2021-01TIP Revision Summary
Description of ChangeTIP ID Project NameSponsorFunding
Change ($)Funding
Change (%)
System: Local RoadALA170088 Albany San Pablo Ave & Buchanan St Pedestrian
Imps.Update the funding plan to change the program year and source for $535K in CONfunds from FY20 Local to FY22 Sales Tax, reprogram $340K in CON STP fromFY21 to FY22 and add $10K in FY20 PSE Sales Tax and $465K in FY22 CONSales Tax
$474,914 9.0%
SF-130001 San Francisco Dept ofPublic Works (SFDPW)
SF- Better Market Street TransportationElements
Update the funding plan to change the source and program year for $71K in CONfrom FY25 RTP-LRP to FY21 Repurposed Earmark funds
$0 0.0%
SOL110006 Solano TransportationAuthority (STA)
Jepson: Leisure Town Road Phase 1B and1C
Update the funding plan to add $81K in FY22 CON Repurposed Earmark funds $81,047 0.4%
SON170024 Healdsburg Healdsburg Avenue Complete StreetsImprovements
Update the funding plan to reprogram $600K in CON STP and $400K in CON Localfrom FY22 to FY23 and to add $37K in FY23 CON repurposed earmark funds
$36,831 2.9%
VAR170012 Caltrans GL: Bridge Rehab/Recon. - Local HwyBridge Program
Update the funding plan and back-up listing to reflect the latest information fromCaltrans
$4,629,674 0.5%
System: Public Lands/TrailsSCL050083 San Jose Coyote Creek Trail (Hwy 237-Story Rd) Update the funding plan to reprogram $4M in CON ATP from FY21 to FY22 $0 0.0%
System: State HighwaySCL190008 Santa Clara Valley
Transportation Authority(VTA)
US 101/De L Cruz Blvd - Trimble Road I/CImp
Update the funding plan to change the source and program year for $10M in FY25RTP-LRP to FY21 SB1-LPP funds change the source for $15M in FY21 funds fromSales Tax to SB1-LPP
$0 0.0%
SOL090015 Solano County Redwood-Fairgrounds Dr Interchange Imps Update the funding plan to reprogram $428K in FY21 Repurposed Earmark fundsand $56K in FY21 Local funds from CON to PE
-$307 0.0%
SOL110001 MetropolitanTransportationCommission (MTC)
Solano I-80 Managed Lanes Update the funding plan to reprogram $65.3M in other local funds as $63.5M inCMAQ funds in FY24, and $1.8M in STIP funds in FY22; and reprogram $14.2M inTCEP CON Support funds to CON in FY22.
$0 0.0%
SOL190025 Caltrans Solano WB I-80 Cordelia Truck Scales Update the funding plan to reprogram $5.3M in other local funds as STIP funds forPS&E in FY21
$0 0.0%
SON150006 Santa Rosa US 101 Hearn Ave Interchange Update the funding plan to add $4.8M in CON RTP-LRP funds $4,800,000 13.9%
VAR170002 Caltrans GL: Highway Safety Improvement Program Update the back-up listing to reflect the latest information from Caltrans $0 0.0%
System: TollwayMRN050018 Golden Gate Bridge,
Highway and TransitDistrict
Golden Gate Bridge Seismic Retrofit, Phase3B
Update the funding plan to add $544K in FY22 CON Earmark HPP funds beingtransferred from MRN970016
$543,569 0.4%
MRN050019 Golden Gate Bridge,Highway and TransitDistrict
Golden Gate Bridge-Suicide DeterrentSafetyBarrier
Update the funding plan to add $3.6M in prior year Local, $7.9M in FY21 STP, and$11.4M in FY25 RTP-LRP; reprogram $2M in STP from FY22 to FY21; change thesource for $7.7M in FY21 funds from FHIP to STP; remove $29M in prior yearAdvanced Construction
-$6,197,369 -2.4%
2Page 1 of May 12, 2021Metropolitan Transportation Commission
2021-01TIP Revision Summary
Description of ChangeTIP ID Project NameSponsorFunding
Change ($)Funding
Change (%)
MRN970016 Golden Gate Bridge,Highway and TransitDistrict
Golden Gate Bridge Seismic Retrofit, Ph: 1-3A
Update the funding plan to remove $544K in FY21 CON Earmark HPP funds beingtransferred to MRN050018
-$543,569 -0.1%
System: TransitALA190014 Bay Area Rapid Transit
District (BART)BART-Elevator Renovation program Update the funding plan to add $7M in FY21 5337 and $1.75M in FY21 Local funds $8,750,000 50.0%
REG090037 Bay Area Rapid TransitDistrict (BART)
BART: Railcar Procurement Program Update the funding plan to change the program year and source for $156M in CONfunds from FY25 RTP-LRP to FY21 5307-CRRSAA ($6.8M), FY21 5307 ($26M),FY21 5337 ($94M), and FY21 Local ($28M) funds, and reprogram $4M in Localfunds from FY22 to FY21
$0 0.0%
REG170017 Bay Area Rapid TransitDistrict (BART)
BART Transbay Core CapacityImprovements
Update the funding plan to change the program year and source for $475M in CONfunds from FY25 RTP-LRP to FY21 5309 Core Capacity and for $87M in CON fundsfrom FY25 RTP-LRP to FY21 CIG-ARPA funds.
$0 0.0%
SF-050024 San Francisco MunicipalTransport Agency(SFMTA)
SFMTA:Train Control & Trolley SignalRehab/Replace
Update the funding plan to change the source and program year for $29M fromFY25 RTP-LRP to FY21 5337 and for $7.2M from FY25 RTP-LRP to FY21 SalesTax
$0 0.0%
SF-090012 San Francisco MunicipalTransport Agency(SFMTA)
Light Rail Vehicle Procurement Update the funding plan to change the source for $26M in RTP-LRP to $14.7M inAB664 Bridge Toll funds, $6M in BATA Project Savings, and $5.2M in Local fundsand reprogram from FY25 to FY21
$0 0.0%
SF-170021 San Francisco MunicipalTransport Agency(SFMTA)
SFMTA: Rehab Historic Streetcars Update the funding plan to add $7M in 5337 and $1.8M in Sales Tax funds $9,180,385 32.0%
SF-95037B San Francisco MunicipalTransport Agency(SFMTA)
SF Muni Rail Replacement Program Update the funding plan to add $7M in FY21 5337 and $1.8M in FY21 Sales Taxfunds
$8,782,500 3.0%
SF-99T002 San Francisco MunicipalTransport Agency(SFMTA)
Cable Car Traction Power & GuidewayRehab
Update the funding plan to add $1.6M in FY21 5337 and $404K in FY21 Sales Taxfunds
$2,021,250 2.0%
SOL190017 Solano County Transit(SolTrans)
SolTrans Electric Bus ChargingInfrastructure
Update the funding plan to add $439K in FY21 5339 funds and $110K in FY21 Localfunds
$548,684 6.8%
VAR190002 Bay Area Rapid TransitDistrict (BART)
BART: TOD Implementation Update the funding plan to add $350K in FTA Pilot Program for Transit-OrientedDevelopment (TOD) Planning grant funds
$350,000 6.7%
Total Funding Change: $33,457,609
$25,000,000
Proposed:
2021 TIP Only
$834,849,370
$6,548,406,279
$1,262,895,934
$20,720,222
Regional Total
$2,532,308,354
Federal
$3,355,248,216
State
$2,097,745,304
Local
$827,677,527
$10,945,148,931
TIP Revision Summary
$7,383,608,754Current:
$33,457,609
$10,911,691,322
Delta:
$168,096,687
$822,939,862
$852,677,527 $188,816,909
-$835,202,475
2Page 2 of May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -335,000 -335,000ATP-STATE -
PSE - - - -65,000 -65,000LOCAL GEN FUND -
PSE - - - -10,000 -10,000SALESTAX-MEASURE -
ROW - - - -- --GASTAX -
CON - - - -- --GASTAX -
CON - - - -- --LOCAL GEN FUND -
CON - - - -- 4,000,0004,000,000RTP-LRP -
CON - 1,000,000 - -- -1,000,000SALESTAX-MEASURE -
CON - 340,000 - -- -340,000STP-T5 -
410,000 4,000,000Total Funding - -1,340,000 -5,750,000 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -335,000 -335,000ATP-STATE -
PSE - - - -65,000 -65,000LOCAL GEN FUND -
ROW - - - -- --GASTAX -
CON - - - -267,543 -267,543GASTAX -
CON - - - -267,543 -267,543LOCAL GEN FUND -
CON - - - -- 4,000,0004,000,000RTP-LRP -
CON 340,000 - - -- -340,000STP-T5 -
935,086 4,000,000Total Funding 340,000 -- -5,275,086 -
Albany
Sec. RTP ID:
CTIPS ID:
Mode:
San Pablo Ave & Buchanan St Pedestrian Imps.
ACTIVEALA170088
Trans. System:
RTP Cost:
2021-00 Version:
EXEMPT (40 CFR 93.126) - Projects that correct, improve, or eliminate a hazardous location or featureAQ Description:
Albany
RTP Cycle:
Status:
Project Type:
20600006485
Project Name:
SYSTMGMTPurpose:
17-10-0022 AA
Revision:
Hwy Rte:
LOCAL ROAD
TIP ID:
PLANBAYAREA2040
123
Primary RTP ID:
Implementing Agency:
3
$20,698,000,000
ENHANCEMENTS
CURRENT
Review:
Sponsoring Agency:
End of Project ALA170088
Local and Streets and Roads - Existing ConditionsRTP Description:
Albany: Various Locations on Buchanan St and San Pablo Ave: Streetscape improvements including medians, bulb outs, signal modifications,striping of high visibility crosswalks. Project is phased.
Proj Description:
2021 TIP UpdateRevision Reason:
BIKE/PED:85% | BUS:15%
AQCTF Review: Review Pending
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
ALA170088 2021-01 ACCEPTED
17-10-0022
20600006485
Albany Albany
4
San Pablo Ave & Buchanan St Pedestrian Imps.
AA
ENHANCEMENTS SYSTMGMTLOCAL ROAD BIKE/PED:85% | BUS:15%
PLANBAYAREA2040
$20,698,000,000
EXEMPT (40 CFR 93.126) - Projects that correct, improve, or eliminate a hazardous location or feature
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte: 123
Local and Streets and Roads - Existing ConditionsRTP Description:
Albany: Various Locations on Buchanan St and San Pablo Ave: Streetscape improvements including medians, bulb outs, signal modifications,striping of high visibility crosswalks. Project delivery is phased.
Proj Description:
Update the funding plan to change the program year and source for $535K in CON funds from FY20 Local to FY22 Sales Tax, reprogram$340K in CON STP from FY21 to FY22 and add $10K in FY20 PSE Sales Tax and $465K in FY22 CON Sales Tax
Revision Reason:
AQCTF Review: Review Pending
27Page 1 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
CON 14,000,000 - - -7,000,000 -21,000,0005337-T5 -
CON 3,500,000 - - -1,750,000 -5,250,000LOCAL GEN FUND -
8,750,000 -Total Funding 17,500,000 -- -26,250,000 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
CON 7,000,000 - - -7,000,000 -14,000,0005337-T5 -
CON 1,750,000 - - -1,750,000 -3,500,000LOCAL GEN FUND -
8,750,000 -Total Funding 8,750,000 -- -17,500,000 -
BART
Sec. RTP ID:
CTIPS ID:
Mode:
BART-Elevator Renovation program
ACTIVEALA190014
Trans. System:
RTP Cost:
2021-00 Version:
EXEMPT (40 CFR 93.126) - Reconstruction or renovation of transit buildings and structures (e.g., rail or bus buildings, storage andmaintenance facilities, stations, terminals, and ancillary structures)
AQ Description:
BART
RTP Cycle:
Status:
Project Type:
20600006606
Project Name:
MAINT/REHABPurpose:
17-10-0032 PR
Revision:
Hwy Rte:
TRANSIT
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
3
$360,000,000
STRUCTURE/BLDG
CURRENT
Review:
Sponsoring Agency:
End of Project ALA190014
Regional Rail Station Modernization and Access ImprovementsRTP Description:
BART: Various locations system-wide: Renovate or rehabilitate elevatorsProj Description:
2021 TIP UpdateRevision Reason:
RAIL:100%
AQCTF Review: Review Pending
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
ALA190014 2021-01 ACCEPTED
17-10-0032
20600006606
BART BART
4
BART-Elevator Renovation program
PR
STRUCTURE/BLDG MAINT/REHABTRANSIT RAIL:100%
PLANBAYAREA2040
$360,000,000
EXEMPT (40 CFR 93.126) - Reconstruction or renovation of transit buildings and structures (e.g., rail or bus buildings, storage andmaintenance facilities, stations, terminals, and ancillary structures)
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Regional Rail Station Modernization and Access ImprovementsRTP Description:
BART: Various locations system-wide: Renovate or rehabilitate elevatorsProj Description:
Update the funding plan to add $7M in FY21 5337 and $1.75M in FY21 Local fundsRevision Reason:
AQCTF Review: Review Pending
27Page 2 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -33,887,342 -33,887,342EARMARK-T3 -
PSE - - - -- --LOCAL GEN FUND -
CON 51,060,990 - - -- -51,060,990AC-LOCAL -
CON - 543,569 - -1,138,191 -1,681,760EARMARK-T3 -
CON - - 9,500,000 -- 41,560,99051,060,990HBP-T3 -
CON - - - -- --LOCAL GEN FUND -
35,025,533 41,560,990Total Funding 51,060,990 9,500,000543,569 -137,691,082 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -33,887,342 -33,887,342EARMARK-T3 -
PSE - - - -- --LOCAL GEN FUND -
CON 51,060,990 - - -- -51,060,990AC-LOCAL -
CON - - - -1,138,191 -1,138,191EARMARK-T3 -
CON - - 9,500,000 -- 41,560,99051,060,990HBP-T3 -
CON - - - -- --LOCAL GEN FUND -
35,025,533 41,560,990Total Funding 51,060,990 9,500,000- -137,147,513 -
GGBHTD
Sec. RTP ID:
CTIPS ID:
Mode:
Golden Gate Bridge Seismic Retrofit, Phase 3B
ACTIVEMRN050018
Trans. System:
RTP Cost:
2021-00 Version:
EXEMPT (40 CFR 93.126) - Widening narrow pavements or reconstructing bridges (no additional travel lanes)AQ Description:
GGBHTD
RTP Cycle:
Status:
Project Type:
20600003406
Project Name:
MAINT/REHABPurpose:
17-10-0009 AA
Revision:
Hwy Rte:
TOLLWAY
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
28
$2,031,000,000
BRIDGE
CURRENT
Review:
Sponsoring Agency:
End of Project MRN050018
Golden Gate Bridge Capital and OperationsRTP Description:
SF/Marin County: Golden Gate Bridge; Seismic retrofit of the Golden Gate Bridge - construction of suspension span, south pier and fender.Proj Description:
2021 TIP UpdateRevision Reason:
AUTO:100%
AQCTF Review: Reviewed
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
MRN050018 2021-01 PROPOSED
17-10-0009
20600003406
GGBHTD GGBHTD
29
Golden Gate Bridge Seismic Retrofit, Phase 3B
AA
BRIDGE MAINT/REHABTOLLWAY AUTO:100%
PLANBAYAREA2040
$2,031,000,000
EXEMPT (40 CFR 93.126) - Widening narrow pavements or reconstructing bridges (no additional travel lanes)
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Golden Gate Bridge Capital and OperationsRTP Description:
SF/Marin County: Golden Gate Bridge; Seismic retrofit of the Golden Gate Bridge - construction of suspension span, south pier and fender.Proj Description:
Update the funding plan to add $544K in FY22 CON Earmark HPP funds being transferred from MRN970016Revision Reason:
AQCTF Review: Reviewed
27Page 3 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
ENV - - - -143,000 -143,000LOCAL GEN FUND -
ENV - - - -1,850,000 -1,850,000MTC-LOCAL -
PSE - - - -5,543,101 -5,543,101LOCAL GEN FUND -
CON - - - -15,817,782 -15,817,782AC-LOCAL -
CON - - - -45,239,332 -45,239,332FHIP-T5-APPR -
CON 15,000,000 6,057,600 - -48,942,400 -70,000,000HBP-T4 -
CON - - - -428,461 -428,461LOCAL GEN FUND -
CON - - - -- 11,430,84911,430,849RTP-LRP -
CON - - - -7,000,000 -7,000,000STATE-OTHER -
CON - - - -12,000,000 -12,000,000STP-T4 -
CON 17,670,668 - - -- -17,670,668STP-T5 -
CON - - - -63,614,407 -63,614,407TOLLS-LOC -
200,578,483 11,430,849Total Funding 32,670,668 -6,057,600 -250,737,600 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
ENV - - - -143,000 -143,000LOCAL GEN FUND -
ENV - - - -1,850,000 -1,850,000MTC-LOCAL -
PSE - - - -5,543,101 -5,543,101LOCAL GEN FUND -
CON - - - -45,000,000 -45,000,000AC-LOCAL -
CON 7,681,887 - - -45,239,332 -52,921,219FHIP-T5-APPR -
CON 15,000,000 - 6,057,600 -48,942,400 -70,000,000HBP-T4 -
CON - - - -398,868 -398,868LOCAL GEN FUND -
CON - - - -7,000,000 -7,000,000STATE-OTHER -
CON - - - -12,000,000 -12,000,000STP-T4 -
CON - 2,078,781 - -- -2,078,781STP-T5 -
CON - - - -60,000,000 -60,000,000TOLLS-LOC -
226,116,701 -Total Funding 22,681,887 6,057,6002,078,781 -256,934,969 -
GGBHTD
Sec. RTP ID:
CTIPS ID:
Mode:
Golden Gate Bridge-Suicide Deterrent SafetyBarrier
ACTIVEMRN050019
Trans. System:
RTP Cost:
2021-00 Version:
EXEMPT (40 CFR 93.126) - Safer non-Federal-aid system roadsAQ Description:
GGBHTD
RTP Cycle:
Status:
Project Type:
20600003535
Project Name:
SYSTMGMTPurpose:
17-10-0009 PR
Revision:
Hwy Rte:
TOLLWAY
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
29
$2,031,000,000
BRIDGE
CURRENT
Review:
Sponsoring Agency:
End of Project MRN050019
Golden Gate Bridge Capital and OperationsRTP Description:
Golden Gate Bridge: Build suicide deterrent system. Including design & Environmental analysis, plus analysis of alternatives & wind tunneltests to ensure the feasibility of designs and build deterrent system. Project will be constructed in phases.
Proj Description:
2021 TIP UpdateRevision Reason:
BIKE/PED:100%
AQCTF Review: Reviewed
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
MRN050019 2021-01 ACCEPTED
17-10-0009
20600003535
GGBHTD GGBHTD
30
Golden Gate Bridge-Suicide Deterrent SafetyBarrier
PR
BRIDGE SYSTMGMTTOLLWAY BIKE/PED:100%
PLANBAYAREA2040
$2,031,000,000
EXEMPT (40 CFR 93.126) - Safer non-Federal-aid system roads
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Golden Gate Bridge Capital and OperationsRTP Description:
Golden Gate Bridge: Build suicide deterrent system. Including design & Environmental analysis, plus analysis of alternatives & wind tunneltests to ensure the feasibility of designs and build deterrent system. Project will be constructed in phases.
Proj Description:
Update the funding plan to add $3.6M in prior year Local, $7.9M in FY21 STP, and $11.4M in FY25 RTP-LRP; reprogram $2M in STP fromFY22 to FY21; change the source for $7.7M in FY21 funds from FHIP to STP; remove $29M in prior year Advanced Construction
Revision Reason:
AQCTF Review: Reviewed
27Page 4 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -4,609,513 -4,609,513DBR-T2 -
PSE - - - -1,176,000 -1,176,000EARMARK-T3 -
CON - - - -73,974,676 -73,974,676DBR-T2 -
CON - - - -25,096,077 -25,096,077EARMARK-T2 -
CON 1,393,864 - - -17,240,519 -18,634,383EARMARK-T3 -
CON - - - -145,939,010 -145,939,010HBRR -
CON - - - -72,183,942 -72,183,942LOCAL GEN FUND -
CON - - - -26,000,000 -26,000,000RIP-T2 -
CON - - - -5,000,000 -5,000,000TCRP -
371,219,737 -Total Funding 1,393,864 -- -372,613,601 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -4,609,513 -4,609,513DBR-T2 -
PSE - - - -1,176,000 -1,176,000EARMARK-T3 -
CON - - - -73,974,676 -73,974,676DBR-T2 -
CON - - - -25,096,077 -25,096,077EARMARK-T2 -
CON 1,937,433 - - -17,240,519 -19,177,952EARMARK-T3 -
CON - - - -145,939,010 -145,939,010HBRR -
CON - - - -72,183,942 -72,183,942LOCAL GEN FUND -
CON - - - -26,000,000 -26,000,000RIP-T2 -
CON - - - -5,000,000 -5,000,000TCRP -
371,219,737 -Total Funding 1,937,433 -- -373,157,170 -
GGBHTD
Sec. RTP ID:
CTIPS ID:
Mode:
Golden Gate Bridge Seismic Retrofit, Ph: 1-3A
ACTIVEMRN970016
Trans. System:
RTP Cost:
2021-00 Version:
EXEMPT (40 CFR 93.126) - Widening narrow pavements or reconstructing bridges (no additional travel lanes)AQ Description:
GGBHTD
RTP Cycle:
Status:
Project Type:
20600000347
Project Name:
MAINT/REHABPurpose:
17-10-0009 AA
Revision:
Hwy Rte:
TOLLWAY
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
31
$2,031,000,000
BRIDGE
CURRENT
Review:
Sponsoring Agency:
End of Project MRN970016
Golden Gate Bridge Capital and OperationsRTP Description:
San Francisco /Marin Counties: Golden Gate Bridge; Seismic retrofit of the Golden Gate Bridge - construction on north and south approachviaducts, and Ft. Point Arch.
Proj Description:
2021 TIP UpdateRevision Reason:
AUTO:100%
AQCTF Review: Review Pending
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
MRN970016 2021-01 ACCEPTED
17-10-0009
20600000347
GGBHTD GGBHTD
32
Golden Gate Bridge Seismic Retrofit, Ph: 1-3A
AA
BRIDGE MAINT/REHABTOLLWAY AUTO:100%
PLANBAYAREA2040
$2,031,000,000
EXEMPT (40 CFR 93.126) - Widening narrow pavements or reconstructing bridges (no additional travel lanes)
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Golden Gate Bridge Capital and OperationsRTP Description:
San Francisco /Marin Counties: Golden Gate Bridge; Seismic retrofit of the Golden Gate Bridge - construction on north and south approachviaducts, and Ft. Point Arch.
Proj Description:
Update the funding plan to remove $544K in FY21 CON Earmark HPP funds being transferred to MRN050018Revision Reason:
AQCTF Review: Review Pending
27Page 5 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
CON 6,754,237 - - -- -6,754,2375307-CRRSAA -
CON - - - -44,059,933 -44,059,9335307-T4 -
CON 25,983,047 - - -77,126,193 -103,109,2405307-T5 -
CON - - - -12,565,777 -12,565,7775309-T3 -
CON - - - -10,000,000 -10,000,0005309-T4-FG -
CON - - - -1,500,000 -1,500,0005337-T4 -
CON 94,924,189 - - -86,464,385 -181,388,5745337-T5 -
CON - - - -12,556,599 -12,556,599BT-664 -
CON - - - -40,000,000 -40,000,000BT-RM2 -
CON - - - -99,800,000 -99,800,000CMAQ-T5 -
CON 27,915,371 - - -- -27,915,371FARE REVENUE -
CON 4,000,000 - - -1,514,792,141 -1,518,792,141LOCAL GEN FUND -
CON - - - -- 562,757,375562,757,375RTP-LRP -
CON - - - -107,100,000 -107,100,000SB1 -
2,005,965,028 562,757,375Total Funding 159,576,844 -- -2,728,299,247 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
CON - - - -44,059,933 -44,059,9335307-T4 -
CON - - - -77,126,193 -77,126,1935307-T5 -
CON - - - -12,565,777 -12,565,7775309-T3 -
CON - - - -10,000,000 -10,000,0005309-T4-FG -
CON - - - -1,500,000 -1,500,0005337-T4 -
CON - - - -86,464,385 -86,464,3855337-T5 -
CON - - - -12,556,599 -12,556,599BT-664 -
CON - - - -40,000,000 -40,000,000BT-RM2 -
CON - - - -99,800,000 -99,800,000CMAQ-T5 -
CON - 4,000,000 - -1,514,792,141 -1,518,792,141LOCAL GEN FUND -
CON - - - -- 718,334,219718,334,219RTP-LRP -
CON - - - -107,100,000 -107,100,000SB1 -
2,005,965,028 718,334,219Total Funding - -4,000,000 -2,728,299,247 -
BART
Sec. RTP ID:
CTIPS ID:
Mode:
BART: Railcar Procurement Program
ACTIVEREG090037
Trans. System:
RTP Cost:
2021-00 Version:
NON-EXEMPTAQ Description:
BART
RTP Cycle:
Status:
Project Type:
20600004447
Project Name:
MAINT/REHABPurpose:
17-10-0026 AA
Revision:
Hwy Rte:
TRANSIT
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
25
$30,564,000,000
ROLLING STOCK
CURRENT
Review:
Sponsoring Agency:
End of Project REG090037
Regional Transit Capital - Existing ConditionsRTP Description:
BART: Procure 790 Railcars (includes the replacement of 669 Railcars)Proj Description:
2021 TIP UpdateRevision Reason:
RAIL:100%
AQCTF Review: Reviewed
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
REG090037 2021-01 ACCEPTED
17-10-0026
20600004447
BART BART
26
BART: Railcar Procurement Program
AA
ROLLING STOCK MAINT/REHABTRANSIT RAIL:100%
PLANBAYAREA2040
$30,564,000,000
NON-EXEMPT
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Regional Transit Capital - Existing ConditionsRTP Description:
BART: Procure 790 Railcars (includes the replacement of 669 Railcars)Proj Description:
Update the funding plan to change the program year and source for $156M in CON funds from FY25 RTP-LRP to FY21 5307-CRRSAA($6.8M), FY21 5307 ($26M), FY21 5337 ($94M), and FY21 Local ($28M) funds, and reprogram $4M in Local funds from FY22 to FY21
Revision Reason:
AQCTF Review: Reviewed
27Page 6 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -300,000,000 -300,000,0005309-T5-CC -
CON 812,775,134 - - -- -812,775,1345309-T5-CC -
CON - - - -819,000,000 -819,000,000LOCAL GEN FUND -
CON - - - -- 1,148,524,8661,148,524,866RTP-LRP -
CON - - - -111,800,000 -111,800,000SALESTAX-MEASURE -
CON - - - 174,110,000144,490,000 -318,600,000SB1 -
1,375,290,000 1,148,524,866Total Funding 812,775,134 -- 174,110,0003,510,700,000 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -300,000,000 -300,000,0005309-T5-CC -
CON 250,700,000 - - -- -250,700,0005309-T5-CC -
CON - - - -819,000,000 -819,000,000LOCAL GEN FUND -
CON - - - -- 1,710,600,0001,710,600,000RTP-LRP -
CON - - - -111,800,000 -111,800,000SALESTAX-MEASURE -
CON - - - 174,110,000144,490,000 -318,600,000SB1 -
1,375,290,000 1,710,600,000Total Funding 250,700,000 -- 174,110,0003,510,700,000 -
BART
Sec. RTP ID:
CTIPS ID:
Mode:
BART Transbay Core Capacity Improvements
ACTIVEREG170017
Trans. System:
RTP Cost:
2021-00 Version:
NON-EXEMPTAQ Description:
BART
RTP Cycle:
Status:
Project Type:
20600006294
Project Name:
EXPANSIONPurpose:
17-10-0006 PR
Revision:
Hwy Rte:
TRANSIT
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
5
$3,132,000,000
OTHER
CURRENT
Review:
Sponsoring Agency:
End of Project REG170017
BART Transbay Core Capacity Project (Financing cost included in RTPID 17-10-0016)RTP Description:
BART: Systemwide: Implement communication-based train control (CBTC) system, expand rail car fleet by 306 vehicles, add traction powersubstations (5); At Hayward Maintenance Complex; Expand facilities to accommodate expanded fleet
Proj Description:
2021 TIP UpdateRevision Reason:
RAIL:100%
AQCTF Review: Review Pending
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
REG170017 2021-01 ACCEPTED
17-10-0006
20600006294
BART BART
6
BART Transbay Core Capacity Improvements
PR
OTHER EXPANSIONTRANSIT RAIL:100%
PLANBAYAREA2040
$3,132,000,000
NON-EXEMPT
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
BART Transbay Core Capacity Project (Financing cost included in RTPID 17-10-0016)RTP Description:
BART: Systemwide: Implement communication-based train control (CBTC) system, expand rail car fleet by 306 vehicles, add traction powersubstations (5); At Hayward Maintenance Complex; Expand facilities to accommodate expanded fleet
Proj Description:
Update the funding plan to change the program year and source for $475M in CON funds from FY25 RTP-LRP to FY21 5309 Core Capacityand for $87M in CON funds from FY25 RTP-LRP to FY21 CIG-ARPA funds.
