the use of cpm in construction five
TRANSCRIPT
-
8/10/2019 The Use of CPM in Construction Five
1/21
CHAPTER FlVE
THE CONTROL MONITOR PHASE
Since CPM users have no crystal balls, circumstances will frequently force
changes to the plan of accomp lishment for projects. Strikes, adverse weather,
shipping delays, change orders, and numerous other conditions can disrupt
the original plan and schedule. Activities are sometimes discovered to be
necessary despite the fact tha t they are no t on the arrow diagram and no t in
the schedule and certain activities in the project are found to be
unnecessary. The schedule can go out-of-date quickly for these and other
reasons.
W he n this happens, The C ontrol M on itor P hase of CPM is effectively and
valuably used. This phase enables the project manager to quickly and
eff iciently revise and refine the in pu t information, including the arrow diagram
and the duration estimates, so th at CPM can indicate the status of the p roject
as we ll as prod uce new up-to -date schedules for the activities yet to occur.
The Control Monitor Phase consists o f collecting actual job data and
subm itting it to CPM for M onitoring purposes.
M on itoring can be done as frequently o r a s infrequen tly as the user desires
or finds necessary. It uses inform ation suppiied abou t new activities, changes
to durations, com pleted activit ies and rearrangements of the arrow diagram to
indicate what effect al1 these have on the original schedule produced. In
addition, a new schedule is produced for activities remaining to occur based
on this job data.
On most projects, Monitoring is done monthly.
INPUTS
Actua l job data, as used in the Con trol M on itor Phase, include the fo llow ing
items:
1.
ddirions ro rhe arrow diagram
New activit ies caused by change
orders or by n ew approaches t o the project.
2 Delerions from rhe arrow diagram For the same reason as 1.
3.
Changes
One might decide to change an activity's code, cost or
resource requirement for any reason.
4
criviry crual Stan Dates Used for historical record keeping.
5.
criviry crual Finish Dares
For notif ication of an activity's
completion; used for h istorica l r e l r d keeping.
6
crivity Percenr Complere
A n indicat ion of wh at port ion of the cost is
payable to the contractor because of completed work upon the act ivi ty.
(Percent com plete has nothing to d o w ith the t ime aspects of the activity; it
relates only to co st. Time progress on a started bu t n ot com pleted activity is
established b y reducing the activity's d uration to the amou nt o f t ime remaining
for accomplishment as of the monitor date.)
Actua l job data is provided CPM via forms or more frequently by
-
8/10/2019 The Use of CPM in Construction Five
2/21
marking on previously produced schedules or reports. Figure 5-1 on the
following page, illustrates a schedule marked up to show progress as of the
date indicated in the upper left corner. All the markings are self-explanatory.
The collection of job progress data by marking-up actual schedules ensures
careful and frequent reanalysis of the schedule by field personnel and
additionally produces a valuable job diary.
OUTPUTS
The Control Monitor Phase is capable of producing the following items:
Time Status Reports
Revised CPM Reports
Cost Status Reports
Requisition Backup Reports
Payment Documents
From the CPM Schedule's point of view, the objective of monitoring
progress is two-fold. One, it is desirable to determine where the project is in
relation to what was originally scheduled; and two, it is necessary to produce
revised scheduled resource analyses, etc., on the basis of what the job
situation is at the time of monitoring.
As a result of CPM progress monitoring, Cost Status Reports, Requisition
Backup Reports, Payment Documents and current, as-of-now, Cashflow
Projections are produceable as by-products.
TIME STATUS REPORTS
There are two types of Time Status Reports; one for specific (Key) activities
within a single project and one for each project in a multiproject program of
effort.
A Key Activity Status Report is illustrated in Figure
5-2
on the following
page. The activities contained in the report illustrated were identified as Key
activities by the project manager so that a synoptic status report such as this
could be produced. Note that for each Key Activity shown is:
1.
The ~'ccur rence ate The CPM EARLY START value.
2. The 'Target Date An externally supplied date by which time the activity
was to have been started.
3.
A Status Value indicating how far ahead (if positive) or behind (if
negative) of the Target Date is the schedule for the activity.
4. A Trend Value ndicating whether or not the schedule for the activity is
better than the last time the Status Report was produced (Trend Up), worse
than last time (Trend Down) or exactly the same as the last produced report
(Trend Steady).
Use of such a report provides the project manager or anyone else with
a quick evaluation of where the project is time-wise.
-
8/10/2019 The Use of CPM in Construction Five
3/21
C 2 & ?
