the united republic of tanzania ministry of … iv mid year... · kra key result area mca – t ......
TRANSCRIPT
0
THE UNITED REPUBLIC OF TANZANIA
MINISTRY OF FINANCE
PUBLIC FINANCIAL MANAGEMENT REFORM PROGRAMME
(PFMRP PHASE IV)
MID-YEAR PROGRESS REPORT FOR FY 2012/13
(JULY – DECEMBER 2012)
CONTACT:
Permanent Secretary
Ministry of Finance
P.O.Box 9111
Dar es Salaam
April, 2013
1
TABLE OF CONTENTS
LIST OF ABBREVIATIONS ................................................................................................................................. 2
Executive Summary ................................................................................................................................................ 3
Chapter 1.0 BACKGROUND AND INTRODUCTION ........................................................................................ 4
Chapter 2.0 PROGRESS ON IMPLEMENTATION OF PLANNED ACTIVITIES IN FY 2012/13 ................... 7
Chapter 3.0 BUDGET EXECUTION ................................................................................................................... 19
Chapter 4.0 CHALLENGES AND RECOMMENDATIONS FOR NEXT PERIOD .......................................... 24
Annexes:
- Annex 1: Procurement progress report ended 31st December, 2012
- Annex 2: Detailed assessment of milestone status as at Dec 2012 based on M&E
Framework for 2012 – 2017
- Annex 3: Report of the 2012 PFMRP IV Joint Supervision Mission
2
LIST OF ABBREVIATION
AG Attorney General
CAG Controller and Auditor General
ICT Information & Communication Technology
IPSAs International Public Sector Accounting Standards
LAAC Local Authority Accounts Committee
LGAs Local Government Authorities
JSC Joint Steering Committee
KRA Key Result Area
MCA – T Millennium Challenge Account - Tanzania
MCC Millennium Challenge Cooperation
MDAs Ministries, Departments and Agencies
M&E Monitoring and Evaluation
MIS Management Information System
MKUKUTA Mkakati wa Kukuza Uchumi na Kupunguza Umaskini Tanzania
MoF Ministry of Finance
MTEF Medium Term Expenditure Framework
PAC Public Accounts Committee
PEFA Public Expenditure Framework for Assessment
PFMRP Public Financial Management Reform Program
PMU Procurement Management Unit
PO-PC President’s Office – Planning Commission
PO- PSM President’s Office – Public Service Management
RSs Regional Secretariat’s
SMTB Secretary for Ministerial Tender Board
TRA Tanzania Revenue Authority
TRMIS Treasury Registrar Management Information System
TWG Technical Working Group
3
EXECUTIVE SUMMARY
PFMRP Phase IV was officially launched in June, 2012 and its implementation started on 1st
July, 2012. The Programme is designed to consolidate and build on achievements of the previous
phases in line with National policy objectives stated in the Tanzania Development Vision 2025,
the Five Year Development Plan (FYDP) 2011/12 - 2015/16 and the MKUKUTA/MKUZA II
aimed at fostering economic growth and the reduction of poverty in the country. PFMRP IV aims
at strengthening and improving public financial management in a more coordinated manner in
order to meet the current fiscal policy challenges.
PFMRP Phase IV implementation is organized in five Key Result Areas (KRAs) of the PFM
system; namely 1) Revenue management, 2) Budget and Planning, 3) Budget execution,
Transparency and Accountability, 4) Budget Control and Oversight, 5) Change management,
Program Monitoring and Communication. The KRAs are structured to ensure that all the
different aspects and dependencies of a sound PFM are managed during the program
implementation. The strategic actions are facilitated through the results-based management,
program based budgets, accountability and performance audits, transparency and
communication.
The approved budget for FY 2012/13 is Tshs 33,597,704,853 of which Tshs 3,996,904,853 are
Project funds1, Tshs. 16,250,000,000 Government funds and Tshs. 13,350,800,000 Basket
Funds2. During the period a total of Tshs. 4,902,205,444 was released of which Tshs.
2,058,325,000 from GoT; Tshs. 36,835,194 from Project funds and Tshs. 2,807,045,250 from
Basket Funds. Actual expenditure as at 31st December, 2012 amounted to Tshs. 1,456,163,521
being 30% of the funds released. Expenditure by source was GoT Tshs. 592,775,065 being 29%
of the released funds; Project Tshs. 36,835,194 being 100% of the released funds and Basket
Funds Tshs. 826,553,262 being 29% of the released funds.
In procurement, activities which were at contracting stage including on-going activities from
financial year 2011/12 were Tshs. 11,701,520,000 representing 59.5% of the total procurements
1 Bilateral project funds include AfDB and World Bank
2 DFID, CIDA, Denmark, Ireland and KFW have signed a Memorandum of Understanding with the GoT establishing a pooled
funding mechanism.
4
value of Tshs. 19,674,640,000. Out of these Tshs. 10,520,000,000 are for two works project and
Tshs. 1,181,520,000 are for five consultancy activities. During the period under review, 11
activities estimated value of Tshs. 2,081,000,000 representing 10.6% of the total procurement
estimates were at various procurement stages. 41 activities estimated to cost Tshs.
5,892,120,000 being 30% of the total procurement estimates had not been started. Detailed
procurement progress report is displayed under Annex A1.
The programme recorded fairly satisfactory progress whereby 15 milestones were achieved and
87 milestones were on track. Notable achievements are: chart of accounts have been modified
to accommodate program based budgeting; EPICOR system was upgraded from version 7.3.5 to
9.05; Approved National Budget and Citizens Budget were published on MoF website; and Joint
Supervision Mission was conducted and report approved. However, there was low absorption of
funds during the period under review due to late release of funds.
The remaining period of the work plan (Jan – June 2013), the respective component managers
are committed to fast track the implementation of activities and will utilize the TWGs to discuss
and resolve emerging issues. It is envisaged that through enhanced information sharing there will
be smooth coordination to achieve milestone targets. The PEFA Central and Local government
will be important exercises for the PFMRP.
5
CHAPTER ONE
BACKGROUND AND INTRODUCTION
1.0 Background
The Government of Tanzania has been implementing Public Financial Management Reform
Programme (PFMRP) for the past two decades in different phases aiming at improving Public
financial management systems across all levels. Phase I was implemented from 1998-2004 with
an objective of controlling expenditure, introducing aggregate fiscal discipline and contributing
to stable macro-economic growth. Phase II was implemented from 2004 to 2008 with an
objective of progressively modernizing the processes, procedures and systems involved in PFM
through the implementation and use of ‘best practice’ tools, techniques and methodologies to
improve revenue forecasting and resource allocation for strategic priorities. Phase III was
implemented from 2008 to 2011 with the objective of ensuring greater predictability and
availability of medium term resources to executing agencies.
1.1 Introduction
PFMRP IV was launched in June 2012 and its implementation started on 1st July 2012. PFMRP
Phase IV is designed and implemented to complement efforts to achieve national policy
objectives stated in Tanzania Development Vision 2025, Five Year Development Plan (FYDP)
2011/12-2015/16 and MKUKUTA/MKUZA II so as to achieve economic growth. The
overarching goal of attaining sound financial management and discipline in public service
delivery for sustainable development will be achieved through implementation of PFMRP IV
five Key Results Areas which are: Revenue management; Budget and Planning; Budget
execution, Transparency and Accountability; Budget Control and Oversight; and Change
management, Program Monitoring as well as Communication. Table 1.1 gives a summary of
KRA overview.
The Public Financial Management reform is implemented in line with the on-going reforms in
the Public Sector which aim at improved performance, efficiency and effectiveness in service
delivery for sustainable economic growth. In doing so, PFMRP IV will address interventions
which will be:
6
Comprehensive, to include the various key reform activities in the PFM systems as well as
the cross-cutting issues related to capacity building, improving infrastructure for service
delivery, and reviewing the institutional policy and regulatory frameworks;
Captured in a well defined Monitoring and Evaluation framework, sequenced to manage
priorities and ensure a more accurate cash forecasting and achievement of results;
Linked and inter-dependent with clear demarcation of responsibilities and accountability
Better standardized and automated systems to ensure attainment of desired results in financial
recording and reporting;
Well managed, with effective institutional arrangement to support implementation of the
programme
Focused, aiming at supporting agencies and initiatives which are likely to have a great cross
cutting impact on the PFM system.
Table 1.1 KRA and components overview
Key Result Area (KRA) Major Component, Department and
KRA-TWG
KRA 1: Revenue Management
Leader: CPAD
Focus: improving revenue forecasting and resources mobilization and reviewing &
streamlining existing revenue policies, laws and regulations. The intervention aims
at developing appropriate model for revenue forecasting to improve cash flow
forecasting to spending units. Also the KRA will continue to improve external
resource management, review retention schemes and enhance capacity for managing
public investments.
Commissioner for Policy Analysis
Department (CPAD) – MoF
Treasury Registrar (TR) - MoF
Prime Minister’s Office – Regional
Administration and Local Government
(PMO-RALG)
Commissioner External Finance - MoF
MDAs
KRA 2:Planning and Budgeting
Leader: BC
Focus: improving macro-fiscal policy, planning, MTEF credibility, enhancing
budget classification by adopting GFS 2001 and CoFoG standards, facilitate
program based budgeting, broadening the scope of the chart of accounts, enhancing
monitoring, reporting and accountability and review of the Medium Term Strategic
Planning & Budgeting Manual (MTSPBM) to enable the national development
planning and budgeting system to articulate national policy priority targets with the
desired institutional results.
Commissioner for Budget (CB) – MoF
CPAD – MoF
PMO-RALG
7
KRA 3: Budget Execution, Transparency and Accountability
Leader: ACCGEN
Focus: achieving greater predictability of resources to spending units; strengthening
capacity on procurement, cash and debt management; and improving the scope and
quality of financial recording and reporting
Public Procurement Regulatory Authority
(PPRA)
Public Procurement Policy Unit
Accountant General (ACCGEN) - MoF
CPAD - MoF
Government Asset Management - MoF
KRA 4: Budget Control and Oversight
Leader: IAG
Focus: strengthening capacity on audit functions (internal and external) as well as
oversight function of the Parliament. The interventions involves providing technical
guidance and capacity building to MDAs and LGAs in the areas of internal audit and
to facilitate timely independent external examination of financial and performance
auditing and report to the public
Internal Auditor Department - MoF
National Audit Office (and Parliament
PACs)
TR
KRA 5:Change Management Programme Monitoring and Communication
Leader: DPD
Focus: cross cutting issues including capacity building on change management,
Monitoring and Evaluation, stakeholders’ communication, coordination and
leadership for efficient and effective programme implementation.
