tk21 report assignment2

Upload: titen-pinasti

Post on 13-Apr-2018

233 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/24/2019 Tk21 Report Assignment2

    1/103

    UNIVERSITAS INDONESIA

    RENEWABLE BIODIESEL FROM

    CRUDE PALM OIL, JATROPHA OIL, NYAMPLUNG OIL

    REPORT ASSIGNMENT 2

    GROUP 21

    GROUP PERSONNEL:

    DANAR ADITYA S. (1206263401)

    DENNY SETYADARMA (1206263351)

    HASANNUDIN (1206230725)

    MUHAMMAD HAFIZ AL RASYID (1206219161)

    TITEN PINASTI (1306482054)

    CHEMICAL ENGINEERING DEPARTMENT

    FACULTY OF ENGINEERING

    UNIVERSITAS INDONESIA

    DEPOK

    2015

  • 7/24/2019 Tk21 Report Assignment2

    2/103

    ii Universitas Indonesia

    EXECUTIVE SUMMARY

    In order to design renewable diesel plant, we have to make Piping and

    Instrumentation Diagram and Equipment Sizing. Piping and Instrumentation

    Diagram known as P&ID is one of some objectives in this assignment. It is the

    completion of Process Flow Diagram made in first assignment. It makes P&ID is

    more detail than PFD. P&ID is used in manufacturing the renewable biodiesel

    plant. Valves and some controllers also connected to the P&ID. P&ID is a used by

    process engineer in communicating with other engineer from another discipline.

    With this P&ID, we expect the other engineer can understand the whole plant

    system easily. In this P&ID we separate it to some pages based on process to

    make easy in attaching the valves and controller. There are 4 pages containing of

    Degumming, Bleaching, Steam Methane Reforming, Hydrothreating.

    After designing P&ID, We need to calculate the specification of the

    process equipment being used in a plant known as equipment sizing. This is

    another objective of this assignment There are equipment specifications,

    equipment sizing, equipment calculations used in making renewable biodiesel

    plant in this second assignment. Equipment needed in this plant are 5 tanks, 4

    pumps, heat exchanger, reactor, three phase separator. These data is used for

    manufacturing in plant design. Sizing of equipment based on rule of thumbs of the

    equipment and industrial calculation method by using manual calculation and

    software.

  • 7/24/2019 Tk21 Report Assignment2

    3/103

    iii Universitas Indonesia

    TABLE OF CONTENTS

    EXECUTIVE SUMMARY .................................................................................... ii

    TABLE OF CONTENTS ....................................................................................... iii

    LIST OF FIGURES ................................................................................................ v

    LIST OF TABLES ................................................................................................. vi

    CHAPTER 1 ........................................................................................................... 1

    CONTROL AND INSTRUMENT DESIGN .......................................................... 1

    1.1.

    Plant Control Tabulation .......................................................................... 1

    1.2.

    Piping and Instrument Diagram ..............Error! Bookmark not defined.

    1.3.

    Start up, Normal and Shutdown Procedure ............................................ 12

    1.3.1.

    Start Up Procedure .......................................................................... 12

    1.3.1.1.

    Start Up Procedures for Each Section ..................................... 13

    1.3.2.

    Shut Down Procedure ..................................................................... 14

    CHAPTER 2 ......................................................................................................... 15

    EQUIPMENT SIZING ......................................................................................... 15

    2.1.

    Main Equiment ....................................................................................... 15

    2.1.1.

    Storage Tank ................................................................................... 15

    Crude Palm Oil Storage Tank T-101 ................................................................ 15

    Jatropha Oil Storage Tank T-101 ...................................................................... 16

    Nyamplung Oil Storage Tank T-101 ................................................................ 17

    Renewable Biodiesel Storage Tank T-102........................................................ 18

    Degumming Tank V-101 .................................................................................. 19

    Shift Converter Reactor R-102 ......................................................................... 20

    Absorber Column V-103 ................................................................................... 21

    2.2.

    Supporting Equipment ............................................................................ 24

    Heat Exchanger E-101 ...................................................................................... 24

    Heat Exchanger E-102 ...................................................................................... 25

    Heat Exchanger E-103 ...................................................................................... 26

    Cooler E-104 ..................................................................................................... 29

    CONCLUSION ..................................................................................................... 38

  • 7/24/2019 Tk21 Report Assignment2

    4/103

    iv Universitas Indonesia

    REFERENCES ..................................................................................................... 39

    APPENDIX ........................................................................................................... 40

    Storage Tank ..................................................................................................... 40

    Crude Palm Oil Storage Tank ........................................................................... 41

    Jatropha Oil Storage Tank ................................................................................ 41

    Nyamplung Oil Storage Tank ........................................................................... 42

    Renewable Biodiesel Storage Tank .................................................................. 42

    Degumming Tank ............................................................................................. 48

    Hydrotreating Reactor Sizing ........................................................................... 52

    Shift Converter Reactor R-102 ......................................................................... 60

    Absorber Calculation ........................................................................................ 62

    Heat Exchanger Design Procedure ................................................................... 70

    Heat Exchanger E-101 ...................................................................................... 75

  • 7/24/2019 Tk21 Report Assignment2

    5/103

    v Universitas Indonesia

    LIST OF FIGURES

    Figure A.1. Types of head of storage tank ............................................................ 44

    Figure A.1. Power Number ................................................................................... 51

    Figure B.1. Fixed Bed Reactor ............................................................................. 53

    Figure B.2. Polymath Programming ..................................................................... 55

    Figure B.3. Polymath Programming Result .......................................................... 56

    Figure B.4. Polymath Programming Graph .......................................................... 56

    Figure B.5. Equation used for the design or sizing of fixed bed reactor .............. 61

    Figure B.6. Design for Various Packing............................................................... 64

    Figure B.7. Flooding Line Graph .......................................................................... 65

    Figure C.1. Shell and Tube Overall Coefficient ................................................... 71

    Figure C.2. Air Cooled Exchangers and Immersed Oil Overall Coefficient ........ 71

    Figure C.3. Coomon Tube Layouts ....................................................................... 72

    Figure C.4. Heat exchangers tube-layouts ............................................................ 72

    Figure C.5. Type of Heat Exchanger Baffles ........................................................ 73

    Figure C.6. Temperature Correction Factor : two shell passes ; four or multiple

    passes .................................................................................................................... 76

    Figure C.7. Tube Sheet Layouts (square pitch) .................................................... 77

    Figure C.8. HE Layouts ........................................................................................ 78

    Figure C.9 jH Factor ............................................................................................. 83

    Figure E.1 Impeller shapes related to specific speed ............................................ 92

  • 7/24/2019 Tk21 Report Assignment2

    6/103

    vi Universitas Indonesia

    LIST OF TABLES

    Table 1.1. Tabulation of degumming process ......................................................... 1

    Table 1.2. Tabulation of bleaching process ............................................................ 2

    Table 1.3. Tabulation of hydrotreating process ...................................................... 2

    Table 1.4. Tabulation of steam methane reforming process ................................... 4

    Table 1.7. Startup procedure ................................................................................. 12

    Table 1.8. Emergency Shutdown .......................................................................... 14

    Table 2.1 Specification Data of Storage Tank ...................................................... 15

    Table 2.2. Specification Data of Storage Tank ..................................................... 16

    Table 2.3 Specification Data of Storage Tank ...................................................... 17

    Table. 2.4. Specification Data of Storage Tank .................................................... 18

    Table. 2.5. Specification Data of Degumming Tank ............................................ 19

    Table. 2.6. Specification Data of Shift Converter Reactor ................................... 20

    Table. 2.7. Specification Data of Absorber Column ............................................. 21

    Table. 2.8. Specification Data of Steam Methane Reformer ................................ 22

    Table. 2.9. Specification Data of Hydrotreating Ractor Design ........................... 23

    Table. 2.10. Specification Data of Heat Exchanger E-101 ................................... 24

    Table. 2.11. Specification Data of Heat Exchanger E-102 ................................... 25

    Table. 2.12. Specification Data of Heat Exchanger E-107 ................................... 26

    Table. 2.13. Specification Data of Heat Exchanger E-105 ................................... 27

    Table. 2.14. Specification Data of Heat Exchanger E-106 ................................... 28

    Table. 2.15. Specification Data of Fired Heater E-103 ......................................... 29

    Table. 2.16. Specification Data of Fired Heater E-104 ......................................... 30

    Table 2.18. Specification Data of Compressor C-102 .......................................... 33

    Table 2.19. Specification Data of Pump P-101 ..................................................... 34

    Table 2.20. Specification Data of Pump P-102 ..................................................... 35

    Table 2.21. Specification Data of Pump P-103 ..................................................... 36

    Table 2.22. Specification Data of Pump P-104 ..................................................... 37

    Table A.1. List of Materials that Selected for Each Storage Tank ....................... 40

    Table B.1. Sizing Shift Converter Reformer ........................................................ 62

    Table B.2. Composition of the Incoming Gas ....................................................... 63

    Table B.2. Steam Methane Reformer ................................................................... 69

    Table C.1. Composition Properties ....................................................................... 79

  • 7/24/2019 Tk21 Report Assignment2

    7/103

    1 Universitas Indonesia

    CHAPTER 1

    CONTROL AND INSTRUMENT DESIGN

    1.1. Plant Control Tabulation

    Table 1.1. Tabulation of degumming process

    No DeviceControl

    Variable

    Manipulated

    Variable

    Location

    of Control

    Valve

    Sequence of

    Instrumentation

    Degumming Process

    1 T-101 Level of Oil

    Tank

    Flow of crude

    oil

    After pump

    and before

    heater

    If the level of tank is

    low, valve before

    heater will be closed

    and the other valve

    will be opened. It

    make the oil go back

    until the level is

    normal enough

    2 E-101 Temperature

    outlet of

    Heat

    Exchanger

    Temperature

    heating fluid

    Inlet of the

    heater

    Increase the flow of

    heating fluid if the

    temperature of oil

    going to degumming

    tank does not react

    the set point

    3 V-101 Level of

    Degumming

    Tank

    Flow of

    degummed

    oil

    After pump If the level of mixing

    tank is low, valve

    before heater will be

    closed and the other

    valve will be opened.

    It make the oil go

    back until the level is

    normal enough

  • 7/24/2019 Tk21 Report Assignment2

    8/103

    2

    Universitas Indonesia

    Table 1.2. Tabulation of bleaching process

    No DeviceControl

    Variable

    Manipulated

    Variable

    Location

    of

    Control

    Valve

    Sequence of

    Instrumentation

    Bleaching Coloumn

    1 E-102 Temperature

    outlet of Heat

    Exchanger

    Temperature

    heating fluid

    Inlet of

    the heater

    Increase the flow of

    heating fluid if the

    temperature of oil

    going to adsorber

    coloumn does not

    react the set point

    2 V-102 Level of

    Bleaching

    Tank

    Flow of

    bleached oil

    After

    pump

    If the level of adsorber

    coloumn is low, valve

    before heater will be

    closed and the other

    valve will be opened.

