tlona:rffe~~c~~ contents ~orcommunffy … with pre—cast roof) afternoon discussion with...
TRANSCRIPT
rn—2—
Contents
Preliminary Remark n
1. Objectives and Approach N
2. Schedule of Activities
3 Major Dates of Implementation
4. Organizational Set-Up
5. Target Group Analysis — Selection of Beneficiaries
5.1 Selection of Villages
5.2 Procedure of Target Group Selection
5.3 Evaluation of Questionnaire Survey
5.4 Special Features of Target Group Selection
5.5 Assesament
6. Technical Aspects - Toilet Design and Execution
6.1 Seloction of Design
6.2 Assessment of Execution
7. Socio-Cultural Aspects — Awareness Building
7.1 Introduction — Background
7.2 Findings
7.2.1 Quantitative Aspects
7.2.2 Qualitative Assessment
8. Proposals and Recommendations
9. Working Summary
Appendices
1. Vikas Kendra: “Bird’s eye view of our awareness
campaign on low—cost toilet project”
2. Form of questionnaire for socio—economic survey (target
group selection)
3. Vikas Kendra: “Low—cost toilet status report as on
16.07.1993”
4. Vikas Kendra~ ‘Bird’s eye view of socio—economic survey
report as on 22.07.1993”
~2SRARY.NTEr?~:fi\TloNA:RFFE~~C~~~ORCOMMUNFFY WATE~1~‘Jr~L~ A~DSANITAT~G3~URC’~
Society for Equitable Voluntary Action (SEVPj, Calcutta/Indis
Indienhilfe e.V. , Berrsching/Germany
Low—Cost Toilet Pro]ectat
Vikas Kendra, Atghara/West Bengal
Report on Project Review Tour from 12th to 17th July 1993
by
Hans Escher
BahnhofstrsRe
86504 Merching
Germany
August 1993
if’C’w32:
NN03
—3—
Preliminary Remark
For the midterm—assessment of the low—cost’ toilet pro]ect of
Society for Equitable Voluntary Actions (SrA)/Vlkas Kendrs the
author proposed - due to various reasons the month of July,
1993, a time, when sonsoon in Bengal reache its peak.
Despite the adverse weather the programme o the review could be
carried out as per schedule.
and the neighbouring
h!3s lent me all the
t eir assistance I am
Herrsching/Germany, August 1993
Hans Escher
—4—
1. Objectives and Approach
The purpose of this review was to avail the implementing NGO a\
feedback from an outsider while the project was still executed. C
The review happened to be undertaken, after more than half of the
toilets had already been completed. At that time construction
work had, as foreseen in the planning, stopped to a large extent,
as due to the monsoon many villages were inaccessible. So this
break, which VK-staff had anyway earmarked for a review, luckily
coincided with the reviewer’s visit to Atghara. It was hoped that
an outsider would bring over fresh inputa and inapirations for
the remaining part of the project and possible extensions of it.
In the planning of his stay the reviewer saw to it that he would
get as much exposure to the “grassroot reality’ as possible. This
implied that on all days besides the days of arrival and
departure trips to various villages were made. There the reviewer
could not only get a look at toilets in various stages of
completion, but could also intensively talk with beneficiaries
and contact persons from the village organizations - the in—
charges for the toilet project in their areas.
L~Y~ :~~H~r:~“ ~L ~EF?~ENCEI F “ • ‘ ‘~VIER SUPrLY
gAEl) L -‘~
ID y~’7’~a’-~ t~I
~— I/In -
LO: 9~——
As Vikas Kendra had set up a very efficient monitoring system,
data about the project were readily available. Regarding the
quantitatiye~aspects_the_Jmplementation_of_the_project_haa~been -
-fully according~ to plan. As the exchange rate developed other - - -
than calculated in the project application to 8HZ, there are evenfunds left for construction of approximately 100 additional
toilets. (At the beginning of August 1993 8HZ gave permission to
use the funds accordingly.)
Due to the limited time available a systematic questionnaire
survey was found to be beyond the reviewer’s capacity. A cross—
check of the selection of beneficiaries was therefore not
attempted. So the evaluation of the target group analysis relies
to a great extent on a scrutiny of the questionnaire survey which
had been done by Vikas Kendra.
Regarding design and technical execution of the toilets the
reviewer incorporated the assessment of two representatives of
Central Building Research Institute (CBRI) , with which Vikas
Kendra is continuously in contact. The reviewer had the
opportunity to interview the representatives on 15th July 1993 at
Vikas Kendra.
For the numerous field trips in Atghara
villages staff members of Vikas Kendra
support and co-operation necessary, For
most grateful.
