tier 3 & 4 projects
TRANSCRIPT
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Project DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)Project Status and Timeline
1 CoA
2018 Archibus Upgrade, Mobility &
Portfolio Management
Implementation of new modules of Archibus for Property &
Lease Administration and for upgrading the existing modules to
Version 23 and implementing the mobile framework for Building
Operations. Archibus is the Integrated Workplace Management
System (IWMS) used by FAF and HHS.
$452,150 $366,150 $86,000
Project Status ‐ There are two components to this project: Archibus v23 Upgrade and
Portfolio Management.
Archibus Enhancements:
1.Development work on approved enhancement requests is being carried out. In
parallel, new requirements are being reviewed, prioritized, and specifications
developed.
Portfolio Management:
1. Completed Fit‐gap analysis and Functional documents for Lease module. Change
Request given to vendor, awaiting quote and estimates.
2. Completed Functional documents on Employee Count Enhancements to Occupancy
module. Change Request given to vendor, awaiting quote and estimates.
2 CoA
2019 CEO Reasonable
Accommodation and
Investigations
Develop and implement a system to manage reasonable
accomodation requests and other investigations, in accordance
with Title 1 of the Americans with Disabilities Act. The new
system will provide notifications, workflows, and other case
management features. Project Allocation provides resources for
a project discovery phase. Additional funding from the IT Capital
Reserve or other sources may be needed after a project scope
and estimate is developed.
$50,000 $0 $50,000
Project Status ‐ Engaging with Procurement to define RFP process, update RFP
documentation
3 CoA
2018 Image Conversion Project ‐
Phase II
The current project is a multi‐year project spanning 2 years (FY17
and FY18). In FY16, the 1st phase of this project, was approved
for the conversion of all film records for the year of 1980. For
FY17, the 2nd phase of this project, was approved to convert
document images for our films records for years 1960 to
1979. Phase III of this project (targeted for FY19 and FY20) will
convert our book records from 1858 to 1959.
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ We are continuing to review business requirements with procurement
and are looking towards publishing an RFP within the next 1‐2 months. The project
status will remain yellow since the procure phase is taking more time than expected.
Plan to get to Green ‐ Once the RFP timeline is established, the project timeline will be
changed accordingly.
4 CoA
2018 Implementation of CME V3 Currently Coroner's office uses VAST for recording of autopsy
data and images. The project is to replace the current outdated
version of VAST 2.2 which is, missing a lot of features that the
current staff at MEC need. Vertiq the parent company will no
longer support the current version post 2019.
$175,000 $0 $175,000
Project Status ‐ The project is in the Procurement Stage and waiting for a quote from
the vendor.
5 CoA
2018 IPM Spatial Monitoring and
Data Management Project
RFP development and implementation of custom software from
a professional services vendor selected for IPM Spatial Mapping
and Data Management Software. Assessment has been
completed ‐ business, functional, and technical requirements
have been gathered. Implementation includes development of
forms, relational data input/output, custom report writing, test,
UAT, and roll‐out, and on‐going maintenance.
$125,000 $0 $125,000
Project Status ‐ The project is in the Procurement Stage and approval by the Director of
Procurement to proceed with negotiation is in process.
6 CoA
2016 Park Ranger Information
Management System (PRIMS)
Software implementation for Park Ranger information
management system, requiring implementation and professional
services. Parks approved a new proposal that was presented to
Parks in Nov. 2017. This proposal has TSS taking a key role the
implementation and support for this new setup and revised cost
estimate for both TSS and County Communications.
$86,978 ($30,960) $117,938
Project Status ‐ In Construction Stage. Three parks have Wi‐Fi working. Preparing for
next five parks (Almaden, Casa Grande, Field Sports, Hellyer).
7 CoA
2017 Replace iVOS and RiskMaster
with RMIS/Claims Manage
The RMIS project is a replacement of iVOS and RMA applications
which are used by Worker's Compensation and Property/Liability
Claims Departments. These applications were purchased in 1997
and 2003 respectively and both contracts ended July 2017.
This project consists of three Phases:
Phase 1 ‐ Worker’s Compensation module.
Phase 2 ‐ Property/Liability Claims Processing Module
Phase 3 ‐ Risk Management reporting County wide.
$2,266,462 $483,020 $1,783,442
Project Status ‐ The Project Team is working with the Vendor in the Execution Phase of
the project.
8 FES
2019 Direct Assessor Interface
Phase 1
Upgrading the Tax Collection and Apportionment
System (TCAS) will allow route the data files to be
routed directly from the Assessor's system, utilizing
modern technology and bypassing the mainframe.
Project allocation provides resources for a project
discovery phase. Additional funding from the IT Capital
Reserve or other sources may be needed after a project
scope and estimate is developed.
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ The project to modernize the transfer of billing data between the
Assessor's Office and DTAC Tax is on schedule and in active development. The combined
team (ASR‐DTAC) works very well together and we are on course for our first major
milestone on December 1, 2018.
9 FES
2019 DTAC Collections System
Upgrade
This upgrade will facilitate and implement the
consolidation of all of Department of Tax and
Collections collection activities within a single system.
Project allocation provides resources for a project
discovery phase. Additional funding from the IT Capital
Reserve or other sources may be needed after a project
scope and estimate is developed.
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ Proejct Team is in the initial draft phases of gathering requirements for
completion of the RFP.
10 FES
2019 DTAC Trust Replacement
Project
Enhancing the capabilities of the Tax Collection and
Appropriation System (TCAS) will allow for better
communication and collaboration with tax payers,
business units and taxing jurisdictions by eliminating
manual processes. Project allocation provides resources
for a project discovery phase. Additional funding from
the IT Capital Reserve or other sources may be needed
after a project scope and estimate is developed.
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ We are in active requirements gathering and fighting back against
increased scope requests. The increased scope requests are not delaying our
investigation.
Tier 3 & 4 Projects
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 1
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Project DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)Project Status and Timeline
Tier 3 & 4 Projects
11 FES
2019 Human Resource Information
System (HRIS) Maint Upg
The County's Human Resources Management System
needs to be upgraded and prepared for migration to the
next future version or to another comparable product.
Project allocation provides resources for a project
discovery phase. Additional funding from the IT Capital
Reserve or other sources may be needed after a project
scope and estimate is developed.
$666,600 $0 $666,600
Project Status: Project kicked off late August. September progressed as planned,
completing current state and fit/gap analysis. October plans are to confirm scope,
complete solution design, and add detail to the baseline schedule to build, test, and
deploy.
12 FES
2019 Property Tax E‐Comm Project A new property tax tool will allow taxpayers to pay
property taxes online and access other property tax
information. Requested features include text message
notifications, paperless billing, and other subscription
communication services. Project allocation provides
resources for a project discovery phase. Additional
funding from the IT Capital Reserve or other sources
may be needed after a project scope and estimate is
developed.
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ Plan Phase started.
13 FES
2019 Property Tax Mobile
Application
A mobile application for County taxpayers will allow
taxpayers to view balances, pay taxes, receive
reminders, manage partial payments or multiple
properties. Project allocation provides resources for a
project discovery phase. Additional funding from the IT
Capital Reserve or other sources may be needed after a
project scope and estimate is developed.
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ The Project Team has completed the Analysis and Design and the project
is in the Development Stage of the Execute Phase.
14 HHS
2017 Behavioral Health Services
Practice Manage Sol
To Procure and Implement a Practice Management System (PMS)
that includes: Provider Billing, Managed Care, Credentialing and
Capacity Management as well as establish Electronic Data
Interchange (EDI) for County Service Providers (CSP) and
HealthLink resulting in improved clinical and administrative
outcomes for consumers receiving services from Behavioral
Health Services and the network of CSPs
Information
unavailable
Information
unavailable
Information
unavailable
Project Status (As of May 2018) ‐ Declines to critical as there are serious issues halting
revenue that must be addressed from the Specialty Mental Health go‐live. To improve,
billing modifiers must be sent from HL to myAvatar, table values for providers, billing
rates, etc. updated by BHS and PBS, missing program admissions and financial eligibility
to be entered into myAvatar. These issues are critical to revenue risk for Specialty
Mental Health as claims cannot be submitted until the issues are resolved.
Plan to get to Green ‐ To address this issue the following is in progress:
1.Netsmart/PBS to complete modifier testing.
2.BHS to update provider values in order to pass billing edits.
3.PBS complete testing of rate values.
4.Continued review of missing clinic admission numbers
5.MH Clinic Program Managers will begin receiving clinic‐specific reports so they can
work with clinicians to add diagnoses in HealthLink where needed.
15 HHS
2018 Enterprise Imaging Archive The vision for an SCVHHS Enterprise Imaging Strategy is to enable
electronic access to any medical image, anywhere, anytime by
caregivers across the care continuum – inter and intra health
system(s) fostering true interoperability and positively impact
both the clinical and business side by improving patient care and
health outcomes as well as streamlining operations and
maximizing insurance reimbursements under accountable care.
This project, therefore, is about the selection, procurement, and
eventual implementation of the most optimal VNA system for
SCVHHS.
Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ A contract was signed on 9/28/18 and the Project Manager is working
with the vendor to get a project manager assigned from the vendor side for project
planning. Hardware procurement is in progress.
16 HHS
2018 HHS ‐ Microsoft Desktop
Upgrade Windows 10
Windows 10 Upgrade for HHS Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ The overall project status remains satisfactory. Deployment throughout
the hospital started June 18, 2018. The Project team continues to make progress with
deploying Windows 10. The decision is made to deploy SSO (Single Sign‐On) machines
with OWA (Outlook Web Access) web application as part of Microsoft applications. Any
traditional MS application operations such as opening, and editing Excel or Word will
have to be carried out from a nursing station or from a non SSO workstation. Once the
training documentation and process is confirmed, the new SSO configuration will be
introduced to leaders and endusers at the Hospital for feedback prior to
implementation.
17 HHS
2018 HHS Governance, Risk &
Compliance (GRC) Solution
SCVHHS Ethics & Compliance Office is seeking a software solution
to manage health care regulatory compliance and risk across the
enterprise. The solution should be capable of addressing a wide
range of compliance areas, including revenue cycle, claims audits,
policy management, privacy, conflicts of interest, internal audit,
enterprise risk management, contracts, and fraud, waste and
abuse.
Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ The overall project status improves to satisfactory. Recruitment for a
replacement hire is complete and the resource is on‐board. Completed soft launch of
Claims Audit Manager (CAM) and Compliance Workspace (CW) on 09/04/2018. Planning
activities are in progress for TPRM (Third Party Risk Management) module
implementation.
18 HHS
2019 New Integrated Library
System
A new integrated library system will replace the existing
static database currently in use.
$333,600 $0 $333,600
Project Status ‐ This project consist of replacing the legacy Hospital Medical Library
system. Current health of the project is Green! The Project Manager is meeting with
Project Sponsors in order to learn more about the scope, functional requirements and
engagement with Procurement buyer.
19 HHS
2019 Nursing Administration ‐
Patient Video Surveillance
RFP and implementation of a Patient Video Surveillance Solution
to help reduce costs by eliminating the need for 'SITTERS' in all
adult inpatient units.
Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ Functional and technical requirements were documented and the
Project Team is drafting the RFP. Also exploring the possibility of using the existing
Vendor contract to purchase this system. Procurement and Network provided initial
approval, however, Procurement is now requesting a second review scheduled for
October.
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 2
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Project DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)Project Status and Timeline
Tier 3 & 4 Projects
20 HHS
2019 Pacemaker Database System Procurement effort and implementation of a solution to replace
the current pacemaker database system which is out of
compliance with regulatory requirements and to improve system
usability.
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ Market research results confirmed that the current vendor's system is
the only provider providing this service. The Project Manager submitted a sole source
justification approval request to Procurement which is currently in progress.
21 HHS
2018 PHD Open Data Portal Public Health Open Data Portal Solution is to use dashboards to
track health and social determinant data, track progress made on
the strategic plan and performance improvement activities as
well as an easy to use mapping interface.
Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ The overall project status remains satisfactory. The PHD Open Data
Portal was launched on September 4, 2018.
22 HHS
2018 PHD: ESSENCE Syndromic
Surveillance MU
Syndromic Surveillance Meaningful Use project is for a new
contract upgrade, hardware; implement real‐time HL7 ADT
interfaces, testing and validation of data submissions.
Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ The overall project status is satisfactory. Secured funding commitment
from Public Health Finance to roll‐over funding from FY18 to FY19 budget to the
project's cost center. Vendor is re‐engaged to support HL7 interface updates to meet
Meaningful Use Stage 2 requirements
23 HHS
2018 Public Health Integrated
Health System ‐ Solution
RFP and implementation of a Public Health Integrated Health
System (PHIHS) Solution. Current County‐owned system that
functions as the Public Health Master Client Index and gives the
ability to do client tracking across the The Public Health
Integrated Health System (PHIHS) was developed by Envision
Technology Partners, Inc. and went live for data entry in 2003.
Current vendor support for PHIHS ended effective 6/30/2016.
Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ This project status remains satisfactory.
Shortlisted vendors demos and presentations completed.
RFP Vendor Evaluation activities complete.
Evaluation Committee will decide on final candidate on October 12th.
Working on RPF recommendation short list request
24 HHS
2018 Philips Fetal Monitor
Integration with HL
The fetal monitors have been installed and are integrated with
GE/Centricity. The department would like to explore if and how
this data can go into HealthLink instead because there is
additional cost and resource to maintain the GE/Centricity
system.
Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ Project overall health is in Red status.
Project team is currently working with the Vendor's contract team to finalize revision of
their proposed contract by end of October. A meeting will be held in mid‐October to
have a final draft of revised contract.
Plan to get to Green ‐ Escalate to Vendors' Senior leadership in order to expedite
closure on their pending action items.
25 HHS
2016 Resp. Care Masimo Pulse HL
Interface/Philips Upgr
County and SCVMC has signed a new capital equipment and
committed use contract with Masimo Corporation. Total install
of 235 oximeters, 84 hand‐held and 8 wireless portable monitors.
Contract also includes Patient Safety Net monitoring of 88 beds
(2 patient care units) which provided for a telemetry type,
wireless monitoring that will alert healthcare provider if/when a
patient desaturates. New equipment will be installed in or
around April 2016. All Masimo equipment is compatible with HL
and will need to be integrated through interfaces which will allow
seamless and wireless communication between Masimo
equipment and HL. Before Masimo's A05 module with Rainbow
technology can be utilize, all existing Philips monitors need to be
upgraded to the latest software, hose‐wide, in any area that
currently uses a Philips monitor. Also, Philips needs to upgrade
their surveillance network from ver. A to ver. B.02.
Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ The overall project status remains critical due to delay in amendment
execution and vendors failure to provide accurate test plans in a timely manner to
complete (configuration and testing) by 9/10/18 in order to be included in the Epic
upgrade scheduled for 11/4/18. The HealthLink team’s recommendation is to move the
go‐live to Feb 2019. This will be the last update until the project reconvenes back on
February 2019.
Plan to get to Green ‐ A meeting has been setup with the Project Sponsors for mid‐
October to discuss the new Feb 2019 timeline and get their approval.
26 HHS
2017 VMC Ambulatory Video Visits
Technical Solution
Implement enablement of video visits for VMC patients that is
easier, secure and integrated with HealthLink for billing.
