the use of high modulus self compacting concrete in icc a · the use of high modulus self...
TRANSCRIPT
THE USE OF HIGH MODULUS SELF COMPACTING CONCRETE
FOR INTERNATIONAL COMMERCE CENTRE
Eddie Ho
28 February 2007
SITE LOCATION
Package 7 Package 6
Package 5
Pa
ck
ag
e 2
Package 4
Package 3
Package 1
SSSSTTTTRRRRUUUUCCCCTTTTUUUURRRRAAAALLLL SSSSYYYYSSSSTTTTEEEEMMMM�
TOP OF PARAPET @ +490m PD
TypicalFloorPlanTypicalFloorPlanTypicalFloorPlanTypicalFloorPlan
International Commerce Centre
ò Building Height = 485m
ò No of Stories = 118
ò GFA = 270,000 sq.m.
ò Foundation: Shaft Grouted Barrettes (241 Nos.)
ò Basement: 4 levels with a 76mØ 1.5m-thk Circular Diaphragm Wall
ò Floor System: Steel Composite
ò Stability System: RC Central Core + 8 R.C. Mega Columns with 4 outriggers (1 Post Tension RC + 3 Structural Steel)
ò Grade 90 High Modulus Concrete
ò Design Wind Speed = 59.5 m/s
TTTTEEEECCCCHHHHNNNNIIIICCCCAAAALLLL RRRREEEEAAAASSSSOOOONNNNSSSS TTTTOOOO UUUUSSSSEEEE HHHHIIIIGGGGHHHH MMMM OOOODDDDUUUULLLLUUUUSSSS SSSSEEEELLLLFFFF CCCCOOOOMMMM PPPPAAAACCCCTTTTIIIINNNNGGGG
CCCCOOOONNNNCCCCRRRREEEETTTTEEEE
Wind
Solution:
High Modulus Concrete
Solution:
Self Compacting Concrete
Congested Reinforcement Large Deflection
1.2
1
0.8
0.6
0.4
1996 1997 1998 1999 2000 2001 2002 2003 2004 2005
Concrete (grade 45) Reinforcem ent StructuralSteel
TTTTRRRREEEENNNNDDDD OOOOFFFF MMMM AAAATTTTEEEERRRRIIIIAAAALLLL CCCCOOOOSSSSTTTT�
E-modulus VS Strength
y = 1.6918x0.6555
R2 = 0.8635
y = 7.5126x0.3773
R2 = 0.6001
24262830323436384042
40 60 80 100Strength (Mpa)
E-m
od
ulu
s (
Gp
a)
Volcanic Tuff
Granite
igh Modulus Concrete
Design:
Grade 90
EC = 39G
Reactive E-modulus VS Strength
y = 1.6918x0.6555
R2 = 0.8635
y = 7.5126x0.3773
R2 = 0.6001
24 26 28 30 32 34 36 38 40 42
40 60 80 100 Strength (Mpa)
E-m
od
ulu
s (
Gp
a)
Volcanic Tuff
Granite
Aggregate
HHHHIIIIGGGGHHHH SSSSTTTTRRRREEEENNNNGGGGHHHHTTTT HHHHIIIIGGGGHHHH MMMM OOOODDDDUUUULLLLUUUUSSSS SSSSEEEELLLLFFFF CCCCOOOOMMMM PPPPAAAACCCCTTTTIIIINNNNGGGG CCCCOOOONNNNCCCCRRRREEEETTTTEEEE�
H
Pa
WWWW hhhhaaaatttt ssss AAAASSSSRRRR????iiii
ò An expansive chemical reaction between excessive alkalis and a REACTIVE
AGGREGATE
reactive aggregate which occurs inside the hardened concrete over a long period of time
ALKALI-SILICA REACTION
ALKALI MOISTURE
SSSSYYYYMMMM PPPPTTTTOOOOMMMM SSSS�
…….internal expansion…
ALKALI-SILICA REACTION
BBBBDDDD AAAAPPPPPPPPRRRROOOOVVVVAAAALLLL PPPPRRRROOOOCCCCEEEESSSSSSSSEEEESSSS�
Before the new concrete is being used, the proposed materials shall go through a stringent testing, classification, assessment and evaluation process to the satisfaction of RSE.
ò Taking Representative Samples Sample from each aggregate stockpile on a 3-monthly basis for 9 months.
ò Petrographical Assessment Characterise the aggregate source, identify mineralogy, rock type, assess variability and any potential reactive components.
