the unresolved struggles between project managers and functional managers in matrix organizations
TRANSCRIPT
1
The unresolved struggles between Project Managers and Functional Managers in Matrix
Organizations
Abstract
Having personal that works in projects but belongs to a functional organization is the way that
many companies organized their labor force today. Previous research shows that this implies
management contradictions and ambiguities between functional manager and project manager;
there are unresolved struggles between these two roles in terms of power, accountability,
authority and legitimacy.
With this paper we aim to analyze those struggles based on previous research and to generate
working propositions.
We first provide a review of the different matrix organizations focusing on the relation between
the functional manager and the project manager. We then review the literature concerning
temporary organizations and projects as temporary organizations. We conclude by integrating the
findings of these perspectives and by identifying working propositions and areas for further
research.
Key words: Temporary organization, Matrix organizations, Functional Manager, Project
Manager
Introduction
2
Is a project a part of a company‟s day-to-day business or an extraordinary task? Is it therefore
part of the „company being a going concern‟ or is it a standalone building block of the business,
which requires dedicated management structures and control mechanisms?
The answers to these questions differ whether seen from the perspective of the functional
manager or the project manager, especially in the context of matrix organizations.
These differences in perspective lead to different understandings of objectives and priorities,
which can cause struggles between functional and project managers when it comes to assigning
resources to projects and resource availability (Engwall 2001, 2003; Turner and Müller, 2003).
According to Forman and Selly (2001), the achievements of the organization‟s objectives are
dependent on the effectiveness of the resource utilizations. This statement makes the above
struggles a key concern (source of poor performance) for any organization and raises the
following questions:
What are the main reasons for the struggles?
What are the main factors constituting these struggles?
What are the consequences of these struggles?
This paper addresses these questions from a theoretical perspective through a critical review of
the literature and suggests a conceptual model that helps to identify the categories of the
struggles between project managers and functional managers, and their main characteristics.
3
On the basis of in-depth investigation of the literature, four main categories of struggles were
identified; authority, accountability, legitimacy and power. These four categories of struggles
can be defined in different ways and have different strength depending of the theoretical domain
that they are applied in. In this paper we use the following definitions which apply to the
theoretical domains of organization, management and leadership:
1. Authority is the right to give commands, enforce obedience, take actions or make final
decisions (Popper, 1960).
2. Accountability in leadership roles is the acknowledgment and assumption of
responsibility for actions, products, decisions, and policies including the administration,
governance and implementation within the scope of the role or employment position and
encompassing the obligation to report, explain and be answerable for resulting
consequences (TutorVista.com, 2010).
3. Legitimacy is a perception or assumption that the actions of an entity are desirable,
proper, or appropriate within some socially constructed system of norms, values, belief,
and definitions (Suchman, 1995).
4. Power is defined as the right or means to command or control others. In organizations
there are two major kinds of power:
1. “Position power is the power a person derives from a particular office or rank in a
formal organizational system.
2. Personal power is the influence capacity a leader derives from being seen by
followers as likable and knowledgeable” (Northouse, 2009, p7).
4
The literature on matrix organizations and temporary organizations that we reviewed used these
terms without definitions and let the reader make his own interpretations of these terms.
Confusions occur when citing definitions, especially between authority and power since the
classical definitions of these terms are based on each other (Grimes, 1978).
The distinction that we choose to use is based on Grimes (1978) work that states that authority
and power are both a type of control and influence. The difference lies on that authority of the
role is based on voluntary consensus while the power of the role is base on compliance.
Struggles at work!
The above categories of struggles have different manifestations in different matrix organizations.
The most often cited evidences of those struggles are those regarding resource allocation to
projects and implied priority of projects. Examples include conflicts in which project managers
aim to establish changes, which are resisted by functional managers; or conflicts concerning
resource utilization when both managers try to optimize their individual objectives at the expense
of the other part (Knight, 1976; Müller, 2009; Turner and Müller, 2003; Brown, 2008).
Authority
Continuous resource demands by project managers may be perceived by functional managers as
a threat to their authority and a loss of accountability (Brown and Botha, 2005). This focus is
taken further by Engwall (2001) who emphasizes that functional managers are stuck in between
different project managers asking for resources and with no clear authority over those resources.
Taking the perspective of the project members we see that their reasons for compliance with
functional managers and project managers are different, caused by the perception that project
5
managers authority is less than the functional managers‟ authorities (Dunne, Stahl and Melhart,
1978).
Accountability
Accountability is an issue, for instance, when project managers aim to establish changes, which
are resisted by functional managers (Turner 1999; Turner and Müller, 2003; Brown 2008).
Dunne, Stahl and Melhart (1978) found empirical evidence that project managers have the
responsibility to meet project deliverables, but are not always have the authority to make the
required decisions. This creates conflicts.
Legitimacy
Another struggle often cited in publications is that of legitimacy. Temporary organizations
especially struggle with legitimacy for their management (Martinsuo and Lehtonen, 2007).
Engwall (2003, p791) describes the Project Manager “as a non-legitimate change agent in a
conservative, or sometimes even hostile organizational environment”. By broadening this
perspective, Lundin and Söderholm (1995) identified legitimacy as a key element in the relation
between the temporary organization and its environment, which may cause conflicts between
competing teams or organizational structures. Legitimacy of roles might also be affected in
matrix organizations by people being more loyal to their functional managers than their project
managers since the functional managers conduct their annual appraisal. This decreases the
legitimacy of the project manager (Turner 1999).
Power
6
The fourth struggle that we found is about power. In this paper we refer to Positional power
meaning the power that the project manager and the functional manager have from the position
their role gives them. Larson and Gobeli (1987) found in their studies evidence of power
struggles between project managers and functional managers. The underlying causes for the
struggles are competition for the control of the same resources and different personal objectives.
Power in leadership and management is based on the classic view of management being
planning, organizing, leading, coordinating and controlling (Fayol, 1949). In matrix
organizations most of these activities are performed by the project manager, some by the
functional manager and others are shared between the two. This creates a power struggle
generated by the ambiguity and overlapping of roles. This was treated by Ford and Randolph
(1992) in their literature review about integration of matrix and project management. They
highlighted conflicts about scheduling, personnel resources, administrative procedures and
priorities.