    It make the oil go backuntil the level is

    normal enough

    Table 1.3. Tabulation of hydrotreating process

    No Device Control

    Variable

    Manipulated

    Variable

    Location

    of Control

    Valve

    Sequence of

    Instrumentation

    Hydrotreating Reactor

    1 E-107 Temperature

    outlet of

    Heat

    Exchanger

    Temperature

    of heating

    fluid

    Inlet of

    the heater

    Increasing the flow of

    heating fluid if the

    temperature of oil

    going to hydrogenation

    reactor does not reach

    the set point

  • 7/24/2019 Tk21 Report Assignment2

    9/103

    3

    Universitas Indonesia

    Table 1.3.Tabulation of hydrotreating process (Contd)

    2 C-102 Flow of

    Hydrogen

    Pressure

    outlet of

    Compressor

    Before

    entering

    compresso

    r

    If the pressure outlet of

    comprossor is

    decreasing, the valve

    will be closed slowly

    in order to make the

    flow of hydrogen

    entering the

    compressor decrease.

    3 R-104 Flow

    Control

    Flow of

    Bleached Oil

    Before the

    reactor

    Increasing or

    decreasing the flow of

    degummed oil if the

    flow of oil going to

    reactor is not suitable

    4 R-104 Pressure of

    hydrothreati

    ng reactor

    pressure

    safety valve

    Pressure

    Relieve

    If the pressure is to

    high, the pressure

    safety valve will be

    opened to release theexcess gas until the

    normal pressure. If the

    reactor does not

    release the gas, the

    reactor will be hold

    the over pressure and

    the equipment will be

    broken soon.

    5 R-104 Level of

    Hydrotreatin

    g Reactor

    Flow of

    Green Diesel

    outlet

    After

    hydrotreat

    ing reactor

    If the level is too low,

    the valve will be

    closed slowly until the

    normal level.

  • 7/24/2019 Tk21 Report Assignment2

    10/103

    4

    Universitas Indonesia

    Table 1.4. Tabulation of steam methane reforming process

    No DeviceControl

    Variable

    Manipulate

    d Variable

    Location of

    Control

    Valve

    Sequence of

    Instrumentation

    Steam Methane Reformer

    1 C-101 Flow of Gas

    Inlet

    Separator

    Pressure

    outlet of

    Compressor

    Before

    entering

    compressor

    If the pressure outlet

    of comprossor is

    decreasing, the valve

    will be closed slowly

    in order to make the

    flow of hydrogen

    entering the

    compressor decrease.

    2 E-103 Temperatur

    e outlet of

    Heat

    Exchanger

    Temperature

    of heating

    fluid

    Inlet of the

    heater

    Increasing the flow

    of heating fluid if the

    temperature of oil

    going to the next

    process does notreach the set point

    3 E-104 Temperatur

    e outlet of

    Heat

    Exchanger

    Temperature

    of heating

    fluid

    Inlet of the

    heater

    Increasing the flow

    of heating fluid if the

    temperature of oil

    going to the next

    process does not

    reach the set point

    4 E-105 Temperatur

    e outlet of

    Heat

    Exchanger

    Temperature

    of heating

    fluid

    Inlet of the

    heater

    Increasing the flow

    of heating fluid if the

    temperature of oil

    going to the next

    process does not

    reach the set point

  • 7/24/2019 Tk21 Report Assignment2

    11/103

    5

    Universitas Indonesia

    Table 1.6 Tabulation of steam methane reforming process (Contd)

    5 E-106 Temperatur

    e outlet of

    Heat

    Exchanger

    Temperature

    of heating

    fluid

    Inlet of the

    heater

    Increasing the flow

    of heating fluid if the

    temperature of oil

    going to the next

    process does not

    reach the set point

    6 R-101 Pressure Flow of gas

    outlet

    After

    reactor

    If the pressure is too

    low, the valve will

    be closed slowly

    until the normalcoloumn level.

    7 R-101 Pressure Pressure

    safety valve

    Pressure

    Relieve

    If the pressure is too

    high, the pressure

    safety valve will be

    opened to release the

    excess gas until the

    normal pressure. If

    the coloumn does not

    not release the gas,

    the coloumn will be

    hold the over

    pressure and the

    equipment will be

    broken soon.

    8 R-102 Pressure Flow of gas

    outlet

    After

    reactor

    If the pressure is too

    low, the valve will

    be closed slowly

    until the normal

    coloumn level.

  • 7/24/2019 Tk21 Report Assignment2

    12/103

    6

    Universitas Indonesia

    Table 1.6 Tabulation of steam methane reforming process (Contd)

    9 R-102 Pressure Pressure

    safety valve

    Pressure

    Relieve

    If the pressure is too

    high, the pressure

    safety valve will be

    opened to release the

    excess gas until the

    normal pressure. If

    the coloumn does not

    not release the gas,

    the coloumn will be

    hold the overpressure and the

    equipment will be

    broken soon.

    10 R-103 Pressure Flow of gas

    outlet

    After

    reactor

    If the pressure is too

    low, the valve will

    be closed slowly

    until the normal

    coloumn level.

    11 R-103 Pressure Pressure

    safety valve

    Pressure

    Relieve

    If the pressure is too

    high, the pressure

    safety valve will be

    opened to release the

    excess gas until the

    normal pressure. If

    the coloumn does not

    not release the gas,

    the coloumn will be

    hold the over

    pressure and the

    equipment will be

    broken soon.

  • 7/24/2019 Tk21 Report Assignment2

    13/103

    7

    Universitas Indonesia

    Table 1.6 Tabulation of steam methane reforming process (Contd)

    12 V-103 Pressure Flow of gas

    outlet

    After

    reactor

    If the pressure is too

    low, the valve will

    be closed slowly

    until the normal

    coloumn level.

    13 V-103 Pressure Pressure

    safety valve

    Pressure

    Relieve

    If the pressure is too

    high, the pressure

    safety valve will be

    opened to release the

    excess gas until thenormal pressure. If

    the coloumn does not

    not release the gas,

    the coloumn will be

    hold the over

    pressure and the

    equipment will be

    broken soon.

    1.2. Process & Instrumental Design

  • 7/24/2019 Tk21 Report Assignment2

    14/103

    8

    Universitas Indonesia

    Steam

    DATESIGNATURENAME

    GROUP 21NAME

    CORRECTED BY

    PICTURE NO.

    NO REVISION WITHOUT SCALE

    P&ID DEGUMMING UNIT

    RENEWABLE BIODIESEL FROM CPO,

    JATROPHA OIL & NYAMPLUNGS OIL

    DEPARTEMEN TEKNIK KIMIA

    FAKULTAS TEKNIK

    UNIVERSITAS INDONESIA

    Condensate

    T-101

    Crude Oil Tank

    P-101

    Feed Pump

    E-101

    Heat Exchanger

    V-101

    Degumming tank

    P-102

    Feed Pump

    Fosforic Acid

    Gum

    CPO /

    NYAMPLUNG /JATHROPA LT

    P-101

    101101

    101

    M

    102102

    102

    M

    101

    101

    LT

    101

    1

    2

    34

    5

    6

    7

    8

    9V-96

    T-101

    E- 101

    V-101

    P- 102

    LIC

    FIC

    PI FT TT

    LIC

    FIC

    PI FT

    LIC

    DegummedOil

  • 7/24/2019 Tk21 Report Assignment2

    15/103

    9

    Universitas Indonesia

    DATESIGNATURENAME

    GROUP 21NAME

    CORRECTED BY

    PICTURE NO.

    NO REVISION WITHOUT SCALE

    P&ID BLEACHING UNIT

    RENEWABLE BIODIESEL FROM CPO,

    JATROPHA OIL & NYAMPLUNGS OIL

    DEPARTEMEN T EKNIK KIMIA

    FAKULTAS TEKNIK

    UNIVERSITAS INDONESIA

    E-102

    Heat Exchanger

    V-102

    Bleaching Unit

    P-103

    Pump

    Steam

    Condensate

    BleachedOil

    Degummed Oil

    103103

    103

    M

    102

    102

    102

    1

    2

    4

    5

    3

    6

    102

    E- 102

    V-102

    P-103

    TIC

    TT

    LT

    FIC

    PI FT

    LIC

  • 7/24/2019 Tk21 Report Assignment2

    16/103

  • 7/24/2019 Tk21 Report Assignment2

    17/103

    11

    Universitas Indonesia

    DATESIGNATURENAME

    GROUP 21NAME

    CORRECTED BY

    PICTURE NO.

    NO REVISION WITHOUT SCALE

    P&ID HYDROTHREATING UNIT

    RENEWABLE BIODIESEL FROM CPO,

    JATROPHA OIL & NYAMPLUNGS OIL

    DEPARTEMEN TEKNIK KIMIA

    FAKULTAS TEKNIK

    UNIVERSITAS INDONESIA

    E-107Heater

    R-104Hidrotreating Reactor

    V-108Green Diesel Tank

    C-102Compressor

    BleachedOil

    Steam

    Condensate

    Hydrogen

    107

    1

    2

    5

    6

    4

    7

    3

    107

    102

    102

    102

    E-107

    R-104

    C-102

    104

    TT

    FIC

    PIC

    PT

    PIC

    FC

    Excess Reactant11

    104PT

    104PIC

    V-108

    104

    104

    LT

    LIC

  • 7/24/2019 Tk21 Report Assignment2

    18/103

    12

    Universitas Indonesia

    1.3. Start up, Normal and Shutdown Procedure

    1.3.1. Start Up Procedure

    Start up actions occurs every day beside Saturday and Sunday, this

    makes 330 days plant startup per year. Startup will be explained step by step in

    Table 1.7 below.

    Table 1.7. Startup procedure

    No Procedure DescriptionSafety

    Precautions

    1

    All piping and instrument

    are completed as P&ID.

    Electrical set start up. All

    electrical cords are

    connected and no faulty

    cord.

    Instrument set start up

    2

    Ensure functionality of

    control valves,

    controllers, emergency

    shutdown system, etc.

    All equipment and

    instrument set start up

    3Install and activate

    electrical systemElectrical set start up

    All electrical

    cords are

    connected and no

    faulty cord

    4 Activate steam utilitiesHeater start up for

    heating water utilities

    Desired

    temperature has

    been reached

    5 Pre-treatment startup

    Pre-treatment

    equipment start up to

    produce CPO from

    palm fruit, nyamplung,

    jathropa

    All pre treatment

    equipment is safe

    to operate

    6 Activate plant process Starting all controller

  • 7/24/2019 Tk21 Report Assignment2

    19/103

    13

    Universitas Indonesia

    instrument and checking

    alarm panel

    on plant and checking

    alarm function

    7Activate main process

    equipment

    Starting reactor and

    other process

    equipment after CPO

    level is adequate for

    process

    All equipment

    connected and no

    leakage

    1.3.1.1.Start Up Procedures for Each Section

    Start-up procedures in this system are divided into four parts based on

    the number of units in our plant. Below are the procedures:

    a. Degumming Unit

    1. Check all of the systems are installed correctly

    2. Check the controller of the system

    3. Check the temperature at 65C and the process lasts for 15 minutes

    b. Bleaching Unit

    1. Check all of the systems are installed correctly

    2.

