the use of cpm in construction five

Upload: constanza-belen-vergara-lagos

Post on 02-Jun-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 The Use of CPM in Construction Five

    1/21

    CHAPTER FlVE

    THE CONTROL MONITOR PHASE

    Since CPM users have no crystal balls, circumstances will frequently force

    changes to the plan of accomp lishment for projects. Strikes, adverse weather,

    shipping delays, change orders, and numerous other conditions can disrupt

    the original plan and schedule. Activities are sometimes discovered to be

    necessary despite the fact tha t they are no t on the arrow diagram and no t in

    the schedule and certain activities in the project are found to be

    unnecessary. The schedule can go out-of-date quickly for these and other

    reasons.

    W he n this happens, The C ontrol M on itor P hase of CPM is effectively and

    valuably used. This phase enables the project manager to quickly and

    eff iciently revise and refine the in pu t information, including the arrow diagram

    and the duration estimates, so th at CPM can indicate the status of the p roject

    as we ll as prod uce new up-to -date schedules for the activities yet to occur.

    The Control Monitor Phase consists o f collecting actual job data and

    subm itting it to CPM for M onitoring purposes.

    M on itoring can be done as frequently o r a s infrequen tly as the user desires

    or finds necessary. It uses inform ation suppiied abou t new activities, changes

    to durations, com pleted activit ies and rearrangements of the arrow diagram to

    indicate what effect al1 these have on the original schedule produced. In

    addition, a new schedule is produced for activities remaining to occur based

    on this job data.

    On most projects, Monitoring is done monthly.

    INPUTS

    Actua l job data, as used in the Con trol M on itor Phase, include the fo llow ing

    items:

    1.

    ddirions ro rhe arrow diagram

    New activit ies caused by change

    orders or by n ew approaches t o the project.

    2 Delerions from rhe arrow diagram For the same reason as 1.

    3.

    Changes

    One might decide to change an activity's code, cost or

    resource requirement for any reason.

    4

    criviry crual Stan Dates Used for historical record keeping.

    5.

    criviry crual Finish Dares

    For notif ication of an activity's

    completion; used for h istorica l r e l r d keeping.

    6

    crivity Percenr Complere

    A n indicat ion of wh at port ion of the cost is

    payable to the contractor because of completed work upon the act ivi ty.

    (Percent com plete has nothing to d o w ith the t ime aspects of the activity; it

    relates only to co st. Time progress on a started bu t n ot com pleted activity is

    established b y reducing the activity's d uration to the amou nt o f t ime remaining

    for accomplishment as of the monitor date.)

    Actua l job data is provided CPM via forms or more frequently by

  • 8/10/2019 The Use of CPM in Construction Five

    2/21

    marking on previously produced schedules or reports. Figure 5-1 on the

    following page, illustrates a schedule marked up to show progress as of the

    date indicated in the upper left corner. All the markings are self-explanatory.

    The collection of job progress data by marking-up actual schedules ensures

    careful and frequent reanalysis of the schedule by field personnel and

    additionally produces a valuable job diary.

    OUTPUTS

    The Control Monitor Phase is capable of producing the following items:

    Time Status Reports

    Revised CPM Reports

    Cost Status Reports

    Requisition Backup Reports

    Payment Documents

    From the CPM Schedule's point of view, the objective of monitoring

    progress is two-fold. One, it is desirable to determine where the project is in

    relation to what was originally scheduled; and two, it is necessary to produce

    revised scheduled resource analyses, etc., on the basis of what the job

    situation is at the time of monitoring.

    As a result of CPM progress monitoring, Cost Status Reports, Requisition

    Backup Reports, Payment Documents and current, as-of-now, Cashflow

    Projections are produceable as by-products.

    TIME STATUS REPORTS

    There are two types of Time Status Reports; one for specific (Key) activities

    within a single project and one for each project in a multiproject program of

    effort.

    A Key Activity Status Report is illustrated in Figure

    5-2

    on the following

    page. The activities contained in the report illustrated were identified as Key

    activities by the project manager so that a synoptic status report such as this

    could be produced. Note that for each Key Activity shown is:

    1.

    The ~'ccur rence ate The CPM EARLY START value.

    2. The 'Target Date An externally supplied date by which time the activity

    was to have been started.

    3.

    A Status Value indicating how far ahead (if positive) or behind (if

    negative) of the Target Date is the schedule for the activity.

    4. A Trend Value ndicating whether or not the schedule for the activity is

    better than the last time the Status Report was produced (Trend Up), worse

    than last time (Trend Down) or exactly the same as the last produced report

    (Trend Steady).

    Use of such a report provides the project manager or anyone else with

    a quick evaluation of where the project is time-wise.

  • 8/10/2019 The Use of CPM in Construction Five

    3/21

    C 2 & ?

