the miso transmissiontasmartenergy.com/resources/miso_transmissioncost... · 2014. 7. 14. · the...
TRANSCRIPT
A c o s t a n a l y s i s p r e p a r e d
f o r t h e M i c h i g a n P u b l i c
P o w e r A g e n c y a n d t h e
M i c h i g a n M u n i c i p a l
E l e c t r i c A s s o c i a t i o n
S t e v e n A . T r a n s e t h
T r a n s e t h & A s s o c i a t e s
1 0 5 H i l l s d a l e S t
L a n s i n g , M I 4 8 9 3 3
( 5 1 7 ) 8 9 9 - 6 2 3 5
6 / 3 0 / 2 0 1 0
The Midwest ISO is going to file with FERC on July 15, 2010
a proposed tariff which establishes a socialized method for
transmission cost allocation for all members of the RTO.
Under this tariff Michigan will be assessed a
disproportionate share of the costs without the
commensurate benefits.
The MISO Transmission Cost Allocation Proposal – The Implications for Michigan
1
Introduction
Electricity transmission cost allocation methodology. The problem of deciding which
customers pay how much of the cost of building and operating new transmission lines that
cross several states has become a very contentious issue. But for a topic that has received so
much attention in certain circles, it is amazing how few people really understand the potential
impact on this State of the current proposed decisions being considered regarding how we are
going to pay for new transmission in the years to come. Because for the most part our state
has very little control over the lines that carry the power from the generation facilities to the
end user, transmission is often an overlooked component to our energy delivery system.
Transmission rates are set at the federal level and are passed along to the end user through
their utility bills. Over the next couple decades billions of dollars are going to be spent in
upgrading and expanding the transmission network and renewable energy is playing a key role
in the need for this new transmission. On a state, regional and national level we have
embarked on an important mission to generate more “green” energy. To meet this need, wind
has received the most attention, with solar, biomass and battery power not far behind. This
will require us moving away from large generation facilities located near the customer to a
more distributive model of smaller facilities located near the energy source. Because
renewable resources are often quite remote, the cost to transmit the power can be high and
how these costs going to be paid can be challenging.
This challenge has resulted in a debate as to what should be the appropriate size of this
new transmission system and how the costs associated with construction should be allocated.
Should the costs be broadly socialized or assessed to those directly benefiting from the new
resources? The current proposed development of wind in the Michigan Thumb area is but one
example of the problems we face on this issue. The wind is there and the developers are ready
to build, but it means little unless we can get the electricity onto the grid. To do so is going to
require the building of new transmission lines and the question is how much transmission is
needed and how are we going to pay for it? Should these costs be a state obligation or part of
an overall regional or federal plan? Should only those who directly benefit from the new
transmission pay or should the costs be spread over the Midwest ISO (MISO) footprint? Should
a portion of the profits made by the developers be returned to the ratepayers given that the
ratepayers paid the costs for the new transmission? The answers to those questions will have
significant implications for Michigan on both a short and long term basis.
The issue of regional cost sharing will come to a head on July 15, 2010 when MISO files
with the Federal Energy Regulatory Commission (FERC) its proposed cost allocation method.
2
Michigan needs to fully understand how this proposed allocation will eventually impact
this State and ensure it is part of the debate in determining the final decision. This paper was
prepared to provide context on the MISO proposal and to ensure that our State regulators and
policy makers have the necessary information to make informed decisions.
This is most certainly a complicated issue and there is no simple answer.
Historical Summary
Much of the cost allocation issue became a problem only in recent years as the need for
more renewable energy required new transmission. The primary Regional Transmission
Organization (RTO) for Michigan is MISO. Beginning in 2008, several smaller utilities,
particularly Otter Tail Power, challenged the then current MISO cost sharing formula for the
interconnection of wind into their system. They expressed concern that the transmission rates
resulting from wind generation being connected to their system were not commensurate with
the benefits associated with supporting their own internal load or Renewable Portfolio
Standard (RPS) needs. These entities said that unless MISO changed the allocation cost rules
they would leave the RTO.
