Transformer Asset Management. Pitfalls of Existing Process. No information on transformers if not installed in the field. Limited electrical characteristic data No history No comparative analysis possible Repetitive entry of the same information in FIS. New Process. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Transformer Asset Management

Transformer Asset Management

Page 2: Transformer Asset Management

Pitfalls of Existing Process

No information on transformers if not installed in the field.

Limited electrical characteristic data

No historyNo comparative analysis possibleRepetitive entry of the same

information in FIS

Page 3: Transformer Asset Management

New Process

Transformers treated similarly to other materials in a warehouse.

Data linked to graphics (PcAge, Asset Viewer).

Enhanced electrical test data.Complete history from receipt to

retirement.Simple search for inventory.

Page 4: Transformer Asset Management

Receipt

Minimal data entered by Material Coordinator on receipt of transformer.– Company number (application does not

allow duplicates)

–Manufacturer– Serial number– KVA– Location– Notes (job #, special characteristics, etc)

Page 5: Transformer Asset Management

Data Entry - New XFMR

Page 6: Transformer Asset Management

Receipt - cont.

All remaining information imported from csv file provided by manufacturer.– Voltages– IR, IX, IZ– Losses (load, no load)– Regulation–Mfr. date

Text Document

Page 7: Transformer Asset Management

Assigning Transformers to Location CodesFind the transformer by Company #.

Page 8: Transformer Asset Management

Assigning Transformers - cont.

Assign to Location CodeSelect position (graphics link)– application prevents inserting a

transformer in an occupied position

Add notesClick on out button.

Page 9: Transformer Asset Management

Removing Transformers

Enter Company # and find.Confirm location code.Enter location where transformer is

returnedEnter status (Yard, unusable)

– Yard indicates transformer is suitable to be put back in the field.

– Unusable to be retired or sent for repair.

Page 10: Transformer Asset Management

Removing Transformers

Page 11: Transformer Asset Management

Transfer Between CC’s

Enter Company #Confirm transformer informationSelect transfer option Select new CC

Page 12: Transformer Asset Management

Transfer Between CC’s

Page 13: Transformer Asset Management

Retirement

Enter Company #Must Have Status of Yard or

Unusable.Confirm Transformer InformationEnter Retirement Date

Page 14: Transformer Asset Management

Retirement

Page 15: Transformer Asset Management

Search / Edit

Search by– Company Number– KVA– Location– Location Code– Serial #– Status

Two Qualifiers possible with and/or selection

Page 16: Transformer Asset Management

Search / Edit

Operands– = Equal– != Not Equal– < Less Than– <= Less Than or Equal To– > Greater Than– >= Greater Than or Equal To

Page 17: Transformer Asset Management

Search / Edit

Sort of results availableSave results as csv for import to

other applicationsPopup window for expanded

viewingFull edit capabilities - TREAT WITH

CARE!

Page 18: Transformer Asset Management

Search / Edit

Page 19: Transformer Asset Management

Popup and Edit Windows

Page 20: Transformer Asset Management

Impact to Mapping Process

EC’s Create new Location CodeEnter KVA and Phase ConnectionAll Remaining Information is

Inserted Through Transformer Application

Location Code Must Exist in Database for Transformer Application to Work

Page 21: Transformer Asset Management

Impact to Mapping Process

Elimination of Work LibraryImplement Pending Flags in

DatabaseActions Through Transformer

Application Immediately Available in Next Graphics Retrieval

Page 22: Transformer Asset Management

Improvements to Process

Permanent Retention of Transformer Information

Transformer Installations Available in Graphics Sooner

Quick Reporting of InventoryBuilt-in Error CheckingImproved Work Flow