Department for Financial Management
Information System (DFMIS) - MoF
Government Communication Unit - MoF
Department for Planning Division – MoF
Support to Zanzibar
PMO – RALG
ACGEN - MoF
DAHRM - MoF
Layout of the report
This report comprises of an executive summary followed by five chapters which are: Chapter
one provides background information and introduction; Chapter two covers progress on
implementation of the planned activities; Chapter three reports the budget execution; Chapter
four highlights on challenges and recommendations for next period; Annex 1: Procurement
Progress report for the period ended 31 December 2012; Annex 2: Detailed assessment of
milestone status as at Dec 2012 based on M&E Framework for 2012 – 2017
8
CHAPTER TWO
PROGRESS ON IMPLEMENTATION OF PLANNED ACTIVITIES IN FY
2012/13
The Fiscal Year 2012/13 being the first year of PFMRP phase IV implementation is focusing on
activities that lay foundation for the attainment of milestones as outlined in the M&E Framework
as well as Performance Assessment Framework (PAF) 2012 key policy actions.
2.1 Highlights on Targets/Outputs and Implementation Status of Milestones as Per M&E
Result Framework
167 milestones are included in the work plan and budget for FY 2012/13. Out of 167 milestones,
achievement was realized in 11 (7%) milestones. Satisfactory progress was recorded as on track
in 115 (69%) milestones. Delayed and pending milestones were 29 (17%), these involves
activities that could not be initiated before getting specific inputs from stakeholders. 12 (7%)
milestones were at risk of implementation. Milestones on track include those in areas of
consultancy for various studies, works, training and review of legal instruments. Status of
milestones per KRA as at 31st December, 2012 is in table 2.1 while detailed information on each
milestone is outlined in Annex 2. Progress toward achieving the output under each KRA is
presented in the next part.
Table 2.1: Cumulative Milestone Status FY 2012/13 – December, 2012
KRA Achieved On
Track
Pending/Delayed At Risk Total
KRA 1 0 13 5 6 24
KRA 2 1 15 3 1 20
KRA 3 5 39 4 4 52
KRA 4 1 21 3 0 25
KRA 5 4 27 14 1 46
TOTAL 11 115 29 12 167
Percentage 7 69 17 7 100
9
KRA 1 Revenue Management:
Objective: Strengthened systems, processes and procedures for improving the operational
capability of the revenue collection by June 2016
Output 1.2: The Government improves efficiency in domestic revenue mobilization both at the
policy and the administration levels by updating legal instruments towards international best
practices:
Non-tax revenue study on Integration and harmonization of revenue collection is in
progress. A consultant is continuing with a study.
A draft of Tax Administration Bill has been submitted to the cabinet for approval. It is
expected that Cabinet approval and Attorney General Verification will be done early in
third quarter for the draft Act to be submitted to Parliament in April, 2013.
The first draft of new TR Bill has been submitted to Cabinet Secretariat for an initial
review. The bill is expected to be sent to parliament by June, 2013
Implementation Status of Milestones as Per M&E Result Framework
The implementation status on the 24 milestones was fair satisfactory of which 13 (54%) were on
track, 5 (21%) pending and 6 (25%) at risk. Figure 1 below depicts schematic presentation of
KRA 1status as at December, 2012.
Achieved, 0%
On Track, 54%Pending, 21%
At Risk, 25%
Figure 1: KRA Milestone Status
10
Milestones at risk include the amendment of the Local Government Finance Act as well as the
assessment of revenue potential for LGAs.
Delayed milestones include revision of the JAST (DCF) and AMP user guidelines. Concerted
efforts may change status on pending milestones once a way forward is agreed to address factors
that are hindering the implementation process.
KRA 2 Budgeting and planning
Objective: Strengthened capacity of planning and budget management, including results and
program based budgeting, within MOF, MDAs and LGAs by June 2016.
Output 2.1: Strengthened capacity of MDAs, RSs and LGAs in implementing program based
budgeting by June 2016.
Programs and sub-programs have been (tentatively) defined and objectives, outputs and
performance indicators were developed from MKUKUTA II and FYDP. Six ministries
were involved in training as a part of pilot phase in fiscal year 2012/13.; these ministries
are Community Gender and Children, Ministry of Finance, Ministry of Education and
Vocational Training, Ministry of Health and Social Welfare, Ministry of Agriculture,
Food Security and Cooperatives and Ministry of Water.
The chart of account has been modified to accommodate Program Based Budgeting.
Continued to implement Program Based Budgeting (PBB) action plan.
Output 2.2: Increased effective utilization of Planning and budgeting tools by 2016
Studies were undertaken in view of a specific budget law and recommendations on legal
review were made.
PER Annual National Policy Dialogue was conducted
Training on resource prioritization and planning was undertaken for members of budget
committee in selected RSs and LGAs.
Implementation Status of Milestones as Per M&E Result Framework
During the period under review one milestone (5%) was achieved, 15 milestones (75%) were on
track, 3 milestones (5%) were pending and one (5%) milestone was at risk out of 20 Milestones
11
in this KRA. Figure 2 below depicts the schematic presentation for KRA 2 status as at
December, 2012.
At Risk5%
On Track, 75%
Pending 15%
Achieved5%
Figure 2: KRA 2 Milestone Status
The milestones at risk and delayed include those relate to agreement on the improvement of
LGAs allocation formula.
KRA 3: Budget Execution, Accountability and Transparency
Objective: Improved utilization of public resources in a more effective, efficient and transparent
manner by June 2016
Output 3.1: Improved public procurement performance by PEs by 2015
Annual audit conducted and preliminary results indicated positive trend based on
compliance and Value for Money (VfM) audits in 30 PEs.
Circular has been issued to Procurement Entities (PEs), which makes mandatory Public
Procurement Plan to be part of Strategic Plan.
About 302 PEs out of 393 have been connected with PMIS as reporting tool for procuring
entities to report back to PPRA
Feasibility study was carried out to move from paper based to e-procurement.
With the exception of PEs within newly established districts, 393 PEs were audited by
2012.
12
Output 3.2: Strengthened public sector procurement by June 2015
A draft of the public procurement regulations has been prepared and submitted to the
Attorney General’s office for verification. Following the minister’s finalization, the
regulation will be submitted to responsible parliamentary committee.
The staff database has currently registered 824 procurement and supply staff in central
and Local government
Development of the National Procurement Policy is under way and a consultant has
submitted a framework paper for discussion among stakeholders. Finalization is foreseen
before June 2013.
Output 3.3: Strengthened capacity of MDAs, RSs and LGAs in Cash management by 2015
Each LGAs now operates only 6 bank accounts with the substantial amount of dormant
bank accounts to be closed.
Output 3.4: Strengthened public debt management capacity by 2015
The draft debt management report from WB Debt management mission and action plan
on steps towards establishment of Debt management has been shared within GoT to all
relevant stakeholders (technical and national debt committees). A structure of a unified
debt management office had been submitted to PO-PSM for approval.
Output 3.5: Improved integrity and content of government financial statements and the
migration from IPSAS cash to IPSAS accrual accounting for all government accounts is
progressing in accordance with plans.
Action plan for migration towards IPSAS Accrual accounting has been prepared.
Opening balances for the financial year 2012/2013 for all MDAs were established in order
to facilitate the implementation of IPAS Accrual;
A draft of revised PFA has been circulated to stakeholders’ for comments. This revised
PFA provides for migration to IPSAS accrual among others.
250 accountants from MDAs, Regions were trained on migration to IPSAS Accrual;
13
Output 3.6: Improved accountability in management of Government Assets for supporting
migration to IPSAS Accrual
Valuation of Government assets in 16 MDAs has been conducted. ToR for consultancy
for the next phase has been drafted and waiting fund release to embark on tender process.
The ToRs for the drafting of the asset policy management have been shared. They are
approved at Government Asset Management Division (GAMD) level, and are circulated
among other stakeholders.
Implementation Status of Milestones as Per M&E Result Framework
Out of 52 milestones achievement was realized in 5 (8%) milestones, which include Procurement
Plans being a mandatory requirement for strategic and budget plans for MDAs, LGAs and
Parastatal Institutions as well as each LGA now operates only bank accounts. Satisfactory
progress (on track) was recorded in 39 (75%) milestones. These are in areas related to
compliance to 2004 PPA; review of procurement regulations to achieve Value for Money in
public procurement; capacity building to PPRA; preparation for e-procurement; development of
National Public Procurement Policy; capacity building on Cash Management; updating IPSAS
guidelines from Cash to Accrual accounting; and improvement on accountability in Government
Asset Management.
About four (8%) milestones were at pending status due a number of factors including the action
plan for implementing the 2011 PPA, training strategy and plan for public procurement cadre as
well as approval of TORs for the uploading 16 MDAs in EPICOR. Establishment of Debt
Management Department was awaiting approval of PO -PSM. Four (8%) milestone were at risk.
Figure 3 below depicts the schematic presentation for KRA 3 status as at December, 2012.
14
Achived 10%
On Track 75%
At Risk 8%
Pending 8%
Figure 3: KRA 3 Milestone Status
KRA 4: Budget Control and Oversight
Objective: Improved adherence and enforcing of MDAs and LGAs to financial internal controls,
rules, laws, regulations and audit recommendations by June 2016
Output 4.1: Increased coverage and quality of the internal audit functions by 2016
Internal audit operational plan for 2012/13-2016/17 have been developed and submitted
to PS for approval.
Internal Audit manuals for LGAs and MDAs to ensure consistency with the International
Practice Framework (IPPF) have been reviewed.
Survey to identify weaknesses of MDAs audit committees was conducted.
Training Needs Assessment and training plan in risk management and risk based audit
has been developed. Guidelines on implementation of institutional risk management
framework were being developed.
20 champions were trained on audit systems as well as 20 champions were trained on risk
management in the Public Sector
15
Output 4.2: Strengthened External audit functions by 2016
The report which outlined the findings and recommendations on the legal amendments
(existing laws) which impede independence of the NAOT has been submitted to the
Attorney General’s Office
An AFROSAI-E team undertook an assessment of NAO`s performance in September,
2012. It is anticipated that the official response from AFROSAI-E upgrading NAO to
AFROSAI-E level 3 will be received in the next quarter.
5 Performance audits were conducted using internal coaching
Alignment of audit methodology is progressing well, with ISSAIs guidelines already in
place
The scoping study to ascertain the parameters of the outstanding matters database was
on-going with completion foreseen in the fourth quarter.
National Audit Office Head Quarter is now connected to its 10 Regional Offices.
Action plan for activating four Team Mate modules to increase its application in auditing
was developed.
The Training Needs Assessment has been undertaken and training policy has been shared
to stakeholders
Output 4.4: Improved performance of parastatals by June 2016
The 10 pilot which will sign the performance contract have been selected based on the
turnover, size and strategic importance.
Database on parastatals has been designed and currently data has been entered into the
Treasury Registrar Information System (TRIMS). However, the reports are expected to
be issued at the end of current year
Implementation Status of Milestones as per M&E Result Framework
During the period, one milestone (4%) was achieved, 21 milestones (84%) were on track and
three (12%) was pending. Milestone achievement was recorded in area of production of Value
for Money audit reports annually. Milestones at on track status included areas of increasing areas
of internal audit functions, development of Internal Audit Manual, capacity building in
computerized auditing, enhancing accountability on parastatals performance and production of
citizen audit reports. Figure 4 below depict milestone status for KRA 4 by mid-year 2012/13.
