the jucar pilot river basin in spain · the jucar river basin - first results, seminar organised by...

25
1 THE JUCAR PILOT RIVER BASIN IN SPAIN Teodoro Estrela Jefe de la OPH de la CHJ INBO General Assembly Martinica, 24 – 28 January 2004

Upload: others

Post on 20-Jun-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

1

THE JUCAR PILOT RIVER BASININ SPAIN

Teodoro Estrela

Jefe de la OPH de la CHJ

INBO General Assembly

Martinica, 24 – 28 January 2004

Page 2: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

2

B, F, N (Scheldt)

D, F, Lux (Moselle-Sarre)

Denmark (Odense)

Finland (Oulujoki)

Norway(Suldalsvassdraget)

France (Marne)

Ireland (Shannon)

Greece (Pinios)

Portugal (Guadiana)

Spain (Júcar)

Italy (Cecina, Tevere)

Romania Hungary (Somos)

CZ, D, PL (Neisse)

European Pilot River Basin Network

Page 3: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

32.960Water Demand

(hm3/year)

3.400Water Resources(hm3/year)

370.000Irrigated land (ha)

1.400.000Equivalent Populationdue to Tourism(inhabitants)

4.360.000Population(inhabitants)

43.000Area (km2)

Main figures of Júcar River Basin

DEL

DEL

T A J ODEL

C U E N C A

GUADALQUIVIR

CUENCA

DELC U E N C A

C U E N C A

C U E N C A

E B R ODEL

G U A D I A N A

S E G U R A

COMUNIDAD

MURCIA

CATALUÑA

VALENCIANA

CASTILLA-LA MANCHA

ARAGÓN

CUENCA

TERUEL

ALBACETE

ALICANTE

VALENCIA

CASTELLÓN

Río

Río

Río

Turia

Al bai da

Río

Algar

R. Amadorio

Alfam

bra

Río Guadalaviar

Río

Serpis

Río

Palancia

Cenia

Vinalopó

Río

Ca briel

Río

Mag ro

Río

Magro

Río

Cabriel

Mijares

Río

Río

Turia

RÍO

JÚCARRÍO

JÚCAR

RÍO

JÚCA

R

E. de

E. Contreras

E. Guadalest

E. Beniarrés

E. Bellús

E. Escalona

E. BenagéberE. Loriguilla

Amadorio

CristinaE. M aría

E.deUlldecona

E. ArenósE. Alcora

E. Sichar

E. El Regajo

E. Tous

E. Arquillode S. Blas

E.deForata

E. Alarcón

Cana

lAc

.

R eal

Júca

rde

l

-Jú

car

Turia

CanalTuria

delCampos

- Segura

Tajo

Trasvase

- Segura

Tajo

Page 4: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

4

•Characterization of surface andgroundwater bodies

•Register of protected areas

•Analysis of pressures and impacts due tohuman activity

•Economic Analysis

•Public participation

Main activities for WFD implementation

Page 5: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

5

River typologies

Page 6: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

6

Surface water bodies

Digital terrain model(100 m x 100 m)

Drainage network with basins > 100l /s and drainage area > 10 km2

Page 7: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

7

Initial characterization of aquifers

Groundwater body =Hydrogeological unit

Activities in course

Page 8: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

8

Additional characterisation: Case study ManchaOriental Aquifer

Irrigated Area

Abstractions

Water levels

Modelling

Page 9: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

9

Water intended for humanconsumption

Natura 2000 network

Protected Areas

Page 10: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

10

Morphological alterations (weirs)

Page 11: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

11

Morphological alterations (channelling)

Page 12: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

12

Pressures: urban and industrial pointdischarges

Urban discharges

Industrial discharges

Page 13: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

13

Pressures: diffuse pollution

Flow returns from irrigation

CORINE land cover map

Agricultural Demand Units

Page 14: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

14

Impact: biological monitoring network

Page 15: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

15

Impact: surface water bodies status

Page 16: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

16

Levels of risk for surface water bodies

Page 17: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

17

Groundwater bodies: quantitative status

Exploitation index:

Abstractions /Available waterresources

Page 18: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

18

Groundwater bodies: qualitative status

Page 19: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

19

Preliminary status for groundwater bodies

Page 20: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

E.deForata

E. Amadorio

E. Guadalest

E. Beniarrés

E. Arquillode S. Blas

E. Contreras

E. Benageber

E. Tous

E. Sichar

E. ArenósE. Alcora

E. El Regajo

E.deUlldecona

E. MaríaCristina

E. Loriguilla

E. Alarcón

Algar-Guadalest

Canal Júcar-Turia

Canal del Magro

Canal PrincipalCampo del Turia

Main hydraulic infrastructure at Benageber-Loriguilla System

BENEGEBERRESERVOIR

LORIGUILLARESERVOIR

CAMPO DEL TURIACHANEL

TRADICIONAL TURIARIVER CHANEL

CITY OF VALENCIA

Year1955

Year1967

Page 21: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

02468

101214

Wat

erav

aila

bilit

y(r

eser

voir

)

Wat

erav

aila

bilit

y(c

hann

el)

Wat

erdi

stri

butio

n

Was

tew

ater

colle

ctio

nan

dtr

eatm

ent

Dis

char

ge

ctm

€/m

3

Operational Investment Total cost

Costs for irrigation users

020406080

100120

City

of

Val

enci

a

Cam

pode

l Tur

iaIr

riga

tion

ctm

€/m

3%

rec

over

y

Total cost Tariff _ _ Recovery (%)

Cost recovery analysis

0

10

20

30

40

50

60W

ater

avai

labi

lity

(res

ervo

ir)

Wat

erav

aila

bilit

y(c

hann

el)

Wat

erdi

stri

butio

n

Was

tew

ater

colle

ctio

nan

dtr

eatm

ent

Dis

char

ge

ctm

€/m

3

Operational Investment Total cost

Costs for urban users

Page 22: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

22

Public Participation

Supply ofinformation

Consultation

ActiveParticipation

Page 23: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

23Web Page http : //www.chj.es/

Supply of information: WEB page

Page 24: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

24

Supply of information and consultation•Droughts within the European Water Framework Directive and implications on river basindistricts. Seminario Internacional sobre gestión de recursos hídricos en situaciones desequía, Universidad Politécnica de Valencia, marzo 2003.

•Reunión de coordinadores europeos de cuencas piloto en el Joint Research Centre,ISPRA, Italia, Presentación del avance de los trabajos en la cuenca del Júcar. Abril 2003. LaDirectiva Marco del Agua. Sala de Juntas de la Confederación Hidrográfica del Júcar.Abril 2003.

• La Directiva Marco del Agua y la cuenca piloto del Júcar. Escuela de Caminos de la UPV.15 mayo 2003, Valencia

• Análisis económicos en la cuenca piloto del Júcar. Sala de reuniones de la DGOHCA, 4junio 2003. Ministerio de Medio Ambiente. Madrid. The jucar river basin - First results,Seminar organised by EC on Integrated management -The river basin perspective, 2003,Athens, Greece.

•Meeting with ONGs (Organizaciones No Gubernamentales). Septiembre 2003

•Presentación The pilot Jucar River Basin. Economical analysis of water uses and cost recovery.Paris, octubre 2003.

•Presentación del artículo La Directiva Marco del Agua y la cuenca piloto del Júcar. CongresoMundial de la IWRA celebrado en octubre, Madrid.

Page 25: THE JUCAR PILOT RIVER BASIN IN SPAIN · The jucar river basin - First results, Seminar organised by EC on Integrated management -The river basin perspective, 2003, Athens, Greece

25

•Confederación Hidrográfica del Júcar is takingpart in the project HARMONIRib funded by EC.

•Partners: Centre for Ecology and Hydrology(CEH) of England , Geological Survey of Denmark,DHI of Denmark, CNR-IRSA (Italy), IDR UCLM(Spain), etc

European Research and Development Projects