V I W W
w
c ;
C m
Z O O
V I
9 l n Q
Z
U W
7
z
t C
O N 2
o m o
o m o
Q n z
0 0
O
4 . 4
e
4
4
o
FIGUR
5 1
6
-
8/10/2019 The Use of CPM in Construction Five
4/21
C P H A U TO M A TE D C O N TRO L S Y S TE M
L A M O l FRO H?NC.ER R E N N A T I O N P G F
K E ~CTI VITY S T A T U S R E P O R T S E W E Y C E =
TIWGET
~ O R K - W E E K
=
5 DUMMIES
NO
FINISHED NO
AS
OF
1 5 D E C 7 5 P R E D I C T E D C O M PL E T IO N
.........
C 1 J TRACE C EA D E SC R I P T I ON
1 5 6 1
'73C .
KE
t S k I T C H GEAR I N S T A L L E D
0 1 3 8 1
0 3 0 0 0
KEY
HAWGER ROOFED
0 1 5 9 0
0 3 0 0 0
K FV
H A G E R F I R CP R nO F E O
q 1 5 7 7 )3 ?
K E Y 1 S T
L Q
O F F I C E D 9 Y E
0 2 0 0 0
0 3 0 0 0
K E Y
P R 3 J E C T C O P P L E T
O C C UR A N CE T A R G E T P R E V I C U S
D A T E D A T E S T A T U S T R E N 0 O C C UR A N CE
-
8/10/2019 The Use of CPM in Construction Five
5/21
PS D F 1 5 C E C 7 5
A L L P R O J E C T S T A T L S R EP O R T
C P M 1 1 A U TO M P T ED C C h T R C L S Y S T E M
P A C E 1
S E O
=
P R C J E C T
................ F R C J E C T ..... .
I D N AM E
P R E O I C T E O S T A T U S
C O M P L E T I C h T A R G E T
1
N
D A T E D A T E C P L - OA Y S T R E N 0
P E R I O D S
1
N
T R E N )
P R E V I O L S D A TE O F
COMP L A S T
D A T E U P O A T E
A N A H B W A R E H O C S E P N A R BO S T O R AG E C C 3 D M A R 7 6 1 O C T 7 5 - 1 7 1 O W N
AW CAN A M E Rl C d N P H O l C C A l C F F I C E B L D G 2 5 P P t 7 6 2 5 S E P 7 6 1 2 2 U P
C H A S H D F F C E / S T C F A G E C l - ES A P EP K
E
A S W R E IM: l O J A N 7 0 Z 2 A U G 7 5 141 S T E A D Y
CUWIL C O L L I N S M F G ~ I L S C R B L D G
D A AB T D A V I S P B B A T O I R
ObWAR O A V I S CO '4P A N, MP RE kf OLS E
i
2 2 J U L 7 6
2 O J U L 7 6 - 2
DOWN
1 9 M A R7 7 1 5 M l R 7 7 1 4 U P
I O J U h 7 6
1 5 M4 Y 76 6 O O i h
3 1 S E P 7 7
3 1 S E P 7 7 O
S T E A O Y
C R lN K C A V I S I C E R l F K
M GF iK 6 M hi KE Y H O U S E R E G I O N A L Z C C 2 5 0 C T 7 6 3 0 C C T 7 6 - 5 S T E A O Y
U S M N W AN AG EM EN T T P A l N N G C EN TER U SA RT WT l b F E e 7 7 l S F E B 7 7
1
S T E P D Y
U SP AV F O B P A V I L I C N 1 8 D E C 7 7 I O F E e 7 8 5 3 U P
V AM AC V A H O S P I T A L A C D I T I O N C A CA L I S L A N O 1 5 F E B 7 6 2 5 F E 8 7 6 1 0 S T EA O Y
Z YT RO Z Y T R C h I N C 3 F F I C E P R CC E SS I NG C E NT ER I O J U N 7 0 2 4 J A N 7 6 - 1 3 7 D O l h
-
8/10/2019 The Use of CPM in Construction Five
6/21
AS O F l S D E C 7 5 C PM 11 A UT CC AT ED C C N T R a S I S T E M
PACE 1
TROURL ED PROX.U.-SJA.TU f- fEPUlr . . . - .