Following are the details of requirements/goals will be met after
implementing this project:
o Enablement of Video visits
o Formal Consultation ‐ Physician to Patient Consult
o Ability for a remote provider to consult with a colleague
o Rehab Center ‐ Ability to consult discharged spinal‐cord injury
patient consultations using video
o Custody ‐ Ability to schedule follow‐up video visits with
patients at potentially several locations at the jail
o BHS and BHS custody ‐ Ability to consult providers who are in
custody facilities and outside with SCVMC
o Telestroke ‐ Ability to consult out into the field with
paramedics
o Homeless health and residential ‐ Ability to remotely consult
with homeless clinics
Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ Approval of sole source request is completed and the project is currently
in active contract negotiations with the vendor.
Plan to get to Green ‐ Procurement (along with County Counsel and Vendor Attorney) to
work on alternative options. Project Manager will escalate to Sponsor if it impacts
project timeline.
27 HHS
2018 VMC Cardio Cath Lab & Echo
Storage System Solution
The AGFA HeartLab hardware and software system contract
expired in Sept. '17. In order to meet the IT needs of the
Cardiology Dept. in providing critical patient care services to
utilize, store and access dynamic DICOM images from the Cath
Lab and Echo Lab, a RFP will need to be processed. The current
HeartLab system does not meet Cardiology Department's and
Clinician's access and utilization requirements. The proposed
system requires software to automatically check and correct
duplicate Medical Record numbers, also to ensure patient studies
are accessible to Clinicians for accurate diagnosis. This improved
functionality will minimize loss of patient data if the current
system fails and cannot be fully restored. The new system
requires EPIC interfaces with ADT inbound and outbound, EPIC
orders to the worklist manager on ECHO carts and GE Cath
Camera and inbound/outbound LCR interface to Openlink.
Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ The project remains at watch, trending up negotiations are complete.
The business owner chose a solution. The schedule for executing the contract is delayed
due to the extended amount of time required to complete final negotiations. To get
back on track County Counsel and project leadership will need to complete a final
contract review. A new go live date will be determined following this milestone.
Plan to get to Green ‐ To get back on track County Counsel and Project Leadership will
need to complete a final contract review.
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 3
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Project DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)Project Status and Timeline
Tier 3 & 4 Projects
28 HHS
2018 VMC Enterprise Staff
Scheduling System Solution
Seeking an RFP to evaluate and implement a SCVMC Enterprise
Staff Scheduling System that can meet the functional needs of
the Physicians, Nurses and Pharmacists. SCVMC does not have a
standardized scheduling system to assist management with
allocation of staff time to meet the needs of clinical operations.
Nursing currently uses two systems, one for scheduling and
staffing, one for patient acuity. Title 22 requires that acuity drive
staffing. Current systems are not integrated nor are they linked
to the EMR and current timekeeping system. The current paper
system used for physicians increases the risk of errors and does
not allow tracking and verification of physicians’ time. Clinical
staff such as pharmacists also lack a standardized scheduling
system.
Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ The overall project status remains at watch ‐ trending up. Completed
Phase I testing of the mapping. Starting Phase II of testing validating different scheduling
scenarios in the TRAIN environment and having Time Keeper verifying the info is coming
across correctly. Team met and recommended last week to take the approach of going
live first with 2 small pilot units (MICU/CCU) tentatively on Nov. 5, 2018 to determine if
we should go‐live with the rest of the 17 units in early December. The November 5th go‐
live will be dependent on the completion of Phase II testing, acceptance testing sign‐off
and production set‐up.
Plan to get to Green ‐ Schedule meeting with all stakeholders to discuss back‐up plan
before cut‐over to production for Nov. 5th go‐live for MICU/CCU.
29 HHS
2018 VMC Nutrition & Food Serv
Dietary System Solution
RFP and implementation of Nutrition & Food Serv Dietary System
Solution. The Nutrition and Food Services Department currently
uses the CBORD program to support patient meal delivery,
cafeteria food management system that include point‐of‐sale
registers and to produce printed reports which enable both the
kitchen and the clinical staff to ensure patients receive the right
meals and nourishments according to their diet orders.
Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ The overall project status remains on watch – trending up as we have
finalized Statement of Work (SOW), price quote, payment schedule, vendor SLA,
contract draft 1, initial review with Legal. Vendor has accepted county's BAA.
Continuous reviewing and refining contract in progress. Nov. 1, 2018 is the new target
for contract signing.
Plan to get to Green ‐ The procurement officer will work closely with County Legal team
to expedite the last steps of the Procurement phase. Project Manager will re‐baseline
project milestones and will present to Project Sponsors for acceptance.
30 HHS
2016 VMC PACS Upgrade Project brings Radiology IMPACS system to the latest version of
Software which includes a refresh of multiple servers that are
over 5 years old.
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ The overall project status remains satisfactory. Workflow Design
sessions with Radiologists and Managers were held and the project has reached another
milestone ‐ an integrated design signoff. Epic Radiant RIS and HL7 integration reviews
are also currently underway to validate as well as capture current and future state
integration requirements.
Vendor Deployment team and EMC are scheduled to come onsite in mid‐October
(originally mid‐Sept.) to complete storage provisioning. Following this event, software
configuration will be completed. Currently, there is enough slack in the project schedule
to absorb a one month delay without impacting the overall implementation timeline.
31 HHS
2018 VMC Pharmacy ‐ Bin
Management
To improve the accuracy of the drug dispensation and window.
Solution for storage of medications in a secured location with
barcode scanning on patient's MRN number so only the patient's
medication will be available for staff to pick up and delivered to
the patient.
Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ Overall project status is green. Pharmacy resource assigned. Completed
final onsite demonstrations. Already submitted the market research findings to
Procurement for review. Next steps, gather initial requirements and develop a Sole
Source Justification document.
32 HHS
2015 VMC/VHP Physician
Credentialing
This credentialing system provides compliance with the Centers
for Medicaid & Medicare Services (CMS) and The Joint
Commission (TJC) requirements for Ongoing Professional Practice
Evaluation (OPPE), Focused Professional Practice Evaluation
(FPPE), Telemedicine, and Peer Review. This also efficiently
manages the appointment, reappointment, and privileging
processes. The system allows compliance to all CMS, TJC, and
National Committee for Quality Assurance (NCQA) standards.
The system maintains compliance to CMS, TJC, and NCQA
standards as they change in the future.
Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ VMC and VHP leadership teams have finalized the Data Sharing
Agreement to share five forms and Data Governance decisions have been made. We are
now ready to re‐baseline the VHP Project and move forward with the Data Conversion.
Plan to get to Green ‐ The Project team will work with the business teams to ensure
they have a timeline on completing Data Cleanup Exercise of the five shared forms.
33 PSJ
2016 CAD‐RMS (aka Cons Dispatch‐
Records Management)
A multi‐year project to replace both the existing Computer Aided
Dispatch (CAD) system for County Communications and the
Records Management System (RMS) for the Sheriff’s Office with
current state‐of‐the‐art Commercial‐Off‐The‐Shelf products.
These new systems will provide significant improved emergency
public safety response and services for the County. Legacy
systems in use today are largely home‐grown, obsolete, and
custom solutions that are expensive to maintain and operate.
This project will include the development of requirements for a
Request for Proposal, a formal Procurement, and new System
Implementation for approximately 2,000 Communications and
Sheriff users. The new CAD/RMS consolidated solution will
support Fire, Law, and Emergency Medical Dispatch needs within
the County of Santa Clara. The primary County stakeholders
supported are County Communications, Sheriff’s Office, Health &
Hospital System, Emergency Operations Center, Emergency
Services, County Roads and Airports Department and 17 Public
Safety Answer Points.
$4,050,745 $1,011,662 $3,039,083
Project Status ‐ The project continues in the Procure Stage.
•Shortlist Memo in review with Procurement Office
•Demonstration windows' schedules are being re‐evaluated
PSJ
2016 County Justice Information
Center
Develop a County Justice Information Center that will support
data sharing between criminal justice agencies, shared services,
cross‐agency business intelligence and criminal history archives.
Note: this was called the Countywide Data Exchange previously.
$16,637,079 $7,954,664 $8,682,415 This project will be reported as separate projects :
•CJIC Decommissioning/Gap Analysis
•Court/Tyler ‐ CSM •Defense Case Management System Replacement (DCMSR)
•Enterprise Master Indices ‐ Code Tables (EMI)
•Enterprise Master Indices Subproject ‐ RDM
•Informa on Sharing Environment (ISE) ‐ Phase 2
•Infrastructure for PSJ Projects ‐ Phase 2 •PSJ Data Exchanges (PSJDX) •PSJSP DR Strategy •Public Safety & Jus ce Business Intelligence Sol
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 4
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Project DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)Project Status and Timeline
Tier 3 & 4 Projects
34 PSJ
2018 CJIC Decommissioning/Gap
Analysis
Identification of features and functions addressed by the Court’s
Case Management System and by Sheriff’s Office Jail
Management System and comparison with those of CJIC.
Remaining items, identified as gaps, will be analyzed to identify a
proposed resolution for each. Each gap will then be addressed
by an associated sub‐project rolling up to this project for the
overall monitoring of activities for delivery.
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Project Status ‐
The Project Team continues steady progress forward in the CJIC Decommissioning and
Future State Development efforts. Specifically, we:
•Completed the Development Review of DA Filing and Informal Booking/Citations
•Held a demo of Search/Print capabilities for Consolidated Criminal History
•Reviewed Warrant mockups and Warrant Search prototype
The Project Team is in the process of completing the development of Criminal History;
complete the Solution and Data Architecture of Disposition Reporting, Probation,
Evidence Disposition, and Victim (Restitution) Data.
Plan to get to Green ‐ Address resource shortage ‐ Additional Business Analysts have
been assigned to create User Stories that address the CJIC gaps. The rate that the User
Stories are being created will be reviewed weekly.
35 PSJ
2017 Court/Tyler ‐ CSM Santa Clara County Superior Court is currently in the process of
migrating from the CJIC platform into a new Criminal Case
Management system; Tyler Odyssey. The separation of the Court
function from CJIC represents a near fatal impact to the
functionality that CJIC provides today to over 4,000 users in the
criminal justice community. This project will integrate Tyler Court
data into CJIC to ensure the application can continue to be
operational for justice partners across the County. The current
activities include data mapping, partner agency workflow and
interface data exchange definitions, data conversion and
business process change management.
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Project Status ‐ Schedule ‐ Remains Red (At Risk) to reflect additional testing delays.
Plan to get to Green ‐ A Change Request for the Court’s announced delay to November
13 has been approved. Another Change Request for the Alternate Approach for Go‐Live
is also pending.
36 PSJ
2015 Defense Case Management
System Replacement
(DCMSR)
Replace the County's Defense Case Management System Part of County
Justice Information
Center
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Project Status ‐ System testing is scheduled to start in October. First run of
performance and load testing is complete.
Plan to get to Green ‐ In a process of hiring a new OCM resource. Finalized a tool for
Performance and load testing with TSS. Finalized a plan for User Acceptance Test.
37 PSJ
2016 Enterprise Master Indices ‐
Code Tables (EMI)
Establish reference repository (master data indices, code values
and terminology) that will exchange data via the PSJSP
Information Sharing Environment (ISE) and put in place a
governance processes to ensure on‐going support and
maintenance of codified databases for all systems, sub‐systems
or components of systems.
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Project Status ‐ The project is in the Execute phase as the team has completed installing
the product on the development server. the data modelling is complete. Team has also
finalized the Test and Production server architecture for cloud installation.
Plan to get to Green ‐ Project team is working with the Sheriff's office regarding delay in
masked data which is impacting the schedule to complete Phase 1.
38 PSJ
2016 Enterprise Master Indices
Subproject ‐ RDM
EMI ‐ Reference Data Management will control the codes
mapping from each agency data, standardizing the data and
putting change control management for data elements that will
be used across agencies for PSJ.
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Project Status ‐ Initiated RFP work for the Reference Data Management product.
Procurement team is reviewing the documents and releasing it next month.
∙ Working with the Procurement team to get a RDM solution through RFP process and
finalize the timeline.
Plan to get to Green ‐ Working with project team to identity the core functionalities
needed for the March 2019 release and prioritize them with the development team to
accommodate to reference data mappings till new RDM solution is procured.
39 PSJ
2018 Information Sharing
Environment (ISE) ‐ Phase 2
Information Sharing Environment (ISE) is an enterprise system
that enables data exchanges between all Santa Clara County
Justice and Public Safety agencies, based on key business events.
Additionally, PSJSP ISE provides capabilities to query, analyze,
report, and monitor the information that agencies publish and
subscribe to through the data exchanges. The participating
agencies, as both data providers and consumers, are provided
with APIs and modern web clients that enables data submitting
and data consuming in the managed, monitored and secured
information sharing environment.
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Project Status ‐ The project is in Phase 2 using an agile approach with user involvement.
Each agile sprint includes design, configuration, implementation, testing and support of
features. Features addressed are as per the scope defined by the CJIC Decommissioning,
SVRIA‐DX and PSJ‐DX Projects.
Plan to get to Green ‐ CJIC Decommissioning Project is currently reporting Status as
Yellow. Plan to get to green is aligned with CJIC Decommissioning Project providing
interfaces in time for the Portal to leverage by Fall 2018.
40 PSJ
2016 PSJ Data Exchanges (PSJDX) This project seeks to address the need to track and sequence,
according to priority, data exchange requests for delivery by the
development team(s).
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Project Status ‐ The County interface has been revised to include only Docket and
Warrant with User Acceptance Test scheduled to complete October 5. Referral Tracking
System (RTS) is undergoing a major redesign of the application and it will not have a
connection to CJIC. The PDO Data Exchange is ready for implementation. The proposed
post triage sequence for Exchanges is, in order starting with highest priority POPS. The
outstanding items in the backlog for Development are Probation (awaiting sign‐off),
DTAC (now moving forward with the receipt of data sample from the Court), Pretrial.
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 5
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Project DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)Project Status and Timeline
Tier 3 & 4 Projects
41 PSJ
2019 Public Safety & Justice
Business Intelligence Sol
An integrated and automated approach for data
extraction and reporting processes for Public Safety and
Justice agencies will create efficiencies and bring the
process into compliance with current security
standards.
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Project Status ‐ The PSJ BI project is currently behind schedule in providing data, reports
and support to the various county agencies. This is due to the lack of development
resources to deliver on projects. The PSJ BI team is facing challenges recruiting to fill
vacation positions due to the current competitive job market.
PSJ BI delivered the “Jail to Court Data Extract” for “live” use by Pretrial Services. PSJ BI
delivered the requested data access modifications for “live” use by Palantir. PSJ BI team
continue providing support for Probation BI team continued validation of the data
migrated from DB2 to SQL Server. PSJ BI has started transitioning the load processes so
Probation BI can take over future support and maintenance.
Plan to get to Green: To address the resource issue, the project schedule will be
extended. The focus for the PSJ BI team will be continued support for Probation
migration from DB2 to SQL Server. In addition, the PSJ BI team will schedule only the
highest priority user stories for development.
42 PSJ
2019 Jail Inmate Services Platform Provide WiFi enabled tablets for inmates as part of jail
reform.
$1,440,000 $240,768 $1,199,232
Project Status ‐ The Project is in the final stages of the procurement process and is in the
evaluation step.
Plan to get to Green ‐ The Project Manager will re‐baseline the schedule once the
project moves into the Plan Phase.