    Check the controller of the system

    3. Check substances that give color to the oil

    4. Check all the equipment safe to operate

    c. Hydrotreating

    1. Check all of the systems are installed correctly

    2.

    Check the controller of the system

    3. Processes implement reactions of hydrotreatment promoted by catalysts

    Nickel Molybdenum with buffer Alumina4. The hydrotreatment reactions are generally carried out in the presence of

    hydrogen

    5.

    Check temperature at 300C and pressure at 2 atm

    d. Steam Methane Reforming

    1. Check all of the systems are installed correctly

    2. Check the controller of the system

  • 7/24/2019 Tk21 Report Assignment2

    20/103

    14

    Universitas Indonesia

    3. Check the steam flow from its temperature whether it is suitable or not for

    entering the steam methane reformer

    4.

    Reduced localized temperature

    1.3.2. Shut Down Procedure

    Manual shutdown. Manual shut down occur every end of year. It

    occurs according to procedure:

    1.

    Decrease the flow rate of feed CPO, Nyamplung oil, and Jathropa oil

    gradually until the flows stop

    2. Let all the flue gas flow until there is no excess flue gas in the piping line

    3.

    Turn off all the equipment, such as heat exchanger, steam methane

    reformer, and pump.

    4. Uninstall the catalyst from all unit.

    Emergency shutdown. Emergency shutdown only happen if theres

    special condition occurs. Emergency shutdown relies on plant process control

    instrument and alarm. The condition and procedure are shown in Table 1.8.

    Table 1.8. Emergency Shutdown

    No Condition Procedure

    1Reactor temperature condition

    reach too high or too low

    Shut the ball valve that related to the flow,

    and maintenance or change with reserve

    equipment if available

    2Reactor flow condition reach

    too high

    3

    Hydrotreating temperature

    condition reach too high or

    too low

    4Steam Methane Reforming

    flow condition reach too high

    5 Pump failures

  • 7/24/2019 Tk21 Report Assignment2

    21/103

    15 Universitas Indonesia

    CHAPTER 2

    EQUIPMENT SIZING

    2.1. Main Equiment

    2.1.1. Storage Tank

    2.1.1.1.Crude Palm Oil Storage Tank T-101

    Table 2.1 Specification Data of Storage Tank

    Identification

    Item : Storage Tank

    Item Number : T-101

    Name of Equipment : Crude Palm Oil Storage Tank

    Item Amount : 10

    Function : Storing of Crude Palm Oil

    Composition

    Crude Palm Oil: 100%

    Operation Data

    Capacity : 44.70 ton/hr

    Pressure : 2.576 atm

    Temperature : 25oC

    Storage Time : 7 days

    Specification Design

    Type :Cylindrical Tank with Ellipsoidal Top

    and Flat Bottom

    Joint : Double Welded Butt Joint

    Material : SA-283, Grade C

    Volume : 949 m3

    Diameter Tank : 7.48 m

    Height Tank : 16.21 m

    Wall Thickness : 0.97 inch

    Head Thickness : 1.40 inch

  • 7/24/2019 Tk21 Report Assignment2

    22/103

    16

    Universitas Indonesia

    2.1.1.2.Jatropha Oil Storage Tank T-101

    Table 2.2. Specification Data of Storage Tank

    Identification

    Item : Storage Tank

    Item Number : T-101

    Name of Equipment : Jatropha Oil Storage Tank

    Item Amount : 10

    Function : Storing of Jatropha Oil

    Composition

    Crude Palm Oil: 100%

    Operation Data

    Capacity : 44.70 ton/hr

    Pressure : 2.5645 atm

    Temperature : 25oC

    Storage Time : 7 days

    Specification Design

    Type :Cylindrical Tank with Ellipsoidal Top

    and Flat Bottom

    Joint : Double Welded Butt Joint

    Material : SA-283, Grade C

    Volume : 968 m3

    Diameter Tank : 7.53 m

    Height Tank : 16.32 m

    Wall Thickness : 0.97 inch

    Head Thickness : 1.40 inch

  • 7/24/2019 Tk21 Report Assignment2

    23/103

    17

    Universitas Indonesia

    2.1.1.3.Nyamplung Oil Storage Tank T-101

    Table 2.3 Specification Data of Storage Tank

    Identification

    Item : Storage Tank

    Item Number : T-101

    Name of Equipment : Nyamplung Oil Storage Tank

    Item Amount : 10

    Function : Storing of Nyamplung Oil

    Composition

    Crude Palm Oil: 100%

    Operation Data

    Capacity : 44.70 ton/hr

    Pressure : 2.565 atm

    Temperature : 25oC

    Storage Time : 7 days

    Specification Design

    Type :Cylindrical Tank with Ellipsoidal Top

    and Flat Bottom

    Joint : Double Welded Butt Joint

    Material : SA-283, Grade C

    Volume : 961 m3

    Diameter Tank : 7.51 m

    Height Tank : 16.27 m

    Wall Thickness : 0.97 inch

    Head Thickness : 1.40 inch

  • 7/24/2019 Tk21 Report Assignment2

    24/103

    18

    Universitas Indonesia

    2.1.1.4.Renewable Biodiesel Storage Tank T-102

    Table. 2.4. Specification Data of Storage Tank

    Identification

    Item : Storage Tank

    Item Number : T-102

    Name of Equipment : Renewable Biodiesel Storage Tank

    Item Amount : 2

    Function :Storing of Renewable Biodiesel

    Product

    Composition

    Crude Palm Oil: 100%

    Operation Data

    Capacity : 37,88 ton/hr

    Pressure : 1.863 atm

    Temperature : 25oC

    Storage Time : 7 days

    Specification Design

    Type :Cylindrical Tank with Ellipsoidal Top

    and Flat Bottom

    Joint : Double Welded Butt Joint

    Material : SA-283, Grade C

    Volume : 640 m3

    Diameter Tank : 3.83 m

    Height Tank : 8.94 m

    Wall Thickness : 0.64 inch

    Head Thickness : 0.80 inch

  • 7/24/2019 Tk21 Report Assignment2

    25/103

    19

    Universitas Indonesia

    2.1.1.5.Degumming Tank V-101

    Table. 2.5. Specification Data of Degumming Tank

    Identification

    Item Mixer Tank

    Item number V-101

    Equipment name Degumming Tank

    Number of Unit 1

    Function Reacting phosporic acid with gum

    Mode Operation Continue

    Composition (%)

    Oil 11.39 kg/h

    Phosporic Acid 27,005.35 kg/h

    Operating condition Capacity 45,560 kg/h

    Pressure 168.2 kPa

    Temperature 64.12 oC

    Spesification Design Type Ellipsoidal vertical tank

    Material Stainless Steel 316

    Volume 59.33 m3

    Diameter tank 3.19 m

    Height tank 8.51 m

    Height of cylinder 6.38 m

    Height of ellipsoidal 1.06 m

    Wall thickness 4.29 mm

    Head thickness 4.29 mm

  • 7/24/2019 Tk21 Report Assignment2

    26/103

    20

    Universitas Indonesia

    Table. 2.5. Specification Data of Degumming Tank (Contd)

    Stirrer Design Impeller type Axial four blade

    Number of impeller 1

    Impeller diameter 1.06 m

    Impeller level width 0.213 m

    Impeller to bottom 1.06 m

    Diameter stick 0.353 m

    Diameter baffle 0.266 m

    Impeller speed 2 rps

    Utilities Power 0.114 kW/h

    2.1.2. Reactor

    2.1.2.1.Shift Converter Reactor R-102

    Table. 2.6. Specification Data of Shift Converter Reactor

    Identification

    Item Shift Converter

    Item Number R-102

    Function: To produce syngas from Natural Gas and SteamType of Reactor Multitubular Packed Bed Reactor