—5—A survey about the quantitative aspects was supplied by Vikas
Kendra at the beginning of the stay in Atghsra. So during his
field trips the reviewer could concentrate on taking a look at
the toilets and on interviewing beneficiaries and village
organization members. As the technical aspects had been covered
by CBRI, the reviewer could focus on the socio—cultural aspects
of the project. Here one of his chief interests was to gauge the
impact of awareness building measures. In this regard a list
detailing awareness building events which had been carried out in
the framework of the project had been drawn up by Vikas Kendra.
tour to Purba Simla
pick—up of representatives of CentralBuilding Research Institute (CHRI) at
Maslandapur railway station
tour of Maslandapur and Kirtipur (model
toilets with pre—cast roof)
afternoon discussion with CBRI—representatives
In order to become aware of possible diverging perceptions the
preliminary results of the review were presented at the final
meeting with the core team/low—cost toilet task force of Vikas
Kendra. There Vikas Kendra accepted the basic findings of the
review. The exchange with Vikas Kendra about possible
modifications in planning and implementation of the project will
continue after completion of this report.
pick-up from Calcutta airport andjourney to project area
meeting with Vikaa Kendra (VK) core teamand low-cost toilet task force in
Atghara, mutual introduction,
presentation of objectives of project
tour
introduction into administrative
infrastructure of low—cost toilet
project by VK-staff members;
presentation about monitoring of
construction activities by Srikantha
Mandal
tour of Atghara village and of Bagan
Atghara
Thursday, 15th July
morning
afternoon
meeting of Vikas Kendra core team and
presentation of Preliminary findings
with discussion
interview of contact persons of village
organisafion~ who had come to a meeting
to Vikas Kendra -
journey by train to Calcutta..
night stay at SEVA office in Calcutta
meeting with Mr. Kumar Ray, chartered
accountant. Briefing by him on his
midterm assessment of the accounts of
low-cost toilet project
working committee meeting of SEVA,
mutual introduction, presentation and
discussion of findings of project tour
12 noon
afterwards
function at Dishery Sangha village
organization in Pashim Simla in honor of
project director VK and visitor
tour of Paahim Simla
Wednesday, 14th July
morning
—6—
tour to IVarayanpur
presentations hy individual
members and paperworkVK-gtaff
2. Schedule of Activities
Monday, 12th July
12 p.m.
5p.m.
Tuesday, 13th July
9 a.m.
afterwards
Friday, 17th July
morning preparation of draft of review
afternoon
evening
Saturday, 18th July
morning
afternoon
afternoon tour to Nikrahati village
BMZ sanctions advance use of
Indienhilfe’s contx~ibution
Vikaa Kendra core team meeting.
Elaboration of plan for construction of
toilets I!Message by phone from Indienhilfe to
SEVA/VK: 1000 toil~ts have been granted
byBMZ
Start of introductory meetings/awareness
building activities with village groups;
each village group~nominates one contact
person.
Opening of complaint book for village
groups, beneficiaries, masons
Socio—economic survey and selection of
beneficiaries (97Oc selected; selections
from panchayats [village councils] still
awaited; 75 rejected due to non-
fulfillment of the criteria(
reduction/suspension of building
activities due to sonsoon
midterm review by representative of
—I-nd-i-enh-i--Ij-f-e
visit of -represecitatives of Central
Building Research Institute (CBRI)
Inspection of t~ilets, approval of
construction. ——~Toi1ets are released
for general use.
372 toilets are tdlly completed
—8—
4. Organizational Set—up
After the funds had been sanctioned for the project, Vikas Kendr~r
set up a low—cost toilet task force, in which the majority of its
staff members was and is represented. Through regular meetings
(on average three times per fortnight) a regular flow of
information was assured.
A key role in the implementation process was assigned to the
village organizations. These consist mainly of young persons,
engage themselves in the fields of social service, culture
sports. Vikas Kendra has for long established close links
them, as VK co—operates with them also at other measures.
members regularly take part in VKs training programmes.
The village organizations constitute the crucial link between VK
and the individual households. They have the task to communicate
all the relevant information, ranging from operational aspects to
matters such as health and hygiene, to the participating
families.
The overall monitoring of the project is, however, done by VK.
For this purpose detailed records are maintained at its project
centre. As on every toilet building a serial number is imprinted,
the construction of the 1000 toilets, which are spread over 26
—v-ill ages-,—can—be—mon-i-tored—easaLy. -___________________________
An excellent infrastructure for the implementation as such is,
however, not sufficient. The people, who are involved in
executing the project, and their commitment is of equal
isportance.
For the reviewer one of the strong points of the project is the
highly motivated team of VK-staff. They are not only able of
motivating themselves. Also the responsible persons of the
village organizations were found to be very enthusiastic and
committed. Through them true “grassroot’ activities become
possible. The basis for this is the close and trustful
relationship between VK—staff and the village organizations.
—7—
3. Implementation Low—Cost Toilet Project ~- Major Dates
24th February 1993
6th April 1993
27th April 1993
29th April 1993
May 1993
June — August 1993
12th — 17th July 1993
29
who
and
with
Their
— 15th July 1993
16th July 1993
The “material” and the “human” infrastructure assure a high
degree of effectiveness and efficiency in the project.
