tomas damage assessment no pictures

43
GOVERNMENT OF ST. LUCIA Ministry of Communications, Works, Transport and Public Utilities HURRICANE TOMAS DAMMAGE ASSESSMENT HURRICANE TOMAS DAMMAGE ASSESSMENT REPORT ONE (1) FDL Consult Inc. P.O. Box 1803 Goodlands Castries, St. Lucia Tel: (758) 453-5727 / 5271 Fax: (758) 453-7048 E il fdl@fdl lti Email: fdl@fdlconsultinc.com www.fdlconsultinc.com DECEMBER 2010

Upload: eipem1

Post on 03-Mar-2015

28 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Tomas Damage Assessment No Pictures

GOVERNMENT OF ST. LUCIA Ministry of Communications, Works, Transport and 

Public Utilities

HURRICANE TOMAS DAMMAGE ASSESSMENTHURRICANE TOMAS DAMMAGE ASSESSMENT

REPORT ONE (1)

FDL Consult Inc.P.O. Box 1803

GoodlandsCastries, St. Lucia

Tel: (758) 453-5727 / 5271Fax: (758) 453-7048

E il fdl@fdl ltiEmail: [email protected]

DECEMBER 2010

Page 2: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | i   

TABLE  OF  CONTENTS  

Executive summary ................................................................................................................................................. 1 

1  Introduction ....................................................................................................................................................... 4 

2  Immediate Assessment ................................................................................................................................. 6 

2.1  Roads ............................................................................................................................................................ 6 

2.2  Bridgesand Other Crossings ........................................................................................................... 12 

2.3  Water Supply Infrastructure .......................................................................................................... 13 

2.4  Watersheds and Rivers ..................................................................................................................... 14 

2.5  Landslides ............................................................................................................................................... 15 

2.5.1  Natural Slope and Fluvial Processes .................................................................................. 15 

2.5.2  Guesneau ........................................................................................................................................ 18 

2.5.3  Columbette (Sabby) ................................................................................................................... 20 

2.5.4  Barre de L’Isle .............................................................................................................................. 22 

2.5.5  Bagatelle ......................................................................................................................................... 22 

3  Disaster Response Rationale and Methodology .............................................................................. 25 

3.1  Monitoring and Supervision ........................................................................................................... 25 

3.2  Rationale and Approach ................................................................................................................... 26 

3.3  Emergency Works ............................................................................................................................... 27 

3.3.1  Upslope Landsides (Debris Flows) ..................................................................................... 30 

3.3.2  Down Slope Failures .................................................................................................................. 30 

3.3.3  Bridges and Culverts ................................................................................................................. 32 

3.3.4  Rivers and Streams .................................................................................................................... 34 

3.4  Assistance to WASCO ......................................................................................................................... 34 

3.5  Roseau Dam and Transmission Mains........................................................................................ 35 

Page 3: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | ii   

3.6  Millet and Ravine Poisson Intakes ............................................................................................... 35 

3.6.1  Canaries Intake ............................................................................................................................ 36 

4  The Way Forward ......................................................................................................................................... 37 

5  Cost Estimates ................................................................................................................................................ 39 

6  RecommendationS ....................................................................................................................................... 40 

 

 

 

Page 4: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 1   

EXECUTIVE  SUMMARY    

The country’s infrastructure, among other things suffered significant and extensive damage 

following  the passage of Hurricane Tomas, on Saturday 30 October, 2010. The maximum 

sustained winds measured  at Hewanorra  and GFL Charles Airport were  89(143)  and 35 

(156.2  mph  (Km/h).    The  total  rainfall  recorded  during  the  24  hr  period  ranged  from 

533mm (24 inch) at Hewanorra Airport to 668 mm (26.3) inches at Desrache.  

 

The hurricane intensity and duration has been identified by others as about a 1 in 200 year 

event,  based  on  hind‐casting  (subject  to  confirmation).  However,  the  occurrence  of 

hurricanes  in  recent  years,  possibly  associated  with  climate  change,  could  require  this 

statistic to be significantly revised to become a higher frequency event in years to come.  

 In particular, major sections of  the primary and secondary road network were rendered 

impassable due to a combination of  factors  including  land slippages, severed bridges and 

roads,  mudslides,  fallen  trees  and/or  utility  poles.  As  a  result  some  communities  were 

completely isolated or partially accessible overland for several days. The historic landslide 

prone areas  in Soufriere, Canaries,  the Bar de L’isle and Castries North East and East are 

worthy of note.  

 

An immediate damage/condition assessment was made by a team of engineers from FDL 

Consult Inc. which involved primarily a walk‐through along with an aerial observation of 

the obstructed and collapsed roads and bridges.   

 

Generally  the  bridges/crossings  performed well  during  the  passage  of Hurricane Tomas. 

Many of those which failed were constructed of corrugated pipes. However, most of these 

pipes  were  constructed  more  than  35  years  ago  (normal  design  life  for  these  pipes  is 

25yrs) and had exhibited earlier signs of structural damage. 

 

 

Page 5: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 2   

Numerous  landslides  of  varying  types  and  magnitude  accompanied  the  Hurricane,  the 

impact  variable,  but  most  intense  in  the  historically  prone  areas.  Some  emergency 

clearance has taken place to ensure access to all communities and to permit economic and 

other  activities  to  resume. The  extent  and  results  of  the  geotechnical  assessment will  be 

elaborated on elsewhere in the report. 

 

The  MCWT&PU  with  the  support  of  FDL  Consult  Inc  oversaw  the  immediate  recovery 

works  for  the  country’s  road  and  bridges  infrastructure  including WASCO.  The  primary 

objectives of the emergency recovery were: 

Restoration of accessibility through the primary network 

Reinstatement of the water supply network 

Enhancing public safety  

Providing access to locked communities 

Preservation of critical infrastructure most at risk from further damage 

 

The emergency nature of the works,  limited access and the attendant adverse impacts on 

logistics meant that predominantly all the clearing works were implemented on a day work 

basis. A small percentage that involved construction of structures, emergency repairs and 

highly  labour  intensive  works  were  implemented  on  a  works  contract  basis  through  a 

direct  selection  based  on  availability,  capacity  and  qualification  based  on  pre‐existing 

criteria. Examples  included bridge  reinstatement and repairs and construction of Vanard 

Intake. The day work rates were pre‐established rates  included  in  the Disaster Response 

Plan  of  the  MCWT&PU.  All  claims  for  payments  had  to  be  submitted  to  the  Command 

Centre  for  review,  auditing  and  processing.  A  review  process  was  established  for  the 

accurate  and  timely  processing  of  payments.  Taking  into  account  the  factors  described 

above there is a clear need to identify a sensible and reasonable approach to managing the 

vulnerability of the existing roads, drainage and structures, which are still exposed to the 

slope‐related hazards and consequential fluvial hazards, post‐Tomas. This will require both 

remedial and preventative works.  

 

Page 6: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 3   

It must be accepted that the existing roads and river crossings will suffer in the future from 

some damage and blockage by landslide debris and erosion during prolonged wet periods. 

It  seems unacceptable  that  such  processes  should  be permitted  to  continue  in  key  areas 

where there is dense population or vital services infrastructure. Some stretches of road will 

inevitably suffer severe damage since preventative work may prove to be too costly, i.e. it 

may be more cost‐effective to permit the damage to occur and then rebuild the stretch of 

road  using  a  more  appropriate  design.  Monitoring  of  these  areas  must  be  considered; 

either as permanent telemetry installations, or frequent site inspections during periods of 

prolonged  wet  weather.  Construction  of  upstream  debris  control  structures  must  also 

feature in this strategy (such as permeable rip‐rap bunds, columns and cable traps). 