As a result of the “Otter Tail” issue MISO resurrected their Regional Expansion and
Criteria Benefits Task Force (RECB TF) for the purpose of reexamining and making
recommendations regarding transmission cost allocation concerns for reliability driven projects
and economically driven projects. The RECB TF was also given the charge of developing a new
transmission cost sharing mechanism for handling future projects intended to support
renewable energy development. This last type of development is the center of the cost
allocation debate and is what MISO now labels Multi Value Projects (MVP)
The Organization of MISO States (OMS), which is made up of a representative from each
of the regulatory commissions of the various MISO states, also decided to weigh in on this issue
and created the Cost Allocation and Regional Planning group (CARP). This group’s purpose was
to also review and make recommendations regarding potential cost allocation methods, with
particular attention to projects directed at enabling states to meet their RPS.
The initial efforts of RECB TF and CARP resulted in a filing by MISO with FERC in July of
2009. FERC supported the recommendations made in this filing and issued an order in October
2009. The tariff changed the cost allocation to address the Otter Tail problem and prevent
further erosion of MISO membership. MISO portrayed this tariff only as an “interim” solution
3
and agreed to establish a process to determine a more permanent solution which would be
submitted to FERC no later than July 15, 2010.
In early 2010 a number of MISO Transmission Owners (TO) came together to develop
their own transmission cost allocation proposal. This group took a quite different approach by
distinguishing between the different types of transmission projects. Their recommendation
was to maintain the current cost allocation methodologies used for reliability and economic
projects and introduced a socialized approach for new projects developed to meet any state or
federal regulatory mandates such as a RPS. The Michigan Public Power Agency, ITC and
Wolverine Power withdrew from the TO group on the basis that they were unable to support
the final recommendations.
At the April, 2010 CARP meeting the western MISO states which support a regional
socialized approach dominated the discussion and the voting on the proposed allocation plan.
The final version of the CARP proposal provided 100% of the costs for all MVP projects to be
allocated regionally on a “postage stamp” basis. The CARP proposal continued the current
approach for allocating costs associated with reliability projects but proposed a socialized
allocation for projects which can be justified for economic reasons.
The vote on the CARP proposal was 11 states in favor and 2 abstentions. Illinois did not
register a vote but is most likely opposed given it appealed the FERC order approving socialized
cost allocation in the PJM Interconnection (PJM) that led to the ruling by the Seventh Circuit
Court which rejected FERC’s decision (see discussion below). Even though Michigan will bear a
disproportionate amount of the costs for the MVP overlay transmission build-out, it was one of
the 11 states that voted to support the 100% postage stamp proposal.
After weighting proposals by the RECB TF, CARP, and the transmission owners, on June
22, 2010, MISO presented its final cost allocation proposal calling for the broad socialization of
costs associated with new transmission network to be developed to accommodate state RPS
requirements. The stated goals were to create a fair cost allocation system that would enable
transmission development to support renewable energy integration, public policy, reliability
and economic goals while maintaining the “Midwest ISO Value Proposition”.
Causation and Beneficiary vs. Socialization
The debate regarding transmission cost allocation typically has involved the choice
between “cost-causers”, “beneficiary pays” and “socialization”. These terms have different
meanings depending on which side of the debate you are on. Proponents of “cost-causers” and
“beneficiary pays” argue that those parties benefitting from the new transmission should pay
the costs of building the transmission. This model has been the traditional means of how we
have allocated transmission costs. However, it is often difficult to identify exactly who are all
the beneficiaries or even what benefits should be considered. The proponents of “socialization”
argue that important benefits, such as grid reliability, reduced power loss and less congestion,
cannot be easily allocated because all parties enjoy these benefits, and therefore costs should
be spread over all users connected to the transmission system. Because of these differing
positions and the changing nature of the transmission system, it is becoming exceedingly
difficult to apportion transmission costs in a way that satisfies all parties.
The choice of an allocation method may depend on the priorities placed on the type of
benefits and practical considerations. If the emphasis is more on the direct cost-causers then
allocation will be based on flow-based or monetary metric methods because it’s important to
identify and ensure that beneficiaries are specifically allocated costs. Conversely, if there is a
strong emphasis on grid reliability or the fact that users may see some benefit from reduced
losses with new transmission facilities, then allocating costs based on a socialized model will be
preferred. A socialized allocation method, which spreads the costs equally across all affected
parties, assumes that benefits are equally distributed. However, when dealing with multiple
jurisdictions with varied interests there is going to be a strong likelihood of variance between
the costs assessed and the benefits received. The question becomes at what point does this
differential become too great and the benefits are no longer commensurate with the costs? An
allocation method that in general serves the Midwest ISO Value Proposition may, when
implemented, not be a value to a specific group within the region. MISO has created
precedents, even here in Michigan, for exceptions when it was necessary to have different
treatment of parties to avoid unfair treatment under a tariff. MISO recognized the necessity for
differential treatment when it addressed the Otter Tail issue and that practice should continue
in establishing any cost allocation method as it relates to Michigan.