    Operating Condition

    Pressure bar 4,16

    Temperature oC 427

    Dimension

    Reaction Rate kgmol/kg cat.h 0,378978

    Residence Time min 10,73Volume Reactor m3 16,35581

    Catalyst Weight kg 0,57

    No. of Tubes 8

    Tube Diameter cm 1,733461

    Diameter cm 173,3461

    Height m 6,933845

    Thickness cm 5,0225

  • 7/24/2019 Tk21 Report Assignment2

    27/103

    21

    Universitas Indonesia

    2.1.2.2.Absorber Column V-103

    Table. 2.7. Specification Data of Absorber Column

    Identification

    Name Absorber Column

    Item Number V-103

    Function To separating H2and CO2from Shift

    converter unit

    Number of unit 1

    Material Carbon Steel SA-283 Grade C

    Type Packing

    Packing Width and Height

    Tower Diameter 12.60 m

    Height of packing 20.51 m

    Permissible tensile stress 950 kg/cm2

    Mechanical Design

    Working pressure 101300 N/m2

    Design pressure,p 106365 N/m2

    0.106365 N/mm2

    Permissible stress 95 N/mm2

    Joint Efficiency (j) 0.85

    Corrosion allowance 3 mm

    Outer diameter, Do 12.659 m

    Input Amine. T 150 oC

    Input CO2, T 75oC

    Output Amine, T 80 oC

    Output CO2, T 95oC

  • 7/24/2019 Tk21 Report Assignment2

    28/103

    22

    Universitas Indonesia

    2.1.2.3.Steam Methane Reformer R-101

    Table. 2.8. Specification Data of Steam Methane Reformer

    Identification

    Item Steam Methane Reformer

    Item Number R-101

    Function: To produce syngas from Natural Gas and

    Steam

    Type of Reactor Multitubular Packed Bed Reactor

    Operating Condition

    Pressure bar 4,5

    Temperature oC 760

    Dimension

    Reaction Rate kgmol/kg cat.h 4,08045

    Residence Time min 10,73

    Volume Reactor m3 57,39

    Catalyst Weight kg 523.23

    No. of Tubes 8

    Tube Diameter cm 2,63

    Diameter cm 263,41

    Height m 10,54

    Thickness cm 5,0225

  • 7/24/2019 Tk21 Report Assignment2

    29/103

    23

    Universitas Indonesia

    2.1.2.4.Hydrotreating Reactor Design

    Table. 2.9. Specification Data of Hydrotreating Ractor Design

    Unit: CRV-100 Hydrotreating Reactor

    Function:To Produce Green Diesel via

    Triglycerides and Hydrogen

    Operating Condition

    Type of Reactor Packed Bed Reactor

    Pressure bar 34.378

    Temperature oC 300

    Catalyst Volume m3 8.33

    DimensionResidence Time s 8.62

    Volume m3 10.42

    Number of Tubes 414

    Tube Diameter in 1.968

    Diameter m 1.744

    Height m 4.366

    Thickness mm 5

    Shell Thickness mm 4.9

    Material Stainless Steel 316 SS

  • 7/24/2019 Tk21 Report Assignment2

    30/103

    24

    Universitas Indonesia

    2.2. Supporting Equipment

    2.2.1. Heat Exchanger

    2.2.1.1.Heat Exchanger E-101

    Table. 2.10. Specification Data of Heat Exchanger E-101

    Equipment Specification

    Equipment Name Heat Exchanger

    Equipment Code E-101

    FunctionIncrease the temperature of CPO

    before entering degumming process

    Amount 1

    Material Carbon Steel

    Type Shell and Tube

    Operating Data

    Shell Tube

    Flow Rate kg/h 10000.00 4594.85

    Temperature Inlet C 155.00 25.00

    Temperature Outlet C 134.00 65.00

    Operating Pressure kPa 300.00 200.00

    Construction Data

    LMTD C 99.1969

    UA W/m C 5.7046

    Duty kW 122.1208

    Heat Transfer Area m 4.1637

    Number of Passes 1-2

    Shell ID m 0.49

    Tube Arrangement Triangular

    Number of Tubes 220

    Tube Length m 4.00

    Tube OD m 0.0191

    Tube BWG 14.0000

    Tube Pitch m 0.0254

  • 7/24/2019 Tk21 Report Assignment2

    31/103

    25

    Universitas Indonesia

    2.2.1.2.Heat Exchanger E-102

    Table. 2.11. Specification Data of Heat Exchanger E-102

    Equipment Specification

    Equipment Name Heat Exchanger

    Equipment Code E-102

    FunctionIncrease the temperature of CPO

    before entering bleaching process

    Amount 1

    Material Carbon Steel

    Type Shell and Tube

    Operating Data

    Shell Tube

    Flow Rate kg/h 10000.00 5138.21

    Temperature Inlet C 155.00 64.23

    Temperature Outlet C 134.00 100.00

    Operating Pressure kPa 300.00 200.00

    Construction Data

    LMTD C 62.0925

    UA W/m C 32.0492

    Duty kW 122.1208

    Heat Transfer Area m 6.7828

    Number of Passes 1-2

    Shell ID m 0.30

    Tube Arrangement Triangular

    Number of Tubes 32

    Tube Length m 8.00

    Tube OD m 0.0191

    Tube BWG 14.0000

    Tube Pitch m 0.0238

  • 7/24/2019 Tk21 Report Assignment2

    32/103

    26

    Universitas Indonesia

    2.2.1.3.Heat Exchanger E-103

    Table. 2.12. Specification Data of Heat Exchanger E-107

    Equipment Specification

    Equipment Name Heat Exchanger

    Equipment Code E-107

    FunctionIncrease the temperature of oil before

    entering the reactor

    Amount 1

    Material

    Type Shell and Tube

    Operating Data

    Shell Tube

    Flow Rate kg/h 90000.00 41928.91

    Temperature Inlet C 400.00 102.44

    Temperature Outlet C 294.84 300.00

    Operating Pressure kPa 800.00 700.00

    Construction Data

    LMTD C 141.1967

    UA () W/m C 20.2749

    Duty () kW 5504.0209

    Heat Transfer Area m 165.4549

    Number of Passes 1-2

    Shell ID m 0.49

    Tube Arrangement Triangular

    Number of Tubes 264

    Tube Length m 12.00

    Tube OD m 0.0191

    Tube BWG 14

    Tube Pitch m 0.0238

  • 7/24/2019 Tk21 Report Assignment2

    33/103

    27

    Universitas Indonesia

    2.2.1.4. Heat Exchanger

    Table. 2.13. Specification Data of Heat Exchanger E-105

    Equipment Specification

    Equipment Name Heat Exchanger

    Equipment Code E-105

    Function

    Decrease the temperature of shift

    product before entering absorption

    process

    Amount 1

    Material Carbon Steel

    Type Shell and Tube

    Operating Data

    Shell Tube

    Flow Rate kg/h 2135.00 36787.10

    Temperature Inlet C 430.00 25.00

    Temperature Outlet C 38.00 41.50

    Operating Pressure kPa 340.00 100.00

    Construction Data

    LMTD C 110.5275

    UA () W/m C 743.3854

    Duty () kW 727.5363

    Heat Transfer Area m 27.5850

    Number of Passes 1-2

    Shell ID m 0.39

    Tube Arrangement Triangular

    Number of Tubes 154

    Tube Length m 4.00

    Tube OD m 0.0191

    Tube BWG 14.0000

    Tube Pitch m 0.0238

  • 7/24/2019 Tk21 Report Assignment2

    34/103

    28

    Universitas Indonesia

    2.2.1.5.Heat Exchanger

    Table. 2.14. Specification Data of Heat Exchanger E-106

    Equipment Specification

    Equipment Name Heat Exchanger

    Equipment Code E-106

    Function

    Decrease the temperature of

    methanator feed before entering

    reactor

    Amount 1

    Material Carbon Steel

    Type Shell and Tube

    Operating Data

    Shell Tube

    Flow Rate kg/h 18000.00 1845.43

    Temperature Inlet C 280.00 138.00

    Temperature Outlet C 262.75 260.00

    Operating Pressure kPa 340.00 100.00

    Construction Data

    LMTD C 57.2235

    UA () W/m C 743.3854

    Duty () kW 269.8557

    Heat Transfer Area m 18.4039

    Number of Passes 1-2

    Shell ID m 0.30

    Tube Arrangement Triangular

    Number of Tubes 90

    Tube Length m 4.00

    Tube OD m 0.0191

    Tube BWG 14.0000

    Tube Pitch m 0.0238

  • 7/24/2019 Tk21 Report Assignment2

    35/103

    29

    Universitas Indonesia

    2.2.1.6.Fired Heater E-103

    Table. 2.15. Specification Data of Fired Heater E-103

    Equipment Specification

    Equipment Name Fired Heater

    Equipment Code E-103

    FunctionIncrease the temperature of mixed

    feed before entering reformer process

    Amount 1

    Material Stainless Steel

    Type Shell and Tube

    Operating Data

    Shell

    Flow Rate kg/h 2135.00

    Temperature Inlet C 140

    Temperature Outlet C 760

    Operating Pressure kPa 500

    Radiant Section

    Tube OD in 8.626

    Tube Thickness in 0.05118

    Number of Tubes

    (Radiant) -40

    Number of Tubes (Shield) - 12

    Combustion (Fraction

    Excess Air) -0.15

    Firebox Diameter ft 19.98

    Flue Gas Temperature R 2077,1Emmisivity - 0.5087

    Radiation Heat Transfer Btu/hr 3.37 x 107

  • 7/24/2019 Tk21 Report Assignment2

    36/103

    30

    Universitas Indonesia

    Table. 2.15. Specification Data of Fired Heater E-103 (Contd)

    Convection Section

    Tube BWG 14.0000

    Tube Pitch m 0.0238

    Wall Temperature 959Number of Rows - 5

    Number of Tubes per Row - 4

    Flue Gas Temperature 1472LMTD 430.28Convection Heat Transfer Btu/hr 3.37 x 107

    2.2.1.7.Fired Heater E-104

    Table. 2.16. Specification Data of Fired Heater E-104

    Equipment Specification

    Equipment Name Fired Heater

    Equipment Code E-104

    FunctionIncrease the temperature of shift feed

    before entering water-gas-shift

    process

    Amount 1

    Material Stainless Steel

    Type Shell and Tube

    Operating Data

    Shell

    Flow Rate kg/h 2135.00

    Temperature Inlet C 760

    Temperature Outlet C 1050

    Operating Pressure kPa 500

  • 7/24/2019 Tk21 Report Assignment2

    37/103

    31

    Universitas Indonesia

    Table. 2.16. Specification Data of Fired Heater E-104 (Contd)