(ft
—9—5. Target Group Analysis — Selection of Beneficiaries
5.1 Selection of Villages
The following villages were selected (see also appendix 3; one
village organization per village unless otherwise stated)
Criterion for the selection was the degree of activeness of the
village organization and the intensity of their contact with VK.
Baduria block:
Atghara (3)
Uttar Simla
Chandpur
Dakshin Bena
Dakshin Simla
Dakshin Jangalpur
Srirumpur
Kirtipur
Malayapur
Mamudpur
Purba Pingaleswar
Narayanpur (2)
Paschim Simla
Naturia
Pingaleswar
Panji
Uttar Jangalpur
Purba Simla
Bagan Atghara
Ghoahpur
20 villages, 23 groups
Deganga block
Beliakali
Chandalati
Nikrahati
Bunarati
4 villages, 4 groups
Habra block
Vi jaynagar
Simulpur
2 villages, 2 groups
— 10 -
New groups, where toilets have been sanctioned, but work has not
yet started:
Solua Group, Village Sanhati, Habra block
Kolsur Udayan Sangha, Kolsur, Habra block
5.2 Procedure of target group selection
The thrust of the project is to provide individual families with
toilets which would be erected on their premises and become their
private property. According to the planning the following groups
should primarily benefit from the low—cost toilet project:
— Small and marginal farmers (marginal farmer: upto 6000
Rupies annual income for a family of five; size of
agricultural land: upto one hectar [1 hectar = approx. 2.5acres]; small farmer: upto 12.000 Rupies income for a family
of five; size of agricultural land: upto 2 hectars)
— Scheduled Castes and Scheduled Tribes
- Other disadvantaged people such as handicapped persona,
widows and old-aged persons
As a first step the village organizations proposed families for
selection to VK. A surveyor from VK then visited the individual
households in order to get a first impression about the social
status of the family through various indicators such as
- does the family own a two-storeyed building~
- do one or more family members have permanent employment in
the organized sector?
At a later stage a thorough socio-economic questionnaire survey
was made (the form of the questionnaire, translated into English,
is documented in appendix 2)
5.3 Evaluation of the questionnaire survey
A tabulation of the information contained in 750 questionnaires
was done on 22nd July 1993 by VK-staff members (see appendix 4).
Coverage
Through being a member of one of 750 households a total of 4778
persons (1445 males, 1238 females and 2095 minors) gets access to
toilets. The average household size amounts thus to 6.4.Total
26 villages, 29 groups
— 12 —
— 11 —
Religious and Social Status
3671 persons (77%) are Muslims, while 1107 persons (23%) are
Hindus. These ratios are approximately proportionate with the
overall population shares of both communities in the area.
Of the benefitting Hindus 814 persons (76% of the community and
17% of the total of 4778) belong to Scheduled Castes and 16
persons belong to the Scheduled Tribes cate~ory. (According to
the 1991 census the share of Scheduled Cast~s in West Bengal is
24%. In the project area the share of Scheduled Tribe population
is negligible.)
Income
Of the 750 families 268 (36%) had an annual~ income of less than
6400 Rupies, The income of 378 families (50%~ ranged between 6400
and 10.000 Rupies. 104 families (14%) disposed of an income of
more than 10.000 Rupies. (Unfortunately it ~~aa not enquired, by
how much exactly their income exceeded the sum of 10.000 Rupies.)
Occupation
485 households (65%) have their mainstqy in farming. 101
households (13%) stated as their main occupation “daily
labour”. The remaining 164 households (22%) have employment in
other fields.
Land Ownership
- 101 households (14%) can be regarded as lai~dless, as they rated
themselves as daily labourers. Judging from~ the statements about
land sizes the share of landless agricultufal labourers say be
even higher: 312 families (42%) own less than 0.33 acres of land,
363 (48%) from 0.33 acres to 2.5 acres and’75 (10%) between 2,5
and 5 acres. Families owning more than S ac~es were not selected.
The marginal land sizes include also the fkarmstead area, which
may explain why there is no category of “landless families” in
the tabulation of beneficiaries according t~o land ownership.
5.4 Special features of target group seleètion
On the whole 10 handicapped persons were selected for
participation.
In Atghara Mahila Mandala, the village’ women’s organization
was alloted a quota of eight toilets. The ~~orresponding number of
families in the Boidupara para (neighboufrhood) of Atghara was
duely selected.
VK sanctioned on request a quota of 10 toilets for two panchayats
(village councils), which will allot them ‘to private households.
For the following public institutions toilets were sanctioned on
request:
— hath (local market) Atghara: 1 toilet
— Public Library Kolsur: 1 toilet
- mosque Uttar Simla: 1 toilet
— 2 mosques Bunarati: 1 toilet each
5.5 Assessment
Taking into account the average family size of 6.4 and the fact
that no household owns more than 5 acres land one can assume that
the overwhelming majority of the beneficiaries, i.e. at least the
86% whose annua] income is below 10.000 Rupies, lives below the
poverty line. In addition the fact that 65% of the beneficiary
families live on agriculture and that 13% belong to the daily
labour category indicates that an overwhelming majority of the
participants belong to the category of small and marginal
farmers.
