time value analysis
TRANSCRIPT
-
8/4/2019 Time Value Analysis
1/35
February 17, 2009
1
Engineering Economics
-
8/4/2019 Time Value Analysis
2/35
Engineering Economy
2
It deals with the concepts and techniques of analysisuseful in evaluating the worth of systems, products,and services in relation to their costs
-
8/4/2019 Time Value Analysis
3/35
Engineering Economy
3
It is used to answer many different questions
Which engineering projects are worthwhile? Has the mining or petroleum engineer shown that the mineral or
oil deposits is worth developing?
Which engineering projects should have a higherpriority? Has the industrial engineer shown which factory improvement
projects should be funded with the available dollars?
How should the engineering project be designed? Has civil or mechanical engineer chosen the best thickness for
insulation?
-
8/4/2019 Time Value Analysis
4/35
Basic Concepts
4
Cash flow
Interest Rate and Time value of money Equivalence technique
-
8/4/2019 Time Value Analysis
5/35
Cash Flow
5
Engineering projects generally have economic
consequences that occur over an extendedperiod of time For example, if an expensive piece of machinery is
installed in a plant were brought on credit, the simple
process of paying for it may take several years The resulting favorable consequences may last as long
as the equipment performs its useful function
Each project is described as cash receipts or
disbursements (expenses) at different points intime
-
8/4/2019 Time Value Analysis
6/35
Categories of Cash Flows
6
The expenses and receipts due to
engineering projects usually fall into one ofthe following categories: First cost: expense to build or to buy and install
Operations and maintenance (O&M): annualexpense, such as electricity, labor, and minorrepairs
Salvage value: receipt at project termination for saleor transfer of the equipment (can be a salvage cost)
Revenues: annual receipts due to sale of products
or services Overhaul: major capital expenditure that occurs
during the assets life
-
8/4/2019 Time Value Analysis
7/35
Cash Flow diagrams
7
The costs and benefits of engineering projectsover time are summarized on a cash flowdiagram (CFD). Specifically, CFD illustratesthe size, sign, and timing of individual cashflows, and forms the basis for engineering
economic analysis A CFD is created by first drawing a
segmented time-based horizontal line, dividedinto appropriate time unit. Each time when
there is a cash flow, a vertical arrow is added pointing down for costs and up for revenuesor benefits. The cost flows are drawn torelative scale
-
8/4/2019 Time Value Analysis
8/35
Drawing a Cash Flow Diagram
8
In a cash flow diagram (CFD) the end of period t isthe same as the beginning of period (t+1) Beginning of period cash flows are: rent, lease, and
insurance payments End-of-period cash flows are: O&M, salvages,
revenues, overhauls The choice of time 0 is arbitrary. It can be when a
project is analyzed, when funding is approved, orwhen construction begins
One persons cash outflow (represented as a negative
value) is another persons inflow (represented as apositive value) It is better to show two or more cash flows occurring
in the same year individually so that there is a clearconnection from the problem statement to each cashflow in the diagram
-
8/4/2019 Time Value Analysis
9/35
An Example of Cash Flow Diagram
9
A man borrowed $1,000 from a bank at 8%
interest. Two end-of-year payments: at theend of the first year, he will repay half of the$1000 principal plus the interest that is due. Atthe end of the second year, he will repay the
remaining half plus the interest for the secondyear.
Cash flow for this problem is:End of year Cash flow
0 +$1000
1 -$580 (-$500 - $80)
2 -$540 (-$500 - $40)
-
8/4/2019 Time Value Analysis
10/35
Cash Flow Diagram
10
$1,000
0
1 2
$580 $540
-
8/4/2019 Time Value Analysis
11/35
Time Value of Money
11
Money has value
Money can be leased or rented
The payment is called interest
If you put $100 in a bank at 9% interest for one timeperiod you will receive back your original $100 plus $9
Original amount to be returned = $100
Interest to be returned = $100 x .09 = $9
-
8/4/2019 Time Value Analysis
12/35
Compound Interest
12
Interest that is computed on the original unpaid
debt and the unpaid interest Compound interest is most commonly used in
practice
Total interest earned = In = P (1+i)n - P
Where, P present sum of money
i interest rate
n number of periods (years)
I2 = $100 x (1+.09)2 - $100 = $18.81
-
8/4/2019 Time Value Analysis
13/35
Future Value of a Loan WithCompound Interest
13
Amount of money due at the end of a loan F = P(1+i)1(1+i)2..(1+i)n or F = P (1 + i)
n
Where, F = future value and P = present value
Referring to slide #10, i = 9%, P = $100 and say n= 2.Determine the value of F.