ò Aggregate Reactivity Classification Conduct RILEM AAR2 Ultra-Accelerated Mortar Bar test and classify the aggregate reactivity based on the degree of expansion resulted.
ò Environmental Exposure Risk Environmental risk shall be determined by RSE, i.e. Dry, Exposed and Severe.
MMMM EEEEAAAASSSSUUUURRRREEEESSSS TTTTAAAAKKKKEEEENNNN TTTTOOOO CCCCOOOONNNNTTTTRRRROOOOLLLL AAAASSSSRRRR�
ò Moisture Contact Temporary Waterproofing Plaster to Mega Column & Central Corewall made of G90 during Construction Stage. Permanent Waterproofing Plaster to Perimeter Mega Columns at Mechanical Floors. Permanent Waterproofing Plaster to Walls Exposing to Toilet/Shower Room.
ò Sufficient Alkaline Pore Solution Limit Alkali Level to Maximum of 3 kg/m3
ò Reactive Aggregate Use of Secondary Cementitious Materials, e.g. PFA, Microsilica
Eliminating one or more of the above components!
HHHHIIIIGGGGHHHH SSSSTTTTRRRREEEENNNNGGGGHHHHTTTT HHHHIIIIGGGGHHHH MMMM OOOODDDDUUUULLLLUUUUSSSS SSSSEEEELLLLFFFF CCCCOOOOMMMM PPPPAAAACCCCTTTTIIIINNNNGGGG CCCCOOOONNNNCCCCRRRREEEETTTTEEEE�
Self Compacting Concrete
How to produce SCC?
• Increase paste volume
• Reduce Volumetric Ratio of Aggregate to Cementitious materials
• Optimize Particle Size Grading
• Use of SCC Admixture ‚‚‚‚ Polycarboxylate Type (w/o viscosity modifier)
A long polymer chain
Formation of weak links with cement particles
HHHHIIIIGGGGHHHH SSSSTTTTRRRREEEENNNNGGGGHHHHTTTT HHHHIIIIGGGGHHHH MMMM OOOODDDDUUUULLLLUUUUSSSS SSSSEEEELLLLFFFF CCCCOOOOMMMM PPPPAAAACCCCTTTTIIIINNNNGGGG CCCCOOOONNNNCCCCRRRREEEETTTTEEEE�
Self Compacting Concrete
Three Key Characteristics:
Filling Ability ò Able to flow into all the spaces within
the formwork under its own weight. This is related to workability
Passing Ability ò Able to flow through tight openings
such as spaces between steel reinforcing bars under its own weight. They must not ‘block’ during placement.
Resistance to Segregation ò Able to meet the above two
requirements while it’s original composition remains uniform
HHHHIIIIGGGGHHHH SSSSTTTTRRRREEEENNNNGGGGHHHHTTTT HHHHIIIIGGGGHHHH MMMM OOOODDDDUUUULLLLUUUUSSSS SSSSEEEELLLLFFFF CCCCOOOOMMMM PPPPAAAACCCCTTTTIIIINNNNGGGG CCCCOOOONNNNCCCCRRRREEEETTTTEEEE�
Self Compacting Concrete (Filling Ability Test)
Slump Flow Test
- assess the horizontal free flow distance.
- as the acceptance criteria for workability because of its simplicity.
700mm x 700mm Flow in 2 minutes
HHHHIIIIGGGGHHHH SSSSTTTTRRRREEEENNNNGGGGHHHHTTTT HHHHIIIIGGGGHHHH MMMM OOOODDDDUUUULLLLUUUUSSSS SSSSEEEELLLLFFFF CCCCOOOOMMMM PPPPAAAACCCCTTTTIIIINNNNGGGG CCCCOOOONNNNCCCCRRRREEEETTTTEEEE�
Self Compacting Concrete (Passing Ability Test – L Box Test)
Testing of filling abilityDone on the laboratory and plant trials to demonstrate the passing ability
HHHHIIIIGGGGHHHH SSSSTTTTRRRREEEENNNNGGGGHHHHTTTT HHHHIIIIGGGGHHHH MMMM OOOODDDDUUUULLLLUUUUSSSS SSSSEEEELLLLFFFF CCCCOOOOMMMM PPPPAAAACCCCTTTTIIIINNNNGGGG CCCCOOOONNNNCCCCRRRREEEETTTTEEEE�
Self Compacting Concrete (Passing Ability Test – L Box Test)
Measure concrete ability to flow in the present of reinforcement
HHHHIIIIGGGGHHHH SSSSTTTTRRRREEEENNNNGGGGHHHHTTTT HHHHIIIIGGGGHHHH MMMM OOOODDDDUUUULLLLUUUUSSSS SSSSEEEELLLLFFFF CCCCOOOOMMMM PPPPAAAACCCCTTTTIIIINNNNGGGG CCCCOOOONNNNCCCCRRRREEEETTTTEEEE�
Self Compacting Concrete (Segregation Resistance Test)
ò Visual Inspection slump flow and L-box test
ò GTM Screen Stability
Step 1: Allow 10 Litre of concrete to stand for 15 min.