43 PSJ
2019 JMS HR Module Add‐Ons The new PSJSP Jail Management System needs payroll
processing functionality.
$12,141,010 $2,323,588 $9,817,422
Project Status ‐ Currently working with ESA to determine a way forward to meet the
specific HR requirements identified for the Sheriff's Office custody staff.
44 PSJ
2019 JMS RFID Inmate Tracking The automatic tracking and logging of inmate
movement inside and outside of the facility will allow
for the identification of an inmate's location at all times.
This project provides an important service to the jail
reform effort.
$33,400 $22,785 $10,615
Project Status ‐ Continued with scope definition and the development of requirements
for the RFP. Continued to work with Procurement to formalize the RFP ‐ RFP number,
structure and content of RFP, and procurement schedules.
45 PSJ
2016 Mainframe Re‐hosting Procure/install replacement hardware and migrate the County’s
legacy mainframe applications, CJIC, JRS and Property Tax, to the
new hardware.
$644,259 $355,910 $288,349
Project Status ‐ Transition of the project to the Shared Services portfolio remains
pending.
46 PSJ
2019 Patrol Dash‐Cams The Sheriff's patrol cars (approximately 200 vehicles)
are equipped with L3 dashboard cameras and an
associated DVR that will reach their end of useful life in
FY 18‐19. Once the equipment is out of support, the
vendor will not provide updates, including security
patches. This project will replace both the cameras and
the storage solution with current technology.
$288,000 $0 $288,000
Project Status ‐ Procurement to provide method for acquisition
47 PSJ
2016 PROB Adult and Juvenile Case
Management System
Replacement of Probation's unsupported Lotus Notes
application.
$16,526,211 $1,865,191 $14,661,020
Project Status ‐ The project is moving out of the Procurement phase into Plan Phase of
the project lifecycle framework. Contract was approved by Board of Supervisors on
September 25.
48 PSJ
2016 PROB Juvenile Institutions Replacement of Probation's unsupported Lotus Notes
application.
Part of PROB Adult
and Juvenile Case
Management
System
Part of PROB Adult
and Juvenile Case
Management
System
Part of PROB Adult
and Juvenile Case
Management
System
Project Status ‐ Probation Executive has made the decision to move forward with the
JMS (IRIS) contract amendment process. The Juvenile Assessment team received high‐
level overview of the contract amendment process and are currently reviewing artifacts.
Project team started conversations with vendor.
49 PSJ
2015 PSJ County Document &
Evidence Exchange System
The overall objective of the enterprise content management
project is to automate and standardize the collection, storage,
access and distribution processes for electronic content
management in the County. By implementing an Enterprise
Content Management (ECM) system, the County of Santa Clara
will enhance the management of unstructured information
throughout the records’ lifecycle, from capture to indexing,
retrieval, and authorized disposal or long‐term preservation.
$4,690,802 $930,792 $3,760,010
Project Status ‐ The Project is continuing in the Procurement Phase. Vendor
demonstrations have been completed. The finalist memo will be drafted, socialized and
submitted for approval.
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 6
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Project DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)Project Status and Timeline
Tier 3 & 4 Projects
50 PSJ
2016 PSJSP Public Safety and Justice ‐ Program Administration $1,925,781 $1,206,174 $719,607
Project Status ‐ The program office administrates the following for all Public Safety and
Justice projects: Communications, Organizational Change Management, Program
Strategic Planning and Scheduling, Requirements Management, Architecture and
Standards, Risk Management, Employment, Staffing Assistance and Assignment,
Procurement and Contract Compliance, Testing and Quality Assurance Oversight,
Continuous Training and Education, Budget Management and Oversight.
51 PSJ
2018 Public Key Infrastructure Provide PSJSP Security Public Key Infrastructure to meet CJIS
requirements
Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ Phase 2 RFP pending ‐ PSJSP would like to separate PKI instance for each
participating LEA pending Steering Committee Approval. PKI project team to review in
July to modify design. Possible impact to schedule ‐ re‐baseline after review.
52 PSJ
2017 Replace Microwave System
Radio
The current countywide microwave radio system and operational
point‐to‐point design does not provide capacity needed to
support SVRCS IP‐based traffic. Manufacturer support for
existing microwave radios was discontinued in 2010. There is
presently no microwave path between County Communications
and the Berger Drive Service Center to facilitate alternate
dispatch operations..
$229,700 $1,410 $228,289
Project Status ‐ The Microwave radios have been received and installed. Some
configuration still must be preformed and 48 volt back up battery system must be
received and installed.
53 PSJ
2016 RRC Referral Tracking Implement a centralized referral tracking system managed by the
Reentry Resource Center to enhance the County’s ability to
coordinate services between agencies, more easily measure
outcomes, accurately track service delivery, and more effectively
allocate resources to support the success of Re‐Entry initiatives.
$2,440,445 $307,959 $2,132,486
Project Status ‐ The project is in the Execute Phase Construction stage using an agile
approach. Currently in progress of redevelopment and data migration. A revised re‐
development timeline has been established and change order has been executed.
54 SHR
2018 Annual Allocation for Security
Projects (CISO)
An annual allocation for a bundle of security projects for the
Chief Information Security Officer (CISO) to proactively deal with
new IT security threats. Security projects include enterprise
access management, data loss prevention, cloud security
gateway, intrusion detection and prevention, Endpoint
Protection, and application development security.
$900,566 $0 $900,566
Project Status ‐
Security projects include enterprise access management, data loss prevention, cloud
security gateway, intrusion detection and prevention, Endpoint Protection, and
application development security – Progress 35%.
55 SHR
2016 Websense Internet
Monitoring System Upgr/Repl
(CISO)
Upgrade Websense infrastructure hardware to better support
decryption of traffic to enable full analysis of sites visited and
pages viewed, and to identify and block malware based attacks.
$333,643 $0 $333,643
Project Status ‐ Infrastructure hardware decryption of traffic to enable full analysis of
sites visited and pages viewed, and to identify and block malware based attacks –
Progress 77%.
56 SHR
2019 Acquire Analytics Toolset for
Applications
The implementation of an analytic toolset will allow IT
to capture performance metrics for Connect, the
County’s data sharing platform application, and for all
ECM developed internal and external County
applications.
$141,600 $0 $141,600
Project Status ‐ The County is currently unable to capture performance information on
most on‐premise web applications. The ECM Analytics Toolset for Applications project
acquires a tool that captures performance metrics on Connect, SharePoint and all ECM‐
developed internal and external applications.
The project team is currently gathering requirements for the new tool, in preparation
for release of an RFP in early 2019.
57 SHR
2018 Annual Refresh Desktops &
Laptops
Starting in FY 17‐18, ISD service rates began establishing a
workstation reserve for the replacement of desktops and laptops
beyond their useful life. This project provides additional base
funding to allow the reserve to begin funding replacements in FY
20‐21. The following departments will be included in this
replacement program:
•County Execu ve Office sub‐units
•Re‐entry Services •Employee Services Agency
•Clerk of Board/Board of Supervisors •Pretrial Services •County Counsel •Office of the Sheriff
•District A orney
•Informa on Services (par al)
$4,558,970 $1,940,573 $2,618,397
Project Status ‐ Refresh of desktops are in progress: Steady progress but needs to pick
up. Extra help hiring is in progress.
58 SHR
2019 Data Center Consolidation
and Upgrade
Initial resources to consolidate data centers from ten to
two. The consolidated data centers will be modernized,
more secure, and reduce overall support requirements.
$1,651,500 $17,271 $1,634,229
Project Status ‐ (As of July 2018) PSJ delivered a proposal for Agreement Authorizing ISD
Staff to Operate and Support IT Systems That Handle CJIS, CLETS and CORI Data to the
Sheriff’s department and County Counsel on the last week of January. PSJ and the
Sheriff’s office were scheduled to meeting on 03/02/18 to discuss if the Sheriff’s
department agrees with the proposal. TSS chose to continue with Data Center
Consolidation and Upgrades at Berger Dr.
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 7
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Project DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)Project Status and Timeline
Tier 3 & 4 Projects
59 SHR
2019 ECM Portal Platform &
Content Management System
The County's current public portal platform is showing
degradation in performance and is unable to maintain
accessibility standards. Replacement of the existing
platform will reduce upkeep and the need for custom
coding, increase security, and provide a more userfriendly
interface.
$1,660,000 $0 $1,660,000
Project Status ‐ The ECM Portal Platform & Content Management System (CMS)
Replacement project moves all public‐facing County websites to a new cloud‐based
environment. The project includes several major activities:
1. Selection of a new technology base and hosting service
2. Design refresh of the standard SCCGOV web site template
3. Construction and configuration of the new cloud‐based platform
4. Migration of more than 90 existing public‐facing web sites to the new environment
The project team is currently gathering requirements for the new platform, in
preparation for release of an RFP in early 2019.
SHR
2017 Implement Volunteer
Management ‐ Phase 2
Project is to migrate the 2nd wave of departments to the county‐
wide Volunteer Management System (VMS) acquired in FY16.
VMS provides the information and processes needed by the
volunteers and volunteer coordinators, such as defining skill
requirements, scheduling volunteers, communicating when and
where volunteers are needed, collecting and reporting metrics,
and providing communications. The VMS also allows potential
volunteers to search for opportunities.
$224,130 $13,494 $210,636 The project is divided into the following sub‐projects, detailed separately as follows:
(a) Implement ROV VMS ‐ Active
(b) Implement OES VMS ‐ On Hold
(c) Implement Animal Shelter VMS ‐ Complete
(d) Implement VMS Enhancements ‐ Active
60 SHR
2017 Implement ROV VMS Add Volunteer Management capability to Registrar of Voters
(ROV) to streamline recruitment and management of ROV
Volunteers.
Part of Implement
Volunteer
Management ‐
Phase 2
Part of Implement
Volunteer
Management ‐
Phase 2
Part of Implement
Volunteer
Management ‐
Phase 2
ROV's review and approval of the vendor project plan occurred in March 2018. During
the review, it became clear that the project could not be completed before the June
election. ROV activities were suspended until July 9th. The project is on track to go live
before the November election.
61 SHR
2017 Implement VMS
Enhancements
The project adds post‐Go Live enhancements to all County
instances of the VMS System
Part of Implement
Volunteer
Management ‐
Phase 2
Part of Implement
Volunteer
Management ‐
Phase 2
Part of Implement
Volunteer
Management ‐
Phase 2
This project adds 5 new features to the County's Volunteer Management System. Three
features ‐ DocuSign Integration, Training & Certifications and Enhanced Sign‐In Station ‐
are complete. One feature ‐ Onboarding Dashboard ‐ has been dropped from the
project. The final feature ‐ Single Sign On is scheduled for completion by November 15,
2018.
62 SHR
2016 IT Asset Management
Implementation ‐ ITAM
The IT Asset Management implementation is now part of the
larger Business Solutions suite. Internal business process
improvement programs were created to ensure IT asset, service,
project and financial service Management solutions are
optimized. The next phase of the asset management
implementation will focus on mapping interactions between
applications, servers, databases, networking and storage devices.
The financial management solution will be migrated to the latest
system update to enhance integration of asset management data
and take advantage of improved functionality for management of
resource capacity and project financials.
$400,000 $97,874 $302,126
Cherwell Service Management (ITSM Tool Implementation): Core team working on
project charter, including iterations break‐down/sequence, WBS and Execution Phase
schedule. The Change Management functionality is desired at the first iterative release.
Project Manager will work with the SMEs and Business Analyst to determine a target
date for completion of the Plan Phase.
Plan to get to Green: When target completion date for the Plan Phase is known and we
have a milestone project schedule, the status will turn back to green.
Aspera SmartTrack (IT‐SAM Tool Implementation): Development of the project
schedule for remaining tasks 98% complete and the County members of the core project
team are ready to move into the Execution Phase. Great progress and negotiation on an
Oct 4th meeting with Aspera, Legal, and Procurement will lead to a new SOW effort
soon.
Plan to get to Green ‐ Once an SOW Execution date is known, the project schedule can
be updated and status will turn back to green.
63 SHR
2018 Jail Network Infrastructure
Capacity Enhancement
This project will look at identifying & implementing an Enterprise
Wi‐Fi solution in which will address the network needs across
multiple justice partners in both the Main Jail and Elmwood
facilities. It will focus on expanding the capacity and coverage
area of the current Aruba Wi‐Fi network to support new Jail
services including the new Jail Management System (JMS) and
Tablets for inmates as part of the Jail Inmate Service Platform
(JISP).
$12,141,010 $2,323,588 $9,817,422
Project Status ‐ The teams focus is on getting agreed upon plans with dates for the
installation. Equipment is in process of being ordered. Delivery expected by end of
December 2018.
Plan to get to Green ‐ The Project to obtain agreement on the installation plan and
dates
64 SHR
2015 Modernize Enterprise GIS
Repository‐Infrastructure
Modernize the ten‐year old Enterprise Geographic Information
System (GIS) Repository and Infrastructure to take advantage of
off‐the‐shelf software or cloud solutions.
$340,000 $9,049 $330,951
Project Status ‐
1) Geocortex Project
Team has completed the public version of viewer (a.k.a. SCCMap) and currently available
as Beta. This project is at socialization phase where team receive feedback from the
expected users.
2) Address Management System
Currently at the procurement phase where proposals were submitted. Team is
expected to finish the evaluation by the end of October.
65 SHR
2019 Oracle Key Vault Database storage encryption keys needs to be
established to provide secure and reliable retrieval of
encrypted data.
$64,800 $0 $64,800
Project Status ‐ The project team is currently gathering requirements for the new
platform, in preparation for release of an RFP in early 2019.
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 8
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Project DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)Project Status and Timeline
Tier 3 & 4 Projects
66 SHR
2019 Oracle Upgrade Upgrade Oracle from 11.2 & 12.1 to 12.2 .DBA team is working
with apps owner to identified which application is supported the
new version.
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ Execution phase:
DBA team upgrading Pretrial, GIS & Peoplesoft databases.
Peoplesoft /1 DEV DB left.
Pretrial, test is done in QA & DEV by DBA, but have dependency on Pretrial team for
testing.
GIS started / it has dependency on application
Estimated to finished by March 2019
67 SHR
2018 Professional Services to Lead
Office 2016 Image Refresh
Upgrade all user PC / Notebook to Windows 10 operating system $211,635 $180,462 $31,173
Project Status ‐ The TSS budgetary transition has a realized risk which was "Disruption to
Business". The ITAM and SSA procurement operations have had to react to the change in
budget and responsibility.
Plan to get to Green: ITAM to provide plan to absorb additional responsibilities in order
to facilitate the load for SSA inventory management.
68 SHR
2019 Replace 33‐x86 Env Project to replace 33‐x86 Servers that have reached the end of
their useful life.
$1,635,200 $0 $1,635,200
Project Status ‐ EIS team is working with Vendor, procurement department, and TSS
team on purchasing process.
69 SHR
2017 Replace Obsolete Nortel
Phone Systems ‐ Phase2
Replace Obsolete Nortel Phone systems with Cisco VOIP. $1,760,616 $339,327 $1,421,289
Project Status ‐ The project status improves to satisfactory. Failover validation between
the two IP Flex circuits was successfully conducted. Following validation, the technical
team worked with AT&T to schedule the SIP Cutover for FAF Junction on September
19th.
Preparations are also well underway to migrate Finance & Department of Tax &
Collections (DTAC) to Cisco on October 17th, 2018.