The impact of the control structure
Having dual lines of authority and split responsibilities generates ambiguity in many areas such
as resources, compensations, loyalty and recognition. This ambiguity generates the struggles
(Larson and Gobeli, 1987; Turner, 1999; Ford and Randolph, 1992; Knight, 1976; Engwall,
2001; Pinto and Rouhiainen, 2001). Turner (1999) traces these struggles back to organization
structures stating that the struggles are embedded on the structure since matrix structures are
combinations of functional hierarchical organization, where the head of a function is responsible
for both staff members and deliveries, as well as autonomous project organizations in which the
7
project manager is responsible for the staff and the deliveries. Taken the organization structure
perspective rises the following question:
Are there any difference in the way of controlling projects and functional departments?
Ouchi's (1979) work looked at correlation between different organizational structures and the
mechanism of control. He identified two major control mechanisms: Output control and
Behavior control.
Output control is based on controlling the performance and deliveries and is related to
organizations, which aim for legitimate objective control and where supervisors cannot
supervise their employees directly, for example in functional departments where the
resources are assigned to projects. Or project managers in mega projects not having the
possibility of supervising the behavior of all the members of the projects.
Behavior control on the contrary is based on a holistic approach that focuses on the way
that tasks are performed and is only appropriate to the supervisor for a working resource,
when the supervisor has a good understanding of the means-end relationship of the
behavior. An example of this is a project manager who understands the tasks and the
behavior needed to accomplish the task. These differences in control mechanism might
affect project managers and functional managers in different ways and contribute to the
struggles between the roles.
The above indicates the need for a deeper understanding of the factors and combinations of
factors that constitute the struggles between functional manager and project manager. This leads
us to address the following research questions:
8
1. What is the nature and strengths of the factors constituting the struggles
between functional managers and project managers in matrix
organizations?
2. How do project control mechanisms affect those four categories of
struggles?
3. Is there any correlation between the struggles?
Hence, the aim of the present paper is to suggest a framework to identify and assess the nature
and strength of factors in matrix organizations that make up the struggles described above.
Our unit of analysis is the type of struggles that functional manager and project manager have.
The results of this paper will contribute to a better understanding of the nature of these struggles
in matrix organizations. It will provide a framework of factors that make up the strength of
struggle, and identify further areas for research concerning this subject.
The paper continues with a review of the relevant matrix organization structures. Then it reviews
literature of projects as temporary organizations and subsequently outlines the differences
between functional organizations and project organizations when it comes to control needs. The
paper concludes by integrating the findings of these two perspectives into a framework and
defining propositions for further research.
Literature review
Matrix organizations
9
Matrix structure is one of the three classical organizational forms: Functional Organizations,
Matrix Organizations and Pure Project Organizations. In functional organizations the staff
belongs to a line function and performs all their work within that function, with no or very
limited interaction with other functions. The resources are grouped in functional areas such as
finance, marketing, design, engineering, production or in skill areas such as chemistry,
electronics, aerodynamics etc. The opposite of this organizational type is the Pure Project
Organization where all the work is performed in temporary structures or projects that are
separate from the parent organization and where the staff does not always belongs to a function.
The project manager has full authority over the project and resources. Strengths of this
organization type are that project members have one manager and are fully dedicated to the
project. In between these two organization types is the Matrix Organization which is a
combination of hierarchical structures and lateral communications, work co-operations and
authorities. In the matrix functions are the columns and projects are the rows (Turner, 1999;
Morgan, 1997).
The main reason for adopting the matrix as an organizational structure is the need for handling
high task complexity. The matrix deals with the kinds of communication and decision needs that
arise in complex interdisciplinary projects (Knight, 1976). “The term matrix organization was
coined to capture a visual impression of organizations that systematically attempt to combine the
kind of functional or departmental structure of organization found in a bureaucracy with a project
team structure” (Morgan 1997, p52). Galbraith (1971) and Curran (2002) describe the position of
the functions and projects in the matrix. They state that the matrix model creates a horizontal
interaction between the vertical functions which connects people across different functions.
10
Strengths of the matrix organizations are flexible resource utilization and better focus on tasks.
Among weaknesses we find unclear responsibilities and authorities. This implies conflicts and
ambiguity for all parties involved; for project managers and functional managers because they
share /divide power for project members and stakeholders (Morgan, 1997; Larson and Gobeli,
1987; Andersen, 2000; Galbraith, 1971; Knight, 1976).
The pros and cons of matrix organization are presented in Table 1.
-----------------------
Insert Table 1 here
-----------------------
Types of matrix organizations
The classical categorization of matrix organizations is based on the relation between project and
function. There are mainly three different forms: Functional Matrix, Project Matrix and
Balanced Matrix, (Larson and Gobeli, 1987; Morgan, 1997).
Functional Matrix
Functional Matrix is also called Coordinating Matrix or Functional Project Organization and
applies to organizations where the functional manager is responsible for assigning tasks and the
project coordinator coordinates tasks between functions. The project in some cases may not have
a project manager and the work is performed through the different organizational functions. This
type of organization focuses on an optimal use of resources. Common problems are poor quality
and poor communication (Turner, 1999; Pinto and Rouhiainen, 2001).
11
Another structure of the functional matrixes is the Lightweight Project Organization, where there
is a project manager with an overall responsibility for the project, but with limited power and
authority. The functional manager controls the resources and is the one who is in command. In
this kind of organizations we find a power conflict between the project manager and the
functional manager. The nature of this conflict is based on the roles and the different goals since
the project manager is more of a coordinator with no authority to make decisions. The project
manager is responsible for the outcome while the functional manager makes the decisions,
focuses on an optimal use of resources but not on the outcome (Pinto and Rouhiainen, 2001).
Analyzing the above definitions we see that in the functional matrix the weight is on the
functional side and as a consequence the functional manager has higher authority, power and
legitimacy than the project manager. The project manager is mostly accountable for the progress
of the project and for the deliveries.
Project Matrix
On the other extreme we have the Project Matrix, which has its focus and weight on the project
dimension. These types of matrix organizations are also called Pure Project Matrix, Secondment
Matrix or Autonomous Team Organization. Contrary to the functional matrix, project managers
are here the ones making decisions about the realization and decide on the involved staff, while
the functional managers are supporting them in the background. This support is mostly
performed by providing projects with personnel upon request. The project manager has
responsibility for resources, assigns and distributes work, and has the authority, status and
responsibility for project success. These organizations focus on problem solving, which (among
12
others) allows for customer-orientation, but they tend to overlook efficiency and costs and may
become too expensive. This potentially generates a goal conflict between functional manager and
project manager since the functional manager is typically responsible for the efficiency of the
organization (and sometimes even for the costs) while the project manager typically concentrates
on the deliveries through which he or she might fails take into account the wider organizational
picture (Larsson and Gobeli, 1987; Turner, 1999; Pinto and Rouhiainen, 2001).