Revision Reason:
AQCTF Review: Review Pending
27Page 7 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
ENV - - - -457,000 -457,000EARMARK-T3 -
ENV - - - -115,000 -115,000LOCAL GEN FUND -
PSE - - - -1,210,000 -1,210,000ATP-REG -
PSE - - - -861,000 -861,000EARMARK-T3 -
PSE - - - -429,530 -429,530LOCAL GEN FUND -
PE - - - -92,400 -92,400LOCAL GEN FUND -
PE - - - -712,700 -712,700STP-T4 -
CON - 4,046,000 - -- -4,046,000ATP-REG -
CON - - - -2,356,000 -2,356,000EARMARK-T3 -
CON - - - -10,403,001 -10,403,001LOCAL GEN FUND -
CON - - - -- 20,900,00020,900,000RTP-LRP -
16,636,631 20,900,000Total Funding - -4,046,000 -41,582,631 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
ENV - - - -457,000 -457,000EARMARK-T3 -
ENV - - - -115,000 -115,000LOCAL GEN FUND -
PSE - - - -1,210,000 -1,210,000ATP-REG -
PSE - - - -861,000 -861,000EARMARK-T3 -
PSE - - - -429,530 -429,530LOCAL GEN FUND -
PE - - - -92,400 -92,400LOCAL GEN FUND -
PE - - - -712,700 -712,700STP-T4 -
CON 4,046,000 - - -- -4,046,000ATP-REG -
CON - - - -2,356,000 -2,356,000EARMARK-T3 -
CON - - - -10,403,001 -10,403,001LOCAL GEN FUND -
CON - - - -- 20,900,00020,900,000RTP-LRP -
16,636,631 20,900,000Total Funding 4,046,000 -- -41,582,631 -
San Jose
Sec. RTP ID:
CTIPS ID:
Mode:
Coyote Creek Trail (Hwy 237-Story Rd)
ACTIVESCL050083
Trans. System:
RTP Cost:
2021-00 Version:
EXEMPT (40 CFR 93.126) - Bicycle and pedestrian facilitiesAQ Description:
San Jose
RTP Cycle:
Status:
Project Type:
20600003862
Project Name:
EXPANSIONPurpose:
17-07-0001 AA
Revision:
Hwy Rte:
PUBLICLANDTRAIL
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
16
$874,000,000
MULTI-USE TRAIL
CURRENT
Review:
Sponsoring Agency:
End of Project SCL050083
Bicycle and Pedestrian ProgramRTP Description:
San Jose: From Highway 237 to Story Road: Master plan entire system, design and construction of the trail.Proj Description:
2021 TIP UpdateRevision Reason:
BIKE/PED:99% | OTHER:1%
AQCTF Review: Reviewed
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
SCL050083 2021-01 ACCEPTED
17-07-0001
20600003862
San Jose San Jose
17
Coyote Creek Trail (Hwy 237-Story Rd)
AA
MULTI-USE TRAIL EXPANSIONPUBLICLANDTRAIL BIKE/PED:99% | OTHER:1%
PLANBAYAREA2040
$874,000,000
EXEMPT (40 CFR 93.126) - Bicycle and pedestrian facilities
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Bicycle and Pedestrian ProgramRTP Description:
San Jose: From Highway 237 to Story Road: Master plan entire system, design and construction of the trail.Proj Description:
Update the funding plan to reprogram $4M in CON ATP from FY21 to FY22Revision Reason:
AQCTF Review: Reviewed
27Page 8 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
ENV - - - -1,000,000 -1,000,000LOCAL GEN FUND -
PSE - - - -3,000,000 -3,000,000LOCAL GEN FUND -
PSE - - - -4,000,000 -4,000,000SALESTAX-MEASURE -
ROW - - - -7,000,000 -7,000,000SALESTAX-MEASURE -
CON - - - -- --RTP-LRP -
CON 13,000,000 - - -- -13,000,000SALESTAX-MEASURE -
CON 25,000,000 - - -- -25,000,000SB1 -
15,000,000 -Total Funding 38,000,000 -- -53,000,000 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
ENV - - - -1,000,000 -1,000,000LOCAL GEN FUND -
PSE - - - -3,000,000 -3,000,000LOCAL GEN FUND -
PSE - - - -4,000,000 -4,000,000SALESTAX-MEASURE -
ROW - - - -7,000,000 -7,000,000SALESTAX-MEASURE -
CON - - - -- 10,000,00010,000,000RTP-LRP -
CON 28,000,000 - - -- -28,000,000SALESTAX-MEASURE -
15,000,000 10,000,000Total Funding 28,000,000 -- -53,000,000 -
VTA
Sec. RTP ID:
CTIPS ID:
Mode:
US 101/De L Cruz Blvd - Trimble Road I/C Imp
ACTIVESCL190008
Trans. System:
RTP Cost:
2021-00 Version:
NON-EXEMPTAQ Description:
VTA
RTP Cycle:
Status:
Project Type:
20600006524
Project Name:
SYSTMGMTPurpose:
17-07-0031 PR
Revision:
Hwy Rte:
STATE HWY
TIP ID:
PLANBAYAREA2040
101
Primary RTP ID:
Implementing Agency:
3
$53,000,000
LOCAL I/C
CURRENT
Review:
Sponsoring Agency:
End of Project SCL190008
US 101 Southbound/Trimble Rd./De La Cruz Blvd./Central Expressway InterchangeImprovements
RTP Description:
Santa Clara: At the US101/De La Cruz Blvd/Trimble Rd IC: Modify interchange into a partial cloverleaf.Proj Description:
2021 TIP UpdateRevision Reason:
AUTO:80% | BIKE/PED:20%
AQCTF Review: Review Pending
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
SCL190008 2021-01 ACCEPTED
17-07-0031
20600006524
VTA VTA
4
US 101/De L Cruz Blvd - Trimble Road I/C Imp
PR
LOCAL I/C SYSTMGMTSTATE HWY AUTO:80% | BIKE/PED:20%
PLANBAYAREA2040
$53,000,000
NON-EXEMPT
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte: 101
US 101 Southbound/Trimble Rd./De La Cruz Blvd./Central Expressway InterchangeImprovements
RTP Description:
Santa Clara: At the US101/De La Cruz Blvd/Trimble Rd IC: Modify interchange into a partial cloverleaf.Proj Description:
Update the funding plan to change the source and program year for $10M in FY25 RTP-LRP to FY21 SB1-LPP funds change the source for$15M in FY21 funds from Sales Tax to SB1-LPP
Revision Reason:
AQCTF Review: Review Pending
27Page 9 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
ENV 4,243,000 500,000 - -2,435,000 -7,178,000LOCAL GEN FUND -
ENV - - - -- 1,757,0001,757,000RTP-LRP -
PSE 1,690,000 3,856,000 1,475,000 -- -7,021,000LOCAL GEN FUND -
PSE - - - -- 7,879,0007,879,000RTP-LRP -
CON - - - -16,112,000 -16,112,0005309-T3 -
CON - - - -19,150,000 -19,150,0005309-T4-FG -
CON - - - -5,000,000 -5,000,0005337-T4 -
CON 28,931,000 - - -18,140,000 -47,071,0005337-T5 -
CON - - - -12,007,337 -12,007,337BT-664 -
CON - 1,782,000 4,328,000 -5,903,000 -12,013,000LOCAL GEN FUND -
CON - - - -6,000,000 -6,000,000PROP-1B -
CON 1,092,315 2,493,385 - -3,156,105 -6,741,805PROPERTY TAX -
CON 13,752,000 - - -- -13,752,000RIP-T5 1,577,354
CON - - - -- 11,174,25011,174,250RTP-LRP -
CON 9,616,050 2,539,300 - -17,502,808 -29,658,158SALESTAX-MEASURE -
CON - - - -712,000 -712,000SALESTAX-TRANSIT -
CON 250,000 715,117 - -5,484,814 -6,449,931STA-REV -
111,603,064 20,810,250Total Funding 59,574,365 5,803,00011,885,802 -209,676,481 1,577,354
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
SF-050024 2021-01 ACCEPTED
17-10-0026
20600003616
SFMTA SFMTA
23
SFMTA:Train Control & Trolley Signal Rehab/Replace
AA
OTHER MAINT/REHABTRANSIT RAIL:100%
PLANBAYAREA2040
$30,564,000,000
EXEMPT (40 CFR 93.126) - Rehabilitation or reconstruction of track structures, track, and trackbed in existing rights-of-way
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Regional Transit Capital - Existing ConditionsRTP Description:
SFMTA: Systemwide: Rehabilitate or replace elements of the ATCS Wayside/Central Train Control & Rail/Bus Signal Systems.Proj Description:
Update the funding plan to change the source and program year for $29M from FY25 RTP-LRP to FY21 5337 and for $7.2M from FY25 RTP-LRP to FY21 Sales Tax
Revision Reason:
AQCTF Review: Reviewed
27Page 10 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
ENV 4,243,000 500,000 - -2,435,000 -7,178,000LOCAL GEN FUND -
ENV - - - -- 1,757,0001,757,000RTP-LRP -
PSE 1,690,000 3,856,000 1,475,000 -- -7,021,000LOCAL GEN FUND -
PSE - - - -- 7,879,0007,879,000RTP-LRP -
CON - - - -16,112,000 -16,112,0005309-T3 -
CON - - - -19,150,000 -19,150,0005309-T4-FG -
CON - - - -5,000,000 -5,000,0005337-T4 -
CON - - - -18,140,000 -18,140,0005337-T5 -
CON - - - -12,007,337 -12,007,337BT-664 -
CON - 1,782,000 4,328,000 -5,903,000 -12,013,000LOCAL GEN FUND -
CON - - - -6,000,000 -6,000,000PROP-1B -
CON 1,092,315 2,493,385 - -3,156,105 -6,741,805PROPERTY TAX -
CON 13,752,000 - - -- -13,752,000RIP-T5 1,577,354
CON - - - -- 47,338,00047,338,000RTP-LRP -
CON 2,383,300 2,539,300 - -17,502,808 -22,425,408SALESTAX-MEASURE -
CON - - - -712,000 -712,000SALESTAX-TRANSIT -
CON 250,000 715,117 - -5,484,814 -6,449,931STA-REV -
111,603,064 56,974,000Total Funding 23,410,615 5,803,00011,885,802 -209,676,481 1,577,354
SFMTA
Sec. RTP ID:
CTIPS ID:
Mode:
SFMTA:Train Control & Trolley Signal Rehab/Replace
ACTIVESF-050024
Trans. System:
RTP Cost:
2021-00 Version:
EXEMPT (40 CFR 93.126) - Rehabilitation or reconstruction of track structures, track, and trackbed in existing rights-of-wayAQ Description:
SFMTA
RTP Cycle:
Status:
Project Type:
20600003616
Project Name:
MAINT/REHABPurpose:
17-10-0026 AA
Revision:
Hwy Rte:
TRANSIT
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
22
$30,564,000,000
OTHER
CURRENT
Review:
Sponsoring Agency:
End of Project SF-050024
Regional Transit Capital - Existing ConditionsRTP Description:
SFMTA: Systemwide: Rehabilitate or replace elements of the ATCS Wayside/Central Train Control & Rail/Bus Signal Systems.Proj Description:
2021 TIP UpdateRevision Reason:
RAIL:100%
AQCTF Review: Reviewed
27Page 11 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
CON 13,220,000 - - -- -13,220,0005337-T5 -
CON 14,727,570 - - -- -14,727,570BT-664 -
CON 5,992,652 - - -59,118,014 -65,110,666BT-RM1 -
CON - - - -10,227,539 -10,227,539CMAQ-T4 -
CON 5,180,056 - - -208,098,540 -213,278,596LOCAL GEN FUND -
CON - 20,459,409 - -- -20,459,409PRIVATE -
CON - - - -- 484,911,380484,911,380RTP-LRP -
CON - - - -191,885,171 -191,885,171SALESTAX-MEASURE -
CON - - - -26,867,000 -26,867,000SB1 -
CON - - - -86,273,000 -86,273,000TIRCP -
582,469,264 484,911,380Total Funding 39,120,278 -20,459,409 -1,126,960,331 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
CON 13,220,000 - - -- -13,220,0005337-T5 -
CON - - - -59,118,014 -59,118,014BT-RM1 -
CON - - - -10,227,539 -10,227,539CMAQ-T4 -
CON - - - -208,098,540 -208,098,540LOCAL GEN FUND -
CON - 20,459,409 - -- -20,459,409PRIVATE -
CON - - - -- 510,811,658510,811,658RTP-LRP -
CON - - - -191,885,171 -191,885,171SALESTAX-MEASURE -
CON - - - -26,867,000 -26,867,000SB1 -
CON - - - -86,273,000 -86,273,000TIRCP -
582,469,264 510,811,658Total Funding 13,220,000 -20,459,409 -1,126,960,331 -
SFMTA
Sec. RTP ID:
CTIPS ID:
Mode:
Light Rail Vehicle Procurement
ACTIVESF-090012
Trans. System:
RTP Cost:
2021-00 Version:
NON-EXEMPTAQ Description:
SFMTA
RTP Cycle:
Status:
Project Type:
20600004361
Project Name:
EXPANSIONPurpose:
17-10-0026 AA
Revision:
Hwy Rte:
TRANSIT
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
13
$30,564,000,000
ROLLING STOCK
CURRENT
Review:
Sponsoring Agency:
End of Project SF-090012
Regional Transit Capital - Existing ConditionsRTP Description:
SFMTA: Fleet-wide: Procure 219 light rail vehicles with an option for an additional 45 vehicles to replace existing fleet and expand serviceProj Description:
2021 TIP UpdateRevision Reason:
RAIL:100%
AQCTF Review: Reviewed
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
SF-090012 2021-01 ACCEPTED
17-10-0026
20600004361
SFMTA SFMTA
14
Light Rail Vehicle Procurement
AA
ROLLING STOCK EXPANSIONTRANSIT RAIL:100%
PLANBAYAREA2040
$30,564,000,000
NON-EXEMPT
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Regional Transit Capital - Existing ConditionsRTP Description:
SFMTA: Fleet-wide: Procure 219 light rail vehicles with an option for an additional 45 vehicles to replace existing fleet and expand serviceProj Description:
Update the funding plan to change the source for $26M in RTP-LRP to $14.7M in AB664 Bridge Toll funds, $6M in BATA Project Savings,and $5.2M in Local funds and reprogram from FY25 to FY21
Revision Reason:
AQCTF Review: Reviewed
27Page 12 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
ENV - - - -1,000,000 -1,000,000LOCAL GEN FUND -
PSE - - - -6,429,000 -6,429,000LOCAL GEN FUND -
PE - 2,071,000 - -- -2,071,000LOCAL GEN FUND -
PE - - - -13,864,000 -13,864,000SALESTAX-MEASURE -
ROW - 500,000 - -- -500,000PRIVATE -
CON - - - -3,366,000 -3,366,000AC-LOCAL -
CON 70,627 - - -- -70,627EARMARK-T5 -
CON - - - -15,000,000 -15,000,000FEDERAL-OTHER -
CON - - - -2,686,101 -2,686,101LOCAL GEN FUND -
CON - - - -1,500,000 -1,500,000PRIVATE -
CON - - - -- 365,147,272365,147,272RTP-LRP -
CON 3,366,000 - - -- -3,366,000STP-T5 -
43,845,101 365,147,272Total Funding 3,436,627 -2,571,000 -415,000,000 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
ENV - - - -1,000,000 -1,000,000LOCAL GEN FUND -
PSE - - - -6,429,000 -6,429,000LOCAL GEN FUND -
PE - 2,071,000 - -- -2,071,000LOCAL GEN FUND -
PE - - - -13,864,000 -13,864,000SALESTAX-MEASURE -
ROW - 500,000 - -- -500,000PRIVATE -
CON - - - -3,366,000 -3,366,000AC-LOCAL -
CON - - - -15,000,000 -15,000,000FEDERAL-OTHER -
CON - - - -2,686,101 -2,686,101LOCAL GEN FUND -
CON - - - -1,500,000 -1,500,000PRIVATE -
CON - - - -- 365,217,899365,217,899RTP-LRP -
CON 3,366,000 - - -- -3,366,000STP-T5 -
43,845,101 365,217,899Total Funding 3,366,000 -2,571,000 -415,000,000 -
SF DPW
Sec. RTP ID:
CTIPS ID:
Mode:
SF- Better Market Street Transportation Elements
ACTIVESF-130001
Trans. System:
RTP Cost:
2021-00 Version:
NON-EXEMPTAQ Description:
SF DPW
RTP Cycle:
Status:
Project Type:
20600005552
Project Name:
SYSTMGMTPurpose:
17-05-0016 AA
Revision:
Hwy Rte:
LOCAL ROAD
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
9
$415,000,000
OTHER
CURRENT
Review:
Sponsoring Agency:
End of Project SF-130001
Better Market Street - Transportation ElementsRTP Description:
In San Francisco: Market St from Steuart St to Octavia Blvd: improve roadway, including resurfacing, sidewalk and transit boardingimprovements, transit connections, traffic signals, transportation circulation changes and utility relocation and upgrade.
Proj Description:
2021 TIP UpdateRevision Reason:
BUS:65% | BIKE/PED:35%
AQCTF Review: Review Pending
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
SF-130001 2021-01 ACCEPTED
17-05-0016
20600005552
SF DPW SF DPW
10
SF- Better Market Street Transportation Elements
AA
OTHER SYSTMGMTLOCAL ROAD BUS:65% | BIKE/PED:35%
PLANBAYAREA2040
$415,000,000
NON-EXEMPT
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Better Market Street - Transportation ElementsRTP Description:
In San Francisco: Market St from Steuart St to Octavia Blvd: improve roadway, including resurfacing, sidewalk and transit boardingimprovements, transit connections, traffic signals, transportation circulation changes and utility relocation and upgrade.
Proj Description:
Update the funding plan to change the source and program year for $71K in CON from FY25 RTP-LRP to FY21 Repurposed Earmark fundsRevision Reason:
AQCTF Review: Review Pending
27Page 13 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
CON 7,344,308 - - -15,000,000 -22,344,3085337-T5 -
CON - - - -- --LOCAL GEN FUND -
CON 2,630,936 1,958,286 - -- -4,589,222PRIVATE -
CON 1,836,077 - - -9,059,501 -10,895,578SALESTAX-MEASURE -
24,059,501 -Total Funding 11,811,321 -1,958,286 -37,829,108 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
CON - - - -15,000,000 -15,000,0005337-T5 -
CON - - - -- --LOCAL GEN FUND -
CON 2,630,936 1,958,286 - -- -4,589,222PRIVATE -
CON - - - -9,059,501 -9,059,501SALESTAX-MEASURE -
24,059,501 -Total Funding 2,630,936 -1,958,286 -28,648,723 -
SFMTA
Sec. RTP ID:
CTIPS ID:
Mode:
SFMTA: Rehab Historic Streetcars
ACTIVESF-170021
Trans. System:
RTP Cost:
2021-00 Version:
EXEMPT (40 CFR 93.126) - Rehabilitation of transit vehiclesAQ Description:
SFMTA
RTP Cycle:
Status:
Project Type:
20600006444
Project Name:
MAINT/REHABPurpose:
17-10-0026 PR
Revision:
Hwy Rte:
TRANSIT
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
3
$30,564,000,000
LT RAIL TRANSIT
CURRENT
Review:
Sponsoring Agency:
End of Project SF-170021
Regional Transit Capital - Existing ConditionsRTP Description:
SFMTA: Fleet of historic streetcars: Rehabilitate vehiclesProj Description:
2021 TIP UpdateRevision Reason:
RAIL:100%
AQCTF Review: Review Pending
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
SF-170021 2021-01 ACCEPTED
17-10-0026
20600006444
SFMTA SFMTA
4
SFMTA: Rehab Historic Streetcars
PR
LT RAIL TRANSIT MAINT/REHABTRANSIT RAIL:100%
PLANBAYAREA2040
$30,564,000,000
EXEMPT (40 CFR 93.126) - Rehabilitation of transit vehicles
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Regional Transit Capital - Existing ConditionsRTP Description:
SFMTA: Fleet of historic streetcars: Rehabilitate vehiclesProj Description:
Update the funding plan to add $7M in 5337 and $1.8M in Sales Tax fundsRevision Reason:
AQCTF Review: Review Pending
27Page 14 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -1,500,000 -1,500,0005307-T3 -
CON - - - -7,674,700 -7,674,7005307-T3 -
CON - - - -4,026,555 -4,026,5555307-T4 -
CON - - - -39,000,000 -39,000,0005309-T3 -
CON - - - -55,010,000 -55,010,0005309-T4-FG -
CON - - - -37,401,144 -37,401,1445337-T4 -
CON 7,026,000 - - -36,343,309 -43,369,3095337-T5 -
CON - - - -8,618,827 -8,618,827BT-664 -
CON - - - -1,550,910 -1,550,910BT-RM1 -
CON 4,518,731 9,155,191 - -39,959,751 -53,633,673LOCAL GEN FUND -
CON - - - -4,000,000 -4,000,000PROP-1B -
CON 3,284,140 1,527,640 - -26,087,672 -30,899,452SALESTAX-MEASURE -
CON - - - -5,511,925 -5,511,925SALESTAX-TRANSIT -
CON 4,500,000 706,126 - -1,836,317 -7,042,443STA-REV -
268,521,110 -Total Funding 19,328,871 -11,388,957 -299,238,938 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -1,500,000 -1,500,0005307-T3 -
CON - - - -7,674,700 -7,674,7005307-T3 -
CON - - - -4,026,555 -4,026,5555307-T4 -
CON - - - -39,000,000 -39,000,0005309-T3 -
CON - - - -55,010,000 -55,010,0005309-T4-FG -
CON - - - -37,401,144 -37,401,1445337-T4 -
CON - - - -36,343,309 -36,343,3095337-T5 -
CON - - - -8,618,827 -8,618,827BT-664 -
CON - - - -1,550,910 -1,550,910BT-RM1 -
CON 4,518,731 9,155,191 - -39,959,751 -53,633,673LOCAL GEN FUND -
CON - - - -4,000,000 -4,000,000PROP-1B -
CON 1,527,640 1,527,640 - -26,087,672 -29,142,952SALESTAX-MEASURE -
CON - - - -5,511,925 -5,511,925SALESTAX-TRANSIT -
CON 4,500,000 706,126 - -1,836,317 -7,042,443STA-REV -
268,521,110 -Total Funding 10,546,371 -11,388,957 -290,456,438 -
SFMTA
Sec. RTP ID:
CTIPS ID:
Mode:
SF Muni Rail Replacement Program
ACTIVESF-95037B
Trans. System:
RTP Cost:
2021-00 Version:
EXEMPT (40 CFR 93.126) - Rehabilitation or reconstruction of track structures, track, and trackbed in existing rights-of-wayAQ Description:
SFMTA
RTP Cycle:
Status:
Project Type:
20600003911
Project Name:
MAINT/REHABPurpose:
17-10-0026 AA
Revision:
Hwy Rte:
TRANSIT
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
24
$30,564,000,000
TRACK
CURRENT
Review:
Sponsoring Agency:
End of Project SF-95037B
Regional Transit Capital - Existing ConditionsRTP Description:
SFMTA: Systemwide: Phased design and replacement of trackway, rail replacement, grinding, ultrasonic testing, track fastener, specialtrackwork, and related systems serving light rail and cable car lines.
Proj Description:
2021 TIP UpdateRevision Reason:
RAIL:100%
AQCTF Review: Reviewed
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
SF-95037B 2021-01 ACCEPTED
17-10-0026
20600003911
SFMTA SFMTA
25
SF Muni Rail Replacement Program
AA
TRACK MAINT/REHABTRANSIT RAIL:100%
PLANBAYAREA2040
$30,564,000,000
EXEMPT (40 CFR 93.126) - Rehabilitation or reconstruction of track structures, track, and trackbed in existing rights-of-way
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Regional Transit Capital - Existing ConditionsRTP Description:
SFMTA: Systemwide: Phased design and replacement of trackway, rail replacement, grinding, ultrasonic testing, track fastener, specialtrackwork, and related systems serving light rail and cable car lines.