-
qF
PPn lFCT
PR E I C T E D S T A T U S P 10M PR EV IO US DATE ff
C O M P L E T I O N T A RG E T I N N COM P L A S 1
D A T E D A T E C AL -D AY S T R E N 0 T R E M DA T E U P D A U
W m A N A f l R C
S T i l f A E
I IL
3
PAR76 1 1 M T 3 5
.?m . n Y N i
OBT AIN ROOF STEEL
A YA R D A V I S C O MP AN I b A R E M U S E 1 0 J U N 7 6 1 5 M A Y 7 6 - 2 6 D W N 2 2 W A Y 7 6 3 0 N OV 7 5
E X 1 M S O N R Y VE S1 H A L L L I P T
W D E R S L AB P L BG S OU TH H U F
Z Y TR O Z Y T R ON I N C O F F I C E # P R U E SC I N G C W T E R 1 0 J U h 7 6 2 U A N 7 6 - 1 3 7 OOYN 6 2 8 M A Y 7 6 1 5 D E C T S
L A T H P L AS T E R 4 T H FLR
-
8/10/2019 The Use of CPM in Construction Five
7/21
Figure 5-3 i llustrates an All-Project S tatus Report. No te that it is similar t o
the Key Activity Status Report described earlier. The major difference is of
course that, for each project, only the termination date (Project Completion
Date) is considered. This n a multi-p roje ct environment is al1 that is
required to p rovide the user w ith an easily evaluated report on the status o f
each project in the program.
The optimum situation is one in which the All-Project Status Report is
s u ~ p o r t e d y Key Activity Reports for al1 projects.
Figure 5 4 is a special kind of mu lti-project status report.
It
is an extraction
from al1 the projects of those tha t are in-trouble. In the case of those
illustrated, in-trouble is defined as any tha t are behind schedule (S ta tus less
than zero) and getting worse (Trend
Down). It is possible to identify
trouble in any way desired.
REVISED REPORTS
Because time has elapsed whe n m onitoring takes place and because
changes w ill have been made to t he original inputs, the Control M on itor Phase
produces new, revised versions of al1 the reports described as available in the
Scheduling Phase. It mu st be kep t in mind, however, that w hen such revisions
occur the as o f date, or date set equal to time-zero, w ill change to th e date
monitor information was collected instead of remaining at the project start
date. This means that from the point of view of schedule calculation, each
schedule produced ignores wh at had been previously scheduled and considers
only what exists when calculations are done. Earlier in this chapter it was
stated that time progress on a started bu t no t com pleted activity is established
by reducing the activity's duration to the amount of t ime remaining for
accomplishment as of the monitor date. This is so that the calculation of a
revised schedule w ill be done properly fr om the new time-zero date.
Because of th e above, the CPM user co llecting actual job progress data
mu st take care to rev iew al1 activities that had been scheduled t o start du ring
the time that had elapsed since the schedule being monitored had been
produced. Long lead time activities, such as delivery activities or shop
draw ing preparation, if no t duration (.e., reduced to re flect time elapsed since
their duration estimates were last established), will be assumed to need as
much time as was previously indicated despite the fact that the previous
duration estimate was relative to an earlier time-zero date.
If it is desired to measure a revised schedule against what was originally
scheduled, a Relative report can be prod uce d.
Figure
5-5
is a page from a CPM schedule report in wh ich LATE STA RT and
LATE FlNlSH have been replaced by dates that have been calculated not in
the norm al backward-pass way (see Chapter for an extensive discussion of
the calculation of Late Dates via the backward pass method), but by
establishing as the starting point for the backward pass the original project
completion date.
If project progress has been less than what was originally scheduled or
if change data entered into CPM during the Control Monitor Phase has
lengthened the revised schedule, EARLY S TA RT and EARLY FINISH will win d
-
8/10/2019 The Use of CPM in Construction Five
8/21
CPH I PUTOCATED CONTROL SYSTEM
L A H O l F B O H L U G f R R E N U V A T l O h P AG E L
RE LATIVE FLU AT REPCPT SEQUEVCk
=
T F L
~ O R K - W E E ~ - - u ~ C ~ ( ~ ~ N C - F I N I S H E D
O
AS DF 15 CE C7 5 PR EO IC TE O COMPLETION........ .2OFEB7-6
CURRENT COhTRACT COMPLETION..15JAN76
VARIANCE I h WORKING OA-YS - 24 -
0 1 3 8 0 C L 39 1 1 L A T t O C F
MTL STUOS
1ST FLR YEST
C 1 3 9 1 C 1 4 1 4 1 L b 1 H
CFF HTL
STUOS 1ST FL P EdST
0 1 4 1 4 0 1 4 2 2
2 LATH CFF
MTL STUDS
ZYD FLR YEST
F l N l S H E AR L Y EA R LY
.