In the extreme case of project matrix organization, a Full Authority Project Organization, the
project manager has full authority and project members are 100 percent allocated to the project.
The organization is outside the parent organization and considered a true temporary organization
(Andersen, 2000). In their empirical study, Morrison, Brown and Smit (2006) found out that in
this type of organizations the projects are large or semi-permanent and this gives the project
manager legitimacy in the organization. This legitimacy means that the project managers‟ inputs
and requests are being considered and can influence the parent organization and that their role is
recognized as a key role. Functional managers on the other side, see their roles limited by little
authority and are considered by the organization a supportive role.
An analysis of these definitions shows that in project matrix organizations the weight is on the
project side and the project manager has authority, power and legitimacy. On the other hand the
functional manager might face struggles in these areas due to the limited involvement and
possibilities to decide on the projects. The findings of Larson and Gobeli‟s (1987) study show
that the struggles between the roles are differently moderated in this type of matrix organization.
13
Balanced Matrix
In a Balanced Matrix the power is divided between the project manager and functional manager.
Project managers decide and plan what has to be done and functional managers are responsible
for how the work will be done. These organizations are a mix of functional hierarchies and pure
project-oriented structures. This positions the balanced matrix organizations in-between the
functional matrix and the project matrix. In these organizations the project managers and
functional managers share responsibilities, the project manager is responsible for time and cost
and functional manager for scope and quality (Larsson and Gobeli, 1987; Turner,1999; Pinto and
Rouhiainen, 2001).
Balanced Matrix Organizations are generally implemented in order to share resources between
functional work and project work and to create better balance between function and projects.
However, this may be difficult because dual authorities result in authority problems between
Project Manager and Functional Manager (Morrison, Brown and Smit, 2006; 2008). As a result
of unclear authorities, project managers might have less legitimacy and less authority than the
functional managers to influence the parent organization. The reason for this phenomenon could
be that the project managers tend to be isolated from the traditional function area of expertise. By
not being involved they face difficulties in gaining credibility and possibilities to be heard at
senior levels in the organization (Ford and Randolph, 1992).
Heavyweight Project Organizations are often organized around products or services which
require focus on customer needs and expectations (Pinto and Rouhiainen, 2001). In this type of
organizations the project managers share responsibilities and authorities with the functional
14
manager, the areas of accountability are specific for each of the roles but sometimes overlap each
other, thus generating power conflicts.
Andersen (2000) called this type of organization Split Authority Project Organization. His
emphasis is on the splitting of authority and work, since project members are recruited from
different functions and they need to perform both project work and functional work. Project
managers share authority with functional managers.
Research has shown that power struggles occur especially in the Balanced Matrix Organization
because its nature does not clearly define power and authority by role (Larson and Gobeli, 1987).
Project managers are considered responsible for deliveries but do not have the authority to
acquire resources (Brown, 2008).
Accountability issues may arise as well in balanced matrix organizations through the ambiguity
of situations in which the functional managers have the responsibility for assigning personnel to
a project and are responsible for the result of their functional area, while project managers set the
schedule and manage the project (Larsson and Gobeli, 1987). According to the conceptual study
of Goold and Campbell (2002), matrix organizations might collapse because of this lack of
clarity about responsibilities and accountabilities between the project managers and the
functional managers.
Summary of Matrix organizations review
15
The literature review showed a lack of common definitions and classifications of matrix and
project organizations. The differences are not only the names but also the definitions and
responsibilities of the project manager and functional manager. For example, for Larson and
Gobeli (1987) the project manager in a balanced matrix is responsible for the scope, while for
Turner (1999) the scope in a balanced matrix is the responsibility of the functional manager. This
example illustrates the need for harmonization, unification, or at least a context dependency of
definitions. It also shows that the term “balanced matrix” cannot be used without further
definition, because it has different meaning for different writers.
This paper adopts the definition of Knight (1976), where a Balanced Matrix Organization is seen
as an organization with a vertical functional structure and a horizontal project structure. In this
organization the functional managers are responsible for the line organization; they have
responsibility for resources, competence development, promotion, employee evaluation, and
recruiting new staff. They are also responsible for providing projects with staff when requested
and balancing these requests with available resources. When a project is finalized the functional
manager is responsible for transferring the knowledge that has been acquired by the project
members to the line organization (Turner, 1999). The functional manager could do the first
preliminary definition of the scope and the goal of the project. The identification of the scope is
based on the strategy, aligning the function with the strategy is one of the main responsibilities of
the functional manager (Larsson and Gobeli, 1987). The definition of the scope and the project
goal could also come from other stakeholders. In this case the functional manager is not the
initiator of the project but is still the owner of the project initiation in relation to the project
manager. The final scope and goals need to be handled and stated by the project manager.
16
Meaning that the project manager needs to do an analysis of the requested outcome and an
adjustment of the initial goals and requested deliveries.
Among the above descriptions, seems to be a consensus that a balanced matrix distributes power,
authority and responsibility in a shared manner or allows for an overlap between the project
manager and functional manager authorities. It is in this type of organization where we find most
struggles.
Table 2 summarizes the above review of matrix typologies and its classifications, focusing on the
project manager and functional manager. It also shows that the role of the project manager and
functional manager differs depending on the type of matrix organization. Power, responsibilities
and accountabilities of these two roles are thus dependent on the organizational structure.
-----------------------
Insert Table 2 here
-----------------------
Having reviewed the different types of matrix organizations we have seen that there are
differences in the categories of struggles between project managers and functional manager in
each one of these organization types. We were unable to find theoretical evidence for legitimacy
struggles being present in functional matrix and in balanced matrix structures.
Table 3 maps some of the factors that constitute the category of struggles for each type of matrix
organization.
------------------------
Insert Table 3 here
17
-----------------------
The critical literature review indicates:
If the functional manager has stronger power and authority his/her role may have stronger
legitimacy in the organization.
On the contrary, if the project manager has more power and authority over the resources,
the plans and the outcomes, his/her role may have the stronger legitimacy.
Different degrees of responsibility sharing will also influence the legitimacy of the roles,
i.e. if the project manager is responsible for the outcome but cannot influence the
selection of resources or the end date of the project. Especially when this is the
responsibility of the functional manager it may lead to equal levels of legitimacy, but it
can also minimize the legitimacy of the project manager.
This leads to the first two propositions:
Proposition 1a: The legitimacy struggles in matrix organizations depend on the distribution of
power, authority and accountability between the project manager and the functional manager.
Proposition 1b: Legitimacy struggles are dependent on the type of matrix structure.