Cost allocation is public policy mixed with engineering, economic and political
considerations. By its very nature, cost allocation must balance individual as well as collective
interests. However, regardless of how you define the terms beneficiary or socialization, any
authorized cost allocation of large transmission projects on a regional basis must demonstrate
that the “right load” pays for the cost of the new transmission built as a result of that load and
that the “benefits” received are commensurate with the costs that are being assessed. This
5
concept is consistent with one of the MISO’s guiding principles in establishing a fair cost
allocation method.
Illinois Commerce Commission v. FERC
The decision of the Seventh Circuit in Illinois Commerce Commission v. FERC1 rejected
the cost allocation plan approved by FERC that allowed the costs of certain new regional
transmission to be spread widely among ratepayers in PJM (the RTO directly east of MISO)
because it included those who did not substantially or clearly benefit from the new
transmission. This case involved several issues which went to justifying a cost socialized
approach (all of which were rejected) but the Court directed most of its decision to the FERC
rational that such cost sharing was supported because every member of the RTO would benefit
from improve reliability of the new transmission facilities. The Court found while there might
be certain “secondary” benefits to all PJM members, those benefits could be minor in
relationship to the costs imposed. Such benefits can not be merely presumed but there is a
duty of “comparing the costs assessed against a party to the burdens imposed or benefits
drawn by that party”.2
The most significant restriction placed on FERC by the Court was that before it can
approve a socialized cost allocation process for a RTO, it must show that any claimed benefit
received by a party must be roughly commensurate with the cost assessed.
Michigan’s unique position
Given the complexities of the issues it is easy to see the appeal of the MISO proposal
and the “value” to MISO in managing the grid. Unfortunately, what might be of value to the
RTO generally may have a negative impact on Michigan. A socialized cost allocation based on
load will mean Michigan will carry a disproportionate share of the costs without the
commensurate benefit. The reasons are three-fold: First, Michigan represents nearly 20% of
the MISO market and accordingly, under the proposed formula this State would be responsible
for 20% of the costs associated with specific new transmission project throughout the Midwest.
Michigan’s contribution will far exceed any benefit realized by these new transmission projects.
As stated earlier, whenever costs are proportionally spread out over all participates there will
always be some who will pay more than that which equals the benefits they receive. However,
the cost differential to benefits received for Michigan under the MISO scenario is so great that
it will result in this State being subjected to rates which do not meet the standard of being just
1 576 F.3d 470 (7
th Cir, 2009)
2 Id. at 477
6
and reasonable. Second, Michigan has a RPS of 10% by the year 2015 and the renewable
energy must have been generated within the State3. This requirement will mean Michigan will
receive little benefit from renewable energy generated from outside the state. Third, as a
result of legislative mandates, Michigan is currently aggressively developing its own renewable
energy market and hopes to be in the position of exporting green energy out of the state and is
willing to build transmission within the state to accomplish this goal. Given that almost all of
the new transmission in the MISO market will be for renewable energy outside of this State, the
situation for Michigan is only exacerbated and may actually create unfair markets for the power
we want to sell. The proposed allocation method creates an open checkbook for MISO and
leaves us with very little to say on how our money is spent. We will be in essence paying for
others to compete against us.
It also should be noted that with the exit of First Energy to PJM in the middle of next
year, Michigan will only have limited remaining electrical interconnections to MISO. This again
calls into question the benefit to Michigan in paying 20% of the large MVP transmission projects
being proposed in the western MISO states.
Finally and most importantly, if Michigan is required to pay 20% of even the low MISO
estimate of $16 billion in transmission costs, we will have hundreds of millions of dollars less
annually to spend in developing our renewable industry, revitalizing the economy and creating
new jobs.