HHHHIIIIGGGGHHHH SSSSTTTTRRRREEEENNNNGGGGHHHHTTTT HHHHIIIIGGGGHHHH MMMM OOOODDDDUUUULLLLUUUUSSSS SSSSEEEELLLLFFFF CCCCOOOOMMMM PPPPAAAACCCCTTTTIIIINNNNGGGG CCCCOOOONNNNCCCCRRRREEEETTTTEEEE�
Self Compacting Concrete (Segregation Resistance Test)
GTM Screen Stability
Step 2: Extract fine materials on Step 3: Weight the percentage of fine materials the top layer by sieve
HHHHIIIIGGGGHHHH SSSSTTTTRRRREEEENNNNGGGGHHHHTTTT HHHHIIIIGGGGHHHH MMMM OOOODDDDUUUULLLLUUUUSSSS SSSSEEEELLLLFFFF CCCCOOOOMMMM PPPPAAAACCCCTTTTIIIINNNNGGGG CCCCOOOONNNNCCCCRRRREEEETTTTEEEE�
Self Compacting Concrete (Acceptance Criteria Summary)
Method Property Brief description ����
Typical Range of Values
Unit Min. Max.
Slump flow test Filling ability Assess Horizontal Free Flow Distance in the absence of obstructions mm 650 800
T50cm slump flow Filling ability Assess Time Required to flow 50cm Horizontally in the absence of obstructions sec 2 5
L-box Passing ability
In a rectangular section box with an 'L' shape, vertical section is filled with concrete and then gate lifted to let concrete flow into the horizontal section. Measure the height of concrete at the end of the horizontal section (H2) and remaining vertical section(H1)when the flow start
h2/h1 0.8 1
GTM screen stability test
Segregation resistance
Allow 10 liter of concrete to stand for 15 minutes for internal segregation to occur, then pouring half of it onto a 5mm sieve of 350mm diameter which stands on a sieve pan on a weight scale. After two minutes, mortar which pass through the sieve is weighted and expressed as a percentage of the weight of the original sample on sieve.
% 0 15
HHHHIIIIGGGGHHHH SSSSTTTTRRRREEEENNNNGGGGHHHHTTTT HHHHIIIIGGGGHHHH MMMM OOOODDDDUUUULLLLUUUUSSSS SSSSEEEELLLLFFFF CCCCOOOOMMMM PPPPAAAACCCCTTTTIIIINNNNGGGG CCCCOOOONNNNCCCCRRRREEEETTTTEEEE�
Self Compacting Concrete (Site Trials)
Trial Block – Casting of SCC into Trial Column Construction Formwork
HHHHIIIIGGGGHHHH SSSSTTTTRRRREEEENNNNGGGGHHHHTTTT HHHHIIIIGGGGHHHH MMMM OOOODDDDUUUULLLLUUUUSSSS SSSSEEEELLLLFFFF CCCCOOOOMMMM PPPPAAAACCCCTTTTIIIINNNNGGGG CCCCOOOONNNNCCCCRRRREEEETTTTEEEE�
Self Compacting Concrete (Actual Site Construction)
Cooling Pipes Insulation
5 5
5 5
5 5
0 5
5 5
4 5
0 5
5 50 5
0 5
5 5
0 5
0 55 5
0 55 5
5 5
5 5 0 5
4 50 5
0 5 0 5
0 5
4 5
5 5
4 5
4 5
eqR r ui ed
4 5
4 5
5 5
4 5
4 5
4 54 5
4 54 5
4 5
4 5
5 5
0 5
5 5
0 5
4 5
0 5
4 5
4 5
4 5
4 50 5
5 5
4 5
0 5
0 5
9 P3 G a
0 5
0 5
0 5
0 5
MMMM oooodddduuuulllluuuussss ooooffffEEEEllllaaaassssttttiiiicccciiiittttyyyy Modulus of Elasticity 4
5 5 24
0 50455 9
55 0
5 0 4
5 0 5 0 05 5 0
5 5 5 0 5 5 4 5 4 5 5 4 4