    Radiant Section

    Tube OD in 8.626

    Tube Thickness in 0.05118

    Number of Tubes

    (Radiant) -40

    Number of Tubes (Shield) - 12

    Combustion (Fraction

    Excess Air) -0.15

    Firebox Diameter ft 19.98

    Flue Gas Temperature R 2077,1Emmisivity - 0.5087

    Radiation Heat Transfer Btu/hr 3.37 x 107

    Convection Section

    Tube BWG 8.626

    Tube Pitch m 0.5

    Wall Temperature

    959

    Number of Rows - 5

    Number of Tubes per Row - 4

    Flue Gas Temperature 1472LMTD 430.28Convection Heat Transfer Btu/hr 3.37 x 107

  • 7/24/2019 Tk21 Report Assignment2

    38/103

    32

    Universitas Indonesia

    2.2.2. Compressor

    2.2.2.1.Compressor C-101

    Table 2.17. Specification Data of Compressor C-101

    Equipment Specification

    Name Feed Methane Compressor

    Code C-101

    Function To help methane flow to feed mixer

    Total 1

    Vendor Ingersoll Rand

    Model UP5 22-7

    Type Rotary Screw Air Compressor

    Material Carbon Steel

    Frequency (Hz) 50

    Nominal Power (kW) 22

    Flow (m3/min) 3.54

    Length/Width/Height (cm) 128/92/105

    Weight (kg) 540

    Operation Data

    Flow rate (m3/h) 2.672

    Mass flow (kg/h) 800

    Suction Pressure (kPa) 520

    Discharge Pressure (kPa) 824

    Temperature Inlet (oC) 20

    Temperature Outlet (oC) 63.25

    Power (kW) 21.6

  • 7/24/2019 Tk21 Report Assignment2

    39/103

    33

    Universitas Indonesia

    2.2.2.2.Compressor C-102

    Table 2.18. Specification Data of Compressor C-102

    Equipment Specification

    Name Hydrogen Compressor

    Code C-102

    Function To help hydrogen flow from methanator

    to hydrogenation reactor

    Total 1

    Vendor Ingersoll Rand

    Model M300-2S

    Type Rotary Screw Air Compressor

    Material Carbon Steel

    Frequency (Hz) 50

    Nominal Power (kW) 300

    Flow (m3/min) 60.2

    Length/Width/Height (cm) 400/193/215

    Weight (kg) 5540

    Operation Data

    Flow rate (m3/h) 5.391

    Mass flow (kg/h) 1578

    Suction Pressure (kPa) 241

    Discharge Pressure (kPa) 544.9

    Temperature Inlet (oC) 280

    Temperature Outlet (oC) 440.7

    Power (kW) 290.2

  • 7/24/2019 Tk21 Report Assignment2

    40/103

    34

    Universitas Indonesia

    2.2.3. Pump

    2.2.3.1.Pump P-101

    Table 2.19. Specification Data of Pump P-101

    Equipment Specification

    Name Oil Feed Pump

    Code P-101

    Function To help oil to flow to heat exchanger then

    mixer

    Number of unit 1

    Type Centrifugal Pump

    Operation Data

    Liquid Volume Flow (m3/h) 49.96

    Temperature (oC) 25

    Suction Pressure (kPa) 101.3

    Discharge Pressure (kPa) 202.6

    Head (ft) 54.714

    NPSHA (ft) 0.111

    Efficiency 0.75

    Hydraulic Power (kW) 2.35

    BHP (kW) 3.14

    Spesific Speed (rpm) 1327.109

    Jenis Impeller Radial Vane

  • 7/24/2019 Tk21 Report Assignment2

    41/103

    35

    Universitas Indonesia

    2.2.3.2.Pump P-102

    Table 2.20. Specification Data of Pump P-102

    Equipment Specification

    Name Refined Oil Pump

    Code P-102

    Function To help refined oil to flow to heat exchanger

    then adsorption column

    Number of unit 1

    Type Centrifugal Pump

    Operation Data

    Liquid Volume Flow (m3/h) 50.76

    Temperature (oC) 64.15

    Suction Pressure (kPa) 66.85

    Discharge Pressure (kPa) 168.2

    Head (ft) 54.724

    NPSHA (ft) 0.111

    Efficiency 0.75

    Hydraulic Power (kW) 2.39

    BHP (kW) 3.19

    Spesific Speed (rpm) 1336.109

    Jenis Impeller Radial Vane

  • 7/24/2019 Tk21 Report Assignment2

    42/103

    36

    Universitas Indonesia

    2.2.3.3.Pump P-103

    Table 2.21. Specification Data of Pump P-103

    Equipment Specification

    Name Refined Bleached Oil Pump

    Code P-103

    Function To help oil to flow to heat exchanger then

    hydrogenation column

    Number of unit 1

    Type Centrifugal Pump

    Operation Data

    Liquid Volume Flow (m3/h) 49.96

    Temperature (oC) 100

    Suction Pressure (kPa) 101.3

    Discharge Pressure (kPa) 2758

    Head (ft) 960.21

    NPSHA (ft) 0.111

    Efficiency 0.75

    Hydraulic Power (kW) 39.699

    BHP (kW) 52.932

    Spesific Speed (rpm) 151.618

    Jenis Impeller Radial Vane

  • 7/24/2019 Tk21 Report Assignment2

    43/103

    37

    Universitas Indonesia

    2.2.3.4.Pump P-104

    Table 2.22. Specification Data of Pump P-104

    Equipment Specification

    Name Green Diesel Pump

    Code P-104

    Function To help green diesel to flow

    Number of unit 1

    Type Centrifugal Pump

    Operation Data

    Liquid Volume Flow (m3/h) 34.01

    Temperature (oC) 349.4

    Suction Pressure (kPa) 101.3

    Discharge Pressure (kPa) 202.6

    Head (ft) 54.714

    NPSHA (ft) 0.111

    Efficiency 0.75

    Hydraulic Power (kW) 1.6

    BHP (kW) 2.138

    Spesific Speed (rpm) 1094.523

    Jenis Impeller Radial Vane

  • 7/24/2019 Tk21 Report Assignment2

    44/103

    38 Universitas Indonesia

    CONCLUSION

    Each equipment is sized to suit the need of the process. The main aspects

    considered are volume, height, diameter, and energy.

    The main equipment that uses multiple units to accommodate the process are

    storage tank, hydrotreating reactor and unit separator.

    The supporting equipment that used are pump, compressor, heat exchanger

    and cooler.

    The complete main equipment and its intrumentation is depicted in P&ID

    The controller needed to be arranged based on the risk of the variable that

    being controlled.

  • 7/24/2019 Tk21 Report Assignment2

    45/103

    39 Universitas Indonesia

    REFERENCES

    Branan. 2012.Rules of Thumb for Chemical Engineer.5 thedition. USA: Stephen

    Hall.Brownell, L.E & Edwin H.Y. 1959. Process Equipment Design: Vessel Design.

    John Wiley & Sons.

    Walas, S.M. 1990. Chemical Process Equipment. Selection and Design.

    Massachusetts Institute of Technology: Butterworth-Heineman Series in Chemical

    Engineering.

  • 7/24/2019 Tk21 Report Assignment2

    46/103

    40 Universitas Indonesia

    APPENDIX A

    A.1. Storage Tank

    In the process of producing renewable biodiesel, because of not continues

    supplies, storage tank are needed to store the raw materials and product. We have

    to determine the size and dimension based on the flow rate of each material that

    goes in and out the storage tanks.

    We use three different types of storage tank to store three different type

    crude oil for process that is crude palm oil, jatropha oil and nyamplung oil.

    Moreover, we need storage tank for renewable diesel produced.

    Material Selection

    The raw material storage tanks form are cylindrical tanks because a

    cylinder shape has a great structural strength and easier to fabricate. The top end

    of storage tanks use ellipsoidal shape, while the bottom end is flat and stand

    directly upon the ground. We use carbon steel as the material for storage tanks.

    Table A.1. List of Materials that Selected for Each Storage Tank

    No. Storage Tank Material Specification

    1. Crude Palm Oil Storage Tank SA-283, Grade C2. Jatropha Oil Storage Tank SA-283, Grade C

    3. Nyamplung Oil Storage Tank SA-283, Grade C

    4. Renewable Biodiesel Storage Tank SA-283, Grade C

    A.1.1. Volume of Storage Tank

    For sizing the storage tanks, we estimate that the capacity of crude oil

    storage tanks are able to fulfill the needs of material for a week depending on the

    supply attendants. So, we determine one week as a batch.

  • 7/24/2019 Tk21 Report Assignment2

    47/103

    41

    Universitas Indonesia

    Crude Palm Oil Storage Tank

    Crude Palm Oil mass flow rate is 44700 kg/hour. So the storage tanks have

    to store 7,509,600 kg/batch crude palm oil. The calculation of storage tanks

    volume needed to store :

    = = 7,509,600kgweek879.3 kgm

    = 8540.43 mweekTo store the crude palm oil, we will use 10 storage tank. so, the crude palm oil

    volume per tank is :

    =8,540.43 m

    week10 =854.04 m

    week

    To calculate the total volume of storage tanks, safety factor has to be

    considered. Safety factor of the tank is 10% of the total volume. This is based

    on literature saying that for tanks which volume is above 3,8 m 3, only 90%

    volume is filled.

    = 854.04 mweek0.9 = 948.94 m

    week

    Jatropha Oil Storage Tank

    Jatropha Oil mass flow rate is 44700 kg/hour. So the storage tanks have to

    store 7,509,600 kg/batch jatropha oil. The calculation of storage tanks volume

    needed to store :

    = = 7,509,600kgweek862 kg

    m

    = 8711.83 mweekTo store the jatropha oil, we will use 10 storage tank. so, the jatropha oil

    volume per tank is : = 8,711.83 m

    week10 =871.18 m

    weekTo calculate the total volume of storage tanks, safety factor has to be

    considered. Safety factor of the tank is 10% of the total volume. This is based

  • 7/24/2019 Tk21 Report Assignment2

    48/103

    42

    Universitas Indonesia

    on literature saying that for tanks which volume is above 3,8 m 3, only 90%

    volume is filled.

    = 871.18 m

    week0.9 = 967.98 mweek Nyamplung Oil Storage Tank

    Nyamplung Oil mass flow rate is 44700 kg/hour. So the storage tanks have

    to store 7,509,600 kg/batch nyamplung oil. The calculation of storage tanks

    volume needed to store :

    = = 7,509,600 kgweek869 kgm = 8641.66 mweekTo store the nyamplung oil, we will use 10 storage tank. so, the nyamplung oil

    volume per tank is : = 8,641.66 m

    week10 =864.17 m

    weekTo calculate the total volume of storage tanks, safety factor has to be

    considered. Safety factor of the tank is 10% of the total volume. This is basedon literature saying that for tanks which volume is above 3,8 m 3, only 90%

    volume is filled.

    = 864.17 mweek0.9 = 960.18 m

    week

    Renewable Biodiesel Storage Tank

    Renewable biodiesel produced have mass flow rate is 37880 kg/hour. For,

    renewable biodiesel we determine 1 day for a batch. So the storage tanks have

    to store 909,120 kg/batch renewable biodiesel. The calculation of storage tanks

    volume needed to store :

    = = 909,120kgweek790 kgm

    = 1150.78 mweek

  • 7/24/2019 Tk21 Report Assignment2

    49/103

    43

    Universitas Indonesia

    To store the renewable biodiesel product, we will use 2 storage tank. so, the

    renewable biodiesel volume per tank is :

    = 1150.78 m

    week2 =575.39 mweekTo calculate the total volume of storage tanks, safety factor has to be

    considered. Safety factor of the tank is 10% of the total volume. This is based

    on literature saying that for tanks which volume is above 3,8 m 3, only 90%

    volume is filled.

    =575.39 mweek

    0.9 = 639.32m

    weekA.1.2. Diameter and Height of Storage Tank

    Based on rule of thumb, the ratio of height and diameter of tank for

    cylindrical tanks is 2:1. Therefore, H = 2D. The volume of cylinder can be

    calculated as :

    = 1

    4 = 1

    2

    The shape of tanks top cover is ellipsoidal and the bottom cover is flat, with

    major axis ratio of 2:1. The volume of heads (cover and pedestal) is . The tank

    volume is:

    = 2

    24 = 13

    24

  • 7/24/2019 Tk21 Report Assignment2

    50/103

    44

    Universitas Indonesia

    Figure A.1. Types of head of storage tank

    (Source:Perrys Chemical Engineering Handbook, 1999)

    We use the equation of cylinder tank volume to determine the diameter of

    cylinder.

    = 2413 The height of tank is an addition of cylinder and head of tank height. The cylinder

    height is 2D as stated before. The head height is D/6.