70 SHR
2019 Replace‐Refresh 10 Storage Network storage, including five SAN switches, two SAN
storage controllers, and two storage arrays have reached
the end of their useful life and need to be replaced.
$884,000 $0 $884,000
Project Status ‐ EIS team is working with Vendor, procurement department, and TSS
team on purchasing process.
71 SHR
2019 Software AG 10.2 Upgrade Technology that drives the Information Sharing
Environment (ISE) has reached the end of its useful life
and needs to be upgraded. The ISE connects Fire,
Ambulance, 911 CAD, and other emergency services
with each other and with other jurisdictions.
$526,600 $217,408 $309,192
Project Status
•Completed end‐to‐end testing of the Pilot environment
•Cutover Pilot environment into production mode (9/18)
•Initiated the provisioning and setup of the Baseline environment, which introduces
additional components on top of the Pilot infrastructure.
•Onboarded IT Consultant for assistance
72 SHR
2019 Solutions Manager
Production on HANA
For support reasons, the County's financial system
needs to be upgraded to centralized management of the
enterprise landscape.
$706,600 $0 $706,600
Project Status ‐ EIS team is working with Vendor on hardware requirements.
73 SHR
2018 TSM Storage Upgrade Upgrading backup storage, and purchased additional storage. $512,802 $0 $512,802
Project Status ‐ We are working on purchasing additional storage for TSM backup. We
are working with procurement to purchase hardware and additional licenses.
74 SHR
2018 Upgrade SAP PBF to SAP SBP The County uses SAP PBF as its system for budgeting formulation
and reporting. SAP will cease to support PBF at the end of 2017,
this will impact the County as the necessary support from SAP
will be lost, improvements to the system will not be performed,
and ability to serve evolving needs will be compromised.
SAP has merged and replaced its PBF and BPC modules to create
SBP. SBP comes equipped with enhanced usability and more
capabilities than PBF. The project will implement the upgrade
from PBF to SBP, and assess if any of the added features can be
incorporated into the currently used functions.
$996,047 $61,303 $934,744
Project Status ‐ Project is on track. All forms and some of the reports have been
transported to QAS for Unit testing. The Project Team is working on a cutover plan to
prepare for system rollout. The Security Team is working on all of the newly added roles
and tests in QAS.
75 SSA
2018 APS SDM Develop and implement a Structured Decision Making web based
tool to utilize a systemic and evidenced based approach to
evaluate present and future risk, and informed decision making.
$581,850 $338,393 $243,457
Project Status ‐ Screening and response priority integration tasks are being tested. IRR
testing and analysis is completed. Risk and Strengths & Needs tools are being
programmed by NCCD. Business is requesting to postpone the implementation of 3rd
and 4th tools from November 2018 to early 2019. Vendor is drafting a no cost extension
of the project and is updating project tasks and timeline.Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 9
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Work DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)Executive Status Summary
1 CoA
2017 Customer Relationship
Management (CRM)
Dynamics
Project to continue enhancements and possible development of
new features to leverage maximum use of current CRM system
and revise work flow functionality.
$50,000 $0 $50,000
Project Status ‐ CRM Dynamics App is in use within EOD and LR. EOD Users have
requested several minor enhancements, and TSS is working to onboard a vendor to
complete this work. EOD Reasonable Accommodation application on CRM.
2 CoA
2019 PRK Parks Website
Upgrade
Updates and enhancements are needed to the Parks and
Recreation's public website to meet the County's initiative of
standardizing its branding and publicpresence. This project will
migrate the Parks website to the new standard template to
provide a better look and feel, offering robust mobile support,
additional features,and improved accessibility and usability.
Existing resources will be used to complete this project.
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ Project kick off completed. The project will include
‐ upgrades to the templates to bring them to current standards
‐ responsive design for better mobile experience
‐ content refresh to better serve customer needs
3 CoA
2019 PRK Pixie Dust (Parks
Mobile Apps)
Developing Parks and Recreation specific applications will enhance
the citizen experience by offering access to data and applications
via mobile devices at park locations. This project will be
implemented with existing resources.
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ Discussions with business owners have been initiated to understand
what are potential areas for mobile content to serve up for both visitors and staff. This
phase of the project is to identify and propose options for mobile content
4 CoA
2019 PRK Museum 2.0 Moving the Casa Grande Park archive data to the cloud will take
advantage of periodic updates and provide easy access to
information for customers as part of the Parks customer
satisfaction measure. The database is home to information
regarding artifacts in the Casa Grande Museum. This project will be
implemented using existing resources.
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ Pending Vendor readiness for new SaaS version to be released. Vendor
indicated next update will be available Oct end / November
5 HHS
2018 HHS Computer Assisted
Coding Software
Solution
HHS Computer Assisted Coding Software Solution Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ Overall Project health is Green.
Project is almost complete, there are a few pending items to validate with the Vendor
in order to fully close out the project. The project has been transitioned to Vendor
support.
6 HHS
2019 InSight Sepsis Study Current sepsis mortality range for VMC is 14‐19%, would like to
bring it down to 7‐10% if not lower.
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ Completed project discovery package and HHS scoring, project charter
draft, security review, compliance review, and technical feasibility assessment.
Currently waiting for IT Data Governance Group ITDGC’s approval to kick off project
officially (ETA mid September) and to proceed with the MOU/contract (no ETA)
7 HHS
2017 Stroke Clinic Rapid
Image Viewing System
RAPID is a Linux‐based system integrated into the DICOM network
via TCP/IP, within the firewall that receives scans from scanner
modalities and sends processed data to PACS and also sends de‐
identified (non‐PHI) data via the SMTP (email) server to a
predetermined email distribution list. All data are purged from
RAPID after delivery to PACS.
Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ Single Source Request to procure was approved by Procurement.
Currently going thru final stages of contract negotiation .
8 HHS
2018 Therapy Services Pt
Scheduling System
Software
The Therapy Services Patient Scheduling System Software is an
inpatient scheduling and treatment management tool that will
support Therapy Services to meet the reimbursement standards
set forth by CMS/Centers for Medicare & Medicaid Services for
inpatient rehabilitation treatment. The system tracks daily
treatment times and flags patients who require additional therapy.
The system interfaces with HealthLink in ADT segment and also
generates printed treatment reports.
Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ Project is in implementation stage with a GO‐LIVE date of 11/12/2018.
County EPIC ADT interface will be turned on 11/4/2018, so the data can flow thru to
the Mediware system. On target for GO‐LIVE on 11/12/2018
9 HHS
2018 VMC PMM Upgrade Upgrade PMM to version 16 Information
unavailable
Information
unavailable
Information
unavailable
Project Status ‐ The project status improves to satisfactory. The Sponsor has approved
a revised go‐live date of 5/18/19 that is based on HealthLink 2018 Upgrade resource
availability, v17 validation requirements as well as hospital staff’s training needs.
Following signed contract agreement, and PO to vendor, project planning has
commenced that included Project Charter, High‐Level Timeline and Security
Questionnaire reviews with TSS Security & Infrastructure, Materials Management, and
Allscripts. Project kick‐off has also been scheduled for October 11th that will mark the
formal beginning of the project.
Tier 1 & 2 Projects
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 10
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Work DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)Executive Status Summary
Tier 1 & 2 Projects
10 PSJ
2018 Infrastructure for PSJ
Projects ‐ Phase 2
Infrastructure for PSJ Projects ‐ Phase 2 Part of County
Justice Information
Center
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Project Status ‐ Project Charter Draft completed. Obtained Infrastructure‐systems,
hardware estimates. Exploring Cloud option as Primary Data center for PSJ. ISE Changes
(provision two ISEs. One would be for LEAs only, and the other for non‐LEA data
sharing primarily from the Court). POC for ISE on the Cloud completed with success.
11 PSJ
2019 Kronos Clock
Replacement
Fifteen timekeeping clocks operated by the Sheriff Office are not
compatible with the latest version of the County's time‐tracking
software and need to be
replaced.
$67,500 $67,327 $173
Project Status ‐ Sheriff's Office has received 17 Kronos Clocks for the Kronos Clock
Replacement Project and the installation for these clocks is in progress. Three clocks
remain to be installed. Estimated installation date, per the Sheriff's Office is Nov/Dec
2018.
12 PSJ
2018 PSJSP DR Strategy Since the PSJSP IT DR capability is a complex and critical
undertaking, the effort will be divided into two parts. The first part,
the PSJSP IT DR Strategy will first capture the requirements for the
DR capability, document the constraints within which the
capability must operate, identify the criteria for weighing options
for addressing the need, study the available options along those
criteria, and involve the appropriate cross‐section of technical
experts as well as management and agency stakeholders in the
review and adoption of the strategy.
The second phase will be part of the PSJSP Infrastructure Phase 2
project and use the adopted
strategic direction to drive out the tactical execution to
implement, document, and test the IT DR
capability and ensure its operational readiness long term.
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Part of County
Justice Information
Center
Project Status ‐ Gathered and compiled all PSJSP Infrastructure Capacity data and Effort
Estimates. Team reviewed different options such as On premise, Third Party hosting,
Cloud. Next step is to make decision and to select appropriate a DR solution that will
meet recovery requirements, budget and organizational constraints
Plan to get to Green ‐ Need resources for reviewing and reevaluating DR Strategy
proposal. As of 10/4, we are not making any progress for months. That is due to the fact
the assigned resource is not available to work on reviewing and re‐evaluating existing
DR Strategy and to include Dual ISE, Cloud and On Premise options.
13 PSJ
2017 Replace Animal Control
Radio
Replacing/upgrading Animal Control mobile and portable radios. $2,315 $0 $2,315
Project Status ‐ The Radios have been received and aligned and letters authorizing use
of San Jose Animal Control and County Parks have been received. The project is in a
transition phase waiting for the completion of the Silicon Valley Regional
Communications System (SVRCS). Overall the project is 80% complete. The Project
completion will coincide with the completion of the SVRCS estimated in May '19.
14 SHR
2019 Apptio R12 Upgrade Technology Services and Solutions (TSS) implemented Apptio
Technology Business Management (TBM) to support the
organization’s rate and budget development processes. This cloud
application (SAAS) allows users to understand billing rate cost
drivers and provides visibility and transparency into the cost of the
IT services delivered to the County and Non‐County customers.
This project will upgrade Apptio to the R12 version. This will make
IT related processes more efficient by utilizing a standardized
model and by implementing the newest Cost Transparency, Cloud
Cost Management integration, and Bill of IT modules.
Part of IT Asset
Management
Implementation ‐
ITAM
Part of IT Asset
Management
Implementation ‐
ITAM
Part of IT Asset
Management
Implementation ‐
ITAM
Project Status ‐ The Statement of Work was negotiated and approved by the Board of
Supervisors in October 2018. Preliminary planning is complete and the formal kick‐off
took place in October. The upgrade includes Cloud Cost Management, a more robust
Bill of IT and improved cost transparency features that will allow for better integration
of Cherwell, Aspera and Planview data. The upgrade is on track for an April 2019
completion date.
15 SHR
2018 Business Object/Data
Services Migration
SAP BO Data Services (BODS) is an ETL tool used for data
integration, data quality, data profiling and data processing. It
allows you to integrate, transform trusted data‐to‐data warehouse
system for analytical reporting.
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ Execution Phase:
Project Team is waiting for a contractor resource from the Procurement Department in
order to move forward. This project belongs to Procurement and resources are needed
from the business.
16 SHR
2018 HHS Unix Server
Upgrade or
Decommission
We are consolidating datacenter in SCC. We need to upgrade, or
migrate Unix servers to the supported operating system in HHS.
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ We need to upgrade or decommission 26 Linux servers to supported
OS.
1‐ Five Servers Upgraded
2‐ Three Servers can't upgraded now.
3‐Ten servers are appliances and IS don't have access top them
4‐ Four Servers decommissioned
5‐ Four servers already have supported RedHat OS
17 SHR
2018 HHS Windows Server
Upgrade or
Decommission
EIS division is working with HHS team to migrate all the physical
servers to virtual in HHS campus.
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ There are 139 physical active windows servers in HHS that need to
decommission or move to the Virtual system.
1‐ 10 servers migrated.
2‐ 27 servers in progress of migration.
3‐ 25 servers on hold due to management decision on SQL strategy.
4‐ 11 servers will stay physical now.
5‐ 22 servers decommissioned.
6‐ 10 Servers not supported by HHS/IT.
7‐ 15 servers / we are waiting for application owners’ response.
8‐ I still need to reach out to 21 server owners by September.
‐ Our major issue is lack of Technical resources; some of these migrations are major
projects (Pharmacy, iCal, Public Health, VHP).
Plan to get to Green ‐ Management has been engaged to contract resources to fulfill
the Server Engineer role. The Project Manager is actively working to elicit business
owner cooperation at the HHS site.
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 11
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Work DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)Executive Status Summary
Tier 1 & 2 Projects
18 SHR
2018 IBM XiV Storage Array
Migration
IBM XiV storage array migration project. The storage is out of
support and we need to migrate all the LUNS and data to another
storage.
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ Execution:
There’s still data on the following LUNS.
HHSXIV_AOB1: 24 LUNs – 7.01 TB
HHSXIV_AOB2: 9 LUNs – 25.9 TB
HHSXIV_RA: 16 LUNs – 19.21 TB
•Working with application owners about migrating raw data mapping disks to Unity.
•We need to purchase additional disks.
•We need to extend the warranty.
19 SHR
2018 Installing Cylance in HHS
Servers
In an effort to protect citizen’s information, the Information
Security Office, in collaboration with TSS‐Health Systems staff is
installing Cylance on all HHS servers. This installation will provide
protection against security threats such as ransomware.
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status
‐ Cylance is installed on 378 Servers out of 628 servers
‐ 130 Non‐Epic Servers (Test,QA,DEV,PRD)
‐ 220 Citrix Servers
‐ 28 Epic Servers
‐CAG team installed SCCM agent in 166 servers.
‐We still have 200 production servers that are scheduled to be done by the end of
October.
20 SHR
2018 Installing Cylance in SSA
Servers
In an effort to protect citizen’s information, the Information
Security Office, in collaboration with TSS‐Social Service staff is
installing Cylance on SSA servers. This installation will provide
protection against security threats such as ransomware.
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ We have installed Cylance on all the SSA servers, but CISO is working
with SSA application owner to move them to protect mode. There are only 10 servers
left to move to protect mode.
21 SHR
2019 TSS Oracle Multitenant Multitenant provides a high‐level database consolidation service
using fewer server resources and providing rapid provisioning and
cloning of databases, rapid patching and upgrades, and the ability
to manage multiple databases at once.
$171,600.00 $0.00 $171,600.00
Project Status ‐ DBA team is working with Vendor, Procurement department, and TSS
team on the purchasing process.
22 SHR
2018 Isilon Relocation to
Sobrato
TSS‐HS is moving one of the Isilon (HHS‐File share system) to
Sobrato building
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ The Project Team is engaged with the Vendor and are working on detail
planning.
23 SHR
2019 Oracle Real Application
Testing (RAT) Tool
An application testing tool will allow for performance testing of
County databases when databases are upgraded and enable
comparison of baseline performance measurements.
$254,015 $0 $254,015
Project Status ‐ DBA team is working with Vendor, Procurement Department, and TSS
teams on the purchasing process.
24 SHR
2019 Purchase VEEAM Backup
Software
Additional backup software licenses are needed to support
enterprise data backups estimated to grow to 1500 terabytes.