    V I W W

    w

    c ;

    C m

    Z O O

    V I

    9 l n Q

    Z

    U W

    7

    z

    t C

    O N 2

    o m o

    o m o

    Q n z

    0 0

    O

    4 . 4

    e

    4

    4

    o

    FIGUR

    5 1

    6

  • 8/10/2019 The Use of CPM in Construction Five

    4/21

    C P H A U TO M A TE D C O N TRO L S Y S TE M

    L A M O l FRO H?NC.ER R E N N A T I O N P G F

    K E ~CTI VITY S T A T U S R E P O R T S E W E Y C E =

    TIWGET

    ~ O R K - W E E K

    =

    5 DUMMIES

    NO

    FINISHED NO

    AS

    OF

    1 5 D E C 7 5 P R E D I C T E D C O M PL E T IO N

    .........

    C 1 J TRACE C EA D E SC R I P T I ON

    1 5 6 1

    '73C .

    KE

    t S k I T C H GEAR I N S T A L L E D

    0 1 3 8 1

    0 3 0 0 0

    KEY

    HAWGER ROOFED

    0 1 5 9 0

    0 3 0 0 0

    K FV

    H A G E R F I R CP R nO F E O

    q 1 5 7 7 )3 ?

    K E Y 1 S T

    L Q

    O F F I C E D 9 Y E

    0 2 0 0 0

    0 3 0 0 0

    K E Y

    P R 3 J E C T C O P P L E T

    O C C UR A N CE T A R G E T P R E V I C U S

    D A T E D A T E S T A T U S T R E N 0 O C C UR A N CE

  • 8/10/2019 The Use of CPM in Construction Five

    5/21

    PS D F 1 5 C E C 7 5

    A L L P R O J E C T S T A T L S R EP O R T

    C P M 1 1 A U TO M P T ED C C h T R C L S Y S T E M

    P A C E 1

    S E O

    =

    P R C J E C T

    ................ F R C J E C T ..... .

    I D N AM E

    P R E O I C T E O S T A T U S

    C O M P L E T I C h T A R G E T

    1

    N

    D A T E D A T E C P L - OA Y S T R E N 0

    P E R I O D S

    1

    N

    T R E N )

    P R E V I O L S D A TE O F

    COMP L A S T

    D A T E U P O A T E

    A N A H B W A R E H O C S E P N A R BO S T O R AG E C C 3 D M A R 7 6 1 O C T 7 5 - 1 7 1 O W N

    AW CAN A M E Rl C d N P H O l C C A l C F F I C E B L D G 2 5 P P t 7 6 2 5 S E P 7 6 1 2 2 U P

    C H A S H D F F C E / S T C F A G E C l - ES A P EP K

    E

    A S W R E IM: l O J A N 7 0 Z 2 A U G 7 5 141 S T E A D Y

    CUWIL C O L L I N S M F G ~ I L S C R B L D G

    D A AB T D A V I S P B B A T O I R

    ObWAR O A V I S CO '4P A N, MP RE kf OLS E

    i

    2 2 J U L 7 6

    2 O J U L 7 6 - 2

    DOWN

    1 9 M A R7 7 1 5 M l R 7 7 1 4 U P

    I O J U h 7 6

    1 5 M4 Y 76 6 O O i h

    3 1 S E P 7 7

    3 1 S E P 7 7 O

    S T E A O Y

    C R lN K C A V I S I C E R l F K

    M GF iK 6 M hi KE Y H O U S E R E G I O N A L Z C C 2 5 0 C T 7 6 3 0 C C T 7 6 - 5 S T E A O Y

    U S M N W AN AG EM EN T T P A l N N G C EN TER U SA RT WT l b F E e 7 7 l S F E B 7 7

    1

    S T E P D Y

    U SP AV F O B P A V I L I C N 1 8 D E C 7 7 I O F E e 7 8 5 3 U P

    V AM AC V A H O S P I T A L A C D I T I O N C A CA L I S L A N O 1 5 F E B 7 6 2 5 F E 8 7 6 1 0 S T EA O Y

    Z YT RO Z Y T R C h I N C 3 F F I C E P R CC E SS I NG C E NT ER I O J U N 7 0 2 4 J A N 7 6 - 1 3 7 D O l h

  • 8/10/2019 The Use of CPM in Construction Five

    6/21

    AS O F l S D E C 7 5 C PM 11 A UT CC AT ED C C N T R a S I S T E M

    PACE 1

    TROURL ED PROX.U.-SJA.TU f- fEPUlr . . . - .