MISO final cost allocation proposal
MISO’s basic approach centered on the premise that there is a need for major new
transmission build in the RTO to meet state RPS requirements (mainly through the
development of wind generation) and that current cost allocation method impose a barrier to
large scale transmission development. Unfortunately, the debate has focused on “who pays”
and not what we should be paying for. The economics seem to have been lost in the
discussions. For example, wind development located closer to load will require less
transmission infrastructure and be less costly than massive high voltage transmission
superhighways moving power from remote locations with greater wind capacity. Little analysis
has been done to distinguish between or relate capacity and cost factors. In other words, it
may be more cost effective to utilize a lower capacity wind zone closer to the load.
At the June 22, 2010 RECB TF meeting MISO presented its FINAL Cost Allocation
Proposal. The basic proposal is as follows:
1. 100% postage stamp of revenue requirements to load and exports (MWh) for Multi
3MCLA 460.1029
7
Value Projects (Overlay transmission build-out for renewable energy).
2. Generation Interconnection Projects cost sharing methodology remains the same.
3. 10% of 345kV and above facilities will be shared postage stamp to load. - All other costs borne by the interconnecting developer.
4. Use inclusion criteria for qualifying projects.
- Multi Value Projects.
- RECB I baseline reliability stays the same.
- RECB II criteria stay the same (for now).
At the June 22 presentation of it final cost allocation proposal, MISO included a slide
titled “Annual Estimate of MVP Usage Rate for Various Load Allocation Percentages” (see Chart
A) indicating an average annual MVP charge of $2.10/MWh with the charge ramping up from
$0 in 2011 to a high of $3.83 in 2024 and declining after that.
Chart A – MISO’s Estimate of MVP Usage Rate – See Appendix 1
This forecast was based on: 1) 100% of costs being recovered from load on a $/MWh basis;
2) an overlay cost of $16B with capital being expended over a thirteen year period beginning in
2011 and rate recovery beginning in 2013; and 3) MWh withdrawals from the MISO grid would
escalate at approximately 2.2% per year (MISO did not adjust the base for the withdrawal of
First Energy or Duke). There is another assumption that the annual charge rate is based on a
8
revenue requirement calculation utilizing an average fixed charge rate based on each individual
transmission owner’s cost structure.
The problem for Michigan is MISO chose to use calculations which presented the least
possible impact and made assumptions based on best case scenarios. For example, MISO has
previously indicated that the transmission overlay should cost between $16 and $20 billion but
elected to use the lowest cost number for its analysis. Another problem is the use of a 2.2%
energy growth rate which understates what the annual MVP charge rate will be and thus, when
applied to Detroit Edison and Consumer Energy’s own load circumstance, understates what
their total annual costs will be.
It is also important to note that the $16 billion cost estimate provided by MISO does not
include the cost of any underlying feeder systems required to connect renewable generation to
the transmission overlay. Also, MISO’s definition of what it considers to be a MVP remains
unclear and depending on the final determination could add substantially more cost than
estimated.
Cost Analysis
To arrive at a more accurate picture of the cost implications for Michigan, data from
MISO’s most recent Annual Electric Control and Planning Area Report contained in its FERC
Form 714 submittal was utilized to adjust the MWh withdrawals used in MISO’s presentation
shown above. The energy growth rate reflected in MISO’s FERC Form 714 is 0.84% which
compares favorably with the North American Electric Reliability Council’s 2009 Reliability
Assessment’s projected growth rate of 0.67% for the MISO region.
Replacing the MWh transaction data in the MISO’s cost allocation presentation with
that contained in its FERC Form 714 results in an increase of the annual average MVP charge
rate from $2.10/MWh to $3.40/MWh and an increase in 2024 peak rate of $3.83/MWH to
$5.59/MWH. The adjusted figures are included in Chart B, which also include the estimated
usage rates for transmission development in the Michigan Thumb area.
9
Chart B – Adjusted Annual Estimate of MVP Usage Rate – See Appendix 2
$5.59
$0.86
$3.40
$0.65
$0.00
$1.00
$2.00
$3.00
$4.00
$5.00
$6.00
MV
P U
sage
Rat
e ($
per
MW
h)
100% Load Allocation
100 % Michigan Thumb Allocation
100% Load Allocation - Levelized
100% Michigan Thumb Allocation - Levelized
The before and after impacts for Detroit Edison and Consumers Energy are summarized in the
table below:
MISO’s Initial Presentation
MISO’s Presentation Adjusted
DE Average Annual Cost
$123 million $199 million
CE Average Annual Cost
$105 million $170 million
Total Average Cost $228 million $369 million
DE 2024 Cost $210 million $307 million
CE 2024 Cost $179 million $262 million
Total 2024 Cost $389 million $569 million
These numbers are substantial, representing costs which are 60% more than those
presented by MISO. Even then, there have been arguments made that once they are spread
over the entire MISO membership the increases are tolerable. For example, using the more
10
accurate figures in Chart B the total increase per kWh would be slightly more than a half of one
penny.