 

The following are recommendations which should not be considered exhaustive: 

Review of the recommendations and level of implementation of existing watershed 

and environmental management plans. A new plan may be required in light of new 

observations and climatic data; 

Geotechnical assessment of all major landslides; 

Update of landslide hazard map; 

Reconstruction  of  Bois  D’orange,  Choc,  Crestlands,  Grand  Ravine  and  Canaries 

bridges; 

Structural assessment of all bridges; 

Retrofitting of bridges where required 

Immediate de‐silting of rivers in Bexon, Marc, Deglos  and Soufriere River; 

Immediate  lope  stabilisation  works  on  all  failures  affecting  the  primary  and 

secondary road network and major tourist attractions. 

 

 

 

 

 

 

Page 7: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 4   

1 INTRODUCTION  

The country’s infrastructure, among other things suffered significant and extensive damage 

following  the passage of Hurricane Tomas, on Saturday 30 October, 2010. The maximum 

sustained  winds  measured  at  Hewanorra  and  GFL  Charles  Airport  were  89(143)  and 

35(156.2 mph  (Km/h).    The  total  rainfall  recorded during  the 24 hr period  ranged  from 

533mm (24 inch) at Hewanorra Airport to 668 mm (26.3) inches at Desrache.  

 

The hurricane intensity and duration has been identified by others as about a 1 in 200 year 

event,  based  on  hind‐casting  (subject  to  confirmation).  However,  the  occurrence  of 

hurricanes  in  recent  years,  possibly  associated  with  climate  change,  could  require  this 

statistic to be significantly revised to become a higher frequency event in years to come.  

 In particular, major sections of  the primary and secondary road network were rendered 

impassable due to a combination of  factors  including  land slippages, severed bridges and 

roads,  mudslides,  fallen  trees  and/or  utility  poles.  As  a  result  some  communities  were 

completely isolated or partially accessible overland for several days. The historic landslide 

prone areas  in Soufriere, Canaries,  the Bar de L’isle and Castries North East and East are 

worthy of note.  

An  immediate damage/condition assessment was made by a  team of engineers  from FDL 

Consult  Inc. which  involved primarily a walk‐through along with an aerial observation of 

the obstructed and collapsed roads and bridges.  The major failures are reported below in 

terms of affected roads1. 

 

The water treatment and supply systems were disrupted significantly, as major catchment 

areas were affected by high  levels of siltation and debris, destruction to pumps and main 

pipes  severed.  The  John  Compton  Dam,  which  supplies  water  to  about  100,  000  users 

during  the peak  tourist  season was non‐operational  for 15 days/weeks The  result was a 

national shortage of potable water and reliance on importation from neighbouring islands. 

                                                        1 Road names used are consistent with the directories of Primary, Secondary and Tertiary Roads (Version 4: 1 Sept 2003). 

Page 8: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 5   

The  water  situation  was  exacerbated  by  reduced  access  to  the  water  catchments  and 

distribution  points  to  conduct  thorough  assessments  and  undertake  appropriate  and 

timely action. Emergency, temporary and in a few cases more permanent works have been 

undertaken  to help  restore  the water  supply. At  the  time of  reporting most  communities 

had had their potable supply restored, though not necessarily to the pre Hurricane Tomas 

level. 

 

Many bridges were also completely or partially destroyed, in particular the Choc and Bois 

d’  Orange  bridges  linking  two major  commercial  zones,  Castries  and  Gros  Islet,  and  the 

Fond St. Jacques bridge.  The approaches to or support mechanisms for other bridges and 

crossings,  such  as  Troumassee  were  also  severed,  some  immediately  following  the 

hurricane, others overtime, due in part to prolonged and intense rainfall episodes coupled 

with an already volatile situation. 

 

Numerous  landslides  of  varying  types  and  magnitude  accompanied  the  Hurricane,  the 

impact  variable,  but  most  intense  in  the  historically  prone  areas.  Some  emergency 

clearance has taken place to ensure access to all communities and to permit economic and 

other  activities  to  resume. The  extent  and  results  of  the  geotechnical  assessment will  be 

elaborated on elsewhere in the report. 

 

 

 

 

 

 

 

 

 

 

 

Page 9: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 6   

2 IMMEDIATE  ASSESSMENT  

An immediate damage/condition assessment was made by a  team of engineers  from FDL 

Consult  Inc. which  involved primarily a walk‐through along with an aerial observation of 

the obstructed and collapsed roads and bridges.  The major failures are reported below in 

terms of affected roads2. 

2.1 ROADS 

A number of roads were rendered impassable by landslides on both the upslope and down 

slope. Additionally some bridges and crossing were washed away. 

 

Choc – Cap Estate 

This  is  the  primary  link  to  St.  Lucia’s  major  commercial  and  touristic  centre.  There  are 

alternative  routes  but  are  limited  geometrically  to  use  by  goods  vehicles. Moreover,  the 

bypass  routes  are  not  designed  to  carry  the  vehicle  volumes  presently  carried  by  the 

primary link.  

 

The  two  major  crossings  at  Bois  D’orange  and  Choc  constructed  of  large  diameter 

corrugated pipes were damaged. The fill over the pipes was eroded by the corrosive power 

of the flood waters. In both instances the water undermined the fill after breaching spaces 

between  headwall  and  pipe  or  scoured  the  fill  through  the  roof  of  the  pipe  which  had 

previously collapsed from corrosion. 

 

Cul de Sac – Ravine Poisson ­ Marc Deglos 

All  the roads, primary, secondary and tertiary were  inundated with silt and debris as the 

rivers  were  rechanneled  on  these  roads  for  reasons  discussed  in  other  sections  of  this 

report. The silt was up to 2m high in many areas rendering some areas inaccessible. There 

                                                        2 Road names used are consistent with the directories of Primary, Secondary and Tertiary Roads (Version 4: 1 Sept 2003). 

Page 10: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 7   

was  considerable  loss  of  private  and  some  public  property.  The  Bexon  School  was 

surrounded with silt while the pedestrian access was completely washed away. 

 

Barre de L’isle – Hill Top Dennery 

Historically the Barre De L’isle  is known for  its  instability. There were a number of slope 

failures  over  the  entire  length,  approximately  2km,  of  the  north  side  of  the  ascent  from 

Ravine  Poisson. On  the  southern  descent which  is  along  a  ridge  a  high  number  of  down 

slope  failures  occurred.  Therefore,  most  of  the  clearing  was  required  on  the  North  side 

while retaining structures are required on the south side.  

 

The landscape of the lower portions of the Barre de L’isle on the Ravine Poisson side has 

been  transformed.  Steep  hillsides  above  the  road  which  were  once  covered  with  lush 

vegetation have been stripped bare. 

 

The  remedial  long  term  solution  to  prevent  future  landslips  could  be  a  combination  of 

slope stabilisation options. 

 

The Grand Ravine Bridge which is a  low crossing also overtopped with at  least 2.00 m of 

debris during high intensity rainfall.  

 

Praslin Bridge – Fond Bridge  

This section of road was virtually  intact except  for  the erosion of  the  fill over corrugated 

pipe  at  the  crossing  near  the  Lombard  intersection.  This  pipe  had  significantly  less 

discharge capacity than an upstream bridge along the old ECR alignment. The failure could 

have been attributed  to  the clogging of  the culvert and  the subsequent  force and erosive 

power of the water.  A culvert with a larger discharge capacity must be considered for this 

area. 

 

 

 

Page 11: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 8   

ECR (Troumassée Bridge – Wanier Bridge) 

The road was eroded pre Hurricane Tomas in the area of two culverts along the strait to the 

Troumassée  Bridge.  One  culvert  was  already  damaged  and  earmarked  for  replacement. 

These  crossing  were  also  constructed  of  multiple  corrugated  pipes  which  should  be 

replaced with clear span culverts. 

 

Subsequent  rainfall  on  Thursday  11th  November  2010  exacerbated  the  erosion  of  the 

southern abutment of the Troumassée Bridge.  Scour from below caused the collapse of the 

backfill to the abutment. 

 

Quart Chemin – Soufriere 

This section of the West Coast Road is known for its instability. The upper northern section 

(Bouton to Colombette) succumbed to a series of landslides over a 0.5 km span. LUCELEC 

lost the only section of the 66 KV lines in that area. The details of the slide are discussed in 

another section. 