    Crude Palm Oil Storage Tank

    Using the equation, the diameter of tank is :

    = 2413 = 28540.4313 = 7.48 The cyclinder height is:

    = 2 = 2 7.48 = 14.96

    The head height is:

    = 6 = 7.48 6 =1.247 The total height is:

    = =16.207

  • 7/24/2019 Tk21 Report Assignment2

    51/103

    45

    Universitas Indonesia

    Jatropha Oil Storage Tank

    Using the equation, the diameter of tank is :

    = 2413

    = 28711.8313

    = 7.53 The cyclinder height is:

    = 2 = 2 7.53 = 15.06 The head height is:

    = 6 = 7.53 6 =1.255 The total height is:

    = =16.315 Nyamplung Oil Storage TankUsing the equation, the diameter of tank is :

    = 2413 = 28641.6613 = 7.51 The cyclinder height is:

    = 2 = 2 7.51 = 15.02

    The head height is:

    = 6 = 7.51 6 =1.252 The total height is:

    = = 16.27 Renewable Biodiesel Storage Tank

    Using the equation, the diameter of tank is :

    = 2413 = 21150.7813 = 3.83 The cyclinder height is:

    = 2 = 2 3.83 = 7.66 The head height is:

    = 6 = 7.66 6 =1.27 The total height is:

  • 7/24/2019 Tk21 Report Assignment2

    52/103

    46

    Universitas Indonesia

    = = 8.937 A.1.3. Design Pressure

    Pressure design of storage tank determines the type of storage tank used.

    Height of fluid in the tank is calculated as follows:

    = The pressure of the tank is:

    = In calculating the design pressure, we assuming that the pressure safety factor is

    15%. = 1 1 5 % 1 Crude Palm Oil

    = 854.0416.207948.94 = 14.59 = 879.3 9,81 14.59 = 1.24 =115% 11.24 =2.576 Jatropha Oil

    = 871.1816.315967.98 = 14.68 = 862 9,81 14.68 = 1.23 =115% 11.23 = 2.5645 Nyamplung Oil

    = 864.1716.27960.18 = 14.64

    = 869 9,81 14.64 = 1.23

    =115% 11.23 = 2.5645 Renewable Biodiesel

    = 575.398.937639.32 = 8.04 = 790 9,81 8.04 = 0.62 =115% 10.62 =1.863

  • 7/24/2019 Tk21 Report Assignment2

    53/103

    47

    Universitas Indonesia

    A.1.4. Wall and Head Thickness

    To calculate the wall and head thickness, there are several data we needs

    to be determined such as corrosion factor, maximum allowable stress, joint

    efficiency, and equipment age. These data determined based on the material

    selected for each storage tank. Carbon steel has a bigger corrosion factor than

    stainless steel, since carbon steel is more prone to corrosion. Corrosion factors of

    stainless steel are also different depending on the grade of stainless steel.

    Calculation of storage tanks wall thickness is based on circumferential

    stress (longitudinal joint). We can use the following formula (Towler, 1990):

    =

    0.6

    While head thickness of storage tank could be calculated with the following

    formula:

    = 20.2 where,

    t = material thickness

    P = pressure gauge

    R= shell radius

    Di= shell inner diameter

    K = ellipsoidal formula factor

    S = maximum allowable stress

    E = joint efficiency = 0.85

    C = corrosion factor = 0.015

    A = planned equipment age = 30 year

    Crude Palm Oil

    = 37.86147.2412,6500.850.637.86 0.01530=0.969 = 37.86294.481.833212.6500.850.237.86 0.015 30 = 1.40

  • 7/24/2019 Tk21 Report Assignment2

    54/103

    48

    Universitas Indonesia

    Jatropha Oil

    = 37.69148.2312,6500.850.637.69 0.01530=0.971

    = 37.69296.461.833212.6500.850.237.69 0.01530=1.40 Nyamplung Oil

    = 37.69147.8312,6500.850.637.69 0.01530=0.969

    =37.69295.661.833

    212,6500.850.237.69 0.01530=1.40 Renewable Biodiesel

    = 27.3875.3912,6500.850.627.38 0.01530=0.642 = 27.38150.781.833212,6500.850.227.38 0.01530

    = 0.802

    A.2. Degumming Tank

    Volume

    Flow rate into the tank 46560 kg/h, to gain the volume we could divide the mass

    rate with total density.

    =

    = 46560 kgh

    872

    = 53.39 So, the volume tank is 53.39 m3. Base on literature if volume above 3,8

    3volume of each tank only filled 90%. The headspace is 10% thus the workingvolume which calculated before is 90%. The use of headspace is a safety unit for

    sudden increment volume.

    = 53.390.9 = 59.33 Diameter and height of mixing tank

  • 7/24/2019 Tk21 Report Assignment2

    55/103

    49

    Universitas Indonesia

    Comparison of high tank with tank diameter (Hs: D) = 2:1. The volume will be

    represented by using ellipsoidal shape, the diameter and height of tank could be

    calculated.

    = 14 = 14 2Cover and pedestal tank of ellipsoidal shape with major to minor axis ratio of 2:1,

    so high head is h=16(Walas, 1990). Volume of 2 cover is:= 14 2 = 14 16 2 = 112

    Tank volume is:

    = = 14 2 112 = 712 Tank diameter is: = 127 = 1259.337 = 3.19

    Height of cylinder is Hs= 2D = 6,38 m

    Height of cover ellipsoidal is Hh = = 1.06

    Height tank is Ht = Hs + (2xHh) = 6.38 + (2x1.06) = 8.51

    Pressure Design

    Height of fluid in the tank

    = = 53.39 8.5159.33 = 7.66

    Pressure

    = = 872 9.8 7.66 = 0.646 = 9.494 Thick of Wall and HeadMaterial choosen is stainless steel because condition of solution must be at pH

    4,5. Avoiding corrosion, stainless steel used for this case

    Thick of wall

    Assumption of corrosion factor is (C) = 0,0042 in/year

    Allowable working stress is (S) = 16.250 lb/in2 (Walas, 1990)

    Assumptions connection efficiency is (E) = 0,85

  • 7/24/2019 Tk21 Report Assignment2

    56/103

    50

    Universitas Indonesia

    Planned of tool age (A) = 30 years

    Thick of cylinder is

    = 0.6

    = 9.49462.9916.2500.850.69.494 0.0042 30 = 0.169 = 4.29 Thick wall head (cap)

    Assumption of corrosion factor is (C) = 0,0042 in/year

    Allowable working stress is (S) = 16.250 lb/in2 (Walas, 1990)

    Assumptions connection efficiency is (E) = 0,85

    Planned of tool age (A) = 30 years

    Thick of wall head is

    = 0.2 = 9.49462.9916.2500.850.29.494 0.0042 30 = 0.169 = 4.29 Impeller

    Type: axial four blade, this kind of impeller is chosen based on literature, if

    viscosity < 5000 cp propeller is common used. This solution has 79 cpAssumption of rotation speed (N): 120 rpm = 2 rps

    Assumption of 80% efficiency motors

    Mixer is designed with the following standards: (Walas, 1988)

    Da : Dt = 1 : 3 Dt : J = 12

    W : Da = 1 : 5 where:

    Da : Db = 6 : 1 Da = stirrer diameter

    C : Dt = 1 : 3 Dt = the diameter of the tank

    Db = stick diameter

    W = width of leaf stirrer

    C = the distance from bottom of the tank

    Reynold number is

    = Stirrer diameter is

    = =

    3.19 = 1.06

  • 7/24/2019 Tk21 Report Assignment2

    57/103

    51

    Universitas Indonesia

    Stirrer leaf widhth is = = 1.06 = 0.213 Strirrer height from the bottom = = 3.19 = 1.06 Diameter of stick = = = 1.06 = 0.353 Diameter baffle = = 3.19 = 0.266 Where

    Da = diameter impeller (ft)

    N = rotation speed (rps)

    = density (lb/ft3) = viscosity (lb/(ft.s))

    = 0.35324.490.05 =63.40

    Figure A.1. Power Number

    (Source: Walas, 1990)

    Then, the power is

    = 1 0 = 1 03 4 . 4 9 2 1.06 = 0.114 /

  • 7/24/2019 Tk21 Report Assignment2

    58/103

    52

    Universitas Indonesia

    APPENDIX B

    B.1. Hydrotreating Reactor

    Fixed-Bed Reactors (FBRs) are the most commonly used reactor systems

    in commercial hydrotreating operations. They are easy and simple to operate.

    However, the simplicity of operation limits their use to the HDS of light feeds.

    For example, in case of naphtha hydrodesulfurization, the reaction is carried out in

    two-phases (gas-solid) fixed-bed reactors since at the reaction conditions the

    naphtha is completely vaporized. On the contrary, for heavier feeds three phases

    are commonly found: hydrogen, a liquid-gas mixture of the partially vaporized

    feed, and the solid catalyst. The latter system is called a trickle-bed reactor (TBR),

    which is a reactor in which a liquid phase and a gas phase flow co-currently

    downward through a fixed bed of catalyst particles while reactions take place.The

    gas is the continuous phase, and the liquid is the disperse phase (Quann et al.,

    1988). A schematic representation of the phenomena occurring in a TBR based on

    three-film theory is presented in Figure 3.3 (Korsten and Hoffmann, 1996;

    Bhaskar et al., 2004). It is common to assume that mass transfer resistance in the

    gas film can be neglected and that no reaction occurs in the gas phase, so that for

    the reactions to occur, the hydrogen has to be transferred from the gas phase to the

    liquid phase, whose concentration is in equilibrium with the bulk partial pressure

    and then adsorbed onto the catalyst surface to react with other reactants. The gas

    reaction products are then transported to the gas phase, while the main liquid

    hydrotreated reaction product is transported to the liquid phase.

    In Hydrotreating Reactor there will be two main reaction which are

    reaction of tryglycerides and H2also reaction between tryglicerides and H2, those

    reaction can be combine into one that will produce the green diesel itself. Thevolume of reactor is equal to the amount of catalyst used. It is because common

    reactor for hydrotreating reactor is fixed bed reactor. In this process, catalyst used

    is Nickel-Molybdenum alumina supported.

    The material for the hydrotreating reactor was chosen to be Stainless Steel

    316 SS. Due to the temperature conditions at about 250C, metal dusting not

    comes into consideration. This leads to a construction material of carbon steel,

    which is the least expensive material (Peters, 2003). However, since the process

  • 7/24/2019 Tk21 Report Assignment2

    59/103

    53

    Universitas Indonesia

    streams at this stage produce some amount of CO2, sweet corrosion is believed to

    be a problem. That is why we chose Stainless Steel as a material for hydrotreating

    reactor.

    Figure B.1. Fixed Bed Reactor

    Source: Handbook of Petroleum Processing

    1. Hydrotreating Reactor (CRV-100)

    Catalyst Weight

    2 21 3 3 6 2 , =

    k1= 0.008554 m3kmol-1 s-1

    Assumption:

    Rate law of these reaction follow one order rate reaction in Packed Bed

    Reactor. Equation for rate law in Packed Bed Reactor is

    = Where:

    =

    /

  • 7/24/2019 Tk21 Report Assignment2

    60/103

    54

    Universitas Indonesia

    Equation for one order rate reaction:

    = So = / The derivation of equation

    = / =

    = = 1

    =

    = 1 = = 1 1

    = = 1

    So,

    = . 1 1 . 1

    = 1 1

  • 7/24/2019 Tk21 Report Assignment2

    61/103

    55

    Universitas Indonesia

    This equation will be used to determine how much catalyst needed for each

    reaction.

