the sc@la project - · pdf filebased on the tool mdm hub informatica (master data management)...
TRANSCRIPT
November 7, 2014 1
The Sc@la Project MDM Hub Implemention for Natural Gaz Transport Informatica Day – Zurich 2013
Agenda
Presenting GRT Gaz
Business Case – MDM Rationale
Project Scope and Schedule
Data found in MDM Hub
Datastewardship
In summary
Presenting Arhis
Q&A
November 7, 2014 2
07/11/2014 3
GRTgaz performs three main roles: It transports natural gas on behalf of its customers,
ensuring safety, cost, reliability.
It delivers gas to recipients directly connected to the transmission network:
major industrial users, power plants that use natural gas to produce electricity, public distribution networks and neighboring transmission networks.
It expands its transmission capacity in order to meet market demand and enhance security of supply for France and Europe.
Key figures ~3000 employees
TURNOVER In millions of euro
INVESTMENTS In millions of euro
Presenting GRT Gaz Activities and Some figures at a glance
07/11/2014 4
Infrastructures : GRT Gaz owns and operates the largest High Pressure Natural Gaz network in Europe :
32 000 km of natural gas network 25 compressor stations 9 nodes 870 industrial connected clients 4550 shiping points
677 TWh transported (60 billions m3)
Presenting GRT Gaz
Presenting GRT Gaz The largest High Pressure Natural Gaz network in Europe
07/11/2014 5
What is SC@LA ?
Main components
Steady State Simulation
Simulation statique
Front-End Acquisition
Real Time Network
Simulation Simulation dynamique
PI Data Historian Historisation
Analyse
SCADA OASys Configuration Surveillance
Pilotage
RFO
Project Scope and Schedule
SC@LA is a project that aims to provide a Gas Network Management system, with accurate and consolidate information for the enterprise, which meet the needs of the market.
SCADA based on the tool OASys of Schneider Electric (ex Telvent) in core of project SIMONE the dynamic simulation module of the network PI the real time Data Historian of OSIsoft RFO based on the tool MDM Hub Informatica (Master Data Management)
RFO is completed by Informatica Powercenter used as a vehicle for data flows between systems
The project has chosen specialized applications in each of the functional area to build the solution :
The Sc@la project building blocks
07/11/2014 6
Data created in siloed environments and heterogeneous systems by teams that did not have necessarily other systems views, however some common concepts needed to be shared Various sources of data which need to be consolidated, cleanst, enriched before reaching the SCADA (Supervisory Control And Data Acquisition) Current Data structure based on measurement equipment (and not on physical network) has reached its limitations Will to reuse and leverage existing data sources (No need to rebuild all)
Reasons for creating the Sc@la RFO (Using Informatica MDM Hub)
07/11/2014 7
Founding principles of the RFO A cautious approach : minimal impact on legacy
SC@LA will be based on a Master Data Management solution
This first brick shall serve as a foundation for other domains in the future
This MDM brick shall have minimum impact on legacy systems :
o Connection to legacy systems (Geographical ( GIS), MRO (CMMS), etc…) possible
to collect data but no exchange or data modifications with those critical systems
o No formal commitment in validating data consistency between systems (GIS or CMMS) for Sc@la.
8
Summary planning On schedule delivery !
Project Scope and Schedule
Metering DB
7 novembre 2014 9
RFO Exchanges (Step 1)
Delivery Point Capacity Calc.
CMMS Compression
CMMS Réseau
GIS
Metering DB
RFO
Geographical Information system
connection
Project Scope and Schedule
• 5 source systems to contribute data into MDM • SCADA is Synchronizing with MDM • Metering DB a provider & consumer of MDM data
Electronic Logbook
HELP
ANGEL
CMMS Réseau
Metering Db
WIP Db
7 novembre 2014 10
Delivery Point Capacity Calc.
CMMS Compression
CMMS Réseau
GIS
Metering Db
RFO
Trans@ction Possible extensions
Plugin GIS View
Pegaz
Project Scope and Schedule
RFO Exchanges (Step 2) Future extensions
•Passive Network Elements
Réseau
Section principale
Antenne/Boucle
Segment
Section élémentaire
Nœud
Artère Zones
Data Found in the MDM Hub
•Actifs
Passive and Active Networks elements Extensive use of Hierarchy Manager !