 

Amazingly the road carriage remained intact for most of the road.  

 

A number of slides also took place between La huat and Soufriere town section.  

 

Choiseul Village – Myers Bridge 

Most of the landslides occurred at the known areas of instability, namely Ravine Cacoa, and 

Victoria to Myers Bridge. A number of 11KV utility poles were also grounded by slides.  

 

Myers Bridge – Soufriere   

Ladera to Soufriere section can be regarded as the section of the South Coast Road with the 

highest  level of  slope  instability.   This proved  true during hurricane Tomas as  it was  the 

site of some significant slides of over 10000  cubic meters with boulders up to 10 tonnes. 

Large boulders are characteristic feature of the slopes and geology in this area. 

 

Page 12: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 9   

Anse La Raye – Canaries  

This section had one major slide coupled with the collapse of a gabion wall. The Anse Gallet 

crossing along that route was also completely blocked with the collapse of a large diameter 

corrugated pipe. The river channel was completely silted as a result of the blockage forcing 

the river to be diverted in two branches. 

 

Soufriere ­ Crestlands – Fond St. Jacques 

The Crestlands  area was  severely  hit  as  it  is  traversed by  several  streams  that  converge 

into  the  Soufriere  River.  A  number  of  the  streams  changed  course  transplanting  large 

boulders onto the road and through houses. A small bridge was washed off its foundation. 

 

 There was  on major  slide  along  the  route which  brought  thousands  of  tonnes  of  debris 

comprising silt, rocks and trees at crossings. 

 

Bagatelle – Castries 

The  upper  Bagatelle  section  had  two  major  landslides  on  the  upslope  which  forms  the 

down slope to the Morne – Guesneau Road. The largest slide was triggered by uncontrolled 

roof water  charging  the  slope.  Slope  stability options are necessary  to preserve both  the 

integrity and safe use of the two aforementioned roads.  

 

Guesneau ­ Ti Rocher – Four Roads 

A  huge  down  slope  occurred  at  the  junction  to  Forestierre.  It  is  reported  that  several 

houses collapsed with the slide along with utility poles and lines. The details of  this slide 

are discussed in sections to follow. 

 

 

 

 

 

Page 13: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 10   

The following tables present a summary of the observed immediate and critical damages to 

the various classes of roads: 

 

TABLE 1: SUMMARY OF CRITICAL DAMAGE ­ PRIMARY ROADS 

Road  Description of Damage  Outcome 

Choc – Cap Estate  Collapse  of  Choc  and  Bois  D’Orange crossings 

Route impassable at crossings ‐

Cul de Sac – Ravine Poisson 

Landslips and heavy siltation Route impassable 

Barre de Lisle –Hill top Dennery 

Major landslides, fallen telecommunication lines. Bridge at Grand Ravine overtopped with 3m of debris 

Route impassable 

ECR  (Praslin Bridge  –  Fond Bridge 

Collapsed crossing Route impassable 

ECR(Troumassée Bridge  –Wanier Bridge) 

Partial collapse of two culverts Single lane traffic 

Quarte  Chemin  ­ Soufriere 

Major landslides ‐ fatalities Route impassable 

Choiseul  Village Bridge  –Myers Bridge 

Major landslides between Ravine Cacoa and Myers bridge 

Route impassable from Victoria toMyers Bridge 

(Anse  La  Raye  ­ Canaries) 

Major  Landslide(Anse  La  Verdue), Collapsed culvert  at Anse Gallet 

Road impassable 

Myers  Bridge  ­ Soufriere 

Major landslides Road impassable 

  

 

 

 

 

 

 

 

 

Page 14: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 11   

TABLE 2: SUMMARY OF CRITICAL DAMAGE –SECONDARY AND OTHER ROADS 

Road  Description of Damage  Outcome 

Soufriere  ­ Crestlands  ­ Fond 

St. Jacques 

Major landslides ,  

Collapsed Bridge 

Road impassable 

Saltibus Main Road  Downslope landsides  Single lane traffic 

Deglos ­ Trois Piton  Major Landslide  Single lane traffic 

Talvern ­ Cacoa ­ Guesneau  Major Landslide  Road impassable 

Guesneau  ­ Ti Rocher  ­ Four 

Roads 

Downslope landsides  Single lane traffic 

Debrieul ­ Myers Bridge  Downslope landsides  Single lane traffic 

Bagatelle ­ Castries  Major Landslide  Road impassable 

Roseau ­ Vanard ­ Millet  Major landslides  Road impassable 

Soufriere Hospital Road  Completely eroded  Road impassable 

 

 

 

 

 

 

Page 15: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 12   

2.2 BRIDGES AND OTHER CROSSINGS 

Generally  the  bridges/crossings  performed well  during  the  passage  of Hurricane Tomas. 

Table 3 below provides a summary of the major bridge failures. Many of those which failed 

were  constructed  of  corrugated  pipes.  However,  most  of  these  pipes  were  constructed 

more  than  35  years  ago  (normal  design  life  for  these  pipes  is  25yrs)  and  had  exhibited 

earlier signs of structural damage. Anse Gallet was, however, constructed  in 1993 and  its 

failure was not due  to aging but  initial poor maintenance (The crossing was damaged by 

previous severe weather systems). The raging water entered the space between the head 

wall and pipe which may have existed prior to Tomas.  

 

The Mon Repos failure could have been avoided with the provision of a head wall. 

 

Additionally a number of bridges/crossings were loaded with debris. 

 

TABLE 3: MAJOR FAILURES – BRIDGES/CROSSINGS 

Location  Type  Description of Failure Crestlands  Reinforced concrete slab  Washed away Fond St. Jacques  Bailey Washed off abutmentBois D’Orange  Corrugated pipe culverts Erosion  of  fill  and  west 

retaining wall Choc  Corrugated pipe culverts Erosion of fill Morn Repos  Corrugated pipe culverts Erosion of fill above pipeAnse Gallet  Corrugated pipe culverts Collapsed pipe Troumassée  Composite  deck  with  central 

pier founded on steel piles Erosion of southern approach

Marc Community  Reinforced concrete Collapsed  

 

 

 

 

 

 

Page 16: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 13   

2.3 WATER SUPPLY INFRASTRUCTURE 

There are 28 water production facilities in  Saint  Lucia  which  produce 

17 million gallons per day (MGD).   The main damage sustained varied from destruction to 

pumping  facilities  to  silted  intakes.  A  tabular  summary  of  the  damages  of  some  of  the 

infrastructure investigated FDL Consult Inc. follows. 

 

TABLE 4: DESCRIPTION OF DAMAGE: SOME WATER FACILITIES 

Facility  Summary of Damage John Compton Dam  Inaccessibility due to landslides; 

Raw water pumping faculty was inoperable.;  Damaged incoming electrical supply; Damaged electrical panels;  Damaged  back  up  A  slab  on  the  spillway  was dislodged; Minor structural damage to the service buildings

Grace Intake  Excessive siltationBeausejour Intake  Excessive siltationCanaries Intake  Washed away;

Partial loss of transmission line  

Anse La Raye  Siltation of intake;Partial loss of transmission line 

Millet Intake  Landslide;Siltation of intake 

Vanard Intake  Siltation of intakeRavine Poisson  Siltation of intake   

 

 

 

 

 

 

 

 

Page 17: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 14   

TABLE 5: MAJOR FLOODING RIVERS 

Name  Description of Failure  Outcome 

Ravine Poisson ­ Bexon  Silted to top of bank,  

Bank erosion,  

Realigned in sections 

Extensive  flooding  of 

surrounding  lands;  major 

property damage 

Marc River  Silted to top of bank,  

Bank erosion,  

Realigned in sections 

Extensive  flooding  of 

surrounding lands 

Soufriere River  Silted  next  to  footbridge, 

Realigned,  

Bank erosion 

Extensive flooding and siltation 

of Soufriere town 

Anse Gallet River  Silted to top of bank, 

Realigned at crossing 

Flooding  of  surrounding 

agricultural land 

Fond River  Excessive debris at bridge   

Canaries River  Siltation and realignment in the 

upper reaches  

 

 

2.4 WATERSHEDS AND RIVERS  

A number of slides occurred in watershed areas. Consequently, the debris ended up in the 

rivers and streams which deposited them along the length of the rivers and plains.  