F = $100 (1 + .09)2 = $118.81
-
8/4/2019 Time Value Analysis
14/35
Notation forCalculating a Future Value
14
Formula:
F=P(1+i)n is the
single payment compound amount factor. Functional notation:
F=P(F/P,i,n) F=5000(F/P,6%,10)
F =P(F/P) which is dimensionally correct.
-
8/4/2019 Time Value Analysis
15/35
Notation forCalculating a Present Value
15
P=F(1/(1+i))n=F(1+i)-n is the
single payment present worth factor.
Functional notation:
P=F(P/F,i,n) P=5000(P/F,6%,10)Interpretation of (P/F, i, n): a present sum P, given a
future sum, F, n interest periods hence at aninterest rate i per interest period
-
8/4/2019 Time Value Analysis
16/35
-
8/4/2019 Time Value Analysis
17/35
Equivalence
17
Relative attractiveness of different alternatives can
be judged by using the technique of equivalence We use comparable equivalent values of
alternatives to judge the relative attractiveness of thegiven alternatives
Equivalence is dependent on interest rate Compound Interest formulas can be used to
facilitate equivalence computations
-
8/4/2019 Time Value Analysis
18/35
Technique of Equivalence
18
Determine a single equivalent value at a point intime for plan 1.
Determine a single equivalent value at a point intime for plan 2.
Both at the same interest rate and at the same time point.
Judge the relative attractiveness of thetwo alternatives from the comparable
equivalent values.
-
8/4/2019 Time Value Analysis
19/35
Engineering Economic Analysis Calculation
19
Generally involves compound interest formulas(factors)
Compound interest formulas (factors) can beevaluated by using one of the three methods
Interest factor tables Calculator
Spreadsheet
-
8/4/2019 Time Value Analysis
20/35
Given the choice of these two plans whichwould you choose?
Year Plan 1 Plan 2
0 $5,000
1 $1,000
2 $1,0003 $1,000
4 $1,000
5 $1,000Total $5,000 $5,000
20
To make a choice the cash flows must be altered
so a comparison may be made.
eso v ng as ows to qu va ent resent
-
8/4/2019 Time Value Analysis
21/35
eso v ng as ows to qu va ent resentValues
P = $1,000(PA,10%,5)
P = $1,000(3.791) =$3,791
P = $5,000
Alternative 2 is better than
alternative 1 sincealternative 2 has a greaterpresent value
21
A E l f F V l
-
8/4/2019 Time Value Analysis
22/35
An Example of Future Value
22
Example: If $500 were deposited in a banksavings account, how much would be in theaccount three years hence if the bank paid 6%interest compounded annually?
Given P = 500, i = 6%, n = 3, use F =
FV(6%,3,,500,0) = -595.91 Note that the spreadsheet gives a negative
number to find equivalent of P. If we find P usingF = -$595.91, we get P = 500.
A E l f P V l
-
8/4/2019 Time Value Analysis
23/35
An Example of Present Value
23
Example 3-5: If you wished to have $800 in asavings account at the end of four years, and 5%interest we paid annually, how much should youput into the savings account?
n = 4, F = $800, i = 5%, P = ?