Projects as Temporary Organizations
In this section we will review projects as temporary organizations, in order to provide a broader
spectrum of project organizations. Looking at projects as temporary organizations we can
classify them in two types. In the first type people in the organization alternate between different
projects and do not have a manager outside these projects. This is typical for movie and theatre
productions. These organizations focus on the skills of the team members; they are expected to
18
perform complex tasks with little coordination (Goodman and Goodman, 1976; Bechky, 2006).
The second type of projects as temporary organization comes from the matrix organizational
form, where project members belong to functional departments in form of resource pools, from
where they are lend out to the different projects.
We are going to review both types of temporary organizations, but prioritize the second type
because the purpose of the present study is to focus on the struggles between project manager
and functional manager and these are more often associated with the second type of temporary
organizations.
A large amount of existing literature is based on standards such as “The Guide to the Project
Management Body of Knowledge” (PMBOK) from the Project Management Institute (PMI®)1
and has a tendency to focus on the project itself. It pays little attention to the organization and
environment that surrounds the project. Engwall (2003) introduced a contingency-based
ontology by looking at the surroundings and proposing a conceptualization of projects as
contextually embedded open systems; open in both time and space. He stated the importance of
seeing temporary organizations as parts of the whole organization and not as isolated entities.
This perspective identifies projects as being context dependent on, for example, the surrounding
organization, previous projects, other ongoing projects and future projects. It shows the
importance of analyzing the struggles between the roles by taking these perspectives into
consideration.
1 “PMI is a registered trademark and service mark of the Project Management Institute, Inc
19
Table 4 shows a comparison of the different factors that characterize permanent organizations
and temporary organizations. The differences in the factors that characterize temporary
organizations and permanent organization may be the underlying the reasons for the struggles
between the roles (Lundin and Söderholm, 1995). Project managers of temporary organizations
and functional managers of permanent organizations may have different foci, different control
mechanism, different relational patterns and work in different organizational structures. The
strength of the struggles could vary depending on the dominance of these factors.
-----------------------
Insert Table 4 here
-----------------------
Aspects of projects as temporary organizations
Several aspects that need to be taken into account when looking at projects as temporary
organizations. These are temporariness, context and control mechanisms (Lundin and
Söderholm, 1995; Engwall, 2003; Packendorff, 2003). In this section we will review those
aspects and see whether they have an impact on the category of the struggles between project
managers and functional managers.
Temporariness
According to Lundin and Söderholm (1995), temporariness is the primary element to be
considered because it represents the main difference between functional and temporary
organizations. Time is fundamental to understanding temporary organizations, since they are
limited by time. In permanent organizations time is seen as eternal, in temporary organizations
20
time is seen as something that comes to an end. The view of projects as temporary organization
which coexists within permanent organizations has an impact on both organizations.
Considering temporariness as a crucial aspect there are differences on its impact on projects
depending on their categorization. Janowicz, Bakker and Kenis (2009) categorized temporariness
in:
1. Temporariness as Short Duration
2. Temporariness as Limited Duration
3. Temporariness as Awareness of Impeding Termination.
Defining Temporariness as Short Duration focuses on the limitation of the time available to
conduct tasks as well as the time group members are part of the organization.
Temporariness as Limited Duration refers to the duration of the temporary organization based on
a specific predetermined date, or events or conditions that need to be completed. Temporariness
as Awareness of Impeding Termination is a subcategory of the limited duration approach that
adds members´ awareness of limited duration and their behavior in order to cope with this fact
(Janowicz, Bakker and Kenis, 2009).
Even though these theories argue that time is the key element of the temporary organization there
are different perspectives and implications depending on the different approaches. It implies that
time is not only the start and end point of temporary organizations, meaning that when
discussing time and its effect on temporary organizations, it is not only the awareness about
insufficient time and deadlines what we need to take into consideration.
21
Looking further we see also that time affects the goals of project managers and functional
managers. Project managers have a shorter time perspective because of the temporary nature of
the project, while functional managers have a longer term overall business perspective, which is
based on business result and continuity instead of time (Jugdev and Müller, 2005). This
contradiction in the perspective of goals, which is based on time aspects, could generate conflicts
between project managers and functional managers. Examples of this conflict are mentioned by
Pinto and Slevin (1987) as a result of their empirical research having project managers who are
focused on client acceptance and expectation while the functional manager focused on strategic
time aspects. In addition to this project managers deal with possible risks stemming from the
project members awareness of the temporariness of the project. This may lead them to focus on
finding the next assignment, which may impact the effectiveness of the current project and thus
the project manager‟s authority (Gadis, 1959). The latter is in contradiction to the findings by
Bakker and Janowicz (2009), that the members of a temporary organization focus more on the
present than on the past and future. They argued that the members of a temporary organization
have a strong present orientation and that this has a positive influence on performance. At the
same time team members are mentally decoupled from the rest of the organization. This implies
that the functional manager has limited authority and possibilities to influence the project
members.
The above indicates that depending on the two above approaches, the authority of the project
manager and the functional manager may differ. If the project members focus on the present the
project manager may have higher authority, if the project members focus on the future and the
next assignment the functional manager may have more authority.
22
How does temporariness affect legitimacy? The findings of Janowics, Kenis and Vermeulen
(2009) showed that external legitimacy, meaning the legitimacy of the project outside the project
organization, is affected negatively by temporariness. This is generated by the fact that
temporary organizations function in isolation from the structures of their context. As a
consequence of this temporary isolation temporary organizations tend to create their own norms
that diverge from those of the permanent parent organization. This may affect the external
legitimacy; affect the capacity of receiving support and the project manager possibilities of being
heard within the organization. This leads to a weakness in the ability to perform the tasks.
Especially if newly developed norms in a project challenge the established norms of the parent
organization (Engwall, 2003; Lundin and Söderholm, 1995).
Is there a relation between temporariness and the distribution of power between project
managers and functional managers? The answer to this question may depend on the definition of
temporariness. In short duration temporariness power should benefit the functional managers
since they have the long term perspective in their roles, meaning that the project members will be
more loyal to their long term manager or supervisor (Turner, 1999).
Temporariness as limited time may be favorable for the project manager since there is a specific
event or date that marks the end of the organization. Focusing on the event could give the power
of leading and using the event as a power mechanism (Lundin and Söderholm, 1995; Bechky,
2006).
23
Having the perspective of temporariness as impeding termination could give more power to one
of the roles depending on the situation and the mechanism that the team members use to cope
with the fact that the project is only temporary. If the project members‟ strategy to cope with the
insecurity that the temporariness causes led them to situations of isolation from the line
organization, then the likelihood of power reduction on the side of the functional manager is
reduced. Similarly, if the project members do not strive to move towards termination of the
project, the power of the project manager in his or her role to lead the project towards its goals
may be reduced.