Conclusion
Why argue over a half of a penny per kWh? First, the cost projections are based on
“best case” scenarios. The actual costs could be double the estimated figures. Any cost per
MWh can be made to look minimal if taken to a large enough denominator. Much of the
debate within MISO is limited to the stakeholders who for the most part are generators and
transmission operators. Ratepayers usually have little or no say in the final decisions, even
though it is they who will pay the bill. This is a rate payer risk we should not take.
Second, these pennies add up to real dollars. As stated above, under the MISO proposal
Michigan will be sending hundreds of millions dollars annually outside the state to fund
transmission projects which not only provide little value to the State but will actually harm our
ability to develop our own renewable energy market.
Finally, this State is in one of the worse recessions in its history. If Michigan is going to
invest hundreds of millions of dollars in infrastructure and the development of renewable
energy then it should do so within its own borders.
While as a general rule socializing of some of the costs may make sense, there are gong
to be exceptions to this rule to avoid unattended consequences. While MISO’s proposed cost
allocation formula may work for the majority of the members served by the RTO, it would have
a disproportionate negative impact on Michigan. Although Michigan would initially benefit
from socializing the $510 million it will cost to bring the wind out of the thumb, this State
becomes a huge loser in the years to come when we are required in turn to pay over 20% of the
$16 billion or more that will be spent for new transmission planned in the rest of the region.
Because of this State’s unique situation, any cost allocation approved by FERC needs to
provide a solution to the problems facing Michigan under the current MISO proposal. This will
allow for the advantage of spreading costs over most of the region to those who will directly
benefit by the new transmission but account for the unfair application a socialized allocation
would have on this State.
11
COST ALLOCATION COMPARISON MISO Overlay vs. Northeast Region
12
Implications of Regional Cost Allocation of MISO Overlay vs. Michigan-Specific Region 4 Cost Allocation Methodology
• Annual charges associated with Region 4 System Annual charge rate ~ 20% x ($510 M) = $102 Million (average over life of project)
• Annual charges associated with of MISO Regional Overlay
Expect $15B - $20B investment over 15 year period
Annual charge rate ~ 20% x ($15 - $20B) = $3B to $4B Michigan represents approximately 18% of MISO region and thus would be allocated between $540M -$720M for the MISO overlay
• For Michigan to be indifferent, MISO overlay, including the Region 4 System, needs to be limited to: $102M /18% market position / 20% Fixed Charge Rate = $2.8B
• MISO expects that $4.6B (including Michigan Region 4 build) will be authorized within the next 18 months.
13
MISO NORTHEAST REGION
Advocacy Document
14
Background
Michigan's regulated electric utilities, municipal electric providers and businesses remain
deeply concerned with the direction that the Midwest Independent Transmission System
Operator (Midwest ISO) has proposed related to the cost allocation of future electric
transmission system improvements and expansion, in particular the massive projects intended
to support renewable portfolio standards (RPS) throughout the region.
On July 15, 2010 the Midwest ISO filed a request with the Federal Energy Regulatory
Commission (FERC) seeking approval of a tariff that will allocate billions of dollars of costs
for transmission projects designed to meet state RPS requirements throughout the Midwest
ISO region to areas or states that may see little benefit from those projects. While we are not
in any way arguing against other areas of the Midwest ISO developing transmission to
support their needs, we are fundamentally and philosophically opposed to having Michigan's
customers pay for the projects when they provide little or no benefits to Michigan's residents.
