the kleverud-sأ¸rli and sأ¸rli- أkersvika projects statsbudsjett 2020 tangenvika jernbanebru 9....
Post on 28-Oct-2019
2 views
Embed Size (px)
TRANSCRIPT
The Kleverud-Sørli and Sørli- Åkersvika projects
Marketdialog 1. – 19. oktober 2018
KLEVERUD-SØRLI AND SØRLI-ÅKERSVIKA
• Rules for the meeting/ marketdialog
‒ The agenda has to be equal for all supplier meeting to secure the same information level to all suppliers
• Agenda
‒ Presentation [x]
‒ Introduction to the projects
‒ Status/ Schedule
‒ Challenges
‒ Discussion
‒ Market/ Capacity 2019/ 20
‒ Priorities
‒ Contract strategy/ Enterprises
‒ Other relevant challenges and problems
2
PORTEFOLIE AND MARKET
3
PORTEFOLIE AND MARKET
Sterk satsing på samferdsel i det skandinaviske markedet
4
More value for money
5
6
• No injuries
• Cost effective
• Predictible
The Infrastructure Construction Division’s vision
Norways leading organisation for planning and execution of large infrastructure project
Kleverud-Sørli
• 15,8 km double-track railway, designed for 250 km/h. Included in the project is the construction of the longest railway bridge in Norway, Tangenvika bridge (1070m), one rock tunnel the Hestnes tunnel 3,1 km and a new station at Tangen.
Sørli-Åkersvika
• 14 km double-track, designed for 250 km/h. A new station at Stange is included in the project, as well as Åkersvika Wetlands.
7
Kleverud-Sørli-Åkersvika
THE KLEVERUD-SØRLI AND SØRLI-ÅKERSVIKA PROJECTS
8
2 StationsTunnel 3,10 km Bridge 1,07 km Open landscape 21,75 km
Approx. 30km double track:
Consists of:
Railroadtechnik
KLEVERUD – SØRLI
• Approx.16 km double track from Kleverud to Sørli
• The Hestnestunnel 3,1 km long
• The Tangenvika bridge 1,07 km long from Espa to Tangenhalvøya
• A new Tangen Station
• Challenges:
➢Statsbudsjett 2020
➢Tangenvika jernbanebru
9
SØRLI – ÅKERSVIKA
• Approx. 14 km doubletrack from Sørli to Åkersvika
• Zoning plan planned approved autumn 2019
• Re building of the Stange Station
• New railway will cross farmland, through densely populated areas, and cross protected wetlands
• Challenges:
➢Financing SB2021
➢Environment
‒ Farmland
‒ Enviromental protected area and Ramsarareas
‒ Extencive deposit management
‒ Ground condition
10
Kleverud-Sørli:
• 2016: Local development plan approved
• 2018 (Q4): Approved contract strategy
• 2019 (Second half): Start prequalification of first main contract
• 2019: Start preparatory works
• 2020: Planned government funding
• 2020: First main contract award
• 2026: New infrastructure in operation
11
Sørli-Åkersvika:
• 2018 (Q4): Approved contract strategy
• End 2019: Local development plan approved
• 2019: Start preparatory works
• 2020 (Second half): Start prequalification of first main contract
• 2021: Planned government funding
• 2021: First main Contract award
• 2026: New infrastructure in operation
Planned Schedule
PLAN AND BUDGET
• Cost frame 2018:
‒ Kleverud-Sørli Approx 5,9 Billion NOK
‒ Sørli-Åkersvika Approx 4,7 Billion NOK
• Expected financing:
‒ Kleverud-Sørli Statsbudsjett 2020
‒ Sørli-Åkersvika Statsbudsjett 2021
• New double track to Åkersvika in operation 2026.
12
Bane NOR is dependent on our suppliers to realise our portfolio
13
Planned investments - Bane NOR
Bane NOR
Engineering
Railway technique
Construction
Typical project Bane NOR project cost split
0
2
4
6
8
10
12
14
16
18
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
B ill
io n N
O K
Source: Bane NOR’s proposal of operationalisation of NTP (Innspill til Handlingsprogrammet) incl efficiency improvements
Schedule for competition Kleverud – Sørli – Åkersvika (K-S-Å)
Q4Q3Q2Q1 Q4Q4Q3Q2Q1 Q4Q3Q2Q1 Q3Q2Q1
Evaluation
and
negotiation PreQ
UPG
2
2018 2019 2020 2021 2022
Q1 Q2 Q3 Q4
Contract
strategy
K-S-Å
UPG
2 PreQ
Project exicution Preparation
of offer KS2
Evaluation
and
negotiations
Zone plan & Detaled plan Sørli - Åkersvika S-Å Project exicution
K-S
SB2020
SB2021
KS2 Preparation
of offer
CONTRACT STRUKTUR….?
Kleverud - Sørli 16 km (fra km92,5 til km108,5) Sørli – Åkersvika 14 km (fra km 108,5 til 122,5km)
Strekning / Fag
Dagsone kleverud Nærføring 1,00km
Tunnel Kleverud - Espa 3,10 km
Espa dagsone 0,2km
Tangenvika jernbanebru 1,07km
Dagsone Furnesodden - Tangen st Høye skjær-inger 1,80km
Ny Tangen St Stor fylling (inkl. overkjør- ingssløyfer) 2,00km
Dagsone Tangen St - Sørli Massebalanse 6,00 km
Dagsone Sørli Nærføring 0,5km
Dagsone Sørli - Stange st Nærføring 3,25km
Ny Stange St Nærføring 1,50km
Dagsone Stange st - Ottestad 3,50km
Ottestad st. Nærføring 1,50km
Dagsone Ottestad - Åkersvika Parselldele 4,00km
Hamar st midlertidig tiltak
Forbredende arbeider
Prosjektering UNB II
Underbygning