Temporariness in general could also lead to a power balance between project managers and
functional managers since, according the findings of Bakker and Janowicz (2009), the member‟s
awareness about the unexciting or low probability of future collaboration make them concentrate
on the present with little or no focus on the future. Thus leading to higher creativity and
innovation. The reason for this phenomenon is that the members are acting in a “protective
bubble”, guarded from the shadow of the future and the burden of the past” (Bakker and
Janowicz, 2009 p128). This underlying factor could give project managers a committed and
motivated team and could give the functional manager fast paced zone which works in a short
time towards the long time goals.
The above review shows that temporariness has potentially an impact on the struggles in
authority, legitimacy and power between project managers and functional managers. Thus
having an impact on the temporary organization. It also shows that the time impact could have
both positive and negative consequences for both project and the functional organization.
24
Context
As mentioned in the previous section; Engwall (2003) addresses the Context aspect of a project,
stating that it is highly dependent on the surrounding organization, on previous projects, other
ongoing projects and future projects. In his research he found that the degree to which project
management approaches challenge norms and structures of the parent organization affect the
results of the projects. The more project management challenges established structures and
norms of the organization, the smaller the chance to succeed.
Does context affect the four categories of struggles?
Before answering this question, it is necessary to clarify that there are different contexts
perspectives: Considering the context of projects requires to look at organizational aspects and
perceive the parent and temporary organization as distinct entities. This perspective allows to
look at the relationship between the two organizations from an Principal – Agent Theory
perspective. Jenssen and Meckling (1976), describe Principal – Agent Theory as a relationship
between two institutions (people or organizations) where one institution, which is called the
principal, delegates works to another institution, which is called the agent. Their relationship is
subject to two agency problems, which occur when both try to maximize their own utility in their
relationship. These are goal conflict and the difficulty and cost that the principal faces in order
to control the agent. This conflict of interest has it nature in the differences of goals. The
principal may wish that the agent run the organization (e.g. a project) in a way that increases the
value for the principal. On the other hand, the agent may wish to manage the organization (e.g.
25
the project) in ways that maximize the agent‟s personal goals, which may not be in the best
interests of the principal (Jensen and Meckling, 1976; Eisenhardt, 1989).
Agency problems in relation to project management were, among others, discussed by Müller
(2009), Andersen (2009), Eisenhardt (1989), Turner and Müller (2003). These authors
considered the parent organization as the principal and the project organization as the agent, or
assumed that the sponsor or project owner is the principal and the project manager is the agent.
There is a risk for conflict of interest if these two are not completely aligned in their goals,
information and directions. Elimination of this risk will rarely be possible because the project
manager as the agent focuses on project performance and the project owner as the principal
focuses on the parent organization with a broader set of objectives. The agency problem stems
from the separation of ownership and management. The project manager as an agent manages
the project, but the project is owned by the principal – If the principal is the functional manager
we might find power struggles between the project manager and the functional manager.
The underlying assumptions of Principal – Agent Theory are challenged by Stewardship Theory,
which questions the assumption that a principal – agent relationship will always be characterized
by a conflict. This theory states that, on the contrary to the agency assumption, the agent will act
in the interest of the principal and focus on generating benefit for the principal and not for his/her
own interest (Davis, Schoorman and Donaldson, 1997; Donaldson and Davis, 1991; Lee and
O‟Neill, 2003).
26
Müller (2010) relates the two theories to the type of industries, where agency theory is applied in
for-profit organizations but might not be appropriate for non-profit sectors. In non-profit sectors
Stewardship theory is applied, due to collaborative approaches between the principal and the
steward. Stewardship Theory assumes a different relationship between project managers and
their context and thus a different relationship towards the functional mangers, because of
synchronization of objectives and a mutually supportive relationship.
Considering the functional lines of the organization as context, Brown (2008) found empirical
evidence of the lack of legitimacy of project managers as a consequence of the challenging
changes that projects generate on the functional lines. Furthermore she found that there was a
correlation in this area that depended on the extent in which the project was challenging the
permanent organization. This is also supported by Engwall (2001) and his empirical study of two
projects that were among the biggest capital investment projects carried out in Scandinavia
during the late 1980s. His finding does not only support the legitimacy disadvantage of the
project manager in relation to the functional manager, he also relates authority and accountability
struggles to it.
Summarizing the above in relation to projects as temporary organizations and their context,
principal – agent theory is based on the assumption that there is a conflict of interests and
therefore a need for control. This might affect the authority of project managers because they are
controlled by functional managers. While stewardship theory is based on a harmonization of
interests between the project and it context and therefore collaboration and trust are developed.
27
Furthermore, prior research indicates that that the contexts of projects impact on the four
categories of struggles.
Control Mechanism
Control Mechanism in temporary organizations differs from those of permanent organizations in
a way that the focus is on relations instead of controlling by lines of authority (Bechky, 2006).
Temporary organizations tend to develop their own mechanisms of control, which are based on
interpersonal processes (Packendorff, 2003). This can be observed not only in firms, but also in
theater groups and film teams. Temporary organizations need to deal with tasks and
environmental uncertainty; this is managed by interpersonal processes instead of formal
structures. These interpersonal processes are the base of the control mechanisms, indicating
behavior control as stated by Ouchi (1979). A temporary organization does not necessarily
become an unstructured work organization. On the contrary it tends to develop alternative and
normative rules (Bechky, 2006).
Control mechanisms can be based on project performance, project deliverables and project
behavior, or through controlling the gap between project preferences and parent organization.
The last mentioned control mechanism is a holistic approach which is based on achieving
common values and beliefs within the parent organization and project organization (Andersen,
2009).
The above addresses differences in the way of controlling projects and the way of controlling
permanent organizations. These differences might affect project managers and functional
28
managers in different ways and contribute to the struggles between their roles. Controlling a
project in the same way as controlling a plan affects the autonomy of the project and this lead to
an authority disadvantage for the project manager (Packendorff, 2003). On the other hand if the
parent organization does not have any other way of influencing and or participating in the work
of the temporary organization than controlling the performance or the deliveries, the functional
manager authority might be weaker or even imbalanced in relation to the project manager
(Turner and Müller, 2003; Müller and Turner, 2005). This may also have an impact on
legitimacy, because if the project is not accepted as organization, the project manager‟s
legitimacy will be lower than that of the functional manager (Brown, 2008). As a consequence,
this could also influence team commitment and loyalty (Turner, 1999).