75 5 0 57 457 457 5 0 557 057 4 57
557 540 5 557
57 5 04 57
5 45 0 5 55 5 50 005 504
5 5 0 5 0 5 05 0 5 5 4 5 45
45 5 0 05 4
5 0 5 5 05
505 5
0 55 400 5 0 5 0 4 5 0 4 5 0 4 5 0 4 5 0 4 5 0 4
5 55 0 5 0 5 50 5 55 05 0
5 45
5 5 4
5 5 55 0 5 5 5 45
4 5 45 5 45 5 4 4 5 545 5 5 50 0 5 0 5 55 0 5 45 0 55
5 9 4 5 9 4 5 9 4
5 9 5 0 5 9 4 5 99 5 45 05 9 4
5 9 5 0 5 95 95 550 0
5 9 4
5 5 9 550 5 95 95 5 0 0 5 9 5 0 5 95 5 9 95 540 05 9 45 5 05 5 05 5
50 4 50 5004
5 545 050 5 005 550 5 50 50 04
0 5 5 05 50 5 0 50 50 4 4
50 5 0 50 55 0 550 5 0
5M 5 4 M 5M4 5M54
M 5 0 5M 5 0 M5 5 5M0M 4
5M5 45M 5 4
05M 4
5 5 5 5M 5 0 5M 55M04 5M 4
5M 5 05 5M 5 0
5 5 5M 5 05M 4
4
5 55
5
454
50 5 0 55 4 00 5
54 4
0 5 55
5 544 4 5
5 054
54 4
05 5 4 4
5 0
5 45
5 45 4 45 45
5 4 4 5 45 0 5 0 5 0 5
9 49 0 5 900
0 5499 090 4 0
9 09 4 0 4
99
9
00
04
55
55 59 0
04
99 0
94 5 9
99
0 0 00 0 4 4
9 9 0 05 5 0 0 9 9 0 05 550 0
990 9 4
0 55 0
0 5 499
0 5 09000 549 00 59 9 0 0 9 0 459 5 0
5 5 9 50 5 45 5 5 5 5 5 5 5
65 55 5 2655255 652 566526565 55 25605205605204
560
55255
625YL
2 25 CM
65ka
25 Med
65 Yy
2565256 2 662665256020602065256254
44
44
44
44
445M
44
40
5 55
5 55
55
55
55 5
09
07
55
55
4 4 4 4 4
0
55
0M
59
99 7
MMMM eeeeggggaaaa CCCCoooolllluuuummmm nnnn EEEEmmmm bbbbeeeedddd DDDDeeeessssiiiiggggnnnn ffffoooorrrrSSSStttteeeeeeeellllPPPPllllaaaatttteeee GGGGiiiirrrrddddeeeerrrraaaattttPPPPeeeerrrriiiipppphhhheeeerrrryyyy�
Conventional Design
MMMM eeeeggggaaaa CCCCoooolllluuuummmm nnnn EEEEmmmm bbbbeeeedddd DDDDeeeessssiiiiggggnnnn ffffoooorrrrSSSStttteeeeeeeellllPPPPllllaaaatttteeee GGGGiiiirrrrddddeeeerrrraaaattttPPPPeeeerrrriiiipppphhhheeeerrrryyyy�
Anchor Embed with Vertical Plates
Design Principle Fabricated Steel-Plate Embed
MMMM eeeeggggaaaa CCCCoooolllluuuummmm nnnn EEEEmmmm bbbbeeeedddd DDDDeeeessssiiiiggggnnnn ffffoooorrrrSSSStttteeeeeeeellllPPPPllllaaaatttteeee GGGGiiiirrrrddddeeeerrrraaaattttPPPPeeeerrrriiiipppphhhheeeerrrryyyy�
Anchor Embed with Horizontal Plates
Design Principle A 3-D View
Remark: Higher Through Thickness Stress
MMMM eeeeggggaaaa CCCCoooolllluuuummmm nnnn EEEEmmmm bbbbeeeedddd DDDDeeeessssiiiiggggnnnn ffffoooorrrrSSSStttteeeeeeeellllPPPPllllaaaatttteeee GGGGiiiirrrrddddeeeerrrraaaattttPPPPeeeerrrriiiipppphhhheeeerrrryyyy�
Anchor Embed with Horizontal Plates
Full-scale Mock-up: To Investigate How High-Performance Concrete Works with Steel Embed
MMMM eeeeggggaaaa CCCCoooolllluuuummmm nnnn EEEEmmmm bbbbeeeedddd DDDDeeeessssiiiiggggnnnn ffffoooorrrrSSSStttteeeeeeeellllPPPPllllaaaatttteeee GGGGiiiirrrrddddeeeerrrraaaattttPPPPeeeerrrriiiipppphhhheeeerrrryyyy�
Anchor Embed with Horizontal Plates