RE
L
PE L
D AT E S TA RT F I N I S k S TA RT F I N I S H R F L K
0 1 4 2 2 - 0 1 4 3 5
1 LATH CFF HTL ' LOS ZYD- FLR EAST ..
1 ,1437 21 4 41
1
FLECT CFF CT3hDUl T 1ST FLR YEST
' 2 1 4 4 1 0 1 4 4 6
1 E L E CT C FF C C K I U I T 1 ST F L R E AS T
~
1 4 4 8 ' 21 45 4 1 E LE CT C FF C O hD U IT ZND F L P WFST i 9 0 E C 7 5 3 0 ~ ~ ~ 7 5 2 1 b K I I 7 54 N O V 7 5 - 2 6
' 1 4 5 4 C 1 4 5 F 1 L E C 1 C F F C O N D U IT 2 YD F L P E A S T B O E C .7 ' 3 1 U E C 7 5 2 4 h O V 7 5 2 5 N O V 7 5 2 0
0 1 4 5 0 0 1 4 6 4 2 I Y S U L C FF I PJ SU L AT IC N I S T F L R W EST 3 1 0 E C 7 5 0 2 J A h 7 6 2 5 h O V 7 5 2 7 N O V 7 5 - 2 6
0 1 4 6 4 0 1 4 6 7 I h S U L C FF I " 1 S U L A T I O N 1 S T F LR E A S T
-- - O Z J A N 7 6 0 6 J A N 7 t 2 7 h O V 7 5 0 1 D E C 7 5 - 2 6
C 1 5 i l C 1 5 0 7 1 F LB G C FF P L C C F I K T U R E S 1 S T F L k E AS T & J A N 7 6 . 0 7 J A N 7 6 O l C E C 7 5 0 2 0 E C 7 5 - 2 6
0 1 5 1 1 0 1 5 1 5 5 T PA RT C C F T C I L E T P b R T I T l O N 5 1 S T F LR E AS T 0 7 J A N 7 6 4 J A N 7 6 0 2 D E C 7 5 0 90 E C- r5
_y=
0 1 5 2 0
C 1 5 2 2 5 l P A R T C F F
T O I L E T
PARTI T IONS 2NC
FLG h E S T 1 4 J A Y 7 t
2 1 J A N 7 6 0 9 C E C 7 5 1 6 0 E C 7 5 - 2 6
0 1 5 2 5
0 1 5 3 5
5 l P d R T C F F
T 3 1 L E T P A R T I T l O h S 2 h C
FLR EbST
2 1 JA h 7 6 2 B J A N 7 6 1 6 D E C 7 5 2 3 C E C 7 5 - 2 6
'
0 1 5 3 5 0 1 5 6 5 2 I A C C ' C FF T O I LE T A C CE S SO IE S 2 PD F L P E PS T 2 A J A N 76 3 0 J a N 7 t 230Ec< 2 5 0 E C 7 5 - 2 6
i
0 1 5 6 9 0 1 5 7 2 1 G
-
8/10/2019 The Use of CPM in Construction Five
9/21
up later in time than their Relative counterparts. It is for this reason tha t a
Relative Report does not refer to LAT E STA RT or L ATE F INISH.
Note in Figure 5-5 that the float field is headed RFL which stands for
RELATIVE FLOAT. RFL is calculated by subtracting EARLY START from
RELATIVE START, and when the revised project schedule has been
lengthened in any way, it wil l be a negative number. For this reason, some
CPM users when referring to float calculated in this manner will erroneously
cal1 it Negative Float. This practice should be avo ided since if the revised
project schedule is less in time than the original, the RFL value will be positive.
It doesn't mak e mu ch cense to cal1 it negative w hen it can be either.
The C ontro l Monito r Phase can, of course, prod uce revised versions of th e
Resource Reports and the Cash Flow Analyses described in the chap ter on the
Scheduling Phase. The,only difference in these revised versions is that they
project resource and cash posit ions for the wo rk remaining as of the m onito r
date.
COST STATUS REPORTS
The CPM user natural ly wants t o kn ow th e t ime status of his project, bu t in
addit ion, he wants to know its Cost Status. The Control Monitor Phase
produces a report tha t indicates just h o w the project looks from a cost
standpoint.'
This report whic h is called the Cost S tatus Report is prepared in the
following fashion:
As described in Chapter 4 the contractor must first prepare cost estimates
for each of the activities in the project. Then, for activities that have been
completed, as shown in the MONITOR Report, appropriate costs can be
calculated. This gives the contractor an ES TIMA TE D COS T TO DATE. This
estimated cost is then a yardstick against whic h the contractor can com pare
the ACT UAL COST TO DA TE for that
articular
phase of work. The actual
costs are relatively easily collected. Anyone who keeps books can determine
his actual costs. CPM, however, gives him at any tim e during the progress of
the project an estimate of the cost for the w ork reported as complete so th at
effective comparisons can be made. W ith this report the co ntractor does no t
have to wa it unti l the end of the project to discover the status of his costs.
Cost Status Reporring is described ar great length in Chapter of this book.
This secrion will discuss it as a function of The Control Monitor Phase.