We collectively and unanimously subscribe to the following statements:
a. The costs of system improvements or system expansion that are allocated to regions within
Midwest ISO must be directly related and traceable to the level of benefits received by those
regions.
b. Under the current Midwest ISO cost allocation proposal Michigan customers will be
assessed a significant portion of the costs for projects built in other regions but will receive
little, if any, benefits from these projects. Any benefits received will certainly not even be
“roughly commensurate” with the costs imposed on Michigan customers.
c. Michigan will ultimately be exposed to much larger costs than are currently being
proposed by Midwest ISO due to the broad project qualification criteria, including a lack of a
voltage based cost threshold contained in the Midwest ISO filing.
d. Midwest ISO's cost allocation proposal will significantly undercut the progress of
Michigan's in-state renewable energy development goals.
e. Given the limited interconnections with the other regions of the Midwest ISO, Michigan
needs to be placed into its own transmission planning and cost allocation region within the
Midwest ISO.
Overview of Concern
Significant Transmission Expansion is Being Proposed in the Midwest ISO region
With the advancement of state renewable portfolio standards and in anticipation of federal
standards, the Midwest ISO4, along with its member transmission owners, have initiated
plans calling for the development of a broad regional transmission system intended to
connect remotely sited renewable generation, mainly wind turbines, with the urban electric
load centers.
4 The electric transmission system across much of the Midwest, while owned by individual transmission owning utilities, is
operated and planned for by the Midwest Independent Transmission System Operator (Midwest ISO) headquartered near
Indianapolis. Midwest ISO’s operations are regulated by the Federal Regulatory Energy Commission.
15
Who Should Pay for the Cost of Transmission is a Hotly Debated Issue
Over the last couple of years the Midwest ISO engaged stakeholders in a discussion of how
and from whom the cost of such a new transmission system would be recovered. Whether or
not the project costs should be socialized across the Midwest ISO footprint; or whether the
beneficiaries of each transmission project should or could be identified and charged
individually was hotly debated. The Midwest ISO proposal will result in the widespread
socialization of future transmission costs, without regard to who will actually benefit from
each transmission project.
Current Cost Allocation Proposal
Midwest ISO’s Proposal to Socialize Costs
Prompted to do so by FERC, on July 15th
Midwest ISO submitted for FERC’s approval a
proposed cost allocation methodology which would socialize across all of the utilities in its
footprint the costs for a new class of transmission projects described as “Multi Value
Projects” (MVPs). MVPs are projects essentially designed to support current or future state
or federal electric generation policy requirements or to provide regional economic or
reliability benefits. Costs for the multi value projects are proposed to be recovered based on
the percentage of the energy that each transmission customer, primarily electric utilities,
withdraws from the entire transmission system; not just from the MVPs.
Michigan’s Transmission Requirements in the Thumb Qualify as a MVP
An example of one MVP project is the 345kV transmission line proposed to be constructed
in Michigan’s Thumb intended to enable the state’s utilities to comply with the RPS
requirements set forth by the Michigan legislature in Public Act 295 (PA295) of 2008. This
project and the wind resources connected to it will provide more than adequate electric
transmission and generation capacity to enable the state’s utilities to achieve compliance with
the in-state development requirement set forth in PA295 intended to create an in-state
renewables industry with its incumbent benefits. The Act specifically intended to:
“promote the development of clean energy, renewable energy, and energy optimization
through the implementation of a clean, renewable, and energy efficient standard that will
cost-effectively . . . [p]rovide greater energy security through the use of indigenous energy
resources available within the state [and] [e]ncourage private investment in renewable
energy and energy efficiency.”
o Michigan’s Thumb Transmission Investment is Projected at $510 Million
The investment in this project is expected to be $510 million with annual associated
investment and operating charges expected to be $140 million.
o Michigan Utilities Support Building Transmission in the Thumb
The state’s utilities are supportive of the construction of, and will recognize benefit
from, the transmission system to be developed in the Thumb. However, once that
system is built, the capability to comply with PA295 will be met and no additional
out-of-state resources are necessary to enable the state’s utilities to reach compliance.
In fact, with the requirement that the renewable energy be sourced largely from in-
state resources, Michigan’s utilities can’t use out-of-state transmission resources to
16
meet their RPS compliance requirements.
Transmission Expansion Outside of Michigan Provides Few Benefits to Michigan
The transmission systems in the Lower Peninsula of Michigan are loosely connected with
the other transmission systems in the Midwest ISO. Once First Energy leaves the
Midwest ISO in 2011, the majority of Michigan’s transmission capacity will be only
interconnected with transmission systems in Canada and PJM Interconnections, resulting
in Michigan having little benefit from transmission expansion in other parts of the
Midwest ISO.
o In particular, Michigan Doesn’t Benefit from MVPs Outside of Michigan
Michigan has a RPS of 10% by the year 2015 and the renewable energy must be
generated, with limited exception, within the State. This requirement will mean
Michigan will receive little benefit from renewable energy generated from outside the
state and from Midwest ISO’s proposed transmission system to serve that generation.
