the simple problem of schedule performance indices (neutral)
DESCRIPTION
Using Earned Value to measure project performanceTRANSCRIPT
THE SIMPLE PROBLEM OF
SCHEDULE PERFORMANCE
INDICES
Knowing how our project is performing means knowing how our Cost, Schedule and Technical Performance is performing
1
Glen B. Alleman
Lewis & Fowler
Keeping on Pace
If the performance of our project is like cycling, then we plan to ride at a known pace –say 20 mph
If our group maintains the target pace of 20 mph they can look at their watches to determine if we’re on pace to complete our 40 mile ride in 2 hours
30 minutes into the ride we’re still all riding as a group. Nice sustainable pace, we’ll make the 40 miles in our planned time – no problems so far
2
Falling off Our Planned Pace
But some of us are starting to get tired. We’re falling off the back of pace line.
Instead of our planned 20 mph, we’ve dropped to 19 mph, still moving along but a gap is starting to open
As time passes this gap is opening further –we’re falling off the back of pace line – and we’re gonna get dropped if we don’t do something soon
We’re Underperforming to our Plan
For the invested effort (ACWP) we’re under delivering value (BCWP)
3
Assessing the Widening Gap
If we keep riding at our 19 mph pace, the gap will continue to open and we’ll soon be all alone
Our planned performance (BCWP) has fallen off the planned pace (BCWS) and we need to do something about it, and we need to do it fast
If we can get back on pace (BCWP) – go back to our planned 20 mph –this will be good, but the gap that opened up will remain (SPI < 1.0)
Our riding group is now far ahead
We’re not falling further behind, but we’re still behind
We’ll need to pick up the pace (SPI > 1.0)
4
Time to Pick Up the Pace
In order to close the gap,
riding at our planned 20 mph
pace is not enough
We have to ride faster – say
a 22 mph pace to close the
gap
Let’s assume we have the strength, skills, stamina, and mental
fortitude to pick up the pace and ride a 22 mph pace to try to
reconnect with the Peloton
Exactly how to do this will require some thought Simply peddle faster – steady increase in effort
Sprint to close the gap on an uphill section
Ride faster down hill
Find someone to pull us to the Peloton in a draft
5
Closing the Gap
In order to close the gap,
we need to find the
needed actions to close the
gap that put us back on
pace – 20 mph
But first we need to ride
faster – at 22mph
Both are needed
Close the gap – ride at 22 mph
Once reconnected with the group, keep on planned pace
– maintain 20 mph
Easy in concept – hard in the execution
6
RIDING IN A PELOTON IS LIKE
MANAGING A PROJECT WITH
EARNED VALUEThe planned pace is BCWS
The actual pace is BCWP
The effort need to close the gap is TCPI
7
Glen B. Alleman
Lewis & Fowler
Earned Value Components8
Budgeted Cost of Work Scheduled
The planned spend rate in hours and / or dollars
Budget Cost of Work Performed
The planned value of the work delivered
When BCWS = BCWP we’re staying with the Peloton
We’re staying on Plan
Actual Cost of Work Performed
The cost in dollars or hours to produce the value
(BCWP)
Simple Cost Performance9
TIME
CO
ST
Planned Cost
Actual Costs
Time
Now
Measuring budget performance is
useful for the financial staff.
But program managers need
insight into the delivery of
techncial value
Earning the Value for the Project
Planned Costs
Earned Value
Actual Costs
Time
Now
TIME
CO
ST
It’s the Earned Value
measurement we’re after.
The EV represents the delivered
value to the customer, not just
the consumption of resources
10
Measuring Schedule Performance
Schedule Variance
BC WS:
BC WP:
Of the work scheduled to have done,
how much was it budget for it to cost?
Of the work actually performed,
how much was it budget for it to cost?
SCHEDULE VARIANCE is the difference between work scheduled
and work performed (expressed in terms of budget dollars)
formula: SV$ = BCWP – BCWSexample: SV = BCWP – BCWS = $1,800 – $2,000
SV= –$200 (negative = behind schedule)
SCHEDULE VARIANCE is the difference between work scheduled
and work performed (expressed in terms of budget dollars)
formula: SV$ = BCWP – BCWSexample: SV = BCWP – BCWS = $1,800 – $2,000
SV= –$200 (negative = behind schedule)
Convert SCHEDULE VARIANCE to a percentage
formula: SV% = BCWP – BCWS = SV$
BCWS BCWS
example: SV% = – $200 = –10%
$2,000
Convert SCHEDULE VARIANCE to a percentage
formula: SV% = BCWP – BCWS = SV$
BCWS BCWS
example: SV% = – $200 = –10%
$2,000
11
Measuring Cost Performance
Cost Variance
BC WP:
AC WP:
Of the work actually performed,
how much was it budgeted to cost?
Of the work actually performed,
how much did it actually cost?
COST VARIANCE is the difference between the budgeted cost and
the actual cost
formula: CV$ = BCWP – ACWPexample: CV = BCWP – ACWP = $1,800 – $1,900
SV= –$100 (negative = cost overrun)
COST VARIANCE is the difference between the budgeted cost and
the actual cost
formula: CV$ = BCWP – ACWPexample: CV = BCWP – ACWP = $1,800 – $1,900
SV= –$100 (negative = cost overrun)
Convert COST VARIANCE to a percentage:
formula: CV% = BCWP – ACWP = CV $
BCWP BCWP
example: CV% = –$100 = –6%
$1,800
Convert COST VARIANCE to a percentage:
formula: CV% = BCWP – ACWP = CV $
BCWP BCWP
example: CV% = –$100 = –6%
$1,800
12
Closing the Gap13
When a gap opens in cost or schedule, it needs to be closed
Knowing the CPI and SPI is necessary but not sufficient
We need to know how much better we must perform to close the gap
Have much faster do we need to ride to get back to the Peloton?
How much more efficient do we need to be for each dollar spent to get back on schedule?
To Complete Performance Index (TCPI)14
The To Complete Performance Index (TCPI) is an
index states how much better we need to perform
to close the gap
The TCPI is an indicator of how our performance
needs to improve to close the gap between the
planned performance and the actual performance
BAC BCWPTCPI
EAC ACWP
Closing the Gap15
If the TCPI is > 1.0 something has to change to stay
on schedule and budget
Reduce scope – do less work (BCWP) for the same
effort
Reduce rework – reduce breakage
Increase efficiency – do more work (BCWP) with the
same (ACWP)
In the End It’s About Staying on Pace
When a gap opens
Getting back on the original plan (pace) is necessary but not sufficient
We have to perform better (faster than plan) in order to close any gaps that opened while we were falling behind
Knowing the level to which we need to perform to close the gap is the To Complete Performance Index (TCPI)
Being able to perform at this level requires we understand what went wrong and how to fix it
16