 

Consistent with  the  location  and  size  of  landslides  and  the  amount  of  rainfall,  there was 

considerable  flood  damage  in  Bexon,  Marc  and  the  Soufriere  basin.  These  catchments 

recorded high levels of rainfall in excess of 600mm over the 24 hr. period.  

 

Table  5  provides  a  summary  of  the  major  flooding  episodes.  Most  of  the  flood  damage 

around the area of the Soufriere Hospital resulted from the construction of the foot bridge 

next  to  the  Soufriere Primary  School.  The  concern with  the  potential  implications  of  the 

location  of  the  footbridge  was  highlighted  in  the  Watershed  and  Environmental  Report 

(WEMP) 1997. As indicated in that report, the foot bridge would restraint trees and other 

Page 18: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 15   

debris which would cause it to over top, directing flows out of the channel into the town. In 

fact  that  same  effect  was  observed  on  most  brides  to  various  extents  which  also 

contributed to flooding level upstream and depositing of silt.   

 

2.5 LANDSLIDES 

2.5.1 NATURAL SLOPE AND FLUVIAL PROCESSES 

The  natural  topography  of  St  Lucia  has  gradually  evolved  from  original  volcanic  activity 

several million years ago. More  recent activity  (during  the past 100,000 years or  so,  and 

historic tropical weathering processes resulted in something resembling the present day St 

Lucia topography. The current landform is a reflection of more recent tropical weathering 

processes  and  the presence of  the  following main  rock  types:  closely  jointed  andesite  or 

basalt and volcanic ash/tuff bedrock, other volcanic deposits, and colluvium/alluvium. The 

exposed  rocks  vary  from  competent,  moderately  weathered  material  to  completely 

weathered, very weak, friable rock/residual soil – generally heavily vegetated except near 

man‐made developments, such as roads, agriculture, housing, etc. 

 

The  ancient  landscape  has  been  incised  by  large  ravines  with  associated  coastal  flood 

plains (where towns and villages have developed), and there are many other, established, 

smaller  ravines which  are more  often  dry watercourses.  The  bedrock may  include  local 

weak  planes,  which  historically  have  resulted  in  significant  slope  failures  where  the 

strata/joint  dip  is  parallel  or  sub‐parallel  to  the  slopes.  The  completely weathered  rock 

(residual  soil)  is  typically  1.5  to  3  metres  thick  in  some  exposures;  however,  in  some 

locations  it  is  likely  to  be  considerably  thicker.  Excavations  may  reveal  that  there  is 

evidence  that  historic  slopes  failures  are  present  in  the  flanks  of  some  of  the  ravines 

(where rock‐head has been eroded and replaced with slip debris). 

 

The  overall  slope  processes  depict  areas  of  limiting  equilibrium with  varying  degrees  of 

tree,  shrub  and  other  vegetation  cover.  Exceptional,  prolonged  rainfall  would  have 

Page 19: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 16   

triggered debris flows, mud‐runs and tree falls, temporarily blocking natural watercourses 

and creating new ones. These unstable areas would gradually evolve with new vegetation 

growth adapting until meta‐stable slope conditions were re‐established.  

 

To  summarise,  the  vegetation  and  natural  topography  have  evolved  through  geological 

time  to  produce  natural  25  to  45  degree  slopes  (sometimes  much  steeper),  which  are 

globally stable (locally marginally unstable) during prolonged periods of heavy rainfall. The 

shallow‐depth  stability  of  these  slopes  probably  increases  by  up  to  50%  during  the  dry 

season, due to increase in effective stress as a result of the groundwater level dropping, and 

negative pore water pressures. 

 

2.5.1.1 INFLUENCE OF MAN‐MADE STRUCTURES ON SLOPE AND FLUVIAL 

PROCESSES 

The construction of carefully designed roads, drainage, and other development in this type 

of  terrain,  even  adopting  best  practice,  will  generally  be  slightly  to  significantly 

detrimental, compared to the long‐term stability and performance of the otherwise natural 

slopes. 

 

The construction of ill‐considered roads, drainage and other structures using poor practice 

will  invariably contribute directly to significant  landslides, slumping of sidelong fill, mud‐

runs  and  serious  damage  to  infrastructure/property.  In  many  instances  throughout  the 

tropical countries this approach to design and construction has proved to be catastrophic – 

causing some large areas to be subsequently evacuated and abandoned. 

 

The  present  situation  in  St  Lucia,  post‐Tomas,  suggests  that,  whereas  many  of  the 

landslides  were  probably  inevitable,  in  some  areas  poor  geotechnical  design  and 

construction  practice  have  been  adopted  in  the  past.  In  hindsight,  the  prevailing  ground 

conditions and potential impact of changes in rainwater infiltration and run‐off conditions 

do not seem to have been addressed in full. As a direct result, uncontrolled run‐off with a 

significant debris bed‐load and mud‐runs/log jams has blocked established watercourses, 

Page 20: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 17   

culverts,  and  road  crossings.  These  blockages  created  new  river  courses  resulting  in 

significant  erosion,  build‐up  of  slope  debris,  and  loss  of  trees  (which  usually  help 

strengthen the slopes).  If  the existing  landslide/erosion debris  is simply cleared from the 

roads and moved to the nearest tip area, then the slopes would continue to deteriorate in 

some places during the prolonged wet weather, probably at an accelerated rate. This “do 

minimum”  strategy  may  inevitably  present  an  increased  health  and  safety  risk  at  some 

stage in the future and additional loss of assets. 

 

The “do minimum” approach to slope remedial works, road maintenance and new‐build is 

considered to be unacceptable because of the probable future consequences. Likewise, fully 

engineered  slope  stabilisation works  and  run‐off  control measures,  are  considered  to  be 

also  unacceptable  because  of  prohibitive  costs  and  massive  impact  on  the  natural 

environment (which is one of the key assets and attractions of St Lucia). 

 

2.5.1.2 COMMENTS ON SELECTED POST‐TOMAS LANDSLIDES 

The  nature  of  these  selected  slides  which  occurred  as  a  result  of  the  heavy  rains  of 

hurricane  Tomas  varied  in  depth  and  type  of  movement.  They  also  differ  in  soil 

characteristics and local. However, the common denominator was the exceptional rainfall 

event. 

 

Some of the landslides evaluated in this report are characterised by clay soil evident in the 

Ti Rocher  area  and  sandy‐clay  soil with  gravel,  cobbles  and boulders  evident  in  the  two 

slides within the Bagatelle area. Steeply inclined bedrock was exposed in small areas as a 

result  of  the  landslides.  Sabby3 appears  at  first  sight  to  be  less  clay  content  than  the 

Bagatelle sites. Barre de L’isle is much more variable and will require site specific landslide 

soil descriptions. 

 

                                                        3 For ease of reference in this report “Sabby” refers to the major landslide at Colombette which resulted in the death and/or disappearance of Sabby’s family. 

Page 21: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 18   

2.5.2 GUESNEAU 

The  Gesneau  landslide  can  only  be  described  as  “massive”  in  aerial  extent,  with  an 

approximate  width  and  length  of  substantially  affected  slope  of  about  450m.  The 

approximate  maximum  depth  of  the  slide  is  likely  to  be  20  to  25m  below  post‐failure 

ground  profile.  However,  this  has  to  be  confirmed  by  comparison  to  pre‐failure 

photographs  and  landslide  volume  calculations.  This  slide  occurred  in  a  semi‐residential 

area where loss of 6 properties occurred. In the past the affected road has been a key link 

for through traffic. 

 

The  slip  surface  is  exposed  in  certain  areas  revealing  an  exposed  rock  face which  varies 

from 0 to 5m below the original ground level. This exposed rock face is evidence of the fact 

that  the slide mass  itself  is generally now  inactive, with a  few areas still  at  risk of minor 

slippage, although the toe of the slip above the ravine has yet to be examined. However, the 

main  back‐scarp  is  over‐steep  and  is  likely  to  continue  to  back‐sap  during wet weather. 