    -

    qF

    PPn lFCT

    PR E I C T E D S T A T U S P 10M PR EV IO US DATE ff

    C O M P L E T I O N T A RG E T I N N COM P L A S 1

    D A T E D A T E C AL -D AY S T R E N 0 T R E M DA T E U P D A U

    W m A N A f l R C

    S T i l f A E

    I IL

    3

    PAR76 1 1 M T 3 5

    .?m . n Y N i

    OBT AIN ROOF STEEL

    A YA R D A V I S C O MP AN I b A R E M U S E 1 0 J U N 7 6 1 5 M A Y 7 6 - 2 6 D W N 2 2 W A Y 7 6 3 0 N OV 7 5

    E X 1 M S O N R Y VE S1 H A L L L I P T

    W D E R S L AB P L BG S OU TH H U F

    Z Y TR O Z Y T R ON I N C O F F I C E # P R U E SC I N G C W T E R 1 0 J U h 7 6 2 U A N 7 6 - 1 3 7 OOYN 6 2 8 M A Y 7 6 1 5 D E C T S

    L A T H P L AS T E R 4 T H FLR

  • 8/10/2019 The Use of CPM in Construction Five

    7/21

    Figure 5-3 i llustrates an All-Project S tatus Report. No te that it is similar t o

    the Key Activity Status Report described earlier. The major difference is of

    course that, for each project, only the termination date (Project Completion

    Date) is considered. This n a multi-p roje ct environment is al1 that is

    required to p rovide the user w ith an easily evaluated report on the status o f

    each project in the program.

    The optimum situation is one in which the All-Project Status Report is

    s u ~ p o r t e d y Key Activity Reports for al1 projects.

    Figure 5 4 is a special kind of mu lti-project status report.

    It

    is an extraction

    from al1 the projects of those tha t are in-trouble. In the case of those

    illustrated, in-trouble is defined as any tha t are behind schedule (S ta tus less

    than zero) and getting worse (Trend

    Down). It is possible to identify

    trouble in any way desired.

    REVISED REPORTS

    Because time has elapsed whe n m onitoring takes place and because

    changes w ill have been made to t he original inputs, the Control M on itor Phase

    produces new, revised versions of al1 the reports described as available in the

    Scheduling Phase. It mu st be kep t in mind, however, that w hen such revisions

    occur the as o f date, or date set equal to time-zero, w ill change to th e date

    monitor information was collected instead of remaining at the project start

    date. This means that from the point of view of schedule calculation, each

    schedule produced ignores wh at had been previously scheduled and considers

    only what exists when calculations are done. Earlier in this chapter it was

    stated that time progress on a started bu t no t com pleted activity is established

    by reducing the activity's duration to the amount of t ime remaining for

    accomplishment as of the monitor date. This is so that the calculation of a

    revised schedule w ill be done properly fr om the new time-zero date.

    Because of th e above, the CPM user co llecting actual job progress data

    mu st take care to rev iew al1 activities that had been scheduled t o start du ring

    the time that had elapsed since the schedule being monitored had been

    produced. Long lead time activities, such as delivery activities or shop

    draw ing preparation, if no t duration (.e., reduced to re flect time elapsed since

    their duration estimates were last established), will be assumed to need as

    much time as was previously indicated despite the fact that the previous

    duration estimate was relative to an earlier time-zero date.

    If it is desired to measure a revised schedule against what was originally

    scheduled, a Relative report can be prod uce d.

    Figure

    5-5

    is a page from a CPM schedule report in wh ich LATE STA RT and

    LATE FlNlSH have been replaced by dates that have been calculated not in

    the norm al backward-pass way (see Chapter for an extensive discussion of

    the calculation of Late Dates via the backward pass method), but by

    establishing as the starting point for the backward pass the original project

    completion date.

    If project progress has been less than what was originally scheduled or

    if change data entered into CPM during the Control Monitor Phase has

    lengthened the revised schedule, EARLY S TA RT and EARLY FINISH will win d

  • 8/10/2019 The Use of CPM in Construction Five

    8/21

    CPH I PUTOCATED CONTROL SYSTEM

    L A H O l F B O H L U G f R R E N U V A T l O h P AG E L

    RE LATIVE FLU AT REPCPT SEQUEVCk

    =

    T F L

    ~ O R K - W E E ~ - - u ~ C ~ ( ~ ~ N C - F I N I S H E D

    O

    AS DF 15 CE C7 5 PR EO IC TE O COMPLETION........ .2OFEB7-6

    CURRENT COhTRACT COMPLETION..15JAN76

    VARIANCE I h WORKING OA-YS - 24 -

    0 1 3 8 0 C L 39 1 1 L A T t O C F

    MTL STUOS

    1ST FLR YEST

    C 1 3 9 1 C 1 4 1 4 1 L b 1 H

    CFF HTL

    STUOS 1ST FL P EdST

    0 1 4 1 4 0 1 4 2 2

    2 LATH CFF

    MTL STUDS

    ZYD FLR YEST

    F l N l S H E AR L Y EA R LY

    .

