thermal energy storage and peak load reduction mark m. maccracken, pe, leed ap, pte calmac mfg....

46
Thermal Energy Storage and Peak Load Reduction Mark M. MacCracken, PE, LEED AP , Pte CALMAC Mfg. Corp. Fair Lawn, NJ Calmac.com NARUC Summer Meeting 7-16-07

Upload: gordon-pope

Post on 17-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Thermal Energy Storage and Peak Load Reduction

Mark M. MacCracken, PE, LEEDAP, PteCALMAC Mfg. Corp.

Fair Lawn, NJCalmac.com

NARUC Summer Meeting 7-16-07

Benefits of Thermal Energy Storage

Reduces Peak Demand at most critical time 20-40%

Reduces consumer’s energy costs 10-20%

May reduce energy usage at the building up to 14%

Reduces source energy usage at power plant 8-34%

Reduces emissions up to 50%

Increases Load Factor of Generation up to 25%

Provides operational flexibility

Thermal Energy Storage For Off-Peak Cooling

What is it?How does it work?Why is it Green?Other “Green” AdvantagesApplications/Case Studies

Storage is Natural

Most common TES System

Water Heater (Electric)

Assume one low-flow shower

((2.5gpm x 8.33 lb/gal x (110-60))

x 60 minutes/hr / 3,414 Btu/kW = 18.3 kW

4.5 kWHeater

Gas Water Heater

Design Load = 2 Showers at a time

18.3 kW x 2 x 3414 = 124,950 Btus

East Coast of US 100,000,000 people x 25% x 1/12 Hr/shower x 18.3 kW=

38 Gigawatts = CA Electric Peak on Summer day

TES has already impacted US infrastructure

Utility Load Factors* in the USA

50

55

60

65

70

Percent

1955 1965 1975 1985 1995

Year*Load Factor = Avg. Load Peak Load

ASHRAE 90.1 Base BuildingNon-Storage Electrical Profile

Lighting

FansPumps

Base Load

Cooling

0200400600800

100012001400160018002000

k W

Total kWh = 28,000/day

Peak Load2000 kW

Avg. Load

1050 kW

(Load Factor = 53%)

Design 30% better than 90.1 Non-Storage Electrical Profile

LightingFans

Pumps

Cooling

Base Load0

200400600800

100012001400160018002000

k

WAvg. Load

800 kW

Total kWh = 19,200/day

Peak Load1500 kW

(Load Factor = 53%)

Off Peak Cooling (OPC) Electrical Profile

Base Load

LightingFans

Pumps

0200400600800

100012001400160018002000

k

W

Total kWh = 19,200/day (Load Factor = 88%)

Charging Storage

600 kW Shed600 kW Shed

Avg. Load

800kW

40% Peak Load Reduction

Peak Load 900kW

Power continue to be less expensive at Night because of Generation Load Factor

4 Buildings x 1 Megawatt4 Buildings x 1 Megawatt

= 4 Megawatts= 4 Megawatts

8,000 mW-h Sold8,000 mW-h Sold

The same generator produces The same generator produces

25% more sellable kW-h!25% more sellable kW-h!

5 Buildings with TES @ 0.8 mW 5 Buildings with TES @ 0.8 mW

= 4 Megawatts = 4 Megawatts

10,000 mW-h Sold!10,000 mW-h Sold!

3-D Electric Load Profile -- Full Year

4200 ton-hr of StorageInstalled 1990

Large Scale Sustainable Energy Future will Require Storage

1 TRILLION Watts of Generation in USA (approx.)

Costs of New Generation, InstalledCombined Cycle Gas Turbine ~ $0.50 to $1.00/WattNuclear $3.00 to $6.00/Watt

New Coal Plant $1.50/Watt New Clean Coal $2.00/Watt

Wind (30% Cap Factor ~ 0 Peak Reduction)$1.60/WattPV (30% Cap Factor ~ 15% Peak Reduction*) $7.50/ Watt

STORAGE (Thermal) $0.50 to $1.00/Watt*NREL Report

Thermal Energy Storage For Off-Peak Cooling

What is it?

How does it work?

Two Basic Systems

Water

Ice

40

56

Load

Chiller

40

40

56

Load

Chiller

40

Warm Water56 F

Cold Water40 F

Thermocline

TemperatureModulating Valve

Storage Tanks

Control Logic

Chiller Based System

Closed System

So what is “Different”?

Heat Transfer Fluid 75%H20/25%EG

Bank of America Tower at 1 Bryant Park, New York City

Bank of America / Durst Organization

History Channel “Sky Scrapers” 9-7-04

~2.2 Million ft2

Going for LEED Platinum

Thermal Storage Tank Ice-on-Coil Internal Melt

Expansion Chamber

Heat Exchanger

Tank

Insulation

Coil & Glycol25

TemperatureControl Valve

31

Ice 1000 tonOn-Peak Load

500 tonChiller

25 31

44

TemperatureControl Valve

54

Ice500 tonLoad

500 tonChiller

44

Coil & Glycol

52

TemperatureControl Valve

60

44

IceMeltedIce

Coil & Glycol

1000 tonLoad

500 tonChiller

44

34- 44

Basic Operating Modes for any Storage System

0102030405060708090

100

Time

Tons

Making Ice-Meeting LoadIce DischargeChillers Meeting LoadIce Charge

Storage System60 ton Chiller

1,100 ton-hr Storage

Load Reduction90 ton or ~ 90 kW

ICE DISCHARGE

CHILLERS

ICE CHARGE

Space?