Equally the categories of Scheduled Castes/Scheduled Tribes and
disadvantaged persons are well representad in the group of
beneficiaries.
The overall correspondence between the actual target group
selection and the criteria given in the planning is high.
Some applicants’ farmstead size was-to small to guarantee the
minimum distance between toilet and water source. Their
applications could not be considered. As these applicants might
belong to the “poorest of the poor”, ideas should be developed
about possible solutions for them. These solutions can possibly
only be found on a case—to—case basis.
— 13 — — 14 —
6.1 Selection of Design
The design of the toilet was selected in F0)~1abo~ti0n with the
Central Building Research Institute (CBRI)’. The model of two pit
hand flushed low—cost toilet was chosen. According to CBRI this
model is universally accepted for rural areas and is also
employed by the reputed Sulabh Mo’~ement and international
agencies such as UNICEF.
CBRI is a Government of India (GUI) research institute, which has
its headquarters at Roorkee/Uttar Pradesh. It is under the GOl
apex research body of CSIR (Centre for Sdience and Industrial
Research). Working areas of CBRI include the development of low-
cost building materials and technology.
Vikas Kendra is in close contact with Mr. Bose, scientist—in—
chief, and Mr. Dasgupta, in-charge civil engineering, of the
Calcutta branch of CBRI, amongst whose tasks are development,
construction and extension in the building sector.
The reviewer had the opportunity to interview Messrs. Bose and
Dasgupta on 15th July 1993 at Atghara. He was very grateful thatthis meeting had been arranged by Vikas Kendra, as the technical
aspects could thus be covered by specialists.
Several special features of the execution of the model at Vikas
Kendra were discussed:
- Vikas Kendra uses fibre glass as material for the pan. It is
of a reasonable cost, as it can be manufactured locally by
small—scale companies. It is of light weight and experience
so far has shown that it is durable. The experience with the
coating has been so far very good. Toilets which had been
built in 1987 with the same type of pan have so far shown no
wear—off.
- The bottom of the pits remains uncemented. The standard
material to fortify the pits is bricks. Earthen rings were
found to be considerably less costly and were therefore
applied by VK. These earthen rings are manufactured in West
Bengal usually for the support of wells. As there is a good
quality of clay available, the durability of the earthen
rings is quite high.
- Originally it was proposed to use recycled materials
drums for the doors of the toilet. As used material was
so popular with the beneficiaries, new sheets, which
sore shining and which look more attractive, had to
taken.
— The CBRI—representatives lauded the “package approach” of
Vikas Kendra, i.e. the fact that the beneficiaries receive a
100%—complete toilet in exchange for payment of a lump sum
of 500 Rupies and procurement of local sand.
They mentioned that Government of India agencies had built
at least 10 toilets in Baduria block (where also Atghara is
situated) upto the plinth level with the expectation that
the superstructure would be done by the users themselves.
Theme toilets have not been completed and lie still idle.
- The CBRI—representatives were of the opinion that the
toilets constructed by Vikas Kendra cost less than those
executed by government agencies such as Public Works
Department (PWD) . This is due to the close supervision of
Vikas Kendra and due to their highly motivated team, which
is very keen for possible savings.
6.2 Assessment of Execution
- According to the CBRI-representatives the construction quality of
the, toilets is according to the standard required.
Beneficiaries could not be interviewed regarding their
experiences with the toilets, as these were released for use only
after CBRI had given its approval on 15th July 1993.
The solid superstructure of the toilets was generally appreciated
by the beneficiaries.
The satisfaction of CBRI with the work of Vikas Kendra is also
reflected in the fact that CBRI wants to continue collaboration
with this organization.
7. Socio—Cultural Aspects — Awareness Building
7.1 Introduction — Background
It is generally agreed that in the past technical and
quantitative aspects in sanitation projects have often received
sore—than—sufficient attention, while socio—cultural aspects have
rather been neglected. This has lead to a low degree of
acceptance among the target population. As a consequence
sustainability was also severely affected.
6. Technical Aspects - Toilet Design and Execution from
not
are
be
—15—
On this backdrop the reviewer was particularly keen to assess the
motivation of the participants as well as their motives for
participating.
Due to previous efforts of VK the star�ing position for a
successful propagation of toilets in tite project area is
favourable. According to VK—staff members, toilets are not,
unlike at the outset of its work in 1985, something totally
strange. At that time 15 toilets had been~ constructed in the
framework of a pilot project. Then beneliciaries had to be
cajoled into accepting sanitation. A secon~ project under which
300 toilets were constructed in 1989 showed already a better
response. The fact that these toilets were~accessible and could
be seen functioning dispelled many doubts1~ So by example the
popular belief that nuisance through smell ~would increase could
be refuted easily.