Proj Description:
Update the funding plan to add $7M in FY21 5337 and $1.8M in FY21 Sales Tax fundsRevision Reason:
AQCTF Review: Reviewed
27Page 15 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -1,000,000 -1,000,0005309-T3 -
CON - - - -13,146,055 -13,146,0555307-T3 -
CON - - - -33,016,901 -33,016,9015309-T3 -
CON - - - -3,076,000 -3,076,0005309-T4-FG -
CON - - - -1,000,000 -1,000,0005337-T4 -
CON 1,617,000 - - -7,250,000 -8,867,0005337-T5 -
CON - - - -1,745,000 -1,745,000BT-664 -
CON - - - 1,378,11412,923,908 -14,302,022LOCAL GEN FUND -
CON - 3,899,714 - -1,270,000 -5,169,714PRIVATE -
CON - - - -- 7,347,1727,347,172RTP-LRP -
CON 404,250 3,500,000 - -1,630,994 -5,535,244SALESTAX-MEASURE -
CON - - - -5,640,000 -5,640,000SALESTAX-TRANSIT -
CON - - - -2,178,869 -2,178,869STA-REV -
CON - - - -638,000 -638,000STP-T2 -
84,515,727 7,347,172Total Funding 2,021,250 -7,399,714 1,378,114102,661,977 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -1,000,000 -1,000,0005309-T3 -
CON - - - -13,146,055 -13,146,0555307-T3 -
CON - - - -33,016,901 -33,016,9015309-T3 -
CON - - - -3,076,000 -3,076,0005309-T4-FG -
CON - - - -1,000,000 -1,000,0005337-T4 -
CON - - - -7,250,000 -7,250,0005337-T5 -
CON - - - -1,745,000 -1,745,000BT-664 -
CON - - - 1,378,11412,923,908 -14,302,022LOCAL GEN FUND -
CON - 3,899,714 - -1,270,000 -5,169,714PRIVATE -
CON - - - -- 7,347,1727,347,172RTP-LRP -
CON - 3,500,000 - -1,630,994 -5,130,994SALESTAX-MEASURE -
CON - - - -5,640,000 -5,640,000SALESTAX-TRANSIT -
CON - - - -2,178,869 -2,178,869STA-REV -
CON - - - -638,000 -638,000STP-T2 -
84,515,727 7,347,172Total Funding - -7,399,714 1,378,114100,640,727 -
SFMTA
Sec. RTP ID:
CTIPS ID:
Mode:
Cable Car Traction Power & Guideway Rehab
ACTIVESF-99T002
Trans. System:
RTP Cost:
2021-00 Version:
EXEMPT (40 CFR 93.126) - Rehabilitation or reconstruction of track structures, track, and trackbed in existing rights-of-wayAQ Description:
SFMTA
RTP Cycle:
Status:
Project Type:
20600001467
Project Name:
MAINT/REHABPurpose:
17-10-0026 AA
Revision:
Hwy Rte:
TRANSIT
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
26
$30,564,000,000
OTHER
CURRENT
Review:
Sponsoring Agency:
End of Project SF-99T002
Regional Transit Capital - Existing ConditionsRTP Description:
SFMTA: Cable Car System: Traction power and guideway rehab-repair various guideway, track curves, frogs, sheaves, replace Barn 12KV,switchgear, DC Motor, mechanical and infrastructure to improve the cable car system.
Proj Description:
2021 TIP Update - Update the funding planRevision Reason:
RAIL:100%
AQCTF Review: Reviewed
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
SF-99T002 2021-01 ACCEPTED
17-10-0026
20600001467
SFMTA SFMTA
27
Cable Car Traction Power & Guideway Rehab
AA
OTHER MAINT/REHABTRANSIT RAIL:100%
PLANBAYAREA2040
$30,564,000,000
EXEMPT (40 CFR 93.126) - Rehabilitation or reconstruction of track structures, track, and trackbed in existing rights-of-way
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Regional Transit Capital - Existing ConditionsRTP Description:
SFMTA: Cable Car System: Traction power and guideway rehab-repair various guideway, track curves, frogs, sheaves, replace Barn 12KV,switchgear, DC Motor, mechanical and infrastructure to improve the cable car system.
Proj Description:
Update the funding plan to add $1.6M in FY21 5337 and $404K in FY21 Sales Tax fundsRevision Reason:
AQCTF Review: Reviewed
27Page 16 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -- 4,966,7274,966,727RTP-LRP -
PE - - - -94,000 -94,000CMAQ-T4 -
PE - - - -1,290,419 -1,290,419EARMARK-T3 -
PE 427,693 - - -- -427,693EARMARK-T5 -
PE 56,000 - - -446,187 -502,187LOCAL GEN FUND -
ROW - - - -- 26,000,00026,000,000RTP-LRP -
CON - - - -397,000 -397,000LOCAL GEN FUND -
CON - 5,000,000 - -- -5,000,000RIP-T5 -
CON - - - -- 57,797,90257,797,902RTP-LRP -
2,227,606 88,764,629Total Funding 483,693 -5,000,000 -96,475,928 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -- 4,966,7274,966,727RTP-LRP -
PE - - - -94,000 -94,000CMAQ-T4 -
PE - - - -1,290,419 -1,290,419EARMARK-T3 -
PE - - - -- --EARMARK-T5 -
PE - - - -446,187 -446,187LOCAL GEN FUND -
ROW - - - -- 26,000,00026,000,000RTP-LRP -
CON 428,000 - - -- -428,000EARMARK-T5 -
CON 56,000 - - -397,000 -453,000LOCAL GEN FUND -
CON - 5,000,000 - -- -5,000,000RIP-T5 -
CON - - - -- 57,797,90257,797,902RTP-LRP -
2,227,606 88,764,629Total Funding 484,000 -5,000,000 -96,476,235 -
Solano County
Sec. RTP ID:
CTIPS ID:
Mode:
Redwood-Fairgrounds Dr Interchange Imps
ACTIVESOL090015
Trans. System:
RTP Cost:
2021-00 Version:
NON-EXEMPTAQ Description:
Solano County
RTP Cycle:
Status:
Project Type:
20600004556
Project Name:
EXPANSIONPurpose:
17-08-0010 AA
Revision:
Hwy Rte:
STATE HWY
TIP ID:
PLANBAYAREA2040
80
Primary RTP ID:
Implementing Agency:
23
$100,000,000
FREEWAY I/C
CURRENT
Review:
Sponsoring Agency:
End of Project SOL090015
Improve interchanges and widen roadways serving Solano County Fairgrounds, including RedwoodParkway
RTP Description:
Solano County: I-80 Redwood St. I/C and SR-37/Fairgrounds Dr. I/C: Implement I/C and safety improvements; Fairgrounds Dr. from RedwoodSt. to SR-37: Remove left turn lane and widen to add one lane in each direction and add bike lanes; transit improvements
Proj Description:
2021 TIP UpdateRevision Reason:
AUTO:70% | BIKE/PED:15% |BUS:15%
AQCTF Review: Review Pending
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
SOL090015 2021-01 ACCEPTED
17-08-0010
20600004556
Solano County Solano County
24
Redwood-Fairgrounds Dr Interchange Imps
AA
FREEWAY I/C EXPANSIONSTATE HWY AUTO:70% | BIKE/PED:15% | BUS:15%
PLANBAYAREA2040
$100,000,000
NON-EXEMPT
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte: 80
Improve interchanges and widen roadways serving Solano County Fairgrounds, including RedwoodParkway
RTP Description:
Solano County: I-80 Redwood St. I/C and SR-37/Fairgrounds Dr. I/C: Implement I/C and safety improvements; Fairgrounds Dr. from RedwoodSt. to SR-37: Remove left turn lane and widen to add one lane in each direction and add bike lanes; transit improvements
Proj Description:
Update the funding plan to reprogram $428K in FY21 Repurposed Earmark funds and $56K in FY21 Local funds from CON to PERevision Reason:
AQCTF Review: Review Pending
27Page 17 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
ENV - - - -10,900,000 -10,900,000BT-RM2 -
PSE - - - -3,800,000 -3,800,000BT-664 -
PSE - - - -14,600,000 -14,600,000BT-RM2 -
PSE 5,100,000 - - -- -5,100,000LOCAL GEN FUND -
ROW - - - -2,655,000 -2,655,000BT-664 -
ROW-SUP 545,000 - - -- -545,000BT-664 -
CON - - - 63,464,510- -63,464,510CMAQ-T5 -
CON - 31,276,000 - -- -31,276,000LOCAL GEN FUND -
CON - 115,759,490 - -- -115,759,490SB1 -
CON-CE - 1,859,490 - -- -1,859,490RIP-CRRSAA -
CON-CE - 17,300,000 - -- -17,300,000RIP-T5 -
CON-CE - 7,640,510 - -- -7,640,510SB1 -
31,955,000 -Total Funding 5,645,000 -173,835,490 63,464,510274,900,000 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
ENV - - - -10,900,000 -10,900,000BT-RM2 -
PSE - - - -3,800,000 -3,800,000BT-664 -
PSE - - - -14,600,000 -14,600,000BT-RM2 -
PSE 5,100,000 - - -- -5,100,000LOCAL GEN FUND -
ROW - - - -2,885,000 -2,885,000BT-664 -
ROW-SUP 315,000 - - -- -315,000BT-664 -
CON - 96,600,000 - -- -96,600,000LOCAL GEN FUND -
CON - 17,300,000 - -- -17,300,000RIP-T5 -
CON - 101,600,000 - -- -101,600,000SB1 -
CON-CE - 21,800,000 - -- -21,800,000SB1 -
32,185,000 -Total Funding 5,415,000 -237,300,000 -274,900,000 -
MTC
Sec. RTP ID:
CTIPS ID:
Mode:
Solano I-80 Managed Lanes
ACTIVESOL110001
Trans. System:
RTP Cost:
2021-00 Version:
NON-EXEMPTAQ Description:
STA
RTP Cycle:
Status:
Project Type:
20600004647
Project Name:
EXPANSIONPurpose:
17-10-0044 AA
Revision:
Hwy Rte:
STATE HWY
TIP ID:
PLANBAYAREA2040
80
Primary RTP ID:
Implementing Agency:
11
$44,000,000
HOV
CURRENT
Review:
Sponsoring Agency:
End of Project SOL110001
I-80 Express Lanes in both directions: Airbase Parkway to Red Top RoadRTP Description:
Solano County: I-80 from Red Top Rd to I-505: Convert existing HOV to Managed Lane; I-80 from Air Base Parkway to I-505: Construct newManaged Lanes. Project also references RTP IDs 17-10-0059 and 17-10-0056
Proj Description:
2021 TIP UpdateRevision Reason:
AUTO:100%
AQCTF Review: Review Pending
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
SOL110001 2021-01 ACCEPTED
17-10-0044
20600004647
MTC Caltrans
12
Solano I-80 Managed Lanes
AA
HOV EXPANSIONSTATE HWY AUTO:100%
PLANBAYAREA2040
$44,000,000
NON-EXEMPT
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte: 80
I-80 Express Lanes in both directions: Airbase Parkway to Red Top RoadRTP Description:
Solano County: I-80 from Red Top Rd to I-505: Convert existing HOV to Managed Lane; I-80 from Air Base Parkway to I-505: Construct newManaged Lanes. Project also references RTP IDs 17-10-0059 and 17-10-0056
Proj Description:
Update the funding plan to reprogram $65.3M in other local funds as $63.5M in CMAQ funds in FY24, and $1.8M in STIP funds in FY22; andreprogram $14.2M in TCEP CON Support funds to CON in FY22.
Revision Reason:
AQCTF Review: Review Pending
27Page 18 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -564,000 -564,000LOCAL GEN FUND -
PE - - - -185,000 -185,000EARMARK-T2 -
PE - - - -46,250 -46,250LOCAL GEN FUND -
PE - - - -3,500,000 -3,500,000PRIVATE -
PE - - - -200,000 -200,000RIP-T2 -
ROW - - - -893,000 -893,000LOCAL GEN FUND -
CON - 1,407,000 - -- -1,407,000CMAQ-T5 -
CON - 81,047 - -- -81,047EARMARK-T5 -
CON - - - -890,592 -890,592LOCAL GEN FUND -
CON - 4,871,000 - -- -4,871,000PRIVATE -
CON - 3,296,000 - -- -3,296,000RIP-T4 -
CON - 6,000,000 - -- -6,000,000RIP-T5 -
6,278,842 -Total Funding - -15,655,047 -21,933,889 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -564,000 -564,000LOCAL GEN FUND -
PE - - - -185,000 -185,000EARMARK-T2 -
PE - - - -46,250 -46,250LOCAL GEN FUND -
PE - - - -3,500,000 -3,500,000PRIVATE -
PE - - - -200,000 -200,000RIP-T2 -
ROW - - - -893,000 -893,000LOCAL GEN FUND -
CON - 1,407,000 - -- -1,407,000CMAQ-T5 -
CON - - - -890,592 -890,592LOCAL GEN FUND -
CON - 4,871,000 - -- -4,871,000PRIVATE -
CON - 3,296,000 - -- -3,296,000RIP-T4 -
CON - 6,000,000 - -- -6,000,000RIP-T5 -
6,278,842 -Total Funding - -15,574,000 -21,852,842 -
STA
Sec. RTP ID:
CTIPS ID:
Mode:
Jepson: Leisure Town Road Phase 1B and 1C
ACTIVESOL110006
Trans. System:
RTP Cost:
2021-00 Version:
NON-EXEMPTAQ Description:
Vacaville
RTP Cycle:
Status:
Project Type:
20600004764
Project Name:
EXPANSIONPurpose:
17-08-0012 AA
Revision:
Hwy Rte:
LOCAL ROAD
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
10
$85,000,000
MAJOR ARTERIAL
CURRENT
Review:
Sponsoring Agency:
End of Project SOL110006
Construct 4-lane Jepson Parkway from Route 12 to Leisure Town Road at I-80RTP Description:
Vacaville: (Phase 1B) Leisure Town Rd from Elmira Rd to Sequoia and (Phase 1C) from Sequoia Dr to Horse Creek: Widen to 4 lanes withmultiuse sidewalk and safety improvements
Proj Description:
2021 TIP UpdateRevision Reason:
AUTO:80% | BIKE/PED:20%
AQCTF Review: Review Pending
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
SOL110006 2021-01 ACCEPTED
17-08-0012
20600004764
STA Vacaville
11
Jepson: Leisure Town Road Phase 1B and 1C
AA
MAJOR ARTERIAL EXPANSIONLOCAL ROAD AUTO:80% | BIKE/PED:20%
PLANBAYAREA2040
$85,000,000
NON-EXEMPT
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Construct 4-lane Jepson Parkway from Route 12 to Leisure Town Road at I-80RTP Description:
Vacaville: (Phase 1B) Leisure Town Rd from Elmira Rd to Sequoia and (Phase 1C) from Sequoia Dr to Horse Creek: Widen to 4 lanes withmultiuse sidewalk and safety improvements
Proj Description:
Update the funding plan to add $81K in FY22 CON Repurposed Earmark fundsRevision Reason:
AQCTF Review: Review Pending
27Page 19 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -1,000,000 -1,000,000TIRCP -
CON 2,746,527 - - -1,800,000 -4,546,5275339-T5 -
CON 250,000 - - -1,731,000 -1,981,000LCTOP -
CON 109,737 - - -200,000 -309,737LOCAL GEN FUND -
CON 736,500 - - -- -736,500TDA4 -
4,731,000 -Total Funding 3,842,764 -- -8,573,764 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE - - - -1,000,000 -1,000,000TIRCP -
CON 2,307,580 - - -1,800,000 -4,107,5805339-T5 -
CON 250,000 - - -1,731,000 -1,981,000LCTOP -
CON - - - -200,000 -200,000LOCAL GEN FUND -
CON 736,500 - - -- -736,500TDA4 -
4,731,000 -Total Funding 3,294,080 -- -8,025,080 -
SolTrans
Sec. RTP ID:
CTIPS ID:
Mode:
SolTrans Electric Bus Charging Infrastructure
ACTIVESOL190017
Trans. System:
RTP Cost:
2021-00 Version:
EXEMPT (40 CFR 93.126) - Construction or renovation of power, signal, and communications systemsAQ Description:
SolTrans
RTP Cycle:
Status:
Project Type:
20600006638
Project Name:
MAINT/REHABPurpose:
17-10-0026 PR
Revision:
Hwy Rte:
TRANSIT
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
3
$30,564,000,000
LOCAL BUS
CURRENT
Review:
Sponsoring Agency:
End of Project SOL190017
Regional Transit Capital - Existing ConditionsRTP Description:
SolTrans: Systemwide: Implement core infrastructure improvements to support the charging of a 100% Zero Emissions Bus fleet.Proj Description:
2021 TIP UpdateRevision Reason:
BUS:100%
AQCTF Review: Review Pending
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
SOL190017 2021-01 ACCEPTED
17-10-0026
20600006638
SolTrans SolTrans
4
SolTrans Electric Bus Charging Infrastructure
PR
LOCAL BUS MAINT/REHABTRANSIT BUS:100%
PLANBAYAREA2040
$30,564,000,000
EXEMPT (40 CFR 93.126) - Construction or renovation of power, signal, and communications systems
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Regional Transit Capital - Existing ConditionsRTP Description:
SolTrans: Systemwide: Implement core infrastructure improvements to support the charging of a 100% Zero Emissions Bus fleet.Proj Description:
Update the funding plan to add $439K in FY21 5339 funds and $110K in FY21 Local fundsRevision Reason:
AQCTF Review: Review Pending
27Page 20 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE 5,268,000 - - -- -5,268,000RIP-T5 -
PSE 24,002,000 - - -- -24,002,000SB1 -
ROW - 42,750,000 - -- -42,750,000LOCAL GEN FUND -
ROW-SUP - 750,000 - -- -750,000LOCAL GEN FUND -
CON - - - -- 97,230,00097,230,000RTP-LRP -
- 97,230,000Total Funding 29,270,000 -43,500,000 -170,000,000 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
PSE 5,268,000 - - -- -5,268,000LOCAL GEN FUND -
PSE 24,002,000 - - -- -24,002,000SB1 -
ROW - 42,750,000 - -- -42,750,000LOCAL GEN FUND -
ROW-SUP - 750,000 - -- -750,000LOCAL GEN FUND -
CON - - - -- 97,230,00097,230,000RTP-LRP -
- 97,230,000Total Funding 29,270,000 -43,500,000 -170,000,000 -
Caltrans
Sec. RTP ID:
CTIPS ID:
Mode:
Solano WB I-80 Cordelia Truck Scales
PROPOSEDSOL190025
Trans. System:
RTP Cost:
2021-03 Version:
EXEMPT (40 CFR 93.127) - Truck size and weight inspection stationsAQ Description:
Caltrans
RTP Cycle:
Status:
Project Type:
20600006726
Project Name:
MAINT/REHABPurpose:
17-08-0017 PR
Revision:
Hwy Rte:
STATE HWY
TIP ID:
PLANBAYAREA2040
80
Primary RTP ID:
Implementing Agency:
2
$170,000,000
OTHER
CURRENT
Review:
Sponsoring Agency:
End of Project SOL190025
I-80 WB Truck ScalesRTP Description:
Solano County: WB I-80: Replace and relocate the existing Cordelia Truck Scales, expand capacity and create braided off-ramp connectionto WB I-80
Proj Description:
Carry this project forward into the 2021 TIPRevision Reason:
FREIGHT:100%
AQCTF Review: Review Pending
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
SOL190025 2021-01 ACCEPTED
17-08-0017
20600006726
Caltrans Caltrans
3
Solano WB I-80 Cordelia Truck Scales
PR
OTHER MAINT/REHABSTATE HWY FREIGHT:100%
PLANBAYAREA2040
$170,000,000
EXEMPT (40 CFR 93.127) - Truck size and weight inspection stations
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte: 80
I-80 WB Truck ScalesRTP Description:
Solano County: WB I-80: Replace and relocate the existing Cordelia Truck Scales, expand capacity and create braided off-ramp connectionto WB I-80
Proj Description:
Update the funding plan to reprogram $5.3M in other local funds as STIP funds for PS&E in FY21Revision Reason:
AQCTF Review: Review Pending
27Page 21 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
ENV - - - -1,150,000 -1,150,000LOCAL GEN FUND -
ENV - - - -1,150,000 -1,150,000SALESTAX-MEASURE -
PSE - - - -1,800,000 -1,800,000SALESTAX-MEASURE -
ROW - - - -800,000 -800,000LOCAL GEN FUND -
ROW - - - -800,000 -800,000SALESTAX-MEASURE -
CON - - - -- 30,300,00030,300,000RTP-LRP -
CON - - - -3,450,000 -3,450,000SALESTAX-MEASURE -
9,150,000 30,300,000Total Funding - -- -39,450,000 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
ENV - - - -1,150,000 -1,150,000LOCAL GEN FUND -
ENV - - - -1,150,000 -1,150,000SALESTAX-MEASURE -
PSE - - - -1,800,000 -1,800,000SALESTAX-MEASURE -
ROW - - - -800,000 -800,000LOCAL GEN FUND -
ROW - - - -800,000 -800,000SALESTAX-MEASURE -
CON - - - -- 25,500,00025,500,000RTP-LRP -
CON - - - -3,450,000 -3,450,000SALESTAX-MEASURE -
9,150,000 25,500,000Total Funding - -- -34,650,000 -
Santa Rosa
Sec. RTP ID:
CTIPS ID:
Mode:
US 101 Hearn Ave Interchange
ACTIVESON150006
Trans. System:
RTP Cost:
2021-00 Version:
NON-EXEMPTAQ Description:
Santa Rosa
RTP Cycle:
Status:
Project Type:
20600005906
Project Name:
SYSTMGMTPurpose:
17-09-0010 AA
Revision:
Hwy Rte:
STATE HWY
TIP ID:
PLANBAYAREA2040
101
Primary RTP ID:
Implementing Agency:
4
$36,000,000
FREEWAY I/C
CURRENT
Review:
Sponsoring Agency:
End of Project SON150006
Hearn Avenue InterchangeRTP Description:
Santa Rosa: US 101/Hearn Avenue over-crossing/interchange: Replace the US 101/Hearn Avenue over-crossing/interchange with a new overcrossing/interchange including bike lanes, sidewalks, and re-aligned ramps to US 101.
Proj Description:
2021 TIP UpdateRevision Reason:
AUTO:85% | BIKE/PED:10% | BUS:5%
AQCTF Review: Review Pending
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
SON150006 2021-01 ACCEPTED
17-09-0010
20600005906
Santa Rosa Santa Rosa
5
US 101 Hearn Ave Interchange
AA
FREEWAY I/C SYSTMGMTSTATE HWY AUTO:85% | BIKE/PED:10% | BUS:5%
PLANBAYAREA2040
$36,000,000
NON-EXEMPT
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte: 101
Hearn Avenue InterchangeRTP Description:
Santa Rosa: US 101/Hearn Ave over-crossing/interchange: Replace the US 101/Hearn Ave over-crossing/interchange with a new overcrossing/interchange including bike lanes, sidewalks, and re-aligned ramps to US 101. Project also references RTP ID 17-09-0001
Proj Description:
Update the funding plan to add $4.8M in CON RTP-LRP fundsRevision Reason:
AQCTF Review: Review Pending
27Page 22 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
ENV - - - -200,000 -200,000LOCAL GEN FUND -
PSE - - - -50,000 -50,000LOCAL GEN FUND -
CON - - 36,831 -- -36,831EARMARK-T5 -
CON - - 400,000 -- -400,000LOCAL GEN FUND -
CON - - 600,000 -- -600,000STP-T5 -
250,000 -Total Funding - 1,036,831- -1,286,831 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
ENV - - - -200,000 -200,000LOCAL GEN FUND -
PSE - - - -50,000 -50,000LOCAL GEN FUND -
CON - 400,000 - -- -400,000LOCAL GEN FUND -
CON - 600,000 - -- -600,000STP-T5 -
250,000 -Total Funding - -1,000,000 -1,250,000 -
Healdsburg
Sec. RTP ID:
CTIPS ID:
Mode:
Healdsburg Avenue Complete Streets Improvements
ACTIVESON170024
Trans. System:
RTP Cost:
2021-00 Version:
EXEMPT (40 CFR 93.126) - Projects that correct, improve, or eliminate a hazardous location or featureAQ Description:
Healdsburg
RTP Cycle:
Status:
Project Type:
20600006458
Project Name:
SYSTMGMTPurpose:
17-09-0005 PR
Revision:
Hwy Rte:
LOCAL ROAD
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
3
$272,000,000
PAVEMENT
CURRENT
Review:
Sponsoring Agency:
End of Project SON170024
Roadway OperationsRTP Description:
Healdsburg: On Healdsburg Ave from Powell Ave to Passalaqua Rd: Implement complete streets improvements for all modes of travelincluding reducing travel lanes from 5 to 3
Proj Description:
2021 TIP UpdateRevision Reason:
AUTO:50% | BIKE/PED:35% |BUS:15%
AQCTF Review: Review Pending
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
SON170024 2021-01 ACCEPTED
17-09-0005
20600006458
Healdsburg Healdsburg
4
Healdsburg Avenue Complete Streets Improvements
PR
PAVEMENT SYSTMGMTLOCAL ROAD AUTO:50% | BIKE/PED:35% | BUS:15%
PLANBAYAREA2040
$272,000,000
EXEMPT (40 CFR 93.126) - Projects that correct, improve, or eliminate a hazardous location or feature
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Roadway OperationsRTP Description:
Healdsburg: On Healdsburg Ave from Powell Ave to Passalaqua Rd: Implement complete streets improvements for all modes of travelincluding reducing travel lanes from 5 to 3
Proj Description:
Update the funding plan to reprogram $600K in CON STP and $400K in CON Local from FY22 to FY23 and to add $37K in FY23 CONrepurposed earmark funds
Revision Reason:
AQCTF Review: Review Pending
27Page 23 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
CON - - - -2,899,300 -2,899,300HSIP-T4 253,785
CON 3,020,963 20,713,847 9,142,600 2,741,23045,860,570 -81,479,210HSIP-T5 314,419
CON 699,337 1,564,662 - 567,3553,719,673 -6,551,027LOCAL GEN FUND -
52,479,543 -Total Funding 3,720,300 9,142,60022,278,509 3,308,58590,929,537 568,204
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
CON - - - -2,899,300 -2,899,300HSIP-T4 253,785
CON 3,020,963 20,713,847 9,142,600 2,741,23045,860,570 -81,479,210HSIP-T5 314,419
CON 699,337 1,564,662 - 567,3553,719,673 -6,551,027LOCAL GEN FUND -
52,479,543 -Total Funding 3,720,300 9,142,60022,278,509 3,308,58590,929,537 568,204
Caltrans
Sec. RTP ID:
CTIPS ID:
Mode:
GL: Highway Safety Improvement Program
ACTIVEVAR170002
Trans. System:
RTP Cost:
2021-00 Version:
EXEMPT (40 CFR 93.126) - Highway Safety Improvement Program implementationAQ Description:
Caltrans
RTP Cycle:
Status:
Project Type:
20600006070
Project Name:
SYSTMGMTPurpose:
17-10-0025 PR
Revision:
Hwy Rte:
STATE HWY
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
13
$13,014,000,000
NON-PAVEMENT
CURRENT
Review:
Sponsoring Agency:
End of Project VAR170002
Regional State Highways - Existing ConditionsRTP Description:
GL: Safety Imprv - Highway Safety Improvement Program: Projects are consistent with 40 CFR Part 93.126 Exempt Tables 2 and Table 3categories.
Proj Description:
2021 TIP UpdateRevision Reason:
AUTO:100%
AQCTF Review: Reviewed
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
VAR170002 2021-01 ACCEPTED
17-10-0025
20600006070
Caltrans Caltrans
14
GL: Highway Safety Improvement Program
PR
NON-PAVEMENT SYSTMGMTSTATE HWY AUTO:100%
PLANBAYAREA2040
$13,014,000,000
EXEMPT (40 CFR 93.126) - Highway Safety Improvement Program implementation
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Regional State Highways - Existing ConditionsRTP Description:
GL: Safety Imprv - Highway Safety Improvement Program: Projects are consistent with 40 CFR Part 93.126 Exempt Tables 2 and Table 3categories.