Does the control mechanism affect the power struggles between project managers and functional
managers? Based on the above we argue that control mechanisms for the project also influence
the power struggle and distribution of power between the managers‟ roles. By creating
alternative norms and rules and by the project‟s isolation the project manager might have a
strong power within the project. Then the functional manager may be limited to controlling the
outcome with no possibility to influence the performance of the work. Contrarily the functional
manager could control the outcome of the project and also controls the project manager itself and
has the majority of the power.
Applying the holistic control mechanism mentioned by Andersen (2000), meaning controlling
what the project manager is doing and not only that he/she is delivering could lead to a different
scenario. The risk for conflict is minimized by taking actions that minimize the divergence of
29
goals between project managers and functional managers. Thus a holistic control mechanism
may contribute to a better balance minimizing the power struggle.
The above review shows that control mechanisms of projects as temporary organizations impact
on the four categories of struggles. Prior research found evidence of both advantages and
disadvantage for the project manager and the functional manager.
Summarizing the review on projects as temporary organizations
The review of literature on projects as temporary organizations indicates that the four categories
of struggles are affected by temporariness, project context and project control mechanisms (see
Table 5).
Furthermore, a gap in previous research was identified in terms of the impact that the
combination of temporariness, context and control mechanisms has on the four categories of
struggles. Further research in this area is suggested.
Huemann (2010), Turner, Keegan and Huemann (2008), Söderlund and Bredin (2005), stated
that HRM practices related to project as temporary organizations is an unexplored area. There is
also a need for clarification of the project manager‟s responsibility in HRM practices and of
moving some HR responsibilities to the project manager. This is needed because the project
manager is affected by HR decisions but is not participating in them. The functional manager, on
the other hand, is having problems in following the competence development of his/her personal
while they are allocated to the projects (Söderlund & Bredin, 2005). HRM practices are a
30
challenge in temporary organizations because they require a new way of managing and a role
demand that differs from the role in traditional organization structures (Turner et al., 2008).
Looking at companies that perform most of their activities in projects we see that “Project
managers carry out HRM tasks for project team members, even if he or she has no personnel
authority” (Huemann 2010,p 367). These facts might contribute to the tension between the two
roles but further research is needed to determinate if the distribution of HRM practices between
the Project Manager and the Functional Manager has an impact on the four struggles that we are
studying.
Table 5 presents a selection of the previous research on the aspects of temporary organizations
and the different categories of struggles.
-----------------------
Insert Table 5 here
-----------------------
Analyzing the table allows us to purpose the following propositions:
Proposition 2a: The legitimacy of the project manager is affected negatively by temporariness,
project context and project control mechanisms.
Proposition 2b: Mutually supportive relations between project managers and functional
managers lead to reduction of authority, power and accountability struggles
Proposition 3c: The unclear distribution of HRM responsibilities is a source of tension between
project managers and functional managers.
Conclusions and areas for further research
31
Having reviewed the literature on matrix and temporary organizations, combining these two
domains of studies and focusing on Project Manager and Functional Manager, we have found
that struggles about Power, Authority, Accountability and Legitimacy are mentioned. These
struggles have been discussed from the early literature on matrix organizations until the latest
contributions. There seems to be consensus that these are frequently present in matrix settings.
This does not mean that these are the only struggles that need to be considered. Further research
is needed in order to determine if they are important struggles and to decide how to measure
them.
Our conclusion is that the nature and factors that underlie the struggles between project managers
and functional manager are grounded in the organizational structures and control structures. The
different matrix organizations distribute power, authority, accountability and legitimacy between
project managers and functional managers in different ways. The strength of the struggles may
vary with the organizational structure and control structure. Applying agency theory and seeing
projects as agencies, lead us to the conclusion that the nature of the struggles lies in the roles
where the project manager (the agent) knows more about project issues, content and projects
members than the functional manager (the principal). The principal may not understand why the
agents makes the choices they do. Both the agent and principal may try to maximize their own
utility and in situations where the objectives are not aligned struggles will arise (Turner and
Müller, 2003; Müller and Turner, 2005; Jensen and Meckling, 1976).
We also see indications of relationships between the parameters that define temporary
organizations (i.e. temporariness, control mechanisms and context), and the four struggles (i.e.
32
accountably, authority, power and legitimacy). This paper has identified the need for more
empirical research in this area.
33
References
Andersen, E. (2009) “Two perspectives of project management”, EURAM. 2009. 9 th. 11th -
14th May, Liverpool.
Andersen, E. (2000). “Managing organization-structure and responsibilities”, in Turner, J. R., &
Simister, S. J. (eds.) Gower Handbook of Project Management (Vol. 3rd, pp. 277-292).
Hampshire, UK: Gower Publishing Ltd.
Bakker, R.M., & Janowicz,M. (2009). “Time Matters: the impact of „temporariness‟ on the
functioning and performance of organizations” in Temporary Organizations “Prevalence, Logic
and Effectiveness” Kenis,P. ,Janowicz,M.and Cambre, B. Cheltenham: Edward Elgar Publishing
Limited.
Bechky, B. A. (2006). Gaffers, Gofers, and Grips, “Role-Based Coordination in Temporary
Organizations”. Organization Science, 17(1), 3-21.
Brown, C. J. (2008). “A comprehensive organisational model for the effective management of
project management”. South African Journal of Business Management, 39(3), 1-10.
Brown, C. J., & Botha, M. C. (2005). “Lessons learnt on implementing project management in a
functionally-only structured South African municipality”. South African Journal of Business
Management, 36(4), 1-7.
Curran, C. J. (2002). “The Myth of Equality in Flatline Organizations”. OD Practitioner, 34(4),
40-46.
Davis, J. H., F Schoorman. D. & Donaldson L (1997). “Toward a stewardship theory of
management”. Academy of Management Review 22(1): 20-47.
Donaldson, L., & J. H. Davis (1991). Stewardship “Theory or Agency Theory: CEO Governance
and Shareholder Returns”. Australian Journal of Management 16(1): 49.
Dunne Jr, E. J., Stahl, M. J., & Melhart Jr, L. J. (1978). “Influence source of project and
functional managers in matrix organizations”. Academy of Management Journal, 21(1), 135-140.
Eisenhardt, K. M. (1989). “Agency theory: An assessment and review”. Academy of
Management Review, 14(1), 57-74.
Engwall, M. (2001). “Moving Out of Plato's Cave: Toward a Multi-Project Perspective on
Project Organizing”. Fenix WP 2001:8.
Engwall, M. (2003). “No project is an island: linking projects to history and context.” Research
Policy, 32(5), 789-808.
