time value of money part 2
DESCRIPTION
The Time Value of MoneyTRANSCRIPT
![Page 1: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/1.jpg)
ALAN ANDERSON, Ph.D. ECI RISK TRAINING
www.ecirisktraining.com
![Page 2: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/2.jpg)
The time value of money formulas can be used to solve for the appropriate rate of interest or time horizon given the present and future value of a sum.
(c) ECI RISK TRAINING 2009 www.ecirisktraining.com 40
![Page 3: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/3.jpg)
The present and future value formulas can be used to solve for the rate of interest.
41 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 4: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/4.jpg)
Suppose that an investor deposits $10,000 in a bank account.
The investor plans to keep these funds in the bank for ten years, with a goal of having $20,000 at the end of that time. What rate of interest would he have to earn to double his money in ten years?
42 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 5: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/5.jpg)
This can be determined algebraically as follows:
FVN = PV(1 + I)N
FVNPV
= (1+ I )N
43 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 6: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/6.jpg)
FVNPV
N = (1+ I )
FVNPV
N −1 = I
44 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 7: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/7.jpg)
In this example,
20,00010,000
10 −1 = 0.07177 = 7.177%
45 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 8: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/8.jpg)
The present and future value formulas can also be used to solve for the time horizon.
46 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 9: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/9.jpg)
Suppose that an investor deposits $5,000 in a bank account that pays 6% interest per year. The investor wants to know how long it will take for these funds to be worth $10,000.
47 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 10: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/10.jpg)
This can be determined algebraically as follows:
FVN = PV(1 + I)N
FVNPV
= (1+ I )N
48 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 11: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/11.jpg)
ln FVNPV
⎛⎝⎜
⎞⎠⎟= N ln(1+ I )
N =ln FVN
PV⎛⎝⎜
⎞⎠⎟
ln(1+ I )
49 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 12: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/12.jpg)
In this example,
N =ln 10,000
5,000⎛⎝⎜
⎞⎠⎟
ln(1+ .06)= 11.896
50 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 13: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/13.jpg)
The Rule of 72 is a quick method for estimating the time horizon or the interest rate needed to double the value of an investment.
51 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 14: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/14.jpg)
Dividing the interest rate into 72 gives the approximate number of years that it would take to double the value of an investment.
For the example of the investor who needs to know how many years it would take to double his money at an interest rate of 6%, dividing 72 by 6 gives a result of 12, which is very close to the actual value of 11.896 years.
52 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 15: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/15.jpg)
Dividing the number of years into 72 gives the approximate interest rate that would be required to double the value of an investment.
For the example of the investor who needs to know what rate of interest is required to double his money in ten years, dividing 72 by 10 gives a result of 7.2%, which is very close to the actual value of 7.177%.
53 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 16: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/16.jpg)
In the case of a stream of cash flows that are not equal, computing the future and present value of the cash flows is a more complex process.
54 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 17: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/17.jpg)
The two basic types of uneven cash flows of interest in finance are:
1) an annuity with an additional payment during the final period
2) a cash flow stream with no pattern, known as an irregular stream of cash flows
55 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 18: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/18.jpg)
(c) ECI RISK TRAINING 2009 www.ecirisktraining.com 56
The cash flows from most bonds take the form of an annuity with an additional payment during the final period.
Investment projects often generate irregular streams of cash flows to firms.
![Page 19: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/19.jpg)
Suppose that a bond offers investors cash flows of $100 each year for the next three years, with an additional payment of $1,000 at the end of the third year. If the periodic rate of interest is 5%, what is the present value of this stream of cash flows?
57 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 20: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/20.jpg)
In this case,
N = 3 I = 5 PMT = $100 FV3 = $1,000
58 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 21: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/21.jpg)
PVAN = PMT1− 1
(1+ I )N
I
⎡
⎣
⎢⎢⎢⎢
⎤
⎦
⎥⎥⎥⎥
59 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 22: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/22.jpg)
PVA3 = 1001− 1
(1+ .05)3
.05
⎡
⎣
⎢⎢⎢⎢
⎤
⎦
⎥⎥⎥⎥
= $272.32
60 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 23: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/23.jpg)
=1,0001.1576
= $863.84
PV =FVN(1+ I )N
=1,000(1.05)3
61 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 24: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/24.jpg)
Combining these results gives the present value of the cash flow stream: PVA3 + PV = 272.32 + 863.84 = $1,136.16
62 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 25: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/25.jpg)
Suppose that an investment project produces cash flows of $200 at the end of the next two years, and $300 at the end of the following three years.
63 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 26: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/26.jpg)
If the periodic rate of interest is 4%, what is the present value of these cash flows?
In this case, the present value of each cash flow is computed using the PV formula; these results are combined to give the present value of the stream of irregular cash flows.
64 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 27: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/27.jpg)
In this case, the present value is:
= 192.31 + 184.91 + 266.67 + 256.44 + 246.58 = $1,146.91
200(1.04)1
+200(1.04)2
+300(1.04)3
+300(1.04)4
+300(1.04)5
65 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 28: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/28.jpg)
Each of the examples considered so far has been based on the assumption that interest is paid annually.