One such area includes part of the intact road section which was virtually unaffected by the 

slide. The cross section of the road which was made visible by the exposure created by the 

slide reveals  that  the road was constructed on a  layer of clay (residual soil or colluvium) 

overlying  weathered  rock.  This  clay  is  probably  now  in  un‐drained  stress  conditions, 

however,  as  pore  water  pressures  approach  drained  conditions  the  clay  will  lose  its 

cohesion  and  will  experience  a  significant  reduction  in  available  shear  strength. 

Alternatively it could become saturated in the presence of water ponding causing softening 

and loss of un‐drained strength.  

 

The  key  remaining  landslide‐associated  risk  is  that  further  mass  movement  could  take 

place  as  a  result  of  heavy  rainfall  or  additional  loading  from  back‐scarp  failures.  The 

slipped  mass  may  require  several  months  of  dry  weather  before  earthworks  and  slope 

drainage  works  could  start  safely.  A  key  aspect  is  the  local  stability  of  the  toe  of  the 

landslide at  the  lip of  the  ravine.  If  this  area  can be  stabilised  then  the main earthworks 

could comprise near‐flat wide benches and shallow counterfort drains. Planting of suitable 

Page 22: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 19   

vegetation  would  be  a  vital  part  of  this  scheme  to  control  future  surface  erosion.  Local 

ground  improvement  measures  near  the  back‐scarp  would  enable  a  reinforced  earth 

buttress to be constructed to support the back‐scarp and the re‐constructed road. 

Even if a permanent road diversion were to be considered, up‐slope of the landslide, then 

some  work  would  still  have  to  be  undertaken  within  the  landslide  to  prevent  it  from 

expanding in the future and to control debris flowing into the ravine. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 23: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 20   

2.5.3 COLUMBETTE (SABBY) 

This  landslide  is  a  large  acute  triangular  feature,  approximately 200m high  and  tapering 

from 10m at the top to 75m at the highway. The volume of debris removed from the event 

is likely to exceed 20,000m3 (subject to survey). The remaining potential source of debris 

for a future similar hurricane could exceed this figure.  

The debris flow is a classic cone shape because concentrated water run‐off has entered the 

already  saturated  slope  at  one  point  near  the  top  of  the  steep  slope.  This  has  caused 

progressive slope failure and erosion gullying from top‐down. 

 

The Sabby slide was apparently caused by a combination of factors: 

Removal of primary vegetative cover due to subsistence farming and a bush fire 

in 2009. 

Heavy  rains,  533mm  in 24 hours,  probably  caused  the ground  to become  fully 

saturated;  that  is  ground water  table at  the  surface. This  situation would have 

reduced  the  effective  shear  stress  in  the  residual  soil  mantel  by  about  50%, 

resulting in the factor of safety against shallow failure dropping to 1.0 or less. 

 

It  is not clear at present whether the overall slope  failure mechanism was triggered  ‘top‐

down’  or  ‘bottom‐up’,  that  is,  toe  failure  first which would  undermine  the  slope  causing 

regressive  upslope  failures,  or  failure  of  the  upper  slope  which  would  have  loaded  the 

lower slope causing failure (like an avalanche). 

 

The long term solution for slope stability and debris flow management would be to remove 

slipped material and bench the slope. In order to gain safe plant access, benches will have 

to be  formed  in a zigzag up  the slope. This will  also help control  future  run‐off provided 

suitable  debris  traps  and  stilling  basins  are  incorporated  into  the  design.  These  works 

should be carried out after prolonged dry weather. Even so some of the work may require 

temporary  road  closures  to  safeguard  the  public  who  would  otherwise  use  the  road. 

Page 24: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 21   

Alternatively, substantial temporary works protection from material rolling down the slope 

during construction work will have to be considered. 

 

The  landslide at Sabby’s place  is probably still potentially active, and susceptible  to even 

moderate rainfall. Therefore there will be a need to place a culvert along the newly formed 

drainage path  to  convey water  across  the  road. Also north  and  south  approach drainage 

channels  to  the  culvert need  to be  cleared. As  a  temporary measure  cross  road drainage 

would be facilitated by a geotextile‐wrapped boulder packed French drain.  

 

The remaining volume of potential slip debris in the slope should be assessed. Whereas the 

proposed  benched  earthworks  concept  should  be  capable  of  preventing  a  similar 

occurrence in the future, it is sometimes prudent to consider implementing a run‐off ‘safety 

valve’  feature.  This  could  include  incorporating  a  secondary  culvert  alongside  and  at  a 

slightly higher invert level (with a bifurcation wall), or a slight dip in the road, along with 

that area being designed as a spillway. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 25: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 22   

2.5.4 BARRE DE L’ISLE 

Historically  the Barre De  L’isle  has  been  recognised  for  its  frequent  slope  failure  events. 

Hurricane  Tomas  caused  numerous  up‐slope  failures  along  the  entire  road  length  of  the 

north side of the ascent from Ravine Poisson. On the southern road descent, which is along 

a  ridge,  numerous down‐slope  failures  occurred.  Therefore, most  of  the  emergency  road 

clearing was required on the North side while new/strengthened retaining structures will 

probably be required on the south side.  

2.5.5 BAGATELLE 

The two landslides in the Bagatelle area are much smaller than TI Rocher, each having an 

approximate width of 50m.  However, they have not only damaged the lower road, but now 

also pose a serious threat to the upper road. 

 

The landslides (referred to here as Slip 1 and Slip 2) occurred in the form of debris flows 

composed  of  the weathered Volcanic Ash  and Tuff  (volcanic  sandy‐clay mixed with  rock 

fragments), which crumble quite easily in the presence of water. Based on the observations 

made on the site, both slides are considered to be still potentially active  in certain areas, 

due  to  the  extremely  steep  incline  on  the  upper  and  lower  slopes,  wet  areas,  and  the 

presence of  trees of  large girth. The presence of a competent rock surface can be seen  in 

certain sections of the upper slopes.  

 

Slip 1 

This  is  a  localised  slip  feature  on  a  steep  “natural”  slope which  persists  for  at  least  100 

metres on either side of the slip. 

The  rubble  wall  supporting  the  upper  road  has  at  least  20nr  75mm  drainage  pipes 

protruding through the exposed down‐slope face. There is evidence that the v‐drain on the 

upslope  side  of  the  upper  road  had  been  blocked  by  a  small  landslip  causing  run‐off  to 

cross the road and soak into the verge. There is also evidence of significant flow over the 

verge and onto the slope where the retaining wall stops. The slip was probably caused by 

Page 26: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 23   

complete saturation of the soil mantle and even free water flowing over the ground surface. 

Local slumping and erosion would have rapidly developed into an expanding debris flow. 

 

Significant re‐profiling of the slope immediately above the lower road has taken place since 

Tomas (as part of the road clearance operations). The ~70 degree new cut slope exposes a 

matrix  of  Grade  5  rock  with  some  soil  matrix  areas.  This  is  considered  to  be  relatively 

stable provided a stub wall, incorporating a road drain, is constructed, and the bare slope is 

suitably vegetated. 

 

However, in the central portion of this slip feature the weathered rock profile is not evident 

and the slope suggests that a landslide has occurred here in the past.  There is a back scarp 

a few metres below the upper retaining wall and evidence of an old arcuate backscarp to 

the right of that, looking up‐slope. There remains a lobe of about 200m3 which may fail at 

any  time.  The  emergency  earthworks  contractor  has  recognised  this  and  is  considering 

whether to wait for the failure event and then clear it, or to remove it now. 

 

There  is  a  perceived  risk  that  further  slippage  may  undermine  support  for  the  upper 

retaining wall and cause displacement or even failure. 