    RE

    L

    PE L

    D AT E S TA RT F I N I S k S TA RT F I N I S H R F L K

    0 1 4 2 2 - 0 1 4 3 5

    1 LATH CFF HTL ' LOS ZYD- FLR EAST ..

    1 ,1437 21 4 41

    1

    FLECT CFF CT3hDUl T 1ST FLR YEST

    ' 2 1 4 4 1 0 1 4 4 6

    1 E L E CT C FF C C K I U I T 1 ST F L R E AS T

    ~

    1 4 4 8 ' 21 45 4 1 E LE CT C FF C O hD U IT ZND F L P WFST i 9 0 E C 7 5 3 0 ~ ~ ~ 7 5 2 1 b K I I 7 54 N O V 7 5 - 2 6

    ' 1 4 5 4 C 1 4 5 F 1 L E C 1 C F F C O N D U IT 2 YD F L P E A S T B O E C .7 ' 3 1 U E C 7 5 2 4 h O V 7 5 2 5 N O V 7 5 2 0

    0 1 4 5 0 0 1 4 6 4 2 I Y S U L C FF I PJ SU L AT IC N I S T F L R W EST 3 1 0 E C 7 5 0 2 J A h 7 6 2 5 h O V 7 5 2 7 N O V 7 5 - 2 6

    0 1 4 6 4 0 1 4 6 7 I h S U L C FF I " 1 S U L A T I O N 1 S T F LR E A S T

    -- - O Z J A N 7 6 0 6 J A N 7 t 2 7 h O V 7 5 0 1 D E C 7 5 - 2 6

    C 1 5 i l C 1 5 0 7 1 F LB G C FF P L C C F I K T U R E S 1 S T F L k E AS T & J A N 7 6 . 0 7 J A N 7 6 O l C E C 7 5 0 2 0 E C 7 5 - 2 6

    0 1 5 1 1 0 1 5 1 5 5 T PA RT C C F T C I L E T P b R T I T l O N 5 1 S T F LR E AS T 0 7 J A N 7 6 4 J A N 7 6 0 2 D E C 7 5 0 90 E C- r5

    _y=

    0 1 5 2 0

    C 1 5 2 2 5 l P A R T C F F

    T O I L E T

    PARTI T IONS 2NC

    FLG h E S T 1 4 J A Y 7 t

    2 1 J A N 7 6 0 9 C E C 7 5 1 6 0 E C 7 5 - 2 6

    0 1 5 2 5

    0 1 5 3 5

    5 l P d R T C F F

    T 3 1 L E T P A R T I T l O h S 2 h C

    FLR EbST

    2 1 JA h 7 6 2 B J A N 7 6 1 6 D E C 7 5 2 3 C E C 7 5 - 2 6

    '

    0 1 5 3 5 0 1 5 6 5 2 I A C C ' C FF T O I LE T A C CE S SO IE S 2 PD F L P E PS T 2 A J A N 76 3 0 J a N 7 t 230Ec< 2 5 0 E C 7 5 - 2 6

    i

    0 1 5 6 9 0 1 5 7 2 1 G

  • 8/10/2019 The Use of CPM in Construction Five

    9/21

    up later in time than their Relative counterparts. It is for this reason tha t a

    Relative Report does not refer to LAT E STA RT or L ATE F INISH.

    Note in Figure 5-5 that the float field is headed RFL which stands for

    RELATIVE FLOAT. RFL is calculated by subtracting EARLY START from

    RELATIVE START, and when the revised project schedule has been

    lengthened in any way, it wil l be a negative number. For this reason, some

    CPM users when referring to float calculated in this manner will erroneously

    cal1 it Negative Float. This practice should be avo ided since if the revised

    project schedule is less in time than the original, the RFL value will be positive.

    It doesn't mak e mu ch cense to cal1 it negative w hen it can be either.

    The C ontro l Monito r Phase can, of course, prod uce revised versions of th e

    Resource Reports and the Cash Flow Analyses described in the chap ter on the

    Scheduling Phase. The,only difference in these revised versions is that they

    project resource and cash posit ions for the wo rk remaining as of the m onito r

    date.

    COST STATUS REPORTS

    The CPM user natural ly wants t o kn ow th e t ime status of his project, bu t in

    addit ion, he wants to know its Cost Status. The Control Monitor Phase

    produces a report tha t indicates just h o w the project looks from a cost

    standpoint.'

    This report whic h is called the Cost S tatus Report is prepared in the

    following fashion:

    As described in Chapter 4 the contractor must first prepare cost estimates

    for each of the activities in the project. Then, for activities that have been

    completed, as shown in the MONITOR Report, appropriate costs can be

    calculated. This gives the contractor an ES TIMA TE D COS T TO DATE. This

    estimated cost is then a yardstick against whic h the contractor can com pare

    the ACT UAL COST TO DA TE for that

    articular

    phase of work. The actual

    costs are relatively easily collected. Anyone who keeps books can determine

    his actual costs. CPM, however, gives him at any tim e during the progress of

    the project an estimate of the cost for the w ork reported as complete so th at

    effective comparisons can be made. W ith this report the co ntractor does no t

    have to wa it unti l the end of the project to discover the status of his costs.

    Cost Status Reporring is described ar great length in Chapter of this book.

    This secrion will discuss it as a function of The Control Monitor Phase.

    6

  • 8/10/2019 The Use of CPM in Construction Five

    10/21

    The process of Cost Status Report creation can best be explained with a

    sample project. Consider that th e arrow d iagram b elow represents a project for

    which periodic Cost Status Reports were desired.