    Molar flow Tryglycerides : = 144 /Molar flow Hidrogen : = 570 /

    = = 144144570 =0.2017 / = y. = 0.20173 1 1 1 =0.4034

    Feed volume flow :

    =4,351 Bulk density, = 3200 /

    Then we use polymath to determine conversion vs catalyst weight:

    Figure B.2. Polymath Programming

  • 7/24/2019 Tk21 Report Assignment2

    62/103

    56

    Universitas Indonesia

    Figure B.3. Polymath Programming Result

    Figure B.4.Polymath Programming Graph

  • 7/24/2019 Tk21 Report Assignment2

    63/103

    57

    Universitas Indonesia

    As the result of the polymath, the higher catalyst weight, the higher of

    conversion. Therefore, we choose the conversion is 18% because the high

    conversion needs a lot of catalyst. As we know that catalyst is expensive and the

    lifetime is just about one year. For example, for 85% conversion needs 500,000 kg

    catalyst, that is too much. So we just need 18% conversion plus we will recycle

    the methane that is not converted into the syngas. At 18% conversion, we need

    catalyst 37,000 kg.

    Dimension of Reactor

    Volume of catalyst that fills the reactor can be calculated as follow:

    = = 30,000 kg3600 kg/m = 8.33 Then we assume that the catalyst fills 80% of reactor volume. So we can estimate

    the reactor volume needed as follow:

    = 10080 8.33 = 10.42 Assume that L:D = 2.5:1 (Rule of Thumbs)

    14 = 10.42 14 2.5 = 10.42 = 16.672 = 1.744

    The length is

    = 2 = 4.36 Retention Time

    = = 10.42

    4,351 m/h 36001 =8.62Wall thickness can be obtained by using method in Wallas.

  • 7/24/2019 Tk21 Report Assignment2

    64/103

    58

    Universitas Indonesia

    Thickness t = P x RSxE0,6P CA Corrosion Allowance

    Head Thickness t =P x D

    2SxE0.2P CA

    With : P = operation pressure (Psig)

    Pc = pressure because of catalyst weight

    R = reactor radius (inch)

    E = Joint efficiency, it assumed that the joint effieciency is 0.8

    S = allowable stress

    Due to the high pressures and temperatures in the primary reformer tubes,

    a 25% chromium-20% nickel alloy is the preferred tube material. The

    allowable stress is very dependent on the material that used for the vessel.

    From the Perrys Chemical engineer handbook the allowable stress for the

    conrete is 9.8 Mpa or 145,054 psi.

    The pressure because of catalyst is :

    = = = 30,0009.80.251.744 = 123,287 = 17.87 Thickness t = 14517.87 34.33145,0540.80.614517.87 0.15 = 0.198

    = 5 Head Thickness t = 145 4.1 x 68.662x145,054x0.81.8x145 0.15 = 0.193 = 4.9

    Tubes calculation

    The maximum conventional heat flux through primary reformer tube walls

    is approximately 5,921.176 kcal/ ft2hr with industry averages. Using this value

    and the heat duty through the reformer calculated by Aspen, the primary reformer

    tube size was calculated as follows:

    = = 8.89510 5,921.176 = 15,174.35

    Then, number of tubes needed is

  • 7/24/2019 Tk21 Report Assignment2

    65/103

    59

    Universitas Indonesia

    = 413.4 414 Height of tube

    Based on rule of thumbs, height of reactor is 1.25 times of tubes, so

    = 11.25 = 11.25 4.36 = 3.488 Pinch tube selection and diameter of tubes

    We choose square pinch of tubes because it is more easy to be cleaned.

    The arrangement is at the picture below

    Where :

    = = 1.5 As we know, diameter of reactor is 1.744 m2, then the length of square is allowing

    at phytagoras rule :

    = 2 =1.744

    = 1.7442 = 1.7442

    = 1.233 Assuming the cover of the shell size is 10 cm = 0.01 m

    Then tube line is

    = 1 . 2 3 3 20.01 = 1.213

  • 7/24/2019 Tk21 Report Assignment2

    66/103

    60

    Universitas Indonesia

    As we know that the number of tubes are 414, so

    =

    414= 1.213 1 1.213 1

    4 1 4 = 1.213

    414= 1.213

    414= 1.213

    20.347=1.213

    19.347=1.213 = 0.0627 So, we can calculate diameter of tubes

    = 1.25 = 0.06271.25 = 0.05 = 1.968 B.2. Shift Converter Reactor R-102

    Water Gas Shift (WGS) is reversible reaction. So both the forward and

    reverse reaction is with thermodynamic equilibrium. The true dimensionless

    equilibrium constant can predict from Gibbs free energy as denoted by the

    following reaction.

    =All fixed Bed catalytic reactor assumed to behave like ideal plug flow reactor.

    Equation used for the design or sizing of fixed bed reactor is:

  • 7/24/2019 Tk21 Report Assignment2

    67/103

    61

    Universitas Indonesia

    Figure B.5. Equation used for the design or sizing of fixed bed reactor

    Here is process condition, mole fraction, and molar flow of feed of water gas shift

    reactor from Aspen Hysys simulation.

    Feed Flowrate :187,5 kgmol/h

    0,052083 kgmol/s

    R 8,314

    P 4,16 bar

    T 1050 K

    Species Fraksi mol P parsial K

    CO2 0,055 0,2288 0

    H2O 0,2237 0,930592 0,908513

    H2 0,5735 2,38576 9,59E-05

    CO 0,1178 0,490048 0,252871

    = 1

    = 1 0,2528710,490048 9,59E052,38576 00,2288 0,9085130,9305922,38576 =1,4785

    Constant rate law

    kj = 34.21

    Rate Law

  • 7/24/2019 Tk21 Report Assignment2

    68/103

    62

    Universitas Indonesia

    R1= 0,3799 kgmol/kg cat. S

    The Calculation for sizing shift converter reformer is using Microsoft Excel and

    the result is shown in the sizing table

    Table B.1. Sizing Shift Converter Reformer

    weight of catalyst 0,57 kg cat

    Cat Vol 13,90244 m3

    Vol Reactor 16,35581 m3

    A Reaktor total 0,016889 ft2

    Tube 100

    D Reaktor 1,733461 m

    173,3461 cm

    L 6,933845 m

    D tube 1,733461 cm

    1,06 in

    Residence time 0,018924 h

    69,14921 s

    1,152487 min

    thickness 1,977392 in

    5,0225 cm

    thicknes head 3,829613 in

    9,6478 cm

    TUBE THICKNESS 0,129954 in

    B.3. Absorber Calculation

    The calculation manually doing which it will be suited to the rule of thumb.

    Firstly, should do design the absorber by know the composition of incoming

    gas from model simulation we have done.

    Basis: 1 hour of operation

  • 7/24/2019 Tk21 Report Assignment2

    69/103

    63

    Universitas Indonesia

    Table B.2. Composition of the Incoming Gas

    Component Kmols Fraction Molecular Weight

    Methane 84.72 0.03 16

    Hydrogen 1799.7352 0.6373 2H2O 451.5576 0.1599 18

    CO 152.496 0.054 28

    CO2 335.4912 0.1188 44

    TOTAL 2824 1

    1. The average of molecular weight of the incoming gas

    =

    MW = 6422.906 kg/kmols

    2. Density of gas mixture

    Given that Tin= 38oC, so the density of gas mixture will be calculated

    by following:

    gas = 251.7014855 Kg/m33. Amine and gas Flowrate Calculation

    CO2absorbed = 335.4912 kmoles = 14761.6128 kgs

    Total CO2absorbed by amine = 1003.2 Kgs

    Based on the calculation:

    0.407667 W needs 13758.41 Kgs

    Then The value of W = 9.37477 Kgs/s

    Amine flowrate (A ) = 9.37477 Kgs/s

    Densitas (A)= 1040 Kg/m3

    Gas Flowrate (G) = 5038.413 Kgs/s

    Densitas (G)= 251.7015 Kg/m3

    4. Column Selection

    In this case of absorber, there are two kind of column, tray column

    and packing column. We have choosen packing column for the reason:

  • 7/24/2019 Tk21 Report Assignment2

    70/103

    64

    Universitas Indonesia

    The gas material which enter to the absorber column is a

    corrosive gas.

    From economic side, packing column is cheaper than tray column.

    The pressure drop result of packing column is lower than tray

    column. The contact between gas and liquid in packing column is

    more perfect due to the higher area contact.

    5. Material Selection

    Then choose the following packing as given in the Richardson and

    Coulson as seen in the Figure below

    Figure B.6. Design for Various Packing

    Based the table, the material selected is Racing Rings Ceramic,

    because if it compared to the other material, Rashing Rings ceramic is

    the best on because of it has corrosif endurance, it will be good to the

    corrosif liquid.

    Material = 3Ceramic. Rasching Rings

    Nominal Size = 76 mm

    Bulk Density = 561 kg/m3

    Surface area = 68 m2/m3

    Packing factor = 65 m-1

    Voidage = 75%

  • 7/24/2019 Tk21 Report Assignment2

    71/103

    65

    Universitas Indonesia

    6. Diameter Calculation

    The calculationof it is based on Richardson and Coulson, volume 6.

    Firstly we have to calculate below

    = { }.FLV = 0.0009154

    Then we have to plot the result to the flooding line graph to get the value

    K4. From the plot of K4 Vs FLV. We get K4 at the flooding line 3.2

    Figure B.7. Flooding Line Graph

    G*= 49.913 Kg/m2s

    Designing for a pressure drop of 42 mm water per m of packing. We

    Have

    K4 = 2.1

    % Loading = 81.00925873%

    G* = 40.4342758 Kg/m2s

    Cross Section Area required

  • 7/24/2019 Tk21 Report Assignment2

    72/103

    66

    Universitas Indonesia

    A = 124.60

    Diameter required

    D = 12.6 m

    Hence the diameter which is calculated from this approach is 12.6 meter

    7. Diameter Calculation

    The number stage of packing column absorbtion tower can be

    calculated by using the graph below from Richard and Coulson. From the

    graph, we get the number of stage is about two stages.

    8. Height of Packing Calculation

    Volumetric Flowrate entering gas

    = 20.017 m3/s

    Gas Velocity at the bottom of tower

    = 0.16 m/s

    Mass Flowrate at the top of tower = 4439.84 Kgs/s

    Volumetric Flowrate at the top of tower

    = 17.64 m3/s

    Gas velocity at the top of tower

    = 0.14 m s

  • 7/24/2019 Tk21 Report Assignment2

    73/103

    67

    Universitas Indonesia

    Liquid Flow

    = 0.075 Kgs/ m2/s

    Then We have to calculate the co-relation by the formula below

    KG = 0.136

    Area of Packing/ft height

    A = 8597.9151 m

    Height of Packing require

    H = 20.51 m

    9. Height of Packing Calculation

    Inner Diameter = 12.60 meter

    Height of pack req = 20.51 meter

    Skirt Height = 2 meter

    Density of mat column = 7700 kg/m3

    Wind pressure = 130 kg/m2

    Material Selection

    Carbon Steel

    Permissible tensile stress (f) = 950 kg/cm2

    Thickness of shell = 3.008 mm

  • 7/24/2019 Tk21 Report Assignment2

    74/103

    68

    Universitas Indonesia

    B.4. Steam Methane Reformer R-101

    Before calculating the volume of the reactor, we should calculate the rate of

    reaction by the kinetic equation of Steam Methane Reforming below (Datta, et al.