P = PV(5%,4,,800,0) = -$658.16 You should use P = $658.16
-
8/4/2019 Time Value Analysis
24/35
Economic Analysis Methods
24
Three commonly used economic analysis methods
are Present Worth Analysis
Annual Worth Analysis
Rate of Return Analysis
-
8/4/2019 Time Value Analysis
25/35
Present Worth Analysis
25
Steps to do present worth analysis for a single
alternative (investment) Select a desired value of the return on investment (i)
Using the compound interest formulas bring all benefitsand costs to present worth
Select the alternative if its net present worth (Presentworth of benefits Present worth of costs) 0
-
8/4/2019 Time Value Analysis
26/35
Present Worth Analysis
26
Steps to do present worth analysis for selecting a
single alternative (investment) from among multiplealternatives
Step 1: Select a desired value of the return oninvestment (i)
Step 2: Using the compound interest formulas bring allbenefits and costs to present worth for each alternative
Step 3: Select the alternative with the largest netpresent worth (Present worth of benefits Presentworth of costs)
-
8/4/2019 Time Value Analysis
27/35
Present Worth Analysis
27
A construction enterprise is investigating the
purchase of a new dump truck. Interest rate is9%. The cash flow for the dump truck are asfollows:
First cost = $50,000, annual operating cost =
$2000, annual income = $9,000, salvage value is$10,000, life = 10 years. Is this investment worthundertaking?
P = $50,000, A = annual net income = $9,000 -$2,000 = $7,000, S = 10,000, n = 10.
Evaluate net present worth = present worth ofbenefits present worth of costs
-
8/4/2019 Time Value Analysis
28/35
Present Worth Analysis
28
Present worth of benefits = $9,000(PA,9%,10) =
$9,000(6.418) = $57,762 Present worth of costs = $50,000 +
$2,000(PA,9%,10) - $10,000(PF,9%,10)=$50,000 + $2,000(6..418) - $10,000(.4224) =
$58,612
Net present worth = $57,762 - $58,612 < 0 donot invest
What should be the minimum annual benefit formaking it a worthy of investment at 9% rate ofreturn?
-
8/4/2019 Time Value Analysis
29/35
Present Worth Analysis
29
Present worth of benefits = A(PA,9%,10) = A(6.418)
Present worth of costs = $50,000 +$2,000(PA,9%,10) - $10,000(PF,9%,10)= $50,000 +$2,000(6..418) - $10,000(.4224) = $58,612
A(6.418) = $58,612 A = $58,612/6.418 =
$9,312.44
-
8/4/2019 Time Value Analysis
30/35
Cost and Benefit Estimates
30
Present and future benefits (income) and costs need
to be estimated to determine the attractiveness(worthiness) of a new product investment alternative
-
8/4/2019 Time Value Analysis
31/35
Annual costs and Income for a Product
31
Annual product total cost is the sum of annual
material, labor, and overhead (salaries, taxes,marketing expenses, office costs, and related costs),annual operating costs (power, maintenance,repairs, space costs, and related expenses), andannual first cost minus the annual salvage value.
Annual income generated through the sales of aproduct = number of units sold annuallyxunit price
-
8/4/2019 Time Value Analysis
32/35
Rate of Return Analysis
32
Single alternative case
In this method all revenues and costs of thealternative are reduced to a single percentagenumber
This percentage number can be compared to other
investment returns and interest rates inside andoutside the organization
-
8/4/2019 Time Value Analysis
33/35
Rate of Return Analysis
33
Steps to determine rate of return for a single stand-
alone investment Step 1: Take the dollar amounts to the same point in
time using the compound interest formulas
Step 2: Equate the sum of the revenues to the sum ofthe costs at that point in time and solve for i
R t f R t A l i
-
8/4/2019 Time Value Analysis
34/35
Rate of Return Analysis
34
An initial investment of $500 is being considered.
The revenues from this investment are $300 at theend of the first year, $300 at the end of the second,and $200 at the end of the third. If the desired returnon investment is 15%, is the project acceptable?
In this example we will take benefits and costs to thepresent time and their present values are thenequated
R t f R t A l i
-
8/4/2019 Time Value Analysis
35/35
Rate of Return Analysis
35
$500 = $300(PF, i, n=1) + 300(PF, i, n=2) +$200(PF, i, n=3)
Now solve for i using trial and error method
Try 10%: $500 = ? $272 + $247 + $156 = $669(not equal)
Try 20%: $500 = ? $250 + $208 + $116 = $574(not equal)
Try 30%: $500 = ? $231 + $178 + $91 = $500(equal) i = 30%
The desired return on investment is 15%, theproject returns 30%, so it should be implemented