Fayol, H. (1949). “General and Industrial Management”. London: Pitman. (Translated by C.
Storra from the original Administration Industrielle et Générale 1916)
Ford, R. C., & Randolph, W. A. (1992). “Cross-Functional Structures: A Review and Integration
of Matrix Organization and Project Management”. Journal of Management, 18(2), 267.
Forman, E., & Selly M A. 2001. “Decision by Objectives: How to Convince Others That You
Are Right”. World Scientific Publishing, River Edge, NJ, 402.
Gaddis, P. O. (1959). “The project manager”. Harvard Business Review, 37(3), 89-97.
34
Galbraith, J. R. (1971). “Matrix organization designs”. Business Horizons, 14(1), 29.
Galbraith, J. R., & R. K. Kazanjian (1986). “Organizing to implement strategies of diversity and
globalization: The role of matrix designs”. Human Resource Management 25(1), 37-54.
Goodman, R. A. (1971). “Organization and the effective use of human resources”. British
Journal of Industrial Relations, 9(1), 55-68.
Goodman, R. A., & Goodman, L. P. (1976). “Some Management Issues in Temporary Systems:
A Study of Professional Development and Manpower--The Theater Case”. Administrative
Science Quarterly, 21(3), 494-501.
Goold, M., & Campbell, A. (2002). “Do You Have a Well-Designed Organization?”, Harvard
Business Review, 80(3), 117-124.
Grimes, A.J. (1978) “Authority, Power, Influence and Social Control: A Theoretical Synthesis”,
Academy of Management 3(4), 724-735.
Huemann, M. (2010) “Considering Human Resource Management when developing a project-
oriented company: Case study of a telecommunication company”, International Journal of
Project Management, 28(4) 361-369.
Janowicz,M., Bakker, R.M., & Kenis,P. (2009) “Research on temporary organizations: the state
of the art and distinct approaches toward “Temporariness” in Temporary Organizations
“Prevalence, Logic and Effectiveness”, Kenis,P.,Janowicz,M.,Cambre,B. Cheltenham: Edward
Elgar Publishing Limited.
Janowicz, M., Kenis, P., ,R,M., & Vermeulen,P.(2009). “The atemporality of temporary
organizations: implications for goal attainment and legitimacy in Temporary Organizations
“Prevalence, Logic and Effectiveness”, Kenis,P.,Janowicz,M.,Cambre,B. Cheltenham: Edward
Elgar Publishing Limited.
Jensen, M. C., & W. H. Meckling (1976). ”Theory of the Firm: Managerial Behavior, Agency
Costs and Ownership Structure”. Journal of Financial Economics, 3, 305-360.
Jugdev, K., & Müller R. (2005). ”A retrospective look at our evolving understanding of project
success”. Project Management Journal 36(4), 19-31.
Katz, R. (1982). “The effects of group longevity on project communication and performance”,
Administrative Science Quarterly, Vol. 27, No. 1, 81-104.
Katz, R., & Allen, T.J. (1985). ”Project performance and the locus of influence in the R & D
matrix”. Academy of Management Journal, 28(1), 67-87.
Knight, K. (1976). “Matrix organization: a review”. Journal of Management Studies, 13(2), 111-
130.
Larson, E. W., & Gobeli, D. H. (1987). “Matrix Management: Contradictions and Insights.”
California Management Review, 29(4), 126-138.
Lee, P. M., & O‟Neill, H. M. (2003) “Ownership structures and R&D investments of U.S. and
Japanese firms: agency and stewardship perspectives.”, Academy of Management Journal, 46,
212-225.
Lundin, R. A., & A. Söderholm (1995). “A Theory of the Temporary Organization.”,
Scandinavian Journal of Management, 11(4), 437-455.
35
Martinsuo, M., & Lehtonen, P. (2007). “Institutional Transformation through Temporary
Organizing. Comparison of two Approaches.”, 23rd EGOS European Group for Organization
Studies Colloquium, 5-7 July 2007, Vienna, Austria.
Morgan, G. (1997). Images of Organization. London: SAGE Publications.
Morrison, J. M., Brown, C. J., & Smit, E. V. D. M. (2006). “A supportive organisational culture
for project management in matrix organisations: A theoretical perspective”. South African
Journal of Business Management, 37(4), 39-54.
Morrison, J. M., C. J. Brown, et al. (2008). "The impact of organizational culture on project
management in matrix organizations". South African Journal of Business Management 39 (4),
27-36.
Müller, R. (2009). Project Governance, Farnharn: Gower Publishing Limited.
Müller, R. (forthcoming). Project Governance, in Morris, P., Pinto, J. & Söderlund, J. (eds.),
Oxford Handbook of Project Management, Oxford University Press, UK.
Müller, R., & J. R. Turner (2005). “The impact of principal, agent relationship and contract type
on communication between project owner and manager”. International Journal of Project
Management 23(5), 398-403.
Northouse, P.G., (2009). Leadership Theory and Practice (fifth edition). Sage Publications Inc.,
California USA.
Ouchi, W. G. (1979). “A Conceptual Framework for the Design of Organizational Control
Mechanisms”. Management Science 25(9), 833-848.
Packendorff, J. (2003). Projektorganisation och Projektorganisering: Projekt som plan och
temporär organisation. 2:a upplagan. Umeå: Handelshögskolan i Umeå, Inst för
Företagsekonomi.
Pinto, J. K., & Rouhiainen, P. (2001). Buildning Customer-Based Project Organizations. New
York: John Wiley & Sons, Inc.
Pinto, J.K., & Slevin, D.P. (1987), “Critical factors in successful project implementation”, IEEE
Transactions on Engineering Management, Vol. 34 No. 1, 22-8.
Popper K. (1960) “On the Sources of Knowledge and Ignorance” in Popper selections, D Miller
(Ed) Princeton University Press 1985.
Project Management Institute (PMI®). (2004), A Guide to the Project Management Body of
Knowledge (PMBOKR Guide), 3rd ed., Newton Square, PA: Project Management Institute.
Söderlund, J., & Bredin, K. (2005), Perspektiv på HRM., Malmö: Liber Ekonomi.
Suchman, M. C. (1995). “Managing legitimacy: Strategic and institutional approaches”,
Academy of management review 20(3), 571-610.
Turner, J. R. (1999). The handbook of Project-based Management: Improving the Process for
Achieving Strategic Objectives, 2nd ed., London: McGraw Hill.
Turner, J.R., Huemann, M., Keegan, A.E., 2008, Human Resource Management in the Project-
oriented Organization, Newtown Square, PA: Project Management Institute.