6
-
8/10/2019 The Use of CPM in Construction Five
10/21
The process of Cost Status Report creation can best be explained with a
sample project. Consider that th e arrow d iagram b elow represents a project for
which periodic Cost Status Reports were desired.
The f irst step necessary to be taken would be the definit ion of the costs
involved per activity. Assume that th e table in F igure
5-6
describes the costs
estimated for the com pletion of each ac tivity. This c ould be prepared any t ime
prior to the pro duc tion of a Cost Status Report, and it cou ld have been revised
at any time.
The entries in this table merely indicate h o w m uch money sho uld have been
spent for various categories (type s) of expense wh en each activity had been
f inished. For example, wh en ~ c t i v i t y is f in ished, the contractor wil l owe
somebody 488.10 for bulldozer expenses, 135.00 for general labor, and
100.00 for engineering expenses. W he n B is finished, 1,085.30 w ill be ow ed
for con crete, 309.10 for concre te labor and 80.00 for general labor. The cos ts
for
al1 activities in the project are similarly described.
The second inp ut is info rm ation a.bout w hic h activities have been finished.
Notice in Figure 5-1 that the Marked-up Schedule indicates clearly what
activities are completed. This is, thus, a good source of this second input.
Suppose that at the time a Cost Status Report was desired for the project
described above, activities A, B, C, D, C and I had been finished. W it h this
information, the ESTIMATED COST
TO
DATE for the various categories
types) of expense can be calculated.
-
8/10/2019 The Use of CPM in Construction Five
11/21
I Activity Category Expense
1
2
A 48 Bulldozer 488.10
46
Gen. Labor 135.00
73
-
Engineering 100.00
2 3 15 Concrete 1,085.30.
16 Concrete Labor 309.10
46 General Labor 80.00
2 5 C 51 Excavation 1,955.10
73 Engineering 190.30
3 4 D 10 Architect 100.00
4 8
F
(No Expense)
4 9 G 22 Carpenter 478.35
18 Lurnber 1,009.90
46 General Labor 195.00
5 - 6 E 38 Masonry Contract 1,800.00
6 - P 10 - Architect 75.00
73 - Engineering 50.00
6 - 7 38 Masonry Contract 1,800.00
46 General Labor 205.60
7
10
J
(No Expense)
8 12 H 15 Concrete 975.00
16 Concrete Labor 255.00
46 General Labor 185.00
9 11 K 46 General Labor 90.00
10- 13 N 22 Carpenter 195.00
18 Lurnber 555.30
11 10 M 15 Concrete 1,907.00
16 Concrete Labor 655.00
11
12 L 46 General Labor 195.00
12- 13 O (No Expense)
FIGURE 5 6
6
-
8/10/2019 The Use of CPM in Construction Five
12/21
If Ac tivity A is finished, the projec t shou ld have cost $488.10 for catetory 48
Bulldozer, $135.00 for General Labor, category 46, and $100.00 for
Engineering. If Activity B also is complete, the costs indicated for it will be
added to those incurred for A. This wil l add costs in two categories
Concrete and Concrete Labor and increase the cost of one already
calculated. General Labor will go from the existing $135.00 to $215.00 because
of Activ i ty
A
($135.00 for A and $80 for B). The com pletion o f Ac tivity C will
create a cost value for category 51
Excavation, and increase the cost for
Engineering by $190.35. All othe r finished activities w ill con tribute an
amount of expense to the project.
When al1 activities reported as finished have been noted, the amount of
money
that should have been spent
based on work reported as comp lete has
been calculated. In the case of th e projec t described above, the EST IMATE D
COST TO DAT E (Table A ) wo uld have been calculated for each category and
for the project in total.
T BLE
ategory
10 ARCHITECT
15 CONCRETE
16 CONCRETE LABOR
38 MSNRY CONTRACT
46 GENERAL LABOR
48 BULLDOZER
51 EXCAVATION
73 ENGlNEERlNG
TOTAL
OR
THE PROJECT
E s t i m a te d o s t t o D a t e
A second kind of information can be calculated if the contractor has
estimated his per activity expenses. He can use the table in wh ich
al
costs are
indicated to determine wh at was the total budge t (estimate) for each category
of expense. Concrete, for example, contributes to the cost of activity B
($1,085.30), H ($975.00) and M ($1,907.00). The total budget for concrete in
the p roject described above is $3,967.30. This means that w he n the projec t has
been completed, the contractor will expect to have spent $3,967.30 for
concrete. The to tal estimate for each category of expense can be fou nd in the
same way, and if it were done for the project above, The Cost Status Report
would begin to grow as shown in Table B.
