIRE

    KVAL-1 L-2 L-3

    INTERIOR LIGHTS 4.0 8.0 4.0 4.0

    EXTERNAL LIGHTS 4.0 - - 1.0

    RECEPTACLES 16.0 16.0 12.0 12.0

    AHU FAN & UNIT HEATER FANS 2.0 2.0 4.0 2.0

    EXHAUST FANS 6.0 1.0 2.0 3.0

    ELECTRIC HEAT - 17.0 17.0 10.0

    * COOLING 9.0 - 9.0 5.0 *

    WATER HEATERS 10.0 10.0 - 5.0

    SHOP EQUIPMENT 7.0 7.0 7.0 6.0

    MISCELLANEOUS 2.0 - 2.0 1.0

    TOTAL 51.0 61.0 48.0 44.0

    * NOT CALCULATED IN TOTAL

  • 8/9/2019 Transformer Sizing Presentation.pdf

    44/54

    Commercial Transformer Loading

    Another Method Engineering Loading Data

    School Maintenance Building

    44 kVA Connected Load

    3,000 Square Foot Facility

    Key Electrical Components Derated for Average Demand: Receptacles: 12 kVA derate to 5% = 0.6 kVA Lighting: 5 kVA derate to 85% = 4.25 kVA Water Heating: 5 kVA derate to 25% = 1.25 kVA Fans: 5 kVA derate to 40% = 2 kVA Heating: 10 kVA derate to 80% = 8 kVA Shop Equipment & Misc: 7 kVA derate to 35% = 2.45 kVA

    Average Demand = 18.55 kVA

    I d t i l / L C i l

  • 8/9/2019 Transformer Sizing Presentation.pdf

    45/54

    Industrial / Large Commercial

    Transformer Loading Engineered Loading Data

    Panel Schedules

    Actual Diversified Load Tables

    Watts per Square Foot Tables

    Usage History from Other Electric Utilities (Other Cities, Co-Op, Investor Owned, and other similar facilities on the same system)

    I d t i l / L C i l

  • 8/9/2019 Transformer Sizing Presentation.pdf

    46/54

    Industrial / Large Commercial

    Transformer Loading

    I d t i l / L C i l

  • 8/9/2019 Transformer Sizing Presentation.pdf

    47/54

    Industrial / Large Commercial

    Transformer Loading Areas of Consideration in Sizing Transformers for High

    Load Factor Customer

    High load factor customers use a large amount of energy (kWh)

    for extended periods of time.

    24-hours per day, 7-days per week department store is high load

    factor usage as compared 10-hour per day, 6-days per week

    local merchant which has a lower load factor.

    Industrial / Large Commercial

  • 8/9/2019 Transformer Sizing Presentation.pdf

    48/54

    Industrial / Large Commercial

    Transformer Loading Areas of Consideration in Sizing Transformers for High

    Load Factor Customer (continued)

    Due to the extended energy usage service transformers do not

    have a chance to cool down from operating at their nameplate

    rating.

    Normal distribution class transformers are not designed to

    operate at their nameplate rating for extended periods of time.

    Industrial / Large Commercial

  • 8/9/2019 Transformer Sizing Presentation.pdf

    49/54

    Industrial / Large Commercial

    Transformer Loading Areas of Consideration in Sizing Transformers for High

    Load Factor Customer (continued)

    To account for the high load factor usage transformers to serve

    this class of customer need to be oversized by 20% to 30% or

    specified as a substation class transformer.

    Substation class transformers can operate at their nameplate

    rating for extended periods without excess heating of the core.

    Delta Secondary

  • 8/9/2019 Transformer Sizing Presentation.pdf

    50/54

    Delta Secondary

    (High-Leg) Transformer SizingTwo-Transformer vs. Three-Transformer Bank Sizing

    Two-Transformer Banks

    Two-Transformers Banks work well for Single Phase Loads and

    relatively small Three Phase Loads.

    Two-Transformer Banks are more stable than Three-Transformer

    Banks because the Neutral on the Primary Side of the bank isGrounded.

    Three-Transformer Banks

    Three-Transformer Banks are well suited for Single Phase Loads

    and Large Three Phase Loads.

    Delta Secondary

  • 8/9/2019 Transformer Sizing Presentation.pdf

    51/54

    Delta Secondary

    (High-Leg) Transformer Sizing

  • 8/9/2019 Transformer Sizing Presentation.pdf

    52/54

    Secondary Conductor Sizing

    Example 4/0 Aluminum Service Drop; 150 feet in length; 25 kVA of

    load. kVA x Feet = 3,750

  • 8/9/2019 Transformer Sizing Presentation.pdf

    53/54

    Future Webinar Discussion

    Future Webinar Topics

    Future Webinar Frequency

    Webinar Instructors

    2013 El t iCiti

  • 8/9/2019 Transformer Sizing Presentation.pdf

    54/54

    2013 ElectriCities

    Electric Utility

    Webinar Series

    Sizing of

    Transformers

    Calculationof Loads