16
KRA 5 – Change Management, Programme Monitoring and Communication
Objective: Improved management practices with increased accountability and leadership to
better manage performance of PFMRP.
Output 5.1: Coordinate Integration, interfacing and rationalization of Government financial
systems.
The selection of the consultant for the ICT mapping study will be finalized by January
2013 and thereafter the inception report will be prepared.
Output 5.2: Utilization of EPICOR modules increased from seven to ten
EPICOR system has been upgraded from version 7.3.5 to version 9.05 with 7 modules
installed of which 6 are activated
Training to 40 ACCGEN staff and 381 end users was undertaken on the new version of
EPICOR.
Output 5.3: All software development and module upgrades are coordinated with the
overarching plans for ICT integration
The three year operational plan is in place and training for 15 DFIMS staff was
undertaken
17
Output 5.4: Improved communication and public access to key fiscal information to
stakeholders
The approved National Budget was published on Ministry of Finance website by
September 2012 and Citizens budget October, 2012
Draft MoF Communication Strategy was prepared;
Output 5.5: Coordination and Standardization of PFM Training Achieved.
ToRs for conducting a PFM training mapping exercise were prepared and a study will be
conducted in the third quarter covering 29 ministries, 14 regions and 28 district councils
from those selected regions.
Output 5.6: PFMRP Component Managers are being guided by detailed multi-year
operating plans
A five year operating work plan has been developed and is intended to be updated when
preparing the next financial years plans.
Output 5.11: PFMRP implemented efficiently and effectively through result based management
approach.
The Joint Supervision Mission for 2012 was conducted in September as scheduled. The
report was prepared and approved by JSC.
Output 5.12: National systems and processes for intergovernmental transfers to LGAs
Streamlined and rationalized
Preparation of ToRs was completed by end of July 2012 and advertisement calling for
interested consultant appeared in the news paper on August 2012. The consultant for the
mapping study was hired early December 2012.
Implementation Status of Milestones as Per M&E Result Framework
Achievement was recorded in four milestones (9%) covering areas of upgrading EPICOR
software, transparency in budget management through publication on MoF website (National
budget, citizen budget, end-year budget out-turn report); coordination of plans for ICT
integration; timely update of MoF website and; consultative PFM Reform management process
through annual supervision mission.
18
Satisfactory progress on milestones represented as on track were by 27 (59%). These cover the
areas of capacity building and linking MoF IFMIS to PMO-RALG IFMS for immediate
capturing of budget and exchequer transfer to RSs and LGAs respectively; development of
MoF Communication Strategy; development of a comprehensive training programme on change
management and result based management and; timeliness of PFMRP dialogue structure.
14 (30%) milestones were on pending status. These included those related to delay such as ICT
mapping exercise; MoF training mapping exercise; prolonged Secretariat recruitment exercise;
Development of Action Plan on transition to accrual accounting by IAG and ACGEN and;
mapping of system and process for intergovernmental transfer of funds. One (2%) milestone is
on risk status. Figure 5 below depicts the schematic presentation for KRA 5 status as at
December, 2012.
19
CHAPTER THREE
BUDGET EXECUTION
3.1 Funds Disbursement and Release
The approved budget for FY 2012/13 is Tshs. 33,597,704,853 of which Tshs. 3,996,904,853 is
Project funds, Tshs. 16,250,000,000 is Government funds and Tshs. 13,350,800,000 is Basket
Funds. Source of Basket Funds and the status on disbursement is shown in table 3.1 below.
Table 3.1: Basket Funds Disbursement by Development Partners FY 2012/13
July – December 2012
DP
DPs Local
Currency
(Million)
Amount
in (USD
Million)
Amount
in (Tshs.
Million)
Actual Disbursement
Date
Amount
USD
Amount in
(Tshs.
Million)
DFID 2.00GBP 3.20 4,960.00 29.11.2012 1.60 2,530.27
KFW 0.69EUR 0.92 1,426.00 24.12.2012 1.06 1,673.06
Canada 1.00CAD 1.00 1,550.00 - - -
DANIDA 13.01DKK 2.19 3,394.50 11.10.2012 1.99 3,140.16
Ireland 1.00EUR 1.34 2,077.00 05.10.2012 1.29 2,036.95
Total 8.65 13,407.50 5.95 9,380.44
3.2 Fund flows
The available Basket Fund in the holding account was Tshs. 10,461,078,608 of which Tshs.
886,496,043 was opening balance, Tshs. 194,142,145 was unspent balance returned by
components and Tshs. 9,380,440,420 was disbursement by DPs. The amount released to
components was Tshs. 2,807,045,250 as detailed in table 3.2 below.
20
Table 3.2: PFMRP Basket Fund Flows FY 2012/13
July – December 2012
Date Description Amount in
USD
Amount in
Tshs
01.07.2012 (a) Opening Balance 568,483 886,496,043
Add Inflows
Returned Unspent Balances
20.07.2012 Natural Resources 7,850 12,237,667
25.07.2012 Accountant General's Department 116,680 181,904,479
(b) Unspent Balance Total 124,530 194,142,145
DP Releases
05.10.2012 Ireland 1,292,300 2,036,949,106
11.10.2012 Royal Danish 1,992,197 3,140,160,677
29.11.2012 DFID 1,601,601 2,530,273,324
24.12.2012 KFW 1,059,467 1,673,057,313
(c) DP Release Total 5,945,565 9,380,440,420
Funds Available (a+b+c) 6,638,578 10,461,078,608
Less Outflows BF `
31.08.2012 Ministry of Finance-Vote 50 349,452 545,000,000
31.08.2012 Ministry of Finance-Vote 21 64,127 100,000,000
31.10.2012 PMO-RALG 63,932 100,000,000
09.11.2012 Ministry of Finance-Vote 21 47,310 74,000,000
14.11.2012 PMO-RALG 37,624 58,865,250
14.11.2012 Ministry of Finance-Vote 50 684,939 1,071,625,000
19.11.2012 Ministry of Finance-Vote 50 228,312 357,555,000
29.11.2012 National Audit Office 319,653 500,000,000
Amount Transferred to Exchequer 1,795,349 2,807,045,250
Balance in The Holding Account as at 31
December,2012
4,843,229 7,649,588,948
Note: Holding Account Balance have been translated at Tshs. 1,579.44 per US $ as at December, 2012
21
During the period a total sum of Tshs 4,902,205,444 was released to components from
Government Funds, Basket Funds as well as Bilateral Projects. The release by sources was GoT
Tshs 2,058,325,000, Bilateral Projects Tshs. 36,835,194 and Basket Fund Tshs. 2,807,045,250
3.3 Actual Expenditure
During the period actual expenditure amounted to Tshs. 1,456,163,521 being 30% of the total
funds released. Actual expenditure by source was GoT Tshs. 592,775,065 being 29% of the
released funds; Project Tshs. 36,835,194 (100%) and Basket Funds Tshs. 826,553,262 being
29% of the released. Table 3.3 below summarizes the overall funds release against actual
expenditure for July to December 2012 period while table 3.4 shows the summary breakdown by
component recipients.
Table 3.3: PFMRP IV Fund Release and Actual Expenditure FY 2012/13
July – December 2012
SOURCE OF
FUNDS
APPROVED
BUDGET FY
2012/13
CUMMULATIVE
RELEASE
CUMMULATIVE
EXPENDITURE
% ON
RELEASE
GOT 16,250,000,000 2,058,325,000 592,775,065 29%
P 3,996,904,853 36,835,194 36,835,194 100%
BF 13,350,800,000 2,807,045,250 826,553,262 29%
GRAND
TOTAL 33,597,704,853 4,902,205,444 1,456,163,521 30%
22
Table 3.4: PFMRP IV Fund Release against Expenditure by component FY 2012/13 July –
December 2012
S/N COMPONENT SOURCE
OF FUND
APPROVED
BUDGET FY
2012/13
CUMMULATIV
E RELEASE
CUMMULATIV
E
EXPENDITURE
% ON
RELEAS
E
1 POLICY ANALYSIS DIVISION GOT 500,000,000 252,000,000 118,829,760 47%
P 1,372,610,557 0%
BF 268,000,000 100,000,000 2,948,000 3%
SUB TOTAL 2,140,610,557 852,000,000 621,777,760 73%
2 PMO-RALG GOT 300,000,000 - - 0%
BF 745,000,000 158,865,250 3,120,000 2%
SUB TOTAL 1,045,000,000 158,865,250 3,120,000 2%
3 EXTERNAL FINANCE
DIVISION
GOT 150,000,000 12,500,000 - 0%
P 95,530,473 - -
BF 115,000,000 24,000,000 0%
SUB TOTAL 360,530,473 36,500,000 - 0%
4 GOVERNMENT BUDGET
MANAGEMENT
GOT 1,500,000,000 98,800,000 - 0%
BF 470,000,000 50,000,000 0%
SUB TOTAL 1,970,000,000 148,800,000 - 0%
5 MINISTRY OF NATURAL
RESOURCES AND TOURISM
BF 127,000,000 - 0%
SUB TOTAL 127,000,000 - 0%
6 ACCGEN GOT 3,500,000,000 875,000,000 346,977,505 40%
BF 2,622,840,000 357,555,000 238,118,850 67%
SUB TOTAL 6,122,840,000 1,232,555,000 585,096,355 47%
7 PUBLIC PROCUREMENT
REGULATORY AUTHORITY
GOT 100,000,000 50,000,000 - 0%
P 2,032,520,000 36,835,194 36,835,194 100%
BF 1,317,188,000 275,000,000 89,336,412 32%
SUB TOTAL 3,449,708,000 361,835,194 126,171,606 35%
8 GOVERNMENT ASSET
MANAGEMENT
GOT 200,000,000 15,400,000 0%
BF 1,378,572,000 120,000,000 0%
SUB TOTAL 1,578,572,000 135,400,000 - 0%
23
9 INTERNAL AUDITOR
GENERAL DIVISION
GOT 300,000,000 - 0%
BF 1,323,050,000 350,000,000 - 0%
SUB TOTAL 1,623,050,000 350,000,000 - 0%
10 NATIONAL AUDIT OFFICE GOT 7,500,000,000 -
P 469,097,486 -
BF 1,654,850,000 500,000,000 343,030,000 69%
SUB TOTAL 9,623,947,486 500,000,000 343,030,000 69%
11 FINANCIAL INFORMATION
SYSTEMS MANAGEMENT
GOT 600,000,000 146,750,000 0%
BF 243,000,000 75,000,000 0%
SUB TOTAL 843,000,000 221,750,000 - 0%
12 GOVERNMENT
COMMUNICATION UNIT
GOT 200,000,000 88,500,000 34,667,800 39%
BF 276,000,000 -
SUB TOTAL 476,000,000 88,500,000 34,667,800 39%
13 ADMINISTRATION AND
GENERAL
GOT 173,500,000 3,500,000 0%
BF 107,000,000 10,000,000 0%
SUB TOTAL 280,500,000 13,500,000 - 0%
14 PLANNING DIVISION GOT 864,000,000 348,375,000 92,300,000 26%
P 27,146,337 - -
BF 1,348,500,000 486,625,000 150,000,000 31%
SUB TOTAL 2,239,646,337 835,000,000 242,300,000 29%
15 TREASURY REGISTRAR GOT 300,000,000 150,000,000 0%
BF 372,800,000 120,000,000 0%
SUB TOTAL 672,800,000 270,000,000 - 0%
16 PUBLIC PROCUREMENT
POLICY DIVISION
GOT 62,500,000 17,500,000 0%
BF 482,000,000 30,000,000 0%
SUB TOTAL 544,500,000 47,500,000 - 0%
17 ZANZIBAR BF 500,000,000 150,000,000 0%
SUB TOTAL 500,000,000 150,000,000 - 0%
GRAND TOTAL 33,597,704,853 4,902,205,444 1,456,163,521 30%
24
CHAPTER FOUR
CHALLENGES AND RECOMMENDATIONS FOR NEXT PERIOD
Challenges
1. Late release of funds delayed the start of some critical activities. The DP disbursements
were received between October and late December, 2012. However, implementation of
some activities went on and the programme was in full swing by the end of December,
2012. As such, actual expenditure will be captured in the next report. The challenges on
delays of operational funds release to components at the beginning of the fiscal year is
anticipated to be resolved under the new government budget cycle whereby, by end of
June, the Government Budget and Appropriation Bill will be approved by the Parliament
for execution from July 1st of each financial year.