-
8/10/2019 The Use of CPM in Construction Five
13/21
T BLE B
Category
10 ARCHITECT
15 CONCRETE
16 CONCRETE
L BOR
38 MSNRY CONTRACT
46 GENERAL LABOR
48 BULLDOZER
51 EXCAVATION
73
ENGlNEERlNG
Estimated Total Cost Estimated Cost to Date
TOTAL FOR THE
PROJECT
$8,248.50
W ith this inform ation it is possible to determine wha t percentage of the total
money to be spent has been spent based on the activities reported as
complete. The contractor can see that he has completed activities involving
27% ($1,085.30/$3,967.30) of wha t he wil l s ~ e n d or concrete, 25%
$309.10/$1,219.10) of his concrete labor budget, 100% of the masonry
contract money and so on through each type of expense. The Cost Status
Report, including this item of information, would appear as in Table C.
T BLE
C
Category
Per C ent
Est To tal Est Cost
Spent Cost
l o D ate
10 ARCHITECT
15
CONCRETE
16 CONCRETE LABOR
38 MSNRY CONTRACT
46 GENERAL
L BOR
48
BULLDOZER
51 EXCAVATION
73 ENGlNEERlNG
This informa tion is valuable in and by itself because it indicates h ow m uch
activity has been accomplished cost-wise. However, if the co ntrac tor supplies
inform ation abou t h ow m uch was actually spent for concrete, for general labor
and for al1 other items of expense, he can find ou t whether or no t he is on
schedule in terms of cost.
As a project proceeds, the contractor collects bills, invoices and so forth as
part of his normal bookkeeping procedures. These at any particular point in
time are ACTUAL COSTS TO DATE. If these actual costs are known, two
additional items of info rma tion can be calculated and placed in the Cost Status
Report. The DO LLAR DIFFERENCE is the result when the EST IMATED COST
TO D ATE for a category is subtracted fro m that category's AC TU AL COST
TO DATE. The DEVlATlON for a category is the ratio of actual costs to
-
8/10/2019 The Use of CPM in Construction Five
14/21
estimated costs (AC TU AL COST TO DATE ESTIMATED COST TO DATE).
The DEVlATlON for a category indicates what percentage of the estimated
cost is actually incurred; the DOLLAR DIFFERENCE is the amount and
direqt ion b y whic h the ESTIMATED COST TO DAT E was missed.
er
Cent Est To ta l
C ategO v S pent ~ o s t
10
Architect
57
$
175.00
15
Gancrete
27 3,967.30
16
Concrete
Labor
5 1,219.10
38
Masonry
Contract
100 3,600.00
46
Gen Labor 39
1,085.60
48
Bulldozer
100 488.10
51
Excavation
100 1,955.10
73
Engineering
85 340.30
Es t C os t h t u a l C o s t
l o D a t e l o D a t e
Dev ia t ion
In the pro ject tha t has been used as a sample for the Cost Sta tus Repo rt, the
ACTUAL COST TO DATE entr ies must be assumed. Assuming the actual
costs indicated, the completed Cost Status Report based upon activities
reported as finished and on actual costs collected would look like Table D.
This report tells the contractor what is the cost status for al1 categories of
expense defined by him. The f inal Cost Status Report contains the inform ation
described above as well as summary type data for the entire project. The
completed Cost Status Report for the project described above is shown in
Figure
5-7
on the fol lowing page.
The Cost Status Report,
because i t indicates how much money is being
spent in relation to what was expected is a very valuable report. The project
manager can tell from this report which areas of expense need investigation,
wh ich e stimates perhaps need revision, an d h o w he is doing in general as far
as his costs are concerned.
There are variations o n the repo rt sh ow n here as a sample. One can include,
as part of the Cost Status Report, inform ation abou t the cost of change orders
or other revisions or separate the labor costs from the material costs just t o
ment ion only tw o.
One question that always arises about the procedure described above
concerns itself with activit ies that have started but have not yet been
completed. A t the tim e the Cost S tatus Report is desired, activities in this sort
of circumstances are assumed to be on schedule, and their costs are
pro-rated accordin g to h o w ma ny days they have been in progress relative
to their schedule dura tion. To illustrate: if Ac tivit y E were a six-day a ctivity tha t
had
been reported as STAR TED three days before the effective date of the
Cost Status Report, the Cost Status Report would have included only half
316)
of the costs involve d for th at activity.