First reports from VK from April 1993 had already shown that the
demand for toilets was higher than the number of toilets budgeted
for
7.2 Findings
The low—cost toilet task force of VK itself had met 16 times. In
order to interest the village organizatiods two meetings with
their leaders (attendance: ca. 60 persons iac~~) had taken placeat an early stage of the project (19th April and 6th May 1993)
In these meetings it was announced that each village organization
should nominate a contact person for the lou-cost toilet project.
In order to inform and motivate these contact persons meetings
were held on 13th May 1993, 9th June 1993 ~and 23rd June 1993,
— 16 —
A motivation training, which was attended by 72 persons, was held’
on 23rd June 1993.
7.2.2 Qualitative Aspects
As already mentioned, the interest to participate in the low—cost
toilet project was unexpectedly high. The demand for toilets
could not he fully satisfied. Therefore the necessity to
“advertise” for the project did not arise.
In the course of his tours to the villages the reviewer asked
both contact persons of village organizations and beneficiaries
for explanations for this strong interest.
The following motives were most often mentioned:
The linkage between toilet usage and the health situation of the
area was rarely mentioned by the respondents. Through
interviews with representatives of the village organizations the
reviewer got the impression that the awareness building events
focussed mainly on
— organizational aspects of implementation, and
— cleaning and maintenance of the toilets.
Life becomes much more convenient, once the toilets are on
one’s own property and thus within easy reach. Previously
the family had to walk some distance to reach the “toilet
ground”, if necessary also during adverse weather in themonsoon season. Due to the preconceived notions of shame the
women would to the toilet only in the dark. Because of thisFor the reviewer this presented an amazing phenomenon, as studies they were compelled to limit their intake of fluid and food
he had come across so far, had rather strem~ed the difficulty of during the day. Now life has become easier for them.
transition from traditional systems of defecation to the usage of - — For many people it appeared to be a good deal to receive a
toilets- So the assessment of the sot
const ij~es_cjf_the—benef-i-c-i-ari-es - ~ Ruptea f0rituted one of the key questiona ot hia4interviewa-. - - the highl~ subsidized price of 500 Ru~ies. Moreover the
contribution demanded of the beneficiaries in the form of
\I
labour was manageable. All organizational matters weretaken care of by Vikas Kendra and the village organizations.
7.2.1 Quantitative Aspects - In the project area “kutcha” structures, i.e. buildings made
Regarding the numbers of awareness building events Vikaa Kendra of clay with paddy straw as roof, are still very common.
supplied the reviewer with a summary (as Jf 8th July 1993) in Pucca structures, buildings made of bricks with tiles as
tabular form (see appendix 1) . From this summary it can he seen roof cover, are the symbol of prosperity and indicate a high
that all the villages covered by the project were visited at social status. Several respondents praised the “solid” or
least once by VK—staff. The 37 meetings in1the villages, which “permanent” structure of the toilets and expressed their
had been organized by the village organiza�ions and which were pride about owning such a type of building.
addressed by VK-staff, were attended by more than 800 persons
(including multiple attendances) .
— 17 — — 18 —
The latter point was mentioned by the ma]ority of the
respondents. The reviewer had the impression that in the course
of various meetings the topic of cleaning, and maintenance had
been communicated in a sufficient way
An indicator that the new toilets will actually be used and
maintained is the fact that the toilets from previous pro]ects
are still in use This could be ascertained by the reviewer, as
he inspected some of these toilets.
8. Proposals and Recommendations
While the operational and technical parts of the project
been dealt with to the full satisfaction~of the reviewer,
main recommendation for the final project phase is to focus
on awareness building measures.
As the beneficiaries gain through the project an asset of
considerable value, there should be a certain preparedness on
their side to participate in awareness building measures.
These awareness building measures should have two objectives:
a) demonstrating the impact of toilet us~ on the general health
situation -
b) increasing the awareness level on hygiene in genera~.
The propagation of low-cost toilets is a welcome occasion forincreased efforts in the field of general
1hygiene education. If
one takes into account the supergoal of the pro]ect — reduction
of the incidence of infectious deseases —, it is clear that the
level of hygiene in general has to be raised. Possible topics
under this heading could for instance be
- washing of hands, especially before meals
- handling of food
- how to impart hygiene education to children
- disposal of solid waste.
As the reviewer had the impression that so far only one person
per family participated in awareness building events (while the
average beneficiary family consists of six persons) , it is
suggested to reach out at least to all the adult members of a
family. In case it is difficult to get a response from women,
separate events for them, organized by female staff of VK, should
be considered.
A precondition for increased efforts in conscientization would be
to initiate a “training of the trainers”, i.e. of VK-staff, in
general hygiene. For this purpose VK could make use of its
contacts to All India Institute of Hygiene and Public Health
(AIIHPH) , Calcutta and International Training Network (ITN( . This
institution is part of the sanitary engineering department of
AIIHPH and is sponsored by the Hinistry of Rural Development, New
Delhi, and by the Overseas Development Administration )ODA) of
UK. Other Indian NGOs, which offer training in this sector, may
be considered as well.