Results showed Good Contacts between Concrete and Steel Embed, i.e. No Voids or Honeycombing
MMMM eeeeggggaaaa CCCCoooolllluuuummmm nnnn EEEEmmmm bbbbeeeedddd DDDDeeeessssiiiiggggnnnn ffffoooorrrrSSSStttteeeeeeeellllPPPPllllaaaatttteeee GGGGiiiirrrrddddeeeerrrraaaattttPPPPeeeerrrriiiipppphhhheeeerrrryyyy�
Anchor Embed with Horizontal Plates
Fabricated Steel-Plate Embed
SSSSTTTTEEEEEEEELLLL OOOOUUUUTTTTRRRRIIIIGGGGGGGGEEEERRRR DDDDEEEESSSSIIIIGGGGNNNN�
Steel Outrigger – Generation 1
Steel Truss Embedded in Concrete Corewall
Force Equilibrium at Meager Connection
SSSSTTTTEEEEEEEELLLL OOOOUUUUTTTTRRRRIIIIGGGGGGGGEEEERRRR DDDDEEEESSSSIIIIGGGGNNNN�
Steel Outrigger – Generation 2
2nd Generation Steel Truss Embedded in Concrete Corewall
SSSSTTTTEEEEEEEELLLL OOOOUUUUTTTTRRRRIIIIGGGGGGGGEEEERRRR DDDDEEEESSSSIIIIGGGGNNNN�
Steel Outrigger – Generation 3
Anchor Type of Embed
SSSStttteeeeeeeellllOOOOuuuuttttrrrriiiiggggggggeeeerrrr
Outrigger Arms with Anchor Plates (1)
A 3-D View
SSSStttteeeeeeeellllOOOOuuuuttttrrrriiiiggggggggeeeerrrr
Outrigger Arms with Anchor Plates (2)
A Magnified 3-D View at Merger Details between Two Outrigger Arms at Corewall Corner
Major Advantage: To Eliminate Transfer of Tensile Forces in Through-Thickness Direction, thus No Risk of Lamellar Tearing
SSSStttteeeeeeeellllOOOOuuuuttttrrrriiiiggggggggeeeerrrr
Buckling Analysis (1)
A FEM Model: To Investigate Buckling Behaviors of Steel Plates Surrounded by Concrete
SSSStttteeeeeeeellllOOOOuuuuttttrrrriiiiggggggggeeeerrrr
Buckling Analysis (2)
Stress Diagram
SSSStttteeeeeeeellllOOOOuuuuttttrrrriiiiggggggggeeeerrrr
Buckling Analysis (2)
Small Force Transfer Zone in Concrete
PPPPoooossssttttTTTTeeeennnnssssiiiioooonnnniiiinnnngggg CCCCoooonnnnccccrrrreeeetttteeee OOOOuuuuttttrrrriiiiggggggggeeeerrrr�TC2 TC5
3rd Steel Outrigger
2nd Steel Outrigger
1st Steel Outrigger
VIEW A
Pre-stresse d Concrete Outrigger
PPPPoooossssttttTTTTeeeennnnssssiiii oooonnnniiii eeee OOOOuuuuttttiiiinnnngggg CCCCoooonnnnccccrrrreeeetttt rrrrggggggggeeeerrrr
D B
TC8 TC7
C C VIEW VIEW
TC1 TC6
TC2 TC5
VIEW VIEW A A
TC3 TC4
VIEW
VI
EW
VIEW
VIEW
6 /F LOWER MECHANICAL FLOOR PLAN
D B
CCCClllloooossssiiiinnnngggg UUUUpppp�
ò Super High-rise Buildings are always Steel Structures which Needs Good Planning;
ò Good Planning Needs Frozen Design;
ò Hong Kong is a Market Driven Society. Frozen Design before Construction are Rare
ò With Advanced Concrete Technology, Concrete/Steel Composite Design Always Provides Feasibility for Design Changes
ò Thorough Understanding of Interaction between Concrete and Steel therefore Becomes Important.
Harbour Gateway
Thank you!