Proj Description:
Update the back-up listing to reflect the latest information from CaltransRevision Reason:
AQCTF Review: Reviewed
27Page 24 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
CON 102,169,871 - - -28,362,175 -130,532,046AC-LOCAL -
CON 67,215 - 45,880 -1,445,726 4,520,5176,079,338BR-SEISMIC -
CON 21,584,864 22,405,980 13,620,644 -165,504,576 -223,116,064HBP-T4 4,801,341
CON - - - 29,502,545- 469,940,285499,442,830HBP-T5 17,028,887
CON 14,477,714 1,040,983 938,137 1,036,47914,623,434 26,778,96158,895,708LOCAL GEN FUND -
209,935,911 501,239,763Total Funding 138,299,664 14,604,66123,446,963 30,539,024918,065,986 21,830,228
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
CON 98,275,609 - - -28,362,175 -126,637,784AC-LOCAL -
CON 67,215 - 45,880 -1,445,726 4,520,5176,079,338BR-SEISMIC -
CON 24,754,308 22,890,109 9,166,548 -165,504,576 -222,315,541HBP-T4 4,906,292
CON - - - 28,539,628- 469,897,923498,437,551HBP-T5 17,008,814
CON 14,287,932 1,093,990 662,350 934,39614,623,434 28,363,99659,966,098LOCAL GEN FUND -
209,935,911 502,782,436Total Funding 137,385,064 9,874,77823,984,099 29,474,024913,436,312 21,915,106
Caltrans
Sec. RTP ID:
CTIPS ID:
Mode:
GL: Bridge Rehab/Recon. - Local Hwy Bridge Program
ACTIVEVAR170012
Trans. System:
RTP Cost:
2021-00 Version:
EXEMPT (40 CFR 93.126) - Widening narrow pavements or reconstructing bridges (no additional travel lanes)AQ Description:
Caltrans
RTP Cycle:
Status:
Project Type:
20600006109
Project Name:
MAINT/REHABPurpose:
17-10-0024 AA
Revision:
Hwy Rte:
LOCAL ROAD
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
21
$14,550,000,000
BRIDGE
CURRENT
Review:
Sponsoring Agency:
End of Project VAR170012
Regional and Local Bridges - Exisiting ConditionsRTP Description:
GL: Local Bridge Rehab/Recon. - Local Highway Bridge Program(HBP) or Highway Bridge Replacement and Rehabilitation (HBRR). Projectsare consistent with 40 CFR Part 93.126 Exempt Tables 2 categories.
Proj Description:
2021 TIP UpdateRevision Reason:
AUTO:100%
AQCTF Review: Reviewed
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
VAR170012 2021-01 ACCEPTED
17-10-0024
20600006109
Caltrans Caltrans
22
GL: Bridge Rehab/Recon. - Local Hwy Bridge Program
AA
BRIDGE MAINT/REHABLOCAL ROAD AUTO:100%
PLANBAYAREA2040
$14,550,000,000
EXEMPT (40 CFR 93.126) - Widening narrow pavements or reconstructing bridges (no additional travel lanes)
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Regional and Local Bridges - Exisiting ConditionsRTP Description:
GL: Local Bridge Rehab/Recon. - Local Highway Bridge Program(HBP) or Highway Bridge Replacement and Rehabilitation (HBRR). Projectsare consistent with 40 CFR Part 93.126 Exempt Tables 2 categories.
Proj Description:
Update the funding plan and back-up listing to reflect the latest information from CaltransRevision Reason:
AQCTF Review: Reviewed
27Page 25 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Report of TIP Revision 2021-01(By Phase & Fund Source)
PROPOSED
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
OTHER 2,350,000 - - -- -2,350,000FEDERAL-OTHER -
OTHER 1,610,000 - - -582,000 -2,192,000LOCAL GEN FUND -
OTHER - - - -1,000,000 -1,000,000STP-T5 -
1,582,000 -Total Funding 3,960,000 -- -5,542,000 -
Phase Prior LaterTotal FY 20/21 FY 21/22 FY 22/23 FY 23/24Fund Source Toll Credit
OTHER 2,000,000 - - -- -2,000,000FEDERAL-OTHER -
OTHER 1,610,000 - - -582,000 -2,192,000LOCAL GEN FUND -
OTHER - - - -1,000,000 -1,000,000STP-T5 -
1,582,000 -Total Funding 3,610,000 -- -5,192,000 -
BART
Sec. RTP ID:
CTIPS ID:
Mode:
BART: TOD Implementation
ACTIVEVAR190002
Trans. System:
RTP Cost:
2021-00 Version:
EXEMPT (40 CFR 93.126) - Planning and technical studiesAQ Description:
BART
RTP Cycle:
Status:
Project Type:
20600006636
Project Name:
OTHERPurpose:
17-10-0021 PR
Revision:
Hwy Rte:
TRANSIT
TIP ID:
PLANBAYAREA2040Primary RTP ID:
Implementing Agency:
3
$200,000,000
PLANNING
CURRENT
Review:
Sponsoring Agency:
End of Project VAR190002
Priority Development Area (PDA) Planning GrantsRTP Description:
Alameda, Contra Costa, San Francisco Counties: On BART property in BART station areas: Planning assistance to support transit orienteddevelopment
Proj Description:
2021 TIP UpdateRevision Reason:
RAIL:100%
AQCTF Review: Review Pending
TIP ID: Status:
Project Name:
Purpose:Project Type:
Implementing Agency:
Version:
Review:
Mode:Trans. System:
Revision: CTIPS ID:
Primary RTP ID:
VAR190002 2021-01 ACCEPTED
17-10-0021
20600006636
BART BART
4
BART: TOD Implementation
PR
PLANNING OTHERTRANSIT RAIL:100%
PLANBAYAREA2040
$200,000,000
EXEMPT (40 CFR 93.126) - Planning and technical studies
RTP Cycle: RTP Cost:
AQ Description:
Sec. RTP ID:
Sponsoring Agency:
Hwy Rte:
Priority Development Area (PDA) Planning GrantsRTP Description:
Alameda, Contra Costa, San Francisco Counties: On BART property in BART station areas: Planning assistance to support transit orienteddevelopment
Proj Description:
Update the funding plan to add $350K in FTA Pilot Program for Transit-Oriented Development (TOD) Planning grant fundsRevision Reason:
AQCTF Review: Review Pending
27Page 26 of Wednesday, May 12, 2021Metropolitan Transportation Commission
Federal
$3,355,248,216
State
$2,532,308,354
Regional
$822,939,862
Local Total
Current:
Proposed:
Delta:
$852,677,527 $188,816,909 $6,548,406,279 $2,097,745,304
$1,262,895,934$7,383,608,754$168,096,687$827,677,527
$834,849,370$20,720,222 -$835,202,475$25,000,000
$10,945,148,931
$10,911,691,322
$33,457,609
2021 TIP Only
TIP Revision Summary
27 Wednesday, May 12, 2021Page 27 of
Report of TIP Revision 2021-01(By Phase and Fund Source)
Metropolitan Transportation Commission
$24,060,664
Toll Credit
$23,975,786
-$84,878
D E T A I L E D L I S T I N G O F P R O J E C T S F O R G R O U P E D
L I S T I N G S A M E N D E D I N T H E C U R R E N T R E V I S I O N
GL: Safety Improvements – Highway Safety Improvement Program
(TIP ID – VAR170002)
Last updated with TIP Revision 2021-01
Caltrans Division of Local Assistance Highway Safety Improvement Program (HSIP)2019 FTIP Back-Up List, sorted by MPO, Agency and Unique Project ID
MTC
3/16/2021
Unique Project ID HR3Eligibility* District Agency MPO Project Location Description of Work Current Total Project Cost
Estimate Current Programmed Federal Funds Other/Local Funds
Federal Funds Programmed under "Prior"
Federal Funds Programmed in
2020/21
Federal Funds Programmed in
2021/22
Federal Funds Programmed in
2022/23
Federal Funds Programmed in
2023/24
Approved Federal Funds (total)
H9-04-001 No 4 Alameda County MTC Various unsignalized intersections in unincorporated Alameda County. Install/upgrade larger or additional stop signs or other warning/regulatory signs; add intersection lighting; add pedestrian crossing with enhanced safety features. $1,942,400 $1,750,000 $0 $192,400 $0 $1,750,000 $0 $0 $1,942,400
H9-04-002 No 4 Alameda County MTC Various signalized intersections throughout Alameda County; urban and suburban contexts.
Install mast arms; install signal hardware improvements such as additional signal heads, reflective backplates; install leading pedestrian interval. $2,493,900 $2,293,900 $0 $200,000 $0 $0 $2,293,900 $0 $2,493,900
H9-04-003 No 4 Alameda County MTC Crow Canyon Road, Palomares Road, North Vasco Road, and Altamont Pass Road in unincorporated Alameda County.
Widen paved shoulders, construct edgeline rumble strips, and install chevron signs and delineators. $1,812,700 $1,330,000 $181,270 $301,430 $0 $1,330,000 $0 $0 $1,631,430
H9-04-004 No 4 Alameda County MTC Thirteen (13) locations along Tesla Road between Eagles Run Road and McLaughlin Road. Upgrade guardrail. $471,300 $384,300 $0 $87,000 $0 $384,300 $0 $0 $471,300
H9-04-005 No 4 Benicia MTC Twenty-eight (28) guardrail locations within Benicia. Upgrade existing guardrails and the end treatments. $996,000 $861,000 $0 $135,000 $0 $861,000 $0 $0 $996,000
H9-04-006 No 4 Benicia MTC The intersections of West 5th St. with Military West and Hasting Dr. with London Dr. Enhance pedestrian crossings by installing ADA curb ramp, RRFB system, median island, and sidewalk, and other relevant elements. $259,100 $222,000 $9,100 $28,000 $0 $222,000 $0 $0 $250,000
H9-04-008 No 4 Concord MTC Various locations.Improve signal hardware (lenses, backplates, mountings, size, number), upgrade cabinet equipment, controllers and modify phasing to provide a Lead Pedestrian
Interval (LPI).$2,460,800 $1,979,576 $73,824 $407,400 $0 $1,979,576 $0 $0 $2,386,976
H8-04-006 No 4 Contra Costa County MTC Danville Boulevard between Stone Valley Road and Jackson Way in unincorporated Alamo of Contra Costa County.
Construct a roundabout at the intersection of Danville Boulevard and Orchard Court in addition to street improvements, such as sidewalk improvements and curb
extensions.$2,978,000 $2,233,000 $260,000 $485,000 $0 $0 $0 $2,233,000 $2,718,000
H8-04-008 No 4 Contra Costa County MTC Byron Highway approx. 350 feet south of Byer Road to Hoffman Lane, adjacent to Excelsior Middle School in unincorporated Byron.
Install southbound left-turn lane on Byron Highway on to Byer Road; Construct a two-way left turn lane to improve access at Excelsior Middle School; and widen roadway
to provide paved shoulders. $1,046,000 $508,230 $429,270 $108,500 $0 $0 $0 $508,230 $616,730
H9-04-009 No 4 Contra Costa County MTC Kirker Pass Road between the city limits of Concord and Pittsburg. Install intersection lighting at two intersections, install protective guardrail along the top of embankment, and install delineators/reflectors along the K-rail median. $1,280,000 $1,051,000 $0 $229,000 $0 $1,051,000 $0 $0 $1,280,000
H9-04-010 No 4 Contra Costa County MTC Various locations on arterials and major collector roadways in the Crockett area.Upgrade sub-standard MBGR guardrails to Caltrans standard MGS guardrails and
end treatments on arterials and major collector roadways (approximately 41 guardrails with a length of over 12,000 linear feet including end treatments).
$1,696,500 $999,963 $696,537 $0 $999,963 $0 $0 $0 $999,963
H9-04-011 No 4 Cupertino MTC The intersection of Homestead Rd and N De Anza Blvd. Upgrade existing pedestal-mounted signal to signal on mast arm. $213,300 $182,300 $0 $31,000 $0 $182,300 $0 $0 $213,300
H9-04-012 No 4 Fairfield MTC14 signalized intersections including N Texas St at Tabor, Travis, Walmart,
Atlantic/Cement Hill; Travis Blvd at 2nd, Pennsylvania, Webster, Union, Holiday, Fairfield, Solano Mall, Oliver; Oliver at Woodcreek; and Gateway at Courtyard.
Install Adaptive Signal Timing and advanced dilemma-zone detection, and enhance the visibility of signals. $1,870,300 $935,150 $935,150 $0 $0 $935,150 $0 $0 $935,150
H9-04-013 No 4 Fairfield MTC Twenty-five (25) locations. Upgrade existing guardrails and their end treatments. $655,400 $655,400 $0 $0 $0 $655,400 $0 $0 $655,400
H9-04-014 No 4 Fairfield MTCFive non-signalized intersections, including: N Texas St at Oak St; Pennsylvania
Ave at Empire St; N Texas St at Wisconsin St; Travis Blvd at Phoenix Dr; and Travis Blvd at Clay St.
Construct pedestrian crossing enhancements including HAWK installation accompanied by ADA curb ramp, and relevant signs and pavement markings. $1,348,100 $1,226,771 $121,329 $0 $0 $1,226,771 $0 $0 $1,226,771
H9-04-015 No 4 Los Gatos MTC Guardrail locatoins on Blossom Hill Road, Cleland Avenue, Los Gatos Boulevard, Miles Avenue, More Avenue, Reservoir Road, and Santa Rosa Drive. Upgrade the existing non-conforming and/or damaged guardrails. $980,100 $834,900 $0 $145,200 $834,900 $0 $0 $0 $980,100
HSIP7-04-011 No 4 Marin County MTC Arterials and rural collector roadways Sign inventory, roadway safety sign audit and signing upgrade project $605,000 $342,000 $60,500 $202,500 $0 $342,000 $0 $0 $544,500
H9-04-016 No 4 Marin County MTC Fifty-one (51) signalized intersections throughout Marin County, including unincorporated Marin County and within 11 incorporated cities and towns.
Install pedestrian countdown heads, pedestrian push buttons, 12" LED signal heads, signal head backplates and advanced dilemma zone detections. $2,800,300 $2,300,200 $0 $500,100 $0 $0 $2,300,200 $0 $2,800,300
H9-04-017 No 4 Marin County MTC Locations on Various rural arterials and major collector roadways in the County of Marin. Upgrade nonstandard guardrails. $961,200 $861,200 $0 $100,000 $0 $861,200 $0 $0 $961,200
H9-04-018 No 4 Napa County MTC Silverado Trail, MM 00.00-11.00. Upgrade existing guardrail on Silverado Trail to meet the current standards. $999,400 $894,100 $0 $105,300 $0 $0 $894,100 $0 $999,400
H9-04-019 No 4 Napa County MTC Silverado Trail north of Trancas St and south of HWY 29, excluding portions within and managed by City of St. Helena, City of Calistoga, and Caltrans jurisdictions.
Install rumble strips/stripes, center lines and shoulder striping on both north-bound and south-bound sides of Silverado trail, approximately 33.4 miles northernmost
point to southernmost point.$1,744,000 $1,626,700 $0 $117,300 $0 $0 $1,626,700 $0 $1,744,000
H9-04-020 No 4 Novato MTC Diablo Avenue/De Long Avenue corridor between Novato Boulevard and Reichert Avenue.
Improve pedestrian crosswalks throughout the corridor, install advanced dilemma zone detection at two key intersections, and provide an advance flashing beacon at
upstream of an intersection with an arterial roadway.$1,146,300 $1,146,300 $0 $0 $0 $1,146,300 $0 $0 $1,146,300
H9-04-021 No 4 Oakland MTC Foothill Blvd between Harrington Ave and Cole St, and MacArthur Blvd between 69th and 96th Ave.
Construct bulbouts, pedestrian median refuge islands, crosswalk enhancements, Rectangular Rapid Flashing Beacons (RRFBs), signs and striping. $1,217,700 $906,930 $121,770 $189,000 $0 $906,930 $0 $0 $1,095,930
H9-04-022 No 4 Oakland MTCFour (4) uncontrolled crosswalks along minor arterials at the following three
intersections: 7th Street & Filbert Street ; Oakland Avenue & Moss Avenue ; and 98th Avenue & C Street.
Install flashing beacons, pavement markings and signs; construct a median island, curb ramps and bulb outs. $282,300 $250,000 $32,300 $0 $0 $250,000 $0 $0 $250,000
H9-04-025 No 4 Pittsburg MTC Various locations throughout the City of Pittsburg. Improve signal hardware (signal heads, backplates, controllers, BBS, UPS, modems, cabinets, etc) and improve signal timing. $1,110,000 $878,400 $44,400 $187,200 $0 $878,400 $0 $0 $1,065,600
H9-04-026 No 4 Rio Vista MTCFour (4) pedestrian crossings at the following intersections: S 2nd and Marina Dr
(Riverview Junior High); DH White Elementary School and Thereza Way; DH White Elementary School and Laurel Way; and S 7th St and Main St.
Enhance pedestrian crossings by the addition of ADA curb ramp, curb extensions, advance yield signs and lines, Rectangular Rapid Flashing Beacons (RRFBs) and
other relevant elements.$249,100 $204,600 $0 $44,500 $0 $204,600 $0 $0 $249,100
MPO:
2021 Backup List Updated On:
Page 1 of 2 Printed On: 4/1/2021
Caltrans Division of Local Assistance Highway Safety Improvement Program (HSIP)2019 FTIP Back-Up List, sorted by MPO, Agency and Unique Project ID
MTC
3/16/2021
Unique Project ID HR3Eligibility* District Agency MPO Project Location Description of Work Current Total Project Cost
Estimate Current Programmed Federal Funds Other/Local Funds
Federal Funds Programmed under "Prior"
Federal Funds Programmed in
2020/21
Federal Funds Programmed in
2021/22
Federal Funds Programmed in
2022/23
Federal Funds Programmed in
2023/24
Approved Federal Funds (total)
MPO:
2021 Backup List Updated On:
H9-04-027 No 4 San Jose MTC Monterey Road between Skyway Drive and Palm Avenue. Upgrade guardrails that are damaged and not up to current standards. $1,002,800 $1,000,000 $2,800 $0 $1,000,000 $0 $0 $0 $1,000,000
H9-04-028 No 4 San Leandro MTC The intersection of Wicks Blvd and Manor Blvd.Install southbound and northbound left-turn signals; Upgrade signal heads and
signal equipment; Install video detections for cars and bikes and advance detection; Install Accessible Pedestrian Signal (APS); Upgrade wheelchair Ramps.
$359,900 $322,550 $0 $37,350 $0 $322,550 $0 $0 $359,900
H9-04-029 No 4 San Pablo MTC The Intersections of Church Lane and Willow Road and El Portal Drive and Mission Bell Road. Install pedestrian crossing enhancements and illumination. $1,015,600 $750,870 $101,560 $163,170 $0 $750,870 $0 $0 $914,040
H9-04-030 No 4 San Rafael MTC Five (5) signalized intersections of Third Street at Lindaro Street, Lincoln Avenue, Tamalpais Avenue, Irwin Street and Grand Street.
Construct high-visibility crosswalks, install advanced stop bars, and install pedestrian countdown signals at five intersections; and add signal mast arms at three locations. $1,575,000 $1,293,800 $0 $281,200 $0 $1,293,800 $0 $0 $1,575,000
H9-04-031 No 4 South San Francisco MTC Three (3) non-signalized intersections: W. Orange Ave at N. Canal St , W. Orange Ave at Myrtle Ave, and Hillside Blvd at Claremont Ave.
Construct pedestrian improvements including advanced pedestrian crosswalk, and ADA curb ramps. $204,800 $204,800 $0 $0 $0 $204,800 $0 $0 $204,800
H9-04-032 No 4 St Helena MTCSilverado Trail, with the project limits bordering Napa County, beginning from
approximately 175 feet north of Howell Mountain Road and ending at the southern City limits (1,475 feet total).
Upgrade approximately 1,175 lineal feet of existing guardrail and wood posts with new steel posts, new metal guardrail beams and guardrail delineators. $556,100 $486,100 $0 $70,000 $0 $486,100 $0 $0 $556,100
H9-04-033 No 4 Suisun City MTCThree (3) pedestrian crossings, including: on Merganser Dr between Sunset Ave and Wigeon Way; the intersection of Pintail Dr. and Scoter Way; and on Lawler
Ranch Pkwy between Fennie Way and Hillborn Way .
Enhance pedestrian crossings by the addition of ADA curb ramp, RRFB system, yield lines and signs, and other relevant elements. $248,100 $186,100 $0 $62,000 $186,100 $0 $0 $0 $248,100
H9-04-034 No 4 Sunnyvale MTC Sixteen (16) locations throughout the City of Sunnyvale Install video detection equipment to provide advance dilemma zone detection. $1,298,000 $1,112,000 $0 $186,000 $0 $1,112,000 $0 $0 $1,298,000
H9-04-035 No 4 Vacaville MTC Twenty-one (21) intersections in the City of Vacaville. Improve signal hardware and timing ; install Advanced Dilemma-Zone Detection. $2,477,700 $2,027,700 $0 $450,000 $0 $0 $2,027,700 $0 $2,477,700
H9-04-037 No 4 Vallejo MTCFive (5) pedestrian crossing at the intersection of Broadway at Illinois, Broadway at
Hampshire, Springs at Tregaskis, Springs at Heartwood, and Springs at Lassen/Hilton.
Installation of High-Intensity Activated Cros.swalk beacon (HAWK) at unsignalized intersections, installing high visible crosswalk, ADA curb ramps, Yield like with
signage and Pedestrian Push Button$1,305,800 $1,155,800 $0 $150,000 $0 $1,155,800 $0 $0 $1,305,800
H9-04-038 No 4 Vallejo MTCFive (5) intersections including: Foothill Dr at Redwood Pkwy, Valle Vista Ave at
Redwood St, Fairview Ave at Redwood St, Howard Ave at Redwood St, and Solano Ave at Tuolumne St.
Construct pedestrian crossing enhancements such as advanced pedestrian warnings and signs as well as Rectangular Rapid-Flashing Beacons (RRFBs). $246,000 $221,000 $0 $25,000 $0 $221,000 $0 $0 $246,000
Total(MTC) $43,909,000 $35,618,640 $3,069,810 $5,220,550 $3,020,963 $20,713,847 $9,142,600 $2,741,230 $40,839,190
Page 2 of 2 Printed On: 4/1/2021
2018/19-2023/24 Highway Bridge Program
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
Note id: 24
1) This is the FTIP lump sum “backup” list for HBP funded projects. Please see the Local Assistance web site for the most currentlistings:
http://www.dot.ca.gov/hq/LocalPrograms/hbrr99/HBP_FSTIP.html
2) The purpose of this list is to show which projects being advanced by local agencies have met the eligibility requirements of thefederal Highway Bridge Program and have been prioritized for funding by the Department in cooperation with local agencies forfunding.
3) Contractual funding levels are determined at time of federal authorization/obligation for given phase of work. For details seeChapter 3 of the Local Assistance Procedures Manual.
4) For FTIP/FSTIP purposes, Federal Highway Bridge Program (HBP) funding constraint is managed by Caltrans.
5) Prop 1B bond funds for the Local Seismic Safety Retrofit Program (LSSRP) used for matching federal funds are also managed byCaltrans.
6) Financial constraint of LOCAL matching funds (including regional STIP funds) and LOCAL Advance Construction (AC) is theresponsibility of the MPOs and their local agencies.
7) Some projects show that they are programmed using State STP funds. These funds are HBP funds transferred to the STP forbridge work that is not ordinarily eligible for HBP funds. See the HB Program Guidelines for details. Do not confuse these STPfunds with Regional STP funds.
8) Corrections to this report should be addressed to the District Local Assistance Engineer:
https://dot.ca.gov/programs/local-assistance/other-important-issues/local-assistance-contacts
Notes:
3/30/2021, 2:27 PM
Caltrans, Division of Local Assistance Page 13/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Alameda
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Alameda County BRIDGE NO. 33C0025, CASTLEWOOD DRIVE OVER ARROYO DE LA LAGUNA, 0.1 MI E/O FOOTHILL RD. Replace existing two-lanebridge with a new two-lane bridge. Chien Wu, 9/9/2016 2:44:45 PM.
Fund Source Summary:
PER/W
Total
CON
Total
4,608,800
570,000 570,000
200,000 200,000
570,000 200,000 5,378,8004,608,8004,608,800
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total504,621 177,060 4,761,852
65,379 22,940 616,948
570,000 200,000 5,378,800
4,080,171
528,629
4,608,800
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4420
5933(159)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total504,621 504,621
65,379 65,379
570,000 570,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total177,060 177,060
22,940 22,940
200,000 200,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total4,080,171
528,629
4,608,800
4,080,171
528,629
4,608,800
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 23/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Alameda
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Alameda County BRIDGE NO. 33C0448, ARROYO ROAD OVER DRY CREEK, 1 MILE SW OF WETMORE. Replace existing two-lane bridge with a newtwo-lane bridge. 10/1/2015: Toll Credits programmed for PE, R/W, & CON.
Fund Source Summary:
PER/W
Total 430,000
CON
Total
1,272,600
430,000
100,000 100,000
100,000 1,802,600
430,000
1,272,6001,272,600
Phase Summary:
Fed $
Local AC
Local Match
Total 430,000
LSSRP Bond
Total100,000 1,802,600
100,000 1,802,600
430,000 1,272,600
1,272,600
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4301
5933(138)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 430,000
LSSRP Bond
Total430,000
430,000
430,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total100,000 100,000
100,000 100,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,272,600
1,272,600
1,272,600
1,272,600
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 33/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Alameda
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Albany BRIDGE NO. 33C0184, BUCHANAN ST OVER UP RR, BNSF RY, & AMTRAK, NEAR I-80. Bridge preventive maintenance project.
Fund Source Summary:
PER/W
Total
CON
Total
291,300
40,000 40,000
4,000
40,000 335,300291,300
4,000
295,300
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total35,412 296,841
4,588 38,459
40,000 335,300
261,429
33,871
295,300
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4157
5178(017)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total35,412 35,412
4,588 4,588
40,000 40,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,541
459
4,000
3,541
459
4,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total257,888
33,412
291,300
257,888
33,412
291,300
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 43/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Alameda
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Oakland BRIDGE NO. 33C0028, ADELINE ST, OVER UP RR,BNSF,AMTRAK,EMBARC, JUST S OF 3RD ST. Voluntary Seismic retrofit only, no lanesbeing added.
Fund Source Summary:
PER/W
Total
80,000
712,000
CON
Total
3,823,750
134,000 766,000
80,000
134,000 4,669,750
632,000
3,823,7503,823,750
Phase Summary:
Fed $
Local AC
Local Match
Total
81,666
712,000
LSSRP Bond
Total118,630 4,134,130
15,370 535,620
134,000 4,669,750
630,334 3,385,166
438,584
3,823,750
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3413
5012(103)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
72,490
632,000
LSSRP Bond
Total118,630 678,140
15,370 87,860
134,000 766,000
559,510
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
9,176
80,000
LSSRP Bond
Total70,824
9,176
80,000
70,824
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,385,166
438,584
3,823,750
3,385,166
438,584
3,823,750
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 53/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Alameda
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Oakland BRIDGE NO. 33C0215, LEIMERT BLVD, OVER SAUSAL CREEK, 0.1 MI E OF PARK BLVD. LSSRP Seismic Retrofit
Fund Source Summary:
PER/W
Total 1,473,000
CON
Total
5,441,250
1,473,000
115,000 115,000
115,000 7,029,250
1,473,000
5,441,2505,441,250
Phase Summary:
Fed $
Local AC
Local Match
Total
168,953
1,473,000
LSSRP Bond
Total
13,191 637,302
101,810 6,222,995
168,953
115,000 7,029,250
1,304,047
624,111
4,817,139
5,441,250
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
2130
5012(025)5012(124)
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
168,953
1,473,000
LSSRP Bond
Total1,304,047
168,953
1,473,000
1,304,047
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
13,191 13,191
101,810 101,810
115,000 115,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
624,111
4,817,139
5,441,250
624,111
4,817,139
5,441,250
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 63/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Alameda
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Oakland BRIDGE NO. 33C0373L, EDGEWATER DRIVE SB OVER ELMHURST CANAL, 0.2 MI N/W ROLAND WAY. Replace existing two-lane bridgewith a new two-lane bridge , Chien Wu, 9/29/2016 9:47:53 AM.