$214,800 $0 $214,800
Project Status ‐ EIS team is working with the Vendor, Finance and Procurement
departments to purchase the product.
25 SHR
2019 Replace EPIC p770
Servers
The EPIC p770 servers (2 node HACMP cluster) that have reached
the end of their useful life need to be replaced.
$476,600 $0 $476,600
Project Status ‐ EIS team is working with Epic team to collaborate on requirements. In
addition, EIS team is working with the Vendor, Procurement Department, and TSS
teams on the purchasing process. This project is dependendant on moving Epic
Production to the Sobrato building.
26 SHR
2019 Replace Refresh TSM
Backup Servers
Backup servers that have reached the end of their useful life need
to be replaced and expanded to provide additional backup
capability to meet increasing demand.
$250,000 $0 $250,000
Project Status ‐ EIS team is working with Vendor, procurement department, and TSS
team on purchasing process.
27 SHR
2018 Replacement of TSS
supported End‐of‐
Support Cisco
Purpose: There are approximately 516 end‐of‐support Cisco model
phones that need to be replaced. The locations are primarily the
DA Crime Lab and many other remote locations where VOIP was
initially installed in 2007. Licensing is not needed and only
replacement of specific model handsets are required.
$120,594 $77,812 $42,783
Project Status ‐ Santa Clara County is in the process of migrating approximately 3000
Nortel users to the existing Cisco Unified Communications Manager (CUCM)
Information Services Department (TSS) cluster.
In preparation for the migration to SIP, all non‐E.164 compatible phones are being
replaced with E.164 compatible phones.
The updated timeline will provide adequate time for deployment and project close‐out.
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 12
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Work DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)Executive Status Summary
Tier 1 & 2 Projects
28 SHR
2019 Scale Arc Purchase and installation of Scale Arc database performance
monitoring on a test and production server
$270,500 $0 $270,500
Project Status ‐DBA team is working with Vendor, procurement department, and TSS
team on purchasing process.
29 SHR
2018 SCC SQL Migration TSS is consolidating and upgrading all SQL Databases based on
Departments. We upgrade all the SQL to the 2016 version, and
separate them by departments, QA,DEV and development servers.
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ Execution Phase:
22 servers built done,
Migrating databases are in the progress.
98 DEV‐72 completed
47 QA‐31 completed
58 PRD‐26 completed
We have 5 more PRD on pipeline by end of September.
Plan to get to Green ‐ There are not enough technical resources within the ECM team.
Management is aware of this issue and we are in the process of hiring additional
resources to help move this project forward.
30 SHR
2018 SSA Consolidation SCC is consolidating datacenters and multiple department. TSS‐
Enterprise Infrastructure Support is working with SSA IT staff to
migrate, upgrade or decommission systems.
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Project Status ‐ Execution Phases:
1‐ SSA start with 26 servers.
A: 24 Servers decommissioned.
B: 1 Server is underwork by DBA team.
D: 1 Server is underwork by Windows team.
E: 4 Servers are test environment.
31 SSA Decision Point
Management
Create dynamic dashboards with drill downs for the following 4
reports: Case child demographics, Referral child demographics,
Quarterly referral tracking on disproportionality, and
Disproportionality tracking report.
$1,321,255 $1,205,733 $115,523
Project Status ‐ Prototype of zip referral (entry cohort) demo to team. BRD for Case
Dashboard and COC posted on BO site. Need to get more info from business on drill
down data.
32 SSA DEBS DW ‐ Phase 2 Phase 2 of DEBS DW and Business intelligence: Caseload, Pending
Application, Disposition.
$558,340 $394,452 $163,888
Project Status ‐ Continued the development of BI dahsboard for the 3rd iteration
(Application Processing Time / Disposition) . and "DEBS phone data" dashboards. Due
to the phase out of Adobe Flash, extend the scope and schedule to convert Xcelsius
dashbaoards with SAP Lumina.
33 SSA HR Dashboard ‐ Phase 3
(Movement &
Retention)
Dashboards to track the movement and retention of SSA
employee.
$529,844 $138,816 $391,028
Project Status ‐ Project is on schedule. Continued working on the business
requirements and indentifying data required. Working on the business rules for
different KPI's.
34 SSA OCM Workflow System,
Phase I
This project is to procure a Contracts Management System for
Office of Contracts Management (OCM) to track and maintain all
the contracts with Social Services Agency.
Phase I is to capture their business processes and requirements to
prepare for system procurement.
$4,694 $4,294 $400
Project Status ‐ OCM is consulting with SSA Executives on next steps.
35 SSA DAAS ‐ In‐Home Support
Services (IHSS) Quality
Assurance Web
Application
Replacing existing FileMaker Pro files, the project aims to develop
a web‐based tool to track work efforts associated with Quality
Assurance activities for the IHSS program.
$315,409 $140,917 $174,492
Project Status ‐ Further enhancements to the Fraud Module for the IHSS Quality
Assurance Applicaiton was developed to comply with new State regulations pertaining
DHCS cases. The project team is continuing to work on two modules concurrently ‐ Fair
Hearings and Unannounced Home Visits. We are in the process of developing
functionality for the two modules based on wireframes that were reviewed and refined
with operations. Another project resource has been developing the quarterly Fraud
Reports out of the new database and will be scheduling this for quarterly runs.
36 SSA Resource Family
Application Tracking
System
Develop a system to track DFCS Resource Family Approval (RFA)
candidates for the placement of children in a timely manner.
CWS/CMS does not have the capability to report on such vacancies
in real time.
$391,392 $322,931 $68,461
Project Status ‐ The Project Sponsor has decided to pursue procurement of the BINTI
solution. As such, we have begun engaging operations with requirements for the
creation and submission of the APD to the State for approval to proceed with the
procurement of the BINTI product and service. Accordingly, this project will revert back
to the Initiate phase.
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 13
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Work DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)Executive Status Summary
Tier 1 & 2 Projects
37 SSA SSA Windows 10 and
Office 2016 Rollout
Implement Windows 10 operating system across SSA and upgrade
MS Office Suite to 2016.
$218,599 $140,739 $77,860
Project Status ‐ A majority of SSA applicaitons have been tested, packaged and ready
for deployment. The remaining applications are in various stages of testing or package
creation. We have seven applicaitons that need to be upgraded to a newer version
before package requests can be submitted. Concurrently, users from across SSA have
been coming to the Windows 10 test lab to conduct UAT with web applicaitons; we are
looking to complete this by the end of August.
38 SSA DFCS ‐ RAIC Dynamic
Dashboards (Receiving,
Assessment, and Intake
Center)
A dynamic dashboard that allows end user to view Receiving,
Assessment, and Intake Center (RAIC) data and information in an
interactive and dynamic way. Data would be pulled from the RAIC
database, from information gathered during the intake procedures
that track and coument children entering RAIC and/or receiving
services from RAIC.
$110,187 $12,967 $97,220
Project Status ‐ The project is in the initiate stage. Project is currently in planning
stages, pending final Business decisions and mapping of Business requirements. 2018
08; This is currently with no movement from last month pending business internal
discussion on how to proceed.
39 SSA DEBS IEVS:
Overpayment and Tally
Computations
Enhancing the new IEVS application to include the ability to
compute monthly overpayment amounts and generate a weekly
tally report for each EE.
$361,968 $110,338 $251,630
Project Status ‐ Release II deliverables UAT complete. BRD in process of being finalized
for both releases. 2nd developer is concurrently working on prototype of OP app.
40 SSA DEBS VSAS: Additional
Functionality and
ABAWDs
Provide automation that is not provided through CalWIN to
appropriately manage ABAWDS and refer to the appropriate
vocational services.
$340,346 $270,226 $70,120
Project Status ‐ Release II went live . BRD being updated. for release 3 .
41 SSA IDM Datacap OCR &
eDoc Implementation
This is Phase 3 of the Datacap implementaton for IDM. Project is to
develop the IDM OCR applications in Datacap to replace Kofax, by
November, 2018. Kofax contract ends in December, 2018.
$120,000 $10,560 $109,440
Project Status: Continue to work with consultant to develop and test the quick,
automated and distributed scan jobs to replace Kofax. BCW and BCW Periodic
Reporting modules are ready for UAT; OPEX jobs are ready for unit testing; and Return
Verifications and New Intakes jobs are being developed. Next steps: Continue to unit
test the modules and prepare for UAT.
42 SSA DEBS SSI Housing and
Disability Advocacy
Program
Based on a joint venture with Office of Supportive Housing and a
grant from HDAP, enhancements to the SSI application need to be
made to support the new program for SSI recipients.
Enhancements will include adding data elements to SSI application
to collect client demographic and participation data required for
State reporting.
$25,000 $400 $24,600
Project Status: Kicked off the project with Supplemental Security Income (SSI) Advocacy
staff and management analyst and began collecting business requirements to
implement the Housing and Disability Advocacy Program (HDAP) and update the SSI
App. Next steps are to compose and finalize the Business Requirements Document
(BRD), finalize the list of State required data for reporting and begin designing and
developing the HDAP tab for the SSI App.
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 14
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Project DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)
1 CoA
2019 Capital Project ‐ Strategic Space Management A capital project and space requests tracking system will automate the process and
integrate it with the County's real estate assets data from Facilities Management to
allow better and more timely decisionmaking and traceability. Project allocation
provides resources for a project discovery phase. Additional funding from the IT Capital
Reserve or other sources may be needed after a project scope and estimate is
developed.
$100,000 $0 $100,000
2 CoA
2019 CCO California Public Records Act (CPRA)
Website
An intake portal for California Public Records Act Requests (CPRA) will facilitate the
proper routing of requests, coordination with departments, assignment of an attorney
if applicable and tracking of requests to ensure timely responses per Ordinance Section
A17‐12.
$350,200 $0 $350,200
3 CoA
2019 CCO Case Management & Billing System
Modernization
Replacement of the County's case management application with a new application will
meet County Counsel's needs. Project allocation provides resources for a project
discovery phase. Additional funding from the IT Capital Reserve or other sources may
be needed after a project scope and estimate is developed.
$50,000 $0 $50,000
4 CoA
2019 CEO Contracting SQL Database A comprehensive database will allow for the compilation of data from the disparate
systems to be used in the source‐to‐pay process of contracting and procurement.
$106,600 $0 $106,600
5 CoA
2019 CEO Driving to Net Zero Website Developing a web portal will enable better communications and sharing of information
with the County's partner jurisdictions. Driving to Net Zero is a grant‐funded
collaborative project surrounding the deployment of electric vehicle infrastructure
across the County. This project will be implemented with existing resources.
Combination of
State grant funding
and Department
match funding
Information
unavailable
Combination of
State grant funding
and Department
match funding
Information
unavailable
Combination of
State grant funding
and Department
match funding
Information
unavailable
6 CoA
2019 CEO Employee Wellness Campaign Builder
Enhancement
Enhancements and additional features to the Employee Wellness custom activity
tracker application will improve employee health.
$70,000 $0 $70,000
7 CoA
2019 CEO Employee Wellness Health Club Directory Developing an online Employee Wellness Health Club Directory will provide
information of local health clubs offering discounts to County employees.
$32,000 $0 $32,000
8 CoA
2019 CEO Employee Wellness Lending Library Automating the County's Wellness Lending Library will provide resources to County
employees for personal development.
$20,000 $0 $20,000
9 CoA
2019 CEPA The Daily Application Redesign of the application used to manage agriculture weights and measures
operations and reporting.
$246,600 $0 $246,600
10 CoA
2019 COB Assessment Appeals Track Faster Better An automated status tracking system for assessment appeals will be implemented with
existing resources.
$265,000 $0 $265,000
11 CoA
2019 COB BOS Chambers Equipment Refresh Broadcast equipment in Board Chambers has reached the end of its useful life. Project
allocation provides resources for a project discovery phase. Additional funding from the
IT Capital Reserve or other sources may be needed after a project scope and estimate is
developed.
$120,000 $0 $120,000
12 CoA
2019 COB Commission and Board Online (CABO) This project will assess and implement Clerk of the Board record tracking that conforms
to required laws and ordinances and improves the operational process. It will also track
support for Assembly bills and trainings and provide detailed reports for County Boards
and Commissions. Project allocation provides resources for a project discovery phase.
Additional funding from the IT Capital Reserve or other sources may be needed after a
project scope and estimate is developed.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
13 CoA
2019 DEH Database Azure Migration Migrating the Department of Environmental Health (DEH) departmental database to
the cloud will allow access to real‐time data for both field staff and their supervisors.
$13,400 $0 $13,400
14 CoA
2019 DPD InSite Business License Module and
Automation
The workflow management tool will be extended to include business licensing and
provide an online mobile citizen portal. Project allocation provides resources for a
project discovery phase. Additional funding from the IT Capital Reserve or other sources
may be needed after a project scope and estimate is developed.
$400,000 $70,680 $329,320
15 CoA
2019 FAF Fleet Fuel System Replacement Replacement of the Fleet fuel system will provide greater reliability and data for County
departments.
$166,600 $0 $166,600
16 CoA
2019 ROV SCCVOTE Website and Mobile App
Enhancement
Development of a SCCVOTE web portal and mobile application will support the vote
center model that require the implementation of four State certified systems (Next Gen
Voting System, Electronic Poll Book, Ballot on Demand Printers, and Remote Accessible
Vote by Mail).
$83,200 $0 $83,200
17 CoA
2019 ROV TrackIt Application Enhancement Automating the processing of provisional envelopes received in elections will improve
accountability. Project allocation provides resources for project discovery only.
Additional funding from the IT Capital Reserve or other sources may be needed after a
project scope and estimate is developed.
$50,000 $0 $50,000
18 CoA
2019 ROV Voting System and Technology
Modernization
Replacement of voting system and associated technologies to support SB450, the
Voters Choice Act, will enable ROV to move toward a voting center model and mitigate
the risk of failure from aging nonsupported equipment.
$90,000 $0 $90,000
19 FES
2019 AES Commercial Appraisal Application A commercial industrial appraisal application for the Real Property Division of the
Assessor's Office will address data tracking and management of multi‐use properties
developed throughout the County. Project allocation provides resources for a project
discovery phase. Additional funding from the IT Capital Reserve or other sources may
be needed after a project scope and estimate is developed.
Information
unavailable
Information
unavailable
Information
unavailable
20 FES
2019 ASR Replacement Assessment System Developing business requirements, analyzing alternatives and performing pilots will
prepare the Assessor’s Office for a broader implementation project relating to the
modernizing of the Assessor's Assessment System.
$600,000 $495,000 $105,000
21 FES
2019 Broker Appointment Intake through DocuSign Update and automation of the County's digital signature process used to appoint
brokers will improve efficiency. The system will include data validation, attachment
management, and signature routing in one process.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
22 FES
2019 Broker Commission Automation & Portal A broker portal, providing insurance brokers the option of self‐service, access and
control over their book of business, will improve efficiency.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
Approved Projects/ No status reported to date
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 15
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Project DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)
Approved Projects/ No status reported to date
23 FES
2017 Broker Commissions Automation First year and renewal Broker commissions are currently paid on a tiered structure
based on the number of active members enrolled by the agent. The amount per active
member is paid as a one‐time payment for the year and invoicing is processed manually
for each broker, demanding 50% of available work time. The Sales & Broker Relations
department is requesting a project that will transition the payment of broker
commissions from the current process to one that reflects the industry standard of
dispersing commissions on a per member per month (PMPM) basis to reduce
overpayment of commissions. In order to accurately and efficiently process broker
commission payments on a PMPM basis and continue to fulfill the job responsibilities
required of the Sales Department an organizational change and technical support to
automate broker payments is needed.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
24 FES
2019 California Immunization Registry (CAIR) Data
Feed
Creating an interface to the California Immunization Registry will improve quality of
care and ensure that members receive timely, effective, and efficient care. This project
will be implemented with existing resources.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
25 FES
2019 Classification Studies & Modifications Database A classification studies database will manage classification studies and modifications
within ESA.