-
8/10/2019 The Use of CPM in Construction Five
15/21
COST STATUS REPORT
Total Estimated 15.069.05
Revised Estimate 14.975.15
Cost To Complete 6.810.55
Categoiy Budget
Number Name Amount
Architect
Concrete
Concrete
Labor
Masonry
Contract
Gen Labor
Bulldozer
Excavation
Engineering
Pement
Complete
Est Cost
To Date
Est Cost To Date 8.248.50
Act Cost To Date 8.164.60
Dollar Difference 83.90
Act Cost Dd la r
To Date Difer Deviation
400.60 20.00 Over .95
527.35 39.25 .O8
1955.00 O
.99
260.00
30.30 Over .89
FIGUR 5 7
-
8/10/2019 The Use of CPM in Construction Five
16/21
REOUlSlTlON BACKUP REPORTS
Since part of the Control Monitor input data is information about what has
been completed Activi ty Percent Complete) and since one of the initial inputs
is a cost value per activity, al1 the elements are available to produce reports
that support contractor requisitioning.
Figure 5-8 presents one page of such a report. It contains al1 the activities for
the sprinkler subcontractor whose code is sprnk. The cost value per activity
was assigned by the contractor and agreed to by the owner. The PERCENT
COMPLETE figure represents the portion of al1 the work to be done on the
activity that the contractor and the owner agree should be paid for. The report
calculates for each activity how much should be paid to the contractor,
therefore. The report also sums the amount earned for al1 activities to produce
a total for the subcontractor.
All subcontractors have their own groupings of activities, and each is
treated in the manner described above. When al1 trades have been presented,
a summary report representing the totals for each is presented. Figure 5-9 is
such a summary.
An interesting feature of The Requisition Backup Report is illustrated in
Figure 5-8. Notice that one of the activity descriptions refers to
Material-On-Site and, in fact, that the cost is offset to the right of the costs
presented for other activities in a column also noted as Material-On-Site.
This feature facilitates payment for materials delivered to the site, the cost of
which is included in the cost value assigned to perhaps several activities for
which no work has yet been accomplished. To indicate that such activities
were partially complete in order to get the Requisition Backup Report to
generate an amount earned value equal to that which the contractor is due for
the material on site) distorts the project progress position of the activity and in
many cases is not allowed by the owner. The report must therefore have some
way to generate payment for materials and the Material-On-Site MOS: type
of activity is the way.
When such an approach is used, a special artificial activity coded to
represent only material and to be ignored by the CPM Schedule Reports) is
added to the CPM data set. The special coding generates the result illustrated
in Figure 5-8. In addition see fol lowing paragraphs) CPM-based Payment
Documents will accumulate Material-On-Site amounts for entry on the final
payment authorizations.
Use of MOS activities must be carefully disciplined. It must be borne in mind
that a cost has been entered into the system twice once in the cost assigned
to the artificial MOS activity and again in the cost assigned to the activities in
which the material will be used). For this reason the user must adjust the MOS
value to reflect subsequent payment via completion of work activities.
Requisition Backup Reports can be used by the contractor to justify what he
seeks in payment from the owner, and it can be used to establish what the
contractor should pay his subcontractors.
The cost values assigned each activity for requisition to the owner can be
factored by CPM by any percentage to produce higher or lower values. If in the
case of the subcontrac?or illustrated in Figure 5-8 the agreement between the
-
8/10/2019 The Use of CPM in Construction Five
17/21
0 1 3 7 4
0 1 4 1
7
S P F UK S P f i Ih K L ' QS w i T k i H f q
0 1 4 0 8 Cl5l ;
S P F ' J K
Y c Q
I ' J S T A L L F AP T.L .dK5
1 4 1
1 5 1 ' S P r V K " 6 I :i CT /T FS T
FY- lP P .CTZL f 5
U 1 4 1 7 U 1 4 3 1
S P F Y K S F 2 I N K L C Q S F O V d3l 1 %
0 1 4 1 7
0 2 4 9 9 S f 0 h C
b r
5 P F l h K L C g S C CA V cGl - 1N
1 4 3 1 L l i t 9 S P E U C T E S T S CK T 4 KL E ;S
P?
E V
T H l S
O U C GE T P C T P C T
C C U S T
E A H L E D
P A G E 2 7
T H I d P PL I C A T I J a F A R N E U
-
8/10/2019 The Use of CPM in Construction Five
18/21
z
-
e
O
i i L
-
A
V
d
d L A L -
" 3- ,
4 -0-
x
2 2 -
~ K d L ~ r L d u V 8 P l d i d d l
< Y > d , a , ~
. n f i o t - ~ - > ~ < ~ .n d h J s a
c U J C < 3 ~ 2 a , ~ - i . . ~ a 1 , d rc ; 9 - ~ - i ; - a c . < a
. x V d O U A 3 1 - 2 7 x ' x l i l a U . 1 m r l > . ~ . . ' I + , -
FIGUR 5 9
-
8/10/2019 The Use of CPM in Construction Five
19/21
contractor and the sub was for 117,471.20 when al1 his work was completed.
the ratio of that amount to what had been agreed to between the contractor
and the owner ( 133,490.00) is 88 . This ratio would be the factor applicable
to the amounts earned for that sub, and the result of such factoring would
justify and support payment to the sub. Figure 5-10 is the backup for payment
to the subcontractor represented t5y the page illustrated.