Fund Source Summary:
PER/W
Total
CON
Total
4,480,000
800,000 800,000
100,000 100,000
800,000 100,000 5,380,0004,480,0004,480,000
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total708,240 88,530 4,762,914
91,760 11,470 617,086
800,000 100,000 5,380,000
3,966,144
513,856
4,480,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4457
5012(161)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total708,240 708,240
91,760 91,760
800,000 800,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total88,530 88,530
11,470 11,470
100,000 100,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,966,144
513,856
4,480,000
3,966,144
513,856
4,480,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 73/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Alameda
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Oakland BRIDGE NO. 33C0373R, EDGEWATER DRIVE NB OVER ELMHURST CANAL, 0.2 MI N/W ROLAND WAY. Replace existing two-lane bridgewith a new two-lane bridge, Chien Wu, 9/29/2016 10:36:18 AM.
Fund Source Summary:
PER/W
Total
CON
Total
4,480,000
800,000 800,000
100,000 100,000
800,000 100,000 5,380,0004,480,0004,480,000
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total708,240 88,530 4,762,914
91,760 11,470 617,086
800,000 100,000 5,380,000
3,966,144
513,856
4,480,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4458
5012(160)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total708,240 708,240
91,760 91,760
800,000 800,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total88,530 88,530
11,470 11,470
100,000 100,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,966,144
513,856
4,480,000
3,966,144
513,856
4,480,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 83/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Alameda
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Oakland PM00002, Bridge Preventive Maintenance Program (BPMP), various bridges in the City of Oakland. See Caltrans Local Assistance HBP website for backup list of bridges.
Fund Source Summary:
PER/W
Total 4,676,335
CON
Total
2,970,335 5,234,991
1,706,000
6,940,991
1,706,000
2,264,6562,264,656
Phase Summary:
Fed $
Local AC
Local Match
Total
536,376
4,676,335
LSSRP Bond
Total6,144,859
-0 0 796,132
6,940,991
4,139,959 2,004,900
259,756
2,264,656
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3304
5012(083)5012(108)5012(109)5012(111)5012(112)5012(121)5012(137)
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
195,678
1,706,000
LSSRP Bond
Total1,510,322
195,678
1,706,000
1,510,322
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
340,697
2,970,335
LSSRP Bond
Total4,634,538
-0 0 600,453
5,234,991
2,629,638 2,004,900
259,756
2,264,656
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 93/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Alameda
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Pleasanton BRIDGE NO. PM00119, Bridge Preventive Maintenance Program (BPMP), various bridges in the City of Pleasanton. See Caltrans LocalAssistance HBP web site for backup list of bridges
Fund Source Summary:
PER/W
Total 151,962
CON
Total
1,291,520 1,291,520
151,962
1,291,520 1,443,482
151,962
Phase Summary:
Fed $
Local AC
Local Match
Total
17,430
151,962
LSSRP Bond
Total1,143,383 1,277,915
148,137 165,567
1,143,383 -1,143,3831,291,520 1,443,482
134,532
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4256
5101(029)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
17,430
151,962
LSSRP Bond
Total134,532
17,430
151,962
134,532
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
0
LSSRP Bond
Total1,143,383 1,143,383
148,137 148,137
1,143,383 -1,143,383
1,291,520 1,291,520
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 103/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Concord PM00023, Bridge Preventive Maintenance Program, various locations. See Caltrans Local Assistance HBP web site for backup list of bridges.
Fund Source Summary:
PER/W
Total 4,021,366
CON
Total
3,211,141 924,427 4,135,568
20,107 830,332
20,107 924,427 4,965,900
810,225
Phase Summary:
Fed $
Local AC
Local Match
Total
461,251
4,021,366
LSSRP Bond
Total17,801 818,395 4,396,311
2,306 106,032 569,589
20,107 924,427 4,965,900
3,560,115
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3392
5135(039)5135(048)5135(049)
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
92,933
810,225
LSSRP Bond
Total17,801 735,093
2,306 95,239
20,107 830,332
717,292
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
TotalPrior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
368,318
3,211,141
LSSRP Bond
Total818,395 3,661,218
106,032 474,350
924,427 4,135,568
2,842,823
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 113/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Contra Costa County BRIDGE NO. 28C0024, ORWOOD ROAD, OVER INDIAN SLOUGH, 2 MI E BYRON HIGHWAY. Replace 2 lane bridge with new 2 lanebridge. 4/5/2010: Toll Credits programmed for R/W & Con.
Fund Source Summary:
PER/W
Total
100,000
9,497,700
CON
Total
8,372,700 1,558,708 1,030,059 10,961,467
387,200 1,412,200
291,781 391,781
2,237,689 1,030,059 12,765,448
1,025,000
Phase Summary:
Fed $
Local AC
Local Match
Total
205,000
9,497,700
LSSRP Bond
Total2,160,249 1,030,059 12,483,008
77,440 282,440
2,237,689 1,030,059 12,765,448
9,292,700
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
1175
5928(045)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
205,000
1,025,000
LSSRP Bond
Total309,760 1,129,760
77,440 282,440
387,200 1,412,200
820,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total 100,000
LSSRP Bond
Total291,781 391,781
291,781 391,781
100,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total 8,372,700
LSSRP Bond
Total1,558,708 1,030,059 10,961,467
1,558,708 1,030,059 10,961,467
8,372,700
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 123/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Contra Costa County BRIDGE NO. 28C0121, BYRON HWY, OVER CALIFORNIA AQUEDUCT, 1.4 MI NW ALA C.L.. Replace existing 2 lane bridge with new 2 lanebridge
Fund Source Summary:
PER/W
Total 675,000
CON
Total
17,880,000
1,525,000 2,200,000
200,000 2,800,000 3,000,000
200,000 4,325,000 23,080,000
675,000
17,880,00017,880,000
Phase Summary:
Fed $
Local AC
Local Match
Total
77,423
675,000
LSSRP Bond
Total4,005,983 20,432,724
22,940 496,078 0 2,647,276
177,060 -177,060200,000 4,325,000 23,080,000
597,578 15,829,164
2,050,836
17,880,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
1677
5928(104)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
77,423
675,000
LSSRP Bond
Total1,350,083 1,947,660
174,918 252,340
1,525,000 2,200,000
597,578
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total2,655,900 2,655,900
22,940 321,160 344,100
177,060 -177,060
200,000 2,800,000 3,000,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total15,829,164
0 2,050,836
17,880,000
15,829,164
2,050,836
17,880,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 133/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Contra Costa County BRIDGE NO. 28C0141, MARSH CREEK RD OVER MARSH CREEK, 1.8 MI E MORGAN TERITY RD. Replace existing two lane bridge withtwo lane bridge,
Fund Source Summary:
PER/W
Total
146,000
6,845,417
CON
Total
5,699,417 120,869 5,820,286
65,000 1,065,000
43,000 189,000
228,869 7,074,286
1,000,000
Phase Summary:
Fed $
Local AC
Local Match
Total5,045,694
785,169
6,845,417
LSSRP Bond
Total5,248,312 6,262,865
26,251 811,421
-5,045,694228,869 7,074,286
1,014,554
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3727
5928(107)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
114,700
1,000,000
LSSRP Bond
Total57,545 942,845
7,456 122,156
65,000 1,065,000
885,300
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
16,746
146,000
LSSRP Bond
Total38,068 167,322
4,932 21,678
43,000 189,000
129,254
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
5,045,694
653,723
5,699,417
LSSRP Bond
Total5,152,699 5,152,699
13,864 667,587
-5,045,694
120,869 5,820,286
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 143/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Contra Costa County BRIDGE NO. 28C0143, MARSH CREEK RD, OVER MARSH CREEK, 7.3 MI E MORGAN TERITY RD combined with BRIDGE NO. 28C0145,MARSH CREEK RD, OVER MARSH CREEK, 3 MI E DEER VALLEY ROAD . Replace two existing 2-lane bridges with two new 2-lane bridges.
Fund Source Summary:
PER/W
Total 1,040,500
CON
Total
13,450,000
500,000 209,500 1,750,000
300,000 310,000 610,000
300,000 810,000 209,500 15,810,000
1,040,500
13,450,00013,450,000
Phase Summary:
Fed $
Local AC
Local Match
Total
119,345
1,040,500
LSSRP Bond
Total265,590 717,093 185,470 13,996,593
34,410 92,907 24,030 1,813,407
300,000 810,000 209,500 15,810,000
921,155 11,907,285
1,542,715
13,450,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3957
5928(125)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
119,345
1,040,500
LSSRP Bond
Total442,650 185,470 1,549,275
57,350 24,030 200,725
500,000 209,500 1,750,000
921,155
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total265,590 274,443 540,033
34,410 35,557 69,967
300,000 310,000 610,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total11,907,285
1,542,715
13,450,000
11,907,285
1,542,715
13,450,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 153/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Contra Costa County BRIDGE NO. 28C0154, PLEASANT HILL RD OVER TAYLOR BLVD, 0.6 MI E OF GEARY ROAD. Rehabilitate existing bridge. Deckreplacement and sliver widening for standard shoulders, no added capacity.
Fund Source Summary:
PER/W
Total
CON
Total
1,756,310
313,627 313,627
25,000 25,000
313,627 25,000 2,094,9371,756,3101,756,310
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total299,786 1,854,648
35,973 2,868 240,289
277,654 -277,654313,627 25,000 2,094,937
1,554,861
201,449
1,756,310
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4527
5928(154)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total277,654 277,654
35,973 35,973
277,654 -277,654
313,627 313,627
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total22,133 22,133
2,868 2,868
25,000 25,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,554,861
201,449
1,756,310
1,554,861
201,449
1,756,310
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 163/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Contra Costa County BRIDGE NO. 28C0376, CANAL RD, OVER CONTRA COSTA CANAL, 0.5 MI W OF BAILEY RD. Replace existing two lane bridge with two lanebridge. 4/1/2010: Toll Credits programmed for PE, R/W, & Con.
Fund Source Summary:
PER/W
Total
112,400
2,281,775
CON
Total
1,724,900 97,100 1,822,000
444,475
43,100 155,500
140,200 2,421,975
444,475
Phase Summary:
Fed $
Local AC
Local Match
Total 2,281,775
LSSRP Bond
Total140,200 2,421,975
140,200 2,421,975
2,281,775
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
829
5928(108)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 444,475
LSSRP Bond
Total444,475
444,475
444,475
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total 112,400
LSSRP Bond
Total43,100 155,500
43,100 155,500
112,400
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total 1,724,900
LSSRP Bond
Total97,100 1,822,000
97,100 1,822,000
1,724,900
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 173/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Contra Costa County BRIDGE NO. 28C0442, MARSH DRIVE OVER WALNUT CREEK, 0.2 MI W OF SOLANO WAY. Replace existing two-lane bridge with a newtwo-lane bridge, Minor seismic contribution.
Fund Source Summary:
PER/W
Total 1,180,000
CON
Total
14,642,100 14,642,100
400,000 120,000 1,700,000
240,000 215,000 455,000
640,000 14,642,100 335,000 16,797,100
1,180,000
Phase Summary:
Fed $
Local AC
Local Match
Total
135,346
1,180,000
LSSRP Bond
Total
229,400
566,592 296,576 14,870,473
73,408 1,679,449 38,425 1,697,227
12,962,651640,000 14,642,100 335,000 16,797,100
1,044,654
229,400
12,962,651
-229,400
-12,962,651
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4299
5928(128)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
135,346
1,180,000
LSSRP Bond
Total354,120 106,236 1,505,010
45,880 13,764 194,990
400,000 120,000 1,700,000
1,044,654
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total212,472 190,340 402,812
27,528 24,661 52,189
240,000 215,000 455,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
229,400
12,962,651
1,679,449 1,450,049
12,962,651
14,642,100 14,642,100
229,400
12,962,651
-229,400
-12,962,651
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 183/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Contra Costa County BRIDGE NO. PM00159,Bridge Preventive Maintenance Program (BPMP) various bridges in Contra Costa County. See Caltrans LocalAssistance HBP website for backup list of projects.
Fund Source Summary:
PER/W
Total
CON
Total
805,778
180,370 180,370
60,000
180,370 1,046,148805,778
60,000
865,778
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total159,682 926,155
20,688 119,993
180,370 1,046,148
766,473
99,305
865,778
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4513
5928(155)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total159,682 159,682
20,688 20,688
180,370 180,370
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total53,118
6,882
60,000
53,118
6,882
60,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total713,355
92,423
805,778
713,355
92,423
805,778
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 193/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Danville BRIDGE NO. 28C0335, LA GONDA WAY, OVER SAN RAMON CREEK, AT DANVILLE BLVD. Widen existing two-lane bridge to includestandard lane width, shoulder and sidewalk. (No added capacity)
Fund Source Summary:
PER/W
Total 600,000
CON
Total
6,420,400
603,807 1,203,807
221,000 221,000
824,807 7,845,207
600,000
6,420,4006,420,400
Phase Summary:
Fed $
Local AC
Local Match
Total
68,820
600,000
LSSRP Bond
Total730,202 6,945,362
94,605 899,845
824,807 7,845,207
531,180 5,683,980
736,420
6,420,400
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4288
5434(024)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
68,820
600,000
LSSRP Bond
Total534,550 1,065,730
69,257 138,077
603,807 1,203,807
531,180
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total195,651 195,651
25,349 25,349
221,000 221,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total5,683,980
736,420
6,420,400
5,683,980
736,420
6,420,400
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 203/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Lafayette BRIDGE NO. PM00174, Bridge Preventive Maintenance Program (BPMP) various bridges in the City of Lafayette. See Caltrans LocalAssistance HBP website for backup list of projects.
Fund Source Summary:
PER/W
Total
CON
Total
334,000
115,000 115,000
115,000 449,000334,000334,000
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total101,810 397,500
13,191 51,500
115,000 449,000
295,690
38,310
334,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4593
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total101,810 101,810
13,191 13,191
115,000 115,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total295,690
38,310
334,000
295,690
38,310
334,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 213/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Moraga BRIDGE NO. 28C0137, CANYON RD OVER W BRANCH SAN LEANDRO CR, 2.4 MI N ALA C.L.. Replace existing 2-lane bridge with new2-lane bridge.
Fund Source Summary:
PER/W
Total
150,000
1,115,875
CON
Total
7,938,750 180,000 2,512,435 10,631,185
624,125 33,000 243,801 1,866,801
25,000 100,194 275,194
8,587,875 213,000 343,995 2,512,435 12,773,180
965,875
Phase Summary:
Fed $
Local AC
Local Match
Total
127,991
1,115,875
LSSRP Bond
Total7,602,846 188,569 304,539 2,224,259 11,308,096
985,029 24,431 39,456 288,176 1,465,084
8,587,875 213,000 343,995 2,512,435 12,773,180
987,884
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4070
5415(011)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
110,786
965,875
LSSRP Bond
Total552,538 29,215 215,837 1,652,679
71,587 3,785 27,964 214,122
624,125 33,000 243,801 1,866,801
855,089
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
17,205
150,000
LSSRP Bond
Total22,133 88,702 243,629
2,868 11,492 31,565
25,000 100,194 275,194
132,795
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total7,028,175 159,354 2,224,259 9,411,788
910,575 20,646 288,176 1,219,397
7,938,750 180,000 2,512,435 10,631,185
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 223/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Oakley BRIDGE NO. 28C0270, MAIN STREET OVER CONTRA COSTA CANAL, .01 MI SE/O OAKLEY RD. Rehabilitate existing bridge (no addedcapacity), Chien Wu, 10/5/2016 10:20:29 AM.
Fund Source Summary:
PER/W
Total
CON
Total
248,402
88,715 88,715
50,000
88,715 387,117248,402
50,000
298,402
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total78,539 342,715
10,176 44,402
88,715 387,117
264,175
34,227
298,402
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4472
5477(008)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total78,539 78,539
10,176 10,176
88,715 88,715
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total44,265
5,735
50,000
44,265
5,735
50,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total219,910
28,492
248,402
219,910
28,492
248,402
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 233/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Orinda BRIDGE NO. 28C0330, MINER RD, OVER SAN PABLO CREEK, AT CAMINO PABLO. LSSRP Seismic Retrofit
Fund Source Summary:
PER/W
Total 195,000
CON
Total
314,000
175,900 370,900
50,000 50,000
175,900 50,000 734,900
195,000
314,000314,000
Phase Summary:
Fed $
Local AC
Local Match
Total
22,367
195,000
LSSRP Bond
Total
5,735 41,751
155,724 44,265 650,607
20,176 42,542
175,900 50,000 734,900
172,634
36,016
277,984
314,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
2073
5444(010)5444(019)
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
22,367
195,000
LSSRP Bond
Total155,724 328,358
20,176 42,542
175,900 370,900
172,634
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
5,735 5,735
44,265 44,265
50,000 50,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
36,016
277,984
314,000
36,016
277,984
314,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 243/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Orinda BRIDGE NO. 28C0331, BEAR CREEK RD, OVER SAN PABLO CREEK, 0.2 MI E CAMINO PABLO. LSSRP Seismic Retrofit
Fund Source Summary:
PER/W
Total 737,000
CON
Total
666,000
737,000
50,000 50,000
50,000 1,453,000
737,000
666,000666,000
Phase Summary:
Fed $
Local AC
Local Match
Total652,466
84,534
737,000
LSSRP Bond
Total
5,735 82,125
652,466 44,265 1,286,341
84,534
-652,46650,000 1,453,000
76,390
589,610
666,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
2074
5444(007)5444(018)
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
652,466
84,534
737,000
LSSRP Bond
Total652,466 652,466
84,534
-652,466
737,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
5,735 5,735
44,265 44,265
50,000 50,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
76,390
589,610
666,000
76,390
589,610
666,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 253/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Pinole BRIDGE NO. 28C0062, SAN PABLO AVE, OVER BNSF RY AND AMTRAK, JUST W/O HERCULES AVE. Replace existing four-lane bridgewith a new four-lane bridge, Chien Wu, 12/24/2015 9:57:52 AM.
Fund Source Summary:
PER/W
Total 893,000
CON
Total
15,773,800
893,000
100,000 100,000
100,000 16,766,800
893,000
15,773,80015,773,800
Phase Summary:
Fed $
Local AC
Local Match
Total
102,427
893,000
LSSRP Bond
Total88,530 14,843,648
11,470 1,923,152
100,000 16,766,800
790,573 13,964,545
1,809,255
15,773,800
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4318
5126(015)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
102,427
893,000
LSSRP Bond
Total790,573
102,427
893,000
790,573
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total88,530 88,530
11,470 11,470
100,000 100,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total13,964,545
1,809,255
15,773,800
13,964,545
1,809,255
15,773,800
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 263/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Pittsburg BRIDGE NO. 28C0165, NORTH PARKSIDE DR, OVER WILLOW PASS ROAD, OVER WILLOW PASS RD.. LSSRP Seismic Retrofit andBridge Preventive Maintenance work.
Fund Source Summary:
PER/W
Total 568,703
CON
Total
339,503 168,382 507,885
229,200
168,382 737,085
229,200
Phase Summary:
Fed $
Local AC
Local Match
Total
32,541
568,703
LSSRP Bond
Total
32,690 13,411 46,100
149,069 652,541
5,903 38,444
168,382 737,085
503,473
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
2061
5127(024)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
26,289
229,200
LSSRP Bond
Total202,911
26,289
229,200
202,911
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
6,251
339,503
LSSRP Bond
Total
32,690 13,411 46,100
149,069 449,631
5,903 12,154
168,382 507,885
300,562
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 273/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Pleasant Hill BRIDGE NO. PM00141, Bridge Preventive Maintenance Program (BPMP) various bridges in the City of Pleasant Hill. See Caltrans LocalAssistance HBP website for backup list of projects.
Fund Source Summary:
PER/W
Total 60,000
CON
Total
166,800 166,800
60,000
166,800 226,800
60,000
Phase Summary:
Fed $
Local AC
Local Match
Total
6,882
60,000
LSSRP Bond
Total147,668 200,786
19,132 26,014
147,668 -147,668166,800 226,800
53,118
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4336
5375(033)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
6,882
60,000
LSSRP Bond
Total53,118
6,882
60,000
53,118
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total147,668 147,668
19,132 19,132
147,668 -147,668
166,800 166,800
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 283/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Richmond BRIDGE NO. PM00093, Bridge Preventive Maintenance Program (BPMP) various bridges in the City of Richmond. See Caltrans LocalAssistance HBP website for backup list of projects.
Fund Source Summary:
PER/W
Total
CON
Total
2,100,000
50,000 50,000
50,000 2,150,0002,100,0002,100,000
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total44,265 1,903,395
5,735 246,605
50,000 2,150,000
1,859,130
240,870
2,100,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4057
5137(046)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total44,265 44,265
5,735 5,735
50,000 50,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,859,130
240,870
2,100,000
1,859,130
240,870
2,100,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 293/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
San Pablo BRIDGE NO. 28C0057, SAN PABLO AVE OVER SAN PABLO CREEK, AT ROAD 20. Replace existing 6-lane bridge with a new 6-lane bridge,Chien Wu, 3/3/2016 10:07:10 AM.
Fund Source Summary:
PER/W
Total
CON
Total
8,312,920
940,000 940,000
200,000 200,000
940,000 200,000 9,452,9208,312,9208,312,920
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total832,182 177,060 8,368,670
107,818 22,940 1,084,250
940,000 200,000 9,452,920
7,359,428
953,492
8,312,920
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4337
5303(021)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total832,182 832,182
107,818 107,818
940,000 940,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total177,060 177,060
22,940 22,940
200,000 200,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total7,359,428
953,492
8,312,920
7,359,428
953,492
8,312,920
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 303/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
San Pablo BRIDGE NO. 28C0326, GIANT HWY OVER SAN PABLO CREEK, AT PARR BLVD. Preventive maintenance to include deck methacrylate andjoint replacement work, Chien Wu, 3/22/2016 10:16:46 AM.
Fund Source Summary:
PER/W
Total 50,000
CON
Total
389,620
50,000
439,620
50,000
389,620389,620
Phase Summary:
Fed $
Local AC
Local Match
Total
5,735
50,000
LSSRP Bond
Total389,196
50,424
439,620
44,265 344,931
44,689
389,620
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4353
5303(019)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
5,735
50,000
LSSRP Bond
Total44,265
5,735
50,000
44,265
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total344,931
44,689
389,620
344,931
44,689
389,620
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 313/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Walnut Creek BRIDGE NO. 28C0052, BANCROFT RD, OVER WALNUT CREEK, 0.1 MI N DAVID ST. Bridge Rehabilitation. Widen existing two-lane bridgeto two-lane bridge.
Fund Source Summary:
PER/W
Total 485,000
CON
Total
1,557,403
440,000 925,000
100,000 100,000
540,000 2,582,403
485,000
1,557,4031,557,403
Phase Summary:
Fed $
Local AC
Local Match
Total
55,630
485,000
LSSRP Bond
Total478,062 2,286,201
61,938 296,202
540,000 2,582,403
429,371 1,378,769
178,634
1,557,403
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4233
5225(027)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
55,630
485,000
LSSRP Bond
Total389,532 818,903
50,468 106,098
440,000 925,000
429,371
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total88,530 88,530
11,470 11,470
100,000 100,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,378,769
178,634
1,557,403
1,378,769
178,634
1,557,403
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 323/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Contra Costa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Walnut Creek BRIDGE NO. 28C0075, SOUTH MAIN ST, OVER LAS TRAMPAS CREEK, 0.1 MI S OLYMPIC BLVD. Replace existing 5-lane bridge with anew 5-lane bridge.
Fund Source Summary:
PER/W
Total 615,000
CON
Total
11,222,000
133,600 1,066,400 1,815,000
750,000 750,000
133,600 1,816,400 13,787,000
615,000
11,222,00011,222,000
Phase Summary:
Fed $
Local AC
Local Match
Total
70,541
615,000
LSSRP Bond
Total118,276 1,608,059 12,205,631
15,324 208,341 1,581,369
133,600 1,816,400 13,787,000
544,460 9,934,837
1,287,163
11,222,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4234
5225(026)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
70,541
615,000
LSSRP Bond
Total118,276 944,084 1,606,820
15,324 122,316 208,181
133,600 1,066,400 1,815,000
544,460
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total663,975 663,975
86,025 86,025
750,000 750,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total9,934,837
1,287,163
11,222,000
9,934,837
1,287,163
11,222,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 333/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Fairfax BRIDGE NO. 27C0008, MEADOW WAY, OVER SAN ANSELMO CREEK, IN FAIRFAX. Replace FO 1 lane timber bridge with wider 1 lanebridge. 4/5/2010: Toll Credits programmed for Con. 3/8/2019: Toll credits used for R/W.
Fund Source Summary:
PER/W
Total 932,238
CON
Total
4,585,000
105,562 619,800 1,657,600
216,000 216,000
105,562 216,000 619,800 6,458,600
932,238
4,585,0004,585,000
Phase Summary:
Fed $
Local AC
Local Match
Total
106,928
932,238
LSSRP Bond
Total93,454 216,000 548,709 6,268,473
12,108 71,091 190,127
105,562 216,000 619,800 6,458,600
825,310 4,585,000
4,585,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
662
5277(025)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
106,928
932,238
LSSRP Bond
Total93,454 548,709 1,467,473
12,108 71,091 190,127
105,562 619,800 1,657,600
825,310
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total216,000 216,000
216,000 216,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total4,585,000
4,585,000
4,585,000
4,585,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 343/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Fairfax BRIDGE NO. 27C0142, AZALEA AVE OVER FAIRFAX CREEK, IN FAIRFAX. Replace existing 2-lane bridge with new 2-lane bridge.3/6/2013: Toll credits used for PE. Toll credits used for CON.
Fund Source Summary:
PER/W
Total 854,121
CON
Total
4,000,000
640,000 1,494,121
200,000 200,000
840,000 5,694,121
854,121
4,000,0004,000,000
Phase Summary:
Fed $
Local AC
Local Match
Total 854,121
LSSRP Bond
Total817,060 5,671,181
22,940 22,940
840,000 5,694,121
854,121 4,000,000
4,000,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4062
5277(028)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 854,121
LSSRP Bond
Total640,000 1,494,121
640,000 1,494,121
854,121
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total177,060 177,060
22,940 22,940
200,000 200,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total4,000,000
4,000,000
4,000,000
4,000,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 353/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Fairfax BRIDGE NO. 27C0144, CREEK ROAD, OVER SAN ANSELMO CREEK, IN FAIRFAX. LSSRP Seismic Retrofit 7/8/2013 and PreventiveMaintenence: Toll credits used for PE. 12/3/2014: Toll credits used for R/W and CON.