 

Slip 2 

This  is  a  localised  slip  feature  on  a  steep  “natural”  slope which  persists  for  at  least  100 

metres either side of the slip. Three houses at the top of the slip have been built in a very 

tight cluster, each with its own septic tank and uncontrolled grey water and roof water run‐

off. The acute triangular shape of the slip indicates that this housing development probably 

caused concentrated run‐off at  this particular point. Upper road run‐off does not seem to 

have been a contributory factor because the road is at an apex at this point. 

The slip was caused by complete saturation of the soil mantle and even free water flowing 

over  the  ground  surface.  Shallow,  low  permeability  rock  profile  would  have  forced  this 

mechanism  to  occur  quickly.  Local  slumping  and  erosion would  have  rapidly  developed 

into an expanding debris flow. 

Page 27: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 24   

 

The  shallow  depth  debris  flow  has  exposed  steeply  inclined  bedrock  at  a  few  localised 

places.  It  seem  obvious  that  the  shallow  bedrock must  be  fully  utilised  in  any  remedial 

works  solution,  otherwise  alternative  could  involve  large,  expensive  structures  with 

considerable volumes of imported bulk fill. 

 

The key issue here is buildability including plant access on very steep slopes. This will be 

addressed during the design process. The diagram for Slip 2 below indicates one possible 

option that may provide a viable solution.  

 

 

 

Page 28: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 25   

3 DISASTER  RESPONSE  RATIONALE  AND  METHODOLOGY  

3.1 MONITORING AND SUPERVISION 

The  MCWT&PU  with  the  support  of  FDL  Consult  Inc  oversaw  the  immediate  recovery 

works  for  the  country’s  road  and  bridges  infrastructure  including WASCO.  The  primary 

objectives of the emergency recovery were: 

Restoration of accessibility through the primary network 

Reinstatement of the water supply network 

Enhancing public safety  

Providing access to locked communities 

Preservation of critical infrastructure most at risk from further damage 

 

All works were undertaken utilizing local equipment and labour resources. The supervision 

of all works was managed by a management team lead by the Hon Minister of Works, Guy 

Joseph;  Permanent  Secretary  (PS),  Allison  Jean; Deputy Permanent  Secretary  (DPS),  Ivor 

Daniel;  Chief  Engineer  (CE),  Lester  Arnold;  Deputy  Chief  Engineer  (DCE),  Albert  Jn. 

Baptiste; Financial Analyst   and Gilbert Fontenard, Civil Engineer and Roger Butcher Civil 

Engineer of FDL Consult Inc.  The disaster response and management was informed by the 

Disaster Response Plan (DRP) of MCWT&PU with expected deviations based on the actual 

circumstances.  This plan also called for the establishment of a Command Centre which was 

established immediately following the passage of the hurricane.  The Command Centre was 

headed  by  the  Deputy  Permanent  Secretary  with  support  from  Deputy  Chief  Engineer, 

Financial  Analysis  and  Quantity  surveyors  and  requisite  administration  staff.  Weekly 

review meetings  chaired  by  the  PS with  the Minister  in  attendance were  held  to  review 

strategy, successes, failures, priorities, procurement and for decision making.  The minutes 

of  the  meetings  up  to  the  date  of  report  are  appended  in  Appendix  A.  The  Ministry  of 

Finance was also represented at subsequent meetings. 

 

 

  

Page 29: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 26   

3.2 RATIONALE AND APPROACH 

The emergency nature of the works,  limited access and the attendant adverse impacts on 

logistics meant that predominantly all the clearing works were implemented on a day work 

basis. A small percentage that involved construction of structures, emergency repairs and 

highly  labour  intensive  works  were  implemented  on  a  works  contract  basis  through  a 

direct  selection  based  on  availability,  capacity  and  qualification  based  on  pre‐existing 

criteria. Examples  included bridge  reinstatement and repairs and construction of Vanard 

Intake. The day work rates were pre‐established rates  included  in  the Disaster Response 

Plan  of  the  MCWT&PU.    A  copy  of  the  Plan  is  included  in  Appendix  B.  All  claims  for 

payments had to be submitted to the Command Centre for review, auditing and processing. 

A review process was established for the accurate and timely processing of payments. 

 

A  critical  success  factor  to  the  efficiency  of  the  recovery  was  the  availability  of  fuel  to 

service heavy equipment.  The availability was constraint by lack of access to fuel stations 

due to blocked roads, unavailability of fuel at the few accessible stations, lack of access to 

site of emergency works and the limited ability of equipment owners (all small businesses) 

to finance the high fuel demand for their machines. A further complicating issue was that 

the  various  pieces  of  equipment  on  one  particular  site  were  of  varied  ownership.  This 

would have posed a logistical nightmare for each machine to be fuelled by its own team in 

areas  of  limited  access,  manoeuvrability  and  high  risk.    Considering  the  challenges 

indicated, to facilitate the implementation of the works, a policy decision was taken to pool 

the supply of  fuel  for equipment working  in some specific areas. The procurement of  the 

fuel would be done through the MCWTPU and delivered to three (3) contractors with the 

logistical capability to deliver and manage fuel.  A system of accountability was established 

for the delivery of the fuel. 

 

On December 1st, 2010 it was deemed that the prime objective of the emergency works had 

been achieved in some areas and all day works would cease with the exception of certain 

areas where progress towards the objective was entrained. However all day works stopped 

Page 30: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 27   

on 2010.   It was agreed that the remaining immediate works would be defined, estimates 

developed and appropriated Conditions of Contract adopted based on value and complexity 

of  work.  The  estimates  would  be  based  on  prevailing  rates  existing  at  MCWT&PU 

incorporating existing conditions. 

 

The focus on the recovery was public infrastructure and WASCO. The MCWT&PU assumed 

full  responsibility  with  the  support  of  WASCO  staff  for  the  reinstatement  of  the  water 

supply  in  the  North  and  parts  of  the  South.  Some  of  the  facilities  under  the  direct 

management  of  MCWT&PU  included:  Roseau  Dam  and  associated  transmission  lines, 

Vanard, Ravine Poisson, Talvern, Canaries  and Millet  intakes  in  the North. Technical  and 

logistics  support  were  also  accorded  to  the  Vieux  Fort  water  supply  including  the 

Beausejour and Grace Treatment plants and the Grace Woodlands Intake and the Fond St. 

Jacques  intakes  in  the  South.    A  more  detailed  discussion  of  the  works  follows  in 

subsequent sections. 

 

It is however recognized that in some areas private properties are still at risk from debris 

leaning  on  structures,  landslides  above  and  below  structures.  Responding  to  these 

circumstances  is  outside  the  remit  of  MCWT&PU  although  some  random  interventions 

have  been  undertaken.  It  is  the  view  of  the  management  team  that  a  special  fund  be 

established  by  Government  with  a  set  of  criteria,  based  on  socio‐  economic  factors,  for 

intervention either by MCWT&PU or the Ministry of Housing. 

 

3.3 EMERGENCY WORKS 

These works commenced on the evening of October 31st, with the immediate reinstatement 

of Bois D’Orange and Choc crossings. The Barre de L’isle was opened to  limited traffic by 

Sunday  November  7th,  2010.  On  that  same  date  there  was  access,  at  least  single  lane, 

through the entire primary road network.  