9. Working Summary
The low—cost toilet project of Vikas Kendra in Atghara/VQest
Bengal was visited by the reviewer from 12th to 17th July 1993.
At this stage 970 beneficiaries had been selected and 372 of the
overall 1000 toilets had been fully completed. Through awareness
building measures from April to June 1993 more than 800 persons
had been reached directly (including multiple attendancem) . The
project is implemented in 26 villages with the help of 29
local organizations.
Through an excellent monitoring system, which has been installed
at the Vikas Kendra project centre in Atghsra, up—to—date
information about the progress in construction of the widely
scattered toilets is permanently available. Hotivation and
commitment of VK—staff and members of the village organizations
were found to be at a high level. The co—operation with the
village organizations is very close. Through them an intensive
participation of the target group is assured.
The selection of beneficiaries was to a very large extent done
according to the criteria laid down in the project planning.
According to representatives from Central Building Research
Institute (CBRI) the construction of the toilets was executed in
a professional way.
have
the
more
As result of measures related to objective “a” the
should become aware about the impact of the
defecation practices on the incidence of infectious
beneficiaries
traditional
deceases.
I,
a: ~ aa ‘a a S
-f~ I—— S
S
if~
~
a~ 5C ~
£a
S
L j ~.iin U.3 58 5 8 1 ~
~ ,: 1, ~14H fff~ ~ ‘: ~~ h .~ hl-:L s H fl=~ g °‘‘flE2 55 1I f3hJ~Ilif U iI1~~
~ s~f~s:~:~ n~: ~
5 3’,,au1 C~
5,. 5,,
BU’
Appendix I
a , I
a a, a’ a,
~ a:a:’0. ‘;
. C
-.4 C CS a a
U’
CS!
:s g a,
C 4’ C S533
S
— 19 —
Awareness building activities could be inten~ified so that a
greater understanding about the relevance of toilet use for
public health can be reached and knowledge about hygiene in
general becomes more widespread.
Overall Vikaa Kendra has reached a high levelA of competence in
the field of sanitation. The reviewer strongl’y recommends Vikas
Kendra as executing agency also for future sanitation projects.
The reviewer found a very strong motivation ~among VK—staff to
continue work in this field.
Herrsching/Germany, August 1993
~
Hans Escher
r I
~ aC 81 8C S.
gg ~ 2~5 ~ 2~128!
aS a 55 3
- S a i~ ~ ri-i i ~8, ~ I ~8FaYIr a ,a~auC
S CC• •CC IS
858 a855g& C~U’R 5 ,~CaC5 a
~, ~ ~ £
H 8, ~55d8I ~J8;fl H~ ~H1S! ~
S
I 4’ — ~ . Ce :s: !~!1~22 29:~ ;an ~‘IC C -,
I.,.
~? -~ ~‘•o,,- -D ‘1 ~
w I-. ~ SSa’
U)I-” C LUaD S Sa a’ a,
4-’ I-’. a, a’I-aU 0 ‘< 305 La 0 r
4C a ‘1 Laa-to Cr - Cr
a,0 0‘a, -,
‘1ID C? Cr
- am
3.0 CF-’ La F--
(am F” ‘~,Or’- ‘0 3ci— a C-‘n a al-
Cr CC ‘1
ao I-i a,
a-C
a- a-a DI a’
0 0
s~ 2a, a-C C
LU 30 00 a-C (4’5 La
La
~~a’‘<0‘-a
a,a-C
CC F’-
II- .0 II-a, a’ I-.-0 ~I 0
Ptma’ a-
a-P (U a0-o a
,Drr 0~‘10 DI
a-I-ID
a-a-CCl-C
~
a’‘1(4’0a
a ~ . LU. (.1 A E.~ ,l LA 4 N3 t~) P.4 P.4 -~ -~ -,
0 0 0 0 0 0 C) 0 C) 0 0 0 0 C) C) C) 0 0 C) C)En ~ L.I P3 -~ (U’ ~ (.4 P3 (11 h. (~! P3 (U’ ~ LA p1 -.
I-. C0 5I) a’~
0-a,
a-’-a-ID
ei-I—.
a-aLaIDC
:3 ,~ -~ -‘a0 0 pI 4)• I-’ ~ Cr S La
a, 14 DI I’ I-.-0 14- I--’ — I--’a, ‘K ‘< ‘<
F”P1 z m .-‘ aw 0 3 a o-, ‘1 • 0. 0 0a ID 0 C— 5 0 5 .03 DI -a, ID CaD F-’ a-P
C ‘l 0 I-’-:3 a, ~a’ a
ID 5 “1 3La F’.0. F” C
3 -< aF”a ~0- C S‘1 5
0~II‘I(I
U) :3 -‘1o C 4)a- I—. a-p5 — a-0. an a,C a.’ ‘-aF” 0 -cu a (a
~0a,
01am0-‘I
n -‘-.~a-
(~) C0) 14’C 0.a-,- - CC 3
0.U)
,-ra-C
010.0F”F..0a,aa-I-
oa-C aIi 01C aF” CIC0.