    2000)

    = 1

    1

    The rate equations that were obtained based on the rate determining steps for

    CH4+ H2O = 3H2+ CO. The rate of reaction use a kgmol/kg cat. S unit ( Hoang,

    2005).

    Where

    = 1 Qr = 4,561

    With parameter kinetic, equilibrium constant and adsorption constant below.

    =

    .

    1

    Reaction rate is rate = 4,08045 kgmol/kgcat.h

    With the molar flow of 2135 kgmol/h, we can calculate the total weight of the

    catalyst below

    Weight of catalyst = 2135/ 4,08045 = 523.23 kg

    By using bulk density of Ni/Mo-Al2O4 catalyst at 0.041 g/ml, we can

    calculate the catalyst volume. Then, the volume of the reactor is (with 80% of

    catalyst volume). After that, we calculate the number of tubes needed. Then,

    calculate number of tubes needed. After that, we calculate the diameter and length

    of reactor by 1:4 ratio. Then, we calculate the diameter of each tube. From the

    literature we read, the construction materials used is a 25% chromium-20% nickel

    alloy is preferred tube material (Low-alloy steels SA-203 grade D). The thickness

    of reactor can be calculated by using a thickness calculation for tall vertical

    vessel. The corrosion allowance is 1/32.

  • 7/24/2019 Tk21 Report Assignment2

    75/103

    69

    Universitas Indonesia

    The value of S can be found onTable 13.1, Process Equipment Design by

    Brownell. A welded-joint efficiency (E) of 0.85 is specified by the ASME code.

    The material we used for our reactor is Low-alloy steels SA 203 grade D. After

    that, we can use a torispherical heads for our reactor design and calculate the head

    thickness.

    The Calculation for sizing steam methane reformer is using Microsoft Excel and

    the result is shown in the sizing table

    Table B.2. Steam Methane Reformer

    weight of catalyst 2 kg cat

    Cat Vol 48,780488 m

    3

    Vol Reactor 57,388809 m3

    A Reaktor total 0,03 ft2

    Tube 100

    D Reaktor 2,6341016 m

    263,41016 cm

    L 10,536406 m

    D tube 2,6341016 cm

    1,06 in

    Residence time 0,0287566 h

    105,0765 s

    1,751275 min

    thickness 1,9773921 in

    5,0225 cm

    thicknes head 3,829613 in

    9,6478 cm

    TUBE THICKNESS 0,1299539 in

  • 7/24/2019 Tk21 Report Assignment2

    76/103

    70

    Universitas Indonesia

    APPENDIX C

    Heat Exchanger Design Procedure

    Step 1. Obtain the required thermos-physical properties of hot and cold

    fluids at the caloric temperature or arithmetic mean temperature. Calculate

    these properties at the caloric temperature if the variation of viscosity

    with temperature is large. The detailed calculation procedure of caloric

    temperature available is in reference.

    r = TT = T TT TStep 2. Perform energy balance and find out the heat duty (Q) of the

    exchanger Q = Q = mCt t = mCT TStep 3. Assume a reasonable value of overall heat transfer coefficient

    (Uo,assm). The value of Uo,assmwith respect to the process hot and cold

    fluids.

  • 7/24/2019 Tk21 Report Assignment2

    77/103

    71

    Universitas Indonesia

    Figure C.1. Shell and Tube Overall Coefficient

    Figure C.2. Air Cooled Exchangers and Immersed Oil Overall Coefficient

    Step 4. Decide tentative number of shell and tube passes (np). Determine

    the LMTD and the correction factor FT. FT normally should be greater

    than 0.75 for the steady operation of the exchangers. Otherwise it is

    required to increase the number of passes to obtain higher FTvalues.

    T =T T T T

    ln T TT T

    Step 5. Calculate heat transfer area (A) required:

    A = QU,LMTD FStep 6. Select tube material, decide the tube diameter (ID = di, OD =

    d0), its wall thickness (in terms of BWG or SWG) and tube length (L).

    Calculate the number of tubes (nt) required to provide the heat transfer area

    (A).

    n = AdLCalculate tube side fluid velocity

    u = 4 m(n n )d

  • 7/24/2019 Tk21 Report Assignment2

    78/103

    72

    Universitas Indonesia

    Re = 4 m(n n )d 10Step 7. Decide type of shell and tube exchanger (fixed tubesheet, U-tube

    etc.). Select the tube pitch (PT), determine inside shell diameter (Ds)

    that can accommodate the calculated number of tubes (nt). Use the

    standard tube counts table for this purpose.

    Figure C.3. Coomon Tube Layouts

    Figure C.4. Heat exchangers tube-layouts

    Step 8. Assign fluid to shell side or tube side. Select the type of baffle

    (segmental, doughnut etc.), its size (i.e. percentage cut, 25% baffles are

    widely used), spacing (B) and number. The baffle spacing is usually chosen

    to be within 0.2 Dsto Ds.

  • 7/24/2019 Tk21 Report Assignment2

    79/103

    73

    Universitas Indonesia

    Figure C.5. Type of Heat Exchanger Baffles

    Step 9. Determine the tube side film heat transfer coefficient (hi) using the

    suitable form of Sieder-Tate equation in laminar and turbulent flow regimes.

    Estimate the shell-side film heat transfer coefficient (ho) from:

    j = hD ck

    .

    And find the hio from:

    h = h IDODStep 10. Calculate overall heat transfer coefficient (Uo,cal)

    U = hhh h

    With the design overall coefficient is

    U = QA TThe dirt factor is calculated from:

    R = U UUU

  • 7/24/2019 Tk21 Report Assignment2

    80/103

    74

    Universitas Indonesia

    Step 11. Pressure drop calculation will be the tube side pressure drop (PT)

    and the shell side pressure drop (PS). Pressure drop in the straight section

    of the tube (frictional loss) (Pt) and return (Pn) due to change of

    direction of fluid. So the total of each pressure drop: PT = Pt + Pn

    P = fGD N 1 5,221010 DsIf the tube-side pressure drop exceeds the allowable pressure drop for the

    process system,

    we can decrease the number of tube passes or increase number of tubes per

    pass.

    P = LfG5,221010 DsIf the shell-side pressure drop exceeds the allowable pressure drop

    P = LfG5,221010 Ds

    The procedure is the same for all heat exchanger, the calculation is using

    Microsoft Excel and the result is shown in the sizing table. Below will be shown

    the calculation for one heat exchanger.

    Material Selection for Heat Exchanger

    For heat exchanger using low pressure and medium pressure steam as

    heating fluid , we used carbon steel as material because temperature of process is

    not too high. Moreover, Fluid that we used is Oil that cant cause corrosion. We

    choose Carbon Steel SA-283 with Grade C because this material is commonly

    used. Carbon steel is used because highly durable, low cost and easy tomanufactured.

    Due to the high temperature like fired heater used for heating feed to steam

    methane reformer. Therefore, carbon steels cannot be used as pipe material

    because this material cannot be used in high temperature conditions. Carbon steel

    can be used as material for temperature conditions bellow 1400oF. Materials that

    can be used as wall material which can also be used in high temperature

    conditions are stainless steel. Therefore, the proper material for low pH and high

  • 7/24/2019 Tk21 Report Assignment2

    81/103

    75

    Universitas Indonesia

    T = 155oC

    T2= 134oC

    t1= 25oC

    t2= 65oC

    temperature is stainless steel (SS)316L. Grade 316 is the standard molybdenum

    bearing grade, second importance to 304 amongst the austenitic stainless steel.

    The molybdenum gives 316 better overall corrosion resistant properties than grade

    304 particular resist to pitting and crevice corrosion in chlorine environment.

    C.1. Heat Exchanger E-101

    Heat Balance

    CPO, =+ = 45, c = 2200 J/kg-KQ =m.c.T

    = 44,700 kg/h) (2200 J/kg-K) (338-298) K

    = 3,933,600,000 J/hSteam, = + =148.5, c =4180 J/kg-K

    W = = ,,, J/ J/K K=44812,03 kg/h

    Determine the LMTD

    LMTD = = = 99.2o

    C

    R = =

    = 0.525S =

    == 0.308

    Determine the temperature difference

  • 7/24/2019 Tk21 Report Assignment2

    82/103

    76

    Universitas Indonesia

    It could be obtained from the graph that shows temperature correction factor. The

    available existing graphs are for two shell passes, four, multiple of four tube

    passes, etc.

    The example graph that is used in this case could be seen below :

    Figure C.6. Temperature Correction Factor : two shell passes ; four or multiple passes

    (Source: Kern)

    The temperature correction factor (FT) that is obtained from Figure C.6 is 1.

    The properties of tube and pitch could be obtained from Table and Table

    From the following table could be obtained the exact value of tube outer diameter,

    square pitch length, shell inner diameter, amount of passes, and the last one in

    amount of tubes. Actually there is no calculation done before choosing the value

    of tube and pitch properties, but the chosen one should logically makes sense.

    In this case, the selected tube OD is 0.75 in = 0.019m

    Square pitch length = 1 in = 0.0254 m

    Shell inner diameter = 19.25 in = 0.49m

    Amount of passes = 2

    So that the amount of tubes is 220

  • 7/24/2019 Tk21 Report Assignment2

    83/103

    77

    Universitas Indonesia

    Figure C.7. Tube Sheet Layouts (square pitch)

    (Source: Kern)

    Besides that, the other tubes properties could be obtainedfrom the following

  • 7/24/2019 Tk21 Report Assignment2

    84/103

    78

    Universitas Indonesia

    Figure C.8. HE Layouts

    (Source: Kern)

    The table above is used by using the previous selected tube OD. As the tube OD is

    considered to be then the BWG value could be obtained. The BWG value is

    chosen randomly, so that the following properties that are in the same row could

    be obtained.

  • 7/24/2019 Tk21 Report Assignment2

    85/103

    79

    Universitas Indonesia

    The BWG value = 14

    The wall thickness = 0.083 in = 0.0021m

    Tube inner diameter = 0.584 in= 0.015m

    Flow area per tube = 0.268 in2= 1.73 x 10-4m2

    Surface/lin (outside) = 0.1963 ft2= 0.018 m2

    Surface/lin (i