    The f irst step necessary to be taken would be the definit ion of the costs

    involved per activity. Assume that th e table in F igure

    5-6

    describes the costs

    estimated for the com pletion of each ac tivity. This c ould be prepared any t ime

    prior to the pro duc tion of a Cost Status Report, and it cou ld have been revised

    at any time.

    The entries in this table merely indicate h o w m uch money sho uld have been

    spent for various categories (type s) of expense wh en each activity had been

    f inished. For example, wh en ~ c t i v i t y is f in ished, the contractor wil l owe

    somebody 488.10 for bulldozer expenses, 135.00 for general labor, and

    100.00 for engineering expenses. W he n B is finished, 1,085.30 w ill be ow ed

    for con crete, 309.10 for concre te labor and 80.00 for general labor. The cos ts

    for

    al1 activities in the project are similarly described.

    The second inp ut is info rm ation a.bout w hic h activities have been finished.

    Notice in Figure 5-1 that the Marked-up Schedule indicates clearly what

    activities are completed. This is, thus, a good source of this second input.

    Suppose that at the time a Cost Status Report was desired for the project

    described above, activities A, B, C, D, C and I had been finished. W it h this

    information, the ESTIMATED COST

    TO

    DATE for the various categories

    types) of expense can be calculated.

  • 8/10/2019 The Use of CPM in Construction Five

    11/21

    I Activity Category Expense

    1

    2

    A 48 Bulldozer 488.10

    46

    Gen. Labor 135.00

    73

    -

    Engineering 100.00

    2 3 15 Concrete 1,085.30.

    16 Concrete Labor 309.10

    46 General Labor 80.00

    2 5 C 51 Excavation 1,955.10

    73 Engineering 190.30

    3 4 D 10 Architect 100.00

    4 8

    F

    (No Expense)

    4 9 G 22 Carpenter 478.35

    18 Lurnber 1,009.90

    46 General Labor 195.00

    5 - 6 E 38 Masonry Contract 1,800.00

    6 - P 10 - Architect 75.00

    73 - Engineering 50.00

    6 - 7 38 Masonry Contract 1,800.00

    46 General Labor 205.60

    7

    10

    J

    (No Expense)

    8 12 H 15 Concrete 975.00

    16 Concrete Labor 255.00

    46 General Labor 185.00

    9 11 K 46 General Labor 90.00

    10- 13 N 22 Carpenter 195.00

    18 Lurnber 555.30

    11 10 M 15 Concrete 1,907.00

    16 Concrete Labor 655.00

    11

    12 L 46 General Labor 195.00

    12- 13 O (No Expense)

    FIGURE 5 6

    6

  • 8/10/2019 The Use of CPM in Construction Five

    12/21

    If Ac tivity A is finished, the projec t shou ld have cost $488.10 for catetory 48

    Bulldozer, $135.00 for General Labor, category 46, and $100.00 for

    Engineering. If Activity B also is complete, the costs indicated for it will be

    added to those incurred for A. This wil l add costs in two categories

    Concrete and Concrete Labor and increase the cost of one already

    calculated. General Labor will go from the existing $135.00 to $215.00 because

    of Activ i ty

    A

    ($135.00 for A and $80 for B). The com pletion o f Ac tivity C will

    create a cost value for category 51

    Excavation, and increase the cost for

    Engineering by $190.35. All othe r finished activities w ill con tribute an

    amount of expense to the project.

    When al1 activities reported as finished have been noted, the amount of

    money

    that should have been spent

    based on work reported as comp lete has

    been calculated. In the case of th e projec t described above, the EST IMATE D

    COST TO DAT E (Table A ) wo uld have been calculated for each category and

    for the project in total.

    T BLE

    ategory

    10 ARCHITECT

    15 CONCRETE

    16 CONCRETE LABOR

    38 MSNRY CONTRACT

    46 GENERAL LABOR

    48 BULLDOZER

    51 EXCAVATION

    73 ENGlNEERlNG

    TOTAL

    OR

    THE PROJECT

    E s t i m a te d o s t t o D a t e

    A second kind of information can be calculated if the contractor has

    estimated his per activity expenses. He can use the table in wh ich

    al

    costs are

    indicated to determine wh at was the total budge t (estimate) for each category

    of expense. Concrete, for example, contributes to the cost of activity B

    ($1,085.30), H ($975.00) and M ($1,907.00). The total budget for concrete in

    the p roject described above is $3,967.30. This means that w he n the projec t has

    been completed, the contractor will expect to have spent $3,967.30 for

    concrete. The to tal estimate for each category of expense can be fou nd in the

    same way, and if it were done for the project above, The Cost Status Report

    would begin to grow as shown in Table B.