36
Turner, R., & Müller R. (2007). “Choosing Appropriate Project Managers: Matching Their
Leadership Style to the Type of Project”. PM Network 21(3), 83-83.
Turner, J. R., & Müller, R. (2003). “On the nature of the project as a temporary organization.”
International Journal of Project Management, 21(1), 1.
TutorVista.com 2010, http://www.tutorvista.com/ 2010/10/8.
37
Table 1. Matrix organizations pros and cons
Matrix organization Citation
Pros Efficient use of resources Goodman 1971
Galbraith 1971
Knight 1976
Larson and Gobeli 1987
Ford and Randolph 1992
Turner 1999
Andersen 2000
Morrison, Brown and Smit 2006
Flexibility Galbraith 1971
Knight 1976
Larson and Gobeli 1987
Improved motivation and commitment Knight 1976
Larson and Gobeli 1987
Ford and Randolph 1992
Improved communication lateral and
vertical
Knight 1976
Larson and Gobeli 1987
Ford and Randolph 1992
Cons Power struggles between the project Knight 1976
manager and functional manager Larson and Gobeli 1987
Ford and Randolph 1992
Engwall 2001
Brown and Botha 2005
Morrison, Brown and Smit
2006;2008
Brown 2008
Competition concerning resources‟ Knight 1976
Galbraith and Kazanjian 1986
Larson and Gobeli 1987
Engwall 2001
Brown and Botha 2005
Morrison, Brown and Smit 2006
Brown 2008
Ambiguity and role conflict due to
duality
Knight 1976
Galbraith and Kazanjian 1986
Larson and Gobeli 1987
Ford and Randolf 1992
Andersen 2000
Engwall 2001
Morrison, Brown and Smit
2006;2008
Brown 2008
Monitoring and control Knight 1976
Larson and Gobeli 1987
Higher administrative cost Knight 1976
Galbraith and Kazanjian 1986
Ford and Randolph 1992
Turner and Müller 2007
38
Table 2. Summary of matrix organization typologies, PM and FM perspective
Matrix organizations typologies: a selection
(Functional Manager (FM), Project Manager (PM))
Larsson and
Gobeli
1987
Functional
Matrix
PM: Coordinator
FM: Responsible
for staff and
deliveries
Project Matrix
PM: Responsible
for staff and
realization
FM: Supporting
Balanced Matrix
Shared responsibilities
PM: Design and plan
Responsible for the
What
FM: Responsible for
the work, for the How
Turner
1999 Coordinating
Matrix
PM: Coordinator
FM: Responsible
for staff and
assigning work
Secondment
Matrix
PM: Responsible
for staff and for
assigning work
FM: Providing
personnel
Balanced Matrix
Share responsibilities
PM: Responsible for
time and cost
FM: Responsible for
scope and quality
Andersen
2000 Split Authority Project Organization
Shared authority between PM and FM
Pinto and
Rouhiainen
2001
Lightweight Project Organization
PM: Coordinator
FM: Responsible for the staff and
assigning work.
Heavyweight Project
Organization
Shared Responsibilities
between PM and FM
39
Table 3 Category of struggles and type of matrix organization
Functional Matrix Project Matrix Balance Matrix
Authority PM faces struggles in
this area (Pinto and
Rouhiainen, 2001).
The FM retain the
ultimate decision
making authority (Ford
and Randolf, 1992).
FM faces struggles due to
the fact that the PM has
the authority to control
both resources and project
direction (Ford and
Randolf, 1992).
In general un-clarity about
authority is largely absent
(Morrison, Brown and
Smit, 2006).
Both PM and FM faces
authority struggles due
the split boundary of
authority (Larsson and
Gobeli, 1987; Brown
2008).
Accountability PM is accountable for
the result but faces
accountability struggles
due to ambiguity and
lack of authority
(Turner, 1999).
FM faces struggles in this
area because the cost and
long term accountability
that is part of the role are
threatened by a problem
solving and customer
focus applied by PM who
have more authority
(Morrison, Brown and
Smit, 2006).
There are struggles in
this area there are
generated by shared or
split accountability
regarding resources,
technical issues, salaries
and personnel
management (Kats and
Allen, 1985).
Power PM and FM faces
conflict dues to
ambiguity of goals
(Pinto and Rouhiainen,
2001).
Both PM and FM faces
moderate power struggles
(Larson and Gobeli,1987).
Power struggles
between PM and FM as
a result of the ambiguity
regarding
accountabilities and
responsibilities (Ford
and Randolf, 1992).
Legitimacy To date no theoretical
evidence.
FM faces struggles in this
area due to limited
authority (Morrison,
Brown and Smit, 2006).
To date no theoretical
evidence.
40
Table 4. Comparison between permanent and temporary organizations
Factors Permanent Organization Temporary Organization
Focus on Long-term Survival
Turner (1999)
Time
Lundin and Söderholm (1995)
Relation to
Organizational hierarchy
Engwall (2003)
Context
Engwall (2003)
Controlled by Formal Structures
Bechky (2006)
Interpersonal Processes and
alternative Control
Mechanisms.
Pakendorff (2003)
41
Table 5. Selection of temporary organizations and struggles
Temporariness Context Project control
Mechanisms
Authority Benefit the authority
of PM if the project
members focus on the
present and benefit the
FM if the focus is on
the future (Bakker and
Janowicz, 2009).
Applying he steward‟s
theory‟s approach gives
mutually supportive
relation between PM and
FM and thus a reduction
of the authority struggle
(Müller 2010).
Applying the Agency
theory is a disadvantage
for the PM
(Müller, 2009; Andersen,
2009; Eisenhardt, 1989;
Turner and Müller, 2003).
Create disadvantage
for the PM
(Packendorff, 2003).
Accountability and
Power
Benefit the FM
(Turner 1999),
Balanced between PM
and FM (Bakker and
Janowicz, 2009)
Benefit the PM
(Lundin and
Söderholm, 1995;
Bechky, 2006).
Applying the Agency
theory gives disadvantage
for the PM or FM
depending on the context
(Müller, 2009; Andersen,
2009; Eisenhardt, 1989;
Turner and Müller, 2003).
A holistic approach
will balance the
power between the
roles (Andersen,
2009).
Legitimacy Affects the legitimacy
of the PM negatively
(Janowics, Kenis and
Vermeulen, 2009;
Lundin and
Söderholm, 1995;
Katz, 1982).
Affects the legitimacy of
the PM negatively
specially if the project
challenges the permanent
organization
(Brown, 2008; Engwall,
2001).
Lower for the PM
(Turner, 1999).