-ipaF’0.
ID‘10
-a,
a-a,-9CLaF’-F”
:—I0.F,-IIIF”
.0.0a-P 0
a- 0 ‘-aI,
~a 5 .0DI 0 UI
(-I—J 0 —
r’l L~ :3—~ (APiC, wr.1 .0C,
—C-b
C—
1t~
14
P3
— — — —— — — — — — I ——
a-Ph
a-C
.0I,0
ID0rt
0
a,0ra-0Ii
[Q~,AJ COST TOILETNAME o~Tl-~EO9~NJtSNV)O~
A~1%A(Mmcu1£Od~~~IDt
PROJECT STATUE_REPORT AS ON 16-07-33~ARTIi5N BR~KLoJoRu~L ? ~OVE~ 04D?~ W0ULUEN ThLS ~‘4HITD -
VILL A~E UNIT R~SETTINI :ULL HA (-4’ST ING~FiseS P~-AT~Fi~IN~FM”lL Fiuti~FIXING wP4sH~c(?~UoV~hoJ~-‘ 22 16 I~ I l6.~’l& i~ g~ 16 16 16 I~
pI,,hq~a.~O.~&dis&bclub “ 33 j~ 3_A~ha~MOhilQ. MOALdaL~GuIel’c.Iub~ ~d~o.a.A Pa.~ishc~
hai~a,UHo.~_6Lm’IIo~.~Bu’twi.~±~
-928~ 19
6J4t3
3a5
Z~
Si!i~i 23 13 23 ‘9
C~dJ3wI. ‘(ubQ. So.*~ba.DoAc~hL,tQuba.UiinyO.M 9a~c3%eQ.
~II)V~’U. I~$’ndrO..~eshba.4I4ko 5a~~5hQ~&vo,~&Sseva.~QMf~hQ.IQ#sJ4un...P4abOJUL~75~~a~ha.MaJLy4~ut~NaITol S’mitth Sapa-Mo..s.udplJt.AIcA4 4’~’~-
r~b~so.w~hQ~LAJQAL/U~ SO~bOj So’.AkrQf~4’~IIbPhAASoL~J& So,~ha.
- PaiL~U)Th’jO.U” 6c8.wL fl4)o~o~hc,y~.$IJTI~1D. ~OhOAi ~OA~?9h4..
PL~n~Ltswvt*c~d&To,wmScj~s4Ip~.p~~4p~a 7~k44tL Sam~P~&~t O..Qo~.S~ p~PTO~%ZrOU’tL sc~jh&Pua~bO~~ t~o.bo.Ko1i~oMSas~
cI-O~id~Oi~-—‘
~x~4çShLe~i~i~Q,” 2~~ ~miIO,-” 30
~s,tL~W.~U~2_IP
25~030
16 ‘I2638~
22~38i5’
22 2236 38
~
25~~
253~
o
2~
~
2238~s
22.3~
~
~h ~‘~- “3~MoJo~jo~~un—40Mo~wL)d~ufl— ‘~
PwzbaP~oit~~~ ‘~
~o..WUcx_ 21&~4aOfL’ 32
(~.Och~a~mt& 55p~IeswM~~~~q3po~’i ‘~
C. hOMdOJ.OJ “30~
Pu(LbO— ~m~& 2~
25
30I 842tO‘~22143312041I ~
24 t3030j~4~—
10 ~~ —
21 —
1331J —
4! —
16
21s
30
~3’(025’2135’II
II16
21 z~24—
‘~0 30 30
i~T~I ~ ~10 10~j 24 32ai ~ ~3 3 33I I ~
~ ~16 ~ 16
21
301631tO32.2133~ I
4116
30~~
32.21~~
~L~
24
30~
31102421
3I
IItG
30~
~I a2421
3I
~~
b~ft1c~a5ay~~ ~ ~W~t AI~~Q~36 30 30 30 30 ~K’LL ShW~iQ cit4~ “
~unhe.’L._.SubIriQ,~Sc~h &UWfl~’OM Som2~h~‘(ub’b.. un’np& Sa~~h~~
oj~~i~~‘ q
t~iI~O-~o,ti 38&ho~h~U’L-‘ 28At~-hOIt&~ TI
U
I ?cj
‘35’23ii
ji~i~
35~
g
I ~g
302’~
IL ]i~i~
8- 28 31~ 24 28
~
I ~1~
3122
-
-~--
311F ~
~
~
92Z
II ~c~ ~
2?I, 2v
~IC’~1A (~,f
VIE.V’J OF’
VtLLAGIE
B ~~-‘
Ar~u~UTIPIR
5IMI.A
8UNER~-rt
CHANOPUR
DAssHIN SIPILA~MSHIHJA~J4LPtJR
S~RAM~URlc
1gT~puR
_MAMU~PUI~______
13ISC)1IWATO~%A
DAVLSHIN 1MlWANPU~PMCHIPI SIML~PINcALE~WPIR
PAN~I
UTTA~W~aLFUR
~ SW’ILA
BMAH
HPAc%~S
5IMULmR
~OS~jFUR.