  • 8/10/2019 The Use of CPM in Construction Five

    13/21

    T BLE B

    Category

    10 ARCHITECT

    15 CONCRETE

    16 CONCRETE

    L BOR

    38 MSNRY CONTRACT

    46 GENERAL LABOR

    48 BULLDOZER

    51 EXCAVATION

    73

    ENGlNEERlNG

    Estimated Total Cost Estimated Cost to Date

    TOTAL FOR THE

    PROJECT

    $8,248.50

    W ith this inform ation it is possible to determine wha t percentage of the total

    money to be spent has been spent based on the activities reported as

    complete. The contractor can see that he has completed activities involving

    27% ($1,085.30/$3,967.30) of wha t he wil l s ~ e n d or concrete, 25%

    $309.10/$1,219.10) of his concrete labor budget, 100% of the masonry

    contract money and so on through each type of expense. The Cost Status

    Report, including this item of information, would appear as in Table C.

    T BLE

    C

    Category

    Per C ent

    Est To tal Est Cost

    Spent Cost

    l o D ate

    10 ARCHITECT

    15

    CONCRETE

    16 CONCRETE LABOR

    38 MSNRY CONTRACT

    46 GENERAL

    L BOR

    48

    BULLDOZER

    51 EXCAVATION

    73 ENGlNEERlNG

    This informa tion is valuable in and by itself because it indicates h ow m uch

    activity has been accomplished cost-wise. However, if the co ntrac tor supplies

    inform ation abou t h ow m uch was actually spent for concrete, for general labor

    and for al1 other items of expense, he can find ou t whether or no t he is on

    schedule in terms of cost.

    As a project proceeds, the contractor collects bills, invoices and so forth as

    part of his normal bookkeeping procedures. These at any particular point in

    time are ACTUAL COSTS TO DATE. If these actual costs are known, two

    additional items of info rma tion can be calculated and placed in the Cost Status

    Report. The DO LLAR DIFFERENCE is the result when the EST IMATED COST

    TO D ATE for a category is subtracted fro m that category's AC TU AL COST

    TO DATE. The DEVlATlON for a category is the ratio of actual costs to

  • 8/10/2019 The Use of CPM in Construction Five

    14/21

    estimated costs (AC TU AL COST TO DATE ESTIMATED COST TO DATE).

    The DEVlATlON for a category indicates what percentage of the estimated

    cost is actually incurred; the DOLLAR DIFFERENCE is the amount and

    direqt ion b y whic h the ESTIMATED COST TO DAT E was missed.

    er

    Cent Est To ta l

    C ategO v S pent ~ o s t

    10

    Architect

    57

    $

    175.00

    15

    Gancrete

    27 3,967.30

    16

    Concrete

    Labor

    5 1,219.10

    38

    Masonry

    Contract

    100 3,600.00

    46

    Gen Labor 39

    1,085.60

    48

    Bulldozer

    100 488.10

    51

    Excavation

    100 1,955.10

    73

    Engineering

    85 340.30

    Es t C os t h t u a l C o s t

    l o D a t e l o D a t e

    Dev ia t ion

    In the pro ject tha t has been used as a sample for the Cost Sta tus Repo rt, the

    ACTUAL COST TO DATE entr ies must be assumed. Assuming the actual

    costs indicated, the completed Cost Status Report based upon activities

    reported as finished and on actual costs collected would look like Table D.

    This report tells the contractor what is the cost status for al1 categories of

    expense defined by him. The f inal Cost Status Report contains the inform ation

    described above as well as summary type data for the entire project. The

    completed Cost Status Report for the project described above is shown in

    Figure

    5-7

    on the fol lowing page.

    The Cost Status Report,

    because i t indicates how much money is being

    spent in relation to what was expected is a very valuable report. The project

    manager can tell from this report which areas of expense need investigation,

    wh ich e stimates perhaps need revision, an d h o w he is doing in general as far

    as his costs are concerned.

    There are variations o n the repo rt sh ow n here as a sample. One can include,

    as part of the Cost Status Report, inform ation abou t the cost of change orders

    or other revisions or separate the labor costs from the material costs just t o

    ment ion only tw o.

    One question that always arises about the procedure described above

    concerns itself with activit ies that have started but have not yet been

    completed. A t the tim e the Cost S tatus Report is desired, activities in this sort

    of circumstances are assumed to be on schedule, and their costs are

    pro-rated accordin g to h o w ma ny days they have been in progress relative

    to their schedule dura tion. To illustrate: if Ac tivit y E were a six-day a ctivity tha t

    had

    been reported as STAR TED three days before the effective date of the

    Cost Status Report, the Cost Status Report would have included only half

    316)

    of the costs involve d for th at activity.