Significant MVP Transmission Expansion is Being Proposed in the Midwest ISO
In addition to Michigan’s project, Midwest ISO has forecasted an initial investment
outlay for other near term MVP projects in the region, referred to as the ”MVP Starter
Projects”, of $4.1 billion with an initial annual associated investment and operating
charges expected to be $ 820 million. The MVP Starter Projects are only a subset of the
overall transmission expansion projects being looked at by the Midwest ISO to cover
potential regional RPS needs in the future, with some of total portfolio investment costs
projected to be as high as $20 billion.
o The defined scope of MVP projects is too broad
We believe that MVP projects should be limited to those projects needed to meet state
and federal electric generation policy requirements, such as RPS standards. They
should not be projects needed to meet reliability or economic requirements – these
types of projects should continue to be handled using the current cost allocation
methodology, which limits socialization to 20% of the total project cost.
o The socialization of MVP projects costs should be limited to projects 345kV and
above
In the Midwest ISO cost allocation proposal there is no voltage threshold limit below
which projects are to be considered “local” versus “regional”. If cost socialization is
to occur, as a minimum it should only apply for costs associated with transmission
projects or transmission project components that are 345kV or larger. To assume
anything smaller than 345 kV has “regional” benefits across the entire Midwest ISO
footprint does not make sense due to the limited regional transfer capability of lower
voltage facilities.
Michigan Residents are Harmed by the Midwest ISO Proposal
17
Michigan Residents Will Pay Millions Annually for Unneeded Transmission
o Socialization Charges Michigan 20%
Michigan represents nearly 20% of the Midwest ISO market and accordingly, under
the proposed Midwest ISO transmission cost allocation formula, Michigan residents
would be responsible for 20% of the costs associated with specific new transmission
projects throughout the Midwest. Michigan’s contribution will far exceed any benefit
realized by these new regional transmission projects.
o Socialization Charges Michigan $164 Million for Unneeded Transmission
The allocation of the initial MVP Starter Projects outside of Michigan would have an
initial annual charge to Michigan residents of $164 Million. This charge is expected
to grow dramatically as additional MVP projects are authorized. Recent projections
have MVP project investments doubling or tripling over the next ten years.
Michigan’s Competitive Position is Harmed
The proposed allocation method creates an open checkbook for those western states in the
Midwest ISO who are aggressively pushing to export remotely located wind energy to other
states and leaves Michigan electric customers with very little to say on how their money is
spent. In essence, Michigan electric customers will be paying for other states to develop
their renewable energy generation along with the accompanying industry, jobs and
infrastructure (i.e. transmission). At a time when one of Michigan’s goals to revitalized our
economy is the development of its own renewable energy market we should not be spending
hundreds of millions of dollars so other states can accomplish this same goal knowing that
the out-of-state projects will provide no benefits to Michigan over the very limited
interconnections with MISO following the departure of FirstEnergy in 2011.
Michigan’s Solution
Create a Michigan Transmission Planning and Cost Allocation Zone
Michigan’s utilities recognize the need for and fully support the development of
transmission to serve renewable resources. However, Michigan’s electric customers
should only be charged for systems that provide benefit to Michigan. As such, Michigan
utilities will respond to Midwest ISO’s July 15th
filing requesting that FERC designate
Michigan as a separate planning and cost region within Midwest ISO and that Michigan
alone will pay for the MVP transmission system developed in state necessary to support
in-state renewable development. In turn, Michigan’s electric customers would not be
forced to pay for transmission MVP systems developed out of state for the purpose of
meeting other states’ RPS requirements or for speculative investments.
As a minimum, the scope of MVP projects should be limited
MVP projects should be limited to only those projects that are required to meet state and/or
federal mandates such as RPS. The costs associated with projects being justified due to
reliability and economic reasons should be allocated in the same manner as is done under the
current Midwest ISO tariff, with only limited socialization.
18
Furthermore, any costs below a 345 kV threshold should be assessed to the local planning
region within the Midwest ISO, and not socialized across the entire Midwest ISO footprint.