Full Storage: 0.70% of cooled floor space

Partial Storage: Ice provides about 33% of a cooling system reducing ice tank floor space to 0.23% of cooled floor space.

Would need 25% of roof space on 100 story building!

Same ratio as the water heater in your house

1 ton cools 500 ft2

1 tank provides 20 tons1 tank cools 10,000 ft2 1 tank needs 70 ft2 (60 ft2 )

National Air and Space Museum, Washington, DC USA

Ice Storage Tanks for the entire

Project

4,700 Ton Hrs of StorageOn-Peak Chiller – 1122 TonsOn-Peak Ice Contribution – 729 Tons40% On-Peak Chiller Demand Avoided

Thermal Energy Storage Myths Article (Ashrae Journal Sept 03)

1. Uncommon2. Too Much Space3. Too Complicated4. Doesn’t Save Energy5. Too Expensive6. Lack of Redundancy (Risky)7. Rates Will Change8. Modeling doesn’t Show Results

Reality: TES is a Proven Technology

that saves Money and Energy

Thermal Energy Storage For Off-Peak Cooling

What is it?

How does it work?

Why is it Green?

Materials & Resources

Energy & Atmosphere

Water Efficiency

Sustainable Sites

Indoor Environmental Quality

LEEDTM Credits

Sustainable Sites: 14 points

Water Efficiency: 5 points

Energy* & Atmosphere: 17 points

Materials & Resources: 13 points

Indoor Environment Quality: 15 points

Innovation & Design: 5 points

69 points

*10 Energy Credit are based on ASHRAE 90.1 which is based on Energy COST Reduction

Real reasons Off-Peak Cooling is Green:

It is much more Energy Efficient to create and deliver a kWh of Electricity at night than during the hot of the day.• Research from the California Energy Commission on 2 Cal. Utilities

Reports 8 to 34% savings in raw fuel when comparing On and Off Peak Operation!

• Heat Rates for Base Load Plants ~7,800 Btu/kWh vs. Peaking Plants ~9,400 to 14,000 Btu/kWh

The last power plants to come on during peak hours are normally the dirtiest per kW• Ashok Gupta (Director of Energy, NRDC) in NYTimes article “Peak

Shifting results in lower emissions because some of the plants used to meet demand peaks are among the dirtiest in the city”

• New CA Report by Greg Kats The Costs and Financial Benefits of Green Buildings states Peak power in CA is twice as dirty as Off Peak Power.

Thermal Energy Storage For Off-Peak Cooling

What is it?

How does it work?

Why is it Green?

Other “Green” Advantages

Other “Green” Issues

Safety Factors/Redundancy (Oversizing)

• Well documented that oversizing chiller plants creates less efficient real world operation.

• Engineers have to protect their license

Storage is the Natural solution

Safety Factor and Redundancy Without Oversizing for same Cost

0

200

400

600

800

1000

1200

1400

Time

Tons

Conventional System* 3-400 ton ChillersStorage System Excess CapacityDesign Day Load

Storage System2 - 400 ton Chiller

3,500 ton-hr Storage

* as per GSA Guideline P-100

Design Day Off-Peak Cooling System

0

200

400

600

800

1000

1200

1400

Time

Tons

Discharge StorageChillers Meeting LoadCharge Storage

Storage System2- 400 ton Chillers

3,500 ton-hr Storage

500 ton Load Reductionor ~ 375 kW

STORAGE DISCHARGE

CHILLERS(ONLY 500 TONS)

Installed Chillers Max Capacity

STORAGECHARGE

Costs of Storage

What’s the Installed Cost of a ton of Chiller Plant?

$1000/ton , $1200/ton, $1400/ton $1600/ton, $1800/ton

Storage Costs installed ~ $100 to $150 per ton-hr

Depending on location, application and design

For each 1 ton of chiller you reduce you need about 8 to 9 ton-hrs of storage.

Costs are similar to conventional design for New Construction

Thermal Energy Storage For Off-Peak Cooling

What is it?How does it work?Why is it Green?Other “Green” AdvantagesApplications/Case Studies

UL8,000 Ton-Hr2.5 days to install

Costco Installations 3 in Japan2 in Korea2 in USA

41 Stories3400 Ton Hours StorageAvoids 700kW out of 3500kW Original Total

Durst Headquarters Retrofit 1155 Avenue of the Americas

VFD PUMP

TS

TOLOAD

FROMLOAD

ICE STORAGE

ICE STORAGE

Ice Plant in Series with Water Chiller

HX

DEMAND LIMITEDTO 700 TONS

490 ICE-MAKING TONS

~1200 TONS

Credit Suisse 11 Madison Ave.

30 Stories, 2.2 Million Ft2

6200 Ton Hours Storage

Avoids ~ 900 kW

NYSERDA Incentive $620,000

Main reason for Storage: Resiliency

Morgan Stanley

Morgan StanleyWestchester, NY

1 Bryant Park Bank of America Tower2.2 Million Sqft

Bank of America Tower ICEBANK Facts

Over Half a Million Pounds of Ice made every night.

Enough Ice to Cool 250 Homes

1000 Tons of Air Conditioning Shifted to Off-Peak

Goldman-SachsNew York City

2.2 Million Sqft.6,000 tons Peak4,500 tons of Chiller (Only 3000 during the Day)

19,000 Ton-hr of Ice Storage~2 MW Reduction

Going for LEED Gold

Off-Peak Cooling… in over 6000 installations in 35 countries, many installed over 20 years ago

Mark M. MacCracken, CEO [email protected]

201-797-1511

NARUC Summer Meeting 7-16-07

Questions?