  • 8/10/2019 The Use of CPM in Construction Five

    15/21

    COST STATUS REPORT

    Total Estimated 15.069.05

    Revised Estimate 14.975.15

    Cost To Complete 6.810.55

    Categoiy Budget

    Number Name Amount

    Architect

    Concrete

    Concrete

    Labor

    Masonry

    Contract

    Gen Labor

    Bulldozer

    Excavation

    Engineering

    Pement

    Complete

    Est Cost

    To Date

    Est Cost To Date 8.248.50

    Act Cost To Date 8.164.60

    Dollar Difference 83.90

    Act Cost Dd la r

    To Date Difer Deviation

    400.60 20.00 Over .95

    527.35 39.25 .O8

    1955.00 O

    .99

    260.00

    30.30 Over .89

    FIGUR 5 7

  • 8/10/2019 The Use of CPM in Construction Five

    16/21

    REOUlSlTlON BACKUP REPORTS

    Since part of the Control Monitor input data is information about what has

    been completed Activi ty Percent Complete) and since one of the initial inputs

    is a cost value per activity, al1 the elements are available to produce reports

    that support contractor requisitioning.

    Figure 5-8 presents one page of such a report. It contains al1 the activities for

    the sprinkler subcontractor whose code is sprnk. The cost value per activity

    was assigned by the contractor and agreed to by the owner. The PERCENT

    COMPLETE figure represents the portion of al1 the work to be done on the

    activity that the contractor and the owner agree should be paid for. The report

    calculates for each activity how much should be paid to the contractor,

    therefore. The report also sums the amount earned for al1 activities to produce

    a total for the subcontractor.

    All subcontractors have their own groupings of activities, and each is

    treated in the manner described above. When al1 trades have been presented,

    a summary report representing the totals for each is presented. Figure 5-9 is

    such a summary.

    An interesting feature of The Requisition Backup Report is illustrated in

    Figure 5-8. Notice that one of the activity descriptions refers to

    Material-On-Site and, in fact, that the cost is offset to the right of the costs

    presented for other activities in a column also noted as Material-On-Site.

    This feature facilitates payment for materials delivered to the site, the cost of

    which is included in the cost value assigned to perhaps several activities for

    which no work has yet been accomplished. To indicate that such activities

    were partially complete in order to get the Requisition Backup Report to

    generate an amount earned value equal to that which the contractor is due for

    the material on site) distorts the project progress position of the activity and in

    many cases is not allowed by the owner. The report must therefore have some

    way to generate payment for materials and the Material-On-Site MOS: type

    of activity is the way.

    When such an approach is used, a special artificial activity coded to

    represent only material and to be ignored by the CPM Schedule Reports) is

    added to the CPM data set. The special coding generates the result illustrated

    in Figure 5-8. In addition see fol lowing paragraphs) CPM-based Payment

    Documents will accumulate Material-On-Site amounts for entry on the final

    payment authorizations.

    Use of MOS activities must be carefully disciplined. It must be borne in mind

    that a cost has been entered into the system twice once in the cost assigned

    to the artificial MOS activity and again in the cost assigned to the activities in

    which the material will be used). For this reason the user must adjust the MOS

    value to reflect subsequent payment via completion of work activities.

    Requisition Backup Reports can be used by the contractor to justify what he

    seeks in payment from the owner, and it can be used to establish what the

    contractor should pay his subcontractors.

    The cost values assigned each activity for requisition to the owner can be

    factored by CPM by any percentage to produce higher or lower values. If in the

    case of the subcontrac?or illustrated in Figure 5-8 the agreement between the

  • 8/10/2019 The Use of CPM in Construction Five

    17/21

    0 1 3 7 4

    0 1 4 1

    7

    S P F UK S P f i Ih K L ' QS w i T k i H f q

    0 1 4 0 8 Cl5l ;

    S P F ' J K

    Y c Q

    I ' J S T A L L F AP T.L .dK5

    1 4 1

    1 5 1 ' S P r V K " 6 I :i CT /T FS T

    FY- lP P .CTZL f 5

    U 1 4 1 7 U 1 4 3 1

    S P F Y K S F 2 I N K L C Q S F O V d3l 1 %

    0 1 4 1 7

    0 2 4 9 9 S f 0 h C

    b r

    5 P F l h K L C g S C CA V cGl - 1N

    1 4 3 1 L l i t 9 S P E U C T E S T S CK T 4 KL E ;S

    P?

    E V

    T H l S

    O U C GE T P C T P C T

    C C U S T

    E A H L E D

    P A G E 2 7

    T H I d P PL I C A T I J a F A R N E U

  • 8/10/2019 The Use of CPM in Construction Five

    18/21

    z

    -

    e

    O

    i i L

    -

    A

    V

    d

    d L A L -

    " 3- ,

    4 -0-

    x

    2 2 -

    ~ K d L ~ r L d u V 8 P l d i d d l

    < Y > d , a , ~

    . n f i o t - ~ - > ~ < ~ .n d h J s a

    c U J C < 3 ~ 2 a , ~ - i . . ~ a 1 , d rc ; 9 - ~ - i ; - a c . < a

    . x V d O U A 3 1 - 2 7 x ' x l i l a U . 1 m r l > . ~ . . ' I + , -

    FIGUR 5 9

  • 8/10/2019 The Use of CPM in Construction Five

    19/21

    contractor and the sub was for 117,471.20 when al1 his work was completed.

    the ratio of that amount to what had been agreed to between the contractor

    and the owner ( 133,490.00) is 88 . This ratio would be the factor applicable

    to the amounts earned for that sub, and the result of such factoring would

    justify and support payment to the sub. Figure 5-10 is the backup for payment

    to the subcontractor represented t5y the page illustrated.