 

 

Page 31: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 28   

The approach to reinstatement of the infrastructure was governed by the following: 

Immediately  restore  critical  components of  the  infrastructure  to ensure access 

to basic services 

Protect  from  further  damage  to  components  of  the  infrastructure  that  are  at 

great risk to the effective functioning of the country and compromising safety 

Replace damaged infrastructure for improved performance 

 

Table 6 provides a summary of some of the reinstatement works and attendant activities.  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 32: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 29   

TABLE 6 MAJOR IMMEDIATE REINSTATEMENT WORKS 

Location Description of Works Status

Choc Bridge Backfilling of culvert, river training, concrete slab, boulder pack for scour protection

Complete

Bois D’Orange Backfilling of culvert, river training, concrete slab, boulder pack for scour protection

Complete

Anse Gallet Limited river training Complete Barre de L’isle Slide clearing, tree cutting, drain cleaning, rock

amour protection

Complete

Quarte - Chemin Soufriere

Slide clearing, tree cutting, drain cleaning, river de-silting, temporary culvert crossing, drainage construction, road reinstatement

On-going

Mon Repos Rock Amour, temporary bypass, guard rail

Paving outstanding

Troumassée River Rock Amour, backfill and river training Scour protection and underpinning required

Choiseul to Soufriere Slide clearing, rock breaking, tree cutting On-going

Crestlands – Fond St. Jacques

Slide clearing, tree cutting, drain cleaning, temporary culvert crossing

On-going

Grand Ravine Bridge Tree cutting, debris removal and de-silting Complete

Guesneau - Ti Rocher - Four Roads

Retaining wall construction On-going

Bexon/Marc Rivers De-silting, log removal and pumping On-going

 

A significant amount of the works was associated with debris removal. The clearance work 

had to be implemented while limiting further damage to the environment. A critical  issue 

was  the  location  and  availability  of  dumb  sites.  Albeit  the  concerns  the  choice  was 

governed  by  proximity  and  accessibility.  The  use  of  some  of  these  dump  sites  has  to  be 

viewed as short term and require further assessment to determine suitability and potential 

to  cause  further  environmental  damage.  It  is  also  recognized  that  some  of  the materials 

Page 33: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 30   

deposited at the dump sites may contain harmful contaminants. The next sections discuss 

the approaches to the various components of the emergency works. 

 

Rapid  assessment  of  each  situation  was  required  and  undertaken  to  determine  the 

condition of the failed slope, extent of damage to the  infrastructure, safety of the existing 

sites,  potential  risk  to  further  damage,  public  safety  and  whether  intervention  would 

exacerbate any of the preceding factors. This assessment in every case included  

3.3.1 UPSLOPE LANDSIDES (DEBRIS FLOWS) 

All  of  these  slides  deposited  the  loose material  on  the  infrastructure  below  and  blocked 

drains  which  in  some  cases  triggered  downslope  slides  by  redirecting  ravaging  waters 

away  from drains  into slopes. The assessment  for  these slides also  involved determining 

whether  clearing  would  have  triggered  further  slop  failures  or  the  landslide  mass  was 

required as part of  the solution. Most slides were cleared but Bagatelle, Ti Rocher, Mingy 

and Fond St. Jacques were determined to require further analysis. 

3.3.2 DOWN SLOPE FAILURES 

Most  of  these  failures were  cordoned  off  for  safety  reasons  because  in many  cases  they 

reduced the carriageway to a single  lane. This scenario  is prevalent  in the Barre de L’isle 

and sections of West Coast Road. There is a section of the Barre de L’isle which was under 

threat of  further collapse  from the  initial  failure; a rock amour slope stabilisation system 

was constructed to facilitate safe passage of vehicles. 

 

 

 

 

 

 

 

Page 34: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 31   

In the case of Ti Rocher the intervention required the immediate construction of retaining 

walls as  the community served by this road has a single access. The alternate access was 

obliterated  by  a  huge  landslide  while  the  landslides  on  this  road  had  reduced  the 

carriageway  to  single  lane  with  the  possibility  of  further  collapse.  Further  slope 

stabilisation works may be required at the toe of the constructed walls. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 35: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 32   

3.3.3 BRIDGES AND CULVERTS 

The emergency intervention was informed by: 

Type of Construction 

Failure mechanism and type 

Availability of alternative route 

Cost of short term reinstatement 

 

The  Bois  D’orange  and  Choc  crossings  were  constructed  of  multiple  large  diameter 

corrugated  pipes.  The  failure  of  the  crossings  involved  primarily  erosion  of  the  backfill, 

collapse of the headwall and partial collapse of the pipes. The pipes of the former were in a 

more  advanced  stage of  corrosion  than  the  latter.    There were no  collapsed pipes  at  the 

Choc crossing. The construction of bypasses was an option but would be timely and very 

costly.  The  most  cost  effective  approach  was  adopted  which  involved  backfilling  of  the 

pipes and overlaying with a 200 mm reinforced concrete slab. 

 

The partial  collapses at Bois D’Orange meant  reduced  flow and discharge  capacity at  the 

crossing.  A  strict  monitoring  and  debris  removal  programme  must  be  in  place  at  this 

crossing to minimise flooding and potential damage to the repairs.   A new structure must 

be constructed as soon as practically possible. 

 

The repair at Choc has more longevity because of the better condition of the pipe. However 

a new structure of a different type of construction should be built in the short to medium 

term. It is also likely that the protective corrosion resisting layer has been damaged which 

will  accelerate corrosion of  the pipes  resulting  in  reduced carrying capacity and possible 

damage of pipe lining by the erosive force of the flowing water. 

 

A bypass was constructed to the Mon Repos collapsed crossing after a load test was carried 

out with single axle 15  ton  truck. This option was significantly  cheaper  than  temporarily 

Page 36: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 33   

reinstating  crossing  by  backfilling  the  existing  crossing.  More  importantly  the  bypass 

allows for the seamless reconstruction of a replacement crossing. 

 

A  bypass  was  also  constructed  to  the  collapsed  Crestlands  Bridge.  This  was  the  only 

alternative because of location and damage. This bridge was completely washed away. This 

bypass is short term as the bridge must be reconstructed urgently. 

 

The Anse Gallet River crossing was not addressed although the corrugated pipe collapsed. 

However the debris inside the pipe provides support to the embankment and road above. 

No rechanneling or de‐silting works was carried out on the river because of the blockage of 

the pipe. The river was allowed to follow the new alignment as a result of the storm. This 

crossing  will  flood  with  the  lightest  of  showers  as  the  river  is  silted  up  to  the  banks 

resulting in temporary delays to users. A new crossing is required as a matter of urgency. 

 

The  Fond  St.  Jacques  Bailey  bridge  washed  off  its  abutment  was  dismantled  and 

repositioned on  the abutment. Additional work  is  required on  fixing  the  structure  to  the 

abutment. 

 

The work done on other bridges focused on removal of the debris load against   the bridges, 

namely  Fond  St.  Jacques,  Grand  Ravine  and  Tomazo.  Additionally  some  of  the  smaller 

culverts  on  the  ECR  were  backfilled  though  with  impeded  flow.  These  culverts  require 

immediate replacement before the next rainy season. 

 

A detailed inspection of the major bridges is recommended for possible stresses and early 

signs of failure. A number of the bridges may require retrofitting and strengthening. 

 

 

 

 

 

Page 37: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 34   

3.3.4 RIVERS AND STREAMS 

Most  rivers  and  streams  overtopped  their  banks  causing  flooding  of  the  surrounding 

communities. This was exacerbated by the heavy debris loads deposited by landslides from 

the  surrounding  hills.  The  communities  of  Fond  St.  Jacques,  Soufriere,  Bexon,  Marc  and 

Deglos were hit the hardest.   The emergency response involved removal of large volumes 

of  silt  loaded  with  tree  trunks  and  boulders.  The  initial  response  involved  clearing  the 

debris and silt from the adjacent infrastructure. 

 

The high level of saturation of the silt in the river channels and along the banks presented a 

major challenge to accessing the channels by excavators. It was impossible for excavators 

to maneuverer as they became fully submerged in the silt and Debris. Therefore immediate 

de‐silting works was not possible  following  the aftermath of  the Hurricane based on  the 

equipment resource available. 

 

Following the heavy rains of November 18, 2010,    significant flooding occurred at Bexon, 

Marc, Deglos and Cul‐de Sac. A policy decision was taken albeit the constraints; immediate 

intervention was  necessary  to mitigate  future  flooding.  It was  accepted  that  the  process 

would be slow, inefficient and costly but further loss of property was not an alternative. 

In other  cases  limited or no de‐silting or  rechanneling works have been carried out. The 

residents  in  the  lower  reaches  of  Fond  St.  Jacques  were  relocated  and  would  not  be 

impacted by swelling river flows in the short term. 