When interest is paid more often than once per year, the present value and future value formulas must be adjusted.
66 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 29: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/29.jpg)
Two adjustments must be made:
1) the periodic interest rate 2) the number of periods
67 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 30: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/30.jpg)
The periodic interest rate equals:
annual rate / number of periods per year
The number of periods equals:
(number of years)(number of periods per year)
68 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 31: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/31.jpg)
Suppose that a sum of $1,000 is invested for two years at an annual rate of interest of 4%. Compute the future value of this sum based on the assumption of:
a) annual compounding b) semi-annual compounding
69 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 32: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/32.jpg)
With annual compounding,
N = 2 I = 4 PV = $1,000
70 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 33: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/33.jpg)
Using the future value formula,
FVN = PV(1+I)N
FV2 = 1,000(1+.04)2 FV2 = 1,000(1.081600) FV2 = $1081.60
71 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 34: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/34.jpg)
With semi-annual compounding,
N = 4 I = 2 PV = $1,000
72 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 35: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/35.jpg)
Using the future value formula,
FVN = PV(1+I)N
FV4 = 1,000(1+.02)4 FV4 = 1,000(1.082432) FV4 = $1082.43
73 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 36: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/36.jpg)
The more frequently interest is paid each year, the greater will be the future value of a sum or an annuity.
74 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 37: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/37.jpg)
Compute the present value of $1,000 to be received in four years using an annual interest rate of 6% with:
a) annual compounding b) semi-annual compounding
75 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 38: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/38.jpg)
With annual compounding,
N = 4 I = 6 FV4 = $1,000
76 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 39: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/39.jpg)
Using the present value formula,
PV =
FVN(1+ I )N
=1000
(1+ .06)4= $792.09
77 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 40: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/40.jpg)
With semi-annual compounding,
N = 8 I = 3 FV8 = $1,000
78 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 41: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/41.jpg)
Using the present value formula,
PV =FVN(1+ I )N
=1000
(1+ .03)8= $789.41
79 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 42: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/42.jpg)
The more frequently interest is paid each year, the smaller will be the present value of a sum or an annuity.
80 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 43: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/43.jpg)
As the frequency of compounding increases, the present value of a sum or annuity decreases, while the future value of a sum or annuity increases.
81 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 44: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/44.jpg)
The limiting compounding frequency is known as continuous compounding. In this case, interest is compounded at every instant in time. As a result, the number of compounding periods is infinite.
The present and future value formulas with continuous compounding are:
82 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 45: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/45.jpg)
FVN = eIN
e = 2.7182818......
PV =FVNeIN
= FVNe− IN
83 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 46: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/46.jpg)
The present value of $1,000 to be received in four years with an annual rate of interest of 5% compounded continuously is computed as follows:
84 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 47: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/47.jpg)
PV = 1,000e-(0.05)(4) =
1,000e-(0.20) = $818.73
85 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 48: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/48.jpg)
The future value of $1,000 invested for three years at an annual rate of interest of 4% compounded continuously is computed as follows:
86 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 49: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/49.jpg)
FV3 = 1,000e(0.04)(3) =
1,000e(0.12) = $1,127.50
87 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 50: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/50.jpg)
In order to compare interest rates with different compounding frequencies, they can be converted into the effective annual rate (EAR).
88 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 51: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/51.jpg)
This is done with the following formula:
EAR = 1+ APRM
⎛⎝⎜
⎞⎠⎟M
−1
89 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 52: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/52.jpg)
where:
APR = the annual percentage rate
90 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 53: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/53.jpg)
If a bank charges an APR of 6% per year, compounded quarterly for a loan, what is the effective annual rate?
91 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 54: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/54.jpg)
This can be determined with the formula, as follows:
EAR = 1+ APRM
⎛⎝⎜
⎞⎠⎟M
−1
92 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 55: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/55.jpg)
EAR = 1+ .064
⎛⎝⎜
⎞⎠⎟4
−1 = 0.06136
93 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 56: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/56.jpg)
This indicates that the borrower is actually paying 6.136% per year for this loan.
94 (c) ECI RISK TRAINING 2009
www.ecirisktraining.com
![Page 57: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/57.jpg)
(c) ECI RISK TRAINING 2009 www.ecirisktraining.com 95
With continuous compounding, the EAR formula becomes:
EAR = eAPR - 1
![Page 58: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/58.jpg)
If a bank charges an APR of 5% per year, continuously compounded, what is the effective annual rate?
EAR = eAPR – 1 = e.05 – 1 = 0.051271 = 5.1271%
(c) ECI RISK TRAINING 2009 www.ecirisktraining.com 96
![Page 59: Time Value Of Money Part 2](https://reader033.vdocuments.mx/reader033/viewer/2022051013/54797908b4af9fef158b483b/html5/thumbnails/59.jpg)
For free problem sets based on this material along with worked-out solutions, write to [email protected]. To learn about training opportunities in finance and risk management, visit www.ecirisktraining.com
(c) ECI RISK TRAINING 2009 www.ecirisktraining.com 97