$123,400 $0 $123,400
26 FES
2019 Cloud Integration Gateway Upgrade for Ariba Upgrading the Cloud Integration Gateway interface between the County's procurement
and financial systems is needed because the current version is no longer supported by
the vendor.
$150,000 $0 $150,000
27 FES
2019 Consumer Engagement/Newsletters Require a vendor to produce member and provider communications
for regulatory and accreditation purposes with potential to send print and email.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
28 FES
2019 ESA ‐ Labor Relations CRM Tech Support Enhancements to Labor Relations' internal portal and CRM system for electronic case
management will be implemented with existing resources.
Information
unavailable
Information
unavailable
Information
unavailable
29 FES
2018 HHS migration to SAP ECC/PBF The Hospital and Health System (HHS) currently maintains its own financial records in
detail within its own systems ‐ Sun for GL, CPM for Budget.
Sun and CPM sends summarized information to the County's Ledger system of record
(SAP, PBF respectively).
Because of this 2‐system solution, the processing of financial information for HHS is not
optimally efficient. Workflow includes manual/ redundancies, and the processing
calendar is difficult to synchronize between the two systems. This project will expand
the County's SAP functionality to fully serve the existing Sun and CMP functions, with a
target to eventually decommission the Sun and CMP systems. This will result in a
smoother workflow, more efficient processing, easier to align calendars, and the
avoidance of costs to run a separate Sun/CMP solution.
A recent audit shared with the Board of Supervisors that it was difficult to tie the
Sun/CPM information with SAP ECC/PBF. The Board supports this project.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
30 FES
2019 Human Resources Recruitment Statistics
Automation
A new reporting system will automate the aggregation data from NeoGOV, the County’s
employee management system, and the County’s financial management system into a
single recruitment report. This project will be implemented with existing resources.
Information
unavailable
Information
unavailable
Information
unavailable
31 FES
2019 Member and Provider Web Portals Member and provider web portals will facilitate access for members, providers, brokers
and employer groups to information on eligibility, claims status and authorizations and
to comply with National Committee for Quality Assurance (NCQA) requirements. NCQA
accreditation is a requirement to remain a Covered California Qualified Health Plan.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
32 FES
2019 PayNearMe This method will allow Covered California and Individual and Family Plan members the
ability to pay premiums online, via a mobile app and at local CVS and 7‐11 retail stores.
This project will be implemented with existing resources.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
33 FES
2019 QNXT Upgrade VHP is currently out of compliance with its warranty on it QNXT system
and need to upgrade the system to become compliant. VHP currently pays time and
materials for any issue that needs to be address within the software as the vendor no
longer supports product defects due to the outdated version of the software.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
34 FES
2019 SAP Business Analytics for HHS A new analytics tools will improve the quality of business analytics performed on
SCVMC's financial and operational systems providing management and executives with
better information for timely decisions. Project allocation provides resources for a
project discovery phase. Additional funding from the IT Capital Reserve or other sources
may be needed after a project scope and estimate is developed.
$50,000 $0 $50,000
35 FES
2019 Scanning Due to Space Constraints Developing the project management, business analysis, documentation of business
requirements to prepare for the eventual mapping/indexing and scanning of the
existing 1.8 million pages of documents in ESA. Additional funding from the IT Capital
Reserve or other sources may be needed after a project scope and estimate is
developed.
$333,400 $0 $333,400
36 FES
2019 Tracking Performance Evaluation Forms Developing a performance appraisals tracking system will address the Grand Jury
recommendation report from June 2017. This project will be implemented with existing
resources.
Information
unavailable
Information
unavailable
Information
unavailable
37 FES
2019 Update of Countys Central Time Management
Solution
The update to the County's time management system will include new features and
improve stability.
Information
unavailable
Information
unavailable
Information
unavailable
38 FES
2019 VHP Network Website A web portal will provide consumer information for non‐commercial products (e.g.
Medi‐Cal, PCAP, Healthy Kids, and Valley Kids) with the goal of reducing inbound calls to
Member Services. This project will be implemented with existing resources.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
39 HHS
2019 Credentialing for Nurses & Ancillaries A new credentialing system will be the single repository for all professional credentials
and certificates in HHS and automatically refresh downstream scheduling and learning
management systems.
$50,000 $0 $50,000
40 HHS
2019 EPIC 2018 Hardware Upgrade Upgrading the HealthLink (EPIC) server will meet EPIC 2018 requirements for the
anticipated November 2018 system update launch.
Information
unavailable
Information
unavailable
Information
unavailable
41 HHS
2019 HealthLink Bones (Ortho) Upgrade the EpicCare Ambulatory platform for orthopedics to accelerate routine office
visit workflows, improve ordering, and gather data for submission to the American
Joint Replacement Registry (AJRR).
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
42 HHS 2019 HealthLink Chronic Dialysis Implement software to allow the dialysis Department to manage and track quality
improvement initiatives and automates dialysis charging.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 16
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Project DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)
Approved Projects/ No status reported to date
43 HHS 2019 HealthLink Customer Relationship Management Provide an integrated solution to track customer service inquiries, responses and follow
ups required.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
44 HHS 2019 HealthLink Rehab Implement a module allowing therapists an appropriate workspace to document
therapy minutes, review therapy information, simplify charge calculations and g‐code
documentation.
Information
unavailable
Information
unavailable
Information
unavailable
45 HHS 2019 Healthlink Transfer Center Implement a module that synchronizes data between a patient movement request and
the patient's hospital encounter eliminating duplicate data entry.
Information
unavailable
Information
unavailable
Information
unavailable
46 HHS 2018 HHS IS AOB Computer Room UPS Upgrade Upgrade AOB computer room Uninterruptable Power Supply (UPS). Current system is
end of life and must be replaced.
Information
unavailable
Information
unavailable
Information
unavailable
47 HHS 2018 HHS IS Epic Tapestry Implementation of Tapestry for HHS (VMC & VHP) for managed care, enrollment &
benefits, utilization review, chronic disease case management and PlanLink.
Implementation costs for Epic and Consultants included in one‐time costs. Operational
Costs include FTE's and maintenance for 3 years (FY19,FY20,FY21)
Information
unavailable
Information
unavailable
Information
unavailable
48 HHS HHS IS Interface Engine (OpenLink) Replacement RFP and implementation of interface engine to term the contract with Siemens for
OpenLink
Information
unavailable
Information
unavailable
Information
unavailable
49 HHS 2018 HHS IS Master Patient Index (MPI) Solution RFP and implementation of a Master Person Index solution for HHS Enterprise. Information
unavailable
Information
unavailable
Information
unavailable50 HHS 2019 Interface Engine for Cerner OPENLink A new interface engine that connects HealthLink to other systems servicing the hospital
will be more efficient and reliable and easier to configure and reconfigure.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
51 HHS 2018 Nursing Administration ‐ Epic Rover for iOS
phone
Epic is the vendor. This is a bedside charting and scanning system. Record
documentation and barcode validation at the point of care.
Information
unavailable
Information
unavailable
Information
unavailable
52 HHS 2019 OPPE Medical Administration Creating the required reporting system will facilitate SCVMC compliance with ongoing
provider performance evaluation (OPPE) for medical staff. This project will be
implemented with existing resources.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
53 HHS 2019 Patient Safety Net Installation Remotrely monitor of patients for SpO2 and ET CO2, patient safety Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
54 HHS 2019 Pharmacy Kit Check A new system is needed to ensure 100 percent accurate contents when delivering
refilled kits and anesthesia workstations trays to providers.
$183,400.00 $0.00 $183,400.00
55 HHS 2019 PHD Phase II Web Improvements Redesign of the public web presence for the Public Health Department will improve
search capabilities and provide capabilities to increase social media interaction. This
project will be implemented with existing resources.
Information
unavailable
Information
unavailable
Information
unavailable
56 HHS 2018 Prescriptive Patient Flow Notifications The business needs a analytics tool to help to resolve the critical challenges of patient
flow throughout the hospital.
Information
unavailable
Information
unavailable
Information
unavailable
57 HHS 2019 Primary Care Access Program On‐Line App ECM Enhancements to the Primary Care Access Program (PCAP) application, with a focus on
reporting, will improve efficiency. This project will be implemented with existing
resources.
Information
unavailable
Information
unavailable
Information
unavailable
58 HHS 2019 Real Time Location System Replacement The HHS' Real Time Location System (RTLS) needs to be expanded into the new Sobrato
Pavilion to allow hospital staff to track medical equipment.
$56,800.00 $0.00 $56,800.00
59 HHS 2018 Trust Community ‐ Health Information Exchange Development of the Trust Community is critical so that a complete picture of utilization
and identification of the highest utilizers of multiple systems can include data beyond
that included in Santa Clara Valley Medical Center’s HealthLink electronic health record.
The Trust Community, care plans would be coordinated allowing for better targeted
outreach to WPC enrollees.
Information
unavailable
Information
unavailable
Information
unavailable
60 HHS 2018 VMC HL Community Connect Implementation of Community Connect for the Community Health Partners (8
organizations, 28 sites and ~300 end users). Implementation costs for Epic and
Consultants included in one‐time costs. Operational Costs include FTE's and
maintenance for 3 years (FY19,FY20,FY21)
Information
unavailable
Information
unavailable
Information
unavailable
61 HHS 2018 VMC IP/OP e‐Prescribing Electronic Prescribing of controlled substances via HealthLink using a third party for
dual authentication as legally required by the DEA.
Information
unavailable
Information
unavailable
Information
unavailable
62 PSJ 2019 Emergency Dispatch Protocol Software &
Licensing
The Emergency Dispatch system requires Fire and Law modules. $411,540 $0 $411,540
63 PSJ 2019 JISP Inmate Tablet/Phone Provide WiFi enabled tablets for inmates as part of jail reform. $1,440,000 $240,768 $1,199,232
64 PSJ 2019 Network Time Protocol (NTP) Servers Existing 911 center NTP servers are at capacity and the County requires separate
redundant NTP servers for the 911 phone, CAD/RMS system, logging systems, and
other time sensitive systems on the network to maintain full operation during failures.
This will provide network analytics for frequency and data stability, accuracy and
records management.
$35,449 $0 $35,449
65 PSJ 2019 Radio Diagnostic Data Systems Tool Remote monitoring of the health of the portable and mobile fleet of radios used by first
responders in the field will identify most public safety or local government radio failures
prior to actual failure or the user experiencing communications problems.
Information
unavailable
Information
unavailable
Information
unavailable
66 PSJ 2019 VHF Conventional Radio Simulcast System A back‐up radio network is needed in case of primary system failure or in the event of a
catastrophic occurrence.
$1,866,579 $0 $1,866,579
67 SHR 2019 ACI Multi‐Site Implementation Joining the independently managed data center switching fabrics at Berger Drive and
Health and Hospital System into a single data center network infrastructure will
improve efficiency and communication.
$189,100 $0 $189,100
68 SHR 2019 Acquire Analytics Toolset for Applications The implementation of an analytic toolset will allow IT to capture performance metrics
for Connect, the County’s data sharing platform application, and for all ECM developed
internal and external County applications.
$141,600 $0 $141,600
69 SHR 2019 Aerial Imagery and LiDAR Data Acquisition Today, Aerial Imagery and LiDAR (Light Detection and Ranging) data and its bi‐products
(e.g. Bulding outline) is essential data and tool for effective government operations.
County of Santa Clara acquired Aerial Imagery back in 2006, and since then there was
no update until the recent Assessor's Office's State County Partnership Program.
Through the program, Assessor's Office established 3‐year contract to acquire updated
Orthogonal Images LiDAR data as one‐time pilot fund. This contract ends in FY18 with
no permanent funding for the future.
$0
70 SHR 2019 AlertUS Phase2: Social Services Phase 2 of the AlertUS implementation will address additional Social Services Agency's
departments. Departments will be able to use AlertUS to alert and inform their
respective staff.
$53,900 $0 $53,900
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 17
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Project DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)
Approved Projects/ No status reported to date
71 SHR 2019 Alternate Fiber Route to 911 Center NFPA 1221 section 4.1.4.1 ‐ Each center shall be provided with an alternate means of
communication that is compatible with the alternate means of communication
provided at the ERFs. The alternate means shall be readily available to the
telecommunicator in the event of failure of the primary communications system. One
gigabit alternate layer 1 fiber connection to 911 communications center.
This request is also identified as a critical need in the 10 year capital request projects.
Assistance is needed from county to determine actual cost to provide required
alternate Physical (layer one) path.
Information
unavailable
Information
unavailable
Information
unavailable
72 SHR 2019 Berger Auditorium AV Improvements Audio and video equipment is needed to support meetings held in the Berger Campus
Auditorium.
$216,800 $0 $216,800
73 SHR 2018 Cashiering System Acquire and implement a cashiering system for use in the departments of the Finance
Agency. This will initailly be targeted for the new consolidated Department of Revenue
and Tax. Currently, there is no cashiering system in place for the Tax Collector's Office
or the Department of Revenue. Both departments currently handle large quantities of
over the counter payments of all types including cash, checks, and credit cards.
Without a cashiering system, the different types of payments are all handled with
different process, some manual. The acquisition and implementation of a cashiering
system will allow the development and deployment of consistent processes for
handling all types of payments, better controls to reduce and eliminate mistakes, and a
better customer experience.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
74 SHR 2019 COB Hedding Lower Level Audio‐Video
Improvement
Audio and video equipment for the Lower Level Conference Room at 70 West Hedding
Street will modernize communication and improve public access. There is currently no
audio or video equipment installed in this facility.
$266,800 $0 $266,800
75 SHR 2019 County Services Centralized Mobile App A mobile application for centralized employee resources will improve communication
and employee connectivity.
$133,400 $0 $133,400
76 SHR 2019 County Wireless Expansion Expand the County's wireless infrastructure to meet increased demand. $316,600 $0 $316,600
77 SHR 2019 DAO Server Refresh Servers used in the District Attorney's Office that have reached the end of their useful
life need to be replaced.
$265,710 $0 $265,710
78 SHR 2019 DEBS Event Equipment Request The equipment in the Employment Connection Center needs to be upgraded to meet
the needs of CalWORKS large audience presentations.
$80,000 $0 $80,000
79 SHR 2019 Document Management System Planning An enterprise‐wide document management system for all County Departments will
improve efficiency and support other County services and functions. This allocation
provides for the completion of a discovery phase of this project. The IT Capital Reserve
includes additional funds for allocation by the Board of Supervisors as needed to begin
to develop this project once discovery is complete.
$100,000 $0 $100,000
80 SHR 2019 ECM Migration of On‐Prem Custom Apps to
Azure
Migrating core On‐Prem applications to the cloud will address obsolescence issues and
security concerns and improve application availability.