Fund Source Summary:
PER/W
Total 795,994
CON
Total
1,594,600
88,500 247,656 1,132,150
13,000 13,000
88,500 260,656 2,739,750
795,994
1,594,6001,594,600
Phase Summary:
Fed $
Local AC
Local Match
Total 795,994
LSSRP Bond
Total88,500 260,656 2,739,750
88,500 260,656 2,739,750
795,994 1,594,600
1,594,600
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
2052
5277(027)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 795,994
LSSRP Bond
Total88,500 247,656 1,132,150
88,500 247,656 1,132,150
795,994
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total13,000 13,000
13,000 13,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,594,600
1,594,600
1,594,600
1,594,600
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 363/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Fairfax BRIDGE NO. PM00083, Bridge Preventive Maintenance Program (BPMP) various bridges in the Town of Fairfax. See Caltrans Local AssistanceHBP website for backup list of projects.
Fund Source Summary:
PER/W
Total 425,420
CON
Total
625,086
53,650 312,458 791,528
12,500 12,500
53,650 324,958 1,429,114
425,420
625,086625,086
Phase Summary:
Fed $
Local AC
Local Match
Total
48,796
425,420
LSSRP Bond
Total47,496 287,685 1,265,195
6,154 37,273 163,919
53,650 324,958 1,429,114
376,624 553,389
71,697
625,086
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4019
5277(026)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
48,796
425,420
LSSRP Bond
Total47,496 276,619 700,740
6,154 35,839 90,788
53,650 312,458 791,528
376,624
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total11,066 11,066
1,434 1,434
12,500 12,500
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total553,389
71,697
625,086
553,389
71,697
625,086
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 373/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Larkspur BRIDGE NO. 27C0028, BON AIR RD, OVER CORTE MADERA CREEK, .5 MI SW SR FRANCIS DRK B. Replace 2 lane bridge with new 2lane bridge with class 1 bikeway.
Fund Source Summary:
PER/W
Total 41,193,750
CON
Total
36,708,750 2,600,000 39,308,750
485,000 4,970,000
485,000 2,600,000 44,278,750
4,485,000
Phase Summary:
Fed $
Local AC
Local Match
Total23,866,581
5,107,494
41,193,750
LSSRP Bond
Total6,609,474 8,631,675 4,943,732 388,000 5,983,481 38,776,036
97,000 298,220 5,502,714
-6,609,474 -8,631,675 -4,943,732 -3,681,701485,000 2,600,000 44,278,750
12,219,675
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
1480
5166(015)5166(025)
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
897,000
4,485,000
LSSRP Bond
Total388,000 3,976,000
97,000 994,000
485,000 4,970,000
3,588,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
23,866,581
4,210,494
36,708,750
LSSRP Bond
Total6,609,474 8,631,675 4,943,732 5,983,481 34,800,036
298,220 4,508,714
-6,609,474 -8,631,675 -4,943,732 -3,681,701
2,600,000 39,308,750
8,631,675
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 383/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Marin County BRIDGE NO. 27C0016, LUCAS VALLEY ROAD OVER MILLER CREEK, 1.8 MI N OF SR 101. Replace existing 2-lane bridge with 2-lanebridge.
Fund Source Summary:
PER/W
Total
CON
Total
7,546,000
1,347,500 1,347,500
1,347,500 8,893,5007,546,0007,546,000
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,192,942 7,873,416
154,558 1,020,084
1,347,500 8,893,500
6,680,474
865,526
7,546,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4558
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,192,942 1,192,942
154,558 154,558
1,347,500 1,347,500
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total6,680,474
865,526
7,546,000
6,680,474
865,526
7,546,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 393/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Marin County BRIDGE NO. 27C0051, SAN ANTONIO RD OVER SOUTH SAN ANTONIO CREEK, 0.6 MI N OF S.H. 101. Replace existing two lane bridgewith two lane bridge. 1/3/2012: Toll Credits programmed for PE, R/W & CON.
Fund Source Summary:
PER/W
Total 821,000
CON
Total
6,539,155
389,710 1,210,710
448,500 448,500
838,210 8,198,365
821,000
6,539,1556,539,155
Phase Summary:
Fed $
Local AC
Local Match
Total 821,000
LSSRP Bond
Total838,210 8,198,365
838,210 8,198,365
821,000 6,539,155
6,539,155
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3891
5927(104)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 821,000
LSSRP Bond
Total389,710 1,210,710
389,710 1,210,710
821,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total448,500 448,500
448,500 448,500
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total6,539,155
6,539,155
6,539,155
6,539,155
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 403/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Marin County BRIDGE NO. 27C0098, NICASIO VAL RD, OVER ARROYO NICASIO, NEAR LUCAS VALLEY RD. Replace existing two-lane bridge with newtwo-lane bridge.
Fund Source Summary:
PER/W
Total 556,300
CON
Total
4,389,000
227,450 783,750
225,000 225,000
227,450 225,000 5,397,750
556,300
4,389,0004,389,000
Phase Summary:
Fed $
Local AC
Local Match
Total
63,808
556,300
LSSRP Bond
Total201,361 199,193 4,778,628
26,089 25,808 619,122
227,450 225,000 5,397,750
492,492 3,885,582
503,418
4,389,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3998
5927(097)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
63,808
556,300
LSSRP Bond
Total201,361 693,854
26,089 89,896
227,450 783,750
492,492
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total199,193 199,193
25,808 25,808
225,000 225,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,885,582
503,418
4,389,000
3,885,582
503,418
4,389,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 413/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Marin County BRIDGE NO. 27C0104, SIR FRANCIS DRAKE OVER OLEMA CREEK, 0.32 MI W SH 1. Replace existing two-lane bridge with new two-lanebridge.
Fund Source Summary:
PER/W
Total 610,000
CON
Total
2,618,000
610,000
250,000 250,000
250,000 3,478,000
610,000
2,618,0002,618,000
Phase Summary:
Fed $
Local AC
Local Match
Total
69,967
610,000
LSSRP Bond
Total221,325 3,079,073
28,675 398,927
250,000 3,478,000
540,033 2,317,715
300,285
2,618,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3996
5927(099)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
69,967
610,000
LSSRP Bond
Total540,033
69,967
610,000
540,033
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total221,325 221,325
28,675 28,675
250,000 250,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total2,317,715
300,285
2,618,000
2,317,715
300,285
2,618,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 423/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Marin County BRIDGE NO. 27C0107, MUIR WOODS RD OVER REDWOOD CREEK, 2.0 MI N OF SR 1. Replace existing two-lane bridge with newtwo-lane bridge.
Fund Source Summary:
PER/W
Total 496,079
CON
Total
1,974,500
182,921 679,000
159,485 159,485
182,921 159,485 2,812,985
496,079
1,974,5001,974,500
Phase Summary:
Fed $
Local AC
Local Match
Total
56,900
496,079
LSSRP Bond
Total161,940 141,192 2,490,336
20,981 18,293 322,649
182,921 159,485 2,812,985
439,179 1,748,025
226,475
1,974,500
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3995
5927(098)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
56,900
496,079
LSSRP Bond
Total161,940 601,119
20,981 77,881
182,921 679,000
439,179
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total141,192 141,192
18,293 18,293
159,485 159,485
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,748,025
226,475
1,974,500
1,748,025
226,475
1,974,500
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 433/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Marin County BRIDGE NO. 27C0111, MARSHALL PETALUMA RD, OVER SALMON CREEK, 3.0MI W OF HICKSVALLEY RD. Replace existing 2-lane bridgewith a 2-lane bridge.
Fund Source Summary:
PER/W
Total
CON
Total
2,818,200
503,250 503,250
503,250 3,321,4502,818,2002,818,200
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total445,527 2,940,480
57,723 380,970
503,250 3,321,450
2,494,952
323,248
2,818,200
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4557
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total445,527 445,527
57,723 57,723
503,250 503,250
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total2,494,952
323,248
2,818,200
2,494,952
323,248
2,818,200
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 443/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Marin County BRIDGE NO. 27C0135, MOUNT LASSEN DR OVER MILLER CREEK, 0.06 MI N LUCAS VALLEY RD. Bridge Preventive MaintenanceProgram project to correct soil erosion. 1/4/2012: Toll Credits programmed for PE & CON. 9/28/2015: Toll credits used for R/W.
Fund Source Summary:
PER/W
Total 350,000
CON
Total
354,200
350,000
81,252 81,252
81,252 785,452
350,000
354,200354,200
Phase Summary:
Fed $
Local AC
Local Match
Total 350,000
LSSRP Bond
Total81,252 785,452
81,252 785,452
350,000 354,200
354,200
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3892
5927(100)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 350,000
LSSRP Bond
Total350,000
350,000
350,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total81,252 81,252
81,252 81,252
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total354,200
354,200
354,200
354,200
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 453/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Novato BRIDGE NO. 27C0021, GRANT AVE OVER NOVATO CREEK, IN NOVATO. Bridge rehabilitation no additional lanes added.
Fund Source Summary:
PER/W
Total 705,424
CON
Total
3,568,320
705,424
4,273,744
705,424
3,568,3203,568,320
Phase Summary:
Fed $
Local AC
Local Match
Total
80,912
705,424
LSSRP Bond
Total3,783,546
490,198
4,273,744
624,512 3,159,034
409,286
3,568,320
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3524
5361(023)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
80,912
705,424
LSSRP Bond
Total624,512
80,912
705,424
624,512
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,159,034
409,286
3,568,320
3,159,034
409,286
3,568,320
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 463/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Ross BRIDGE NO. 27C0074, WINSHIP ROAD OVER CORTE MADERA CREEK, IN THE CITY OF ROSS. Replace existing two-lane bridge withnew two-lane bridge. 3/25/2014: Toll credits used for PE, R/W and CON.
Fund Source Summary:
PER/W
Total 655,700
CON
Total
1,613,640
100,000 755,700
60,000 60,000
160,000 2,429,340
655,700
1,613,6401,613,640
Phase Summary:
Fed $
Local AC
Local Match
Total 655,700
LSSRP Bond
Total160,000 2,429,340
160,000 2,429,340
655,700 1,613,640
1,613,640
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3997
5176(008)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 655,700
LSSRP Bond
Total100,000 755,700
100,000 755,700
655,700
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total60,000 60,000
60,000 60,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,613,640
1,613,640
1,613,640
1,613,640
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 473/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
San Anselmo BRIDGE NO. 27C0080, MADRONE AVE OVER SAN ANSELMO CR, IN SAN ANSELMO. Bridge replacement. Replace existing two lanebridge with two lane bridge widened to accommodate standard lanes, shoulders and sidewalks.
Fund Source Summary:
PER/W
Total 664,000
CON
Total
5,756,800
95,400 488,100 1,247,500
724,900 724,900
95,400 1,213,000 7,729,200
664,000
5,756,8005,756,800
Phase Summary:
Fed $
Local AC
Local Match
Total
76,161
664,000
LSSRP Bond
Total84,458 1,073,869 6,842,661
10,942 139,131 886,539
95,400 1,213,000 7,729,200
587,839 5,096,495
660,305
5,756,800
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3906
5159(018)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
76,161
664,000
LSSRP Bond
Total84,458 432,115 1,104,412
10,942 55,985 143,088
95,400 488,100 1,247,500
587,839
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total641,754 641,754
83,146 83,146
724,900 724,900
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total5,096,495
660,305
5,756,800
5,096,495
660,305
5,756,800
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 483/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
San Anselmo BRIDGE NO. 27C0100, BRIDGE AVE OVER SAN ANSELMO CREEK, 80M SW OF SIR FRANCIS DRK. Replace 2-lane bridge with 2-lanebridge.
Fund Source Summary:
PER/W
Total
CON
Total
4,760,000
833,600 833,600
833,600 5,593,6004,760,0004,760,000
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total737,986 4,952,014
95,614 641,586
833,600 5,593,600
4,214,028
545,972
4,760,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4640
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total737,986 737,986
95,614 95,614
833,600 833,600
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total4,214,028
545,972
4,760,000
4,214,028
545,972
4,760,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 493/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
San Anselmo BRIDGE NO. 27C0153, NOKOMIS AVE OVER SAN ANSELMO CREEK, 300 N MADRONE AVE. Bridge Replacement. Replace existing twolane bridge with two lane bridge to accommodate standard lanes, shoulders and sidewalks. 2/15/2012: Toll Credits programmed for PE & CON.7/15/2020: Toll credits used for R/W.
Fund Source Summary:
PER/W
Total 670,000
CON
Total
5,551,000
95,400 450,600 1,216,000
525,000 525,000
95,400 975,600 7,292,000
670,000
5,551,0005,551,000
Phase Summary:
Fed $
Local AC
Local Match
Total 670,000
LSSRP Bond
Total95,400 975,600 7,292,000
95,400 975,600 7,292,000
670,000 5,551,000
5,551,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3905
5159(017)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 670,000
LSSRP Bond
Total95,400 450,600 1,216,000
95,400 450,600 1,216,000
670,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total525,000 525,000
525,000 525,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total5,551,000
5,551,000
5,551,000
5,551,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 503/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
San Anselmo BRIDGE NO. PM00090, Bridge Preventive Maintenance Program (BPMP) various bridges in the Town of San Anselmo. See Caltrans LocalAssistance HBP website for backup list of projects.
Fund Source Summary:
PER/W
Total 637,426
CON
Total
1,136,441
637,426
1,773,867
637,426
1,136,4411,136,441
Phase Summary:
Fed $
Local AC
Local Match
Total
73,113
637,426
LSSRP Bond
Total1,570,404
-0 203,463
1,773,867
564,313 1,006,091
130,350
1,136,441
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4044
5159(022)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
73,113
637,426
LSSRP Bond
Total564,313
73,113
637,426
564,313
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,006,091
-0 130,350
1,136,441
1,006,091
130,350
1,136,441
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 513/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Marin
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
San Rafael BRIDGE NO. 27C0148, SOUTHRN HEIGHTS BL, OVER HILLSIDE, JCT MEYER RD IN SAN RAFEL. Replace existing one-lane bridge with anew one-lane bridge. 3/4/2015: Toll Credits programmed for PE, R/W, & CON.
Fund Source Summary:
PER/W
Total
180,000
675,000
CON
Total
3,560,000 3,560,000
105,000 600,000
45,000 125,000 350,000
150,000 3,685,000 4,510,000
495,000
Phase Summary:
Fed $
Local AC
Local Match
Total 675,000
LSSRP Bond
Total150,000 3,685,000 4,510,000
150,000 3,685,000 4,510,000
675,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4272
5043(038)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 495,000
LSSRP Bond
Total105,000 600,000
105,000 600,000
495,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total 180,000
LSSRP Bond
Total45,000 125,000 350,000
45,000 125,000 350,000
180,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,560,000 3,560,000
3,560,000 3,560,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 523/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Napa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Calistoga BRIDGE NO. 21C0115, BERRY ST OVER NAPA RIVER, CALISTOGA. Replace two-lane bridge with new two-lane bridge. 9/26/2012: TollCredits programmed for PE & CON. 9/27/2012: Toll credits used for R/W.
Fund Source Summary:
PER/W
Total
364,000
5,826,402
CON
Total
4,918,402 245,392 5,163,794
50,614 594,614
364,000
296,006 6,122,408
544,000
Phase Summary:
Fed $
Local AC
Local Match
Total 5,826,402
LSSRP Bond
Total296,006 6,122,408
296,006 6,122,408
5,826,402
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3986
5061(007)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 544,000
LSSRP Bond
Total50,614 594,614
50,614 594,614
544,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total 364,000
LSSRP Bond
Total364,000
364,000
364,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total 4,918,402
LSSRP Bond
Total245,392 5,163,794
245,392 5,163,794
4,918,402
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 533/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Napa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Napa BRIDGE NO. PM00111, Bridge Preventive Maintenance Program (BPMP) for various bridges in the City of Napa. See Caltrans LocalAssistance HBP website for backup list of projects.
Fund Source Summary:
PER/W
Total 40,375
CON
Total
510,221 13,926 524,147
40,375
510,221 13,926 564,522
40,375
Phase Summary:
Fed $
Local AC
Local Match
Total
4,631
40,375
LSSRP Bond
Total451,699 12,329 499,771
58,522 1,597 64,751
510,221 13,926 564,522
35,744
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4210
5042(059)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
4,631
40,375
LSSRP Bond
Total35,744
4,631
40,375
35,744
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total451,699 12,329 464,027
58,522 1,597 60,120
510,221 13,926 524,147
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 543/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Napa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Napa County BRIDGE NO. 21C0042, GREENWOOD AVE, OVER GARNETT CREEK, .2 MI NE/O MYRTLEDALE RD. Replace existing one-lane bridge withnew two-lane bridge. Toll credits used for PE. Toll credits used for CON. 9/28/2015: Toll credits used for R/W. This is not a capacityenhancing project, changed to lump sum programming.
Fund Source Summary:
PER/W
Total 1,142,282
CON
Total
5,778,920
1,142,282
200,000 200,000
200,000 7,121,202
1,142,282
5,778,9205,778,920
Phase Summary:
Fed $
Local AC
Local Match
Total 1,142,282
LSSRP Bond
Total200,000 7,121,202
200,000 7,121,202
1,142,282 5,778,920
5,778,920
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4239
5921(068)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 1,142,282
LSSRP Bond
Total1,142,282
1,142,282
1,142,282
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total200,000 200,000
200,000 200,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total5,778,920
5,778,920
5,778,920
5,778,920
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 553/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Napa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Napa County BRIDGE NO. 21C0056, DRY CR RD OVER DRY CREEK, 0.8 MI W MT VEEDER RD. Replace existing 2-lane bridge with new 2-lane bridge plus realignment of roadway. 3/6/2013: Toll Credits programmed for PE, R/W, & CON.
Fund Source Summary:
PER/W
Total 899,260
CON
Total
4,762,380
899,260
400,000 400,000
400,000 6,061,640
899,260
4,762,3804,762,380
Phase Summary:
Fed $
Local AC
Local Match
Total 899,260
LSSRP Bond
Total400,000 6,061,640
400,000 6,061,640
899,260 4,762,380
4,762,380
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4063
5921(061)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 899,260
LSSRP Bond
Total899,260
899,260
899,260
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total400,000 400,000
400,000 400,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total4,762,380
4,762,380
4,762,380
4,762,380
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 563/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Napa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Napa County BRIDGE NO. 21C0074, BERRYESSA-KNOXVLLE OVER ETICUERA CREEK, 7.8 MI N/O POPE CYN ROAD. Replace existing 2-lane bridgewith new 2-lane bridge. 3/6/2013: Toll Credits programmed for PE, R/W, & CON.
Fund Source Summary:
PER/W
Total
CON
Total
5,000,000
900,000 900,000
200,000
900,000 6,100,0005,000,000
200,000
5,200,000
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total900,000 6,100,000
900,000 6,100,000
5,200,000
5,200,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4066
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total900,000 900,000
900,000 900,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total200,000
200,000
200,000
200,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total5,000,000
5,000,000
5,000,000
5,000,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 573/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Napa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Napa County BRIDGE NO. 21C0075, CHILES-POPE VLY RD OVER CHILES CREEK, 2.1 MI N OF S.R. 128. Replace existing 2-lane bridge with new2-lane bridge.
Fund Source Summary:
PER/W
Total 842,260
CON
Total
4,477,000
842,260
150,000 150,000
150,000 5,469,260
842,260
4,477,0004,477,000
Phase Summary:
Fed $
Local AC
Local Match
Total
96,607
842,260
LSSRP Bond
Total132,795 4,841,936
17,205 627,324
150,000 5,469,260
745,653 3,963,488
513,512
4,477,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4068
5921(060)5921(074)
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
96,607
842,260
LSSRP Bond
Total745,653
96,607
842,260
745,653
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total132,795 132,795
17,205 17,205
150,000 150,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,963,488
513,512
4,477,000
3,963,488
513,512
4,477,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 583/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Napa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Napa County BRIDGE NO. 21C0077, CONN VALLEY RD OVER CONN CREEK, 4.1 MI E SILVERADO TRAIL. Replace existing 2-lane bridge with new2-lane bridge. 3/6/2013: Toll Credits programmed for PE, R/W, & CON.
Fund Source Summary:
PER/W
Total
CON
Total
5,000,000
900,000 900,000
200,000
900,000 6,100,0005,000,000
200,000
5,200,000
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total900,000 6,100,000
900,000 6,100,000
5,200,000
5,200,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4067
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total900,000 900,000
900,000 900,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total200,000
200,000
200,000
200,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total5,000,000
5,000,000
5,000,000
5,000,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 593/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Napa
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Napa County BRIDGE NO. 21C0088, SODA CYN RD OVER SODA CREEK, 3.1 MI N SILVERADO TRAIL. Replace existing 2-lane bridge with new 2-lanebridge. 3/6/2013: Toll Credits programmed for PE, R/W, & CON.
Fund Source Summary:
PER/W
Total
CON
Total
5,000,000
900,000 900,000
200,000
900,000 6,100,0005,000,000
200,000
5,200,000
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total900,000 6,100,000
900,000 6,100,000
5,200,000
5,200,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4064
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total900,000 900,000
900,000 900,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total200,000
200,000
200,000
200,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total5,000,000
5,000,000
5,000,000
5,000,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 603/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Francisco
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
San Francisco BRIDGE NO. 34C0024, THIRD STREET OVER ISLAIS CREEK, JUST N/O CARGO WAY. Rehabilitate bridge. No added lane capacity. (HighCost Project agreement required)
Fund Source Summary:
PER/W
Total 5,400,000
CON
Total
84,000,000 84,000,000
1,000,000 4,000,000 10,400,000
1,000,000 88,000,000 94,400,000
5,400,000
Phase Summary:
Fed $
Local AC
Local Match
Total
619,380
5,400,000
LSSRP Bond
Total885,300 3,541,200 83,572,320
114,700 10,093,600 10,827,680
77,906,400 -3,541,2001,000,000 88,000,000 94,400,000
4,780,620 74,365,200
-74,365,200
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4004
5934(168)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
619,380
5,400,000
LSSRP Bond
Total885,300 3,541,200 9,207,120
114,700 458,800 1,192,880
3,541,200 -3,541,200
1,000,000 4,000,000 10,400,000
4,780,620
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total74,365,200
9,634,800 9,634,800
74,365,200
84,000,000 84,000,000
74,365,200
-74,365,200
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 613/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Francisco
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
San Francisco County BRIDGE NO. 34C0025, THIRD ST OVER CHINA BASIN, S OF BERRY ST. Rehabilitate existing bridge, Work includes rehabilitating bridgedeck and corroded members, painting, counterweight and fender pile repairs. (No added lane capacity). High Cost Project agreement needed forthis project for construction to be moved into the FTIP.
Fund Source Summary:
PER/W
Total
350,000
36,214,015
CON
Total
31,040,890 31,040,890
4,823,125
350,000
36,214,015
4,823,125
Phase Summary:
Fed $
Local AC
Local Match
Total15,315,823
4,153,748
36,214,015
LSSRP Bond
Total15,315,823 32,060,267
4,153,748
-15,315,82336,214,015
16,744,445
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4282
5934(177)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
553,212
4,823,125
LSSRP Bond
Total4,269,913
553,212
4,823,125
4,269,913
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
40,145
350,000
LSSRP Bond
Total309,855
40,145
350,000
309,855
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
15,315,823
3,560,390
31,040,890
LSSRP Bond
Total15,315,823 27,480,500
3,560,390
-15,315,823
31,040,890
12,164,677
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 623/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Mateo
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Department of Parks and Recreation BRIDGE NO. PM00190, Bridge Preventive Maintenance Program (BPMP) various bridges in District 4. See Caltrans Local Assistance HBPwebsite for backup list of projects.
Fund Source Summary:
PER/W
Total
CON
Total
694,908
232,000 232,000
232,000 926,908694,908694,908
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total205,390 820,592
26,610 106,316
232,000 926,908
615,202
79,706
694,908
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4628
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total205,390 205,390
26,610 26,610
232,000 232,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total615,202
79,706
694,908
615,202
79,706
694,908
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 633/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Mateo
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Half Moon Bay BRIDGE NO. 35C0025, MAIN ST OVER PILARCITOS CREEK, 0.25 MI S/O S.H. 92. Rehabilitate existing historic bridge. No added capacity.Chien Wu, 10/12/2016 9:30:31 AM.
Fund Source Summary:
PER/W
Total 1,291,000
CON
Total
7,230,579
1,291,000
5,000 5,000
5,000 8,526,579
1,291,000
7,230,5797,230,579
Phase Summary:
Fed $
Local AC
Local Match
Total
148,078
1,291,000
LSSRP Bond
Total4,427 7,548,580
574 977,999
5,000 8,526,579
1,142,922 6,401,232
829,347
7,230,579
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4501
5357(010)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
148,078
1,291,000
LSSRP Bond
Total1,142,922
148,078
1,291,000
1,142,922
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total4,427 4,427
574 574
5,000 5,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total6,401,232
829,347
7,230,579
6,401,232
829,347
7,230,579
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 643/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Mateo
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Redwood City BRIDGE NO. 35C0074L, BRIDGE DR PARKWAY OVER MARINE WORLD LAGOON, EAST OF MARINE WORLD PKWY. PreventiveMaintenance.
Fund Source Summary:
PER/W
Total 75,000
CON
Total
518,000
20,000 95,000
20,000 613,000
75,000
518,000518,000
Phase Summary:
Fed $
Local AC
Local Match
Total
8,603
75,000
LSSRP Bond
Total17,706 542,689
2,294 70,311
20,000 613,000
66,398 458,585
59,415
518,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3617
5029(024)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
8,603
75,000
LSSRP Bond
Total17,706 84,104
2,294 10,897
20,000 95,000
66,398
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total458,585
59,415
518,000
458,585
59,415
518,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 653/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Mateo
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Redwood City BRIDGE NO. 35C0074R, BRIDGE DR PARKWAY OVER MARINE WORLD LAGOON, EAST OF MARINE WORLD PKWY. PreventiveMaintenance.
Fund Source Summary:
PER/W
Total 75,000
CON
Total
518,000
20,000 95,000
20,000 613,000
75,000
518,000518,000
Phase Summary:
Fed $
Local AC
Local Match
Total
8,603
75,000
LSSRP Bond
Total17,706 542,689
2,294 70,311
20,000 613,000
66,398 458,585
59,415
518,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3618
5029(025)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
8,603
75,000
LSSRP Bond
Total17,706 84,104
2,294 10,897
20,000 95,000
66,398
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total458,585
59,415
518,000
458,585
59,415
518,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 663/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Mateo
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Redwood City BRIDGE NO. PM00082, Bridge Preventive Maintenance Program (BPMP) various bridges in the City of Redwood City. See Caltrans LocalAssistance HBP website for backup list of projects.
Fund Source Summary:
PER/W
Total 26,250
CON
Total
78,750
26,250
105,000
26,250
78,75078,750
Phase Summary:
Fed $
Local AC
Local Match
Total
3,011
26,250
LSSRP Bond
Total92,957
12,044
105,000
23,239 69,717
9,033
78,750
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4018
5029(032)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
3,011
26,250
LSSRP Bond
Total23,239
3,011
26,250
23,239
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total69,717
9,033
78,750
69,717
9,033
78,750
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 673/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Mateo
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
San Mateo BRIDGE NO. 35C0077, BERMUDA DR, OVER FIESTA CHANNEL, SOUTH OF FIESTA DRIVE. Bridge Replacement. Replace existing two-lanebridge with a new two-lane bridge.