    P A Y M E N ~

    OCUMENTS

    Many owners use CPM as the initial input to an automated contractor

    payment operation. One such organization is the Veterans Administration

    whose payment document is illustrated in Figure 5-11. Use of such an

    approach has significantly reduced the amount of time necessary for

    processing of payments, the result of which is faster payment to the

    contractor.

    Note in the Payment Document illustrated in Figure 5-11 that a separate

    entry is made to accommodate Material-On-Site values. These values are

    those that were discussed earlier in this chapter.

  • 8/10/2019 The Use of CPM in Construction Five

    20/21

    C P M II A UT OMA T E O

    CONTROL

    s Y s T E n

    ~ n ~ O lF BD W NG E R R E N [ N * I O N

    .

    .-

    .

    . . PAG E

    COST EARNEO REPORT BY TRAOE

    A S O F 1 5 0 E C 7 5

    TRAOE

    =

    SPRNK

    P R E V T H I S

    l lOLHT W TE R I A L

    BUDGET

    -

    PCT PCT

    c r ~R~DE .

    EEDES R 1

    O

    ON _ -

    .

    _

    _

    .

    _

    -

    . E ~ N E D M S I T E

    0 1 3 7 4 0 1 4 1 7

    S P R N U

    SPRINKLERS

    un R G H IN

    0 1 4 0 8 0 1 5 1 9 S PR NK M R INSTALL FOAM TANKS

    0 1 4 1 0 0 1 5 1 9

    S PR NK MER I N S T / T E S T F O M N O Z Z L E S

    0 1 4 1 7 O 1 4 3 1 S PR NK S P R I N K LE R S

    F C M

    RGH I N

    0 1 4 1 7 - 0 2 4 9 9

    S P R N K M O S S P R I N K L E R S F C A M Rt I N

    6 1 4 3 1 0 1 4 4 9 S PR NK T ES T SPR I N K L E R S

    ci

    I

    *

    *

    TOTAL H R TRAOE

    m

    Y

    117,471.20

    AMOUNT EARNED 10 DATE .

    P R EV IO U S A M W W E A R M D

    T H I S A PP L I C A T O N E AR NE D 9 36 8 0 0

  • 8/10/2019 The Use of CPM in Construction Five

    21/21

    C.@. CWAhGF

    R C

    P P EV R F P T D

    S Y U .

    A 1 .3

    C.O. P R O C F F D 0 9 C P P F V ? E P T O N O. O T C

    FIELD

    C H AN GE

    ne

    P R E V

    Q P T Q S Y M .

    1 1

    F I E L 0 P RO CE F9 O C F REV Q E PT 9 SVM. A 7

    T I M E E X T E N S I O N S F RE V R F P T f l NO. 1 T O

    I S S U E D T H I S P F R 1 0 0 s C O 2 3 CAC

    Prl

    H

    I S S U t U T H 1 S D E R I ' 7 0 F Pn -H 1 C A N C)

    I S S U E D T U 1

    5

    P E Q I C I C F C O - 3 4

    I S S U E O T H I S PEQ1 P F C O - 3 5

    I S S U E U T H l Z PF Q l C O F C q - 3 6 C A C FPC

    l S S U E 0 T H I S P E R I C O P F r l - B I C A P I C )

    I S S U E O T W I S P F P I C D C C ? -q 7 1 F P T - K )

    I S S U t U T H I S D E Q I C C F C O - 3 8

    I S S U E D T U 1 S P E R l C r F P q -K I C A N C

    I S SU EO T H l S P E R I C P F C C - 1 9

    I S S U E ~

    T n r s O E ~ I C O r v

    C R l G l N A L C O Y T R d C 7 Au OU hT

    Y E T C H A N G E

    C U R R E N T C O b ' 9 A C T A M G U N T

    V A L U E

    OF

    W qP K I N P L A C F T O 1 2 - "1 - 7 5

    V A L U E F W C Q K I F ( S T b L L E C

    -

    C U R QF V T P E R I O O

    V A L U E O F M OQ K I N P L A C E TC 1 2 - 3 7 - 7 5

    V A L U E F M A T E R 1 4 L O h S I T E

    V A L U E O F hOo N O 1 C O UP L ET E O

    E A RY EO T C C AT E ( 1 2 - 3 0 - 7 5 )

    A MO UN T R E T A l N E C (1.7 30 F l X E D A M C t J N T )

    T O T A L P Q E V 1 3 U S P I V M E Q T

    P AY HE NT T H I S P F R 1 3 0

    T O T A L P A V P E' J T T C D A T '

    F I G U R E 5 11