$133,400 $0 $133,400
81 SHR 2019 ECM Portal Platform & Content Management
System
The County's current public portal platform is showing degradation in performance and
is unable to maintain accessibility standards. Replacement of the existing platform will
reduce upkeep and the need for custom coding, increase security, and provide a more
userfriendly interface.
$1,660,000 $0 $1,660,000
82 SHR 2019 Employee Services Centralized Mobile App A mobile application for centralized employee resources will improve communication
and employee connectivity.
$66,800 $0 $66,800
83 SHR 2018 E‐Payment System Upgrade/Expansion Upgrade and expand the E‐Payment system used in the Tax Collector's Office. The tax
collector currently collects over $800 Million in property tax payments electronically
each year. With the population becoming more tech saavy that number is expected to
continue to grow in the future. This project is to acquire a more modern e‐payment
solution with the ability to accept a variety of different types of electronic payments.
This would also integrate into the cashiering systen to give customers a single payment
experience at the counter.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
84 SHR 2017 Implement Volunteer Management ‐ Phase 2 Funding is requested to migrate the 2nd wave of departments to the county‐wide
Volunteer Management System (VMS) acquired in FY16. VMS provides the information
and processes needed by the volunteers and volunteer coordinators, such as defining
skill requirements, scheduling volunteers, communicating when and where volunteers
are needed, collecting and reporting metrics, and providing communications. The VMS
also allows potential volunteers to search for opportunities.
$224,130 $13,494 $210,636
85 SHR 2019 ISD Enterprise Cloud Solutions A new enterprise cloud for the County will improve efficiency and address issues with
the current cloud infrastructure. The existing architecture for authenticating public
users is becoming obsolete and the current environment cannot keep up with the
demand for new application development.
$1,016,800 $96,000 $920,800
86 SHR 2019 ISD Innovation Fund The urgent or critical need for small projects to complete the discovery phase of larger
projects sometimes arises outside of the annual budget cycle. ISD will provide an
accounting of the use of this allocation twice a year to the Board of Supervisors.
$350,000 $0 $350,000
87 SHR 2019 ISD Low Code Rapid Development Tool Mobile and web applications tools will speed County development and allow non‐
developers to perform some functions in the mobile and web application development
process.
$190,000 $0 $190,000
88 SHR 2018 IT Professional Services ‐ BA & PM Provide professional and subject matter contract services are needed to assist with
business needs assessment, business requirements analysis, business process re‐
engineering and improvement, and project management across the County.
$1,000,000 $540,951 $459,049
89 SHR 2018 Kronos Upgrade and Archiving Kronos is the County's system of record for time keeping. The Kronos software supplier
will cease to support the currently installed version of Kronos at the end of 2017. With
the loss of Kronos support, the County will be compromised in its ability to add
functions and serve future needs. Should there be an issue with the application, the
process to collect information for time worked (payroll) and time off (benefits) will be
at risk. Updates to the interfaces and upgrades to the operating system that hosts the
application will continue, which increases risk to compatibility and stability. The project
will also deliver improved features, including the ability to archive Kronos historical
data. This will improve usability, processing and reporting efficiency ‐ and enable the
ability to retain records for a proper amount of time (avoid over‐retention).
$150,000 $0 $150,000
90 SHR 2019 Network Optimization Network devices that have reached the end of their useful life need to be replaced to
allow for increased network bandwidth, improved network manageability, and
improved security and moving toward software defined networking (SDN) and the auto‐
provisioning of addresses for networked devices.
$782,900 $0 $782,900
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 18
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Project DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)
Approved Projects/ No status reported to date
91 SHR 2019 PeopleSoft HCM Archiving Secure hardware and software licenses are needed to ensure compliance with data‐
retention policies and to support the archiving of older data.
$512,000 $0 $512,000
92 SHR 2019 PSJSP Video Conferencing Equipment
Replacement
Three departments have conferencing equipment that have reached the end of their
useful life.
$146,800 $0 $146,800
93 SHR Replace IDM Image Repository Replace IDM Image Repository (software application that stores scanned and imported
images and documents, emails to support the Assessor's office) through RFP Process.
We need funds in reserve to get the RFP Process started which will be requested in
FY17.
Information
unavailable
Information
unavailable
Information
unavailable
94 SHR Replacement of the TRUST application The current TRUST application manages the property tax money that needs to be held
for a period of time in order for proper procedures and investigation to be completed
before the funds are properly dispositioned. This could be a refund, payment of
additional tax liabilities, or transfer to the controller for apportionment. The current
system was implemented as a temporary solution originally slated to last for 6 months.
It has now been in production for over 10 years. This temporary solution has
limitations that encourage manual processes and workarounds which limits the
efficiency of the business processes. This project would replace the TRUST application
by building the functionality into the current Tax Collection and Apportionment System
(TCAS). Currently the staff must switch back and forth between the two systems in
order to perform their job duties. Pulling the functionality into the TCAS system will
allow for better integration and enhanced functionality as well as streamlined
processes.
Information
unavailable
Information
unavailable
Information
unavailable
95 SHR 2019 SHO Custody WiFi WiFi at the County Jail needs to expand to support Jail Inmate Service Platform Tablets. $1,250,000 $0 $1,250,000
96 SHR 2019 SHO Server‐Storage Upgrades Additional servers and storage are needed to provide additional capacity to support the
Sheriff's operations.
$536,800 $0 $536,800
97 SHR 2019 Technology and Network Refresh for SSA Servers and networking hardware that have reached the end of their useful life in
supporting SSA applications and functions.
$133,400 $0 $133,400
98 SHR 2019 UC VoIP Platform Upgrade The current VoIP system operating system is two versions behind the current release
and reaching the end of useful life. Both the VoIP and automatic call distributor (ACD)
platform hardware require replacement. These systems support approximately 8,000
phones countywide. Project funding will address hardware and professional services
costs.
$966,600 $0 $966,600
99 SSA 2019 APS Application Phase 2* A replacement case management system for Adult Protective Services program will
provide identify protection and services to defined vulnerable adult populations, to
collect abuse reports and collect and report statistical information about abuse victims.
This project will be implemented with existing resources.
$10,000 $0 $10,000
100 SSA 2019 APS Structures Decision Making Tools* Developing a decision‐making tool will support a structured assessment process for
program staff to make consistent decisions and improve the overall program
uniformity, reliability and validity of each decision.
$161,500 $0 $161,500
101 SSA 2019 Audible Form Fill‐In Technology Additional functionality will allow Social Services Agency clients to complete forms
verbally over the telephone and have those forms stored and processed electronically.
$100,000 $0 $100,000
102 SSA 2019 CalWIN Interface w/ Scanning Solution* An automated scanning interface to receive electronic inter‐county transfers (ICT),
Benefits CalWIN (BCW) and California Healthcare Eligibility, Enrollment, and Retention
(CalHEERS) documents from CalWIN via batch feed will allow them to be imported into
the Department's scanned image retrieval system. This is currently manually performed
by clerical staff. This project will be implemented with existing resources.
$20,000 $0 $20,000
103 SSA 2019 CalWORKS Employment Services Case Review
Tool
The employment program supervisors are required to conduct monthly CalWORKS
welfare to work case reviews of their unit to ensure accuracy of payments, activities,
meeting the Federal and State work participation rate (WPR) while CalWORKS clients
are on aid. This is currently performed with a manual recording of findings and
corrective actions needed in paper form. This process lacks a systematic tracking of
individual staff performance, error finding, timely follow ups and gathering data for
refresher training needs.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
104 SSA 2019 CalWORKS Outcomes and Accountability A system to capture the data elements will meet the Senate bill 89 requirements for
outcomes‐based funding and accountability reviews for CalWORKS. This project will be
implemented with existing resources.
Information
unavailable
Information
unavailable
Information
unavailable
105 SSA 2019 Corrective Action Tracking & Reporting
Enhancement
Replacing the current Corrective Action Tracking and Reporting application will provide
automation of work assignments and visibility into cases reviewed in each office. This
project will be implemented with existing resources.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
106 SSA 2019 CWES Youth App for Intern & Earn Program* Develop a mobile friendly web application or a native mobile application to support the
Intern and Earn program. This project will be implemented with existing resources.
$10,000 $0 $10,000
107 SSA 2019 Decision Support Data System (DSDS) To participate in the Permanency Innovations Initiative (PII), the federal government
requires that the County implement a decision‐support data system to incorporate
existing and new data sources into an integrated evaluation system. This project will
provide that data system. This project will be implemented with existing resources.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
108 SSA 2019 Enterprise SSA HR Dashboard Phase 3 Reports and tools will support the development of an SSA Human Resources
Dashboard. This project will continue to be developed with existing resources.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
109 SSA 2019 eTime Study Enhancement for SSA* Enhancing the user interface of the current electronic Time Study (eTS) application will
improve user experience and eliminate errors in calculations of monthly and quarterly
time studies for claiming purposes and processing time.
$15,000 $0 $15,000
110 SSA 2019 KRONOS Phase 2 for SSA Departments The roll out of a pilot project to the full Social Services Agency will improve efficiency
and reduce duplications by eliminating paper forms and automating the approval and
tracking processes.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
111 SSA 2019 Mobile DEBS Client Forms Development of a mobile app will allow DEBS clients to access and complete forms on
their mobile device so that form data will be uploaded to DEBS database and linked to
the client's case file. This project will be completed by existing staff.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 19
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Project DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)
Approved Projects/ No status reported to date
112 SSA 2019 Periodic Reporting IDM Interface This functionality will allow client documents to be scanned into the Periodic Reporting
subsystem without manual intervention. This project will be implemented with existing
resources.
Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
113 SSA 2019 Public IHSS Services Online App A web‐based application will allow customers to apply for In‐Home Support Services
(IHSS) online.
$33,200 $0 $33,200
114 SSA 2019 Senior Nutrition Software & Card Reader System A new scanning system will allow staff to enter, store, analyze, and sort information for
the Senior Nutrition Program.
$19,800 $0 $19,800
115 SSA 2019 SSA Contract Management System Phase 2* Developing and implementing Phase 2 will provide a solution to track, maintain, and
audit contracts, vendors and providers by the Office of Contracts Management.
TBD TBD TBD
116 SSA 2019 SSI App Enhancements of HDAP Advocacy
Program
Enhancements to the Supplemental Security Income (SSI) application will to support the
new pilot program for SSI recipients. Enhancements will include adding data elements
to the SSI application to track client housing situation, enrollment in housing program
and other critical data that are required for grant related state funding. This project will
be implemented with existing resources.
Department & State
Grant Funded ‐
Information
unavailable
Department &
State Grant
Funded ‐
Information
unavailable
Department &
State Grant Funded ‐
Information
unavailable
117 SSA 2019 Telephonic Signature Storage* Technology to capture and store telephonic signatures from client interviews will allow
the County to meet regulatory requirement for such.
$335,200 $0 $335,200
118 SSA 2019 Texting in Languages Other than English &
Spanish*
This functionality will allow case workers to text in languages other than English and
Spanish. The state requires that counties have translations available in languages where
the language is spoken by 5 percent or more of the clients.
$201,800 $0 $201,800
119 SSA 2019 Upgrade for Framemaker Upgrade of Adobe Framemaker Department Funded ‐
Information
unavailable
Department
Funded ‐
Information
unavailable
Department Funded
‐ Information
unavailable
*All or partial funding within TSS operating budget.
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 20
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Project Description Project Status SummaryApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)
1 CoA
2019 PRK Data Integration Analytics Implementing a business intelligence solution will combine multiple existing data
sources to provide data mining and analysis relating to project prioritization and other Parks and Recreation Department functions. This project will be implemented with existing resources.
Project on hold. Business resources not available to start working on this till December
Information
unavailable
Information
unavailable
Information
unavailable
2 HHS
2017 CancerLinQ Quality Improvement Platform The business needs CancerLinQ implementation to establish and monitor key
clinical performance indicators, benchmark their patients to national cohorts, and automate data collection to comply with reporting requirements from QOPI, and potentially the state of California (Tumor Registry). This would lead to robust quality improvement and better patient care.
The project status remains Red. The vendor is requesting scanned documents and notes that have sensitive data (e.g. SUTS/DADS, Child Abuse, AIDs, Custody) as a new requirement for this project. The department will need funding to perform this task. Prepared a decision document and met with the internal stakeholders to discuss options. The decision was to put the project On Hold for a year. Meeting scheduled with the vendor on 10/12/18 to relay our concerns and decisions. Will not be reporting on this project until it is picked up again for execution.
Information
unavailable
Information
unavailable
Information
unavailable
3 HHS
2018 VMC Alarms For Telemetry Solution Through use of Vocera or other technology (Pagers or Apple Touch) would have
ability to send alarm signal and telemetry readout to nurses caring for patients requiring telemetry monitoring.
Current project status is on hold the Executive Sponsor is no longer with SCVMC. To get back on track will contact the project requestor to determine if the solution is still needed.
Information
unavailable
Information
unavailable
Information
unavailable
4 HHS
2018 VMC Cardiology Events Monitor Upgrade - Lifewatch The Cardiology Dept staff uses Event Monitors as part of the Electrocardiogram
services for patients. The current Events monitoring system is end of life. King of Hearts Event monitors are repaired only by one vendor located in Oakpark Illinois. Limited parts available currently for current repair and will expire before end of 2015. Therefore, need for software and hardware solution for 20 event monitors and software capability to interface with current ECG system called CardioServer (vendor - Epiphany). System requirements include software solution for wireless and transmission of information functionality. System should also have software capability to be reviewed by EKG Cardiology Technician and then data will be transmitted to CardioServer system.
Project sponsor Dr. Aggarwal requested to place this project on HOLD. Reason: No Physician or clinical resource available to work on this project during 2018. Placed the project on HOLD in plan view. Will start the project in Jan 2019 with a possible GO-LIVE of May 2019.
Information
unavailable
Information
unavailable
Information
unavailable
5 HHS
2016 VMC Enterprise Provider Scheduling System Solution Seeking an RFP to evaluate and implement a SCVMC Enterprise Staff Scheduling
System that can meet the functional needs of the Physicians, Nurses and Pharmacists.SCVMC does not have a standardized scheduling system to assist management with allocation of staff time to meet the needs of clinical operations. Nursing currently uses two systems, one for scheduling and staffing, one for patient acuity. Title 22 requires that acuity drives staffing. Current systems are not integrated together nor are they linked to the EMR or the current timekeeping system. The current paper system used for physicians increases the risk of errors and does not allow tracking and verification of physicians’ time. Other clinical staff such as pharmacists also lack a standardized scheduling system.
Meeting with Steering committee to relay current state workflows is set for 10/10.
Information
unavailable
Information
unavailable
Information
unavailable
6 PSJ
2019 Cellebrite Data Extraction Tool Discovery phase exploration of the technology and identification of suitable vendor
for data extraction from cell phones and other electronic devices. Additional funding from the IT Capital Reserve or other sources may be needed after a project scope and estimate is developed.
PDO/ADO would like a tool to review content and un-encrypt cell phones. They have identified Cellebrite as a platform and tool. The PDO/ADO has submitted a request to the Board of Supervisors, this project is currently on hold until the privacy policy is reviewed prior to purchase.
$60,000 $57,469 $2,531
7 PSJ
2016 JMS Custody Procurement, implementation and support of a new Jail Management System for
the Sheriff's Office.As of September 24, the project is on hold pending the completion of the Management Control Agreement.
All resources have been re-assigned to other work.All wrap-up work completed on the project.