2. The absence of the PFMRP GoT Secretariat to Support coordination. Given the absence,
the component managers showed dedication to ensuring activities were undertaken,
challenges addressed and information shared in TWGs and adhoc meetings.
Recommendations for next period (Jan – June 2013)
1. To build on the pace of PFMRP implementation, TWGs will continue to meet on a
regular basis to review emerging implementation constraints. Information sharing is to be
enhanced for smooth coordination to streamline Action Plan and Cash Flows.
2. Components are encouraged to undertake comprehensive capacity assessment in terms of
working tools and technical skills for the work load and nature of activities as per
milestone targets.
3. Linked to above, all stakeholders will begin to prepare the ground work (agreements) on
the possible revision of targets in the M&E framework so as to ensure that the process is
completed in
4. Given that a number of reform areas are dependent on legislative amendments, the TWGs
will endeavor to list their pending respective legislative so that top management can be
informed to take appropriate action.
25
It is anticipated that flow of operational funds to components will improve in the third quarter
and thus implementation pace will have fully picked up. Government is committed to strengthen
and improve coordination of PFM reform agenda and stakeholders are encouraged to take an
active role to support and embrace results-oriented reforms interventions. The DPs, basket fund
and project contributors, share a common interest in ensuring synergy of efforts and resources in
a view to facilitate a smooth implementation of the programme.
An important development and exercise for the next period will be the repeat (third) assessments
of the PFM system at both central and local government through the PEFA assessments. The
GoT, jointly with the DPs, is committed to applying PEFA as a means of monitoring
improvements in Public Finance Management (PFM) in the country. The assessment process and
the PEFA report will be monitored and endorsed by the PFMRP through the Joint Steering
Committee (JSC) with PEFA secretariat verification checks along the process.
26
Annex A1
PROCUREMENT MID-YEAR PROCUREMENT REPORT
FOR FY 2012/13
A: CONSULTANCY SERVICES
S/N Description Local (Tzs) Foreign
(Tzs)
Total
amount
(Tzs) Sel
ecti
on
Met
hod
Implementation status as
on 31th December, 2012
1.01 Development, installation and operationzalize of a
non taxed revenue collection system
- 58,000,000 58,000,000 IC Draft of TOR done
1.02 Undertake a study to identify major revenue
sources at LGAs
- 150,000,000 150,000,000 QCBS Not initiated
1.03 Undertake 10 PER thematic studies conducted - 80,000,000 80,000,000 CQ Not initiated
1.04 Revise Standard Bidding documents and other
Procurement Implementation tools in line with
PPA, 2011
- 36,350,000 36,350,000 IC EOI received on 5.12.2012,
short listing process on
progress
1.05 Carry out procurement audits to determine the
level of compliance to the PPA
-
934,750,000
934,750,000
IC EOI received on 5.12.2012,
short listing process on
progress
1.06 Survey and update database on average prices of
goods and services in collaboration with GPSA
- 55,900,000 55,900,000 IC EOI received on 5.12.2012,
short listing process on
progress
27
1.07 Prepare JAST II and AMP user guidelines and
disseminate
115,000,000 - 115,000,000 ISS Not initiated
1.08 Conduct Training Needs Assessment for TRs - 142,800,000 142,800,000 QCBS Not initiated
1.09 Conduct capacity and training needs assessment
for Procurement and Supplies Staff in the
Government Sector
19,000,000
159,000,000
178,000,000
QCBS Draft TOR prepared
1.10 Develop human resource structure for
procurement and supplies staff in the public sector
8,000,000 65,000,000 73,000,000 CQ Not initiated
1.11 Preparation of Public Procurement Policy 10,000,000 33,000,000 43,000,000 On-
Going
On-going
1.12 Review public procurement systems - 20,000,000 20,000,000 IC Not initiated
1.13 Provide Consultation and training on debt
management legal framework
- 278,000,000 278,000,000 QCBS Not initiated
1.14 Development of Assets Management Policy 15,700,000 150,000,000 165,700,000 QCBS RFP Submitted to user dpt
1.15 Valuation of Government assets 15,700,000 866,000,000 881,700,000 QCBS On-going
1.16 Uploading 16 MDAs in EPICOR 16,000,000 50,000,000 66,000,000 SS RFP Submitted to user dpt
1.17 Review and streamline Risk Management process
in PFA
-
71,000,000
71,000,000
CQ Preparation of TORs
1.18 Conduct mapping exercise on software and
hardware infrastructure
155,000,000 157,000,000 312,000,000 QCBS Contract Preparation
1.19 Develop MoF communication strategy 200,000,000 66,000,000 266,000,000 QCBS RFP Submitted to user dpt
28
1.20 Conduct TNA and mapping exercise for PFM
training
15,000,000 80,000,000 95,000,000 CQ Not initiated
1.21 Conduct annual financial Audit - 45,000,000 45,000,000 CQ Not initiated
1.22 Conduct annual procurement Audit - 50,000,000 50,000,000 CQ Not initiated
1.23 Conduct Surveys to ensure the KRA teams and
JSC Members are actually working
-
88,000,000
88,000,000
CQ Preparation of TORs
1.24 Undertake study and review the system and
process of fund transfers to MDAs, RSs and
LGAs
- 224,000,000 224,000,000 QCBS Contract Preparation
1.25 Train internal auditors on how to audit
development projects
- 20,000,000 20,000,000 IC Not initiated
1.26 Facilitate 3 stakeholders workshop on the new TR
draft Bil
- 15,000,000 15,000,000 IC Not initiated
1.27 Facilitate consultative meeting with key
stakeholders to identify legislative and policy
supports
- 14,000,000 14,000,000 IC Not initiated
1.28 Facilitate PFMRP Co-ordination Unit - 700,000,000 700,000,000 IC Not initiated
1.29 Improvement of Financial reports in LGAs - 200,220,000 200,220,000 QCBS Will be undertaken
internally. Justification to
be submitted
29
1.30 Set out systems to ensure proper management and
control of revenue collections and reporting in the
LGAs
-
169,000,000
169,000,000
QCBS Draft TOR prepared
1.31 Development of Debt Management Policy - 263,200,000 263,200,000 QCBS Not initiated
1.32 Engage a consultant for the development and
implementation of the plan (to move from IPSAS
Cash Basis to IPSAS Accrual)
- 50,000,000 50,000,000 IC Not initiated
1.33 Build capacity on development of business
operations and support for the Government IFMS
-
202,520,000
202,520,000
QCBS On-going
1.34 Train IFMS end users on the upgraded modules - 94,000,000 94,000,000 SS Not initiated
1.35 Construction of two office buildings 400,000,000 - 400,000,000 On-
going
On-going
1.36 Train 200 auditors on Risk based audit - 154,000,000 154,000,000 CQ Not initiated
1.37 Train 100 auditors on IT audit - 146,000,000 146,000,000 IC Not initiated
1.38 Conduct special audit of National budget - 123,000,000 123,000,000 CQ Not initiated
1.39 Establish system (electronic database) for
tracking ongoing and outstanding audit
recommendations
- 150,000,000 150,000,000 QCBS Not initiated
1.40 Develop and implement Zanzibar PFMRP Strategy - 500,000,000 500,000,000 QCBS Not initiated
30
B: GOODS
S/N Description Local (Tzs) Foreign
(Tzs)
Total
amount
(Tzs)
Select
ion
Meth
od
Implementation status as
on 31th December, 2012
2.01 Servers and computer software for
operationzalization of a non taxed revenue
collection system
- 60,000,000 69,000,000 NCB Not initiated
2.02 Information technology and office equipment - 175,000,000 175,000,000 NCB Not initiated
2.03 Information technology and office equipment - 12,000,000 26,500,000 NCB Not initiated
2.04 Furniture - 6,000,000 6,000,000 NS Not initiated
2.05 Information technology and office equipment - 18,000,000 19,500,000 GPSA Not initiated
2.06 Scientific Equipment - 9,000,000 9,000,000 NS Not initiated
2.07 Information technology and office equipment - 45,000,000 GPSA Not initiated
2.08 Office equipment and furniture - 6,500,000 GPSA Not initiated
2.09 Motor vehicles 100,000,000 100,000,000 NCB Evaluation of Bids
2.10 Motor vehicles 100,000,000 100,000,000 NCB Not initiated
31
C:NON- CONSULTANCY SERVICES
S/N Description Local (Tzs) Foreign
(Tzs)
Total amount
(Tzs)
Sel
ecti
on
Met
hod
Implementation status as
on 31th December, 2012
3.01 Acquisition of software and installation
of Assets Management(tracking)
software-ASSET AUDITOR
4,000,000 118,000,000 122,000,000 NCB Not initiated
3.02 Update SBAS tool to enhance
resources allocation
- 20,000,000 20,000,000 On-
going
Not initiated
3.03 Acquisition of audit software tools and
license fees
- 140,000,000 140,000,000 NCB Not initiated
3.04 Installation and connection of gadgets
for Wide Area Net work to regional
Offices
- 177,000,000 177,000,000 NCB Preparation of schedule of
requirement on progress
3.05 Install and service set up and
connection of the system
- 79,000,000 79,000,000 NCB Not initiated
3.06 Upgrading of Epicor from version 7.3.5
to version 9.05 with three additional
modules
- 350,000,000 350,000,000 SS Not initiated
32
D: WORKS
S/N Description Local (Tzs) Foreign
(Tzs)
Total amount
(Tzs)
Sel
ecti
on
Met
hod
Implementation status as
on 31th December, 2012
4.01 Refurbishment of Zonal offices in
Arusha, Iringa and Mwanza
100,000,000
- 100,000,000 NCB Not initiated
4.02 Construction of two office buildings
7,000,000,000
- 7,000,000,000 ICB Sumbawanga 6%, Dodoma
20% of works
accomplished
4.03 Construction of office accommodation
in Dodoma Sub-Treasury
3,500,000,000
- 3,500,000,000 On-
going
95% of construction
completed
33
Annex 2: PFMRP SEMI-ANNUAL REPORT 2012/13
PFMRP IV M&E RESULT FRAMEWORK 2012 – 2017
STATUS AS AT 31 DECEMBER 2012
KRA 1: Revenue Management
CODE: MILE STONE DESCRIPTIONS STATUS COMMENTS ON THE STATUS
RESPONSIBLE
COMPONENT
Output 1.1: Improved quality of forecasting of fiscal aggregates for three years on a rolling basis
1.1.1 Study on forecasting targets and actual revenue
collection by June 2013
Pending Pending subject to the review of the milestone. The
supervision mission of Sept 2012 agreed that there is a
need to review Output 1.1 (June 2013) (no budget
envisaged) and that there is a need for reviewed
milestones and activities to be formulated.