‘.1 ~ E.R~ -JNITS[UNITS~~ NI ~ ~ -
8LO9C~5uIV(Y1D~• ~ MeJD1~TOTAL -
24 20 ‘~ 31 4~I2I — —
34 ~5 4R 40 ‘~‘~ I~12G —
03 ~O7 16 iS 15 46 —
28,2 ~ 70 G~7~218 —- —
28 2 ~ 45 4L~c ~9158 — 102016 22 27 51100 — —
28~2~47 41 61L49 — —
30~254I~ 43 ~7i8~ 1511~D~2339 36 5~I323~424O~4O68 5G1a~?51 — —
3~’2544 ~2 67153 27—~~r0~0 46 44 ~7I77 — —
~O~3OG’l 50 78192 — —
23 ~23 44 4-~3—6—4Lf-5-j-565G 95 7914732!- _4 —
2~21 43 43 73159 — —
3232 G~571212~G— —
~ 21 32 33 5~19 — —
43~30 71 ~2 ~321G 731631 31 4~41 66150 44630 20 31 30 57118 — 84847 ~3 ~1138302 — —
2~17 24 23 3~~O — —
36 ‘1~34 36 G~13~—2b 17 42 30 2~~3 —
D~0~ io 12 13 35 2~~3~35 55 55 ~ —
28 2~66 46 si 163 46 418 183723 5311920 2~iS 02 65 — 60l25~— —
~2S?5O 1145 1238 ?0~5
125
2 ia
I 0~O149163
52251I 2~17;I 92
-F5-I3 it;15924~1152~
Ito302
11070
J 2.5
Pa ~0SEC ~
ATG.~X’~ Z4t’ft~RMMt?~SWIST 5~N~L IHbTA.
LO(P1 COST TOILET pgo~E~T~OCUO-LCONOM\C su R~.v~’i- l~~PaRT
T.IIw Ca’,i ~oIIU( (‘rojecI
~S ~ 22-07-9’3
- ~, ~jJal T)~ L
EWDRDLAS~ T ro-rAL X4CO I~~ans CCC
NU ~ OF r s’1~~QI~CUPPTWII ‘(~ PaL LANI
)3P(C ~ ç~5~11)MS ~ c~u ~
I T HTOrk( NIIMICIK
5to7
BIRDS EYE~J-~ OF i~-IEORSP~TIO~
~17~NI~thSA~~
)2 ~ ~AHQHPI~ CLUE
~ MAHIL~M~oAL\J4 BULLET CLUBOS BUNE~NT’ ft~iP~?UR~06 ~ ~ ~07 D~.sHHBE~PIUN~A~S~p~iA02 DMs~.VINL~ SEVA KEN0RP~09 D~a~iuSA~H~1 0 GRPIMIN ~ ~11 Ki~n?uR~ SAN~HA
2 NAL~YArURN~cLRUL~ SAH~p1
-1—3 ~4. ~ - - - - - -
1 5 N~RP~A~U~Sp~u~~I 6 ~ SU~’(P1 SPIH~iP4
17 PALL~ UNN~~~18 PASC~WI
5~L~B~sMR.~S~c~I ~ LES~VWEDHS~~20 P~n ~ Sc~21 ~ ~
22 ~ S~x~w~23 Pua~ 1I~Pa NAS~II<IALYAN ~AN~A
24 ~ ~ ~25 R~~R\s~ACLUB
26 RUIINER27 5~28 U~v~SAMm29 ~ UPH~ThN ~3 0~~ ‘~LMs’tctuv\or’4a.
13II01I2‘I011905
2D01
‘414
050201~06
03
01
II020102
05
to0201II03090509(I060806
-7
0110602(1050401100409060709
03
(C120915IDID20135
15
2G
10
2680
2~
4I ~9150
8
‘39.35
1995~
120603
120305‘5II12
Ii
-012707II
05032104I’02Q6030317060301
06160405
(612IG070819
IS—‘-52509‘512‘9I0“426
10II04‘5‘7‘3
02
03
04
01.07030109010203
04050604
020
070303Ol0305Q201
190905221216’20
1635‘4‘716
-‘-51015‘5‘52122‘33~121609
2006I0
08
0403
Q20-1
010604ID
\a3
04020IUI
020~0206
07
0t080202‘3
0612070I050904
-Q81606
0l050~06It0(0I04GA
140~0
022
0210I?0905161’30’3‘9(2(4
—0-9311017040812Og1602030705i2IS0702
4
3
-24lb‘516‘7I8I’24‘I120703210?09
0101
01050I01
0~40403
020202
1903070805(307i007020505l0I!06
2RI0I0
‘7(6
2~l0110303IS1007
09OsII,
3SJ204l~1
o60~7’usOZ
I-~•
.~S
TOTAL I6~~Q73Cfl 2~8378104 48~101 164 312 3~375 — 210 35~l~2