Passifs Emprise
Installation
Groupement/Atelier
Fonction/EFB
Organe
Réseau
Section principale
Antenne/Boucle
Segment
Section élémentaire
Nœud
Artère Zones
Micado GMAO CAPTRANSPORT
Sc@la
Data Found in the MDM Hub
7 novembre 2014 13
•Business Objects : •PCE •FGA •PCR •PPG •PPC •PRL •PLI •ZPS
Additional data types
Dynamic Data : Real time system descriptive
variables Those variables can be linked to
each network element
Data Found in the MDM Hub
7 novembre 2014 14
In the end : a complex data model The RFO is 150 tables linked together in a complex way
Segment Noeud
Ouvrages passifs
Emprise
Organisation GRT gaz
Organisation nationale
Groupement de Fonctions
Fonction Installation
Organe
Ouvrages Actifs
Relation Emprise Secteur
Relation Emprise
Commune
Relation Segment Secteur
Relation Segment
Commune
Installation
Projects highlights • A complex project with limited timeframe • An Agile methodology which allowed to move
forward and manage projects updates on the flow
Tables logiques de spécialisation
Tables de liens n,n
Organisations
Organe
Fonction
Installation
Ouvrage passif
Regroupement de Fonction
Interconnexion-Mélangeur
Compression
Poste de livraison -Pré détente - Comptage - Filtration
Poste de sectionnement - Départ
Service
Traitement
Emprise
Installation Fonction installation
Détente et sécurité RéchauffageEFB comptage EFB Déshydratation EFB Régulation
EFB Compression
EFB Vanne
EFB OdorisationSupervision Air-Electricité
Régulateur
Organe
Compteur
RobinetChromato-AnalyseurRéchauffeur
Organe de sécurité
Ligne Teleco
Section principale
Section élémentaire
Segment
Antenne - Boucle
Noeud
Réseau
Tronçon
Artère de conduite
Département
Commune Secteur d'exploitation
Région GRTGaz
Agence
Exploitation
Région
Ensemble régulateur et vanne
Atelier de compressionGroupement de fonctions
ICT
Rampe ECVFiltre
Comptage
Segmet SESegment antenne-boucle
Segment-Commune Segment-Secteur Emprise-SecteurEmprise-Commune
Artère-AntenneBoucle
Data Found in the MDM Hub
CS V 121301 LIV- Z 1002 - Libreville
CS V - M1301 LIV- Z GTA02 - Libr
GMA 121301 GMA- Z Z 1002 - Libreville
Libreville CP002
Zone de Bel Air
07/11/2014 15
•Extensive use of datastewardship components
micado micado
GMAO
GMAO
GMAO
Cap
tran
spor
t
Cap
tran
spor
t Cap
tran
spor
t
micado micado
LIVRAISON
RFO RFO
Datastewardship
7 novembre 2014 16
Extensive use of Hierarchy Manager
Emprise
Poste de livraison
Fonction Détente et
Sécurité
Fonction comptage
Compteur
Hierarchy Manager
Datastewardship
07/11/2014 17
Dashboard
Datastewardship
Some quantitative elements The RFO is
7 novembre 2014 18
RFO
150 Relational Tables, with over 3 millions records
650 Business Rules to implement at ETL and MDM Hub
Business data and Dynamic data are related to almost all complex structures
A single User Interface (IDD) to support Datastewardship for all GRT components
To manage data flows between systems, 23 Web Services, 5 daily RSS, with multi-daily data feed jobs were built.
In summary
Conclusion
07/11/2014 19
RFO is based on Informatica MDM Hub Adaptable and configurable Tools
The Data Model is consistent with GRTgaz Reference Model The Data Structure of MDM is technically independent to SCADA
which implies that less constraints to development are imposed by GRTgaz source system which could allow to expand the scope of the MDM to other business needs
Fast implementation and strong knowledge of Informatica product were key as well as good cooperation between the project teams to let the project to meet tight deadlines
©www.arhis.com 2013
Arhis Value Proposition A Swiss Leader !
20
Our focus is Master Data Management
Arhis is a clear leader in the MDM implementation space since its creation with more than 30 success stories
One Team & Unique Model
A unique expertise on key vendors solutions (Informatica)
A value-added offering with a team of highly qualified MDM Hub engineers
Implementation best practices combined with a proven MDM project methodology.
Our Religion: Customer Satisfaction at a reasonable TCO
Speed of execution
Reliability in quality and delivery
Strong commitment
Flexibility and adaptability : Agile methodology
Presenting Arhis
©www.arhis.com 2013
Arhis Worldwide Presence in MDM A Swiss System Integrator expert in Master Data Management
21
Presenting Arhis
7 novembre 2014 22
Q&A ?
Thank You !