tk_ps direct activity allocation
TRANSCRIPT
-
8/13/2019 TK_PS Direct Activity Allocation
1/2
TK_PS Direct Activity Allocation
STEP-1: Create allocation cost element
Accounting>>Controlling>>Cost Element Accounting>>Master Data>>Cost Element>>Individual
Processing>> Create Secondary
T code: KA06
Enter your controlling area in the pop up screen for Set Controlling Area
Cost element
Valid from
Click on Master Data button
Name < Enter name of the cost element>
Description Cost element category
STEP-2: Create activity type
Accounting>>Controlling>> Cost Center Accounting>> Master Data>> Activity Type>> Individual
Processing>> KL01 - Create
T code: KL01
Activity Type
Valid from
Click on Master Data button
Name
Description
Activity Unit
Cost center categories < *>
Activity type category
Allocation cost element
Price indicator
STEP-3: Set Planner Profile
Accounting>>Controlling>> Cost Center Accounting>> Planning>> Set Planner Profile
T code: KP04
Select in the pop up screen for Set Planner Profile
Click on green check mark
-
8/13/2019 TK_PS Direct Activity Allocation
2/2
STEP-4: Create 3 new cost centers (T code-KS01)and post transactions in one of this cost center in
current date. This cost center you will use as sender cost center and the other two cost centers you wil l
use as receiver cost centers.
STEP-5: Enter activity price
Accounting>>Controlling>> Cost Center Accounting>> Planning>> Activity Output/Prices>>Change
T code: KP26
Version
From period to period
Fiscal Year
Select the radio button for Form Based optionClick on
Enter activity price for all periods in the presented screen in the column for fixed price.
STEP-6: Enter Activity Allocation
Accounting>>Controlling>> Cost Center Accounting>> Actual Postings>> Activity Allocation>>Enter
T code: KB21N
Sender cost centre
Sender Activity Type
Receiver cost center-1
Total quantity
Receiver cost center-2
Total quantity
STEP-7: Confirm the allocation postings in receiver and sender cost centers in cost center line
item report. T code-KSB1