Once the project resumes, a new timeline will be developed with a supporting change order.
Information
unavailable
Information
unavailable
Information
unavailable
8 PSJ
2018 SVRIA-DX The SVRIA-DX project is being authorized to implement an integrated system that:
1. Creates the ability and capacity for each participating PSAP CAD system to export, import and display event and resource data created for or received from one or more PSAP CAD systems.2. Supports law enforcement, fire and medical core business objectives.3. Enhances and facilitates interoperable cross-agency sharing of information.4. Streamlines dispatch operations and improves operational efficiencies which result in reduced service response times.5. Supports local and regional automated resource sharing such as auto and mutual aid. 6. Provides the ability to share event data and resource commitments at a local, regional or state level with other first responders for improved situational awareness and decision making. 7. Provides a flexible data exchange solution that will provide a basis for future expansion and incorporation of additional data exchange projects.
The Project is awaiting the Master Control Agreement to move forward with implementation for the various PSAPs. In the meanwhile, the ISE Development team is supporting the CAD system upgrade to Hexagon of the City of Santa Clara
Information
unavailable
Information
unavailable
Information
unavailable
9 SHR
2016 HHS-ISD IT Disaster Recovery SCC needs to have an alternate disaster recovery site to ensure that critical
systems are available to the public and County staff in the event of a major disaster. Critical applications like Epic, OpenLink and others need to be available 24x7 to the County staff. The scope of this project includes the building of a DR site in Boulder, CO to host the infrastructure to support these applications.
Reviewed the proposed high-level solution with IBM. IBM has sent us a draft addendum. The addendum is being reviewed by the IBM legal team. Many clarification questions followed and after many back and forth, we were assured by IBM that we will have the final addendum and the PCR by the end of this week.
Information
unavailable
Information
unavailable
Information
unavailable
10 SHR
2017 Implement OES VMS Add Volunteer Management capability to OES to streamline recruitment, activation
and management of OES volunteers.The project was originally approved in 2016 by a previous management team. The project team gave an Executive Presentation to current OES management in March. OES management is unwilling to sponsor the OES Volunteer Management System. The project was placed on hold on April 17 until a Business Sponsor is identified.
Part of Implement
Volunteer
Management ‐
Phase 2
Part of Implement
Volunteer
Management ‐
Phase 2
Part of Implement
Volunteer
Management ‐ Phase
2
11 SHR
2018 Redesign Business Processes for Employee Lifecycle This request is to create an overall strategic Road Map involving ESA, Finance
Agency, and ISD to capture gaps and risks and prioritize organizational business objectives as well as functional and technical requirements needed to support an efficient employee life cycle. This unified and strategic Road Map for the employee life cycle will enable the County to plan and implement integrated and cohesive technology and process improvements over the next several years. The approach is process focused, including a prioritization of resources at ESA, Finance Agency and ISD, to improve employees experiences and increase efficiencies in hiring, onboarding, payroll administration, benefits adminsitration, as well as separation and retirement. Deliverables will include an overview of the “As-Is” landscape, gap analysis - highlighting today’s pain points/issues and a recommendation of the “To-Be” solution, including software recommendation, implementation cost, timelines etc., and a Road Map of prioritization. Consultant fees will include the creation of this business case and will also provide help in the RFP, vendor selection and possibly in the implementation itself. \n\na. $650 K for Consultant (FY 18)\nb. $350K for consulting fees to come up with requirements to support business development for RFP and vendor selection (FY19)\nc. $10 M to implement Finance, ESA joint venture for long term system overhaul (FY20)
Information
unavailable
Information
unavailable
Information
unavailable
On Hold Projects
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 21
Attachment A ‐ IT Portfolio Report
No. Vertical Project Name Project DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)
1 FEP TCAS Enhancement Develop additional TCAS system functionality necessary to support the business
requirements of the Tax Collector and Controller's Office. This will be for the 3rd
year of funding that was approved in FY2015.
$0 $0 $0
2 HHS HHS Elearning System
Replacement
System replacement of vendor hosted elearning system that is supported by 1
FTE system administrator. System implementation duration (after signed
contract) is estimated at 3 to 6 months based on number of system features
purchased.
Information
unavailable
Information
unavailable
Information
unavailable
3 HHS VMC Cardiology Events Monitor
Upgrade ‐ Zio Patch
The Cardiology Dept staff uses Event Monitors as part of the Electrocardiogram
services for patients. The current Events monitoring system is end of life. King
of Hearts Event monitors are repaired only by one vendor located in Oakpark
Illinois. Limited parts available currently for current repair and will expire before
end of 2015. Therefore, need for software and hardware solution for 20 event
monitors and software capability to interface with current ECG system called
CardioServer (vendor ‐ Epiphany). System requirements include software
solution for wireless and transmission of information functionality. System
should also have software capability to be reviewed by EKG Cardiology
Technician and then data will be transmitted to CardioServer system.
Information
unavailable
Information
unavailable
Information
unavailable
4 HHS VMC GI & Pulmonary
Documentation System Solution
Current EndoWorks System Replacement project request.This is a program that
will allow departments (pediatrics GI and pulmonary & adult GI and pulmonary)
to document procedures as required and interface with Healthlink.
Information
unavailable
Information
unavailable
Information
unavailable
5 HHS VMC Laboratory Validation
Software Solution
This product automates the validation of the Beaker build required when
changes are made especially when there are major upgrades. This product
eliminates user error with running test scripts, enable more extensive testing,
provides the necessary testing documentation automatically, enables testing to
be completed quickly, and overall provides the testing needed to truly validate a
laboratory system.
Information
unavailable
Information
unavailable
Information
unavailable
6 HHS VMC Optum Claims Manager HW &
SW Upgrade
Optum Claims Manager version 4.8 will sunset end of calendar year. Request to
upgrade HW & SW to latest version 5.4. This upgrade will improve coding for
Inpatient and Outpatient coders with a more sophisticated application version.
Currently, only scrubbing Professional claims and no Facility Claims.
Information
unavailable
Information
unavailable
Information
unavailable
7 HHS VMC Xper Flex Cardio System
implementation
The WITT Series IV system (WITT System) is a critical application and hardware
system used for the Catheterization Lab with the Cardiology dept. The WITT
system manages the Cath Lab services which include Hemodynamic applications
and the Cath Lab inventory. The Cardiology department has used the same
system since July 2003.\nThe Cardiology department would like to upgrade the
WIIT system to the Phillips (vendor's) current model named Xper Flex Cardio
(product #100751). This upgrade would consist of the Hemodynamic and Cath
Lab inventory software and hardware; and physical servers being upgraded with
a new OS system.
Information
unavailable
Information
unavailable
Information
unavailable
8 PSJ BI ‐ AB109 The County must develop an efficient and effective method for sharing and
reporting on data related to Public Safety and Justice. Failure to collect, share
and analyze the required data will limit the ability of the County to provide
programs and services for Public Safety and Justice individuals, measure program
successes and outcomes, track Public Safety and Justice information and
individuals across County agencies, and potentially impact the County’s ability to
get future funding for Public Safety and Justice efforts.
Information
unavailable
Information
unavailable
Information
unavailable
9 PSJ PSJ County Document Subproject ‐
eDisc Tablets
eDiscovery Tablets provide the accused in custody to review evidence and assist
in their own defense.
Part of PSJ County
Document &
Evidence Exchange
Part of PSJ County
Document &
Evidence Exchange
Part of PSJ County
Document & Evidence
Exchange
SHR Annual Refresh Infrastructure
Servers and Storage
There are requests for $1M in infrastructure refresh, including replacing the
primary storage arrays for backup infrastructure, purchasing additional servers
for the x86 virtual environment to accommodate additional requests from
Security, PDO, FAF, Controllers and others. Also, we plan to replace the County
Comm Storage Area Network (SAN) infrastructure. With the purchase of new
servers we will need new TSM (backup) licenses. The FY18 scope is represented
by the following four projects, three of which have been completed:
(a) Replace Backup Infrastructure
(b) Upgrade Purchase x86 VM
(c) Replace County Comm SAN
(d) TSM Storage Upgrade (Active)
$512,802 $0 $512,802
10 SHR (a) Replace Backup Infrastructure ISD is currently backing up 1500TB of intellectual data. There is a business need
to consolidate the backup needs of SSA, HHS and ISD‐supported departments.
The scope of this project includes replacing the SSA, HHS and ISD backup
infrastructure to aid the consolidation effort.
Part of Annual
Refresh
Infrastructure Servers
and Storage
Part of Annual
Refresh
Infrastructure Servers
and Storage
Part of Annual Refresh
Infrastructure Servers
and Storage
11 SHR (b) Upgrade Purchase x86 VM The x86 virtual environment hosts need to be replaced due to aging, expiring
hardware warranties, eliminating old hardware, improve server utilization and
make legacy applications easier to support.
Part of Annual
Refresh
Infrastructure Servers
and Storage
Part of Annual
Refresh
Infrastructure Servers
and Storage
Part of Annual Refresh
Infrastructure Servers
and Storage
12 SHR (c) Replace County Comm SAN County Communications' Storage Area Network (SAN) needs to be replaced due
to aging infrastructure, expiring warranties and inability to fulfill current
business requirements. SAN replacement will enable ability to support data
growth, increased infrastructure demands and fulfill County Comm's storage
capacity needs.
Part of Annual
Refresh
Infrastructure Servers
and Storage
Part of Annual
Refresh
Infrastructure Servers
and Storage
Part of Annual Refresh
Infrastructure Servers
and Storage
13 SHR DataWatch Upgrade DataWatch needs to be upgraded as the current version is no longer supported
by the vendor. This project includes the upgrade from DataWatch server version
12.1 to Monarch server version 14.1.
Information
unavailable
Information
unavailable
Information
unavailable
Completed Projects
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 22
Attachment A ‐ IT Portfolio Report
No. Vertical Project Name Project DescriptionApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)
Completed Projects
14 SHR HHS‐BW (Data Warehouse App) Enterprise application support is building data warehouse app for HHS to
capture all the historical data prior move to SAP
Information
unavailable
Information
unavailable
Information
unavailable
15 SHR Implement Animal Shelter VMS Add Volunteer Management capability to AEM to streamline recruitment and
management of Animal Shelter volunteers.
$224,130 $13,494 $210,636
16 SHR Replace EoL Existing Employee &
Guest Wi‐Fi Network
Investment in Wi‐Fi network controllers and the Wi‐Fi access point inventory to
expand access in County employee and guest networks.
$38,000 ($0) $38,000
17 SHR Replace/Upgrade SCCLearn (SABA) Replacement of existing Learning Management System $361,229 $0 $361,229
18 SHR Replace Warrant Printing Software SCC is printing checks for warrant, payroll and SSA. The current system call
PayBase, and we need to replace the software because it's no longer supported.
The new Software call C‐Series from the same vendor call Bottom‐line.
$0 $0 $0
19 SSA IDM Barcode Implementation This is Phase 2 of the Datacap project to develop and implement the barcode $22,860 $22,860 $0
20 SSA Master Data Management
Implementation
The Master data management (MDM) program will provide SSA a trusted view
of our critical data across our client, and will allow to identify data relationships
between clients.
$1,280,000 $1,280,000 $0
21 SSA APS Cares Application Replacement Development and implementation of new application to replace existing system
for tracking and management of reported abuse and neglect cases of adults.
$716,934 $716,934 $0
22 SSA Implementation of New EBT
Vendor
This project is to convert to a new Electronic Benefits Transfer (EBT) service
vendor (Fidelity Information Services) and replace all existing EBT machines and
equipment's at eight District Office service sites, by end of January 2018.
$38,162 $38,162 $0
23 SSA AlertUS Notification ‐ Phase 1
Agency Employees
This project is to implement an emergency notification and alert system for
Social Services Agency. Phase 1 of the project involves review of current safety
practices, developing alerts, scripts and messaging, and installation of the
AlertUS software on all agency computers and mobile devices.
$18,294 $14,590 $3,704
24 SSA DFCS Tech Refresh DFCS current deployment of laptops and desktops are running on Windows 7 OS.
On March 2018 CWSCMS will ONLY be supported on Windows 10 Enterprise
LTSB v1607 / Office 2016. Standard application will fail on Windows 7 / Office
2007. In order to support new software requirements a hardware refresh is
needed.
The goal of this project is to deploy new PCs and Laptops for DFCS with the new
tested image running on Windows 10 Enterprise LTSB 64 bits with office 2016 32
bits package
$1,300,000 $1,300,000 $0
25 SSA AO KRONOS: ESS to AO Convert the remaining programs in AO Dept to KRONOS ESS $5,003 $5,003 $0
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 23
Attachment A ‐ IT Portfolio Report
No. Vertical FY Project Name Project Description Project SummaryApproved Budget
(As of Sept. 2018)
Expense +
Encumbrance
(As of Sept. 2018)
Available Budget
(As of Sept. 2018)
1 HHS
2016 VMC Reference Lab Order & Result
Interface Solution
Selection and purchase of a third party software package that
interfaces with EPIC Beaker. The product is designed to allow the
laboratory to implement interfaces to outside referfence labs, state
and local agencies, and other entities at the discretion of the
Director of Laboratories via this established interface. Once
established, this one interface will allow patient orders and results
to flow to multiple selected reference laboratories such as ARUP,
Invitae, Mayo and many others.
Stakeholder wants to cancel the RFP as the ROI
is very minimal compared to spend. Cancellation
request sent to Procurement. Procurement
acknowledged the cancellation of this project.
Information
unavailable
Information
unavailable
Information
unavailable
2 SSA
2018 DFCS ‐ Decision Support Data System
(DSDS)
Develop a program to track if there's an improvement in practice for
the Child & Family Practice Module (CFPM). Departments involved
in assessment include Human Resources (HR), Social Services
Agency (SSA), and Department of Family and Children Services
(DFCS).
Project sponsor instructed to close out project
as business had not clearly defined out the
scope or business need before requesting
automation.
$5,133 $5,133 $0
3 SSA
2017 ERConnect Phase II plus
Enhancements
Build Intake referral functionality, auto referral assignments, and
enhancements to increase scheduling flexibility and data for
reports.
Project Canceled: business did not follow
through.
$94,609 $94,609 $0
4 SSA
2017 Wraparound Business Process
Improvements
Document current wraparound approval process through the point
of payment processing. Identify breaks and pain points. Provide
recommendations for a revised business process to sponsors.
Project Canceled: business did not follow
through.
$204,298 $204,298 $0
Canceled Projects
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 24
Attachment A ‐ IT Portfolio Report
Criteria for Project Tiers Tier 1 Project Tier 2 Project Tier 3 Project Tier 4 Project
Labor Hours 81 ‐ 200 hours 201 ‐ 1500 hours 1501 ‐ 6000 hours >6000 hours
Duration 5 ‐ 12 weeks 13 ‐ 32 weeks 32 ‐ 52 weeks >52 weeks
Non‐Labor Costs $10,000 ‐ $100,000 $100,001 ‐ $1,000,000 $1,000,001 ‐ $5,000,000 >$5,000,000
Project Complexity Low Medium High Critical
Project Sponsor Manager or higher Manager or higher Director or higher Deputy Director
Project Tiers Legend
Verticals
CoA ‐ County Administration
FES ‐ Financial and Employee Systems
HHS ‐ Health System
PSJ ‐ Public Safety and Justice
SSA ‐ Social Services 25