PAD
1.1.2 Recommendations from study on forecasting targets
and actual revenue collection informs budget
preparations for budget 2014/15.
Pending Pending subject to the review of the output and the
milestone above.
PAD
1.1.3 A team of trainers in revenue forecasting developed
by June 2014 (The milestone to be reviewed in line
with recommendation from the study)
On track Target within reach. Priority will be given to those
MDA’s with higher revenue potential (5 MDA’s
suggested to be chosen (including MEM and MNRT).
Training for LGA’s is also found to be very important,
but potentially also costly. With limited resources, there
PAD
34
is need for prioritization and possibly sequencing on
LGA level. Ambition is to train (abroad) 2 persons
from MoF and 2 from TRA in order to hold training
sessions for other staff in-house.
Output 1.2:The Government improves efficiency in domestic revenue mobilization both at the policy and the administration levels by
updating legal instruments towards international best practices
1.2.1 The study on Non Tax Revenue (NTR) -“Integration
and Harmonization of Revenue Collection Systems”
completed by November 2013.
On track Non-tax revenue study is progressing. An inception
report has been discussed with key stakeholders
(income-generating MDA’s).
PAD
1.2.2 Submission of a bill to Parliament to enact Tax
Administration Act for the purpose of establishing a
common tax procedure among different taxes
collected by Tanzania revenue authority (TRA) by
November 2013
On
Track.
Cabinet approval process is on-going. Comment from
first presentation incorporated for second round
presentation to Inter-ministerial Technical Committee
(Permanent Secretaries). It is expected that Cabinet
approval and Attorney General verification will be done
early in third quarter for the draft Act to be submitted to
Parliament in April, 2013. ( These activities are
supported by Norwegian Funding)
PAD
1.2.3 Review laws, rules and regulations for local
government revenue system to improve LGA own
sources in line with best practice by June, 2016
On-Track The review of LGA legislation is treated below in
output 1.3
PMO-RALG
1.2.4 Take policy action to improve revenue mobilization On-Track Target within reach. MNRT
35
from natural resource sectors by June, 2014
1.2.5 The action plan to implement the recommendations
from review of non tax collection developed and
implemented by June 2016
At risk Milestone needs to be revised. Agreed to include an
interim milestone in order to track progress, so that the
action plan should be developed by June 2014, while
implementation of the plan is still assessed in 2016.
PAD
1.2.6 Computerized revenue collection to at least 50% of
participating MDAs and LGAs by 2016
On track A clearer definition of computerization is required
while MDA’s and LGA’s clearly see the need for
increased use of ICT as collection method. The non-tax
study (see above milestone) partly addresses the issue,
yet the milestone needs to be revisited once the study is
finalized and the action plan developed.
According to MNRT, the TORs for the non-tax revenue
collection study (photographic) were developed using
OC budget and shared with MoF - Planning Division. It
should be noted that a non-tax automated system for
hunting collection has been in use since July 2012
financed by OC funds.
PAD/MNRT
1.2.7 New TR's Bill presented to the Parliament by June
2013
On Track The draft has been sent to Cabinet for an initial review. TR
1.2.8 150 Parastatals' Act Reviewed to be in line with the
New TR Act by June 2014
On Track Once the TR bill is passed the Review of individual
parastatals’ Acts will begin. However, areas of conflict
TR
36
between TR Act and the various legislations have been
identified.
1.2.9 TR's Office Capacities enhanced by June 2015 On Track TR has requested approval of 50 specialized staff on
top of the current 56 staff as the organizational structure
provides for 205. The need for a medium and long-term
capacity development, office retooling and training plan
was underlined.
TR
1.2.10 M& E system for Parastatals reviewed and
implemented by June 2015
On track There is no progress on this milestone as the TR bill is
in process. However, it was recommended that TR
reviews this milestone together with 4.4.3 and 4.4.4 as
these three milestones seem to refer to the same
monitoring framework/M&E system
TR
1.2.11 Review the current system of tax exemptions with the
value-added Tax (VAT) regime and amend the VAT
Act with a view to be in line with international best
practices by November 2014
On Track The process of amending the VAT act is progressing
with TA being provided by IMF (missions in July and
Oct 2012). The revised Act is expected to be approved
by cabinet by November 2013. It is recognized that
incorporation of changes in the FY 2013/2014 budget
will be unlikely. It has further been decided to conduct
a broader PER on the costs and benefits of tax
exemptions. This study will probably be available from
May/June 2013.
CPAD
37
Output 1.3: Strengthened capacity of local government authorities to collect revenue by 2015
1.3.1 Completed assessment and evaluation of revenue
potential for major sources of revenue to all LGAs by
June 2014
At risk The draft ToRs for hiring a consultant were prepared.
Given the limited budget, it was found not possible to
assess all sources in all LGA’s. As such, a
representative sample selection is being considered and
the PMORALG will undertake the assessment in house.
PMO-RALG
1.3.2 PMO - RALG staff and Finance Management Officers
at RS are trained in tax revenue plans and budgets to
spearhead LGAs tax reviews and reforms, June 2013
On Track PMORALG is in contact with TRA about using
consultants from the Tax Training Institute to carry out
the training in revenue plans and budgets. Budget
constraints might put the milestone at risk.
PMO-RALG
1.3.3 Local Authorities Tax administration teaching and
practice modules established and TOT completed for
all finance management staff at the regional levels.
At Risk This activity depends on the activity above concerning
Training through TRA
PMO-RALG
1.3.4 Four (4) revenue accountants, 3 Council management
team members and 1 FMO from each LGA and RS are
trained on own source revenue management in every
two years.
Pending The planned training on own sources of revenue will
only start after the study/assessment is done
PMO-RALG
1.3.5 Establishment of known and clear revenue data base
by each source of revenue, presence of trained
personnel and a clear follow up arrangement at
PMORALG and RS levels by June, 2014
At risk The database is supposed to be developed based on the
study outcomes and will encompass sources, rates,
potentials, budget, and collection methods among
others. However, the activity is only scheduled to be
PMO-RALG
38
implemented in the next FY.
1.3.6 Completed study on the effectiveness, relevancy and
sufficiency of the provisions of the Local Government
Finances Act No. 9 by June, 2013
At risk The PMO-RALG directorate of Legal services has
started to review Local Government Finance Act. By
Dec 2012, there was taskforce appointed to analyze the
weaknesses of the current Local Government Finance
Act.
PMO-RALG
1.3.7 A bill for an act to amend the Local Government
Finances Act No.9 of 1982 is finalized and submitted
to the Cabinet by February 2014
At Risk This activity depends on the finalization of the study on
the effectiveness, relevancy and sufficiency of the
provisions of the Local Government Finances Act.
PMO-RALG
Output 1.4: Increase of Donor funding that flows through the exchequer system by 2016
1.4.1 National framework for managing development
cooperation (JAST) be reviewed and put in operation
by December 2012
Delayed The Development Framework Contract - DCF
(successor to JAST I) process was on-going but the
need for broad consultations has required that the
deadline is rescheduled to Nov 2013.
EFD
1.4.2 Revised JAST and AMP user guideline clearly
communicated to both parties by December 2012
Delayed The content of the proposed revision of DCF and AMP
needs to be further defined and the milestone should
possibly be split into two separate activities – one is the
AMP guidelines, which are updated every year and
needs to continuously be disseminated to DP’s, MDA’s,
LGA’s, RS’s, NSA’s etc. The other activity being the
action plan for the DCF.
EFD
39
1.4.3 Analysis of the trends of the direct project fund
portfolio disbursed via exchequer system published
and shared annually by June 2015
On Track The annual report of trends will be available already
this year (target was 2015) as it can now be generated
from the AMP and published every year in October.
EFD
KRA 2: Planning and Budgeting:
Output 2.1: Strengthened capacity of MDAs, RSs and LGAs in implementing program based budgeting by June 2016.
2.1.1 All Sub programs, program objectives and
performance indicators defined by December 2012
On Track Programs and sub-programs have been (tentatively)
defined and objectives, outputs and performance
indicators were developed from MKUKUTA II and
FYDP
GBD
2.1.2 Chart of Accounts modified to accommodate program
based budgeting
Achieved Done GBD
2.1.3 MTEF reviewed to make program based budget
compatible by September 2014
On Track Target within reach GBD
2.1.4 Progress on the PB Action plan implementation On Track Action Plan to move to PBB (Program Based
Budgeting) is in place and the work has started.
GBD
2.1.5 Completed phased training for all MDAs and RSs by
June 2014
On track Will be conducted next year GBD
2.1.6 Completed phased training for all LGAs by June 2014 On track Refer action plan GBD
Output 2.2:Increased effective utilization of Planning and budgeting tools by 2016
2.2.1 MTSPBM reviewed by June 2013 On track SBAS tool updated and used for 2013/14 budget
preparation.
GBD
40
2.2.2 Sixty MDAs, 21 RSs and 133 LGA trained in
MTSPBM by June 2014
On track Review will be followed by change of manual and
training of stakeholders. Training will be done by
facilitation team;
GBD
2.2.3 Reviewed MTSPBM to be applied during FY 2013/14 On track Some of the features MTSPBM has been applied for
FY 13/14. Review is expected in the last quarter of the
financial year because of new budget cycle has affected
completion of the activity.