Fund Source Summary:
PER/W
Total 1,232,539
CON
Total
5,110,000
1,232,539
6,342,539
1,232,539
5,110,0005,110,000
Phase Summary:
Fed $
Local AC
Local Match
Total
141,372
1,232,539
LSSRP Bond
Total5,615,050
727,489
6,342,539
1,091,167 4,523,883
586,117
5,110,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3428
5102(033)5102(049)
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
141,372
1,232,539
LSSRP Bond
Total1,091,167
141,372
1,232,539
1,091,167
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total4,523,883
586,117
5,110,000
4,523,883
586,117
5,110,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 683/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Mateo
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
San Mateo County BRIDGE NO. 35C0041, CLOVERDALE RD OVER BUTANO CREEK, NORTH BUTANO PARK ROAD. Scour countermeasure and treat deckwith methacrylate, Chien Wu, 10/4/2016 1:27:52 PM. 5/7/2018: Toll Credits programmed for PE & CON.
Fund Source Summary:
PER/W
Total
CON
Total
2,731,250
150,000 75,000 225,000
50,000 50,000
150,000 125,000 3,006,2502,731,2502,731,250
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total150,000 119,265 3,000,515
5,735 5,735
150,000 125,000 3,006,250
2,731,250
2,731,250
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4469
5935(079)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total150,000 75,000 225,000
150,000 75,000 225,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total44,265 44,265
5,735 5,735
50,000 50,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total2,731,250
2,731,250
2,731,250
2,731,250
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 693/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Mateo
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
San Mateo County PM00041, Bridge Preventive Maintenance Program, various locations within the County of San Mateo. See Caltrans Local Assistance HBPwebsite for backup list of bridges.
Fund Source Summary:
PER/W
Total 873,520
CON
Total
712,500 390,920 1,103,420
161,020
390,920 1,264,440
161,020
Phase Summary:
Fed $
Local AC
Local Match
Total
100,193
873,520
LSSRP Bond
Total346,081 1,119,409
44,839 145,031
390,920 1,264,440
773,327
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3466
5935(062)5935(069)
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
18,469
161,020
LSSRP Bond
Total142,551
18,469
161,020
142,551
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
81,724
712,500
LSSRP Bond
Total346,081 976,858
44,839 126,562
390,920 1,103,420
630,776
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 703/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Mateo
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
San Mateo County BRIDGE NO. PM00067, Bridge Preventive Maintenance Program, various locations in San Mateo County. See Caltrans Local Assistance HBPweb site for backup list of bridges.
Fund Source Summary:
PER/W
Total 119,000
CON
Total
391,000
119,000
510,000
119,000
391,000391,000
Phase Summary:
Fed $
Local AC
Local Match
Total
13,649
119,000
LSSRP Bond
Total451,503
58,497
510,000
105,351 346,152
44,848
391,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3921
5935(064)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
13,649
119,000
LSSRP Bond
Total105,351
13,649
119,000
105,351
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total346,152
44,848
391,000
346,152
44,848
391,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 713/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Mateo
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
South San Francisco BRIDGE NO. 35C0148L, GRAND AVENUE WB OVER CALTRAIN UPRR INDUSTRIAL, 0.1 MI E OF US 101. Rehabilitate existing bridge.Structural steel painting and deck treatment, (no added capacity).
Fund Source Summary:
PER/W
Total
CON
Total
4,560,000
370,000 370,000
370,000 4,930,0004,560,0004,560,000
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total327,561 4,364,529
42,439 565,471
370,000 4,930,000
4,036,968
523,032
4,560,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4525
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total327,561 327,561
42,439 42,439
370,000 370,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total4,036,968
523,032
4,560,000
4,036,968
523,032
4,560,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 723/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Mateo
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
South San Francisco BRIDGE NO. 35C0148R, GRAND AVENUE WB OVER CALTRAIN UPRR INDUSTRIAL, 0.1 MI E OF US 101. Rehabilitate existing bridge -Structural steel painting and deck treatment (no added capacity).
Fund Source Summary:
PER/W
Total
CON
Total
3,960,000
370,000 370,000
370,000 4,330,0003,960,0003,960,000
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total327,561 3,833,349
42,439 496,651
370,000 4,330,000
3,505,788
454,212
3,960,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4526
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total327,561 327,561
42,439 42,439
370,000 370,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,505,788
454,212
3,960,000
3,505,788
454,212
3,960,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 733/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Mateo
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
South San Francisco BRIDGE NO. PM00153, Bridge Preventive Maintenance Program (BPMP) various bridges in the City of South San Francisco. See CaltransLocal Assistance HBP website for backup list of projects.
Fund Source Summary:
PER/W
Total
CON
Total
366,000
130,000 22,500 152,500
130,000 22,500 518,500366,000366,000
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total115,089 19,919 459,028
14,911 2,581 59,472
130,000 22,500 518,500
324,020
41,980
366,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4459
5177(039)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total115,089 19,919 135,008
14,911 2,581 17,492
130,000 22,500 152,500
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total324,020
41,980
366,000
324,020
41,980
366,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 743/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Mateo
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Woodside BRIDGE NO. 35C0055, PORTOLA RD OVER ALEMBIQUE CR, 0.25 MI E OF SH 84. Replace existing two lane bridge with two lane bridge toaccommodate standard lanes and shoulders.
Fund Source Summary:
PER/W
Total 570,136
CON
Total
1,835,000 1,835,000
51,864 622,000
1,835,000 51,864 2,457,000
570,136
Phase Summary:
Fed $
Local AC
Local Match
Total
65,395
570,136
LSSRP Bond
Total45,915 2,175,182
210,475 5,949 281,818
1,624,5261,835,000 51,864 2,457,000
504,741 1,624,526
-1,624,526
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3790
5333(012)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
65,395
570,136
LSSRP Bond
Total45,915 550,657
5,949 71,343
51,864 622,000
504,741
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
TotalPrior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,624,526
210,475 210,475
1,624,526
1,835,000 1,835,000
1,624,526
-1,624,526
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 753/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Mateo
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Woodside BRIDGE NO. 35C0122, MOUNTAIN HOME RD OVER BEAR CREEK, 0.3 MI S OF S.H. 84. Rehabilitate bridge, widen to accommodatestandard lanes and shoulders. No added lane capacity.
Fund Source Summary:
PER/W
Total 107,428
CON
Total
696,004
200,000 307,428
25,000 25,000
225,000 1,028,432
107,428
696,004696,004
Phase Summary:
Fed $
Local AC
Local Match
Total
12,322
107,428
LSSRP Bond
Total199,193 910,471
25,808 117,961
225,000 1,028,432
95,106 616,172
79,832
696,004
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3793
5333(013)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
12,322
107,428
LSSRP Bond
Total177,060 272,166
22,940 35,262
200,000 307,428
95,106
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total22,133 22,133
2,868 2,868
25,000 25,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total616,172
79,832
696,004
616,172
79,832
696,004
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 763/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Mateo
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Woodside BRIDGE NO. 35C0123, KINGS MOUNTAIN RD OVER WEST UNION CREEK, 0.05 MI E TRIPP RD. Rehabilitate bridge, widen toaccommodate standard lanes, shoulders and bike lane. No added lane capacity
Fund Source Summary:
PER/W
Total 135,090
CON
Total
831,290
200,000 335,090
25,000 25,000
225,000 1,191,380
135,090
831,290831,290
Phase Summary:
Fed $
Local AC
Local Match
Total
15,495
135,090
LSSRP Bond
Total199,193 1,054,729
25,808 136,651
225,000 1,191,380
119,595 735,941
95,349
831,290
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3791
5333(014)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
15,495
135,090
LSSRP Bond
Total177,060 296,655
22,940 38,435
200,000 335,090
119,595
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total22,133 22,133
2,868 2,868
25,000 25,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total735,941
95,349
831,290
735,941
95,349
831,290
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 773/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 San Mateo
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Woodside BRIDGE NO. 35C0190, OLD LA HONDA ROAD OVER DRAINAGE SWALE, 0.1 MI. W. OF PORTOLA RD.Bridge rehabilitation. Rehabilitate existing bridge to function as a culvert (no added capacity.)
Fund Source Summary:
PER/W
Total 305,445
CON
Total
817,700 262,192 1,079,892
125,555 431,000
817,700 125,555 262,192 1,510,892
305,445
Phase Summary:
Fed $
Local AC
Local Match
Total
35,035
305,445
LSSRP Bond
Total111,154 956,028 1,337,593
93,790 14,401 30,073 173,299
723,910 -723,910817,700 125,555 262,192 1,510,892
270,410
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4291
5333(017)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
35,035
305,445
LSSRP Bond
Total111,154 381,564
14,401 49,436
125,555 431,000
270,410
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
-0
LSSRP Bond
Total
-0
-0
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total956,028 956,028
93,790 0 30,073 123,864
723,910 -723,910
817,700 262,192 1,079,892
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 783/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Cupertino BRIDGE NO. 37C0011, STEVENS CR BLVD OVER STEVENS CREEK, 0.2 MI E/O STEVENS CYN RD. Scour Countermeasures.
Fund Source Summary:
PER/W
Total
CON
Total
630,000
230,000 230,000
230,000 860,000630,000630,000
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total203,619 761,358
26,381 98,642
230,000 860,000
557,739
72,261
630,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4563
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total203,619 203,619
26,381 26,381
230,000 230,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total557,739
72,261
630,000
557,739
72,261
630,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 793/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Cupertino BRIDGE NO. PM00132, Bridge Preventive Maintenance Program (BPMP), various bridges in the City of Cupertino. See Caltrans LocalAssistance HBP web site for backup list of bridges.
Fund Source Summary:
PER/W
Total 161,500
CON
Total
1,292,750
161,500
1,454,250
161,500
1,292,7501,292,750
Phase Summary:
Fed $
Local AC
Local Match
Total
18,524
161,500
LSSRP Bond
Total1,287,448
166,802
1,454,250
142,976 1,144,472
148,278
1,292,750
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4309
5318(029)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
18,524
161,500
LSSRP Bond
Total142,976
18,524
161,500
142,976
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,144,472
148,278
1,292,750
1,144,472
148,278
1,292,750
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 803/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Gilroy BRIDGE NO. PM00109, Bridge Preventive Maintenance Program (BPMP) for various bridges in the City of Gilroy. See Caltrans LocalAssistance HBP website for backup list of projects.
Fund Source Summary:
PER/W
Total
CON
Total
227,909 110,000 337,909227,909 110,000 337,909
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total201,768 97,383 299,151
26,141 12,617 38,758
227,909 110,000 337,909
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4200
5034(026)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
TotalPrior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total201,768 97,383 299,151
26,141 12,617 38,758
227,909 110,000 337,909
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 813/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Palo Alto BRIDGE NO. 37C0223, NEWELL RD OVER SAN FRANCISQUITO CR, NEAR WOODLAND AVE. Replace existing two-lane bridge with anew two-lane bridge conforming to current standards.
Fund Source Summary:
PER/W
Total 1,174,809
CON
Total
9,986,645
574,146 1,748,955
113,000 113,000
687,146 11,848,600
1,174,809
9,986,6459,986,645
Phase Summary:
Fed $
Local AC
Local Match
Total
134,751
1,174,809
LSSRP Bond
Total608,330 10,489,566
78,816 1,359,034
687,146 11,848,600
1,040,058 8,841,177
1,145,468
9,986,645
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3722
5100(017)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
134,751
1,174,809
LSSRP Bond
Total508,291 1,548,350
65,855 200,605
574,146 1,748,955
1,040,058
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total100,039 100,039
12,961 12,961
113,000 113,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
0
LSSRP Bond
Total8,841,177
1,145,468
9,986,645
8,841,177
1,145,468
9,986,645
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 823/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
San Jose BRIDGE NO. 37C0033, SANTA CLARA ST, OVER COYOTE CREEK, 0.8 MI W OF SH 101. Replace existing 4 lane bridge with new 4 lanebridge
Fund Source Summary:
PER/W
Total 885,000
CON
Total
4,424,000 4,424,000
885,000
4,424,000 5,309,000
885,000
Phase Summary:
Fed $
Local AC
Local Match
Total
101,510
885,000
LSSRP Bond
Total4,700,058
507,433 608,942
3,916,5674,424,000 5,309,000
783,491 3,916,567
-3,916,567
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3330
5005(089)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
101,510
885,000
LSSRP Bond
Total783,491
101,510
885,000
783,491
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,916,567
507,433 507,433
3,916,567
4,424,000 4,424,000
3,916,567
-3,916,567
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 833/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
San Jose BRIDGE NO. 37C0757, NOBEL AVE, OVER PENITENCIA CREEK, PENITENCIA CREEK RD. Replace existing 2 lane bridge with new 2 lanebridge 4/5/2010: Toll Credits programmed for PE & Con.
Fund Source Summary:
PER/W
Total
CON
Total
1,856,250
450,000 450,000
450,000 2,306,2501,856,2501,856,250
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total450,000 2,306,250
450,000 2,306,250
1,856,250
1,856,250
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3429
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total450,000 450,000
450,000 450,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,856,250
1,856,250
1,856,250
1,856,250
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 843/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Santa Clara County BRIDGE NO. 37C0094, UVAS RD, OVER UVAS CREEK, 0.6 MI S/O CROY RD. Replace 2 lane bridge with new 2 lane bridge.
Fund Source Summary:
PER/W
Total
60,000
1,160,000
CON
Total
6,057,000
500,000 1,600,000
440,000 500,000
940,000 8,157,000
1,100,000
6,057,0006,057,000
Phase Summary:
Fed $
Local AC
Local Match
Total
133,052
1,160,000
LSSRP Bond
Total832,182 7,221,392
107,818 935,608
940,000 8,157,000
1,026,948 5,362,262
694,738
6,057,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
1710
5937(123)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
126,170
1,100,000
LSSRP Bond
Total442,650 1,416,480
57,350 183,520
500,000 1,600,000
973,830
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
6,882
60,000
LSSRP Bond
Total389,532 442,650
50,468 57,350
440,000 500,000
53,118
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total5,362,262
694,738
6,057,000
5,362,262
694,738
6,057,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 853/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Santa Clara County BRIDGE NO. 37C0095, UVAS RD, OVER LITTLE UVAS CREEK, 0.2 MI N/O CROY RD. Replace 2 lane bridge with new 2 lane bridge.
Fund Source Summary:
PER/W
Total
40,000
2,315,000
CON
Total
9,054,602
2,275,000
410,000 450,000
410,000 11,779,602
2,275,000
9,054,6029,054,602
Phase Summary:
Fed $
Local AC
Local Match
Total
265,531
2,315,000
LSSRP Bond
Total362,973 10,428,482
47,027 1,351,120
410,000 11,779,602
2,049,470 8,016,039
1,038,563
9,054,602
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
1711
5937(124)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
260,943
2,275,000
LSSRP Bond
Total2,014,058
260,943
2,275,000
2,014,058
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
4,588
40,000
LSSRP Bond
Total362,973 398,385
47,027 51,615
410,000 450,000
35,412
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total8,016,039
1,038,563
9,054,602
8,016,039
1,038,563
9,054,602
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 863/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Santa Clara County BRIDGE NO. 37C0096, UVAS RD, OVER LLAGAS CREEK, 1.0 MI N/O OAK GLEN AV. Replace 2 lane bridge with new 2 lane bridge.
Fund Source Summary:
PER/W
Total
300,000
1,740,000
CON
Total
6,986,676
260,000 1,700,000
200,000 500,000
460,000 9,186,676
1,440,000
6,986,6766,986,676
Phase Summary:
Fed $
Local AC
Local Match
Total
199,578
1,740,000
LSSRP Bond
Total407,238 8,132,964
52,762 1,053,712
460,000 9,186,676
1,540,422 6,185,304
801,372
6,986,676
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
1709
5937(106)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
165,168
1,440,000
LSSRP Bond
Total230,178 1,505,010
29,822 194,990
260,000 1,700,000
1,274,832
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
34,410
300,000
LSSRP Bond
Total177,060 442,650
22,940 57,350
200,000 500,000
265,590
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total6,185,304
801,372
6,986,676
6,185,304
801,372
6,986,676
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 873/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Santa Clara County BRIDGE NO. 37C0159, ALAMITOS RD, OVER ALAMITOS CREEK, 0.8 MI S OF ALMADEN. Replace 2 lane bridge with new 2 lane bridge. 4/5/2010: Toll Credits programmed for R/W & Con.
Fund Source Summary:
PER/W
Total 1,053,596
CON
Total
9,000,000 9,000,000
1,053,596
9,000,000 10,053,596
1,053,596
Phase Summary:
Fed $
Local AC
Local Match
Total
210,719
1,053,596
LSSRP Bond
Total9,000,000 9,842,877
210,719
9,000,000 -9,000,0009,000,000 10,053,596
842,877
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
1221
5937(058)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
210,719
1,053,596
LSSRP Bond
Total842,877
210,719
1,053,596
842,877
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
TotalPrior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total9,000,000 9,000,000
9,000,000 -9,000,000
9,000,000 9,000,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 883/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Santa Clara County BRIDGE NO. 37C0172, NEW AVE, OVER RED FOX CREEK, 1.6 MI N LEAVESLY ROAD. Bridge Replacement 4/5/2010: Toll Creditsprogrammed for PE & Con. 10/3/2011: Toll credits used for R/W. Replace two-lane with two-lane bridge.
Fund Source Summary:
PER/W
Total 500,000
CON
Total
4,749,196
600,000 1,100,000
80,000 420,000 500,000
80,000 1,020,000 6,349,196
500,000
4,749,1964,749,196
Phase Summary:
Fed $
Local AC
Local Match
Total 500,000
LSSRP Bond
Total1,100,000 6,349,196
80,000 -80,00080,000 1,020,000 6,349,196
500,000 4,749,196
4,749,196
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
189
5937(182)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 500,000
LSSRP Bond
Total600,000 1,100,000
600,000 1,100,000
500,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total500,000 500,000
80,000 -80,000
80,000 420,000 500,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total4,749,196
4,749,196
4,749,196
4,749,196
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 893/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Santa Clara County BRIDGE NO. 37C0501, ALAMITOS RD OVER HERBERT CREEK, 0.7 MI W OF HICKS RD. Replace existing one-lane bridge with a newtwo-lane bridge (non-capacity increasing), 9/28/2015: Toll Credits programmed for PE, R/W, & CON.
Fund Source Summary:
PER/W
Total 580,000
CON
Total
3,500,000
200,000 780,000
300,000 300,000
200,000 300,000 4,580,000
580,000
3,500,0003,500,000
Phase Summary:
Fed $
Local AC
Local Match
Total 580,000
LSSRP Bond
Total200,000 300,000 4,580,000
200,000 300,000 4,580,000
580,000 3,500,000
3,500,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4300
5937(210)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 580,000
LSSRP Bond
Total200,000 780,000
200,000 780,000
580,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total300,000 300,000
300,000 300,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,500,000
3,500,000
3,500,000
3,500,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 903/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Santa Clara County BRIDGE NO. 37C0502, ALAMITOS RD OVER HERBERT CREEK, 0.9 MI SW OF JCT HICKS RD. Replace existing one-lane bridge with anew two-lane bridge.(non capacity increasing) 10/20/2015: Toll Credits programmed for PE, R/W, & CON.
Fund Source Summary:
PER/W
Total 539,825
CON
Total
3,500,000
200,000 739,825
300,000 300,000
200,000 300,000 4,539,825
539,825
3,500,0003,500,000
Phase Summary:
Fed $
Local AC
Local Match
Total 539,825
LSSRP Bond
Total200,000 300,000 4,539,825
200,000 300,000 4,539,825
539,825 3,500,000
3,500,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4280
5937(211)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 539,825
LSSRP Bond
Total200,000 739,825
200,000 739,825
539,825
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total300,000 300,000
300,000 300,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,500,000
3,500,000
3,500,000
3,500,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 913/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Santa Clara County BRIDGE NO. 37C0503, ALAMITOS RD OVER HERBERT CREEK, 1.1 MI SW JET OF HICK RD. Replace existing one-lane bridge with a newtwo-lane bridge, (not capacity increasing) 10/20/2015: Toll Credits programmed for PE, R/W, & CON.
Fund Source Summary:
PER/W
Total 541,825
CON
Total
3,500,000
200,000 741,825
300,000 300,000
200,000 300,000 4,541,825
541,825
3,500,0003,500,000
Phase Summary:
Fed $
Local AC
Local Match
Total 541,825
LSSRP Bond
Total200,000 300,000 4,541,825
200,000 300,000 4,541,825
541,825 3,500,000
3,500,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4281
5937(212)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 541,825
LSSRP Bond
Total200,000 741,825
200,000 741,825
541,825
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total300,000 300,000
300,000 300,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,500,000
3,500,000
3,500,000
3,500,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 923/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Santa Clara County BRIDGE NO. 37C0506, ALDERCROFT HTS RD OVER HOOKER CREEK, 2.12 MI S LOS GATOS SC RD. Replace existing one-lane bridgewith a new two-lane bridge, (not capacity increasing) 10/20/2015: Toll Credits programmed for PE, R/W, & CON.
Fund Source Summary:
PER/W
Total 600,000
CON
Total
3,181,000
200,000 800,000
300,000 300,000
500,000 4,281,000
600,000
3,181,0003,181,000
Phase Summary:
Fed $
Local AC
Local Match
Total 600,000
LSSRP Bond
Total500,000 4,281,000
500,000 4,281,000
600,000 3,181,000
3,181,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4277
5937(205)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 600,000
LSSRP Bond
Total200,000 800,000
200,000 800,000
600,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total300,000 300,000
300,000 300,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,181,000
3,181,000
3,181,000
3,181,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 933/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Santa Clara County BRIDGE NO. 37C0507, ALDERCROFT HTS RD OVER LOS GATOS CREEK, 2.12 MI S LOS GATOS SC RD. Replace existing one-lane bridgeto a new two-lane bridge,(not capacity increasing) 10/20/2015: Toll Credits programmed for PE, R/W, & CON.
Fund Source Summary:
PER/W
Total 600,000
CON
Total
3,645,000
200,000 800,000
300,000 300,000
500,000 4,745,000
600,000
3,645,0003,645,000
Phase Summary:
Fed $
Local AC
Local Match
Total 600,000
LSSRP Bond
Total500,000 4,745,000
500,000 4,745,000
600,000 3,645,000
3,645,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4276
5937(206)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 600,000
LSSRP Bond
Total200,000 800,000
200,000 800,000
600,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total300,000 300,000
300,000 300,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,645,000
3,645,000
3,645,000
3,645,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 943/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Santa Clara County BRIDGE NO. 37C0508, ALDERCROFT HTS RD OVER LOS GATOS CREEK, 2.38 MI S LOS GATOS SC RD. Replace existing one-lanebridge with a new two-lane bridge, (not capacity increasing) 10/20/2015: Toll Credits programmed for PE, R/W, & CON.
Fund Source Summary:
PER/W
Total 600,000
CON
Total
4,000,000
200,000 800,000
300,000 300,000
500,000 5,100,000
600,000
4,000,0004,000,000
Phase Summary:
Fed $
Local AC
Local Match
Total 600,000
LSSRP Bond
Total500,000 5,100,000
500,000 5,100,000
600,000 4,000,000
4,000,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4275
5937(207)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 600,000
LSSRP Bond
Total200,000 800,000
200,000 800,000
600,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total300,000 300,000
300,000 300,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total4,000,000
4,000,000
4,000,000
4,000,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 953/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Santa Clara County BRIDGE NO. 37C0574, STEVENS CYN RD, OVER STEVENS CREEK, 2.5 MI SW/O MT EDEN RD. Replace 2 lane bridge with new 2 lanebridge. 4/1/2010: Toll Credits programmed for R/W, & Con.
Fund Source Summary:
PER/W
Total 3,159,600
CON
Total
2,559,600 213,358 2,772,958
600,000
213,358 3,372,958
600,000
Phase Summary:
Fed $
Local AC
Local Match
Total
68,820
3,159,600
LSSRP Bond
Total213,358 3,304,138
68,820
213,358 3,372,958
3,090,780
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
1378
5937(107)5937(208)
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
68,820
600,000
LSSRP Bond
Total531,180
68,820
600,000
531,180
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
TotalPrior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total 2,559,600
LSSRP Bond
Total213,358 2,772,958
213,358 2,772,958
2,559,600
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 963/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Santa Clara County BRIDGE NO. 37C0575, STEVENS CYN RD, OVER STEVENS CREEK, 2.7 MI SW/O MT EDEN RD. Replace 2 lane bridge with new 2 lanebridge. 4/1/2010: Toll Credits programmed for R/W, & Con.
Fund Source Summary:
PER/W
Total 3,571,000
CON
Total
2,971,000 141,347 3,112,347
600,000
141,347 3,712,347
600,000
Phase Summary:
Fed $
Local AC
Local Match
Total
68,820
3,571,000
LSSRP Bond
Total141,347 3,643,527
68,820
141,347 3,712,347
3,502,180
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
1377
5937(109)5937(209)
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
68,820
600,000
LSSRP Bond
Total531,180
68,820
600,000
531,180
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
TotalPrior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total 2,971,000
LSSRP Bond
Total141,347 3,112,347
141,347 3,112,347
2,971,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 973/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Saratoga BRIDGE NO. 37C0114 & 37C0113, QUITO RD, OVER SAN TOMAS CREEK, NORTH AND SOUTH OF OLD ADOBE RD. Replace 2 lanebridges with new 2 lane bridges.
Fund Source Summary:
PER/W
Total
400,000
1,239,500
CON
Total
4,790,000
839,500
400,000
6,029,500
839,500
4,790,0004,790,000
Phase Summary:
Fed $
Local AC
Local Match
Total
213,780
1,239,500
LSSRP Bond
Total5,266,307
763,193
6,029,500
1,025,720 4,240,587
549,413
4,790,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
932
5332(004)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
167,900
839,500
LSSRP Bond
Total671,600
167,900
839,500
671,600
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
45,880
400,000
LSSRP Bond
Total354,120
45,880
400,000
354,120
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total4,240,587
549,413
4,790,000
4,240,587
549,413
4,790,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 983/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Saratoga BRIDGE NO. 37C0294, 4TH ST, OVER SARATOGA CREEK, NEAR BASIN WAY. Replace deck, railings, widen lanes & shoulders, newsidewalks. No added lane capacity.
Fund Source Summary:
PER/W
Total 105,000
CON
Total
435,000
350,000 455,000
10,000 10,000
360,000 900,000
105,000
435,000435,000
Phase Summary:
Fed $
Local AC
Local Match
Total
12,044
105,000
LSSRP Bond
Total318,708 796,770
41,292 103,230
360,000 900,000
92,957 385,106
49,895
435,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
1793
5332(020)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
12,044
105,000
LSSRP Bond
Total309,855 402,812
40,145 52,189
350,000 455,000
92,957
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total8,853 8,853
1,147 1,147
10,000 10,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total385,106
49,895
435,000
385,106
49,895
435,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 993/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Santa Clara
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Sunnyvale BRIDGE NO. 37C0765, FAIROAKS AVE, OVER CALTRAIN,UP RR, HENDY AVE. Bridge rehabilitation. No adding lane capacity.