P A Y M E N ~
OCUMENTS
Many owners use CPM as the initial input to an automated contractor
payment operation. One such organization is the Veterans Administration
whose payment document is illustrated in Figure 5-11. Use of such an
approach has significantly reduced the amount of time necessary for
processing of payments, the result of which is faster payment to the
contractor.
Note in the Payment Document illustrated in Figure 5-11 that a separate
entry is made to accommodate Material-On-Site values. These values are
those that were discussed earlier in this chapter.
-
8/10/2019 The Use of CPM in Construction Five
20/21
C P M II A UT OMA T E O
CONTROL
s Y s T E n
~ n ~ O lF BD W NG E R R E N [ N * I O N
.
.-
.
. . PAG E
COST EARNEO REPORT BY TRAOE
A S O F 1 5 0 E C 7 5
TRAOE
=
SPRNK
P R E V T H I S
l lOLHT W TE R I A L
BUDGET
-
PCT PCT
c r ~R~DE .
EEDES R 1
O
ON _ -
.
_
_
.
_
-
. E ~ N E D M S I T E
0 1 3 7 4 0 1 4 1 7
S P R N U
SPRINKLERS
un R G H IN
0 1 4 0 8 0 1 5 1 9 S PR NK M R INSTALL FOAM TANKS
0 1 4 1 0 0 1 5 1 9
S PR NK MER I N S T / T E S T F O M N O Z Z L E S
0 1 4 1 7 O 1 4 3 1 S PR NK S P R I N K LE R S
F C M
RGH I N
0 1 4 1 7 - 0 2 4 9 9
S P R N K M O S S P R I N K L E R S F C A M Rt I N
6 1 4 3 1 0 1 4 4 9 S PR NK T ES T SPR I N K L E R S
ci
I
*
*
TOTAL H R TRAOE
m
Y
117,471.20
AMOUNT EARNED 10 DATE .
P R EV IO U S A M W W E A R M D
T H I S A PP L I C A T O N E AR NE D 9 36 8 0 0
-
8/10/2019 The Use of CPM in Construction Five
21/21
C.@. CWAhGF
R C
P P EV R F P T D
S Y U .
A 1 .3
C.O. P R O C F F D 0 9 C P P F V ? E P T O N O. O T C
FIELD
C H AN GE
ne
P R E V
Q P T Q S Y M .
1 1
F I E L 0 P RO CE F9 O C F REV Q E PT 9 SVM. A 7
T I M E E X T E N S I O N S F RE V R F P T f l NO. 1 T O
I S S U E D T H I S P F R 1 0 0 s C O 2 3 CAC
Prl
H
I S S U t U T H 1 S D E R I ' 7 0 F Pn -H 1 C A N C)
I S S U E D T U 1
5
P E Q I C I C F C O - 3 4
I S S U E O T H I S PEQ1 P F C O - 3 5
I S S U E U T H l Z PF Q l C O F C q - 3 6 C A C FPC
l S S U E 0 T H I S P E R I C O P F r l - B I C A P I C )
I S S U E O T W I S P F P I C D C C ? -q 7 1 F P T - K )
I S S U t U T H I S D E Q I C C F C O - 3 8
I S S U E D T U 1 S P E R l C r F P q -K I C A N C
I S SU EO T H l S P E R I C P F C C - 1 9
I S S U E ~
T n r s O E ~ I C O r v
C R l G l N A L C O Y T R d C 7 Au OU hT
Y E T C H A N G E
C U R R E N T C O b ' 9 A C T A M G U N T
V A L U E
OF
W qP K I N P L A C F T O 1 2 - "1 - 7 5
V A L U E F W C Q K I F ( S T b L L E C
-
C U R QF V T P E R I O O
V A L U E O F M OQ K I N P L A C E TC 1 2 - 3 7 - 7 5
V A L U E F M A T E R 1 4 L O h S I T E
V A L U E O F hOo N O 1 C O UP L ET E O
E A RY EO T C C AT E ( 1 2 - 3 0 - 7 5 )
A MO UN T R E T A l N E C (1.7 30 F l X E D A M C t J N T )
T O T A L P Q E V 1 3 U S P I V M E Q T
P AY HE NT T H I S P F R 1 3 0
T O T A L P A V P E' J T T C D A T '
F I G U R E 5 11