GBD
2.2.4 Annexes to budget book volume II for Executive
Agencies completed by June 2014
On Track GoT will introduce more details on expenditures of
public institutions that partially depend on GoT budget
such as TRA, University, etc
GBD
2.2.5 Action plan on implementation of recommendations
on budget legal framework completed by June 2013
On track Studies have been undertaken in view of a specific
budget law.
GBD
2.2.6 At least 10 PER Main Dialogue meetings held by June
2016
On Track PER Main dialogue process conducted that culminates
at the annual meeting held in November 2012.
GBD
2.2.7 Phased training to MDAs, RSs and LGAs Budget
Committees on resources prioritization and planning
On Track Training on resources prioritization and planning was
undertaken for members of budget committee in
selected RSs and LGAs
GBD
2.2.8 Mechanism for quality assurance of Quarterly Budget
Performance Reports (level of detail, timeliness,
accuracy, consistency and usefulness to decision
makers, as well as for budget transparency to citizens)
On track It was agreed to take PEFA study 2009/10 and PEFA
methodology paper as starting point. Upcoming PEFA
study March 2013 guided by a Task Force includes
MoF staff for capacity building.
GBD
41
established by June 2013
Output 2.3: Strengthened capacity of LGAs for MTEF preparation by 2015
2.3.1 Proposal for budget information to be included in the
Budget guideline to be submitted to National Budget
Guideline committee by October annually.
Pending This milestone has to be reviewed PMO-RALG
2.3.2 Recommendations of various studies on LGAs budget
allocation formula reviewed by December, 2012
Delayed The consultancy to conduct a review study is yet to be
initiated to enable revision and full application of LGA
budget allocations formulae. The ToRs are to take into
account the intended transition to PBB. The funding of
this activity was delayed.
PMO-RALG
2.3.3 Agreement on improvement of LGAs budget
allocation formulas among the sector Ministry
(PMORALG, MOF, PO-PSM and Sectors) completed
by June 2013
At risk Delayed awaiting completion of Recommendations of
various studies on LGAs budget allocation formula.
However, no funds were received for this activity by
Dec 2012. Consultation done with PMO – RALG
technical advisors to see how best the activity can be
conducted.
PMO-RALG
2.3.4 All LGAs budget allocation formulae reviewed by
June, 2014
Pending Awaiting completion of recommendations of various
studies on LGAs budget allocation formula.
Implementation is scheduled for next FY.
PMO-RALG
2.3.5 All reviewed LGAs budget allocation formulae applied
in the budget preparation during 2014/15 for the FY
On track Awaiting completion of recommendations of various
studies on LGAs budget allocation formula.
PMO-RALG
42
2015/16 budget. Implementation is scheduled for later years.
2.3.6 Monitoring arrangements are in place for measuring
deviations in actual releases against all formula-based
allocations to LGAs by June 2015.
On track Awaiting completion of recommendations of various
studies on LGAs budget allocation formula.
Implementation is scheduled for other FY
PMO-RALG
KRA 3: Budget Execution, Transparency and Accountability
Output 3.1 Improved public procurement performance by PEs by June 2015
3.1.1 Annual PPRA audit results confirm positive trend on a
yearly basis
On Track Annual audit results indicate positive trend based on
compliance (status 2012: 74%)
PPRA
3.1.2 Revised Procurement Implementation and monitoring
tools issued by December 2013
On track Implementation and monitoring tools based on new
regulations prepared.
PPRA
3.1.3 New Public Procurement Act, 2011, Regulations and
Tools disseminated to major PE's and other
stakeholders by December 2015
On Track Procurement Regulation and implementation tools will
be revised to align with the new Act expected to be
ready by late 2013.
PPRA
3.1.4 Procurement Plans aligned with MDAs, LGAs and
Parastatals Institutional Strategic Plans by June 2015
Achieved It has been made mandatory that Public Procurement
Plan to be part of Strategic Plan and Budget Plan.
PPRA
3.1.5 Value for money procurement enhanced by
Framework contracts for common use items and
services by June 2017
On Track The on-going Audit has conducted Value for Money
Audit for 30 PEs. Selection of consultant to undertake a
study on average pricing as part of the activity will be
completed on May 2013.
PPRA
3.1.6 PPRA operational and outreach capacity strengthened
by June 2014
On Track There is on-going recruitment of staff and providing
training to existing staff. Moreover, PPRA expects to
PPRA
43
open zonal offices and employ up to 141 staff from
current 52 staff. Recruitment of 1 manager for
performance contracts undertaken.
3.1.7 All (393) PEs will have a fully functional PMIS as a
reporting tool for procuring entities to report back to
PPRA by Nov 2014
On Track About 302 PEs have been connected. PPRA has a plan
of providing tender portal, which is within PMIS
(funded by AfDB).
PPRA
3.1.8 e-procurement will start functioning as pilot stage by
Nov. 2016
On Track A feasibility study was carried out to move from paper
based to e-procurement. Inputs provided to MoF on
regulations on e-procurement. The draft TOR have
prepared for consultancy on details of e-procurement
system.
PPRA
3.1.9 393 PEs audited by June 2013 Achieved Done with the exception of PEs within newly
established districts.
PPRA
3.1.10 Follow up audit of 100 PEs to be done annually by
2016
On Track With expected zonal offices and staff easy to make
follow up audit.
PPRA
3.1.11 Annual Procurement Performance Evaluation Report
prepared and published annually
On Track Issued all reports on all 106 PEs and also VfM audits
for 136 projects in 30 PEs. Actual Annual procurement
performance evaluation report has been submitted to
the Minister.
PPRA
Output 3.2: Strengthening public sector procurement by June 2015
3.2.1 Action Plan for implementing Public Procurement Act Delayed Pending written action plan. Collaboration between PPRA
44
is developed by December 2012 (Milestone to be
revised after finalization of action plan)
PPPD and PPRA will be necessary to draw this action
plan. To implement the PPA, PPRA will conduct
training with government procurement service agents,
and information will be disseminated, including on
their website.
3.2.2 New public procurement regulations prepared and
issued by June 2013
On Track Parliament passed the law in 2011 and the draft
regulations prepared which are currently with the
Attorney General’s office for verification. The Minister
will then finalize the regulations, present them before
the Parliamentary Committee responsible for Finance
and Economic Affairs. The regulations become
effective after being gazetted.
PPD
3.2.3 Procurement training needs assessment exercise
completed by June, 2013
On Track A ToR has been written for a consultant to do the
training needs assessment exercise
PPD
3.2.4 [300] procurement staff trained on public procurement
by June 2017 as per TNA.
Pending The numbers and type of training will be revisited
depending on the findings and the recommendations of
the TNA.
PPD
3.2.5 Strategy on public procurement human resource
management developed and disseminated by June,
2015
Pending Focus on strategy to be revised to focus on how
organizational structures within procurement
management units should look. However, there is a
proposal to correctly phrase the milestone as “Strategy
PPD
45
to develop PMU structures in Public Sector by June, 2015”
3.2.6 Procurement and supplies staff database maintained
and updated by December, 2015
On Track The staff database already exists and has registered
about 824 procurement and supplies staff in central and
local government. This is a continuing task as it will be
updated periodically.
PPD
3.2.7 National procurement policy draft is finalized by June
2013
On Track The national procurement policy draft will explain the
PPA and covers central and local government. A
consultant has been hired from University of Dar es
Salaam and has submitted a framework paper.
PPD
3.2.8 Stakeholders’ comments incorporated by June, 2013
On track After discussion of framework paper, a first draft for
comments will be circulated. Comments will be sought
using meetings, websites and newspapers.
PPD
3.2.9 PPDs' office and staff capacity enhanced by June, 2013 On Track PPD will offer training on public procurement policies
for those with relevant responsibilities. PPD currently
has 18 staff. Training foreseen for following quarters.
PPD
3.2.10
-
3.2.17
The following milestones are related to the final
national procurement policy:
20 members of PPD staff equipped with skills on
public policy formulation, implementation and
evaluation by June, 2013
National procurement policy developed and shared
On track Waiting for the processes on draft procurement policy
to be finalized.
PPD
46
by December, 2014
National procurement policy (NPP) strategy
developed and implemented by June 2015
Printing and uploading the NPP on the website by
June, 2015
National procurement policy and procurement law
synchronized by June, 2015
Monitoring the implementation of the National
procurement policy by June, 2015
Evaluation and feedback of the implementation of the
National procurement policy by June, 2016
1000 Stakeholders acquainted with the National
procurement Policy by June, 2016
Output 3.3:Strengthened capacity of MDAs Rs and LGAs in Cash Management by 2015
3.3.1 600 staff of MDAs and LGAs Trained on cash
Management using standardized materials by June 30
2014( Milestones to be reviewed and aligned after the
East AFRITAC recommendations on Cash and
Banking Arrangement Mission)
On Track Milestone is within reach. However the focus for the
period was for staff to update database.
ACGEN
3.3.2 Six bank accounts operated by each LGA by
December, 2013
Achieved Each LGA operates six accounts ACGEN
47
Output 3.4: Strengthened Public Debt Management Capacity by 2015
3.4.1
The agreed actions arising from the Feb. 2012 World
Bank debt management report shared with key
stakeholders by July 31, 2012
Achieved The debt management report from WB Debt
management mission and action plan on steps towards
establishment of Debt management has been shared
within GoT to all relevant stakeholders (technical and
national debt committees). Accomplished by Sept 2012.
PAD
3.4.2 Debt management policy developed and shared by
June 2013
At risk Currently, awaiting the approval of new MoF structure
from PO-PSM to undertake activities. There is a need
to consider possible conflicting legal frameworks under
PPP Act and Loans and Guarantees Act. The unit has a
policy, the idea was to develop a strategy and not a
policy (Milestone has to be revised)
PAD
3.4.3 Capacity of 50 Public Debt management staff
enhanced by June 2014
At risk For ACCGEN part, Debt Management training needs
will be decided after establishment of the debt
management office (DMO). This milestone will kick
off in FY 2013/14
PAD,
ACCGEN
3.4.4 Reviewed Government Loans, Guarantees and Grants
Act by June 2014
At risk Currently, awaiting the approval of new MoF structure
from PO-PSM to undertake activities. There is a need
to consider possible conflicting legal frameworks under
PPP Act and Loans and Guarantees Act.
PAD
3.4.5 Debt Management department established by June On Track Currently, awaiting the approval of new MoF structure PAD
48
2016. from PO-PSM to undertake activities
Output 3.5: Improved Integrity and content of government financial statements and migration from IPSAS cash Basis to
IPSAS accrual is progressing in accordance with the plans.
3.5.1 Completed review of the IPSAS guideline issued by
PMORALG in 2008/09 to accommodate the recent
IPSAS updates by June 2013
On Track The ACCGEN, DGAM, RSs and LGAs clearly
demonstrated, (under ACCGEN leadership) that work
was roughly on track to transition to accrual
accounting. This strategy embraces an analysis of
strength and weaknesses of the past implementation of
IPSAS accrual at local level. However, there is a need
to relook this milestone as an Accounting manual is still
necessary while no IPSAS guideline available.