Fund Source Summary:
PER/W
Total
1,985,000
4,926,000
CON
Total
17,365,000 5,706,436 23,071,436
2,941,000
1,339,505 3,324,505
18,704,505 5,706,436 29,336,941
2,941,000
Phase Summary:
Fed $
Local AC
Local Match
Total
565,012
4,926,000
LSSRP Bond
Total16,559,098 5,051,908 25,971,994
2,145,407 654,528 3,364,947
16,559,098 -16,559,09818,704,505 5,706,436 29,336,941
4,360,988
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3262
5213(039)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
337,333
2,941,000
LSSRP Bond
Total2,603,667
337,333
2,941,000
2,603,667
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
227,680
1,985,000
LSSRP Bond
Total1,185,864 2,943,184
153,641 381,321
1,185,864 -1,185,864
1,339,505 3,324,505
1,757,321
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total15,373,235 5,051,908 20,425,142
1,991,766 0 2,646,294
15,373,235 -15,373,235
17,365,000 0 23,071,436
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1003/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
654,528
5,051,9085,706,436
-5,051,908
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Solano
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Solano County BRIDGE NO. 23C0092, STEVENSON BR RD, OVER PUTAH CREEK, SOL/YOL CO LINE. Bridge rehabilitation. No adding lane capacity.
Fund Source Summary:
PER/W
Total
500,000
1,800,000
CON
Total
6,372,000
428,000 1,728,000
500,000
428,000 8,600,000
1,300,000
6,372,0006,372,000
Phase Summary:
Fed $
Local AC
Local Match
Total
317,350
1,800,000
LSSRP Bond
Total342,400 7,466,182
85,600 1,133,818
428,000 8,600,000
1,482,650 5,641,132
730,868
6,372,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
1498
5923(059)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
260,000
1,300,000
LSSRP Bond
Total342,400 1,382,400
85,600 345,600
428,000 1,728,000
1,040,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
57,350
500,000
LSSRP Bond
Total442,650
57,350
500,000
442,650
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total5,641,132
730,868
6,372,000
5,641,132
730,868
6,372,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1013/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Solano
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Solano County BRIDGE NO. 23C0118, MAIN PRAIRIE RD OVER ULATIS CREEK, 0.3 MI E OF RTE 113. Replace existing 2-lane bridge with a new 2-lanebridge. Chien Wu, 3/3/2017 10:09:01 AM.
Fund Source Summary:
PER/W
Total
CON
Total
3,873,800
691,750 691,750
100,000
691,750 4,665,5503,873,800
100,000
3,973,800
Phase Summary:
Fed $
Local AC
Local Match
Total
LSSRP Bond
Total612,406 4,130,411
79,344 535,139
691,750 4,665,550
3,518,005
455,795
3,973,800
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4524
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total612,406 612,406
79,344 79,344
691,750 691,750
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total88,530
11,470
100,000
88,530
11,470
100,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,429,475
444,325
3,873,800
3,429,475
444,325
3,873,800
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1023/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Solano
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Vacaville BRIDGE NO. 23C0011, BUCK AVE OVER ALAMO CREEK, 0.1 MI E OF ALAMO AVE. Replace existing two-lane bridge with a new two-lanebridge.
Fund Source Summary:
PER/W
Total 716,512
CON
Total
3,926,000 3,939,700
13,560 89,928 820,000
20,000 101,001 15,999 137,000
20,000 4,040,561 105,927 4,896,700
716,512
13,70013,700
Phase Summary:
Fed $
Local AC
Local Match
Total
82,184
716,512
LSSRP Bond
Total17,706 101,421 93,777 3,475,688 4,335,049
2,294 463,452 12,150 561,651
3,475,688 -3,475,68820,000 4,040,561 105,927 4,896,700
634,328 12,129
1,571
13,700
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3944
5094(057)5094(066)
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
82,184
716,512
LSSRP Bond
Total12,005 79,613 725,946
1,555 10,315 94,054
13,560 89,928 820,000
634,328
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total17,706 89,416 14,164 121,286
2,294 11,585 1,835 15,714
20,000 101,001 15,999 137,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
0
LSSRP Bond
Total3,475,688 3,487,816
450,312 451,884
3,475,688 -3,475,688
3,926,000 3,939,700
12,129
1,571
13,700
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1033/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Solano
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Vacaville BRIDGE NO. 23C0236, ALDRIDGE RD OVER PUTAH SOUTH CANAL, 500 W EUBANKS DR . 10/22/2015: Replace existing 2-lane bridge with new 2-lane bridge. No added capacity. 5/9/2012: Toll Credits programmed for PE, R/W, &CON.
Fund Source Summary:
PER/W
Total 671,812
CON
Total
2,932,200
58,188 730,000
30,000 165,000 195,000
30,000 223,188 3,857,200
671,812
2,932,2002,932,200
Phase Summary:
Fed $
Local AC
Local Match
Total 671,812
LSSRP Bond
Total30,000 223,188 3,857,200
30,000 223,188 3,857,200
671,812 2,932,200
2,932,200
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3943
5094(058)5094(065)
Project #:
PE Summary:Fed $
Local AC
Local Match
Total 671,812
LSSRP Bond
Total58,188 730,000
58,188 730,000
671,812
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total30,000 165,000 195,000
30,000 165,000 195,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total2,932,200
2,932,200
2,932,200
2,932,200
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1043/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Solano
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Vallejo BRIDGE NO. 23C0152, SACRAMENTO ST, OVER US NAVY RR, BTWN ILLINOIS FARRAGUT ST. Scope changed to replacement. Replaceexisting two-lane bridge with a new two-lane bridge. No added lane capacity. Seismic funds used for portion of the project.
Fund Source Summary:
PER/W
Total
380,000
1,369,000
CON
Total
8,087,000 2,235,924 10,322,924
159,000 1,148,000
175,000 555,000
334,000 8,087,000 2,235,924 12,025,924
989,000
Phase Summary:
Fed $
Local AC
Local Match
Total
157,024
1,369,000
LSSRP Bond
Total
218,504 218,504
295,690 7,159,421 1,979,464 10,646,551
38,310 709,075 256,460 1,160,870
334,000 8,087,000 2,235,924 12,025,924
1,211,976
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
2041
5030(056)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
113,438
989,000
LSSRP Bond
Total140,763 1,016,324
18,237 131,676
159,000 1,148,000
875,562
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
43,586
380,000
LSSRP Bond
Total154,928 491,342
20,073 63,659
175,000 555,000
336,414
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
218,504 218,504
7,159,421 1,979,464 9,138,885
709,075 256,460 965,536
8,087,000 2,235,924 10,322,924
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1053/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Solano
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Vallejo BRIDGE NO. 23C0248, G STREET, OVER NAPA RIVER, 1 MILE WEST OF SR 29. Bridge Preventive Maintenance (Painting, applyingMethacrylate, piles and boards of fender system repairs, replacing anodes at Piers 26 and 27).
Fund Source Summary:
PER/W
Total 494,280
CON
Total
12,341,000
701,720 1,196,000
701,720 13,537,000
494,280
12,341,00012,341,000
Phase Summary:
Fed $
Local AC
Local Match
Total
56,694
494,280
LSSRP Bond
Total621,233 11,984,306
80,487 1,552,694
701,720 13,537,000
437,586 10,925,487
1,415,513
12,341,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4240
5030(060)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
56,694
494,280
LSSRP Bond
Total621,233 1,058,819
80,487 137,181
701,720 1,196,000
437,586
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total10,925,487
1,415,513
12,341,000
10,925,487
1,415,513
12,341,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1063/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Petaluma BRIDGE NO. 20C0045, WASHINGTON ST OVER PETALUMA RIVER, NEAR DOWNTOWN PETALUMA. Voluntary seismic retrofit project.
Fund Source Summary:
PER/W
Total 250,000
CON
Total
1,680,000
80,000 546,000 876,000
80,000 546,000 2,556,000
250,000
1,680,0001,680,000
Phase Summary:
Fed $
Local AC
Local Match
Total
28,675
250,000
LSSRP Bond
Total70,824 483,374 2,262,827
9,176 62,626 293,173
80,000 546,000 2,556,000
221,325 1,487,304
192,696
1,680,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3570
5022(050)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
28,675
250,000
LSSRP Bond
Total70,824 483,374 775,523
9,176 62,626 100,477
80,000 546,000 876,000
221,325
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,487,304
192,696
1,680,000
1,487,304
192,696
1,680,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1073/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Sonoma BRIDGE NO. 20C0497, CHASE ST OVER NATHANSON CREEK, 0.1 MI E SR 12 SONOMA. Replace existing two lane bridge with two lanebridge widened to accommodate shoulders and sidewalks.
Fund Source Summary:
PER/W
Total
90,000
501,079
CON
Total
1,809,266 1,809,266
411,079
90,000
1,809,266 2,310,345
411,079
Phase Summary:
Fed $
Local AC
Local Match
Total
57,474
501,079
LSSRP Bond
Total1,601,743 2,045,348
207,523 264,997
1,809,266 2,310,345
443,605
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3643
5114(016)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
47,151
411,079
LSSRP Bond
Total363,928
47,151
411,079
363,928
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
10,323
90,000
LSSRP Bond
Total79,677
10,323
90,000
79,677
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total1,601,743 1,601,743
207,523 207,523
1,809,266 1,809,266
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1083/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Sonoma County BRIDGE NO. 20C0005, GEYSERS RD, OVER BIG SULPHUR CREEK, 18.6 MI N OF SH 128. Replace 1 lane bridge with 2 lane bridge.(LSSRP Seismic) 10/11/2011: Toll credits used for R/W. Toll credits used for CON.
Fund Source Summary:
PER/W
Total 1,208,387
CON
Total
6,766,964
442,000 1,650,387
150,000 150,000
592,000 8,567,351
1,208,387
6,766,9646,766,964
Phase Summary:
Fed $
Local AC
Local Match
Total
138,602
1,208,387
LSSRP Bond
Total541,303 8,378,052
50,697 189,299
592,000 8,567,351
1,069,785 6,766,964
6,766,964
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
1993
5920(111)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
138,602
1,208,387
LSSRP Bond
Total391,303 1,461,088
50,697 189,299
442,000 1,650,387
1,069,785
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total150,000 150,000
150,000 150,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total6,766,964
6,766,964
6,766,964
6,766,964
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1093/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Sonoma County BRIDGE NO. 20C0017, WATMAUGH ROAD, OVER SONOMA CREEK, 0.3 MI W HWY 12. Replace 2 lane bridge with new 2 lane bridge.(minor seismic contribution)
Fund Source Summary:
PER/W
Total 900,000
CON
Total
6,812,000
567,000 200,000 1,667,000
250,000 150,000 400,000
817,000 350,000 8,879,000
900,000
6,812,0006,812,000
Phase Summary:
Fed $
Local AC
Local Match
Total
103,230
900,000
LSSRP Bond
Total
50,529
501,965 531,180 7,860,579
93,710 40,145 967,893
221,325 -221,325817,000 350,000 8,879,000
796,770
50,529
6,030,664
730,808
6,812,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
1160
5920(092)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
103,230
900,000
LSSRP Bond
Total501,965 177,060 1,475,795
65,035 22,940 191,205
567,000 200,000 1,667,000
796,770
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
0
LSSRP Bond
Total354,120 354,120
28,675 17,205 45,880
221,325 -221,325
250,000 150,000 400,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
50,529
6,030,664
730,808
6,812,000
50,529
6,030,664
730,808
6,812,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1103/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Sonoma County BRIDGE NO. 20C0018, BOHEMIAN HWY, OVER RUSSIAN RIVER, AT MONTE RIO. Replace the two lane bridge with a new two lane bridgeas LSSRP Seismic Retrofit strategy.
Fund Source Summary:
PER/W
Total 2,977,500
CON
Total
16,674,000
1,000,000 3,977,500
400,000 400,000
1,000,000 400,000 21,051,500
2,977,500
16,674,00016,674,000
Phase Summary:
Fed $
Local AC
Local Match
Total
341,519
2,977,500
LSSRP Bond
Total
45,880 1,958,388
885,300 354,120 18,636,893
114,700 456,219
1,000,000 400,000 21,051,500
2,635,981
1,912,508
14,761,492
16,674,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
1999
5920(135)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
341,519
2,977,500
LSSRP Bond
Total885,300 3,521,281
114,700 456,219
1,000,000 3,977,500
2,635,981
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
45,880 45,880
354,120 354,120
400,000 400,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
1,912,508
14,761,492
16,674,000
1,912,508
14,761,492
16,674,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1113/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Sonoma County BRIDGE NO. 20C0139, WOHLER RD, OVER MARK WEST CREEK, NEAR RIVER RD. Bridge Replacement, no added lane capacity 4/5/2010:Toll Credits programmed for R/W & Con. LSSRP
Fund Source Summary:
PER/W
Total
100,000
865,000
CON
Total
6,659,000 6,659,000
609,161 1,374,161
220,458 320,458
7,488,619 8,353,619
765,000
Phase Summary:
Fed $
Local AC
Local Match
Total
153,000
865,000
LSSRP Bond
Total707,787 6,659,000 8,078,787
121,832 274,832
6,659,000 -6,659,0007,488,619 8,353,619
712,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
2007
5920(056)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
153,000
765,000
LSSRP Bond
Total487,329 1,099,329
121,832 274,832
609,161 1,374,161
612,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total 100,000
LSSRP Bond
Total220,458 320,458
220,458 320,458
100,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total6,659,000 6,659,000
6,659,000 -6,659,000
6,659,000 6,659,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1123/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Sonoma County BRIDGE NO. 20C0155, WOHLER RD, OVER RUSSIAN RIVER, 1.5 MI FROM RIVER RD. LSSRP Seismic Retrofit. 11/13/2012: Toll creditsused for PE. 10/18/2017: Toll credits used for R/W.
Fund Source Summary:
PER/W
Total 1,650,000
CON
Total
13,875,880
1,650,000
100,000 150,000 250,000
100,000 150,000 15,775,880
1,650,000
13,875,88013,875,880
Phase Summary:
Fed $
Local AC
Local Match
Total 1,650,000
LSSRP Bond
Total
1,591,563
250,000 14,184,317
100,000 -100,000100,000 150,000 15,775,880
1,650,000
1,591,563
12,284,317
13,875,880
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
2011
5920(137)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 1,650,000
LSSRP Bond
Total1,650,000
1,650,000
1,650,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total250,000 250,000
100,000 -100,000
100,000 150,000 250,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
1,591,563
12,284,317
13,875,880
1,591,563
12,284,317
13,875,880
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1133/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amounts programmed in the FTIP.
HBP-ID Project Description
Sonoma County BRIDGE NO. 20C0227, GEYSERS RD, OVER FRASIER CREEK, 20.4 MI N OF ST HWY 128. Replace deficient 2-lane bridge with new 2-lanebridge meeting current geometrics standards. 9/14/2010: Toll credits for all phases.
Fund Source Summary:
PER/W
Total 811,250
CON
Total
4,543,000
350,000 1,161,250
80,000 80,000
430,000 5,784,250
811,250
4,543,0004,543,000
Phase Summary:
Fed $
Local AC
Local Match
Total 811,250
LSSRP Bond
Total430,000 5,784,250
430,000 5,784,250
811,250 4,543,000
4,543,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3626
5920(129)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 811,250
LSSRP Bond
Total350,000 1,161,250
350,000 1,161,250
811,250
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total80,000 80,000
80,000 80,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total4,543,000
4,543,000
4,543,000
4,543,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1143/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Sonoma County BRIDGE NO. 20C0242, CHALK HILL RD, OVER MAACAMA CREEK, 1 MI S OF ST HWY 128. Replace one-lane bridge with two-lane bridge.11/10/2010: Toll credits used for PE, R/W, and CON.
Fund Source Summary:
PER/W
Total 1,289,180
CON
Total
12,936,000
1,510,820 2,800,000
250,000 250,000
1,510,820 250,000 15,986,000
1,289,180
12,936,00012,936,000
Phase Summary:
Fed $
Local AC
Local Match
Total 1,289,180
LSSRP Bond
Total1,510,820 250,000 15,986,000
1,510,820 250,000 15,986,000
1,289,180 12,936,000
12,936,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
2016
5920(049)5920(118)
Project #:
PE Summary:Fed $
Local AC
Local Match
Total 1,289,180
LSSRP Bond
Total1,510,820 2,800,000
1,510,820 2,800,000
1,289,180
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total250,000 250,000
250,000 250,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total12,936,000
12,936,000
12,936,000
12,936,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1153/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Sonoma County BRIDGE NO. 20C0248, LAMBERT BRIDGE RD, OVER DRY CREEK, 0.4 MI W OF DRY CREEK RD. Replace one-lane bridge with two-lane bridge. Formerly LSSRP Seismic Retrofit 11/10/2010: Toll credits used for PE, R/W, & CON.
Fund Source Summary:
PER/W
Total 1,068,750
CON
Total
5,985,000
1,068,750
250,000 250,000
250,000 7,303,750
1,068,750
5,985,0005,985,000
Phase Summary:
Fed $
Local AC
Local Match
Total 1,068,750
LSSRP Bond
Total250,000 7,303,750
250,000 7,303,750
1,068,750 5,985,000
5,985,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
2017
5920(050)5920(138)
Project #:
PE Summary:Fed $
Local AC
Local Match
Total 1,068,750
LSSRP Bond
Total1,068,750
1,068,750
1,068,750
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total250,000 250,000
250,000 250,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total5,985,000
5,985,000
5,985,000
5,985,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1163/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Sonoma County BRIDGE NO. 20C0262, BOYES BLVD, OVER SONOMA CREEK, JUST EAST OF RIVERSIDE DR. Replace 2 lane bridge with 2 lane bridgewith LBSRP contribution.
Fund Source Summary:
PER/W
Total
550,000
1,537,369
CON
Total
5,672,353 272,275 5,944,628
719,529 1,706,898
255,915 805,915
6,647,797 272,275 8,457,441
987,369
Phase Summary:
Fed $
Local AC
Local Match
Total
260,559
1,537,369
LSSRP Bond
Total
18,064 55,745 73,809
802,185 1,229,020 4,033,759 7,341,774
823,878 -18,064 -24,516 1,041,857
5,021,734 -1,229,020 -3,792,7146,647,797 272,275 8,457,441
1,276,810
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
1827
5920(059)5920(178)
Project #:
PE Summary:Fed $
Local AC
Local Match
Total
197,474
987,369
LSSRP Bond
Total575,623 1,365,518
143,906 341,380
719,529 1,706,898
789,895
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
63,085
550,000
LSSRP Bond
Total226,562 713,477
29,353 92,438
255,915 805,915
486,915
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total
18,064 55,745 73,809
1,229,020 4,033,759 5,262,779
650,619 -18,064 -24,516 608,039
5,021,734 -1,229,020 -3,792,714
5,672,353 272,275 5,944,628
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1173/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Sonoma County BRIDGE NO. 20C0326, FRANZ VALLEY SCH RD, OVER FRANZ CREEK, JUST N/O FRANZ RD. Replace existing 2-lane bridge with new2-lane bridge. Toll Credits programmed for PE, R/W, & CON.
Fund Source Summary:
PER/W
Total 500,750
CON
Total
3,000,000
250,000 750,750
100,000 100,000
350,000 3,850,750
500,750
3,000,0003,000,000
Phase Summary:
Fed $
Local AC
Local Match
Total 500,750
LSSRP Bond
Total350,000 3,850,750
350,000 3,850,750
500,750 3,000,000
3,000,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4237
5920(149)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 500,750
LSSRP Bond
Total250,000 750,750
250,000 750,750
500,750
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total100,000 100,000
100,000 100,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,000,000
3,000,000
3,000,000
3,000,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1183/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Sonoma County BRIDGE NO. 20C0406, RIVER ROAD OVER GILL CREEK, 2.0 MI NW OF SR 128. Replace existing two-lane bridge with new two-lane bridge.Chien Wu, 3/14/2014 2:55:46 PM. 3/20/2014: Toll Credits programmed for PE, R/W, & CON.
Fund Source Summary:
PER/W
Total 868,250
CON
Total
4,862,220
200,000 1,068,250
120,000 120,000
200,000 120,000 6,050,470
868,250
4,862,2204,862,220
Phase Summary:
Fed $
Local AC
Local Match
Total 868,250
LSSRP Bond
Total200,000 120,000 6,050,470
200,000 120,000 6,050,470
868,250 4,862,220
4,862,220
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4197
5920(144)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 868,250
LSSRP Bond
Total200,000 1,068,250
200,000 1,068,250
868,250
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total120,000 120,000
120,000 120,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total4,862,220
4,862,220
4,862,220
4,862,220
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1193/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Sonoma County BRIDGE NO. 20C0407, WEST DRY CREEK RD, OVER PENA CREEK, 0.7 MI NW YOAKIM BR RD. Replace one-lane bridge with two-lanebridge. Formerly LSSRP Seismic Retrofit 4/26/2010: Toll Credits programmed for PE, R/W & Con.
Fund Source Summary:
PER/W
Total 540,000
CON
Total
4,000,000
710,000 1,250,000
250,000 250,000
710,000 250,000 5,500,000
540,000
4,000,0004,000,000
Phase Summary:
Fed $
Local AC
Local Match
Total 540,000
LSSRP Bond
Total710,000 250,000 5,500,000
710,000 250,000 5,500,000
540,000 4,000,000
4,000,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
2020
5920(139)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 540,000
LSSRP Bond
Total710,000 1,250,000
710,000 1,250,000
540,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total250,000 250,000
250,000 250,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total4,000,000
4,000,000
4,000,000
4,000,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1203/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Sonoma County BRIDGE NO. 20C0433, KING RIDGE RD, OVER BIG AUSTIN CREEK, 2.3 MI N FORT ROSS RD. Replace one lane bridge to two-lane bridge4/1/2010: Toll Credits programmed for PE, R/W, & Con.
Fund Source Summary:
PER/W
Total 628,000
CON
Total
5,000,000
200,000 828,000
150,000 150,000
200,000 150,000 5,978,000
628,000
5,000,0005,000,000
Phase Summary:
Fed $
Local AC
Local Match
Total 628,000
LSSRP Bond
Total200,000 150,000 5,978,000
200,000 150,000 5,978,000
628,000 5,000,000
5,000,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3319
5920(106)5920(146)
Project #:
PE Summary:Fed $
Local AC
Local Match
Total 628,000
LSSRP Bond
Total200,000 828,000
200,000 828,000
628,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total150,000 150,000
150,000 150,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total5,000,000
5,000,000
5,000,000
5,000,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1213/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Sonoma County BRIDGE NO. 20C0440, FREESTONE FLAT RD OVER SALMON CREEK, 0.2 MI E BOHEMIAN HWY. Replace existing one-lane bridge withnew two-lane bridge. 10/4/2010: Toll credits used for PE.
Fund Source Summary:
PER/W
Total 562,500
CON
Total
3,150,000
578,000 1,140,500
400,000 400,000
978,000 4,690,500
562,500
3,150,0003,150,000
Phase Summary:
Fed $
Local AC
Local Match
Total 562,500
LSSRP Bond
Total578,000 400,000 4,690,500
400,000 -400,000978,000 4,690,500
562,500 3,150,000
3,150,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
3707
5920(127)Project #:
PE Summary:Fed $
Local AC
Local Match
Total 562,500
LSSRP Bond
Total578,000 1,140,500
578,000 1,140,500
562,500
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
R/W Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total400,000 400,000
400,000 -400,000
400,000 400,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total3,150,000
3,150,000
3,150,000
3,150,000
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1223/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Sonoma County BRIDGE NO. PM00101, Bridge Preventive Maintenance Program (BPMP) for various bridges in the County of Sonoma. See Caltrans LocalAssistance HBP website for backup list of projects.
Fund Source Summary:
PER/W
Total 182,642
CON
Total
547,925
182,642
730,567
182,642
547,925547,925
Phase Summary:
Fed $
Local AC
Local Match
Total
20,949
182,642
LSSRP Bond
Total646,771
83,796
730,567
161,693 485,078
62,847
547,925
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
4165
5920(163)Project #:
PE Summary:Fed $
Local AC
Local Match
Total
20,949
182,642
LSSRP Bond
Total161,693
20,949
182,642
161,693
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
CON Summary:Fed $
Local AC
Local Match
Total
LSSRP Bond
Total485,078
62,847
547,925
485,078
62,847
547,925
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
Caltrans, Division of Local Assistance Page 1233/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
2018/19-2023/24 Highway Bridge Program
District: County:Responsible Agency
04 Sonoma
See the appropriate FTIP/FSTIP for current funding commitments. This listing provides the backup project information to support the lump sum amountsprogrammed in the FTIP.
HBP-ID Project Description
Number of Projects:
MPO Summary:
Fed $
Local AC
Local Match
Total for all Phases
44,880,564
17,985,022
191,367,003
LSSRP Bond
Total
32,690 13,411 249,758 67,215 45,880 4,929,471
26,850,372 65,501,690 21,584,864 22,405,980 13,620,644 29,502,545 777,875,109
4,498,104 2,046,846 14,477,714 1,040,983 938,137 1,036,479 68,802,246
16,259,867 -42,824,590 102,169,871 -5,683,562 -4,405,610 -17,527,596
47,621,754 24,973,704 138,299,665 17,763,401 10,199,051 13,011,428 851,606,826
128,468,728
4,520,517
469,940,285
26,778,961
-92,868,944
408,370,820
Totals:
Metropolitan Transportation Commission
Prior 18/19 19/20 20/21 21/22 22/23 23/24 Beyond
122
Caltrans, Division of Local Assistance Page 1243/30/2021, 2:27 PM Det2 FL4 SmlTxt brf
Modifications Made to Programming Totals
Source Prior FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24 Beyond TotalFed $ $78,133,378 $28,566,694 $44,585,820 $26,850,372 $65,501,690 $21,584,864 $22,405,980 $13,620,644 $29,502,545 $469,940,285 $800,692,272Local Match $9,897,730 $2,445,962 $5,632,522 $4,498,104 $2,046,846 $14,477,714 $1,040,983 $938,137 $1,036,479 $26,778,961 $68,793,438LSSRP Bond $108,965 $1,182,557 $13,411 $249,758 $67,215 $45,880 $4,520,517 $6,188,303Local AC $15,521,149 $12,102,308 $16,259,867 -$42,824,590 $102,169,871 -$5,683,562 -$4,405,610 -$17,527,596 -$92,868,944 -$17,257,107Total for all Phases $103,661,222 $31,012,656 $63,503,207 $47,621,754 $24,973,704 $138,299,664 $17,763,401 $10,199,051 $13,011,428 $408,370,819 $858,416,906
Source Prior FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24 Beyond TotalFed $ -$78,133,378 -$78,133,378Local Match -$9,897,730 -$9,897,730LSSRP Bond -$108,965 -$108,965Local AC -$15,521,149 $42,824,590 $5,683,562 $4,405,610 $17,527,596 $92,868,944 $147,789,153Total for all Phases -$103,661,222 $42,824,590 $92,868,944 $59,649,080
Source Prior FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24 Beyond TotalFed $ $28,566,694 $44,585,820 $26,850,372 $65,501,690 $21,584,864 $22,405,980 $13,620,644 $29,502,545 $469,940,285 $722,558,894Local Match $2,445,962 $5,632,522 $4,498,104 $2,046,846 $14,477,714 $1,040,983 $938,137 $1,036,479 $26,778,961 $58,895,708LSSRP Bond $1,182,557 $13,411 $249,758 $67,215 $45,880 $4,520,517 $6,079,338Local AC $12,102,308 $16,259,867 $102,169,871 $130,532,046
Total for all Phases $31,012,656 $63,503,207 $47,621,754 $67,798,294 $138,299,664 $23,446,963 $14,604,661 $30,539,024 $501,239,763 $918,065,986
Back-up Listing Total
Total Funding for VAR170012
Project Listing Adjustments
Note: Negative amounts not programmed in FMS; Funding for prior years is programmed on VAR110045