 

3.4 ASSISTANCE TO WASCO 

As discussed MCWT&PU assumed full responsibility for reinstatement of the water supply 

network. FDL Consult on behalf of  the MCWT&PU undertook  the  first visit on  foot  to  the 

Roseau Dam. 

 

 

Page 38: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 35   

3.5 ROSEAU DAM AND TRANSMISSION MAINS 

The emergency response required clearance of major landslides along the access road and 

reinstatement of a corrugated pipe culvert. The Ministry also coordinated the restoration of 

the electricity supply and cleaning of the pump house, generator and surroundings.   

 

There  were  three  breaks  on  the  transmission  which  were  repaired  by  WASCO.  This 

required  the  construction  of  thrust  blocks  which  were  undertaken  by  a  contractor 

appointed by the Ministry. All the associated works including access was undertaken by the 

Ministry. 

 

Some of the future considerations are: 

Stabilisation of the slopes along  the access road 

Reconstruction of the existing culvert with a reinforced concrete box culvert 

Assessing vulnerability of transmission line between the Dam and Vanard 

A comprehensive survey of dam including bathometric survey, backup systems, and 

structural integrity of major components.  

 

3.6 MILLET AND RAVINE POISSON INTAKES 

 Ravine Poisson involved a cycle of clearing followed by immediate re‐silting because of the 

volume of  landslides upstream. There was also an  issue of disposal of  the  silt  to avoid  it 

being  washed  back  into  the  intake  and  downstream  into  Bexon.  The  site  was  also 

inaccessible  to  trucks  while  the  land  surrounding  the  intake  was  claimed  to  be  private 

property. 

 

As  a  long  term  solution  consideration  should  involve  the  construction  of  a  silt  trap 

upstream. Also  the  landownership around  the  intake needs  to be clarified as  these  lands 

can  be  used  to manage  properly  the  silt  since  this  intake will  be  silted  continually  from 

landslides around the watershed. 

Page 39: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 36   

The  Millet  intake  was  inaccessible  via  the  existing  access  road  which  was  completely 

severed by a landslide. An alternative access road was required to get heavy equipment to 

the  intake. All  servicing  of  that machinery  included  fuel  had  to  be  transported manually 

through difficult terrain making the exercise very costly. 

3.6.1 CANARIES INTAKE 

 The intervention involved reinstatement of the access road to the intake site, relaying and 

transporting  replacement  pipes  and  the  partial  construction  of  a  temporary  intake 

structure.  Further  work  on  the  intake  was  suspended  after  the  French  and  American 

Government donated small water treatment facilities.  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 40: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 37   

4 THE  WAY  FORWARD  

Taking into account the factors described above there is a clear need to identify a sensible 

and reasonable approach to managing the vulnerability of the existing roads, drainage and 

structures, which are  still  exposed  to  the  slope‐related hazards  and consequential  fluvial 

hazards, post‐Tomas. This will require both remedial and preventative works.  

 

It must be accepted that the existing roads and river crossings will suffer in the future from 

some damage and blockage by landslide debris and erosion during prolonged wet periods. 

It  seems unacceptable  that  such  processes  should  be permitted  to  continue  in  key  areas 

where there is dense population or vital services infrastructure. Some stretches of road will 

inevitably suffer severe damage since preventative work may prove to be too costly, i.e. it 

may be more cost‐effective to permit the damage to occur and then rebuild the stretch of 

road  using  a  more  appropriate  design.  Monitoring  of  these  areas  must  be  considered; 

either as permanent telemetry installations, or frequent site inspections during periods of 

prolonged  wet  weather.  Construction  of  upstream  debris  control  structures  must  also 

feature in this strategy (such as permeable rip‐rap bunds, columns and cable traps). 

 

Hence,  there  is need  to  identify  and  categorise  the perceived hazards,  and  then  to  relate 

them  to  the  risks  to  assets  and  to  disruption  to  livelihoods.  This  comprehensive 

information  will  be  managed  using  a  GIS  computer  program,  in  order  to  extract  vital 

information quickly and accurately. 

 

The  Landslide  Database  that  FDL  is  compiling  comprises  three  components:  field  data 

sheets,  office  technical  appraisal  sheets,  and  a  computer‐based  GIS  system  (prototype 

recently developed by consultants for the Ministry) which will combine the two sets of data 

into  a  user‐friendly  platform.  This  will  be  a  ‘live’  database  and  will  require  frequent 

updating to reflect events, including remedial works. 

 

Page 41: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 38   

This information should also be used to assess planning applications for new construction 

and possibly to establish new criteria for planning consent.  

 

At present the most prudent strategy has been:‐ 

Obtain a photographic record of all slope damage that has had a significant impact 

on infrastructure; 

Obtain  a  post‐Tomas  land‐satellite  digital  image  of  Saint  Lucia  (or  at  least  Google 

Earth  prints)  and  identify  the  locations  and  geometry  of    the  slides  including  the 

extent of local catchment, and potential future debris sources; 

Using  experienced  geotechnical  and  civil  engineers  identify,  prioritise  and  agree 

(including  stakeholder  agreement)  which  areas  require  stabilisation  or 

management measures (using the database which is currently being completed);  

Agree  a  budget  expenditure  profile  for  the  next  6  months  (say)  and  carry  out  a 

second iteration of prioritised areas (after the next wet season) having established 

budget costs for each element of the proposed works; 

Develop  sketches  and  quantities  for  individual  temporary  works  designs  and 

provide close supervision of the contractor; 

Hold  frequent  liaison  meetings  to  maintain  agreement  and  support  as  the  work 

evolves; 

Develop detailed designs and Tender Documents to attract competitive tenders for 

the main permanent works schemes. 

 

 

Page 42: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 39   

5 COST  ESTIMATES  

They  include  preliminary  cost  of  immediate,  short  and medium  term  emergency works.  

These  estimates  are  preliminary  are  subject  to  change  with  detailed  investigation.  The 

immediate works  are primarily  clearing of debris,  critical  river de‐silting,  diversions  and 

temporary  works.  They  were  aimed  primarily  at  restoring  immediate  access  and  basic 

services. The short and medium term costs  represent  completing some of  the  immediate 

works and preserving the components of the infrastructure under direct threat of further 

damage  with  consequential  paralyzing  effect  on  the  functioning  of  the  country  and 

compromising safety.  It is mainly stabilisation works.  These represent rehabilitation and 

reconstruction cost  for the  infrastructure to the pre Tomas condition with  improvements 

to mitigate future disaster risk based on engineering principles.  They have not factored the 

broad  spectrum  of  disaster  risk  reduction;  for  example,  while  a  new  bridge  may  be 

designed  to  reduce  risk  of  damage  for  a  similar  type  disaster,  fully  mitigating  risk may 

involve implementing comprehensive watershed management.  

 

The estimates were arrived at using prevailing construction cost data from MCWT&PU and 

recent  contracts  implemented  locally.  A  physical  contingency  of  30%  should  be  added 

because of the estimating risks both in terms of scope and assumed optimum engineering 

solution.  

 

Finally,  the  indirect  costs  of  the  damage  are  not  included  and  outside  the  scope  of  this 

consultancy. A detailed cost of the damage is included in Appendix C. 

 

 

 

 

 

 

 

Page 43: Tomas Damage Assessment No Pictures

 FDL Consult Inc  Hurricane Tomas Damage Assessment Report 

December 2010    Page | 40   

6 RECOMMENDATIONS  

The following are recommendations which should not be considered exhaustive: 

Review of the recommendations and level of implementation of existing watershed 

and environmental management plans. A new plan may be required in light of new 

observations and climatic data; 

Geotechnical assessment of all major landslides; 

Update of landslide hazard map; 

Reconstruction  of  Bois  D’orange,  Choc,  Crestlands,  Grand  Ravine  and  Canaries 

bridges; 

Structural assessment of all bridges; 

Retrofitting of bridges where required 

Immediate de‐silting of rivers in Bexon, Marc, Deglos  and Soufriere River; 

Immediate  lope  stabilisation  works  on  all  failures  affecting  the  primary  and 

secondary road network and major tourist attractions.