ACGEN
3.5.2 Training to MDAs, RSs and LGAs accounting officers
to develop awareness on IPSAS Accrual by 2013
At risk Training will be undertaken in the FY 2013/14. As for
the funds available now the priority is to train staff
directly involved in the preparation of Financial
Statements in the MDAs involved in the project so that
target on IPSAS accrual accounting is met.
ACGEN
3.5.3 Capacity building to 250 staffs from MDAs, RSs and
embassies to enhance skills in IPSAS Accrual by 2014.
On track Target within reach ACCGEN
3.5.4 Public Finance Act.No.6 of 2001 and regulations
reviewed by 2016
On track A draft of the revised PFA is ready and currently is
being circulated for Stakeholders’ comments since
August 2012.
ACGEN
49
3.5.5 Consolidated template of financial statements to
include MDAs, Rs, LGAs, Controlled entities and
GBEs developed by June 2016
On track Up to Dec 2012, the work on the Financial Statements
templates was still going on .It is expected that by June
2013 the templates for MDAs and Rs will be ready.
ACGEN
3.5.6 250 government accountants in MDAs /LGAs trained
in IPSAS accrual and accrual modules for Epicor by
September 2013
achieved Done ACGEN
3.5.7 Plan for migration towards IPSAS Accrual accounting
is completed by December 2013.
On track Roadmap and consolidated tree is in place ACGEN
3.5.8 Plan is approved for execution and stakeholder
information sessions have been completed by January
2014
On track Plan has been approved and awareness been done to
some of the stakeholders (e.g. PAC members). Other
groups will follow
ACGEN
3.5.9 All legislative and policy supports have been identified
by 31st Dec.2014
On track Some of the legislative and policy supports have been
identified as accounting policy, PFA, Accounting
manual, LGF act and TR act.
ACGEN
3.5.10 Milestones for the transition have been identified and
approved E.g. Public Finance Act No.2001 and
Regulations amendments by October 2014
On track Some milestones have been identified ACGEN
3.5.11 Plan to integrate all Rs and LGAs operation into
centralized IPSAS accrual architecture is completed
and PMO-RALG is fully engaged as stakeholder by
31st Dec.2014
On track Roadmap and consolidated tree is in place ACGEN
50
Output 3.6: Improve accountability in management of Government asset management for supporting migration to IPSAS
Accrual
3.6.1 Uploading of 16 additional MDAs in EPICOR by
December 2012
Delayed Waiting for approval of ToRs to start uploading the 16
MDAs, which were valued before the division entered
into the programme (PFMRP).
NOTE: 36 MDAs were valued and but only 20 were
uploaded in EPICOR, these was before GAMD joined
the programme.
GAMD
3.6.2 Asset Management (tracking) software acquired by
March 2013
On Track ToRs drafted and shared. Will depend on access to
financial resources at due time.
GAMD
3.6.3 40 staff(25) regional heads(RSVs) and 15 from HQ)
trained on asset management function by December
2013
On track Training programme prepared, awaiting release of
funds
GAMD
3.6.4 Asset Management Policy prepared and submitted by
June 2015
On Track The ToRs for the drafting of the asset policy
management have been shared. They are approved at
DGAM level, and are circulated among other
stakeholders.
GAMD
3.6.5 Valuation of Government assets in 34 MDAs and Rs
completed by June 2016
On track ToRs for consultancy drafted and waiting for fund
release to embark on tender process.
NOTE: The 5-year valuation plan prepared to value government
assets in 7 MDAs on average each financial year
GAMD
51
3.6.6 Progress against target reported annually On track Target within reach (to be reported at the end of FY) GAMD
KRA 4: Budget Control and Oversight,
Output 4.1: Increased coverage and quality of the internal audit functions by 2016
4.1.1 Operational plan developed and approved by June,
2013
On track Operational plan for 2012/13-2016/17 developed and
awaiting approval from PS.
IAG
4.1.2 Internal Audit manual/guidelines, standards and
quality assurance improvement programme in line
with International Standards will be in place by June,
2013
On track Manuals for LGAs and MDAs have been reviewed by
consultants (August 2012) to ensure consistency with
the International Practice Framework (IPPF), training
has been provided on IPPF and inception report
produced for guidelines on quality assurance.
Stakeholders’ consultation conducted.
IAG
4.1.3 Effective internal audit units and audit committees
established to all MDAs and LGAs by June, 2016
On track Survey has been conducted to identify the weaknesses
of MDAs audit committees (members drawn from
management teams) comprise of lack of understanding
of role of committees, training and charters explaining
responsibilities and duties.
IAG
4.1.4 The Pilot stage of Computerized Audit will be
finalized by June 2014
On track Staffs were trained on payroll software. Acquisition of
the audit software is in process. Pilot in 3 MDAs and 2
LGAs would be conducted by June 2013.
IAG
4.1.5 Computerized Audit in place by June 2016. On track Target within reach. IAG
52
4.1.6 550 internal auditors and other stakeholders trained in
risk management process and risk based audit by June,
2017.
On Track Needs assessment undertaken and training plan
developed (July 2012), 20 champions trained by JICA
on audit systems (drawing on existing internal audit
handbook and process guide). In addition, 20
champions trained on risk management. Guidelines on
implementation of institutional risk management
framework being developed.
IAG
4.1.7 Technical Audits are conducted for 70 Projects by
2016
On track This milestone consists of 3 activities: undertaking the
baseline survey; consultant to undertake the training for
IAs who will conduct the technical audits (recruitment
ongoing) and undertaking the technical audits (none as
at Dec 2012). The baseline survey and the process to
recruit the consultant are ongoing.
IAG
Output 4.2: Strengthened External audit functions by 2016
4.2.1 The committee report on needs of legal amendments
(existing laws) to contribute towards reaching level 3
submitted to the attorney General and awareness
programs conducted by December 2012
Delayed Report ready to be submitted to the Attorney
General’s Office. Legal officers have been working
on laws which impede independence of the NAOT
with a view to incorporating independence of the
NAOT into the constitution using Uganda’s
constitution as an example. Other issues relate to
NAOs budget, recruitment and salary structure.
NAOT
53
An AFROSAI-E team undertook an assessment of
NAO`s performance in September 2012, focusing on
institutional assessment, performance audits and
regularity audit
4.2.2 50% of auditors to be accommodated in NAO own
offices by 2014
On Track The CAG has accommodated its auditors in 11 (9
owned and 2 rented) of the 25 regions. Some funds
have been received for construction but are limited.
This should kept under review with increasing staff
numbers
NAOT
4.2.3 300 Auditors trained on Risk Based Audit and 200 in
IT audit by 2014
On track No staff trained by Dec 2012. However, 40 champions
existed before FY2012/13.
NAOT
4.2.4 Two Value for Money audit reports to be produced
each year by NAO staff without technical assistance
from external consultant by 2014.
Achieved 5 performance audits p.a are being carried out using
internal coaching provided by Swedish NAO, providing
a base to build on.
NAOT
4.2.5 300 Auditors trained on international standards of
auditing and full adoption of International Audit
Standards by 2014
On track No training but the existing Champion Group is
practicing (12 people within office plus 3 seconded
from other Government Institutions (TRA and TTCL).
NAOT
4.2.6 Closing of books of accounts for Parastatals
harmonized and audit modalities agreed by 2014.
On track The Treasury Registrar is in charge of parastatals, and
as such NAOT has to follow up with TR on this
milestone. However NAO has played a key role in
determining which institutions are true parastatals and
NAOT
54
this is made complicated by the process of privatization
of state owned companies and GoT majority
shareholdings. Despite these challenges, 176 parastatals
were audited by NAO by Dec 2012.
4.2.7 Audit methodology in line with ISSAIs guidelines
adopted by June 2013
On track Alignment of audit methodology is progressing well,
with guidelines already in place.
NAOT
4.2.8 Scoping study to ascertain the parameters of the
outstanding matters Database is completed by
November 2012
Delayed The scoping study is on-going though details of exact
scope need to be clarified. Given the time constraints,
the assignment to be completed in April 2013.
NAOT
4.2.9 Establish a database that will separate findings
(monetary and non monetary) and recommendations
including by age, and record follow up actions by
December 2013.
Delayed Creation of database is pending completion of scoping
study (see above)
NAOT
4.2.10 200 Auditors trained on audit commanding language
(ACL) and other audit based software by 2014
On track No training undertaken as at Dec 2012. 100 to be
trained between April – June 2013.
NAOT
4.2.11 NAO Headquarter is connected to 10 Regional
offices using WAN by 2014
On track NAO HQ is now connected to all its 10 (owned
buildings) regional offices.
NAOT
4.2.12 Two of five Team mate modules applied in auditing
by October 2014
On track Application of Team Mate modules on track. Action
plan in place to activate four modules with support
from NAO Development project and PFMRP.
NAOT
55
Output 4.3: Improved transparency on audit report (Central, Local and Parastatals levels) to strengthen scrutiny and accountability)
4.3.1 Citizen audit reports available for the 4 General audit
reports by June 2013
On track Preparation of citizen audit is waiting the publication of
the General audit report. Haki Elimu and TWAWEZA
will prepare citizen audit reports and TWAWEZA
maintains the NAO’s website for free. A link to the
citizens report can be put on NAO’s website
NAOT
Output 4.4:Improved Performance of Parastatals by June 2016
4.4.1 Ten (10) Parastatals signed Performance Contracts
with TR by June 2014
On Track All “commercial enterprises”, of which there are more
than 50, are to have performance contracts. The ten
pilot parastatals have been selected based on turnover,
size, strategic importance etc. (further details to be
made available). Contracts will include performance
targets to be measured by the TR, though consistency is
needed with parent MDAs. Among others,
performance incentives are provided for in the 2010 TR
Act.
TR
4.4.2 Database on Parastatals set up and functioning by
December 2014
On track Technical and user-friendliness issues discussed last
year and temporarily have been resolved. Data is
currently being entered into TRIMs (Treasury Registrar
Information System). The system will be deemed fully
functional once it is able to issue reports, now expected
TR
56
by the end of current FY.
4.4.3 Monitoring framework for Parastatals set up by June
2014
On track Establishment of monitoring framework is reliant on
the enactment on the new TR Bill. Given the
timeframe for the Bill there is optimism that the
framework will be set up by June 2014. TR to review
this milestone together with 1.2.10 and 4.4.4 below
TR
4.4.4 Mechanism for measuring Parastatals’ compliance rate
developed by June 2014
On track Performance is to be based on accounts tables and
whether parastatals comply with circulars and
directives issued by the TR, which also conducts
management audits. The new TR Bill includes clauses
on measuring compliance rates. Optimism that the
mechanism to monitor compliance rates will be set up
by the deadline. TR to review this milestone together
with 1.2.10 and 4.4.3 above
TR
Output 4.5: Strengthened Capacity of oversight functions of Parliamentary Accounts Committees by 2016
4.5.1 Capacity building interventions to PACs conducted On track Discussions confirmed that support for Parliamentary
Committees has lagged and requires early attention
during phase 4. Follow up is needed to identify and
agree an appropriate action plan for PFMRP support to
parliamentary committees. First steps in this process
have begun but support needs to be defined and
NAOT
57
coordinated with other stand-alone programs.
KRA 5: Cross-Cutting Issues (Change Management and Programme Monitoring),
Output 5.1: Coordinate Integration, interfacing and rationalization of Government financial systems.
5.1.1 ICT mapping exercise showing location and owners of
all and peri-financial software commenced with
inception report published by December 2012
Delayed The TORs for the mapping were prepared and the
process to select the consultant was on going with
finalization foreseen by Jan 2013.
FISM
5.1.2 Stakeholder coordination meetings held to gather input
and agree on cross functional responsibilities for
financial systems Planning held on by December, 2012
Delayed To follow after the completion of the study. FISM
5.1.3 Sequenced, prioritized and costed action plan to bring
all GoT financial and peri-financial software under one
common Government financial systems architecture
with supporting technical, infrastructure and
management structures completed and approved by the
GoT by June, 2013
At risk To follow after the completion of the study. FISM
5.1.4 Integration/Interfacing plan is engaged and series of
planned actions are being executed and completed by
October, 2015
On track To follow after the completion of the study. FISM
5.1.5 IFMS infrastructure installed to new 34 LGAs, RSs
and PMORALG institutions and connected to central
server at Dodoma and MoF by June 2013
On track All 133 old LGAs and RSs are connected to the IFMIS
system through the Dodoma server network. New 34
will be connected in the next year plan. The planned
PMO-RALG
58
budget is not enough to implement this activity. Once
the fund received, it will be used to procure initial
equipment for installation.
5.1.6 MoF IFMS linked to PMO-RALG IFMS to the
immediate capture of the Approved Budget and all
Exchequer transfers to RSs and LGAs respectively by
June 2013.
On track DFMIS and PMO-RALG indicate that the June 2013
target should be achieved.
FISM/PMO-
RALG
5.1.7 Completed capacity building to key users of IFMS
from all LGAs, RS and PMORALG institutions by
June 2013.
On Track Target within reach but needs attention. PMO-RALG
5.1.8 Audit of IFMIs in LGAs conducted by June 2017 On Track This activity was not planned to be implemented in this
current year 2012/2013
PMO-RALG
Output 5.2: Utilization of EPICOR modules increased from seven to ten
5.2.1 EPICOR system upgrade complete by December 2014 On track Seven (7) modules installed and so far six have been
activated.
ACGEN
5.2.2 ACGEN Staff capacity enhanced by Dec.2014 On track Training on going with 40 staff trained on EPICOR 9 ACGEN
5.2.3 Training for IFMS end users on the upgraded modules
conducted by Dec 2014
On track Training ongoing with 381 end users trained in
EPICOR 9. The MDA training on new version of
EPICOR is planned for completion before June 2013.
ACGEN
5.2.4 EPICOR is able to provide real-time information to all
LGAs on flow of funds by July 2015
On track PMO-RLG and Softech have agreed on how this target
can be met in time.
PMO-RALG
59
Output 5.3: All software development and module upgrades are coordinated with the overarching plans for ICT integration
5.3.1 DFISM is operationalized and controls are put in
place to manage software acquisition and development
by December, 2012.
Achieved Activities are being guided by a 3 year operational plan FISM
5.3.2 DFISM staff capacity enhanced by June, 2015. On track Training for 16 DFMIS staff completed by Dec 2012. FISM
Output 5.4: Improved communication and public access to key fiscal information to stakeholders by 2016.
5.4.1 The Approved National Budget is published on MOF
website by September each year
Achieved Budget was published on the website in September.
2012
GCU
5.4.2 Publish Citizens Budget by November each year Achieved Citizen Budget published in October 2012 GCU
5.4.3 A Year-End Report (budget out turn) comparing the
actual budget execution to the enacted budget is
published on Ministry of Finance website by October
each year
On track The budget outturn report will be produced by adding
annexes in the annual execution report that will reflect
additional information as discussed in the Technical
Working Group (TWG) in the BUDGET DIVISION.
GCU
5.4.4 MoF Communication Strategy developed and
implemented by June 2014
On track Draft communication strategy prepared and is being
shared among stakeholders for comments including
mechanism for information verification, control over
source data and policy support.
GCU
5.4.5 Fiscal Information and Budget Transparency
Publication Cycle developed and implemented by June
2014
On track Milestone to be clarified as TWGs on Budget, CPAD
and GCU did not seem to have details on this
milestone.
GCU
5.4.6 MoF website timely updated by June 2017 On track MoF website updated GCU
60
Output 5.5: Coordination and Standardization of PFM Training Achieved
5.5.1 Training mapping exercise completed by Dec 2012 Delayed Using In-house expertise, ToRs were developed for the
mapping exercise and finalized by Dec 2012. The
questionnaire to be used to undertake the exercise was
also developed. The mapping will cover 29 ministries,
14 regions and 28 district councils from those selected
regions.
DAHRM
5.5.2 Capacity building Plan developed and shared with key
Stakeholders by June 2013.
Pending This milestone will be implemented after the mapping
is completed
DAHRM
5.5.3 Two tracer studies conducted to measure the impact of
training and documented by June 2014 and 2016
Pending Planned for FY2013/14 DAHRM
Output 5.6: PFMRP Component Managers are being guided by detailed multi-year operating plans
5.6.1 All activities are presented for inclusion in PFMRP
annual work plan are presented within the context of a
detailed multi-year operating plans by June 2013
On track A five year operating work plan has been developed
and is intended to be updated when preparing the next
financial years plans. Through TWGs and PMC
meetings the necessary guidance provided to
component managers.
PD
Output 5.7: PFM activities are effectively planned and implemented
5.7.1 Capacity building Plan developed and shared with key
Stakeholders by Dec. 31, 2012
Delayed See above for 5.5.1 PD/DAHRM
61
5.7.2 Training on Change Management and Strategic
Planning completed by Dec.31/13
On track To be implemented in the 3rd
and 4th
Quarter PD
5.7.3 Results Based Management training has been delivered
to 60 PFM RP Component managers by June 30, 2013.
On track To be implemented in the 3rd
and 4th
Quarter PD
Output 5.8: Effective coordination of activities and support provided to the programme implementers
5.8.1 Secretariat procurement process completed by July
2012
Delayed The Secretariat recruitment was done and contract
negotiation for signing was ongoing as at the end of
December, 2012 for 4 out of 6 positions that received
qualified applicants. Re- advertised the post of PFM
expert and M&E specialist in October, 2012.
PD
5.8.2 Secretariat work plan is completed and approved by
JSC by December 2012
Delayed The implementation of this milestone will be done after
hiring of full Secretariat team
PD
5.8.3 PFMRP Co-ordination secretariat facilitated annually. On track Pending contract signing ACGEN, PD
Out Put 5.9: PFM programme oversight and review is being guided by clearly defined milestones derived from an agreed M&E framework
5.9.1 Annual review and amendment of the M&E
framework to ensure ongoing congruence and
relevance annually by Nov 2012
On track The supervision mission was undertaken in Sept 2012
which led to the updating and review of the M&E
framework. (the revised M & E framework is
attached to this report)
PD
62
Output 5.10 All major PFM reforms have been coordinated with and informed by relevant government and DP stakeholders groups
5.10.1 PFM information session completed to disseminate
results of: ICT mapping exercise, ICT Harmonization
Integration Plan by March 2013
Delayed The information session is likely to take place before
June 2013 as some of the elements are not ready such
as the results of the ICT integration mapping (to be
finalized in June 2013.)
PD
5.10.2 IAG action plan, ACGEN’s Plan to transition to
Accrual Accounting
Pending Milestone to be revised IAG ,
AcGEN’s
5.10.3 Minimum of one PFM reform information day
conducted for CSOs , DPs and GoT during Public
Service day annually by Dec.31st each year
On track Information day will conducted in the last quarter. PD
Output 5.11: PFMRP implemented efficiently and effectively through result based management approach.
5.11.1 PFMRP implemented according to annual work plan
and milestones are being met
On track Linked to milestone 5.6.1 (Five Year Work Plan).
There is clearly a shared responsibility with all
participating components in terms or producing timely
information and reports.
PD
5.11.2 Annual supervision mission are conducted by Sept 30
of each year commencing 2012.
on track The supervision mission was undertaken in Sept 2012. PD
5.11.3 Independent program evaluations are completed in
2014
On track Mile stone within reach PD
63
5.11.4 Dialogue structures are working as evidenced by
combined DP/GoT Survey results (Survey 1-March
2013, Survey 2-March 2015 for effective program
implementation improved)
On track TWG dialogues are effectively maintained and produce
mutually beneficial yields for the participants within the
framework of PFMRP. However, the survey will
commence in the fourth quarter
PD
5.11.5 Surveys to ensure that teams (KRA Teams and JSC
members) are actually working completed, March
2013, March 2015 and results informed to JSC for
action.
On Track TWG dialogues are effectively maintained and produce
mutually beneficial yields for the participants within the
framework of PFMRP. However, the survey will
commence in the fourth quarter
PD
Output 5.12: National systems and process for intergovernmental transfer to LGAs streamlined and rationalized
5.12.1 TORs (for Streamlining and rationalizing National
systems and processes for intergovernmental transfers
to LGAs) completed by July 2012.
Achieved Preparation of ToRs was completed by end of July
2012 and advertisement to call for interested
consultants to proposals to undertake mapping was
placed in August 2012.
PD
5.12.2 Mapping commences September, 2012 Delayed The consultant for the mapping study hired early
December 2012
PD
5.12.3 Review and mapping of the systems and processes for
intergovernmental transfers initiated with inception
report finalized by October 2012,
Delayed Based on the delays in completing the selection of
consultant, the inception report is foreseen for Jan/Feb
2013.
PD
5.12.4 Comprehensive and sequenced action plan on a
recommendation of the mapping exercises on the
intergovernmental transfers finalized by June 2013.
On Track The action plan is expected to be prepared and ready
before June 2013.
PD
64
5.12.5 Reports to be produced annually by end September Pending Milestone to be clarified PD
Output 5.13: Strengthened Public Financial Management Reforms in Zanzibar by 2017
5.13.1 Milestones developed and agreed after discussion with
Zanzibar and thereafter decide on the support by
September 2012
Delayed Discussions with Zanzibar are yet to take place as
planned. The intent is to identify a mutually acceptable
and coordinated entry point for PFMRP to support PFM
reform in Zanzibar.
ZANZIBAR
5.13.2 Zanzibar PFMRP Strategy developed by June 2013 On track Target still within reach. ZANZIBAR